The Council of State Governments Eastern Regional Conference Gordon van Welie, President and CEO,...
-
Upload
brian-reynold-davis -
Category
Documents
-
view
219 -
download
2
Transcript of The Council of State Governments Eastern Regional Conference Gordon van Welie, President and CEO,...
The Council of State GovernmentsEastern Regional Conference
Gordon van Welie, President and CEO, ISO New EnglandAugust 16, 2010 Portland, Maine
ISO New England’s Core Responsibilities Are Interconnected and Interdependent
Operating the Power SystemMinute-to-minute reliable operation of region’s generation and transmission system
Administering Wholesale Electric Markets Oversee region’s wholesale marketplace for energy, capacity and reserve supplies
Power System PlanningEnsure reliable and efficient power system to meet current and future power needs
2CSG Eastern Regional Conference
© 2010 ISO New England Inc.
3
Regional Planning, Centralized System Operations, Competitive Markets Provide Benefits
• Expanded transmission development
• New generation and demand resources
• Generator availability improvements
• Economic and environmental benefits
CSG Eastern Regional Conference © 2010 ISO New England Inc.
4
Transmission Projects Maintain Reliability $4 Billion invested since 2002, $5 Billion on horizon
4
5
12
7
9
8b
3
6
101. Southwest CT Phase I2. Southwest CT Phase II3. NSTAR 345 kV Project, Phases I & II4. Northwest Vermont5. Northeast Reliability Interconnect6. Monadnock Area7. New England East-West Solution8. Southeast Massachusetts
a. Short-term upgradesb. Long-term Lower SEMA Project
9. Maine Power Reliability Program10.Vermont Southern Loop
In service
Under construction
Under study
DOE highlights progress in New England
In the Energy Policy Act of 2005, Congress directed the U.S. Department of Energy to conduct a study every three years
on electric transmission congestion and constraints.
In its latest (2009) study, DOE dropped New England from its list of “Congestion Areas of Concern” citing the region’s
success in developing transmission, generation, and demand-side resources.
8a
CSG Eastern Regional Conference © 2010 ISO New England Inc.
5
Region Adding Efficient Generation Capacity
1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010/11
2011/12
2012/13
2013/14
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
Annual Additions Cumulative Additions
Capacity (MW)
*FCA 4 (2013/14) based on preliminary information
FCM
■ New Supply Cleared through FCA-1, 2, 3, 4
5CSG Eastern Regional Conference
© 2010 ISO New England Inc.
Represents approximately 45% of 2013-2014 Installed Capacity Requirement
Strong Growth in Regional Demand Resources
CT 771 CT 930
VT 81VT 148
MA 680
MA 1,379NH 104
NH 129
ME 522
ME 444
RI 140
RI 231
0
500
1,000
1,500
2,000
2,500
3,000
3,500
Capacity(MW)
6
FCM
2010-2014: Total DR Cleared in FCM 1, 2, 3, and 4
(Includes new and existing DR)DR totals include a cap of 600 MW on real-time emergency generation resources
FCA 4 (2013/14) based on preliminary information
Total DR Enrollment in ISO Programs prior to start of FCM
CSG Eastern Regional Conference © 2010 ISO New England Inc.
7
Generator Availability ImprovementsWholesale Markets provide strong incentives to improve resource availability
1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 200960
65
70
75
80
85
90
95
100
System Average Wood/Refuse Hydro
Pumped Storage
New
Eng
land
Sys
tem
Wei
ghte
d E
quiv
alen
t A
vaila
bilit
y F
acto
rs,
%
CSG Eastern Regional Conference © 2010 ISO New England Inc.
Electricity Prices Follow Natural Gas PricesNatural Gas represents approximately 38% and 42% of region’s capacity and energy respectively
8
Mar
-03
Sep-0
3
Mar
-04
Sep-0
4
Mar
-05
Sep-0
5
Mar
-06
Sep-0
6
Mar
-07
Sep-0
7
Mar
-08
Sep-0
8
Mar
-09
Sep-0
9
Mar
-10
$0
$20
$40
$60
$80
$100
$120
$0
$4
$8
$12
$16
$20
$24
Real-Time LMP Natural Gas Price
RT
Hu
b L
MP
($/
MW
h)
Gas
Pri
ce (
$/M
MB
tu)
CSG Eastern Regional Conference © 2010 ISO New England Inc.
9
Many Renewable Projects Proposed 3,400 MW of Renewables in ISO Queue, Majority Wind
CT; 63.5; 2%
MA; 717.5; 21%
ME; 1327.
