Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006
-
Upload
tarik-hoffman -
Category
Documents
-
view
22 -
download
0
description
Transcript of Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006
http://nodal.ercot.com 1Lead from the front
Texas Nodal
Texas Nodal Market Implementation Program
Implementation Scenarios
September 6, 2006
http://nodal.ercot.com 2Lead from the front
Texas Nodal
Scenario #1 – single release (baseline) (Nodal Market live & Zonal Market Shutdown July 2009)
EMS
Early Delivery Systems
MMS
CRR
MIS
NMMS
Commercial Systems
ERCOT & MP Readiness
Q2 2008 Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006 Q4 2007Q3 2007 Q1 2008Q3 2006 Q1 2009
Outage Scheduler
EDW
“UI in production”
Q2 2009
Qualification Freeze
EDS 3 (TXMACS 0.3)SCED; MP SCED Offers
EDS 4 TXMACS 0.4)
with selected MPsEDS 5 (TXMACS 0.5)
MMS FAT MMS SAT
CRR Design, Build, Pre-FAT CRR FAT CRR SAT
Final MP Interface
Specs 3/31
MP Registration complete
MIS FAT MIS SAT
168 hour market trial
FAT SAT
Naming Convention DB
NMMS BuildCommon model update process
NODAL GO LIVE
MIS (EMS/MMS/CRR) Design, Build, Pre-FAT
EDW FAT EDW SAT
StatementsLayout
Script test Credit Monitoring
End of Trials
MP Nodal Registration MP Financial & Operational Qualification
EMS SATEMS EMS FATEMS Requirements, Conceptual Design
MIS SATMIS (SCED) Design, Build, Pre-FAT MIS FAT
MMS Design, Build, Pre-FATMMS Requirements, Conceptual Design
OS SATOS Build OS FATOS Requirements, Conceptual Design
CRR Requirements, Conceptual Design
Commercial Systems Design, Build, Pre-FAT CS FAT CS SAT
EDW Requirements, Conceptual Design
SCED SATSCED Build SCED FATSCED Requirements, Conceptual Design
Registration ready
MPSCED Offers
Business Requirements
complete 10/30
Preliminary MP Interface Specs 12/31
CS FAT CS SAT
EDW FAT EDW SAT EDW FAT EDW SAT
CS Requirements, Conceptual Design
EDW Design, Build, Pre-FAT
MIS FAT MIS SAT
Begin MP trial participation
“Non-binding settlements”
Financial Transfer
CS FAT CS SAT
EDS 4 MP SAT
TXMACS 1.0Live
operations
MIS FAT MIS SAT
“CRR Auction for Go Live”
OTS SAT
OTS FAT
EDS 3 Data Validation
NMMS Conceptual Design
Naming Convention information collection
Model Data Certification Model Data Remediation Reconciliation
Assumptions affecting the critical path
The current State Estimator will meet the necessary criteria
Current NMMS product will be capable of providing Real Time Models for any Nodal System
Vendors selection will be done by Mid-June
Vendors will share detailed design documents with other vendors for interface definitions
TDSPs will be trained on new NMMS and there will dual entry of models – into the new NMMS and into GENESYS. ERCOT will have enough staff to handle this work
To allow for interface definitions, detailed design documents of individual projects can be completed 80 hours after one another. The order of completion will be NMMS – MMS/EMS/SE – CRR/Outage Schedule – Commercial Systems – MIS/EDW
To satisfy section 17.3 of the Nodal protocols, ERCOT will deploy COGNOS and SAS to provide PUCT with the ability to generate reports
ERCOT would need 6 months of integration testing on applications such as MMS, CRR and NMMS
Areva’s EMS will handle CIM models
All systems have to conform with the integrated Data Dictionary
TPTF will hold review meetings as required for approval of requirements and conceptual design documents
http://nodal.ercot.com 3Lead from the front
Texas Nodal
Scenario #2 – 3 incremental releases & slack removed (Release 2 & Zonal Shutdown July ’08, Release 3 January ’09)
EMS
Trials & Implementation
MMS
CRR
MIS
NMMS
Commercial Systems
ERCOT & MP Readiness
Q2 2008 Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006 Q4 2007 Q1 2008Q3 2006 Q1 2009
Integration
EDW
Q2 2009
Qualification Freeze
EDS 3
EDS 4
MMS FAT ITEST
CRR Design, Build, Pre-FAT CRR FAT ITEST
Final MP Interface
Specs 3/31
MP Registration complete
168 hour market
trial
Real Time Operations
GO/NO GOZonal Shutdown
GO/NO GO
MIS (EMS/MMS/CRR) Design, Build, Pre-FAT
EDW FAT ITEST
StatementsLayout
Script test
End of Trials
MP Nodal RegistrationMP Financial &
Operational Qualification
ITESTEMS EMS FATEMS Requirements, Conceptual Design
ITESTMIS (SCED) Design, Build, Pre-FAT MIS FAT
MMS Design, Build, Pre-FATMMS
Requirements, Conceptual Design
ITEST
OS Build
FAT
OS Requirements, Conceptual Design
