Terrace House

92
PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG SUMMARY ELEMENT DESCRIPTION UNIT BLOCK A BLOCK B BLOCK C BLOCK D BLOCK E BLOCK F 单位 - - - - - - A CIVIL & STRUCTURAL WORK - - - - - - Piling - - - - - - Building work - - - - - - M2 644 653 653 448 661 690 - - - - - - - - - - - - B ARCHITECTURE WORK - - - - - - - - - - - - 1 ROOF & ROOF FINISHES - - - - - - M2 276 351 351 351 247 224 NO 6 8 8 8 6 6 NO 6 8 8 8 6 6 - - - - - - 2 M2 1,358 1,477 1,477 1,022 1,595 2,030 - - - - - - 3 M2 4,105 4,396 4,396 3,027 4,687 5,753 - - - - - - 4 M2 5,347 5,541 5,541 3,780 5,733 6,618 - - - - - - 5 M2 1,889 1,980 1,980 1,355 2,070 2,302 - - - - - - 6 M2 771 777 777 521 781 804 - - - - - - 7 NO 98 104 104 74 110 118 - - - - - - 8 NO 54 56 56 38 58 66 - - - - - - 9 NO 54 56 56 38 58 66 - - - - - - 10 M2 390 437 437 307 483 665 - - - - - - 11 MS RAILING - - - - - - M 36 60 60 60 48 72 BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES) 排屋 Waterproofing (防水) Roof Covering (屋顶覆盖) Aluminium Sun Shade (Master Bedroom) (遮阳帘) Glass Cover (玻璃盖) BRICKWALL (砖墙) PLASTERING (抹灰) PAINTING (油漆) TILING (瓷砖) PLASTER CEILING (天花板) ALUMINIUM WINDOWS & DOORS (玻璃窗和门 ) TIMBER DOOR (木门) IRONMONGERY (门锁) TIMBER FLOORING (木地板) Staircase railing (楼梯栏杆)

description

Terrace House Workdone

Transcript of Terrace House

Page 1: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

SUMMARY

ELEMENT DESCRIPTION UNIT BLOCK A BLOCK B BLOCK C BLOCK D BLOCK E BLOCK F 单位

- - - - - - A CIVIL & STRUCTURAL WORK - - - - - -

Piling - - - - - - Building work - - - - - -

M2 644 653 653 448 661 690 - - - - - - - - - - - -

B ARCHITECTURE WORK - - - - - - - - - - - -

1 ROOF & ROOF FINISHES - - - - - - M2 276 351 351 351 247 224 NO 6 8 8 8 6 6 NO 6 8 8 8 6 6

- - - - - - 2 M2 1,358 1,477 1,477 1,022 1,595 2,030

- - - - - - 3 M2 4,105 4,396 4,396 3,027 4,687 5,753

- - - - - - 4 M2 5,347 5,541 5,541 3,780 5,733 6,618

- - - - - - 5 M2 1,889 1,980 1,980 1,355 2,070 2,302

- - - - - - 6 M2 771 777 777 521 781 804

- - - - - - 7 NO 98 104 104 74 110 118

- - - - - - 8 NO 54 56 56 38 58 66

- - - - - - 9 NO 54 56 56 38 58 66

- - - - - - 10 M2 390 437 437 307 483 665

- - - - - - 11 MS RAILING - - - - - -

M 36 60 60 60 48 72

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES) 排屋

Waterproofing (防水)

Roof Covering (屋顶覆盖)Aluminium Sun Shade (Master Bedroom) (遮阳帘)Glass Cover (玻璃盖)

BRICKWALL (砖墙)

PLASTERING (抹灰)

PAINTING (油漆)

TILING (瓷砖)

PLASTER CEILING (天花板)

ALUMINIUM WINDOWS & DOORS (玻璃窗和门 )

TIMBER DOOR (木门)

IRONMONGERY (门锁)

TIMBER FLOORING (木地板)

Staircase railing (楼梯栏杆)

Page 2: Terrace House

M 51 81 81 81 64 90 - - - - - -

12 NO 96 110 110 78 124 180 - - - - - - - - - - - -

C - - - - - - - - - - - -

D - - - - - - - - - - - -

E EXTERNAL WORK - - - - - - Access Slab M2 74 75 75 51 74 74 Access Ramp - - - - - - Fencing & Gate M 166 166 166 128 166 166

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Balcony railing (阳台的栏杆)

SANITARY INSTALLATIONS (卫生级管件)

ELECTRICAL WORK (电气工作)

MECHANICAL WORK (水暖工作)

Page 3: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

SUMMARY

ELEMENT DESCRIPTION UNIT

单位

A CIVIL & STRUCTURAL WORKPilingBuilding work

M2

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES M2NONO

2 M2

3 M2

4 M2

5 M2

6 M2

7 NO

8 NO

9 NO

10 M2

11 MS RAILINGM

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES) 排屋

Waterproofing (防水)

Roof Covering (屋顶覆盖)Aluminium Sun Shade (Master Bedroom) (遮阳帘)Glass Cover (玻璃盖)

BRICKWALL (砖墙)

PLASTERING (抹灰)

PAINTING (油漆)

TILING (瓷砖)

PLASTER CEILING (天花板)

ALUMINIUM WINDOWS & DOORS (玻璃窗和门 )

TIMBER DOOR (木门)

IRONMONGERY (门锁)

TIMBER FLOORING (木地板)

Staircase railing (楼梯栏杆)

