Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006

5
http://nodal.ercot.com 1 Lead from the front Texas Nodal Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006

description

Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006. OTS FAT. OTS SAT. Scenario #1 – single release (baseline) (Nodal Market live & Zonal Market Shutdown July 2009). Q3 2006. Q4 2006. Q1 2007. Q2 2007. Q3 2007. Q4 2007. Q1 2008. Q2 2008. Q3 2008. - PowerPoint PPT Presentation

Transcript of Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006

Page 1: Texas Nodal Market Implementation Program  Implementation  Scenarios  September 6, 2006

http://nodal.ercot.com 1Lead from the front

Texas Nodal

Texas Nodal Market Implementation Program

Implementation Scenarios

September 6, 2006

Page 2: Texas Nodal Market Implementation Program  Implementation  Scenarios  September 6, 2006

http://nodal.ercot.com 2Lead from the front

Texas Nodal

Scenario #1 – single release (baseline) (Nodal Market live & Zonal Market Shutdown July 2009)

EMS

Early Delivery Systems

MMS

CRR

MIS

NMMS

Commercial Systems

ERCOT & MP Readiness

Q2 2008 Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006 Q4 2007Q3 2007 Q1 2008Q3 2006 Q1 2009

Outage Scheduler

EDW

“UI in production”

Q2 2009

Qualification Freeze

EDS 3 (TXMACS 0.3)SCED; MP SCED Offers

EDS 4 TXMACS 0.4)

with selected MPsEDS 5 (TXMACS 0.5)

MMS FAT MMS SAT

CRR Design, Build, Pre-FAT CRR FAT CRR SAT

Final MP Interface

Specs 3/31

MP Registration complete

MIS FAT MIS SAT

168 hour market trial

FAT SAT

Naming Convention DB

NMMS BuildCommon model update process

NODAL GO LIVE

MIS (EMS/MMS/CRR) Design, Build, Pre-FAT

EDW FAT EDW SAT

StatementsLayout

Script test Credit Monitoring

End of Trials

MP Nodal Registration MP Financial & Operational Qualification

EMS SATEMS EMS FATEMS Requirements, Conceptual Design

MIS SATMIS (SCED) Design, Build, Pre-FAT MIS FAT

MMS Design, Build, Pre-FATMMS Requirements, Conceptual Design

OS SATOS Build OS FATOS Requirements, Conceptual Design

CRR Requirements, Conceptual Design

Commercial Systems Design, Build, Pre-FAT CS FAT CS SAT

EDW Requirements, Conceptual Design

SCED SATSCED Build SCED FATSCED Requirements, Conceptual Design

Registration ready

MPSCED Offers

Business Requirements

complete 10/30

Preliminary MP Interface Specs 12/31

CS FAT CS SAT

EDW FAT EDW SAT EDW FAT EDW SAT

CS Requirements, Conceptual Design

EDW Design, Build, Pre-FAT

MIS FAT MIS SAT

Begin MP trial participation

“Non-binding settlements”

Financial Transfer

CS FAT CS SAT

EDS 4 MP SAT

TXMACS 1.0Live

operations

MIS FAT MIS SAT

“CRR Auction for Go Live”

OTS SAT

OTS FAT

EDS 3 Data Validation

NMMS Conceptual Design

Naming Convention information collection

Model Data Certification Model Data Remediation Reconciliation

Assumptions affecting the critical path

The current State Estimator will meet the necessary criteria

Current NMMS product will be capable of providing Real Time Models for any Nodal System

Vendors selection will be done by Mid-June

Vendors will share detailed design documents with other vendors for interface definitions

TDSPs will be trained on new NMMS and there will dual entry of models – into the new NMMS and into GENESYS. ERCOT will have enough staff to handle this work

To allow for interface definitions, detailed design documents of individual projects can be completed 80 hours after one another. The order of completion will be NMMS – MMS/EMS/SE – CRR/Outage Schedule – Commercial Systems – MIS/EDW

To satisfy section 17.3 of the Nodal protocols, ERCOT will deploy COGNOS and SAS to provide PUCT with the ability to generate reports

ERCOT would need 6 months of integration testing on applications such as MMS, CRR and NMMS

Areva’s EMS will handle CIM models

All systems have to conform with the integrated Data Dictionary

TPTF will hold review meetings as required for approval of requirements and conceptual design documents

Page 3: Texas Nodal Market Implementation Program  Implementation  Scenarios  September 6, 2006

http://nodal.ercot.com 3Lead from the front

Texas Nodal

Scenario #2 – 3 incremental releases & slack removed (Release 2 & Zonal Shutdown July ’08, Release 3 January ’09)

EMS

Trials & Implementation

MMS

CRR

MIS

NMMS

Commercial Systems

ERCOT & MP Readiness

Q2 2008 Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006 Q4 2007 Q1 2008Q3 2006 Q1 2009

