The County Road Administration Board - CRAB RAP Process & WACs

53
The County Road Administration Board - CRAB RAP Process & WACs Rural Arterial Program Rules : RCW 36.79 WAC 136 chapters 100 – 210

description

The County Road Administration Board - CRAB RAP Process & WACs. R ural A rterial P rogram Rules : RCW 36.79 WAC 136 chapters 100 – 210. Abandoned Freight Haul System of the past. - PowerPoint PPT Presentation

Transcript of The County Road Administration Board - CRAB RAP Process & WACs

Page 1: The County Road Administration Board -  CRAB RAP Process  & WACs

The County Road Administration Board - CRAB

RAP Process &

WACs

Rural Arterial Program Rules :RCW 36.79 WAC 136 chapters 100 – 210

Page 2: The County Road Administration Board -  CRAB RAP Process  & WACs

Abandoned Freight Haul System of the past

Page 3: The County Road Administration Board -  CRAB RAP Process  & WACs

With Freight now off the rail system, improving county arterial roads statewide allows trucks and cars to share

the road safely.

Page 4: The County Road Administration Board -  CRAB RAP Process  & WACs

CRAB receives County 6 yr road program Dec. 31, 2011 WAC 136-15-045

CRAB Call for projects Jan. 2012

Submit Preliminary Project List. ---- March 1, 2012

Complete CRAB Staff Field Reviews ---- June 30, 2012

Submit Project Prospectuses ---- Sept 01, 2012

CRABoard Approve Project Arrays ---- Oct 21, 2012

CRAB budget proposal to OFM- ---- Nov 01, 2012

Submit Road Levy Report ---- Feb 01, 2013

Annual Certification ----- April 1, 2013

Fund Projects ---- April 2013

Project Submittal - Submittal cycle for 2013 – 2015 Biennium WAC 136-161

Page 5: The County Road Administration Board -  CRAB RAP Process  & WACs

Preliminary ProspectusELIGIBILITY:

•County - Annual Certification – by CRAB every April

•Road - Function Class (02, 06, 07, 08, sometimes 09)

•Project – Must be on even-year County TIP

Page 6: The County Road Administration Board -  CRAB RAP Process  & WACs

COUNTY’S SELECTION OF RAP PROPOSALS Submit enough projects (5 max, no $ limit) so that the county has options, can

review competitiveness.

WAC 136-161-030 – “The number of preliminary prospectuses submitted and the total amount of RATA funds requested by each eligible county shall be sufficient to assure that, based upon such prospectuses, each county will be able to compete up to its county limit within its region.”

A full list of regional projects demonstrates true statewide need, and can accept additional funding such as authorized by legislature from time to time

Political support - 6 year TIP

County should consider design issues among the various project types.

In cases where there is potential for further local input, the project may only be in the preliminary planning stage or facing a Design or Value Engineering study. The county should then submit the proposal next time, after general agreement about the project location and scope.

Page 7: The County Road Administration Board -  CRAB RAP Process  & WACs

WAC 136-15-045RAP projects in the six-year program.

Each county's six-year transportation program in each even-numbered year shall include all projects for which the county may request RATA funds during the succeeding biennium. Project cost estimates for prospective RAP projects shall be considered preliminary and subject to revision until a project application is submitted.

Page 8: The County Road Administration Board -  CRAB RAP Process  & WACs

PRELIMINARY PROSPECTUS FORM Road Number - Follow up DATA, road log.

Legislative District – CRAB’s Projects web site for public/legislators.

F/C - Eligibility problems, adjusting urban growth boundaries, census, annexations. . (2010 census may change some roads to ineligible class). If the project has gained funding, the CRABoard may let the funding remain after jurisdictional or FC change.

Freight and Goods Class. This has received special funding in the past

Vicinity Map - Can a tourist find the project and its’ limits?

Description of improvements - surface, accidents, alignment, type, program (discuss these during CRAB field review).

Worksheets are not due when preliminary prospectus is submitted.

