Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of...

38
Tender No. 07/Bridges/2013 Signature of Contractor(s) Page 1 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013, date of opening on 09.10.2013 for the work of Provision of Standard Height gauges of Road under bridges in ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.” 1 Registered Post-Ack.-Due” भारत सरकार / Govt. of India रेऱ मंाऱय / Ministry of Railways दिण मय रेऱवे / South Central Railway वजयवाडा मंडऱ / Vijayawada Division मंडऱ कायााऱय/Divisional Office, कायशाखा/Works Branch, वजयवाडा/Vijayawada, सं .No.बीB/डबयू W.496/I/4/T.No.07/Bridges/13/T.Bridges दनाँक/Dt.20.12.2013 To M/s Y.Chinna Reddy, Railway Contractors, D.No.27/1083, 3 rd Line, Ramnagar, N E L L O R E 524 002 Sirs, वषय/Sub:- Tender No.07/Bridges/2013 for the work of „SW- 1 : Gudur- Vijayawada Section - Provision of Standard Height gauges of Road under bridges in ADEN/Br/S/BZA Section. SW-2: Vijayawada- Visakhapatnam, Nidadavole-Bhimvaram Sections: Provision of Standard Height gauges at Road under bridges‟. संदबा /Ref:- Your tender for the above work submitted on 09.10.2013. *** 1. The competent authority has accepted your Tender for the above work for a total value of Rs.90,69,052/- (Rupees ninety lakhs, sixty nine thousand and fifty two only) at the following rates. Rates : (i) Schedule-A=(+)45% (Plus forty five percent only) on USSR-2010 with restriction for dissimilar nature and situation (ii) Schedule-A1=(+)30.60% (Plus thirty point six zero percent only) on USSR-2010 (iii) Schedule-A2=(+)27% (Plus twenty seven percent only) on USSR-2010 (iv) Schedule-B=(+)36% (Plus thirty six percent only) on basic rates of NS items 2. The work should be completed within 06 (Six) Months from the date of issue of letter of acceptance of tender with a maintenance period of 06 (Six) Months . 3. The sum of Rs.1,32,510/- submitted vide FDR No.124677, dt.08.10.13 issued by Karnataka Bank Ltd., Dilshuknagar Branch, Hyderabad towards E.M.D has been adjusted as part amount of the security deposit. The balance security deposit of Rs.3,20,943/- shall be recovered at the rate of 10% of the bill amount till the full security deposit of Rs.4,53,453/- is recovered.

Transcript of Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of...

Page 1: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 1 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

1

“Registered Post-Ack.-Due”

भारत सरकार / Govt. of India

रेऱ मंत्राऱय / Ministry of Railways

दक्षिण मध्य रेऱवे / South Central Railway

ववजयवाडा मंडऱ / Vijayawada Division

मंडऱ कायााऱय/Divisional Office,

काया शाखा/Works Branch,

ववजयवाडा/Vijayawada,

स.ंNo.बीB/डबल्यू W.496/I/4/T.No.07/Bridges/13/T.Bridges ददनाँक/Dt.20.12.2013

To

M/s Y.Chinna Reddy,

Railway Contractors,

D.No.27/1083, 3rd

Line, Ramnagar,

N E L L O R E – 524 002

Sirs,

ववषय/Sub:- Tender No.07/Bridges/2013 for the work of „SW- 1 : Gudur-

Vijayawada Section - Provision of Standard Height gauges of Road

under bridges in ADEN/Br/S/BZA Section. SW-2: Vijayawada-

Visakhapatnam, Nidadavole-Bhimvaram Sections: Provision of

Standard Height gauges at Road under bridges‟.

संदबा/Ref:- Your tender for the above work submitted on 09.10.2013.

***

1. The competent authority has accepted your Tender for the above work for a total value of

Rs.90,69,052/- (Rupees ninety lakhs, sixty nine thousand and fifty two only) at the following

rates.

Rates:

(i) Schedule-A=(+)45% (Plus forty five percent only) on USSR-2010 with restriction for

dissimilar nature and situation

(ii) Schedule-A1=(+)30.60% (Plus thirty point six zero percent only) on USSR-2010

(iii) Schedule-A2=(+)27% (Plus twenty seven percent only) on USSR-2010

(iv) Schedule-B=(+)36% (Plus thirty six percent only) on basic rates of NS items

2. The work should be completed within 06 (Six) Months from the date of issue of letter of

acceptance of tender with a maintenance period of 06 (Six) Months.

3. The sum of Rs.1,32,510/- submitted vide FDR No.124677, dt.08.10.13 issued by Karnataka

Bank Ltd., Dilshuknagar Branch, Hyderabad towards E.M.D has been adjusted as part

amount of the security deposit. The balance security deposit of Rs.3,20,943/- shall be

recovered at the rate of 10% of the bill amount till the full security deposit of Rs.4,53,453/- is

recovered.

Page 2: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 2 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

2

4. In terms of Special conditions of contract, you shall furnish a Performance Guarantee

amounting to 5% of the contract value i.e., Rs.4,53,453/- before signing of the agreement.

The performance guarantee should be initially valid up to the stipulated date of completion

plus 60 days beyond that. In terms of Special conditions of contract, you shall submit the

Performance Guarantee (PG) within 30 (thirty) days from the date of issue of Letter of

Acceptance (LOA). Extension of time for submission of PG beyond 30 (thirty) days and up

to 60 days from the date of issue of LOA may be given by the Authority who is competent to

sign the contract agreement. However, a penal interest of 15% per annum shall be charged

for the delay beyond 30 (thirty) days, i.e. from 31st day after the date of issue of LOA. In case

of failure to submit the requisite PG even after 60 days from the date of issue of LOA, the

contract shall be terminated duly forfeiting EMD and other dues, if any payable against the

contract. The failed contractor shall be debarred from participating in re-tender for that work.

5. Until a formal agreement is executed, acceptance of the Tender shall constitute a binding

contract between you and the administration.

6. You have to abide by the Contract Labour (Regulations and Abolition Act 1970) and rules,

regulations and amendments thereto that may be followed from time to time are binding on

you in respect of this contract. You have to submit the application in the prescribed form

(Form-V) in triplicate for license under Contract labour (Regulation and Abolition) Act

for 20 or more workers and under BOCW Act for less than 20 Workers together with

the demand draft towards security deposit and license fee to the undersigned to forward the

same to the concerned Licensing Officer for issue of the license irrespective of the number of

labour employed for the work. The work should not be executed without a valid labour

license.

7. Failure to start the work within ten days, the contractor is liable for penal action as per clause

62 of the General conditions of contract.

Encl: 1) Tender schedule with special conditions & 2) Copy of Performance Guarantee.

आपका / Yours faithfully,

म.इंजीननयर/पऱु

Divisional Engineer/Bridges

द.म.रेऱवे/S.C.Railway,

ववजयवाडा/Vijayawada

Copy to: Sr.DFM/BZA for information.

Copy to: ADEN/BR/N/BZA, ADEN/BR/S/BZA, SSE/BR/I&II/RJY, SSE/BR/I&II/BZA,

SSE/BR/BTTR, SSE(Drg)/BR & OS/WA-BR for information.

Copy to: Asst Labour Commissioner (Central), 5th floor, Central Govt. Office Complex, Plot

No.G-2, Industrial Estate, Auto Nagar, Vijayawada-520007 for information.

(TC : DEN/Bridges/BZA, DFM/BZA & DSTE/BZA – AA:Sr.DEN/Co-ord/BZA)

Page 3: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 3 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

3

South Central Railway Vijayawada Division

Tender No.07/Bridges/2013

Name of

Work :

SW- 1 : GDR - BZA Section Provision of Standard Height gauges of Road

under bridges in ADEN/Br/S/BZA Section.

SW2 : BZA -VSKP, NDD-BVRM Sections : Provision of Standard Height

gauges at Road under bridges.

Similar nature of

work :-

Any work of steel fabrication or fabrication and erection of FOB

or PF shelter or Industrial shed or steel/Composite girder bridge or

Microwave/HT tower or Channel Sleepers.

Appx. Value : Rs.66,25,060/-

Estimate Sd No. DEN/Bridges/BZA B/W.71/I/1458/Plg,

Dt.30.04.2013., B/W.287/I/786/Plg, Dt. 3.05.2013. Allocation : : 26-30-55-03, 26-30-55-03

Completion Period (06) SIX months

Maintenance Period (06) SIX months

Name & address of

the Contractor:-

M/s Y.Chinna Reddy,

Railway Contractors,

D.No.27/1083, 3rd

Line, Ramnagar,

N E L L O R E – 524 002 Approximate value of tender arrived by the addition of "at par" value of USSR items enhanced with

certain estimated percentage and value of the NS items at the basic rates adopted in schedule.

SCHEDULE 'A'

List of items of works that are covered by USSR 2010 of S.C. Railway.

Sl.

No.

SSR

Item No.

Description of

work.

SW 1 App. Qty. SW 2

App.

Qty.

Total Rate Unit Amt in

Rs. BTTR BZA

1 011010+

011011

Earth work in excavation as per approved drawings and dumping at embankment

site or spoil heap, within railway land, including 50m lead and 1.5m lift, the lead

to be measured from the centre of gravity of excavation to centre of gravity of

spoil heap: the lift to be measured from natural ground level and paid for in

layers of 1.5m each, including incidental work, as per specifications-in all kinds of

soils

25 50 275 350 100.28 cum 35098

2 031010+

031012

Providing and laying in position cement concrete of specified proportion

excluding cost of cement, centering and shuttering - All works upto Plinth level :

1:3:6 (1 cement : 3 sand : 6 graded stone aggregate 40mm nominal size)

2.5 5.0 33 41 1865.68 cum 75560

3 042010+

042011

Centering and shuttering including strutting, propping etc. and removal of

form for : Foundations, footings, bases of columns, raft foundation of washable

aprons, Pile caps, Footings of FOB etc.

