Transcript of The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) +...
![Page 1: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/1.jpg)
The Challenge to Install 1,300 New Water Meters
![Page 2: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/2.jpg)
ScopeScope
• Install electromagnetic meters (mostly) + telemetry + solar power
• ~700 sites in Upper Murray Valley
• ~600 sites in Murrumbidgee Valley
• Data forwarded to NOW and SWC
![Page 3: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/3.jpg)
Sites: Upper MurraySites: Upper Murray
• Regulated, unregulated and groundwater sites
![Page 4: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/4.jpg)
Sites: MurrumbidgeeSites: Murrumbidgee
• Regulated entitlement licences only
![Page 5: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/5.jpg)
Challenge 1: Early PlanningChallenge 1: Early Planning
• Align stakeholder expectations
• Scope the practical challenges in detail
• Integrate two projects into a single contract
• Ensure legislative backing (installing meters into private infrastructure)
• Collect extensive site data
• Prepare project plan
![Page 6: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/6.jpg)
Challenge 2: ProcurementChallenge 2: Procurement
• Appoint Managing Contractor
• Draft the meter specifications and establish supply contracts.
![Page 7: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/7.jpg)
Challenge 3: Detailed PlanningChallenge 3: Detailed Planning
• Site data proofing
• Prepare concept designs
• Identify resource requirements
• WHS, QA and Environmental assessment procedures
• Prepare a work schedule
• Establish the Guaranteed Maximum Price
• Review and approve
![Page 8: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/8.jpg)
Challenge 4: ImplementationChallenge 4: Implementation
• Landholder consultation
• Appoint subcontractors
• Site variability (!)
• Buried sites (unable to inspect prior)
• Clarity in specifications for installers
• Consistency in subcontractor outputs (QA)
![Page 9: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/9.jpg)
Murray StatusMurray Status
(31 May 2012)(31 May 2012)
![Page 10: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/10.jpg)
Murrumbidgee StatusMurrumbidgee Status
(31 May 2012)(31 May 2012)
![Page 11: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/11.jpg)
Original SiteOriginal Site
![Page 12: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/12.jpg)
Original SiteOriginal Site
![Page 13: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/13.jpg)
Original SiteOriginal Site
![Page 14: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/14.jpg)
Original SiteOriginal Site
![Page 15: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/15.jpg)
Original SiteOriginal Site
![Page 16: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/16.jpg)
Site Under ConstructionSite Under Construction
![Page 17: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/17.jpg)
Completed SiteCompleted Site
![Page 18: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/18.jpg)
Completed SiteCompleted Site
![Page 19: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/19.jpg)
LessonsLessons
• Require reliable site data
• Regulatory support is critical
• Benefits from an experienced team
• Appropriate landholder consultation
• Need for some flexibility
• Clear specifications and quality control
• Good data management
• Fast roll-out possible with good planning.
![Page 20: The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.](https://reader036.fdocuments.net/reader036/viewer/2022062511/5513c82c5503466f748b48b3/html5/thumbnails/20.jpg)
Thank youThank you
Stephen Moore