BLOCK G BLOCK H BLOCK I BLOCK J BLOCK K

- - - - - - - - - - - - - - - - - - - - 800 448 550 448 448 - - - - - - - - - - - - - - - - - - - - - - - - - 224 179 179 179 179 6 4 4 4 4 6 4 4 4 4 - - - - - 2,366 1,022 1,250 1,022 1,022 - - - - - 6,704 3,027 3,711 3,027 3,027 - - - - - 7,719 3,780 4,661 3,780 3,780 - - - - - 2,673 1,355 1,668 1,355 1,355 - - - - - 938 521 649 521 521 - - - - - 135 74 89 74 74 - - - - - 77 38 47 38 38 - - - - - 77 38 47 38 38 - - - - - 776 307 372 307 307 - - - - - - - - - - 72 36 36 36 36

Page 4: Terrace House

M

12 NO

C

D

E EXTERNAL WORKAccess Slab M2Access RampFencing & Gate M

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Balcony railing (阳台的栏杆)

SANITARY INSTALLATIONS (卫生级管件)

ELECTRICAL WORK (电气工作)

MECHANICAL WORK (水暖工作)

90 47 47 47 47 - - - - - 210 78 94 78 78 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 86 51 63 51 51 - - - - - 185 128 147 128 128 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Page 5: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

SUMMARY

ELEMENT DESCRIPTION UNIT

单位

A CIVIL & STRUCTURAL WORKPilingBuilding work

M2

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES M2NONO

2 M2

3 M2

4 M2

5 M2

6 M2

7 NO

8 NO

9 NO

10 M2

11 MS RAILINGM

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES) 排屋

Waterproofing (防水)

Roof Covering (屋顶覆盖)Aluminium Sun Shade (Master Bedroom) (遮阳帘)Glass Cover (玻璃盖)

BRICKWALL (砖墙)

PLASTERING (抹灰)

PAINTING (油漆)

TILING (瓷砖)

PLASTER CEILING (天花板)

ALUMINIUM WINDOWS & DOORS (玻璃窗和门 )

TIMBER DOOR (木门)

IRONMONGERY (门锁)

TIMBER FLOORING (木地板)

Staircase railing (楼梯栏杆)

BLOCK L

- - - - 661 - - - - - 247 6 6 - 1,595 - 4,687 - 5,733 - 2,070 - 781 - 110 - 58 - 58 - 483 - - 48

Page 6: Terrace House

M

12 NO

C

D

E EXTERNAL WORKAccess Slab M2Access RampFencing & Gate M

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Balcony railing (阳台的栏杆)

SANITARY INSTALLATIONS (卫生级管件)

ELECTRICAL WORK (电气工作)

MECHANICAL WORK (水暖工作)

64 - 124 - - - - - - - 74 - 166 - - - - - - - - -

Page 7: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

SUMMARY

ELEMENT DESCRIPTION UNIT

单位

A CIVIL & STRUCTURAL WORKPilingBuilding work

M2

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES M2NONO

2 M2

3 M2

4 M2

5 M2

6 M2

7 NO

8 NO

9 NO

10 M2

11 MS RAILINGM

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES) 排屋

Waterproofing (防水)

Roof Covering (屋顶覆盖)Aluminium Sun Shade (Master Bedroom) (遮阳帘)Glass Cover (玻璃盖)

BRICKWALL (砖墙)

PLASTERING (抹灰)

PAINTING (油漆)

TILING (瓷砖)

PLASTER CEILING (天花板)

ALUMINIUM WINDOWS & DOORS (玻璃窗和门 )

TIMBER DOOR (木门)

IRONMONGERY (门锁)

TIMBER FLOORING (木地板)

Staircase railing (楼梯栏杆)

BLOCK M BLOCK N BLOCK O BLOCK P BLOCK Q BLOCK R

- - - - - - - - - - - - - - - - - - - - - - - - 470 470 866 448 644 448 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 224 224 247 179 104 179 6 6 6 4 2 4 6 6 6 4 2 4 - - - - - - 1,358 1,358 2,050 1,022 1,358 1,022 - - - - - - 3,851 3,851 6,056 3,027 4,105 3,027 - - - - - - 4,415 4,415 7,494 3,780 5,347 3,780 - - - - - - 1,561 1,561 2,695 1,355 1,889 1,355 - - - - - - 537 537 1,037 521 771 521 - - - - - - 84 84 140 74 98 74 - - - - - - 44 44 76 38 54 38 - - - - - - 44 44 76 38 54 38 - - - - - - 444 444 612 307 390 307 - - - - - - - - - - - - 72 72 48 36 12 36

Page 8: Terrace House

M

12 NO

C

D

E EXTERNAL WORKAccess Slab M2Access RampFencing & Gate M

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Balcony railing (阳台的栏杆)

SANITARY INSTALLATIONS (卫生级管件)

ELECTRICAL WORK (电气工作)

MECHANICAL WORK (水暖工作)

90 90 64 47 17 47 - - - - - - 120 120 156 78 96 78 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 50 50 99 51 74 51 - - - - - - 128 128 204 128 166 128 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Page 9: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

SUMMARY

ELEMENT DESCRIPTION UNIT

单位

A CIVIL & STRUCTURAL WORKPilingBuilding work

M2

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES M2NONO

2 M2

3 M2

4 M2

5 M2

6 M2

7 NO

8 NO

9 NO

10 M2

11 MS RAILINGM

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES) 排屋

Waterproofing (防水)

Roof Covering (屋顶覆盖)Aluminium Sun Shade (Master Bedroom) (遮阳帘)Glass Cover (玻璃盖)

BRICKWALL (砖墙)

PLASTERING (抹灰)

PAINTING (油漆)

TILING (瓷砖)

PLASTER CEILING (天花板)