44 88 300 432 132.50 Sqm 57240

Page 4: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 4 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

4

Sl.

No.

SSR

Item No.

Description of

work.

SW 1 App. Qty. SW 2

App.

Qty.

Total Rate Unit Amt in

Rs. BTTR BZA

4 041010+

041011

Providing and laying in position M 20 Grade concrete for reinforced concrete

structural elements but excluding cost of centering, shuttering, reinforcement and

Admixtures in recommended proportion (as per IS:9103) to accelerate, retard

setting of concrete, improve workability without impairing strength and

durability as per direction of Engineer in charge. All work upto plinth level,

including raft foundation of washable aprons, HS tank, pile cap, footings of FOB,

and Platform shelter etc.

18 36 200 254 2326.7 cum 590982

5 211080 Providing/ fixing/ leaving/ grouting various size HTS bolts / holding down

bolts in concrete column or in other structural steel member with proper nuts,

bolts, washers /plates as a complete job. Note - Cement used in grouting will be

paid separately under relevant item

190 380 1980 2,550 70.01 Kg 178526

6 181020+

181021

Demolishing plain cement concrete including disposal of material within 50m

lead. 1:2:4 or richer mix with max. 20 mm coarse aggregate

5 10 10 25 510.54 cum 12764

7 123040+

123043

Painting, Two coat, any shade as directed of approved make and brand a) Trusses

exceeding 9m clear span, b) Staging with O.H. tank where staging is more than

2.5m in height, c) Flood light towers, d) Chimneys and similar structures With

Synthetic Enamel paint

160 320 0 480 48.62 Sqm 23338

8 238040+

238041

Manufacturing supplying and fixing retro reflective sign boards made up of

2mm thick aluminium sheet, face to be fully covered with high intensity

encapsulated type heat activated retro reflective sheeting conforming to type - IV

of ASTM-D 4956-01 in blue and silver white or other colour combination

including subject matter, message (bi-lingual), symbols and borders etc. as per

IRC ; 67:2001, pasted on substrate by an adhesive backing which shall be

activated by applying heat and pressure conforming to class -2 of ASTM-D-4956-

01 and fixing the same with suitable sized aluminium alloy rivets @ 20 cm c/c to

back support frame of M.S. angle iron of size 25x25x3 mm along with theft

resistant measures, mounted and fixed with2 Nos. M.S. angles of size 35x35x5

mm to a vertical post made up of M.S. Tee section ISMT50x50x6 mm.welded

with base plate of size100x100x5 mm at the bottom end and including making

holes in pipes, angles flats, providing & fixing M.S. message plate of required size

steel work to be painted with two or more coats of synthetic enamel paint of

required shade and of approved brand & manufacture over priming coat of zinc

chromate yellow primer (vertical MS-Tee support to be painted in black and

white colours). Backside of aluminium sheet to be painted with two or more coats

of epoxy paint over and including appropriate priming coat including all leads and

lifts etc. complete as per drawing, specification and direction of Engineer- in-

charge. (Note : Concreting for fixing may be done as per site requirement and

paid forseparately) Cautionary/warning sign boards of equilateral triangular shape

having each side of 900mm with support length of 3650mm

4 8 0 12 3244.16 Each 38930

Page 5: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 5 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

5

Sl.

No.

SSR

Item No.

Description of

work.

SW 1 App. Qty. SW 2

App.

Qty.

Total Rate Unit Amt in

Rs. BTTR BZA

9 238050 Providing and applying 2.5mm thick road marking strips (retro-reflective) of

specified shade/ colour using hot thermoplastic material by fully/ semi automatic

thermoplastic paint applicator machine fitted with profile shoe, glass beads

dispenser, propane tank heater and profile shoe heater, driven by experienced

operator on road surface including cost of material, labour, T&P, cleaning the road

surface of all dirt, seals, oil, grease and foreign material etc. complete as per

direction of Engineer-in-charge and in accordance with applicable specifications

2 4 0 6 584.94 Sqm 3510

( Items Nine only) Schedule 'A' TOTAL : 1015946

Percentage rate in figures (+)45% Percentage rate in words Plus forty five percent only on USSR-2010

with restriction for dissimilar nature and situation

SCHEDULE - 'A-1'

List of items of works that are covered by USSR 2010 of S.C. Railway.

SL.

No.

SSR Item

No.

Description of

work.

SW 1 App. Qty. SW 2

App.

Qty.

Total Rate Unit Amoun

t in Rs. BTTR BZA

1 033062 Supply and

using cement

OPC 53 grade

7.75 15.5 75 98.25 4600 Tonne 451950

(Item One only.) Schedule 'A-1' TOTAL : 451950

Percentage rate in figures (+)30.60% Percentage rate in words Plus thirty point six zero percent only

Page 6: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 6 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

6

SCHEDULE - 'A-2'

List of items of works that are covered by USSR 2010 of S.C. Railway.

SL.

No.

SSR Item

No.

Description of

work.

SW 1 App. Qty. SW 2

App.

Qty.

Total Rate Unit Amoun

t in Rs. BTTR BZA

1 045010+

045011

Supplying Reinforcement for R.C.C. work including straightening, cutting,

bending, placing in position and binding all complete. Mild steel and medium

tensile steel bars.

150 300 1500 1,950 45.93 Kg 89564

(Item One only.) Schedule 'A-2' TOTAL : 89564

Percentage rate in figures (+)27% Percentage rate in words (Plus twenty seven percent only

SCHEDULE -'B'

List of items of works that are not covered by USSR 2010 of S.C. Railway.

SL.

No.

SSR Item

No.

Description of

work.

SW 1 App. Qty. SW 2

App.

Qty.

Total Rate Unit Amt in

Rs. BTTR BZA

1 NS 2010-

22

Supplying , farbicating and erecting welded and/or bolted and/or riveted steel

work in built up sections, trusses and framed work, girders, staging, racks etc.,

using RSJ, tees, angles and channels/flats, plates, gussets, round or square bars,

cleats, bolts etc., with contractor's own steel including cutting, bending,

straightening, drilling, riveting, hoisting, fixing, erecting, welding, bolting etc.,

with Providing stifeners wherever required as per approved drawing including

applying a priming coat of a approved steel primer with all contractor's materials,

labour, tools & plants, lead & lift including crossing of tracks if required etc.,

complete as per specification and as directed by Engineer-in-charge.

9.5 19 55 84 58391 MT 4875649

Page 7: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 7 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

7

SL.

No.

SSR Item

No.

Description of

work.

SW 1 App. Qty. SW 2

App.

Qty.

Total Rate Unit Amt in

Rs. BTTR BZA

2 NS 2010-

40

Fabricating, Supplying and fixing of Helical compression spring, 630mm long and

100mm Mean dia of Helix with 28 Numbers of spring coils, conforming to IS

7906 (part I) -1997 made of 20mm dia spring rod of spring steel conforming to

Grade 2 of I.S.4454 (part I) - 2001 and suitable rubber washers on either side to

suit the horizontal beam of height gauges for heavy traffric, shown in the drawing

No. GM(W)SC/BR/2729/2010 (ALT 2) at any location specified by railway with

all contractor's material, consumables, tools, men, machinery, cranes including all

lead and lift, transportation etc., and as directed by the Engineer-in-charge at site.

This includes arrangements for protection of road traffic and including night

working if required

4 8 12 24 7998 Each

spring

191952

( Items Two only.) Schedule 'B' TOTAL : 5067601

Percentage rate in figures (+)36% Percentage rate in words (Plus thirty six percent only)

CONDITIONS

1. The tenderer / Contractor has to quote a uniform percentage rate above/ at par / below for

Schedule-A & Schedule-B items both in figures and words. If there is any difference between

the percentage rate quoted in words and figures, the percentage rate quoted in words will be

taken as correct and final. The tenderer should not quote different percentage rates for

different items of Schedule and the offers with different percentage rates for different items of

the Schedule are liable to be rejected.

2. The quantities furnished in the tender schedule are approximate and shall be operated in full or

part at the discretion of Engineer-in-charge. The payment will be made for the actual

quantities executed.

3. The work should be done in accordance with the specification laid down in manufacturers

guide lines including lead, lift and as directed by the Engineer-in-charge.

Page 8: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 8 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

8

4. The paint samples have to be get tested at CMT/LGD before commencement of work at

contractors own cost.

5. The paints should be obtained from the following approved firms:

(I). M/s. Shalimar paints, (2) Asian Paints, (3) British/Berger Paints, (4) Jonson & Nicholson Paints,

(5) Good Lac Nerolac, (6) Garware Paints, (7) Addisons Paints and Chemicals. In addition to

the above firms, paints procured from reputed manufacturing firms approved by RDSO/LKO

(out of the approved list) may also be used by the contractor with the prior approval of

Engineer-in-charge.

6. The Rates quoted will include the cost of paint, labour, tools, plant and scaffolding

arrangements etc., complete.

7. The work should be completed with in SIX months including the monsoon period and to be

maintained for period of SIX months.

ANNEXURE-„A‟

SPECIFICATIONS OF CONTROLLED CONCRETE:

1. The agency shall indicate the source of supply of materials viz., course aggregate, fine

aggregate, steel, ordinary Portland cement and cement conforming to IS as applicable.

All the materials shall conform to relevant standard specifications.

2. The TOR steel is purchased from TISCO, IISCO, SAIL, Vizag steel plant or any other

source approved by the Engineer-in-charge. The steel shall not be re-rolled variety. The

agency shall produce necessary vouchers in original in support of the purchase of steel

and cement from the suppliers along with certificates to relevant standards from the

manufacturers before the commencement of work.

