TENDER DOCUMENTS CONTRACT NO. 2019-026 Powerhouse …

117
TENDER DOCUMENTS CONTRACT NO. 2019-026 Powerhouse Springs Production Well Pump and Piping Installation Closing: 2:00 p.m., Wednesday July 24, 2019 District of Squamish 37955 2nd Avenue Squamish, BC V8B 0A3 June 2019 District of Squamish

Transcript of TENDER DOCUMENTS CONTRACT NO. 2019-026 Powerhouse …

TENDER DOCUMENTS

CONTRACT NO. 2019-026

Powerhouse Springs Production Well – Pump and Piping Installation

Closing: 2:00 p.m., Wednesday July 24, 2019

District of Squamish 37955 2nd Avenue

Squamish, BC V8B 0A3

June 2019 District of Squamish

ToC District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

TABLE OF CONTENTS Page No. INVITATION TO TENDERERS INV TENDERERS CHECKLIST TC INSTRUCTIONS TO TENDERERS – Part I

1. Introduction IT – Part I, Pages 1 2. Tender Documents IT – Part I, Pages 1-2 3. Submission of Tenders IT – Part I, Page 2 4. Additional Instructions IT – Part I, Pages 2-5

SUPPLEMENTARY INSTRUCTIONS TO TENDERERS – Part II IT – Part II, Pages 1-2 FORM OF TENDER

1. Items 1 to 8 FT – Pages 1-4 2. Appendix 1 – Schedule of Quantities and Prices FT – Pages 5-8 3. Appendix 2 – Preliminary Construction Schedule FT – Page 9 4. Appendix 3 – Experience of Lead Personnel FT – Page 10 5. Appendix 4 – Comparable Work Experience FT – Page 11 6. Appendix 5 – Subcontractors FT – Page 12

AGREEMENT

1. Agreement between Owner and Contractor AGT – Pages 1-4 2. Schedule 1 – Schedule of Contract Documents AGT – Page 5

SUPPLEMENTARY GENERAL CONDITIONS SGC – Pages 1-4 SUPPLEMENTARY CONTRACT SPECIFICATIONS SCS EXISTING WELL LOG STANDARD DOCUMENTS – NOT SUPPLIED

MMCD (Volume II, Platinum Edition)

INV District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

Invitation to Tenderers

Contract: Powerhouse Springs Production Well – Pump and Piping Installation Contract No: 2019-026 The District of Squamish invites tenders for the construction of a watermain connecting to the existing well and existing watermain, flowmeter chamber and appurtenances, and connection to the existing air release valve at their Powerhouse Springs Well Field. The work includes, but is not necessarily limited to, the following:

Supply and install well station components, including, submersible well pump, piping, valving and electrical components;

Install electrical kiosk (owner supplied kiosk shell);

Supply and install watermain including flowmeter chamber and appurtenances; and

Connect to existing air release valve. The tender is being issued electronically through the BC Bid website (www.bcbid.gov.bc.ca) where any interested party may download the tender documents directly. All addenda or further information will be published on the BC Bid website. It is the sole responsibility of the Tenderer to monitor the website regularly to check for updates. Sealed tenders, clearly marked “CONFIDENTIAL – District of Squamish, Tender for Contract No. 2019-026, Powerhouse Springs Production Well”, must be delivered by hand, either personally or by courier, to: Engineering Department District of Squamish 37955 2nd Avenue Squamish, BC V8B 0A3 Note: Any tender received by the District by mail, email, facsimile or any other means, will be automatically rejected. Tenders must be accompanied by the specified 10% Bid Bond and Consent of Surety. Tender closing time and date: 2:00 p.m. local time, Wednesday, July 24, 2019. There will not be a public tender opening. The lowest or any tender may not necessarily be accepted. Please direct all enquiries, via email, to Anthony Jeffery, Procurement Manager, District of Squamish, [email protected].

The deadline for receiving enquiries is 10:00 a.m., Wednesday, July 17, 2019.

TC District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

Tenderers Checklist

BEFORE SUBMITTING YOUR TENDER, CHECK THE FOLLOWING POINTS:

Item Page Complete ()

Addenda Acknowledged FT 1

Tender Address FT 4

Tenderer Signature and Name Printed FT 4

GST Registration Number FT 4

Appendix 1 – Schedule of Quantities and Prices FT 5-7

Appendix 2 – Preliminary Construction Schedule FT 8

Appendix 3 – Experience of Lead Personnel FT 9

Appendix 4 – Comparable Work Experience FT 10

Appendix 5 – Subcontractors FT 11

Tenderer’s Initials FT 1-11

Bid Bond

Consent of Surety

NOTE: This list is not guaranteed to be complete. It is the Tenderers responsibility to ensure that the tender submission is complete and properly bound or stapled.