ALUMINIUM WINDOWS & DOORS (玻璃窗和门 )

TIMBER DOOR (木门)

IRONMONGERY (门锁)

TIMBER FLOORING (木地板)

Staircase railing (楼梯栏杆)

TOTAL COMPLETED REMAINING

BLOCK S 总量 完成的工作 WORK 剩余工作量

- - - - - - - - - - - - 439 10,889 9,516 1,373 - - - - - - - - - - - - - - 104 4,248 3,676.50 572 2 100 85 15 2 100 85 15 - - - - 903 26,307 22,566 3,741 - - - - 2,736 77,200 66,470.00 10,730 - - - - 3,586 94,830 82,253 12,577 - - - - 1,264 33,732 29,263 4,470 - - - - 515 12,801 11,209 1,593 - - - - 68 1,786 1,548 238 - - - - 36 954 828 126 - - - - 36 954 828 126 - - - - 260 8,035 6,841 1,194 - - - - - - - - 12 888 720 168

Page 10: Terrace House

M

12 NO

C

D

E EXTERNAL WORKAccess Slab M2Access RampFencing & Gate M

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Balcony railing (阳台的栏杆)

SANITARY INSTALLATIONS (卫生级管件)

ELECTRICAL WORK (电气工作)

MECHANICAL WORK (水暖工作)

17 1,162 950 212 - - - - 64 2,072 1,754 318 - - - - - - - - - - - - - - - - - - - - 50 1,224 1,075 150 - - - 128 2,850 2,492 358 - - - - - - - - - - - - - - - - - - - - - - - - - - -

Page 11: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 2 4 Building work 2 4 Waterproofing M2 2 4 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES Roof Covering M2 2 4 37.1 Aluminium Sun Shade (Master Bedroom) NO 2 4 1 Glass Cover NO 2 4 1

2 BRICKWALL M2 2 4 342.2

3 PLASTERING M2 2 4 973.9

4 PAINTING M2 2 4 1105.5 Wall 737.2 Ceiling 342.5 Door 25,2Staircase 25.8

5 TILING M2 2 4 409.8 Wall 110.1 Floor 299.7

6 PLASTER CEILING M2 2 4 134.3

7 ALUMINIUM WINDOWS & DOORS NO 2 4 25

8 TIMBER DOOR NO 2 4 11

Page 12: Terrace House

9 IRONMONGERY NO 2 4 11

10 TIMBER FLOORING M2 2 4 111.5

11 MS RAILINGStaircase railing M 2 4 11.8 Balcony railing M 2 4 14.9

12 SANITARY INSTALLATIONS NO 2 4 30

Page 13: Terrace House

C ELECTRICAL 2 4

D MECHANICAL 2 4

E EXTERNAL WORKAccess Slab M2 2 4 12.2 Access RampFencing & Gate M 2 4 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 14: Terrace House

BLOCK A : Lot 1-6

3STOREY 2STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT

(QTY) (QTY)

109.9 116.1 102.6 233 411

37.1 52 43 104 172 1 1 1 2 4 1 1 1 2 4

336.1 223.6 227.5 448 910

951.1 683 684.6 1,366 2,739

1101.6 912.2 880.5 1,825 3,522 708.1 604.4 606.1 342.5 274.9 241.5 25.2 18.2 18.2 25.8 14.7 14.7

370.5 319.1 312.4 639 1,250 81.8 68.9 65.8 288.7 250.2 246.6

133.7 129.5 128 259 512

17 19 15 38 60

11 9 9 18 36

Page 15: Terrace House

11 9 9 18 36

110.5 64.8 64.8 130 260

11.8 6 6 12 24 14.9 8.4 8.4 17 34

30 16 16 32 64

Page 16: Terrace House

- - - -

12.2 12.2 12.2 25 49 - -

18.9 44.7 18.9 90 76 - -

5,258 10,163

7/SUM

Page 17: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2 - STOREY TERRACE HOUSES)

SUMMARY

2 - STOREY ELEMENT DESCRIPTION PAGE NO. corner Int CORNER LOT

(qty)

A WORK BELOW LOWEST FLOOR FINISH LEVEL 7/A/9

B FRAME 7/B/10

C UPPER FLOORS 7/C/6

D ROOF & ROOF FINISHES 7/D/3Roof Covering 52 43 104.00 Aluminium Sun Shade (Master Bedroom) 1 1 2.00

E EXTERNAL WALLS 7/E/3 98.8 71.4 197.60

F INTERNAL WALL & PARTITIONS 7/F/1 124.8 156.1 249.60

G WINDOW & EXTERNAL DOORS 7/G/7Aluminium Window & Door 7 3 14.00 Door 3 3

H INTERNAL WINDOWS & DOORS 7/H/4Aluminium Window & Door - Door 6 6

I STAIRCASE & STAIRCASE FINISHES 7/I/6

J WALL FINISHES 7/J/7Plastering 245 227 Painting 245 229 Wall tiles

K FLOOR FINISHES 7/K/6 302.9

Page 18: Terrace House

L CEILING FINISHES 7/L/6

M PLUMBING & SANITARY INSTALLATIONS * 7/M/5 5 5 10.00

N BUILDER'S WORKS & SUNDRIES 7/N/1

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY) 577.20

7/SUM

Page 19: Terrace House

BLOCK A : Lot 1-6

2 - STOREY INTERMEDIATE LOT

(RM/CTS)

172.00 4.00

285.60

624.40

12.00

-

Page 20: Terrace House

20.00

1,118.00

7/SUM

Page 21: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 1 1 4 Building work 1 1 4 Waterproofing M2 1 1 4 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 1 1 4 342.2

