TF Joint Testing Data Acquisition Special Test Equipment
Hans Schneiderwith Robert Marsala
(609) [email protected] Operations
April 2003
![Page 2: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April.](https://reader035.fdocuments.net/reader035/viewer/2022062717/56649e485503460f94b3b893/html5/thumbnails/2.jpg)
Hans SchneiderEngineering Operations
2
Resistance Measurement PlanPrototype & Insitu Joints
• Mechanical Prototype Testing
• Electrical Prototype Testing
• Maintenance Insitu Testing
• Commissioning Insitu Testing
![Page 3: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April.](https://reader035.fdocuments.net/reader035/viewer/2022062717/56649e485503460f94b3b893/html5/thumbnails/3.jpg)
Hans SchneiderEngineering Operations
4
Resistance Measurement PlanMechanical TF Joint Test System
• Mechanical Prototype Testing– Cyclical Mechanical Loads Applied to Prototype Joint
– Measure Joint Voltage Drop with 100 Amperes Applied
– Voltage Measured at Two Joint Locations
– Automated Test Stand Control & Data Acquisition
![Page 4: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April.](https://reader035.fdocuments.net/reader035/viewer/2022062717/56649e485503460f94b3b893/html5/thumbnails/4.jpg)
Hans SchneiderEngineering Operations
5
Resistance Measurement PlanMechanical TF Joint Test System
• Mechanical Prototype Testing– Cyclical Mechanical Loads Applied to Prototype Joint
– Measure Joint Voltage Drop with 100 Amperes Applied
– Voltage Measured at Two Joint Locations
– Automated Test Stand Control & Data Acquisition
• Joint Voltage Drop Accuracy Factors– Limited by Cycle Time
– Initial Investigation Indicates 0.5% Should be Possible
– Cycle Dwells Could Increase Accuracy to 0.2% or Better
![Page 5: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April.](https://reader035.fdocuments.net/reader035/viewer/2022062717/56649e485503460f94b3b893/html5/thumbnails/5.jpg)
Hans SchneiderEngineering Operations
8
Resistance Measurement PlanElectrical TF Joint Test System
• Electrical Prototype Testing– Cyclical Electrical Loads Applied to Prototype Joint
– Measure Joint Voltage Drop with > 70,000 Amperes Applied
– Voltage Measured at Up to Eight Joint Locations
– Remote Control of Automated Data Acquisition System
![Page 6: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April.](https://reader035.fdocuments.net/reader035/viewer/2022062717/56649e485503460f94b3b893/html5/thumbnails/6.jpg)
Hans SchneiderEngineering Operations
9
Resistance Measurement PlanElectrical TF Joint Test System
• Electrical Prototype Testing– Cyclical Electrical Loads Applied to Prototype Joint
– Measure Joint Voltage Drop with > 70,000 Amperes Applied
– Voltage Measured at Up to Eight Joint Locations
– Remote Control of Automated Data Acquisition System
• Joint Voltage Drop Accuracy Factors– TF Power Supply Current Measurement Accuracy
– Magnetic Field Influences on Measurement Leads & System
– Unknown Accuracy at This Time
![Page 7: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April.](https://reader035.fdocuments.net/reader035/viewer/2022062717/56649e485503460f94b3b893/html5/thumbnails/7.jpg)
Hans SchneiderEngineering Operations
12
Resistance Measurement PlanInsitu Maintenance Test System
• Maintenance Insitu Testing– Permanent Test Cell Installation
– Measure Joint Voltage Drop with +/-200 Amperes Applied
– Each of 48 Joints Measured at One Joint Location
– Automated Test Cell Data Acquisition System
![Page 8: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April.](https://reader035.fdocuments.net/reader035/viewer/2022062717/56649e485503460f94b3b893/html5/thumbnails/8.jpg)
Hans SchneiderEngineering Operations
13
Resistance Measurement PlanInsitu Maintenance Test System
• Maintenance Insitu Testing– Permanent Test Cell Installation
– Measure Joint Voltage Drop with +/-200 Amperes Applied
– Each of 48 Joints Measured at One Joint Location
– Automated Test Cell Data Acquisition System
• Joint Voltage Drop Accuracy Factors– “Ambient” Electrical Noise & Long Joint Cable Leads
– Combat with DC Current Reversal & Long Integration Times
– Unknown Accuracy at This Time
![Page 9: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April.](https://reader035.fdocuments.net/reader035/viewer/2022062717/56649e485503460f94b3b893/html5/thumbnails/9.jpg)
Hans SchneiderEngineering Operations
15
Resistance Measurement Plan Insitu Commissioning Test System
• Commissioning Insitu Testing– Utilizes Maintenance System Wiring
– Measure Joint Voltage Drop with Up to 72,000 Amperes
– Instrument One, Possibly Two TF Flag Joints
– Data Collected via 908 or 3232 Transient Digitizer
![Page 10: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April.](https://reader035.fdocuments.net/reader035/viewer/2022062717/56649e485503460f94b3b893/html5/thumbnails/10.jpg)
Hans SchneiderEngineering Operations
16
Resistance Measurement Plan Insitu Commissioning Test System
• Commissioning Insitu Testing– Utilizes Maintenance System Wiring
– Measure Joint Voltage Drop with Up to 72,000 Amperes
– Instrument One, Possibly Two TF Flag Joints
– Data Collected via 908 or 3232 Transient Digitizer
• Joint Voltage Drop Accuracy Factors– TF Power Supply Current Measurement Accuracy
– Magnetic Field Influences on Measurement Leads & System
– Unknown Accuracy at This Time
![Page 11: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April.](https://reader035.fdocuments.net/reader035/viewer/2022062717/56649e485503460f94b3b893/html5/thumbnails/11.jpg)
Hans SchneiderEngineering Operations
21
Resistance Measurement PlanPrototype & Insitu Joints
• Mechanical Prototype Testing
• Electrical Prototype Testing
• Maintenance Insitu Testing