Page 9: The County Road Administration Board -  CRAB RAP Process  & WACs
Page 10: The County Road Administration Board -  CRAB RAP Process  & WACs
Page 11: The County Road Administration Board -  CRAB RAP Process  & WACs
Page 12: The County Road Administration Board -  CRAB RAP Process  & WACs

Vicinity Maps

Page 13: The County Road Administration Board -  CRAB RAP Process  & WACs
Page 14: The County Road Administration Board -  CRAB RAP Process  & WACs
Page 15: The County Road Administration Board -  CRAB RAP Process  & WACs
Page 16: The County Road Administration Board -  CRAB RAP Process  & WACs

FIELD REVIEWS – MARCH THROUGH JUNE

Avoid early spring maintenance repairs (overlays, fog seals, grading) prior to field review. Crack sealing, dig-outs and patching would be okay since they are rated as deficiencies.

Personnel (preferably County Engineer as minimum) familiar with six year program, county priority array and traffic, maintenance issues.

Discuss purpose for the project or corridor, overall scope, and possible project alternatives.

Visual Ratings Drive the project once or twice no faster than 25 to 30 mph.

Page 17: The County Road Administration Board -  CRAB RAP Process  & WACs

FINAL Prospectus - Due Sept 1, 2012

Proposed project must improve or replace the deficient section of an existing road.

CRAB staff cannot give assurance of funding on the proposed array.

The CRABoard will not approve requests for increased RATA funding that are due to poor original cost estimating or design assumptions.

Ranking is adjusted to reflect extent of improvement.

Accomplish planning and community input before funding. If a project has unclear environmental, undefined risk or scope, it should be submitted in a later cycle.

Page 18: The County Road Administration Board -  CRAB RAP Process  & WACs
Page 19: The County Road Administration Board -  CRAB RAP Process  & WACs
Page 20: The County Road Administration Board -  CRAB RAP Process  & WACs

Project Selection – Competitive Factors Projects ranked by factors listed in RCW 36.79.080.

• Structural ability to carry loads; • Rated by Extent of Failure

• Ability to move traffic at reasonable speeds;• Design Speed in City and County Design Standards - LAG

• Adequacy of alignment and related geometry;• City and County Design Standards - LAG

• Accident and fatal accident experience;• Documented accidents last 3-5 years, project length

AND:• Local Significance

• Not in statute, but reflects the project’s importance per the 6 Year Program.

Page 21: The County Road Administration Board -  CRAB RAP Process  & WACs

Project Approval - Results in a CRAB/County Contract

Based on commitments in Final Prospectus Amendments (after funding) may be granted

based on:• Increases to funding• Segmentation of the proposed project.• Changes in Scope• Request for phased construction

• (will go away for ‘13-’15 contracts)

• Waiver of payback of spent RATA funds• Other

Page 22: The County Road Administration Board -  CRAB RAP Process  & WACs
Page 23: The County Road Administration Board -  CRAB RAP Process  & WACs

(1) Reconstruction - alignment and grade changes on fifty percent or more of the project length, and may include additional travel lanes and right of way costs.

(2) 3R - resurfacing, restoration, and rehabilitation - less than fifty percent vertical or horizontal changes, and on safety improvements. Right of way costs are eligible for RATA reimbursement as a part of this project type.

(3) 2R - resurfacing and restoration - restoration of the pavement structure on the existing vertical and horizontal alignment and spot safety improvements. Minor widening costs are allowed as a part of this project type. Right of way costs are not eligible for RATA reimbursement in this project type.

(4) Intersection - 3R or reconstruction work limited to the vicinity of an existing intersection, and may include additional travel lanes and right of way costs.

(5) Bridge and drainage structures - replacement or major rehabilitation of an existing bridge or other drainage structure, and may include additional travel lanes and right of way costs. The county road administration board has determined that the interests of the counties in the several regions will be best served by encouraging development of a distinct project priority rating systems for each region.

Prior to each call for projects, and In consultation with the individual regions, the executive director shall approve the various forms and procedures necessary to allocate available RATA funding, consistent with RCW 36.79.080.

Project Types WAC 136-130-020 (following the LAG definitions, not necessarily the worksheet processes)

Page 24: The County Road Administration Board -  CRAB RAP Process  & WACs

Points for Geometry

136-130-080Limitation on rating points.