3 PLASTERING M2 1 1 4 973.9

4 PAINTING M2 1 1 4 1105.5

5 TILING M2 1 1 4 409.8 Wall 110.1 Floor 299.7

6 PLASTER CEILING M2 1 1 4 134.3

7 ALUMINIUM WINDOWS & DOORS NO 1 1 4 25

8 TIMBER DOOR NO 1 1 4 11

9 IRONMONGERY NO 1 1 4 11

10 TIMBER FLOORING M2 1 1 4 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 1 1 4 30

Page 22: Terrace House

C ELECTRICAL 1 1 4

D MECHANICAL 1 1 4

E EXTERNAL WORKAccess Slab M2 1 1 4 12.2 Access RampFencing & Gate M 1 1 4 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 23: Terrace House

BLOCK B : Lot 7-12

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 125 - 117 411

336.1 223.6 227.5 343 - 224 910

951.1 683 684.6 974 - 683 2,739

1101.6 912.2 880.5 1,106 - 913 3,522

370.5 319.1 312.4 410 - 320 1,250 81.8 68.9 65.8 288.7 250.2 246.6

133.7 129.5 128 135 - 130 512

17 19 15 25 - 19 60

11 9 9 11 - 9 36

11 9 9 11 - 9 36

110.5 64.8 64.8 112 - 65 260

30 16 16 30 - 16 64

Page 24: Terrace House

12.2 12.2 12.2 13 - 13 49

18.9 44.7 18.9 45 - 45 76

3,473 - 2,700 10,163

7/SUM

Page 25: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 1 1 4 Building work 1 1 4 Waterproofing M2 1 1 4 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 1 1 4 342.2

3 PLASTERING M2 1 1 4 973.9

4 PAINTING M2 1 1 4 1105.5

5 TILING M2 1 1 4 409.8

6 PLASTER CEILING M2 1 1 4 134.3

7 ALUMINIUM WINDOWS & DOORS NO 1 1 4 25

8 TIMBER DOOR NO 1 1 4 11

9 IRONMONGERY NO 1 1 4 11

10 TIMBER FLOORING M2 1 1 4 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 1 1 4 30

Page 26: Terrace House

C ELECTRICAL 1 1 4

D MECHANICAL 1 1 4

E EXTERNAL WORKAccess Slab M2 1 1 4 12.2 Access RampFencing & Gate M 1 1 4 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 27: Terrace House

BLOCK C : Lot 13-18

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 125 - 117 411

336.1 223.6 227.5 343 - 224 910

951.1 683 684.6 974 - 683 2,739

1101.6 912.2 880.5 1,106 - 913 3,522

370.5 319.1 312.4 410 - 320 1,250

133.7 129.5 128 135 - 130 512

17 19 15 25 - 19 60

11 9 9 11 - 9 36

11 9 9 11 - 9 36

110.5 64.8 64.8 112 - 65 260

30 16 16 30 - 16 64

Page 28: Terrace House

12.2 12.2 12.2 13 - 13 49

18.9 44.7 18.9 45 - 45 76

3,473 - 2,700 10,163

7/SUM

Page 29: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 1 1 2 Building work 1 1 2 Waterproofing M2 1 1 2 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 1 1 2 342.2

3 PLASTERING M2 1 1 2 973.9

4 PAINTING M2 1 1 2 1105.5

5 TILING M2 1 1 2 409.8

6 PLASTER CEILING M2 1 1 2 134.3

7 ALUMINIUM WINDOWS & DOORS NO 1 1 2 25

8 TIMBER DOOR NO 1 1 2 11

9 IRONMONGERY NO 1 1 2 11

10 TIMBER FLOORING M2 1 1 2 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 1 1 2 30

Page 30: Terrace House

C ELECTRICAL 1 1 2

D MECHANICAL 1 1 2

E EXTERNAL WORKAccess Slab M2 1 1 2 12.2 Access RampFencing & Gate M 1 1 2 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 31: Terrace House

BLOCK D : Lot 19-22

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 125 - 117 206

336.1 223.6 227.5 343 - 224 455

951.1 683 684.6 974 - 683 1,370

1101.6 912.2 880.5 1,106 - 913 1,761

370.5 319.1 312.4 410 - 320 625

133.7 129.5 128 135 - 130 256

17 19 15 25 - 19 30

11 9 9 11 - 9 18

11 9 9 11 - 9 18

110.5 64.8 64.8 112 - 65 130

30 16 16 30 - 16 32

Page 32: Terrace House

12.2 12.2 12.2 13 - 13 25

18.9 44.7 18.9 45 - 45 38

3,473 - 2,700 5,202

7/SUM

Page 33: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 2 4 Building work 2 4 Waterproofing M2 2 4 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 2 4 342.2

3 PLASTERING M2 2 4 973.9

4 PAINTING M2 2 4 1105.5

5 TILING M2 2 4 409.8

6 PLASTER CEILING M2 2 4 134.3

7 ALUMINIUM WINDOWS & DOORS NO 2 4 25

8 TIMBER DOOR NO 2 4 11

9 IRONMONGERY NO 2 4 11

10 TIMBER FLOORING M2 2 4 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 2 4 30

Page 34: Terrace House

C ELECTRICAL 2 4

D MECHANICAL 2 4

E EXTERNAL WORKAccess Slab M2 2 4 12.2 Access RampFencing & Gate M 2 4 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 35: Terrace House