IT – Part I District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

Instructions to Tenderers – Part I

IT – Part I, Page 1 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

Instructions to Tenderers – Part I

TO BE READ WITH “INSTRUCTIONS TO TENDERERS - PART II” CONTAINED IN THE PLATINUM EDITION OF THE PUBLICATION “MASTER MUNICIPAL CONSTRUCTION DOCUMENTS” SPECIFIED IN ARTICLE 2.2 BELOW. District of Squamish Contract: Powerhouse Springs Production Well – Pump and Piping Installation Contract No.: 2019-026

Introduction 1. 1.1

These instructions apply to and govern the preparation of tenders for this Contract. The work includes, but is not necessarily limited to, the following:

Supply and install well station components, including, submersible pump, piping, valving and electrical components;

Supply and install watermain including flowmeter chamber and appurtenances; and

Connect to existing air release valve.

1.2 Direct all enquiries regarding the Contract to: Anthony Jeffery, Procurement Manager District of Squamish

Phone: 604-815-5094 Email: [email protected] The deadline for receiving enquiries is 10:00 a.m., Wednesday, July 17, 2019. The District reserves the right not to respond to any enquiries received after the deadline date.

Tender Documents

2 2.1

The tender documents, which a Tenderer should review to prepare a tender, consist of all of the Contract Documents listed in Schedule 1 entitled “Schedule of Contract Documents”. Schedule 1 is attached to the Agreement which is included as part of the tender package.

IT – Part I, Page 2 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

2.2 A portion of the Contract Documents are included by reference. Copies of these documents have not been included with the tender package. These documents are the Instructions to Tenderers - Part II, General Conditions, Specifications and Standard Detail Drawings. They are those contained in the publication entitled “Master Municipal Construction Documents, Volume II, Platinum Edition – General Conditions, Specifications and Standard Detail Drawings”. Refer to Schedule 1 to the Agreement or, if not specified in Schedule 1, then the applicable edition shall be the most recent edition as of the tender closing date.

2.3 Any additional information made available to Tenderers prior to the tender closing time by the Owner or representative of the Owner, such as geotechnical reports or as-built plans, which is not expressly included in Schedule 1 to the Agreement, is not included in the Contract Documents. Such additional information is made available only for the assistance of Tenderers who must make their own judgment about its reliability, accuracy, completeness and relevance to the Contract, and neither the Owner nor any representative of the Owner gives any guarantee or representation that the additional information is reliable, accurate, complete or relevant.

Submission of Tenders

3 3.1

Sealed tenders, clearly marked “CONFIDENTIAL – District of Squamish, Tender for Contract No. 2019-026, Powerhouse Springs Production Well, must be delivered by hand, either personally or by courier, to office of:

Anthony Jeffery, Procurement Manager

Tender Closing Time: 2:00 p.m., local time

Tender Closing Date: July 24, 2019 at

Address: District of Squamish 37955 2nd Avenue Squamish, BC V8B 0A3 Note: Any tender received by the District by mail, email, facsimile or any other means, will be automatically rejected. There will not be a public tender opening.

3.2 Late tenders will not be accepted or considered and will be returned unopened.

3.3 It will be the Tenderers responsibility to ensure that the tender is complete and the tender should be bound or stapled.

Additional Instructions to Tenderers

4 4.1

All construction layouts will be provided by the Contractor. Digital files will be provided for layout purposes.

IT – Part I, Page 3 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

4.2 All materials and density testing, including granular materials, concrete, asphalt and compaction tests, will be arranged by and paid for full by the Contractor. The Contractor is responsible for ensuring all materials meet MMCD specifications. Where initial tests fail and subsequent testing is deemed necessary by the Contract Administrator, the cost of the subsequent testing will be the responsibility of the Contractor.

4.4 Completing the Form of Tender The submitted Form of Tender must be legible, written in ink, or by typewriter and ALL ITEMS MUST BE BID, unless the Form of Tender specifically permits otherwise, with the price for every item and other extras clearly shown. Each page must be initialed by the Tenderer. The Tenderer shall be deemed to have satisfied itself as to the sufficiency of its tender for the work and of the unit and lump sum prices stated in the Form of Tender. These unit prices shall cover all its costs including overhead, profit and tax, except for the Goods and Services Tax as explained in the following paragraphs of this section, for carrying out the works and its obligations under this Contract. The District will not be responsible for any cost incurred by the Tenderer in preparing the tender. A PDF with the complete tender documents will be provided for download form www.bcbid.gov.bc.ca. The Contractor can download, print, complete and submit the Form of Tender, in accordance with the Instructions to Tenderers. Addenda will be available for download at www.bdbid.gov.bc.ca. It will be the bidder’s responsibility to obtain any and all addenda on BC Bid and to acknowledge receipt of addenda in the Form of Tender (page 1). The “Amount” column shall be totaled in groups of items as shown and each total for a group of items shall be carried to the Summary Sheet for insertion in the appropriate place. The totals for all groups of items shall be added to give the Total Tender Price. Goods and Services tax of 5% shall be calculated separately and then added to arrive at the Total Tender Price, including GST. The Tenderers attention is drawn to MMCD, Volume II, Instructions to Tenderers, Part II Section 5-18 for Tender Requirements, Qualifications Modifications, Alternative Tenders, Approved Equals, Inspection of the Place of Work, Interpretation of Contract Documents, Prices, Taxes and Amendment of Tenders, Duration of Tenders, Qualification of Tenderers, Award, Subcontractor and Optional Work and as amended below.