3. The agency shall submit samples of course/fine aggregate along with necessary cement,

required for mix design. The Engineer-in-charge at site shall forward the samples to a

reputed concrete laboratory for carrying out mix design duly specifying the various

parameters as per IRS bridge code, provision and correction slips and Engg. Standard

order No: 11/2000 and RDSO‟s A&C slip no. 8, dt. 15/22-02-2006 The following

parameters shall be specified for the mix design by the Engineer-in-charge.

a) Grade of concrete required as per IRS bridge code.

b) Type of cement sent for mix design.

c) Minimum and maximum cement content prescribed as per the environment

condition prescribed in the IRS concrete bridge code 1997. Corrections slip No:

8 dt. 15/22-02-2006. The environment condition to be decided as per Engg.

Standing order No: 11 dt: 23-10-2000/7-11-2000.

Page 9: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 9 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

9

d) Maximum water cement ratio to be adopted as per environmental condition.

The agency shall arrange for mix design at their own cost including movement

of materials to laboratory. During the execution of work if there is any change

in the materials forming concrete, mix design shall be carried out again and

work to be carried out accordingly.

The following are extracts of IRS concrete bridge code 1997, Correction slip No: 8 dt.

15/22-02-2006

Amend the following clauses as follows.

i) Clause 5.1.1: Table 2 is revised as under.

Table 2: Grades of Concrete (Clause 5.1)

Grade

Designation

Specified Characteristic compressive strength at

28 days (N/mm2)

M10 10

M15 15

M20 20

M25 25

M30 30

M35 35

M40 40

M45 45

M50 50

M55 55

M60 60

ii) Clause No.5.2.2.1: Table is revised as under.

Grade of concrete

(N/mm2)

Modulus of Elasticity

(KN/mm2)

M10 18

M15 22

M20 25

M25 26

M30 28

M40 31

M50 34

M60 36

Page 10: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 10 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

10

iii) Clause No. 5.3.1:

Following note to be added below table given for workability of concrete.

Suitable plasticizers/admixtures may be used to achieve workability of the order of 150-

200mm.Plasticizers/admixtures should confirm to clause 4.4.

iv) Clause No.5.4.1:

The word “low water cement ratio” appearing in fourth sentence should be replaced by

“adequate water cement ratio.”

v) Clause No.5.4.3:

The Table 4(a) is revised as under:

TABLE 4(a) : Maximum water cement ratio: (Clause No.5.4.3:)

Environment

Maximum water cement ratio.

Plain

cement(PCC) Reinforced concrete (RCC)

Prestressed concrete

(PSC)

Mild 0. 55 0. 50 0.45

0. 50 0. 50 0. 40

Severe 0. 50 0. 45 0. 40

0. 50 0. 45 0. 35

Extreme 0. 45 0. 40 0.35

vi) Clause 5.4.4

The Table 4(b) is revised as under:

TABLE 4(b): Minimum grade of concrete: (Clause 5.4.4)

Environment Plain concrete (PCC) Reinforced concrete

(RCC)

Prestressed

concrete (PSC)

Mild M- 10 M- 15 M- 35

Moderate M- 10 M- 20 M- 35

Severe M- 15 M- 20 M- 45

Very severe M- 15 M- 25 M- 50

Extreme M- 20 M- 30 M- 50

The concrete of grades M-10, M-15 & M-20 are normally used in mass concrete work

and usually mixed by volumetric batching also. The mix for this work would be

M-10-1:3:6

M-15-1:2:4

M-20 - 1:1.5:3

Page 11: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 11 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

11

vii) Clause 5.4.5

Table 4 (c) is revised as under

TABLE : 4 ( c ) :Minimum cementitious material content: (Clause 5.4.5)

Environment

Minimum cementitious material content in Kg/cum

Plain concrete

(PCC)

Reinforced

concrete (RCC)

Prestressed concrete

(PSC)

Mild 210 300 350

Moderate 250 300 400

Severe 250 350 430

Very severe 300 400 440

Extreme 300 400 440

Max. Cementitious material content shall be limited to 500 kg/cum vide No. 5.4. 5.

Note: For under water concrete 10 % extra cement should be added over and above the

normal cement content of the concrete mix specified above.

viii) Clause 5.4.7

This clause is deleted along with its sub-clauses

ix) Clause 7.1.3.4

Replace this clause by clause as under:

Sufficient spacers shall be provided as shall in the opinion of the Engineer be necessary

to maintain specified concrete cover to the reinforcement and preventing displacement

before and during the placement of the concrete. Spacers should be of such material and

designs as will be durable, will not lead to the corrosion of the reinforcement and will

not cause spalling of the concrete cover. Spacer block made from cement, sand and

small aggregate should match the mix proportions of the concrete as far as is practicable

with a view to being comparable in strength, durability and appearance. The use of the

pieces of wood, tile or porous material will not be allowed for this purpose.

x) Clause 7.1.3.5

This clause is deleted

Page 12: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 12 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

12

xi) Clause 7.1.5 is replaced as below

Protective coatings: in order to offer adequate resistance against corrosion,

reinforcement bars may be provided with suitable protective coatings depending upon

the environment conditions. In aggressive environments (Severe, Very severe and

extreme) application of cement slurry coatings after removal of rust and other loose

materials from the surface of the reinforcement bar will generally be sufficient.

However, specialist literature may be referred to in extreme exposure condition.

xii) Clause 15.9.2.3:

This clause is deleted.

Clause No. 15.9.2.4 and 15.9.2.5 should be read as 15.9.2.3 and 15.9.2.4 respectively.

4. The following are the extracts of Engg. Standing order No: 11 issued by S.C.Railway dt.

23-10-2000/7-11-2000.

i) Moderate: - All the bridges situated in area which are not exposed to severe rain or

witch are continuously under water of where concrete is in contact with non aggressive

soil/ground water will fall under this category. All sections of this Railway which are

not listed under severe category below are classified under moderate category.

ii) Severe:- Structures which are situated in area which are exposed to severe rain, alternate

wetting and drying or occasional freezing or severe condensation and also in locations

where the concrete is exposed to aggressive sub soil ground water or situated in coastal

environment.

The following sections of this railway have been identified to be classified under severe

category.

a) Londa - Vasco-da-gama ---- Hubli Division.

b) Gudur -Visakhapatnam.

c) Gudur-Machilipatnam. ---- Vijayawada Division.

d) Bhimavaram-Narsapur.

e) Samalkot- Kakinada

i) Industrial areas as decided by the concerned Divisional Engineers, where corrosive

action is severe.

ii) Very severe and extreme:- Classification of particular bridge in these categories of

environment will depend on case basis as per the actual physical location and as decided

by the Chief Bridge Engineer or concerned Chief Engineer/ construction.

All the requirements specified in the correction slip No:1 for the above categories should

be strictly followed in accordance with the correction slip.

Page 13: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 13 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

13

5. The agency shall keep minimum two Nos. of concrete pin vibrators of 25/40mm size in

good working order during concrete operation. At no point of time, vibration of concrete

should suffer for want of power or for any other mechanical problem any such

concreting without proper compaction will be rejected and the agency shall redo the

work at their own cost.

6. The contractor should prepare at his own cost standard cubes of concrete at suitable

intervals, during concreting operations under the supervision of the Engineer or his

representative and submit the same to the Railway for testing. The testing will be

arranged by the Railway at the contractors own cost including freight charges for

transporting the test cubes to the testing laboratory.

7. Protective coatings: In order to offer adequate resistance against corrosion

reinforcement bars shall be provided with suitable protective coating for bridges

depending upon the environment conditions. The recommended

TABLE (d) : Protective coatings:

Aggressive Environment

(severe)

Severe, very severe and

(Extreme)

Non aggressive

environment (Mild and

Moderate)

Important and Major

bridges

Minor bridges and

structures

All structures

Cement polymer composite

coating (or) Fusion bonded

Epoxy coating.

Cement polymer composite

coating (or) Indicated

cement slurry coating.

Truncatevinlubited

cement slurry coating.

Note: The binding wire should also be coated and no GI binding wire without coating

will not be permitted.

SAFETY PRECAUTIONS TO BE TAKEN AT WORK SITE.

1.1. The Contractor shall not allow any road vehicle belonging to his or his suppliers etc. to

ply in railway land next to the running line. If for execution of certain works, viz.,

earthwork for parallel railway line, supply of ballast for new or existing railway line

etc. road vehicles are necessarily to be used in railway land next to the railway line, the

contractor shall apply to the Engineer-in-charge for granting permission giving the type

and number of individual vehicles, names and license particulars and permanent

addresses of drivers, location, duration and timings for such work/movement. The

Engineer-in-charge or his authorized representative will personally counsel, examine

and certify the road vehicle drivers, contractor‟s flagmen and his supervisors to be

deployed on the work, location, period and timing of the work.

Page 14: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 14 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

14

This permission will be subject to the following obligatory conditions:-

i) The Road vehicle will ply only between sunrise and sunset.

ii) Nominated vehicles and drivers will be utilized for work in the presence of at

least one flagmen and one supervisor or his representative certified for such work.

iii) The vehicles shall ply 6 Meters (from Centre of Track) away from track. Any

movement /work at less than 6 Meters and up to minimum 3.5 Meters clear of

track center shall only be done in presence of railway employees authorized by

the Engineer-in-charge . No part of road vehicle will be allowed at less than 3.5

Meters from track center.

iv) The Contractor shall remain fully responsible for ensuring safety and in case of

accident, shall bear the cost of all damages to the equipments and men and also

damages to railway and its passengers.

v) Engineer-in-charge may impose any other condition necessary for a particular

work or site.

1.2.1. The Contractor at all times shall adopt safe working methods to ensure safety of

structures, equipments and labour at site of works.

1.2.2. The contractor shall not start any work without the presence of Railway supervisor or

his representative authorized by ADEN-in-charge and Contractor‟s supervisor at site.