BLOCK E : Lot 23-28

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 250 - - 411

336.1 223.6 227.5 685 - - 910

951.1 683 684.6 1,948 - - 2,739

1101.6 912.2 880.5 2,211 - - 3,522

370.5 319.1 312.4 820 - - 1,250

133.7 129.5 128 269 - - 512

17 19 15 50 - - 60

11 9 9 22 - - 36

11 9 9 22 - - 36

110.5 64.8 64.8 223 - - 260

30 16 16 60 - - 64

Page 36: Terrace House

12.2 12.2 12.2 25 - - 49

18.9 44.7 18.9 90 - - 76

6,808 - - 10,163

7/SUM

Page 37: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 2 4 Building work 2 4 Waterproofing M2 2 4 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 2 4 342.2

3 PLASTERING M2 2 4 973.9

4 PAINTING M2 2 4 1105.5

5 TILING M2 2 4 409.8

6 PLASTER CEILING M2 2 4 134.3

7 ALUMINIUM WINDOWS & DOORS NO 2 4 25

8 TIMBER DOOR NO 2 4 11

9 IRONMONGERY NO 2 4 11

10 TIMBER FLOORING M2 2 4 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 2 4 30

Page 38: Terrace House

C ELECTRICAL 2 4

D MECHANICAL 2 4

E EXTERNAL WORKAccess Slab M2 2 4 12.2 Access RampFencing & Gate M 2 4 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 39: Terrace House

BLOCK F : Lot 29-33a

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 250 440 - -

336.1 223.6 227.5 685 1,345 - -

951.1 683 684.6 1,948 3,805 - -

1101.6 912.2 880.5 2,211 4,407 - -

370.5 319.1 312.4 820 1,482 - -

133.7 129.5 128 269 535 - -

17 19 15 50 68 - -

11 9 9 22 44 - -

11 9 9 22 44 - -

110.5 64.8 64.8 223 442 - -

30 16 16 60 120 - -

Page 40: Terrace House

12.2 12.2 12.2 25 49 - -

18.9 44.7 18.9 90 76 - -

6,808 13,122 - -

7/SUM

Page 41: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 2 5 Building work 2 5 Waterproofing M2 2 5 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 2 5 342.2

3 PLASTERING M2 2 5 973.9

4 PAINTING M2 2 5 1105.5

5 TILING M2 2 5 409.8

6 PLASTER CEILING M2 2 5 134.3

7 ALUMINIUM WINDOWS & DOORS NO 2 5 25

8 TIMBER DOOR NO 2 5 11

9 IRONMONGERY NO 2 5 11

10 TIMBER FLOORING M2 2 5 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 2 5 30

Page 42: Terrace House

C ELECTRICAL 2 5

D MECHANICAL 2 5

E EXTERNAL WORKAccess Slab M2 2 5 12.2 Access RampFencing & Gate M 2 5 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 43: Terrace House

BLOCK G : Lot 35-41

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 250 550 - -

336.1 223.6 227.5 685 1,681 - -

951.1 683 684.6 1,948 4,756 - -

1101.6 912.2 880.5 2,211 5,508 - -

370.5 319.1 312.4 820 1,853 - -

133.7 129.5 128 269 669 - -

17 19 15 50 85 - -

11 9 9 22 55 - -

11 9 9 22 55 - -

110.5 64.8 64.8 223 553 - -

30 16 16 60 150 - -

Page 44: Terrace House

12.2 12.2 12.2 25 61 - -

18.9 44.7 18.9 90 95 - -

6,808 16,336 - -

7/SUM

Page 45: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 1 1 2 Building work 1 1 2 Waterproofing M2 1 1 2 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 1 1 2 342.2

3 PLASTERING M2 1 1 2 973.9

4 PAINTING M2 1 1 2 1105.5

5 TILING M2 1 1 2 409.8

6 PLASTER CEILING M2 1 1 2 134.3

7 ALUMINIUM WINDOWS & DOORS NO 1 1 2 25

8 TIMBER DOOR NO 1 1 2 11

9 IRONMONGERY NO 1 1 2 11

10 TIMBER FLOORING M2 1 1 2 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 1 1 2 30

Page 46: Terrace House

C ELECTRICAL 1 1 2

D MECHANICAL 1 1 2

E EXTERNAL WORKAccess Slab M2 1 1 2 12.2 Access RampFencing & Gate M 1 1 2 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 47: Terrace House

BLOCK H : Lot 42-45

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 125 - 117 206

336.1 223.6 227.5 343 - 224 455

951.1 683 684.6 974 - 683 1,370

1101.6 912.2 880.5 1,106 - 913 1,761

370.5 319.1 312.4 410 - 320 625

133.7 129.5 128 135 - 130 256

17 19 15 25 - 19 30

11 9 9 11 - 9 18

11 9 9 11 - 9 18

110.5 64.8 64.8 112 - 65 130

30 16 16 30 - 16 32

Page 48: Terrace House

12.2 12.2 12.2 13 - 13 25

18.9 44.7 18.9 45 - 45 38

3,473 - 2,700 4,964

7/SUM

Page 49: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 1 1 3 Building work 1 1 3 Waterproofing M2 1 1 3 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 1 1 3 342.2

3 PLASTERING M2 1 1 3 973.9

4 PAINTING M2 1 1 3 1105.5

5 TILING M2 1 1 3 409.8

6 PLASTER CEILING M2 1 1 3 134.3

7 ALUMINIUM WINDOWS & DOORS NO 1 1 3 25

8 TIMBER DOOR NO 1 1 3 11

9 IRONMONGERY NO 1 1 3 11

10 TIMBER FLOORING M2 1 1 3 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 1 1 3 30

Page 50: Terrace House

C ELECTRICAL 1 1 3

D MECHANICAL 1 1 3

E EXTERNAL WORKAccess Slab M2 1 1 3 12.2 Access RampFencing & Gate M 1 1 3 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 51: Terrace House