CRR Requirements, Conceptual Design
Commercial Systems Design, Build, Pre-FAT CS FAT ITEST
EDW Requirements, Conceptual Design
ITESTSCED Build SCED FATSCED
Requirements, Conceptual Design
Registration ready
MPSCED Offers
Business Requirements
complete 10/30
Preliminary MP Interface Specs 12/31
CS Requirements, Conceptual Design
EDW Design, Build, Pre-FAT
MIS FAT ITEST
Begin MP trial participation
EDS 4 MP SAT
OTS ITEST
OTS FAT
EDS 3 Data Validation
Planning UI
FAT ITEST
Naming Convention DB
Common model update processNMMS Conceptual Design
Naming Convention information collection
Model Data Certification Model Data Remediation Reconciliation
NMMS Build
Outage Scheduler
EDS 1/2
Build FAT ITESTRequirements, Conceptual Design
ITESTOS FAT
Forward Markets
GO/NO GO
Single Entry Model
GO LIVE
Q3 2007
Operations UI
http://nodal.ercot.com 4Lead from the front
Texas Nodal
Scenario #3 – Release 2 & 3 combined & slack removed(Nodal Market live & Zonal Market Shutdown January 2009)
EMS
Early Delivery Systems
MMS
CRR
MIS
NMMS
Commercial Systems
ERCOT & MP Readiness
Q2 2008 Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006 Q4 2007Q3 2007 Q1 2008Q3 2006 Q1 2009
Outage Scheduler
EDW
Q2 2009
EDS 3 (TXMACS 0.3)SCED; MP SCED Offers
EDS 4 TXMACS 0.4)
with selected MPs
MMS FAT MMS SAT
CRR Design, Build, Pre-FAT CRR FAT CRR SAT
Final MP Interface
Specs 3/31
NODAL GO LIVE
MIS (EMS/MMS/CRR) Design, Build, Pre-FAT
EDW FAT EDW SAT
StatementsLayout
Script test
EMS SATEMS EMS FATEMS Requirements, Conceptual Design
MIS SATMIS (SCED) Design, Build, Pre-FAT MIS FAT
MMS Design, Build, Pre-FATMMS Requirements, Conceptual Design
OS SATOS Build OS FATOS Requirements, Conceptual Design
CRR Requirements, Conceptual Design
Commercial Systems Design, Build, Pre-FAT CS FAT CS SAT
EDW Requirements, Conceptual Design
SCED SATSCED Build SCED FATSCED Requirements, Conceptual Design
Registration ready
Business Requirements
complete 10/30
Preliminary MP Interface Specs 12/31
CS Requirements, Conceptual Design
EDW Design, Build, Pre-FAT
MIS FAT MIS SAT
EDS 4 MP SAT
TXMACS 1.0Live
operations
OTS SAT
OTS FAT
EDS 3 Data Validation
Qualification Freeze
MP Registration complete
168 hour market
trialEnd of Trials
MP Nodal RegistrationMP Financial &
Operational Qualification
MPSCED Offers
Begin MP trial participation
Planning UI
FAT ITEST
Naming Convention DB
Common model update processNMMS Conceptual Design
Naming Convention information collection
Model Data Certification Model Data Remediation Reconciliation
NMMS Build
Operations UI
EDS 1/2
Single Entry Model
GO LIVE
http://nodal.ercot.com 5Lead from the front
Texas Nodal
Scenario #4 – 3 incremental releases, timed for seasonality(Release 2 & Zonal Shutdown October ’08, Release 3 February ’09)
EMS
Trials & Implementation
MMS
CRR
MIS
NMMS
Commercial Systems
ERCOT & MP Readiness
Q2 2008 Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006 Q4 2007 Q1 2008Q3 2006 Q1 2009
Integration
EDW
Q2 2009
EDS 3
MMS FAT ITEST
CRR Design, Build, Pre-FAT CRR FAT ITEST
Final MP Interface
Specs 3/31
MP Registration complete
168 hour market
trial
Real Time Operations
GO/NO GOZonal Shutdown
GO/NO GO
MIS (EMS/MMS/CRR) Design, Build, Pre-FAT
EDW FAT ITEST
StatementsLayout
Script test
End of Trials
MP Nodal Registration & Qualification sequence
ITESTEMS EMS FATEMS Requirements, Conceptual Design
ITESTMIS (SCED) Design, Build, Pre-FAT MIS FAT
MMS Design, Build, Pre-FATMMS
Requirements, Conceptual Design
ITEST
OS Build
FAT
OS Requirements, Conceptual Design
CRR Requirements, Conceptual Design
Commercial Systems Design, Build, Pre-FAT CS FAT ITEST
EDW Requirements, Conceptual Design
ITESTSCED Build SCED FATSCED
Requirements, Conceptual Design
Registration ready
MPSCED Offers
Business Requirements
complete 10/30
Preliminary MP Interface Specs 12/31
CS Requirements, Conceptual Design
EDW Design, Build, Pre-FAT
MIS FAT ITEST
Begin MP trial participation
EDS 4 EDS 4 MP SAT
OTS ITEST
OTS FAT
EDS 3 Data Validation
Planning UI
FAT ITEST
Naming Convention DB
Common model update processNMMS Conceptual Design
Naming Convention information collection
Model Data Certification Model Data Remediation Reconciliation
NMMS Build
Outage Scheduler
EDS 1/2
Build FAT ITESTRequirements, Conceptual Design
ITESTOS FAT
Forward Markets
GO/NO GO
Single Entry Model
GO LIVE
Q3 2007
Operations UI