1.2.3. The methodology proposed to be adopted by the Contractor is to be approved by

Engineer-in-charge with a view to ensure of safety of trains, passengers and workers

and he shall also ensure that the methods and arrangements are actually available at site

before start of the work and the contractor‟s supervisors and the workers have clearly

understood the safety aspects and requirements to be adopted / followed while executing

the work.

1.2.4. There shall be an assurance Register kept at each site, which will have to be signed by

both, ie., Railway Supervisor or his representative as well as the contractor‟s supervisor

as a token of their having understood the safety precautions to be observed at site.

1.2.5. Survey of site by Supervisor of contractor and Railway‟s Supervisor is to be done to

assess precautions to be taken at site for working of trains and materials required for

protection.

1.2.6. The list of permissible / sanctioned infringements to moving dimensions for the section

shall be made available where work is to be done to execute the works without

infringing the moving dimensions.

1.2.7. Competency certificate issued by ADEN-in-charge with the Contractor‟s supervisor at

site should be available in the format given in Annexure-I.

1.2.8. The detailed plans for safe execution of works, duly approved by the Division should be

available for undertaking execution of such works which have bearing on moving

dimensions, especially those works close to the running lines and fixed structures on

brides, inside tunnels etc.,

1.2.9 Look-out caution, speed restrictions as well as traffic block shall be ensured where

necessary for execution of works affecting running lines.

1.2.10 Mobile phones or Walky-Talkie sets where necessary should be provided at work sites.

Page 15: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 15 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

15

1.3. Precautionary measures to be taken at work site away from the track:-

1.3.1. Trenches and foundation pits should be adequately and securely fenced, provided with

proper caution signs and marked with red lights at suitable intervals during night to

avoid accidents. Adequate protective measures should be taken to see that the

excavation operations do not affect or damage adjoining existing buildings.

1.3.2. Proper precautions should be taken for safety of persons and adjoining property before

undertaking any blasting operation. Red flags should be prominently displayed around

the area to be blasted. All the people on the work except those, who actually light the

fuses, should be withdrawn to a safe distance of not less than 300 meters from the

blasting site. Recommendations given in I.S. 4081:1986 should be followed for safety

during various operations involved in the process of blasting.

1.3.3. Suitable scaffold should be provided for workman for all works that cannot be safely

done from the ground or from solid constructions except such works which can be done

safely from ladders for a short period. When a ladder is used, extra labour should be

engaged for holding the ladder and if the ladder is used for carrying materials as well,

suitable foot holds and handholds should be provided on the ladder and ladder should be

given an inclination not steeper than 4 to 1 ( Four vertical to one Horizontal).

1.3.4. Workers employed on mixing asphalt materials, cement and lime mortars should be

provided with protective hand and footwear and protective goggles.

1.3.5. Workers employed in white washing and stacking of cement bags or any materials

which are injurious to the eyes should be provided with protective goggles.

1.3.6. Workers engaged in welding works should be provided with welder protective eye-

shields, single piece cotton cloth and shoes.

1.3.7. Stone breakers should be provided with protective goggles, leg-guards and protective

clothing and they should be seated at sufficiently safe distance from each other.

1.3.8. A fully equipped First-Aid Box should be maintained at site by the Agency with at least

one person fully trained to give First-Aid.

1.3.9. Inflammable articles such as Petrol, oil etc., should be stored separately from other

materials and all prescribed precautions as per the Indian Explosive Act should be

taken.

1.3.10. In the Bridge work, Track works, repairs to tunnel and demolition of structures through

contractual Agency, the safe working and ensuring safety of workman employed should

be specifically laid down in the contract itself.

1.4. Precautionary measures to be taken at work site in vicinity of track:-

1.4.1. Drivers of trains must be served with caution order to look out for any obstruction at the

place of work.

1.4.2. Arrangements should be made to protect the track in case of emergency at work site.

1.4.3. Before the start of the work, the land strip adjacent to the running track where road

vehicle / machinery is to ply for the work shall be demarcated by lime in advance at the

appropriate distance from the centre of existing track in consultation with the Railway

Supervisor[Annexure-IV(A)]. Sketch showing the location of marking and barricading

along the full length of the work area should be done as per the sketch given in

[Annexure-IV (B)]. This will enable the workmen posted at the site and also the lorry

drivers to have clear guidelines on the movement of vehicles.

Page 16: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 16 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

16

1.4.4. Movement of Lorries near the track should be prohibited during night. In case it is

unavoidable adequate protective measures including lighting must be ensured in the

complete work area for the safety of the Public and Passengers. Also additional staff

shall be posted as necessary for night working.

1.4.5. Work should not be allowed to progress without the prior approval of the Engineer-in-

charge in case movement of vehicles close to the track is involved.

1.4.6. Machines and vehicles should ply 6 meters (from Track centre) in case movement at

less than 6 meters away from the track is inescapable, it should be permitted in the

presence of Railway employee authorized by the Engineer-in-charge.

1.4.7. Contractor‟s representative should be issued a certificate by ADEN to the effect that

they have acquired sufficient knowledge about the safety precautions that are needed to

be followed while working near the track.

1.4.8. The worksite shall be suitably demarcated to keep public and passengers away from

work area. Necessary sign boards such as Work in progress etc. shall be provided at

appropriate locations to warn the Public / passengers.

1.4.9. Check lists given in Annexure-II and III shall be used to ensure that all the requisite

measures have been taken before start of work and work in progress.

1.4.10. All temporary arrangements required to be made during execution of work shall be

made in such a manner that moving dimensions do not infringe. Necessary checks shall

be exercised by Site in-charge from time to time.

WORKING OF CONTRACTOR‟S VEHICLES AT SITE

1. When the contractor‟s vehicles are to be worked closer to 6m but not less

than 3.5m from center line of the running track (Annexure-VA)

i) Drivers of vehicle shall be briefed about safety and precautions to be taken while

moving/working close to traffic.

ii) Demarcation of the land shall be done by bright coloured red ribbon/nylon rope of

12mm thick suspended on 75cm high wooden/bamboo posts at a distance of 3.5m

from center line of nearest running track as shown in (Annexure-IVC)

iii) Contractor shall ensure the road vehicle/Machinery ply in a way so that these do

not infringe the line of demarcation.

iv) Presence of an authorized Railways representative shall be ensured before plying

of vehicles or working machinery.

v) Railway supervisor shall issue suitable caution order to drivers of approaching

train about road vehicles plying or machinery working close to running tracks.

The train drivers shall be advised to whistle freely to warn about the approaching

train. Whistle boards shall be provided wherever considered necessary.

vi) Lookout men shall be posted along the track at a distance of 800m from such

locations, which will carry red flag and whistles to warn to the road

vehicles/machinery users about the approaching trains.

Page 17: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 17 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

17

vii) On curves where visibility is poor, additional lookout men shall be posted.

viii) In unusual circumstances, where operator apprehends infringement to track

while working truck/machinery near running track, following action shall be

taken:

a) The contractor /supervisor/vehicle operator immediately advise the situation to

Railway official and assist him in protecting the track.

b) Protection shall be done for other emergencies.

2. When the contractor‟s vehicles are to be worked close to 3.5m from center

line of running track:

i) Plying of vehicle or working of machinery closer to 3.5m of running track shall be

done under protection of track. Traffic block shall be imposed wherever

considered necessary. The site shall be protected as per the sketch given in

(Annexure-VB) and the provisions of Para No. 806 & 807 of P-way Manual as the

case may be.

ii) Presence of a Railway supervisor shall be ensured at work site.

iii) Railway supervisor shall issue suitable caution order to drivers of approaching

train about road vehicles plying or machinery working close to running tracks.

The train drivers shall whistle freely to warn about the approaching train.

3. Parking of vehicles or construction machinery:

i) No vehicle or construction machinery shall be parked in unmanned condition on a

gradient sloping towards running track.

ii) Even on level ground or gradients sloping away from the track, vehicles or

construction machinery shall be parked in unmanned conditions at a minimum

distance of 6m from nearest track center in fully braked condition. In addition to

brakes, suitable wedges shall also be applied on all the wheels.

4. TRAINING

Training in safe working methods for both along and on the track should be

imparted to supervisors /operators of the work executing agencies. Such training

may be imparted at zonal/divisional training schools for required duration as

deemed fit, with a view to ensure that the field staff engaged in such works get

acquainted with the safety precautions that are needed to be taken while executing

the works.

Page 18: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 18 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

18

ANNEXURE - I

COMPETENCY CERTIFICATE

Certified that Shri…………………………………………………. P.Way

supervisor of M/s. …………………………… has been examined regarding P.Way

working on …………………………. work.

His knowledge has been found satisfactory and he is capable of supervising the work

safely.

ASSISTANT ENGINEER

Page 19: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 19 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

19

ANNEXURE – II

CHECK LIST

(BEFORE STARTING THE WORK)

Name of the work : ……………………………………………………………………

Location …………………………………………………………………………………

Duration of the work : From …………………… To …………………………

Sl.N

o Details Yes No

1 Contractor‟s supervisor identified / Selected. Who is going to be site

in-charge?

2 Training imparted to contractors supervisor & Certificate issued?

3 Work site inspected by Constructions supervisor / other

department‟s supervisors along with contractor‟s supervisor?

4 Precautions to be taken identified and listed?

5 Plan of work, drawn out by contractor‟s supervisor in consultation

with Railway‟s supervisor?

6 Plan of work, brought to the knowledge of open line AEN/IOW &

PWI?

7 Before start of the work, proper lime marking / barricading had done

at site of work?

8 Men deputed for protection of track along with safety equipments?

9 Caution order issued for the train drivers in case work is being done

within 6mts of centre of running track?

10 Drivers of vehicles/machinery being used have been identified?

11 Drivers of vehicles/machinery briefed about the safe working?

12 Sufficient lighting provided at site of work for night working?

13 Infringements checked?

14 Sectional (Open line) AEN/PWI/IOW have satisfied themselves

regarding safety arrangements?