IT – Part I, Page 4 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

4.5

Right to Accept or Reject Tenders The Owner reserves the right to reject any or all tenders or to accept any tender should it be deemed in the interest of the Owner to do so. The lowest tender will not necessarily be accepted (refer to Supplementary Instructions to Tenderers, Award IT – Part II, Page 2). The Owner will be the sole judge of such matters. Any tender considered to be unbalanced may be rejected by the Owner. Without limiting the generality of the foregoing, any tender may be disqualified or rejected which is incomplete, obscure or irregular, which had erasures or corrections in the Form of Tender, in which prices are omitted or which has an insufficient or irregular Surety. Award of Contract is subject to funds being legally available for the project.

4.6 Disposal Site The Contractor is responsible for the provision of all offsite disposal sites for materials that are to be removed from the construction sites in this Contract. The Contractor is responsible for all fees, permits and costs associated with the offsite disposal. The Contractor is responsible for ensuring that the chosen disposal site will accept the material to be removed and will coordinate all necessary environmental or geotechnical sign-offs required to facilitate said approval.

4.7 Substantial Performance and Working Days The Contractor shall schedule the Work under this contract to be completed within forty (40) Days, between issuance of Notice to Proceed and Substantial Performance. The Contractor will be assessed for Inspection charges at a rate of $1000.00 per day for Days used beyond forty (40) Days (as defined in Supplementary General Condition 13.8, included in this document). Additional inspection charges will be deducted from monthly progress payments for days on site beyond forty (40) Days.

4.8 Schedule of Quantities and Prices To be read in conjunction with MMCD, Volume II, Instructions to Tenderers, Part II Section 10 Platinum Edition. It is the responsibility of the Tenderer to include in the tender, sufficient amounts to cover the cost of work and materials not listed in the Schedule of Quantities, but indicated in the plans and/or specifications by either direct mention or implication. All such amounts shall be distributed amongst the major items of the Contract. The cost of a general nature that does not pertain to any items, shall be prorated among all items. Claims for extra payment will not be considered on the grounds that the work performed or the material supplied could not be properly changed to the items listed in the Schedule of Quantities and Prices.

IT – Part I, Page 5 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

4.9 Construction Milestone Dates The Contractor shall schedule its works to meet the following milestone dates:

Substantial Performance – within 40 Days from Notice to Proceed.

Well pumping tests are to be completed after September 15 2019 when the District’s water demand is decreasing from the summer months.

4.10 Pre-locate Utilities

Pre-locates of existing infrastructure crossings must be completed

by the Contractor in advance of construction and notification

provided to the Contract Administrator of any conflicts. No claims

for delay or other impacts will be accepted by the Contract

Administrator or the Owner that arise as a result of not thoroughly

completed pre-locates of all existing utilities and adequately

protecting existing utilities. Pre-locates are to be preceded by BC

One Call and DIG Shaw.

4.11 Site Photographs

The Contractor is responsible to take pre-construction photographs

prior to the commencement of work. The Contractor shall submit

copies of the photographs in digital format to the Owner and to the

Contract Administrator.

4.12 Business Licence

The Contractor and all sub-contractors shall have or obtain a

business license with the District of Squamish in accordance with

Bylaw No. 2455, 2016, The Contractor and all sub-contractors shall

be in possession of a business license prior to the start of any work.

IT – Part II District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

Supplementary Instructions to Tenderers – Part II

IT – Part II, Page 1 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

Supplementary Instructions to Tenderers – Part II

TO BE READ WITH “INSTRUCTIONS TO TENDERERS - PART II” CONTAINED IN THE PLATINUM EDITION OF THE PUBLICATION “MASTER MUNICIPAL CONSTRUCTION DOCUMENTS”.