In each of the project prioritization procedures and associated approved forms, for purposes of the RAP project prospectus submitted to the county road administration board, geometric condition points shall be assigned only for those conditions which will be corrected by construction of the project. Note in Prospectus

  The rating worksheets contain formulas that reduce the points based on the project’s percent of

improvement to AASHTO standards.

Page 25: The County Road Administration Board -  CRAB RAP Process  & WACs

Lack of projects for a project type

136-130-090Reallocation of RATA funds between project types.

In the event that …insufficient number of projects are submitted in any project type to utilize the RATA funds set aside for the project type, all remaining funds shall be divided among the remaining project types as the county road administration board deems appropriate.

Page 26: The County Road Administration Board -  CRAB RAP Process  & WACs

Eligibility – RCW 36.79.140

Only those counties that during the preceding twelve months have spent all revenues collected for road purposes only for such purposes, including removal of barriers to fish passage and accompanying streambed and stream bank repair as specified in RCW 36.82.070, and including traffic law enforcement, as are allowed to the state by Article II, section 40 of the state Constitution are eligible to receive funds from the rural arterial trust account, except that: (1) Counties with a population of less than eight thousand are exempt from this eligibility restriction; (2) counties expending revenues collected for road purposes only on other governmental services after authorization from the voters of that county under RCW 84.55.050 are also exempt from this eligibility restriction; and (3) this restriction shall not apply to any moneys diverted from the road district levy under chapter 39.89 RCW.

Page 27: The County Road Administration Board -  CRAB RAP Process  & WACs

Eligibility – Road Levy

WAC 136-150-021 Ascertaining the road levy. CRAB requires a Road Levy Certification showing the amount, if any,

budgeted for traffic law enforcement and/or any other purpose in accordance with RCW 36.33.220

February 1st of each year

Page 28: The County Road Administration Board -  CRAB RAP Process  & WACs

Eligibility – Traffic Law Enforcement

WAC 136-150-022… the county sheriff shall submit a certification showing the actual expenditure for traffic law enforcement in the previous budget year, provided that counties with a population of less than eight thousand shall be exempt from this requirement.

April 1 of each year.

Page 29: The County Road Administration Board -  CRAB RAP Process  & WACs

Eligibility – Fish Barrier Removal

WAC 136-150-023 … the county engineer shall submit a certification showing that fish passage barrier removal activities beyond the county right of way did not exceed twenty-five percent of the total costs for activities related to fish barrier removal on any one project, and that the total annual cost of activities related to the removal of barriers to fish passage performed beyond the county rights of way did not exceed one-half of one percent of the county's annual road construction budget.

April 1 of each year.

Page 30: The County Road Administration Board -  CRAB RAP Process  & WACs

Eligibility – Contained in Contract language

WAC 136-150-040Constraint of contract execution.

CRAB / County Contract cites the above Road Levy, Traffic Law Enforcement and Fish Barrier Removal certifications.

WAC 136-150-050Certification of CRAB/ County contract required.

Contract is signed by the county executive or chair of the board of county commissioners, assuring that the county is eligible.

Page 31: The County Road Administration Board -  CRAB RAP Process  & WACs

Eligibility – Penalty

In case of violation of certifications, there are consequences:

WAC 136-150-060 Post audit penalty –

Return of funds from violation year, and/or

Loss of current year funding, and/or

Loss of competition for future RATA funds.

Page 32: The County Road Administration Board -  CRAB RAP Process  & WACs

Field Review

WAC 136-161-0460During the field review, CRAB staff will review the overall project scope with the county representative and, conduct visual rating. CRAB staff shall be a PE in the state of Washington, …..

July 1st, 2012

Page 33: The County Road Administration Board -  CRAB RAP Process  & WACs

Final Prospectus

WAC 136-161-050…shall include a vicinity map, a typical cross-section (existing and proposed), and, if a design deviation is required, an evaluation and determination by the county engineer. All final prospectuses shall indicate that the design of the project shall begin not later than one year from the date of project approval by the county road administration board, and that construction of the project shall begin not later than six years from the date of project approval by the county road administration board

Page 34: The County Road Administration Board -  CRAB RAP Process  & WACs

Review of final prospectus

WAC 136-161-060CRAB Staff will ensure that Final is:

1. Complete;2. From the preliminary prospectuses;3. The project is eligible;4. The project is on the current, adopted six-year transportation program;5. Design to commence in one year and const. in 6 years6. Math is correct.7. Exist. and prop. roadway cross sections, project narrative, and preconstruction photos

are attached.