15 Availability of Walkie –Talkie sets for communication?

Signature of construction/

other departments Supervisor

Date:

Signature of Open line‟s Supervisor.

Page 20: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 20 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

20

ANNEXURE – III

CHECK LIST

( WHILE WORK IN PROGRESS )

Name of the work : ………………………………………………………………

Location ………………………………………………………………………………

Duration of the work : From ……………………… To ………………………………

Date of inspection ……………………………………………………

Sl.

No Details Yes No

1 Does the contractor‟s supervisor have the certificate?

2 Does the knowledge of contractor‟s supervisor on safety of track

& work site is up to the mark?

3 Is the Railway‟s supervisor of Construction Organisation/other

departments available at site?

4 Is knowledge of Railway‟s supervisor O.K.?

5 Is lime marking/barricading done?

6 Are adequate safety precaution taken?

7 Are communication facility (Walkie – Talkie sets) available at

site?

8 Are only identified drivers driving the vehicles/machinery?

9 Is whole work site safe for working of men/vehicles & trains?

10 Are adequate lighting arrangements done at site?

11 Are adequate protection equipment available at site?

12 Is caution order to trains being issued?

13 Are train drivers following the enforced temporary speed

restriction?

14 Has work permit been taken for working in Electrified

territory/Station yards (P &C areas)

Signature of inspecting officer

Designation

Page 21: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 21 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

21

ANNEXURE – IV

(A)Marking of Line with Lime

3500mm

150 mm wide white line with lime

Vehicle / trucks can ply in this` area

(B) Provision of Barricading

3500mm

Barricading

Luminous tape/Red Colour Nylon Rope 12 mm thick

Post (Bamboo / Steel / Concrete)

1200mm

3500mm 3500mm 3500 mm

C) Elevation of Barricading

Page 22: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 22 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

22

ANNEXURE –V

A) Plying of Vehicles/Machinery between 3.5 mts. to 6.0 mts from centre of track

3500mm

Contractor‟s supervisor Railway‟s supervisor

150 mm wide white line with lime

6000mm

B) Plying of Vehicles / Machinery within 3.5 mts from center of track

DN LINE

Banner flag in day time / HS lamps in night

detonators

UP LINE

1200 metres

3500mm

detonators

Contractor‟s supervisor Railway‟s supervisor

Page 23: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 23 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

23

ANNEXURE-B

Draft proceeding order to be followed by TRD and Engineering supervisors/

Tenderer /Contractor with regard to maintenance works for the Bridges:

1. “No Work” shall be done above or with in 2 meters from the live OHE with out

a “permit-to-work”.

2. Use of steel measuring tapes or long metalising wires is prohibited in electrified

sections.

3. Painting work should be done under the supervision of competent Bridge

engineering staff only.

4. To carry out the painting/maintenance works on the girder bridges, FOBs i.e.,

with in the vicinity of OHE (less than 2 Meters distance) a memo has to be sent

to TRD supervisor of the jurisdiction by the SSE/SE/BR mentioning the time

period required to arrange the “Permit to work”.

5. No Engineering (SSE/SE/BR) supervisor should allow the contractor staff or

bridge staff to carryout the works on bridges (Less than 2 meters from OHE)

with out obtaining “permit-to-work” from the authorized person of TRD

Official.

6. After obtaining power-block on OHE, the TRD supervisor will then arrange two

discharge rods to OHE on either side of the Bridge work spot, and then issue

permit –to-work to engineering supervisor.

7. After completion of the work, the Engineering supervisor should give a

clearance memo to TRD supervisor and then only the two discharge rods will be

removed from OHE and the OHE will be charged.

8. Care should be taken when labour were engaged by contractor to do the painting

on the girder bridges i.e., they should be allowed to work after obtaining permit

to work only.

9. While doing the painting/maintenance /Erection works beyond 2 meters distance

to OHE the staff must be counseled/watched not to come into the danger zone

(i.e. below 2 meters distance to OHE) during the course of working by

SSE/SE/BR.

10. Responsible person from the SSE/SE/BR side should be available at the work

spot of the Bridge maintenance/painting works during the “power block” (permit

to work) period to avoid any untoward incidents.

Page 24: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 24 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

24

SPECIAL CONDITIONS OF CONTRACT

1. The rates include all lead and if the materials obtained by rail all freight charges including

loading charges. 2. Sales tax, Royalties and Octroi duties, if any, that may be payable under Provincial

Government Sales Tax Act or Local Bodies Act or rules on any of the material that may be

used or supplied by the contractor will be payable by the contractor. The Railway will neither

pay the taxes or duties nor be bound to compensate the contractor for any amounts paid by him

by way of these taxes or duties.

Sales Tax at 4% on the materials portion of the contract will be deducted from each on account

bill where identifiable. Where the labour and material portion is not clearly identifiable, the

labour element shall be taken as 30%. On the balance 70% of the value of the work, 4% shall

be deducted pro-rata from each “on account bill” towards Sales tax.

Seigniorage charges recoverable from bills:-

Seigniorage charges for supply of earth, mooram, sand and other minerals as fixed by the State

Government and payable to them as revised from time to time during the currency of contract

will be recovered by Railway from the contractors “on account” and “final bills” and remitted

to the state government. The rates quoted by the Tenderer shall be inclusive of these charges.

Claims regarding revision of seigniorage charges and consequent enhancement of the accepted

rate will not be entertained. However, no seigniorage charges / fee shall be recovered from the

bills of the contractor, if the contractor produces documentary evidence e.g. “Transit Passes”

issued by State Govt. Officials in token of having paid seigniorage fee. In such cases, the

genuineness of such documentary evidence produced along with proof of payment of

seigniorage charges, shall be got verified by the Railway from the concerned Mining and

Geology Dept 3. WATER:- A charge of One percent will be made by the Railway for the supply by the

Railway of piped water from existing pipe lines and calculated on the amount of all items of

work (USSR/NS items) appearing in the bills payable to the contractor in respect of which

work such water has been issued to the Contractor and such charges should be deducted from

sums due or payable by the Railway to the Contractor from time to time.

4. In the event of water having to be brought by the Railway to the site of the work in traveling

tanks, the actual freight at Public Tariff rate and all other charges incurred therein including any

demurrage that may be levied shall be payable by the Contractor and deducted from sums due

or payable by the Railways to the Contractor from time to time.

In addition to the charges of one percent referred to above, if additional pipe lines to

those already existing are called for by the contractor, the cost of the same and all charges

incurred by the Railway in their laying including supervision charges will be paid by the

contractor or the contractor provides and lay his own piping at the discretion of Divisional

Engineer.

5. The Railway does not guarantee work under each items of the Master Schedule. For example if

a gate-lodge or gang huts are to be built between stations and the work order issued to the

sectional contractors additional payment on account of lead or freight charges for the materials

that may have to be brought by rail or by road, will not be admissible.

Page 25: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 25 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

25

6. If there arises any discrepancy between the printed Unified Standard Schedule of Rates 2010 as

amended by addendum and corrigendum slips issued from time to time upto date and the

schedule attached to the Tender pertaining to this work, the former shall be treated as

authentative and binding in all purposes.

7. Rubble masonry shall be first sum of Railways Specification No 503 according to South

Central Railway Specification for materials and works. Contractors attention is particularly

invited to dressing of stone as laid down in the Railway‟s specification.

8. The Special conditions supplemented to the conditions of Tender and contracts the General

conditions of contract and the notes appearing under the relevant chapter and sub chapters of

the Unified Standard Schedule of Rates 2010 should be considered as part of the contract

papers where the provisions of these conditions are at variance with General Conditions of

Contract these special conditions.

9. Performance Guarantee (P.G.):-

a. The successful bidder shall have to submit a Performance Guarantee (PG) within 30

(thirty) days from the date of issue of Letter of Acceptance (LOA). Extension of time

for submission of PG beyond 30(thirty) days and upto 60 days from the date of issue of

LOA may be given by the Authority who is competent to sign the contract agreement.

However, a penal interest of 15% per annum shall be charged for the delay beyond 30

(thirty) days, ie., from 31st day after the date of issue of LOA. In case the contractor

fails to submit the requisite PG even after 60 days from the date of issue of LOA, the

contract shall be terminated duly forfeiting EMD and other dues, if any payable against

that contract. The failed contractor shall be debarred from participating in re-tender for

that work.

b. The successful bidder shall submit a Performance Guarantee (PG) in any of the

following forms, amounting to 5% of the contract value:-

(i) A deposit of Cash,

(ii) Irrevocable Bank Guarantee,

(iii) Government Securities including State Loan Bonds at 5 percent below the

market value

(iv) Deposit receipts, Pay orders, Demand Drafts and Guarantee Bonds. These

forms of Performance Guarantee could be either of the State Bank of India or

of any of the Nationalized Banks;

(v) Guarantee Bonds executed or Deposits Receipts tendered by all Scheduled

Banks;

(vi) A Deposit in the Post Office Saving Bank;

(vii) A Deposit in the National Savings Certificates;

(viii) Twelve years National Defence Certificates;

(ix) Ten years Defence Deposits;

(x) National Defence Bonds; and

(xi) Unit Trust Certificates at 5 percent below market value or at the face value

whichever is less.

Page 26: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 26 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

26

Also FDR in favour of Senior Divisional Finance Manager, S. C. Railway, Vijayawada

(free from any encumbrance) may be accepted.

1. The Performance Guarantee shall be submitted by the successful bidder after the Letter

Of Acceptance(LOA) has been issued, but before signing of the contract agreement.

This P.G. shall be initially valid up to the stipulated date of completion plus 60 days

beyond that. In case, the time for completion of work gets extended, the contractor

shall get the validity of P.G. extended to cover such extended time for completion of

work plus 60 days.

1.0 The value of PG to be submitted by the contractor will not change for variation upto

25%(either increase or decrease). In case during the course of execution, value of the

contract increases by more than 25% of the original contract value, an additional

Performance Guarantee amounting to 5%(five percent) for the excess value over the

original contract value should be deposited by the Contractor.