These Supplementary Instructions to Tenderers modify the MMCD Instructions to Tender Part II in the following sections:

IT Paragraph Title 5 2 Tender Requirements (Delete clause 5.2 and replace with):

A tender must be accompanied by a tender security ("Bid Security") in the form of: A bid bond issued by a surety licensed to carry out the business of suretyship in British Columbia in a form reasonably satisfactory to the Owner in an amount equal to ten percent (10%) of the total Tender Price, including GST. A cash, bank draft or letter of credit will not be acceptable.

5 4 Tender Requirements Replace “15 Days” with “5 Days”.

5 5 Tender Requirements (Add new clause 5.5 as follows): The Tenderer shall submit, as part of the tender, a Consent of Surety, issued by a surety licensed to carry on the business of suretyship in British Columbia, in a form satisfactory to the Owner. The Consent of Surety is to guarantee that a performance bond and a labour and material payment bond, each equal to fifty percent (50%) of the total tender price, plus GST, as per the Form of Tender - Appendix 1, be issued by the bonding company in accordance with paragraph 5.1.1(a) of FT – Page 2.

5 6 Tender Requirements (Add new clause 5.6 as follows): Any Force Account rates/schedules, submitted as part of the tender will be disregarded.

7 5 Approved Equals (Add new clause 7.5 as follows): The deadline for receiving enquiries, and/or request for approvals is July 17, 2019. The District reserves the right not to respond to any requests for Approved Equals received after the deadline date.

9 1 Interpretation of Contract Documents

(Delete clause 9.1 and replace with): If a Tenderer is in doubt as to the correct meaning of any provision of the Contract Documents, the Tenderer may request clarification before the deadline, as per 7.5, for enquiries found in and from the person named in paragraph 1.2 of the Instructions to Tenderers – Part I.

IT – Part II, Page 2 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

15 3 Award (Delete clause 15.3 and replace with):

The Owner will, following receipt of an acceptable tender, issue in writing a Notice of Award to the successful Tenderer. This notice will be given as soon as possible following the closing of tenders and, unless otherwise agreed to by the Tenderer, not later than sixty (60) days following the closing of tenders. The Tenderer acknowledges and agrees that the Owner will not be responsible for any costs, expenses, losses, damages or liability incurred by the Tenderer as a result of or arising out of submitting a tender for the proposed contract, or due to the Owner’s acceptance or non-acceptance of its tender.

FT District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

Form of Tender

FT – Page 1 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

MMCD – JANUARY 1996 (REV. 2009) Tenderer’s Initials:_

FORM OF TENDER

District of Squamish Contract: Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026 TO OWNER: 1 WE, THE UNDERSIGNED:

1.1 have received and carefully reviewed all of the Contract

Documents, including the Instructions to Tenderers, the specified edition of the “Master Municipal Construction Documents - General Conditions, Specifications and Standard Detail Drawings” and the following Addenda:

_______________________________________________ _______________________________________________ _______________________________________________; (Addenda, if any)

1.2 have full knowledge of the Place of the Work and the Work

required; and

1.3 have complied with the Instructions to Tenderers.

2 ACCORDINGLY WE HEREBY OFFER: 2.1 to perform and complete all of the Work and to provide all

the labour, equipment and material all as set out in the Contract Documents, in strict compliance with the Contract Documents;

2.2 to achieve Substantial Performance of the Work within forty (40) Days from the receipt of the Notice to Proceed; and

2.3 to complete the Work for the price, which is the sum of the products of the actual quantities incorporated into the Work and the appropriate unit prices set out in Appendix 1, the “Schedule of Quantities and Prices”, plus any lump sums or specific prices and adjustment amounts as provided by the Contract Documents. For the purposes of tender comparison, our offer is to complete the Work for the “Tender Price” as set out on Appendix 1 of this Form of Tender. Our Tender Price is based on the estimated quantities listed in the Schedule of Quantities and Prices, and excludes GST.

3 WE CONFIRM: 3.1 that we understand and agree that the quantities as listed in

the Schedule of Quantities and Prices are estimated, and that the actual quantities will vary.

FT – Page 2 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

MMCD – JANUARY 1996 (REV. 2009) Tenderer’s Initials:_

4 WE CONFIRM:

4.1 that the following appendices are attached to and form a

part of this tender:

4.1.1 the appendices as required by paragraph 5.3 of the Instructions to Tenderers - Part II;

4.1.2 the Bid Security as required by paragraph 5.2 of the

Instructions to Tenderers - Part II; and

4.1.3 the Consent of Surety as required by paragraph 5.5 of the Instructions to Tenderers - Part II.