BLOCK I : Lot 46-50

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 125 - 117 308

336.1 223.6 227.5 343 - 224 683

951.1 683 684.6 974 - 683 2,054

1101.6 912.2 880.5 1,106 - 913 2,642

370.5 319.1 312.4 410 - 320 938

133.7 129.5 128 135 - 130 384

17 19 15 25 - 19 45

11 9 9 11 - 9 27

11 9 9 11 - 9 27

110.5 64.8 64.8 112 - 65 195

30 16 16 30 - 16 48

Page 52: Terrace House

12.2 12.2 12.2 13 - 13 37

18.9 44.7 18.9 45 - 45 57

3,473 - 2,700 7,445

7/SUM

Page 53: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 1 1 2 Building work 1 1 2 Waterproofing M2 1 1 2 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 1 1 2 342.2

3 PLASTERING M2 1 1 2 973.9

4 PAINTING M2 1 1 2 1105.5

5 TILING M2 1 1 2 409.8

6 PLASTER CEILING M2 1 1 2 134.3

7 ALUMINIUM WINDOWS & DOORS NO 1 1 2 25

8 TIMBER DOOR NO 1 1 2 11

9 IRONMONGERY NO 1 1 2 11

10 TIMBER FLOORING M2 1 1 2 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 1 1 2 30

Page 54: Terrace House

C ELECTRICAL 1 1 2

D MECHANICAL 1 1 2

E EXTERNAL WORKAccess Slab M2 1 1 2 12.2 Access RampFencing & Gate M 1 1 2 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 55: Terrace House

BLOCK J : Lot 51-53a

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 125 - 117 206

336.1 223.6 227.5 343 - 224 455

951.1 683 684.6 974 - 683 1,370

1101.6 912.2 880.5 1,106 - 913 1,761

370.5 319.1 312.4 410 - 320 625

133.7 129.5 128 135 - 130 256

17 19 15 25 - 19 30

11 9 9 11 - 9 18

11 9 9 11 - 9 18

110.5 64.8 64.8 112 - 65 130

30 16 16 30 - 16 32

Page 56: Terrace House

12.2 12.2 12.2 13 - 13 25

18.9 44.7 18.9 45 - 45 38

3,473 - 2,700 4,964

7/SUM

Page 57: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 1 1 2 Building work 1 1 2 Waterproofing M2 1 1 2 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 1 1 2 342.2

3 PLASTERING M2 1 1 2 973.9

4 PAINTING M2 1 1 2 1105.5

5 TILING M2 1 1 2 409.8

6 PLASTER CEILING M2 1 1 2 134.3

7 ALUMINIUM WINDOWS & DOORS NO 1 1 2 25

8 TIMBER DOOR NO 1 1 2 11

9 IRONMONGERY NO 1 1 2 11

10 TIMBER FLOORING M2 1 1 2 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 1 1 2 30

Page 58: Terrace House

C ELECTRICAL 1 1 2

D MECHANICAL 1 1 2

E EXTERNAL WORKAccess Slab M2 1 1 2 12.2 Access RampFencing & Gate M 1 1 2 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 59: Terrace House

BLOCK K : Lot 55-57a

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 125 - 117 206

336.1 223.6 227.5 343 - 224 455

951.1 683 684.6 974 - 683 1,370

1101.6 912.2 880.5 1,106 - 913 1,761

370.5 319.1 312.4 410 - 320 625

133.7 129.5 128 135 - 130 256

17 19 15 25 - 19 30

11 9 9 11 - 9 18

11 9 9 11 - 9 18

110.5 64.8 64.8 112 - 65 130

30 16 16 30 - 16 32

Page 60: Terrace House

12.2 12.2 12.2 13 - 13 25

18.9 44.7 18.9 45 - 45 38

3,473 - 2,700 4,964

7/SUM

Page 61: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 2 4 Building work 2 4 Waterproofing M2 2 4 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 2 4 342.2

3 PLASTERING M2 2 4 973.9

4 PAINTING M2 2 4 1105.5

5 TILING M2 2 4 409.8

6 PLASTER CEILING M2 2 4 134.3

7 ALUMINIUM WINDOWS & DOORS NO 2 4 25

8 TIMBER DOOR NO 2 4 11

9 IRONMONGERY NO 2 4 11

10 TIMBER FLOORING M2 2 4 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 2 4 30

Page 62: Terrace House

C ELECTRICAL 2 4

D MECHANICAL 2 4

E EXTERNAL WORKAccess Slab M2 2 4 12.2 Access RampFencing & Gate M 2 4 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 63: Terrace House

BLOCK L : Lot 59-63a

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 250 - - 411

336.1 223.6 227.5 685 - - 910

951.1 683 684.6 1,948 - - 2,739

1101.6 912.2 880.5 2,211 - - 3,522

370.5 319.1 312.4 820 - - 1,250

133.7 129.5 128 269 - - 512

17 19 15 50 - - 60

11 9 9 22 - - 36

11 9 9 22 - - 36

110.5 64.8 64.8 223 - - 260

30 16 16 60 - - 64

Page 64: Terrace House

12.2 12.2 12.2 25 - - 49

18.9 44.7 18.9 90 - - 76

6,808 - - 10,163

7/SUM

Page 65: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 2 2 Building work 2 2 Waterproofing M2 2 2 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 2 2 342.2