1.1 The Performance Guarantee (PG) shall be released after physical completion of the

work based on the „Completion Certificate‟ issued by the competent authority stating

that the contractor has completed the work in all respects satisfactorily. The security

deposit, however, shall be released only after the expiry of the maintenance period

and after passing the final bill based on „No Claim Certificate‟ from the contractor.

1.2 Whenever the contract is rescinded, the security deposit shall be forfeited and the

Performance Guarantee shall be encashed. The balance work shall be got done

independently without risk and cost of the failed contractor. The failed contractor

shall be debarred from participating in the tender for executing the balance work. If

the failed contractor is a JV or a partnership firm, then every member/ partner of such

a firm shall be debarred from participating in the tender for the balance work either in

his / her individual capacity or as a partner of any other JV / partnership firm.

1.3 The Engineer shall not make a claim under the Performance Guarantee except for

amounts to which the President of India is entitled under the contract (not

withstanding and / or without prejudice to any other provisions in the contract

agreement) and this shall be in the event of:

i) Failure of the contractor to extend the validity of the Performance Guarantee as

described herein above, in which event the Engineer may claim the full amount

of the Performance Guarantee.

ii) Failure of the contractor to pay President of India any amount due, either as

agreed by the contractor or determined under any of the Clauses / Conditions of

the agreement, within 30 days of the service of notice to this effect by Engineer.

iii) The contract being determined or rescinded under provision of the GCC the

Performance Guarantee shall be forfeited in full and shall be absolutely at the

disposal of the President of India

Page 27: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 27 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

27

10. Security Deposit:-

The scale of Security Deposit that is to be recovered from the contractor shall be as follows.

i) Security Deposit should be 5% of the contract value.

ii) The rate of recovery will be at the rate of 10% of the bill amount till the full

Security Deposit is recovered.

iii) Security Deposit will be recovered only from the running bills of the contract and no

other mode of collecting SD such as SD in the form of instruments like Bank

Guarantee, Fixed Deposit Receipt etc., shall be accepted towards Security deposit.

iv) Conversion of Security Deposit into FDR after recovery of full stipulated SD (FA& CAO/SC letter No.AFX/EMD/Policy/ Vol.I dt.26.8.2010 circulated vide

PCE/SC lr. No.W.148/ SCRCA dt.30.9..2010):- If the contractor so desires, the cash

deposits in the form of security deposit may be allowed to be converted into FDRs (in

favour of respective Accounts Officers and on account of contractor), after full

recovery, at the discretion of the Railway, duly collecting necessary charges of

conversion by the Railway Administration.

The security deposit shall be released only after the expiry of the maintenance period and

after passing the final bill based on „No Claim Certificate‟.

After the work is physically completed, security deposit recovered from the running bills

of a contractor can be returned to him if he so desires, in lieu of FDR/irrevocable bank

guarantee for equivalent amount to be submitted by him.

In case of contracts of value Rs.50 crores and above, irrevocable bank guarantee can also

be accepted as a mode of obtaining security deposit.

11. REVISED COMPREHENSIVE CLAUSE 46A OF GCC–PRICE VARIATION

CLAUSE: As per Railway Board Letter No.2007/CE-CT/18/Pt.19

dt.14.12.2012- Price Variation Clause shall be applicable only for tenders of

value Rs.50 lakh and more, irrespective of the contract completion period: Clause 46A-Price Variation clause:

46A.1. Price Variation clause shall be applicable only for tenders of value as prescribed by

the Ministry of Railways through instructions/circulars issued from time to time and

irrespective of the contract completion period. Materials supplied free of cost by

Railway to the contractors shall fall outside the purview of Price Variation clause. If,

in any case, accepted offer includes some specific payment to be made to consultants

or some materials supplied by Railway free or at fixed rate, such payments shall be

excluded from the gross value of the work for the purpose of payment/recovery of

price variation.

46A.2. The Base Month for „Price Variation clause‟ shall be taken as month of opening

of tender including extensions. If any, unless otherwise stated elsewhere. The

quarter for applicability of PVC shall commence from the month following the

month of opening of tender. The Price Variation shall be based on the average

Price Index of the quarter under consideration.

46A.3. Rates accepted by Railway Administration shall hold good till completion of

work and no additional individual claim shall be admissible on account of

fluctuations in market rates, increase in taxes/any other levies/tolls etc., except

that payment/recovery for overall market situation shall be made as per Price

Variation Clause given hereunder.

Page 28: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 28 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

28

46A.4. Adjustment for variation in prices of material, labour, fuel, explosives

detonators, steel, concreting, ferrous, non-ferrous, insulators, zinc and cement

shall be determined in the manner prescribed.

46A.5. Components of various items in a contract on which variation in prices be admissible

, shall be Material, Labour, Fuel, Explosives, Detonators, Steel, Cement, concreting,

Ferrous, Non-ferrous, Insulator, Zinc, erection etc., However, for fixed components,

no price variation shall be admissible.

46A.6. The percentages of labour component, material component, fuel component etc.,

in various types of Engineering Works shall be as under:

Component Percentage Component Percentage

A) Earthwork contracts:

Labour

component

50% Other material

components

15%

Fuel

component

20% Fixed

component*

15%

B) Ballast and Quarry Products contracts

Labour

component

55% Other material

components

15%

Fuel

component

15% Fixed

component*

15%

C) Tunnelling Contracts

Labour

component

45% Detonators

component

5%

Fuel

component

15% Other material

components

5%

Explosive

component

15% Fixed

component*

15%

D) Other Works Contracts

Labour

component

30% Fuel component 15%

Material

component

40% Fixed

component*

15%

*it shall not be considered for any price variation.

46A.7. The Amount of variation in prices in several components (labour material etc., ) shall

be worked out by the following formulae:

i) L=Rx(I-Io) x P

Io 100

ii) M=Rx(W-Wo) x Q

Wo 100

Page 29: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 29 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

29

iii) U=Rx(F-Fo) x Z

Fo 100

iv) X=Rx(E-Eo) x S

Eo 100

v) N=Rx(D-Do) x T

Do 100

vi) Ms=O x (Bs-Bso)

vii) Mc=A x(Wc-Wco)/Wco

Where

L Amount of price variation in labour

M Amount of price variation in Materials

U Amount of price variation in fuel

X Amount of price variation in Explosives

N Amount of price variation in Detonators

Ms Amount of price variation in Steel

Mc Amount of price variation in Cement

Mcc Amount of price variation in Concreting

Mf Amount of price variation in Ferrous

Mnf Amount of price variation in Non-ferrous

Mz Amount of price variation in Zinc

MIN Amount of price variation in Insulator

O Weight of steel in tones supplied by the contractor as per the „on-account‟ bill for the

month under consideration.

R Gross value of work done by contractor as per on account bill(s) excluding cost of

materials supplied by Railway at fixed price minus the price values of cement and

steel. This will also exclude specific payment, if any, to be made to the consultants

engaged by contractors (such payment will be indicated in the contractors offer)

Ref:Rly Bd Lr.No.2007/CE-I/CT/18/Pt.19, dt.07.05.2013.

A Value of Cement supplied by Contractor as per on account bill in the quarter under

consideration.

Io Consumer Price Index Number for Industrial Workers- All India- Published in RBI

Bulletin for the base period

I Consumer Price Index Number for Industrial Workers- All India-Published in RBI

Bulletin for the average price index of the 3 months of the quarter under consideration

Wo Index Number of Wholesale Prices- By Groups and sub-Groups-All commodities- as

published in the RBI Bulletin for the base period

W Index Number of Wholesale Prices- By Groups and Sub-groups-All commodities- as

published in the RBI Bulletin for the average Price index of the 3 months of the

quarter under consideration.

Page 30: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 30 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

30

Fo Index Number of Wholesale Prices- By Groups and sub-Groups for Fuel, Power,

Light and Lubricants as published in the RBI Bulletin for the base period.

F Index Number of Wholesale Prices- By groups and sub-groups for Fuel, Power, Light

and Lubricants as published in the RBI Bulletin for the average price index of the 3

months of the quarter under consideration.

Eo Cost of explosives as fixed by DGS&D in the relevant rate contract of the firm from

whom purchases of explosives are made by the contractor for the base period.

E Cost of explosives as fixed by DGS&D in the relevant rate contract of the firm from

whom purchases of explosives are made by the contractor for the average price index

of the 3 months of the quarter under consideration.

Do Cost of detonators as fixed by DGS&D in the relevant rate contract of the firm from

whom purchases of detonators are made by the contractor for the base period.

D Cost of detonators as fixed by DGS&D in the relevant rate contract of the firm from

whom purchases of detonators are made by the contractor for the average price index

of the 3 months of the quarter under consideration

Bs SAILs (Steel Authority of India Limited) ex-works price plus Excise Duty thereof ( In

rupees per tone) for the relevant category of steel supplied by the contractor as

prevailing on the first day of the month in which the steel was purchased by the

contractor (or) as prevailing on the first day of the month in which steel was brought

to the site by the contractor whichever is lower

Bso SAILs ex-works price plus Excise Duty thereof ( in Rs. Per tone) for the relevant

category of steel supplied by the contractor as prevailing on the first day of the month

in which the tender was opened

Wco Index no. of Wholesale Price of sub-group (of cement) as published in RBI Bulletin

for the base period.

Wc Index no. of Wholesale Price of sub-group (of cement) as published in RBI Bulletin

for the average price index of the 3 months of the quarter under consideration.

C RBI wholesale price index for cement for the month which is six months prior to date

of casting of foundations

Co RBI wholesale price index for cement for the month which is one month prior to date

of opening of tender

Z IEEMA price for zinc for the month which is two months prior to date of inspection of

material.