Page 35: The County Road Administration Board -  CRAB RAP Process  & WACs

Priority Array

WAC 136-161-060 continued:

Projects are placed in a declining rank order. September CRABoard review - October Send copy of array to each country. Array is used to help county budget and program. No notations as to whether a particular project will or will not be funded will

be included.

County should review past arrays and funding levels.

Page 36: The County Road Administration Board -  CRAB RAP Process  & WACs

Selection for Funding

WAC 136-161-070 Exclude ineligible projects First funding of projects will occur in April, 2013 CRABoard will fund in declining rank order All counties have a funding limit which is also reduced by amounts of

increase and emergency funding the county received in prior cycle. Partially funded projects (from prior biennium) are funded first Funding will be based on Revenue forecast and regional turn-back. < 90% in April 2013 then > 10% at a later date. The CRAB/County RAP Contract is based on scope, design and project

limits indicated in the final prospectus.

Page 37: The County Road Administration Board -  CRAB RAP Process  & WACs

Matching funds

WAC 136-161-110 - Use of other funds to match RATA funds.

Can use other funds to meet the county matching requirement.

Page 38: The County Road Administration Board -  CRAB RAP Process  & WACs

Emergency projects

WAC 136-163-03 Eligibility

The county must declare an emergency - attach to RAP Online form County must evaluate if State declaration ER FHWA And Presidential declaration – FEMA CRABoard will consider matching only after Fed $ is approved. If no Federal funding, CRAB can provide up to 90% If funded, the county will have a commensurate reduction in future funding limit.

Page 39: The County Road Administration Board -  CRAB RAP Process  & WACs

Emergent Projects

WAC 136-163-040

Scored by CRAB as a regular project. Must rank at or above the funding line on the current array County must show the need was unable to be anticipated for 6YR TIP If funded, the county will have a commensurate reduction in future funding

limit.

Page 40: The County Road Administration Board -  CRAB RAP Process  & WACs

Increase RAP funding

136-165-020 Requirements

CRABoard will not fund Scope Creep. The increase must be based extraordinary and unforeseeable circumstances

beyond the control of the county. Cost increases during construction are borne by county Request only once – prior to award or commencement. Increase funding is limited to < 25% of current RATA funding Provide an updated engr. est. 3 months prior to advertisement or

commencement, If funded, the county will have a reduction in future funding limit.

Page 41: The County Road Administration Board -  CRAB RAP Process  & WACs

Alternative to increased funding

136-165-020 continued:

Resubmit the same project for needed funding in the next cycle. If funded 2nd time, prior contract becomes void. Repay expended funds unless waived by CRABoard.

Page 42: The County Road Administration Board -  CRAB RAP Process  & WACs

Withdrawal of contract type 1:– No RATA spent

WAC 136-167-020:

Commissioner or executive signed letter Receipt by CRAB staff County selects Withdraw button online. CRABstaff confirms withdrawal online which archives the contract/project

Page 43: The County Road Administration Board -  CRAB RAP Process  & WACs

Withdrawal of contract type 2:– Some RATA spent

WAC 136-167-030:

Commissioner or executive signed letter, agrees to pay back RATA Reimbursement check sent to CRAB Receipt od letter and reimbursement by CRAB staff County selects Withdraw button online. CRABstaff confirms withdrawal online which archives the contract/project

Page 44: The County Road Administration Board -  CRAB RAP Process  & WACs

Withdrawal of contract type 3:– Waive payback WAC 136-167-030:

Commissioner or executive signed letter, explains request for waiver Attach waiver request form Receipt by CRAB staff County staff attends CRABoard meeting to plea their case. If approved, Contract amendment is sent online County signs and returns amendment and any reimbursable RATA County selects Withdraw button online. CRABstaff confirms withdrawal online which archives the contract/project

Page 45: The County Road Administration Board -  CRAB RAP Process  & WACs

Withdrawal of contract type 4:– Design Study Waiver WAC 136-167-030:

Commissioner or executive signed letter, in which the Engineer explains that prospectus must be altered due to factors not anticipated, and that county intends to withdraw unanticipated scope change.