5 WE AGREE:

5.1 that this tender will be irrevocable and open for acceptance

by the Owner for a period of 60 days from the day following the Tender Closing Date and Time, even if the tender of another Tenderer is accepted by the Owner. If within this period the Owner delivers a written notice (“Notice of Award”) by which the Owner accepts our tender, we will:

5.1.1 within 5 Days of receipt of the written Notice of

Award deliver to the Owner:

a) a Performance Bond and a Labour and Material Payment Bond, each in the amount of 50% of the Contract Price, covering the performance of the Work, including the Contractor’s obligations during the Maintenance Period, issued by a surety licensed to carry on the business of suretyship in the province of British Columbia, and in a form acceptable to the Owner;

b) a Construction Schedule, as provided by GC

4.6.1;

c) a “clearance letter” indicating that the Tenderer is in WORKSAFE BC compliance;

d) a copy of the insurance policies as specified in

GC 24 indicating that all such insurance coverage is in place;

e) a copy of District of Squamish business

license as specified in IT – Part 1, 4.12;

5.1.2 within 2 Days of receipt of written “Notice to Proceed”, or such longer time as may be otherwise specified in the Notice to Proceed, commence the Work; and

5.1.3 sign the Contract Documents as required by GC

FT – Page 3 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

MMCD – JANUARY 1996 (REV. 2009) Tenderer’s Initials:_

2.1.2.

6 WE AGREE: 6.1 that, if we receive written Notice of Award of this Contract

and, contrary to paragraph 5 of this Form of Tender, we:

6.1.1 fail or refuse to deliver the documents as specified by paragraph 5.1.1 of this Form of Tender; or

6.1.2 fail or refuse to commence the Work as required by the Notice to Proceed,

then such failure or refusal will be deemed to be a refusal by us to

enter into the Contract and the Owner may, on written notice to us, award the Contract to another party. We further agree that, as full compensation on account of damages suffered by the Owner because of such failure or refusal, the Bid Security shall be forfeited to the Owner, in an amount equal to the lesser of:

6.1.3 the face value of the Bid Security; or

6.1.4 the amount by which our Tender Price is less than the amount for which the Owner contracts with another party to perform the Work.

FT – Page 4 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

MMCD – JANUARY 1996 (REV. 2009) Tenderer’s Initials:_

7 OUR ADDRESS is as follows:

______________________________________________________

______________________________________________________

______________________________________________________

Phone: ______ ______ - ________ Fax: ______ ______ - ________ Attention: ____________________________________ Email: ____________________________________

This tender is executed this _____ day of _______________, 20 ____.

Contractor: _____________________________________________________ (FULL LEGAL NAME OF CORPORATION, PARTNERSHIP OR INDIVIDUAL)

______________________________________________________ (AUTHORIZED SIGNATORY)

______________________________________________________ (Print Name)

______________________________________________________ (AUTHORIZED SIGNATORY)

______________________________________________________ (Print Name)

_____________________________ (GST Registration Number)

8 WE CONFIRM: 8.1 our Goods and Services Tax Registration status is as follows: 8.1.1 for information purpose, our Goods and Services Tax registration number is: __________________________________________________ (GST REGISTRATION NUMBER)

or; 8.1.2 by signature hereunder, we certify we are not required to provide a registration number: ___________________________________________________ (AUTHORIZED SIGNATURE)

FT – Page 5 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

MMCD – JANUARY 1996 (REV. 2009) Tenderer’s Initials:_

Form of Tender – Appendix 1

Powerhouse Springs Production Well – Pump and Piping Installation

SCHEDULE OF QUANTITIES AND PRICES

(See paragraph 5.3.1 of the Instructions to Tenderers - Part II) (All prices and Quotations including the Contract Price shall include all Taxes, but shall

not include GST. GST shall be shown separately.)

Summary Sheet

Description / Task

1 General Requirements $

2 Mechanical $

3 Electrical $

4 Utilities $

5 Optional Work $

TENDER PRICE $

GST (5%) $

TOTAL TENDER PRICE, INCLUDING GST $

FT – Page 6 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

MMCD – JANUARY 1996 (REV. 2009) Tenderer’s Initials:_

Form of Tender – Appendix 1

Powerhouse Springs Production Well – Pump and Piping Installation

SCHEDULE OF QUANTITIES AND PRICES

S means there is a Supplementary Contract Specification (SCS)

1 General Requirements

Item MMCD

Ref. Description Unit Quantity Unit Price Amount

1 Bonding/ Insurance (Actual Cost + 10%) Lump Sum 1

2 Traffic Regulation, Environmental Protection,

Temporary Facilities, Project Record Documents Incidental to Contract

SECTION 1 SUBTOTAL Carry forward to Summary Sheet

2 Mechanical

Item MMCD Ref. Description Unit Quantity Unit Price Amount

3 Flowmeter Lump Sum 1

4 Steel Piping – flowmeter chamber Lump Sum 1

5 Steel Piping – well riser pipe Lump Sum 1

6 Appurtenances incl. riser pipe check valve Lump Sum 1

7 Peerless Vertical – 14MC 2 Stages Submersible

Pump (including motor) Lump Sum 1

SECTION 2 SUBTOTAL Carry forward to Summary Sheet

3 Electrical

This section is broken out for Tendering purposes only and includes all work listed in the Division 26 Electrical Specifications.

