CLIC Module Working Group Meeting
TEST MODULE TYPE “0”
Accelerating Structure Mock-upMechanical Design Update :
Change of the Manufacturing Method
Dmitry Gudkov 07-FEB-2011 «BE/RF»
![Page 2: TEST MODULE TYPE “0” Accelerating Structure Mock-up Mechanical Design Update :](https://reader036.fdocuments.net/reader036/viewer/2022062521/568163cb550346895dd5069a/html5/thumbnails/2.jpg)
Previous Configuration
2
Bars representing the accelerating structure body and vacuum manifold are produced by electro erosion wire cutting:
The machining takes very long due to large depth of the waveguidesso it was decided to change the production strategy as shown on the next slides.
![Page 3: TEST MODULE TYPE “0” Accelerating Structure Mock-up Mechanical Design Update :](https://reader036.fdocuments.net/reader036/viewer/2022062521/568163cb550346895dd5069a/html5/thumbnails/3.jpg)
Design Update. Accelerating structure
3
Coupler Disk Regular Disk
Cooling Interface Disk
Alignment Interface Disk
Brazed disks
previous
current
![Page 4: TEST MODULE TYPE “0” Accelerating Structure Mock-up Mechanical Design Update :](https://reader036.fdocuments.net/reader036/viewer/2022062521/568163cb550346895dd5069a/html5/thumbnails/4.jpg)
Design Update. Manifold
4
Brazed manifold cells
previous
Extremity cell
Regular cell
DM interface cell
current
![Page 5: TEST MODULE TYPE “0” Accelerating Structure Mock-up Mechanical Design Update :](https://reader036.fdocuments.net/reader036/viewer/2022062521/568163cb550346895dd5069a/html5/thumbnails/5.jpg)
Design Update. Assembly
5
Standard fittings:
Cooling system
Copper tubes
1. Brazing of manifolds; interface WGs; cooling adapters; 2. Brazing of 2 stacks 1005 mm long each:Includes: 4 AS with manifolds;Interconnection MB-MB;
4. Welding (EBW) of two stacks together:
EBW
3. Installation of the damping material, welding of covers:
Damping material
RFN RFNLoadLoad
CVT
AS Interfaces
![Page 6: TEST MODULE TYPE “0” Accelerating Structure Mock-up Mechanical Design Update :](https://reader036.fdocuments.net/reader036/viewer/2022062521/568163cb550346895dd5069a/html5/thumbnails/6.jpg)
Design Update. Project structure
6