3 PLASTERING M2 2 2 973.9

4 PAINTING M2 2 2 1105.5

5 TILING M2 2 2 409.8

6 PLASTER CEILING M2 2 2 134.3

7 ALUMINIUM WINDOWS & DOORS NO 2 2 25

8 TIMBER DOOR NO 2 2 11

9 IRONMONGERY NO 2 2 11

10 TIMBER FLOORING M2 2 2 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 2 2 30

Page 66: Terrace House

C ELECTRICAL 2 2

D MECHANICAL 2 2

E EXTERNAL WORKAccess Slab M2 2 2 12.2 Access RampFencing & Gate M 2 2 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 67: Terrace House

BLOCK M : Lot 65-68

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 250 220 - -

336.1 223.6 227.5 685 673 - -

951.1 683 684.6 1,948 1,903 - -

1101.6 912.2 880.5 2,211 2,204 - -

370.5 319.1 312.4 820 741 - -

133.7 129.5 128 269 268 - -

17 19 15 50 34 - -

11 9 9 22 22 - -

11 9 9 22 22 - -

110.5 64.8 64.8 223 221 - -

30 16 16 60 60 - -

Page 68: Terrace House

12.2 12.2 12.2 25 25 - -

18.9 44.7 18.9 90 38 - -

6,808 6,696 - -

7/SUM

Page 69: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 2 2 Building work 2 2 Waterproofing M2 2 2 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 2 2 342.2

3 PLASTERING M2 2 2 973.9

4 PAINTING M2 2 2 1105.5

5 TILING M2 2 2 409.8

6 PLASTER CEILING M2 2 2 134.3

7 ALUMINIUM WINDOWS & DOORS NO 2 2 25

8 TIMBER DOOR NO 2 2 11

9 IRONMONGERY NO 2 2 11

10 TIMBER FLOORING M2 2 2 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 2 2 30

Page 70: Terrace House

C ELECTRICAL 2 2

D MECHANICAL 2 2

E EXTERNAL WORKAccess Slab M2 2 2 12.2 Access RampFencing & Gate M 2 2 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 71: Terrace House

BLOCK N : Lot 69-72

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 250 220 - -

336.1 223.6 227.5 685 673 - -

951.1 683 684.6 1,948 1,903 - -

1101.6 912.2 880.5 2,211 2,204 - -

370.5 319.1 312.4 820 741 - -

133.7 129.5 128 269 268 - -

17 19 15 50 34 - -

11 9 9 22 22 - -

11 9 9 22 22 - -

110.5 64.8 64.8 223 221 - -

30 16 16 60 60 - -

Page 72: Terrace House

12.2 12.2 12.2 25 25 - -

18.9 44.7 18.9 90 38 - -

6,808 6,696 - -

7/SUM

Page 73: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 2 6 Building work 2 6 Waterproofing M2 2 6 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 2 6 342.2

3 PLASTERING M2 2 6 973.9

4 PAINTING M2 2 6 1105.5

5 TILING M2 2 6 409.8

6 PLASTER CEILING M2 2 6 134.3

7 ALUMINIUM WINDOWS & DOORS NO 2 6 25

8 TIMBER DOOR NO 2 6 11

9 IRONMONGERY NO 2 6 11

10 TIMBER FLOORING M2 2 6 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 2 6 30

Page 74: Terrace House

C ELECTRICAL 2 6

D MECHANICAL 2 6

E EXTERNAL WORKAccess Slab M2 2 6 12.2 Access RampFencing & Gate M 2 6 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 75: Terrace House

BLOCK O : Lot 73 - 80

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 250 - - 616

336.1 223.6 227.5 685 - - 1,365

951.1 683 684.6 1,948 - - 4,108

1101.6 912.2 880.5 2,211 - - 5,283

370.5 319.1 312.4 820 - - 1,875

133.7 129.5 128 269 - - 768

17 19 15 50 - - 90

11 9 9 22 - - 54

11 9 9 22 - - 54

110.5 64.8 64.8 223 - - 389

30 16 16 60 - - 96

Page 76: Terrace House

12.2 12.2 12.2 25 - - 74

18.9 44.7 18.9 90 - - 114

6,808 - - 15,124

7/SUM

Page 77: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 1 1 2 Building work 1 1 2 Waterproofing M2 1 1 2 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 1 1 2 342.2

3 PLASTERING M2 1 1 2 973.9

4 PAINTING M2 1 1 2 1105.5

5 TILING M2 1 1 2 409.8

6 PLASTER CEILING M2 1 1 2 134.3

7 ALUMINIUM WINDOWS & DOORS NO 1 1 2 25

8 TIMBER DOOR NO 1 1 2 11

9 IRONMONGERY NO 1 1 2 11

10 TIMBER FLOORING M2 1 1 2 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 1 1 2 30

Page 78: Terrace House

C ELECTRICAL 1 1 2

D MECHANICAL 1 1 2

E EXTERNAL WORKAccess Slab M2 1 1 2 12.2 Access RampFencing & Gate M 1 1 2 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 79: Terrace House

BLOCK P : Lot 81-83a

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 125 - 117 206

336.1 223.6 227.5 343 - 224 455

951.1 683 684.6 974 - 683 1,370

1101.6 912.2 880.5 1,106 - 913 1,761

370.5 319.1 312.4 410 - 320 625

133.7 129.5 128 135 - 130 256

17 19 15 25 - 19 30

11 9 9 11 - 9 18

11 9 9 11 - 9 18

110.5 64.8 64.8 112 - 65 130

30 16 16 30 - 16 32

Page 80: Terrace House

12.2 12.2 12.2 13 - 13 25

18.9 44.7 18.9 45 - 45 38

3,473 - 2,700 4,964

7/SUM

Page 81: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 2 4 Building work 2 4 Waterproofing M2 2 4 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 2 4 342.2