Item MMCD Ref. Description Unit Quantity Unit Price Amount

8 Electrical Lump Sum

1

SECTION 3 SUBTOTAL Carry forward to Summary Sheet

FT – Page 7 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

MMCD – JANUARY 1996 (REV. 2009) Tenderer’s Initials:_

4 Utilities

Item MMCD

Ref. Description Unit Quantity Unit Price Amount

Waterworks

9 33 11 01

1.8.2 250 mm dia. PVC Pipe

Linear Metre

7

10 33 11 01

1.8.2 25 mm dia. ARV Connection

Lump Sum

1

11 33 11 01

1.8.3 250 mm dia. 45 deg. Bend

HxH45 deg. bend Each 2

12 33 11 01

1.8.3 250 mm dia. X 200 mm dia. Reducer

H x F Reducer Each 1

13 33 11 01

1.8.3 250 mm dia. Restrained Coupling Each 1

14 33 11 01

1.8.3 200 mm dia. Coupling

PVC DR18 to FL/PE Steel Pipe Each 1

15 33 11 01

1.8.3 250 mm dia. Valve

GV HxH Each 2

16 33 11 01

1.8.3 200 mm dia. Dismantling joint

Each 1

17 33 11 01

1.8.3 150 mm dia. Valve

GV FxF Each 1

18 33 11 01

1.8.3 150 dia Sch 40 standpipe c/w cap and sample tap Each 1

19 33 11 01

1.8.3 250 mm dia. Valve

GV HxH Each 1

20 33 11 01

1.8.9 Concrete thrust blocks

Cubic Metre

2

21 33 11 01 1.8.13

Tie-in to existing 250 mm watermain Pipework by contractor

Each 1

22 33 11 01

1.8.3 250 mm dia. cap Each 1

Manholes and Catchbasins

23 33 44 01 1500 mm dia. Manhole

c/w Dobney C22 Frame, Ring and Cover Each 1

SECTION 7 SUBTOTAL Carry forward to Summary Sheet

Optional Work

Well Decommissioning

Item Ref. Description Unit Quantity Unit Price Amount

24 15900 Decommission Existing Well Lump Sum

1

FT – Page 8 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

MMCD – JANUARY 1996 (REV. 2009) Tenderer’s Initials:_

Form of Tender – Appendix 2

Powerhouse Springs Production Well – Pump and Piping Installation PRELIMINARY CONSTRUCTION SCHEDULE (Refer to paragraph 5.3.2 of the Instructions to Tenderers – Part II) INDICATE PRELIMINARY SCHEDULE, AS PER 5.3.2, WITH BAR CHART, INCLUDING MAJOR TASK DESCRIPTIONS AND TIME, AS PER GC 4.6.1. MILESTONE DATE(s): __________________________ __________________________ __________________________

ACTIVITY CONSTRUCTION SCHEDULE (WEEKS)

1 2 3 4 5 6 7 8 9 10

FT – Page 9 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

MMCD – JANUARY 1996 (REV. 2009) Tenderer’s Initials:_

Form of Tender – Appendix 3

Powerhouse Springs Production Well – Pump and Piping Installation

EXPERIENCE OF LEAD PERSONNEL (See paragraph 5.3.3 of the Instructions to Tenderers – Part II)

Name:

Experience:

Dates:

Project Name:

Responsibility:

References:

Dates:

Project Name:

Responsibility:

References:

Dates:

Project Name:

Responsibility:

References:

FT – Page 10 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

MMCD – JANUARY 1996 (REV. 2009) Tenderer’s Initials:_

Form of Tender – Appendix 4

Powerhouse Springs Production Well – Pump and Piping Installation

COMPARABLE WORK EXPERIENCE (See paragraph 5.3.4 of the Instructions to Tenderers – Part II)

PROJECT

OWNER / CONTACT NAME

PHONE and FAX WORK

DESCRIPTION VALUE ($)

Owner / Contract

Phone ( ) Email

Owner /

Contract

Phone ( ) Email

Owner /

Contract

Phone ( ) Email

Owner / Contract

Phone ( ) Email

Owner /

Contract

Phone ( ) Email

Owner /

Contract

Phone ( ) Email

Owner /

Contract

Phone ( ) Email

Owner / Contract

Phone ( ) Email

Owner /

Contract

Phone ( ) Email

Owner /

Contract

Phone ( ) Email

Owner /

Contract

Phone ( ) Email

FT – Page 11 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

MMCD – JANUARY 1996 (REV. 2009) Tenderer’s Initials:_

Form of Tender – Appendix 5

Powerhouse Springs Production Well – Pump and Piping Installation SUBCONTRACTORS (See paragraph 5.3.5 of the Instructions to Tenderers – Part II)