Integration

EDW

Q2 2009

Qualification Freeze

EDS 3

EDS 4

MMS FAT ITEST

CRR Design, Build, Pre-FAT CRR FAT ITEST

Final MP Interface

Specs 3/31

MP Registration complete

168 hour market

trial

Real Time Operations

GO/NO GOZonal Shutdown

GO/NO GO

MIS (EMS/MMS/CRR) Design, Build, Pre-FAT

EDW FAT ITEST

StatementsLayout

Script test

End of Trials

MP Nodal RegistrationMP Financial &

Operational Qualification

ITESTEMS EMS FATEMS Requirements, Conceptual Design

ITESTMIS (SCED) Design, Build, Pre-FAT MIS FAT

MMS Design, Build, Pre-FATMMS

Requirements, Conceptual Design

ITEST

OS Build

FAT

OS Requirements, Conceptual Design

CRR Requirements, Conceptual Design

Commercial Systems Design, Build, Pre-FAT CS FAT ITEST

EDW Requirements, Conceptual Design

ITESTSCED Build SCED FATSCED

Requirements, Conceptual Design

Registration ready

MPSCED Offers

Business Requirements

complete 10/30

Preliminary MP Interface Specs 12/31

CS Requirements, Conceptual Design

EDW Design, Build, Pre-FAT

MIS FAT ITEST

Begin MP trial participation

EDS 4 MP SAT

OTS ITEST

OTS FAT

EDS 3 Data Validation

Planning UI

FAT ITEST

Naming Convention DB

Common model update processNMMS Conceptual Design

Naming Convention information collection

Model Data Certification Model Data Remediation Reconciliation

NMMS Build

Outage Scheduler

EDS 1/2

Build FAT ITESTRequirements, Conceptual Design

ITESTOS FAT

Forward Markets

GO/NO GO

Single Entry Model

GO LIVE

Q3 2007

Operations UI

Page 4: Texas Nodal Market Implementation Program  Implementation  Scenarios  September 6, 2006

http://nodal.ercot.com 4Lead from the front

Texas Nodal

Scenario #3 – Release 2 & 3 combined & slack removed(Nodal Market live & Zonal Market Shutdown January 2009)

EMS

Early Delivery Systems

MMS

CRR

MIS

NMMS

Commercial Systems

ERCOT & MP Readiness

Q2 2008 Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006 Q4 2007Q3 2007 Q1 2008Q3 2006 Q1 2009

Outage Scheduler

EDW

Q2 2009

EDS 3 (TXMACS 0.3)SCED; MP SCED Offers

EDS 4 TXMACS 0.4)

with selected MPs

MMS FAT MMS SAT

CRR Design, Build, Pre-FAT CRR FAT CRR SAT

Final MP Interface

Specs 3/31

NODAL GO LIVE

MIS (EMS/MMS/CRR) Design, Build, Pre-FAT

EDW FAT EDW SAT

StatementsLayout

Script test

EMS SATEMS EMS FATEMS Requirements, Conceptual Design

MIS SATMIS (SCED) Design, Build, Pre-FAT MIS FAT

MMS Design, Build, Pre-FATMMS Requirements, Conceptual Design

OS SATOS Build OS FATOS Requirements, Conceptual Design

CRR Requirements, Conceptual Design

Commercial Systems Design, Build, Pre-FAT CS FAT CS SAT

EDW Requirements, Conceptual Design

SCED SATSCED Build SCED FATSCED Requirements, Conceptual Design

Registration ready

Business Requirements

complete 10/30

Preliminary MP Interface Specs 12/31

CS Requirements, Conceptual Design

EDW Design, Build, Pre-FAT

MIS FAT MIS SAT

EDS 4 MP SAT

TXMACS 1.0Live

operations

OTS SAT

OTS FAT

EDS 3 Data Validation

Qualification Freeze

MP Registration complete

168 hour market

trialEnd of Trials

MP Nodal RegistrationMP Financial &

Operational Qualification

MPSCED Offers

Begin MP trial participation

Planning UI

FAT ITEST

Naming Convention DB

Common model update processNMMS Conceptual Design

Naming Convention information collection

Model Data Certification Model Data Remediation Reconciliation

NMMS Build

Operations UI

EDS 1/2

Single Entry Model

GO LIVE

Page 5: Texas Nodal Market Implementation Program  Implementation  Scenarios  September 6, 2006

http://nodal.ercot.com 5Lead from the front

Texas Nodal

Scenario #4 – 3 incremental releases, timed for seasonality(Release 2 & Zonal Shutdown October ’08, Release 3 February ’09)

EMS

Trials & Implementation

MMS

CRR

MIS

NMMS

Commercial Systems

ERCOT & MP Readiness

Q2 2008 Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006 Q4 2007 Q1 2008Q3 2006 Q1 2009

Integration

EDW

Q2 2009

EDS 3

MMS FAT ITEST

CRR Design, Build, Pre-FAT CRR FAT ITEST

Final MP Interface

Specs 3/31

MP Registration complete

168 hour market

trial

Real Time Operations

GO/NO GOZonal Shutdown

GO/NO GO

MIS (EMS/MMS/CRR) Design, Build, Pre-FAT

EDW FAT ITEST

StatementsLayout

Script test

End of Trials

MP Nodal Registration & Qualification sequence

ITESTEMS EMS FATEMS Requirements, Conceptual Design

ITESTMIS (SCED) Design, Build, Pre-FAT MIS FAT

MMS Design, Build, Pre-FATMMS

Requirements, Conceptual Design

ITEST

OS Build

FAT

OS Requirements, Conceptual Design

CRR Requirements, Conceptual Design

Commercial Systems Design, Build, Pre-FAT CS FAT ITEST

EDW Requirements, Conceptual Design

ITESTSCED Build SCED FATSCED

Requirements, Conceptual Design

Registration ready

MPSCED Offers

Business Requirements

complete 10/30

Preliminary MP Interface Specs 12/31

CS Requirements, Conceptual Design

EDW Design, Build, Pre-FAT

MIS FAT ITEST

Begin MP trial participation

EDS 4 EDS 4 MP SAT

OTS ITEST

OTS FAT

EDS 3 Data Validation

Planning UI

FAT ITEST

Naming Convention DB

Common model update processNMMS Conceptual Design

Naming Convention information collection

Model Data Certification Model Data Remediation Reconciliation

NMMS Build

Outage Scheduler

EDS 1/2

Build FAT ITESTRequirements, Conceptual Design

ITESTOS FAT

Forward Markets

GO/NO GO

Single Entry Model

GO LIVE

Q3 2007

Operations UI