County can request to retain up to 5% of RATA but < $75,000 $s must be associated with the design study CRAB director consideration, determination. (not the CRABoard) Contract is amended County signs and returns amendment and any reimbursable RATA County selects Withdraw button online. CRABstaff confirms withdrawal online which archives the contract/project

Page 46: The County Road Administration Board -  CRAB RAP Process  & WACs

Withdrawal of contract type 4 continued:– Design Study Waiver – further details

WAC 136-167-030 continued –

The County must demonstrate / explain basis of request is for:

Unanticipated subsurface conditions, or Unanticipated cultural resource issues, or Changes due to annexation or FC, or Right of Way issues with agencies not subject to eminent domain, or Major geometric changes required to mitigate unanticipated impacts

Page 47: The County Road Administration Board -  CRAB RAP Process  & WACs

Withdrawal of contract type 4 continued:– Design Study Waiver – further details

WAC 136-167-030 continued – Director determination: Repay all costs in excess of eligible amount within 60 days Contract is amended County signs and returns amendment and any reimbursable RATA County selects Withdraw button online. CRABstaff confirms withdrawal online which archives the contract/project

The County may appeal the director’s determination to the CRABoard.

Page 48: The County Road Administration Board -  CRAB RAP Process  & WACs

WAC 136-167-040

Project must commence design within one year of approval Request reimbursement PDF copy of payment made by other source of funds

Project must commence construction within six years of approval. Start of County Forces Construction. Submit a RAP Voucher or copy of other Advertisement for Construction Bids – PDF Affidavit of Publication Solicitation of prices from contractors on Small Works Roster. Engr. Letter, email

Lapsing Milestones Project Notification and Voucher submittals

Page 49: The County Road Administration Board -  CRAB RAP Process  & WACs

WAC 136-167-040

Delay is unanticipated and beyond county’s control. Demonstrate the project was actively pursued. Request at least 10 days prior to CRABoard withdrawal of project. May be granted once, for no more than 2 years.

Time Extensions

Page 50: The County Road Administration Board -  CRAB RAP Process  & WACs

Time Extensions - CRABoard Moratorium

WAC 136-167-040 continued:

A CRABoard moratorium allows projects to be delayed to fit the CRABoard's programming needs such as maintaining a cash flow balance

A new lapsing date is set for the delayed projects and the usual rules on lapsing are held in abeyance until the new lapsing date.

Page 51: The County Road Administration Board -  CRAB RAP Process  & WACs

Construction methods notification - WAC 136-170 Future CRAB/County contracts

Future RAP contracts will have provisions that allow:a) Phasing, (because phasing is common practice it will be a

standard contract provision)

However, the county must notify of phasing plan at least 15 days prior to:• Advertisement if first phase is by comp. bid• Commencement if 1st phase is by County Forces• Solicitation for prices if 1st phase is by small works roster.

Commencement of all phases must occur within 2 years of commencement of the first phase:

Page 52: The County Road Administration Board -  CRAB RAP Process  & WACs

Completion of Contract notification

WAC 136-170-030 - Completion through the online application requires:

1. Marking each phase as “has commenced – yes” 2. Marking the final voucher as final3. Adding before during and after photos4. Showing costs and funding sources this is a form offered in RAPOnline5. Project Narrative.

• Importance of the road• Deficiencies• Improvements and any special construction features

The above information is ready made for CRAB’s annual Report.

Page 53: The County Road Administration Board -  CRAB RAP Process  & WACs

WEB RAP will adapt Helps County and CRAB can easily monitor project progress.

We can respond to legislature by showing project specific cash flow and lower RATA balance.

Encourages managers and technical staff to communicate more often about the project.

Will continue to be simple, unique and responsive.

Open to suggestions: CRAB Grant Program Manager 360-753-5989.