TENDER ITEM TRADE SUBCONTRACTOR NAME PHONE NUMBER

AGT District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

Agreement

AGT – Page 1 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

Agreement Between Owner and Contractor THIS AGREEMENT made in duplicate this day of , 20____. Contract: Powerhouse Springs Production Well – Pump and Piping Installation Contract No.: 2019-026 BETWEEN: District of Squamish 37955 2nd Avenue Squamish, BC V8B 0A37 (the “Owner”) AND: ________________________________________________________________________ ________________________________________________________________________ ________________________________________________________________________ (the “Contractor”) The Owner and the Contractor agree as follows: ARTICLE 1 THE WORK – START/COMPLETION DATES 1.1 The Contractor will perform all Work and provide all labour, equipment and material and do

all things strictly as required by the Contract Documents. 1.2 The Contractor will commence the Work in accordance with the Notice to Proceed. The

Contractor will proceed with the Work diligently, will perform the Work generally in accordance with the construction schedules as required by the Contract Documents and will achieve Substantial Performance of the Work within forty (40) Days subject to the provisions of the Contract Documents for adjustments to the Contract Time.

1.3 Time shall be of the essence of the Contract.

AGT – Page 2 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

ARTICLE 2 CONTRACT DOCUMENTS 2.1 The “Contract Documents” consist of the documents listed or referred to in Schedule 1,

entitled “Schedule of Contract Documents”, which is attached and forms a part of this Agreement, and includes any and all additional and amending documents issued in accordance with the provisions of the Contract Documents. All of the Contract Documents shall constitute the entire Contract between the Owner and the Contractor.

2.2 The Contract supersedes all prior negotiations, representations or agreements, whether

written or oral, and the Contract may be amended only in strict accordance with the provisions of the Contract Documents.

ARTICLE 3 CONTRACT PRICE 3.1 The price for the Work (“Contract Price”) shall be the sum in Canadian dollars of the

following: 3.1.1 the product of the actual quantities of the items of Work listed in the Schedule of

Quantities and Prices which are incorporated into or made necessary by the Work and the unit prices listed in the Schedule of Quantities and Prices; plus

3.1.2 all lump sums, if any, as listed in the Schedule of Quantities and Prices, for items r

elating to or incorporated into the Work; plus 3.1.3 any adjustments, including any payments owing on account of Changes and

agreed to Extra Work, approved in accordance with the provisions of the Contract Documents.

3.2 The Contract Price shall be the entire compensation owing to the Contractor for the Work

and this compensation shall cover and include all profit and all costs of supervision, labour, material, equipment, overhead, financing, and all other costs and expenses whatsoever incurred in performing the Work.

ARTICLE 4 PAYMENT 4.1 Subject to applicable legislation and the provisions of the Contract Documents, the Owner

shall make payments to the Contractor. 4.2 If the Owner fails to make payments to the Contractor as they become due in accordance

with the terms of the Contract Documents then interest calculated at 2% per annum over the prime commercial lending rate of the Royal Bank of Canada on such unpaid amounts shall also become due and payable until payment. Such interest shall be calculated and added to any unpaid amounts monthly.

ARTICLE 5 RIGHTS AND REMEDIES 5.1 The duties and obligations imposed by the Contract Documents and the rights and

remedies available thereunder shall be in addition to and not a limitation of any duties, obligations, rights and remedies otherwise imposed or available by law.

5.2 Except as specifically set out in the Contract Documents, no action or failure to act by the

Owner, Contract Administrator or Contractor shall constitute a waiver of any of the parties’ rights or duties afforded under the Contract, nor shall any such action or failure to act constitute an approval of or acquiescence in any breach under the Contract.

AGT – Page 3 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

ARTICLE 6 NOTICES 6.1 Communications among the Owner, the Contract Administrator and the Contractor,

including all written notices required by the Contract Documents, may be delivered by hand, fax, email or by pre-paid registered mail to the addresses as set out below:

The Owner: District of Squamish 37955 2nd Avenue Squamish, BC V8B 0A3 Fax: 604-892-1083 Attention: David Roulston Email: [email protected] The Contractor: ______________________________________________________________________________ ______________________________________________________________________________ ______________________________________________________________________________ Fax: _______ _______ - ___________ Attention: ____________________________________________ Email: ____________________________________________ The Contract Administrator: Onsite Engineering Ltd. 103-32310 South Fraser Way Abbotsford, BC V2T 1X1 Fax: 866-235-6943 Attention: Joel McAllister P.Eng Email: [email protected] 6.2 A communication or notice that is addressed as above shall be considered to have been

received: 6.2.1 immediately upon delivery, if delivered by hand; or 6.2.2 immediately upon transmission if sent and received by fax or email; or 6.2.3 after 5 Days from date of posting if sent by registered mail. 6.3 The Owner or the Contractor may, at any time, change its address for notice by giving

written notice to the other at the address then applicable. Similarly if the Contract Administrator changes its address for notice then the Owner will give or cause to be given written notice to the Contractor.

