Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client...

50
Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Transcript of Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client...

Page 1: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Test Lara v3.0

Access acceptance activities for Lara v3.0 client application

18/07/2016-20/07/2016

04/07/2017

Page 2: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

AUP/UUP-Scenario1: Check ‘AUP management’ capabilities

Page 3: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 1 (Draft) CIAM results

Page 4: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 1 (Ready) LARA view

Page 5: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 1 (READY) CIAM results

Page 6: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 1 demote to DRAFT LARA view

Conclusion:

As expected client application is able to handle draft status.

Page 7: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 1 demote to draft CIAM view

Page 8: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario1 +3.3: overlaps in time with deconfliction ON

Page 9: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

AUP/UUP-Scenario2: Check ‘UUP management’ capabilities

See Scenario 4.2 Synchronization with NM after release of AUP (corrective UUP).

Page 10: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

AUP/UUP-Scenario3: Check overlaps

Page 11: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 3.1

Objective Content FL and WEF-TIL Restriction Expected

3.1 Issue a NIL AUP No error, proper Remark field.

Page 12: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.1 Issue NIL AUP – LARA view1/2

Page 13: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.1 Issue NIL AUP - LARA view2/2

Page 14: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.1 Issue NIL AUP – CIAM results view

Conclusion:

As expected, no error, proper Remark field.

Page 15: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 3.2Objective Content FL and WEF-TIL Restriction Expected

3.2 Issue AUP featuring a RSA activation for which there is no NOTAM

EETSA15B Get the Warning “There is no NOTAM closure corresponding to the AUP/UUP closure

Page 16: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.2 NOTAM warning –LARA view

Conclusion :

As expected, client application Get the Warning “There is no NOTAM closure corresponding to the AUP/UUP closure.

Page 17: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.2 NOTAM warning –CIAM Results view

Page 18: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 3.3Content FL

and WEF-TILRestriction Expected

3.3 Issue UUP and include a RSA less than 3 hours in advance

EETSA15B (FL095-UNL; 0800-1100)

Get the warning RSA allocation(RSA ID) is less than 3 hours after planned UUP publication

Page 19: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.3 Issue UUP and include a RSA less than 3 hours in advance

Conclusion:

Get the appropriate warning message route closure less than 3 hours after planned UUP publication.

Page 20: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 3.4Objective Content FL

and WEF-TILRestriction Expected

3.4 Overlaps in time only

EETSA7

EETSA7

(FL095-UNL; 0800-1100)

(FL095-UNL; 0900-1200)

The Client application is able to display RSA allocation error due to the overlap or NM is able to receive unambiguous information.

Page 21: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.4: Overlaps in time – LARA view with de-confliction OFF

Conclusion: 2 missions in client application with de-confliction option OFF results in an ERROR message, as per NM requirement.NOTE: LARA v3.0 client application has a de-confliction function that can be enabled/disabled as per local requirement. The following slides show the results with de-confliction function ON.

Page 22: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.4: overlaps in time – LARA viewwith de-confliction ON

Page 23: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.4: overlaps in time – CIAM results view with de-confliction ON

Conclusion:

Two missions in client application with de-confliction option ON results in one single booking complies with FUA/CADF requirements

Page 24: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 3.5

Objective Content FL and WEF-TIL

Restriction Expected

3.5 Overlaps in Time +FL

EETSA7

EETSA7

(FL095-245; 1430-1530)

(FL195-245; 1430-1730)

The Client application is able to display RSA allocation error due to the overlap or NM is able to receive unambiguous information.

Page 25: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.5 Overlaps in FL- LARA view with de-confliction ON

Page 26: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.5 Overlaps in FL- CIAM results view with de-confliction ON

Conclusion:

Two missions in client application featuring overlaps in FL description results in appropriate non ambiguous 2 bookings that complies with FUA/CADF requirements.

Page 27: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 3.6Objective Content FL

and WEF-TILRestriction Expected

3.6 Overlaps of FBZ with corresponding owner RSA

EETSA7Z

EETSA7

(FL095-225; 1430-1530)

(FL175-225; 1430-1730)

EETSA7ZRA:Y EETSA7ZRB:Y

The Client application is able to display RSA allocation error due to the overlap or NM is able to receive unambiguous information.

Page 28: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.6 Overlaps of FBZ with corresponding owner RSA

Conclusion:

Get the expected RSA allocation error message (Overlaps of FBZ with corresponding owner RSA) or split allocations.