5; 39%
NH464.514%
RI; 598.2; 18%
VT; 221.7;
7%
Wind; 2879; 84%
Hydro; 34; 1%
Biomass; 444; 13%
LFG 35.51%
Solar; 20; 1%
Includes: Landfill Gas, Hydro, Wind , Solar and Biomass. Pump Storage projects in the ISO Queue are not included.
Renewables in Queue
By Fuel Type
Renewables in Queue
By State
CSG Eastern Regional Conference © 2010 ISO New England Inc.
10
ISO Preparing Region to Integrate Wind
• Wind Integration Study– Model on- and off-shore
wind capability
– Recommend technical interconnection requirements
– Assess operational impacts of varying wind scenarios
– Target completion date – October 2010
• Preliminary Observations– Region has large amounts of
high quality wind potential
– Regional wind variability is moderate and manageable
– ISO has ability to manage and integrate significant amounts of wind power
CSG Eastern Regional Conference © 2010 ISO New England Inc.
11
Governors 20-Year Renewable Energy Vision Accessing wind possible but requires investment
States’ Blueprint as guiding policy and regulatory framework
ISO economic study as technical support
CSG Eastern Regional Conference © 2010 ISO New England Inc.
12
Renewable Resources Remote from Demand
Wind zones
Electricity Demand
• Population and electricity demand concentrated in southern New England
• Wind resources do not overlap with high demand areas
• Estimated transmission costs to access 5,500 MW of regional wind plus 3,000 MW of additional Canadian imports: ~$7 B to ~$12 B
CSG Eastern Regional Conference © 2010 ISO New England Inc.
13
5
1. HQ–New Hampshire LineHQ/Northeast Utilities/NSTAR
2. Northeast Energy LinkBangor Hydro/National Grid
3. Green LineNew England ITC
4. Seabrook-Boston-Cape CableNextEra Energy (formerly FPL)
5. Northeast Energy CorridorMaine/New Brunswick
6. Wind from the Midwest
7. Champlain Hudson ExpressTransmission Developers Inc.
8. Plattsburgh, NY–New Haven, VT
9. Interconnect Northern Maine
2
1
4
3
6
57
8
9 New Brunswick
Nova Scotia
Québec
New York
Transmission Projects Vying to Move Renewable Energy to High Demand Areas
Representative Projects
13CSG Eastern Regional Conference
© 2010 ISO New England Inc.
14
Funding Transmission to Access Renewables Remains a Challenge
• Regional cost allocation methodology well-established and generally accepted for reliability projects
• No agreement as to how to pay for transmission built to access renewables– A regional and national issue
• Long-term Power Purchase Agreements (PPAs) could include the cost of energy and transmission – New England has begun exploring potential for coordinated
procurement
CSG Eastern Regional Conference © 2010 ISO New England Inc.
15
Coordinated Effort May Help Facilitate Regional Renewable Supply
CSG Eastern Regional Conference © 2010 ISO New England Inc.
Excerpt New England States’ Committee on Electricity (NESCOE) report, July 2010
“Renewable power procurement could aggregate demand for renewable power and enhance buying power, stimulate the market for renewable resources; and provide value to renewable project developers by creating larger revenue streams than might otherwise be possible. Using cooperative competitive processes may, therefore, facilitate development in cost–effective, low-carbon renewable electric generation in and around the region.”
16
Coordinated Procurement Process Identifies Cost-Effective Projects • Offers states the ability to broadly procure cost-effective
renewables for consumers – Allows use of competitive procurement processes similar to
what the states already utilize– Consistent with authority to site infrastructure, including multi-
state transmission projects – Achieves state public policy objectives
• Focuses ISO planning efforts on broader integration of wind and other resources – Ensures technical feasibility
• Can help resolve cost allocation issues
CSG Eastern Regional Conference © 2010 ISO New England Inc.
17
Federal Activity to Address Transmission Planning and Funding
• Department of Energy funds Eastern Interconnection Planning Collaborative (EIPC)
• Senate energy bill links planning, siting and cost allocation • FERC issued Notice of Proposed Rulemaking (NOPR) to
amend transmission planning and cost allocation– Transmission planners required to account for state and federal
public policies in planning – Cost allocation methods for intra- and inter- regional projects to
be based on beneficiary model
CSG Eastern Regional Conference © 2010 ISO New England Inc.
18
Closing Thoughts … • Region has benefited from a system that combines system
planning, centralized operations and competitive markets
• New England has strong renewable potential– Developers proposing to build renewable generation, particularly wind– See http://www.iso-ne.com/nwsiss/grid_mkts/index.html for recent
article “Where will New England’s electricity come from in 5, 10, and 20 years?”
• Funding transmission to access wind is the outstanding question – but coordinated procurement and regional cooperation may help– Consideration with New England stakeholders underway.
CSG Eastern Regional Conference © 2010 ISO New England Inc.