Zo IEEMA price for Zinc for the month which is one month prior to date of opening of

tender.

Cu IEEMA price for copper wire bar for the month which is two months prior to date of

inspection of material

Cuo IEEMA price for copper wire bar for the month which is one month prior to date of

opening of tender

Sf IEEMA price index for Iron & Steel for the month which is two months prior to date

of inspection of material

Sfo IEEMA price index for Iron & Steel for the month which is one month prior to date of

opening of tender

In RBI wholesale price index for Structural clay products for the month which is two

months prior to date of inspection of material.

Ino RBI wholesale price index for Structural clay products for the month which is one

month prior to date of opening of tender

Page 31: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 31 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

31

P % of Labour component

Q % of Material component

Z % of Fuel component

S % of Explosive component

T % of Detonators component

G % of concreting component

H % of Ferrous component

J % of Non-ferrous component

W % of Zinc component

46A,8. The demands for escalation of cost shall be allowed on the basis of provisional

indices made available by Reserve Bank of India. Any adjustment needed to be

done based on the finally published indices shall be made as and when they became

available.

46A.9. Relevant categories of steel for the purpose of operating Price Variation formula, as

mentioned in this clause, based on Sails Ex-Works Price Plus Excise Duty thereof,

shall be as under:

Sl.

No.

Category of Steel supplied in Railway

work

Category of Steel produced by SAIL Whose Ex-

works Price Plus Excise Duty Would be

Adopted to Determine Price Variation.

1. Reinforcement bars and other rounds TMT 8mm IS 1786 Fe 415/Fe 500

2. All types and sizes of angles Angle 65x65x6mm IS 2062 E250A SK

3. All types and sizes of plates PM plates above 10-20mm IS 2062 E250A SK

4. All Types and sizes of channels and joists Channels 200x75mm IS 2062 E250A SK

5. Any other section of steel not covered in

the above categories and excluding HTS

Average of price for the 3 categories covered

under SL 1, 2, & 3 above.

46A.10 Price variation During Extended Period of contract.

The price adjustment as worked out above, ie., either increase or decrease shall be

applicable up to the stipulated date of completion of work including the extended

period of completion where such extension has been granted under Clause 17-! Of

the General Conditions of Contract. However, where extension of time has been

granted due to contractors failure under Clause-17B of the General conditions of

Contract, price adjustments shall be done as follows:

a) In case the indices increase above the indices applicable to the last month of

original completion period or the extended period under clause 17-A, the price

adjustment for the period of extension granted under Clause 17-B shall be

limited to the amount payable as per the Indices applicable to the last month of

the original completion period or the extended period under clause 17-A of the

General conditions of contract; as the case may be.

b) In case the indices fall below the indices applicable to the last month of

original/extended period of completion under clause 17-A, as the case may be;

then the lower indices shall be adopted for the price adjustment for the period

of extension under clause 17-B of the General Conditions of Contract.

Page 32: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 32 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

32

12. DEDUCTION OF INCOME TAX AT SOURCE

In terms of new Section 194-C inserted by the Finance Act 1972 , in the income tax Act 1961

the Railway shall at the time of arranging payments to the contractor and/or sub contractor(in

the case of sub contractor only when the Railway is responsible for payment of consideration

to him under the contract) for carrying out any work (including supply of labour for carrying

out any work) under the contract be entitled to deduct income tax at source on Income

comprised in the sum of such payments.

The deduction towards income tax to be made at source from the payments due to non-

residents shall continue to be governed by Section 195 of the Income Tax Act 1961.

No Income Tax will be deducted by the Railway on payments made for supply of materials

where such value of supply portion is distinct and ascertainable such as supply of Timber, tiles,

bricks, ballast including track/ballast etc. The deductions towards Income Tax to be made at

source from the payment due to non/residents shall continue to be governed by Section 195 of

the Income Tax Act 1961.

13. LIABILITY OF CONTRACTOR(S) - ANY DAMAGE SUSTAINED BY RAILWAYS

DURING ACCIDENTS ETC., CAUSED DUE TO CONTRACTOR(S) FAILURES, FAULT

OR NEGLIGENCE. Railway will post an Engineer-in-charge who may be SSE/SE/JE or Supervisor of any grade at

site for Technical Supervision of the work. This Engineer-in-charge will be responsible for

safety of the traffic. The work shall be executed by the contractor in a workman like manner to

the satisfaction of the Engineer-in-charge. The Contractor and his labour shall be guided by the

instructions of the Engineer-in-Charge. In the event of any accident occurring at the work site

and it is established during the departmental enquiry by the Railway or by Statutory enquiry of

CRS, that the accident occurred wholly or partly due to any act tantamounting to negligence on

the part of the contractor or his labour in not adhering to the instructions of the engineer-in-

charge, the contractor shall render himself liable for damages and also legal prosecution if loss

of life is involved.

14. Implementation of – the Building and other construction Workers (RECS) Act, 1996

and the Building and other Construction Workers Welfare Cess Act, 1996 in Railway

Contracts. “The Tenderer for carrying out any construction work in Andhra Pradesh (name of State) must

get themselves registered from the Registering Officer under Section-7 of the Building and

other Construction Workers Act, 1996 and rules made thereto by the Andhra Pradesh (name of

State)Government and submit certificate of registration issued from the Registering Officer of

the Andhra Pradesh(name of the State) Government (Labour Department). For enactment of

this act, the Tenderer shall be required to pay cess @ 1% of cost of construction work to be

deducted from each bill, Cost of material shall be outside the purview of cess, when supplied

under a separate schedule item.”

Page 33: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 33 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

33

ANNEXURE- “III”

WORKS CONTRACT CLAUSE-13

1. In case cement, Steel, AC sheet with or without accessories, GI sheets with or without

accessories, glasses or any other materials/items are issued to the contractor(s)either free of cost

or on cost to be recovered for use on the work as stipulated in the agreement the supply thereof

shall be made in stages depending on the progress of the work, limited to the quantity

/quantities computed by the Railway, according to the prescribed specification and approved

drawings as per agreement.

The materials supplied should conform to Railway‟s Specification in all respects should be in

accordance with approved sample.

All such materials supplied to the contractor(s) for the work either free of charge or on

payment as the case may be will be issued to contractor(s) at the Railway depot/godown/goods

shed and will have to be transported by the contractor to the site of work at his cost. All such

materials shall be used by the Contractor for the work in such quantities as are indicated in the

schedule or in the relevant specifications or drawings or as approved by the Engineer, whose

decision thereon shall be final. Wastage or damages of such materials in any manner shall be

totally avoided. The contractor(s) shall be liable to the accountal for all such materials issued

by Railway either free of cost or on payment excluding the permissible wastage which incase

of steel materials should not in any case exceed 1% of the total quantity required for the work

as per the approved drawings. No wastage under other items is permissible. Short lengths of

rods should also be utilized to the extent possible by overlapping joints.

The Cement, Steel, A.C.Sheets with or without accessories, G.I sheets with or without

accessories glasses or any other materials issued in excess of the requirement(s) as above, shall

be returned in perfectly good condition by the contractor(s) to the Railway at the Railway

depot/Godown/Goods shed at________immediately after completion or termination of the

contract. If the contractor fails to return the said materials then the cost of such materials issued

in excess of the requirement as computed by Railway according to the specification and

approved drawings will be recovered from the contractor(s) at twice the prevailing procurement

cost at the time of last issue viz., 2 x (purchases price +5% freight only). This will be without

prejudice to the right of Railway to take action against the contractors under the condition of

the contract for not doing/completing the work according to the prescribed specification and

approved drawings. If it is discovered that the quantity of cement, steel or any other material

used is less than the quantity computed by the Railway, according to specifications and

approved drawings the cost of materials not returned will be recovered at the same rates as

applicable to excess issue of materials, indicated in the preceding para.

Page 34: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 34 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

34

2. It shall be the responsibility of the contractor to keep in safe custody any Railway material

plant or equipment issued for the work. The contractor shall at his own expense provide

suitable temporary shed/sheds for this purpose on the Railway land made available by the

Railway free of rent and shall remove the shed/sheds when no longer required in terms of

clause 30 of General conditions of contract.

3. If due to any reason the Railway is not in a position to make available the Railway land the

Railway Engineer-in-charge of the work may permit the contractor to erect at his own cost

shed/sheds or secure private accommodation outside the Railway premises. In such a case the

contractor may be permitted to take the Railway material required for the works outside the

railway premises and to store in the Shed so erected or private accommodation so secured. It

shall be the responsibility of the contractor to keep the railway material in safe custody and the

same should be kept entire separate from the contractors material and the Railway shall have

liberty to inspect the same from time to time.

4. The code Nos. description and rates given in the schedule are based on the printed USSR -

2010, of S.C.Railway. Any discrepancy noticed during the execution of the work, in the

working rates quantity of cement etc. should be rectified by reference to the printed schedule,

which shall be treated as authoritative and binding on the contract. The relevant notes

applicable to the respective sub chapters will apply to the items of the Tender schedule and

should be considered as having been incorporated in the contract agreement and binding on the

Contractor.

5. For any other items not specially shown in the schedule of rates appended to the tender

document, the Divisional/Executive Engineer will offer rates as shown for the_________ zone

in the South central railway printed USSR - 2010, of S.C.Railway subject to the same

percentage adjustment accepted in the contract being applicable to the additional items.

6. Railway shall not supply from its own quota to the contractors controlled or imported

commodities. Assistance will, however given by recommending to appropriate authorities.

Contractor applications for issue of import licenses and release of controlled commodities if the

Engineer is satisfied that this material is actually required by contractor for carrying out the

work and is not available in the country.