3 PLASTERING M2 2 4 973.9

4 PAINTING M2 2 4 1105.5

5 TILING M2 2 4 409.8

6 PLASTER CEILING M2 2 4 134.3

7 ALUMINIUM WINDOWS & DOORS NO 2 4 25

8 TIMBER DOOR NO 2 4 11

9 IRONMONGERY NO 2 4 11

10 TIMBER FLOORING M2 2 4 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 2 4 30

Page 82: Terrace House

C ELECTRICAL 2 4

D MECHANICAL 2 4

E EXTERNAL WORKAccess Slab M2 2 4 12.2 Access RampFencing & Gate M 2 4 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 83: Terrace House

BLOCK Q : Lot 85-90

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 - - 233 411

336.1 223.6 227.5 - - 448 910

951.1 683 684.6 - - 1,366 2,739

1101.6 912.2 880.5 - - 1,825 3,522

370.5 319.1 312.4 - - 639 1,250

133.7 129.5 128 - - 259 512

17 19 15 - - 38 60

11 9 9 - - 18 36

11 9 9 - - 18 36

110.5 64.8 64.8 - - 130 260

30 16 16 - - 32 64

Page 84: Terrace House

12.2 12.2 12.2 - - 25 49

18.9 44.7 18.9 - - 90 76

- - 5,258 9,925

7/SUM

Page 85: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2&3 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 1 1 2 Building work 1 1 2 Waterproofing M2 1 1 2 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 1 1 2 342.2

3 PLASTERING M2 1 1 2 973.9

4 PAINTING M2 1 1 2 1105.5

5 TILING M2 1 1 2 409.8

6 PLASTER CEILING M2 1 1 2 134.3

7 ALUMINIUM WINDOWS & DOORS NO 1 1 2 25

8 TIMBER DOOR NO 1 1 2 11

9 IRONMONGERY NO 1 1 2 11

10 TIMBER FLOORING M2 1 1 2 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 1 1 2 30

Page 86: Terrace House

C ELECTRICAL 1 1 2

D MECHANICAL 1 1 2

E EXTERNAL WORKAccess Slab M2 1 1 2 12.2 Access RampFencing & Gate M 1 1 2 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 87: Terrace House

BLOCK R : Lot 91-93a

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 125 - 117 206

336.1 223.6 227.5 343 - 224 455

951.1 683 684.6 974 - 683 1,370

1101.6 912.2 880.5 1,106 - 913 1,761

370.5 319.1 312.4 410 - 320 625

133.7 129.5 128 135 - 130 256

17 19 15 25 - 19 30

11 9 9 11 - 9 18

11 9 9 11 - 9 18

110.5 64.8 64.8 112 - 65 130

30 16 16 30 - 16 32

Page 88: Terrace House

12.2 12.2 12.2 13 - 13 25

18.9 44.7 18.9 45 - 45 38

3,473 - 2,700 4,964

7/SUM

Page 89: Terrace House

PROJECT : PROPOSED HOUSING DEVELOPMENT, ON N.T. 213 182 444, N.T. 213 090 245, N.T. 213 090 236, N.T. 213 090 227, N.T. 213 090 254, N.T. 213 090 272, N.T. 213 082 298, N.T. 213 088 512 & N.T. 213 086 376 AT KG. KIBABAIG, DISTRICT OF PENAMPANG

BILL NO. 7 - BUILDING WORKS (2 - STOREY TERRACE HOUSES)

SUMMARY

3STOREYELEMENT DESCRIPTION UNIT 3 STOREY 3STOREY 2 STOREY 2 STOREY corner

(CORNER) (INT) (CORNER) (INT)

A CIVIL & STRUCTURAL WORKPiling 2 2 Building work 2 2 Waterproofing M2 2 2 124.8

B ARCHITECTURE WORK

1 ROOF & ROOF FINISHES

2 BRICKWALL M2 2 2 342.2

3 PLASTERING M2 2 2 973.9

4 PAINTING M2 2 2 1105.5

5 TILING M2 2 2 409.8

6 PLASTER CEILING M2 2 2 134.3

7 ALUMINIUM WINDOWS & DOORS NO 2 2 25

8 TIMBER DOOR NO 2 2 11

9 IRONMONGERY NO 2 2 11

10 TIMBER FLOORING M2 2 2 111.5

11 MS RAILING

12 SANITARY INSTALLATIONS NO 2 2 30

Page 90: Terrace House

C ELECTRICAL 2 2

D MECHANICAL 2 2

E EXTERNAL WORKAccess Slab M2 2 2 12.2 Access RampFencing & Gate M 2 2 44.7

TOTAL FOR 1 UNIT CORNER LOT & 1 UNIT INTERMEDIATE LOT (CARRIED TO FINAL SUMMARY)

7/SUM

Page 91: Terrace House

BLOCK S : Lot 95 - 98

3STOREY 2STOREY 3 - STOREY 2 - STOREY Int corner Int CORNER LOT INTERMEDIATE LOT CORNER LOT INTERMEDIATE LOT

(QTY) (QTY) (QTY) (QTY)

109.9 116.1 102.6 - - 233 206

336.1 223.6 227.5 - - 448 455

951.1 683 684.6 - - 1,366 1,370

1101.6 912.2 880.5 - - 1,825 1,761

370.5 319.1 312.4 - - 639 625

133.7 129.5 128 - - 259 256

17 19 15 - - 38 30

11 9 9 - - 18 18

11 9 9 - - 18 18

110.5 64.8 64.8 - - 130 130

30 16 16 - - 32 32

Page 92: Terrace House

12.2 12.2 12.2 - - 25 25

18.9 44.7 18.9 - - 90 38

- - 5,258 4,964

7/SUM