Page 29: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 3.7Objective Content FL

and WEF-TILRestriction Expected

3.7 Overlaps geometry with FBZOverlaps in geometry (same time but overlapping horizontal definition)

EETSA15AZ

EETSA15B

EETSA15CZ

(FL095-500; 0900-1100)

(FL095-305, 0900-1100)

(FL095-305, 0900-1100)

EETSA15AZR:Y EETSA15AZS:N

-EETSA15ZR:Y

EETSA15AZS:N

Get the Warning about geometrically overlapping area.

Page 30: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.7 Overlaps geometry with FBZ

Conclusion:

Get the expected Warning about geometrically overlapping area.

Page 31: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.7 Overlaps geometry with FBZ

Page 32: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 3.8Objective Content FL

and WEF-TILRestriction Expected

3.8 check the outcomes for FUA/EU restrictions overlapping

EBTRANA (FL045 -195)08:00-12:00

EBTRANAR: YEBTRANAS: NEBTRANAT : Y

The Client application is able to display RSA allocation error due to the overlap or NM is able to receive unambiguous information.

EBTRANA (045 -195)

10:00 -13:00

EBTRANAR: N

EBTRANAS: Y

EBTRANAT : N

Page 33: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.8 Overlaps in FL- CIAM results view with de-confliction OFF

Conclusion: 2 missions in client application with de-confliction option OFF results in an ERROR message, as per NM requirement.NOTE: The following slides show the results with de-confliction function ON.

Page 34: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.8 Overlaps in FL- CIAM results view with de-confliction ON

Conclusion:

Two missions in client application with de-confliction option ON results in one single booking complies with FUA/CADF requirements

Page 35: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.8 Overlaps in FL- CIAM results view with de-confliction ON

Page 36: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.8 Overlaps in FL- CIAM results view with de-confliction ONReady status

Analysis:

LARAv3.0 workflow is the following:

1. Reservation of the airspace

2. Generation of the AUP: at this step the de-confliction is applied: it results in a single booking in this case.

3. Then the operator selects the restriction he wants to apply. As there is only one airspace reservation, it forbids the overlapping in restriction.

1.

2.

3.

The operator clicks on FUA/EU to select the restriction among the one available: in this particular case• EBTRANAR• EBTRANAS• EBTRANAT

Page 37: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

3.8 Overlaps in FL- CIAM results view with de-confliction ON

Conclusion:

• the de-confliction is applied on the airspace reservation before any restriction is applied to it.

• As the result, LARA v3.0 cannot produces any overlaps in the applied restrictions, as they are applied on the “de-conflicted” reserved airspace(s).

• 2 missions in client application with de-confliction option ON results in one single booking complies with FUA/CADF requirements.

Page 38: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

AUP/UUP-Scenario4: Synchronization with NM and take over capabilities in case of service unavailability.

Page 39: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 4.1 Synchronization with NM before release of AUP

Page 40: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 4.1 Synchronization with NM before release of AUP

1st Aup produced by NM

Page 41: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 4.1 Synchronization with NM before release of AUP

1st Aup produced by NM

Page 42: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 4.1 Synchronization with NM before release of AUP

Client application is (re)started and synchronises with NM data.

It gets a notification there is different AUP known by NM

Page 43: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 4.1 Synchronization with NM before release of AUP

Client application promotes the updated AUP.

Page 44: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 4.1 Synchronization with NM before release of AUP

Conclusion: LARA v3.0 is able to synchronise, take over and produce an AUP let by NM in draft.

Page 45: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 4.2 Synchronization with NM after release of AUP (corrective UUP).

Page 46: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 4.2 Synchronization with NM after release of AUP (corrective UUP).

Scenario4 part2creation of UUP10 by NM on behalf on the AMC

Page 47: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 4.2 Synchronization with NM after release of AUP (corrective UUP).

The UUP 10 published by NM is retrieved.

It gets a notification there is different AUP known by NM

Page 48: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 4.2 Synchronization with NM after release of AUP (corrective UUP).

AMC takes over and issue a new UUP11

Page 49: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 4.2 Synchronization with NM after release of AUP (corrective UUP) - results in CADF.

AMC takes over and issue a new UUP11.

Page 50: Test Lara v3 Lara v3.pdf · Test Lara v3.0 Access acceptance activities for Lara v3.0 client application 18/07/2016-20/07/2016 04/07/2017

Scenario 4.2 Synchronization with NM after release of AUP (corrective UUP).

Conclusion:

LARA v3.0 is able to synchronise, take over and produce an UUP after AUP has been published by NM.