7. VARIATION OF COSTS

Price variation clause is not applicable for advertised tender value upto Rs.50 lakhs. Time

is the essence of contract

8. (a) PERIOD OF COMPLETION: The Railway expects that a resourceful and experienced

contractor should be able to complete the work in all respects within the period as

specified in the Tender Notice and in the Schedule where items of work are

furnished from the date of letter of acceptance of the Tender

(b) Extension of time of completion will be governed by clause 17 of General Conditions

of Contract. However, while granting the extension of time under clause 17(B) of

GCC, a token penalty as deemed fit based on the circumstances of the case can be

imposed on the contractor without prejudice to other rights of Railway

Administration as provided under GCC.

9. MAINTENANCE PERIOD: The work shall be maintained after completion for a period as

specified in the Schedule where items of work are furnished by the contractor and he shall

make good any defects, imperfections, shrinkages or faults which may appear at his own cost.

10. It is HEREBY AGREED that it shall be the duty of the contractor to keep himself informed of

all corrections, and amendments of the said General conditions of contract made up to the date

of the execution of these presents and no objection shall be taken by the contractor on the

ground that he was not aware of such amendments and corrections of the said General

Conditions of Contract or to any of them.

Page 35: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 35 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

35

11. VARIATION IN CONTRACT QUANTITIES:-

The procedure as detailed below shall be adopted for dealing with variations in quantities

during execution of works contracts:

a) The Railway reserves the right to alter the designs and drawings. If due to change of drawing or

design or any other reasons, there be variations, either increase or decrease in quantities,

payment will be made only for the actual quantities executed at the accepted rates. If

there be sufficient cause the Railway may grant extension of the date of completion

suitably. Such circumstances shall in no way affect or vitiate the contract or alter the

character thereof, or entitle the contractor to damages or compensation thereof except as

provided for in this contract.

b) The quantities of each item of work furnished in the Schedule are approximate and are

intended for the guidance of Tenderer/Contractor. In actual execution of work there may

be some increase in the quantities specified. Such variation upto 25% shall in no degree

affect the validity of the contract and it shall be performed by the contractor as provided

therein and be subjected to the same conditions, stipulations and obligations originally

and expressly included and provided for in specifications and drawings and the amount

to be paid there for shall be calculated in accordance with accepted schedule rates.

(1) Prior Finance concurrence is necessary for varying the individual quantities

beyond 25% or where the gross agreement value exceeds 25% of the agreement

value.

(2) Individual NS items in contracts shall be operated with variations of plus or minus

25% and payment would be made as per the agreement rate. For this, no Finance

concurrence would be required.

(3) In case an increase in quantity of an individual item by more than 25% of the

agreement quantity is considered unavoidable, the same shall be got executed by

floating a fresh tender. If floating a fresh tender for operating that item is

considered not practicable, quantity of that item may be operated in excess of

125% of the agreement quantity (100% i.e., the original quantity +25% ie.,

quantity over and above the original quantity) subject to the following conditions.

a) Operation of an item by more than 125% of the agreement quantity needs

the approval of an officer of the rank not less than S.A. Grade:

i) Quantities operated in excess of 125% but upto 140% of the

agreement quantity of the concerned item, shall be paid at 98% of the

rate awarded for that item in that particular tender;

ii) Quantities operated in excess of 140% but upto 150% of the

agreement quantity of the concerned item shall be paid at 96% of the

rate awarded for that item in that particular tender;

iii) Variation in quantities of individual items beyond 150% will be

prohibited and would be permitted only in exceptional unavoidable

circumstances with the concurrence of associate finance and shall be

paid at 96% of the rate awarded for that item in that particular tender

b) The variation in quantities as per the above formula will apply only to the

Individual items of the contract and not on the overall contract value.

c) Execution of quantities beyond 150% of the overall agreement value should

not be permitted and, if found necessary should be only through fresh

tenders or by negotiating with existing contractor, with prior personal

concurrence of FA&CAO/ FA&CAO(C) and approval of General Manager.

Page 36: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 36 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

36

4. The limit for varying quantities for minor value items shall be 100% (as against

25% prescribed for other items). A minor value item for this purpose is defined as

an item whose original agreement value is less than 1% of the total original

agreement value.

5. No such quantity variation limit shall apply for foundation items.

6. As far as SSR/SOR items are concerned, the limit of 25% would apply to the

value of SSR/SOR schedule as a whole and not on individual SSR/SOR items.

However, in case of NS items, the limit of 25% would apply on the individual

items irrespective of the manner of quoting the rate (single percentage rate or

individual item rate).

7. For the tenders accepted at the Zonal Railways level, variations in the quantities

will be approved by the authority in whose powers revised value of the agreement

lies.

8. For tenders accepted by General Manager, variations upto 125% of the original

agreement value may be accepted by General Manager.

9. For tenders accepted by Board Members and Railway Ministers variations upto

110% of the original agreement value may be accepted by General Manager

10. The aspect of vitiation of tender with respect to variation in quantities should be

checked and avoided. In case of vitiation of the tender (both for increase as well as

decrease of value of contract agreement) sanction of the competent authority as per

single tender should be obtained.

11. In cases where decrease is involved during execution of contract:

a. The contract signing authority can decrease the items upto 25% of

individual item without finance concurrence.

b. For decrease beyond 25% for individual items or 25% of contract

agreement value, the approval of an officer not less than rank of S.A.

Grade may be taken, after obtaining „No claim certificate‟ from the

contractor and with finance concurrence giving detailed reasons for each

such decrease in the quantities.

c. It should be certified that the quantities proposed to be reduced will not be

required in the same work at a later stage

d. In the event of any reduction in the quantity to be executed for any reasons

whatsoever, the contractor shall not be entitled to any compensation but

shall be paid only for the actual amount of work done.

e. The contractor is bound to notify the Engineer at least seven days before the

necessity arises for the execution of any item in excess of 25% of the over

all value of the agreement.

12. In case the contractor fails to attend the meeting after being notified to do so or in

the event of no settlement being arrived at, the Railway shall be entitled to execute

the extra works by other means and the contractor shall have no claim for loss or

damage that result from such procedure

Page 37: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 37 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

37

12. Employment of Civil Engineering Graduates/Diploma-holders:

The contractor shall employ the following technical staff during the execution of this work.

i) One graduate engineer when the cost of the work to be executed is Rs.2 Crores and

above.

ii) One qualified diploma holder (over-seer) when the cost of the work to be executed is

more than Rs.25 lakhs but less than Rs.2 Crores. Technical staff should be available at

site whenever required by the Engineer-in-charge to take instructions. In case the

contractor fails to employ the technical staff as aforesaid, he shall be liable to pay a

reasonable amount not exceeding a sum of Rs.40,000/- (forty thousand only) for each

month of default in case of graduate engineer and Rs.25,000/- (twenty five thousand

only) for each month of default in case of diploma holder (over-seer)

(Modification of Cl.26 and introduction of new Cl.26A to IR‟s GCC Ref: Rly. Bd.

Lr.No.2012/CE-I/CT/0/20, dt.10.05.2013.)

The decision of the Engineer-in-charge as to the period for which the required technical staff

was not employed by the contractor and as to the reasonableness of the amount to be deducted

on this account shall be final and binding on the contractor.

iii) Individuals having Diploma in Railway Engineering awarded by IPWE (India) shall also

be considered as qualified Diploma holder Engineers and contractors for track contract

works can employ such individuals at their worksite on Indian Railways.

(Ref: Rly. Bd. Lr.No.2012/CE-I/CT/0/20, dt.12.07.2013.)

Note: The above clause is not applicable for contracts for Welding of Rail joints.

13. Railway Contractors / Extension of Provident Fund Act to the Employees working under

Railway Contractors:-

The Contractor shall comply with the provisions of EPF & MP Act, 1952 and obtain code

number from the concerned authorities whenever workmen employed by him are 20 or more.

He shall also indemnify Railways from and against any claim, penalties, recoveries under the

above Act and Rules. Contractors to get the code number under the EPF so as to enable the PF

Commissioners to extend the social security benefits to the workmen engaged by the Railway

contractors. The first month‟s bill will be released only after code number is taken from the PF

Office and a copy of coverage intimation produced. Subsequently for each month, bills will be

released only on submission of challans & 12 A monthly return copy in proof of remittance of

PF dues for previous month.”

14. Conservancy charges as applicable and as modified from time to time will be recovered

from Contractor‟s running bills.

Page 38: Tender No. 07/Bridges/2013 07-BR-13 uploding.pdfTender No. 07/Bridges/20132 Signature of Contractor(s) Page 2 of 38 BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013

Tender No. 07/Bridges/2013

Signature of Contractor(s) Page 38 of 38

BZA Divn., SCR, T.No.07/Bridges/2013 invited vide Open Tender No.DRM/Works/BZA/11/2013 dt.02.09.2013,

date of opening on 09.10.2013 for the work of “Provision of Standard Height gauges of Road under bridges in

ADEN/Br/S/BZA Section and Provision of Standard Height gauges at Road under bridges.”

38

SPECIAL CONDITIONS

MODIFICATION TO CLAUSE 63 & 64 OF

GENERAL CONDITIONS OF CONTRACT

1. The Provision of Clause 63 and 64 of the General Conditions of Contract will be

applicable only for settlement of claims /disputes, for values less than or equal to

20% of the original value (excluding the cost of materials supplied free by

Railway) of the contract or 20% of the actual value of the work done (excluding the

value of the work rejected) under the contract whichever is less. When

claims/disputes are of value more than 20% of the value of the original contract or

20% of the value of the actual work done under the contract, whichever is less, the

contractor will not be entitled to seek such disputes/claims for reference to

arbitration and the provisions of Clause No; 63 &64 of the General Conditions of

Contract will not be applicable for referring the disputes to be settled through

arbitration

2. The Contractor shall furnish his monthly statement of claims as per Clause 43(1) of

General Conditions of Contract. But the Contractor should seek reference to

arbitration to settle the disputes only once, subject to the conditions as per Para 1

3. The Special conditions shall prevail over the existing Clause 63 & 64 of General

Conditions of contract