6.4 The sender of a notice by fax assumes all risk that the fax will be received properly, and the

provisions of paragraph 12.5 of the Instructions to Tenderers apply to the sender.

AGT – Page 4 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

ARTICLE 7 GENERAL 7.1 This Contract shall be construed according to the laws of British Columbia. 7.2 The Contractor shall not, without the express written consent of the Owner, assign this

Contract, or any portion of this Contract. 7.3 The headings included in the Contract Documents are for convenience only and do not

form part of this Contract and will not be used to interpret, define or limit the scope or intent of this Contract or any of the provisions of the Contract Documents.

7.4 A word in the Contract Documents in the singular includes the plural and, in each case,

vice versa. 7.5 This agreement shall ensure to the benefit of and be binding upon the parties and their

successors, executors, administrators and assigns. IN WITNESS WHEREOF the parties hereto have executed this Agreement the day and year first written above.

Contractor: (FULL LEGAL NAME OF CORPORATION, PARTNERSHIP OR INDIVIDUAL) (AUTHORIZED SIGNATORY)

(PRINT NAME)

(AUTHORIZED SIGNATORY)

(PRINT NAME)

Owner: District of Squamish (FULL LEGAL NAME OF OWNER) (AUTHORIZED SIGNATORY)

(PRINT NAME)

(AUTHORIZED SIGNATORY)

(PRINT NAME)

AGT – Page 5 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

Schedule 1 Schedule of Contract Documents The following is an exact and complete list of the Contract Documents, as referred to in Article 2.1 of the Agreement: NOTE: The documents noted with “*” are contained in the “Master Municipal Construction Document,

General Conditions, Specifications, Standard Detail Drawings and Instructions to Tenderers – Part II”, Platinum Edition dated January 1996 (Rev.2009) and all supplementary general conditions as approved by the MMCDA Board. All sections of this publication form part of the Contract Documents.

1. Agreement, including all Schedules; 2. Addendum No. (s): ; 3. Supplementary General Conditions; 4. General Conditions*; 5. Supplementary Contract Specifications; 6. Specifications*;

7. Standard Detail Drawings*; 8. Executed Form of Tender, including all Appendices; 9. Supplementary Instructions to Tenderers; 10. Instructions to Tenderers – Part I; and 11. Instructions to Tenderers – Part II*. 12.

1Government of British Columbia Standards and Best Practices for Instream Works

1 Available from: http://www.env.gov.bc.ca/wld/instreamworks/downloads/GeneralBMPs.pdf

SGC District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

Supplementary General Conditions

SGC – Page 1 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

SUPPLEMENTARY GENERAL CONDITIONS TABLE OF CONTENTS

Page

1 DEFINITIONS SGC 2

1.21 Contract Administrator SGC 2

1.51 Owner SGC 2

1.79 Utilities SGC 2

4 CONTRACTOR SGC 2

4.1 Construction Survey Layout SGC 2

4.9 Materials SGC 2

13 DELAYS SGC 3

13.9 Liquidated Damages for Late Completion SGC 3

18 PAYMENT SGC 3

18.2 Supporting Documentation SGC 3

18.4 Holdbacks SGC 3

20 LAWS, NOTICES, PERMITS and FEES SGC 3

20.4 Environmental Laws SGC 3

25 MAINTENANCE PERIOD SGC 4

25.1 Correction of Defects SGC 4

SGC – Page 2 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

District of Squamish Supplementary General Conditions

TO BE READ WITH “GENERAL CONDITIONS” CONTAINED IN THE PLATINUM EDITION OF THE PUBLICATION “MASTER MUNICIPAL CONSTRUCTION DOCUMENT” SPECIFIED IN SCHEDULE 1 OF THE AGREEMENT”.

GC Paragraph Title

1 21 Contract Administrator

Replace with: “Contract Administrator” shall be Onsite Engineering Ltd. as indicated in the Form of Agreement.

1 51 Owner Replace with: “Owner” shall mean District of Squamish or the authorized representative of the District of Squamish.

1 79 Utilities Add: “Utilities” mean public or private services and their appurtenances which include, but are not limited to, storm drains, sanitary sewers, watermains, street lighting and traffic signal systems, pipe lines, conduits, transmission lines, telephone, cablevision, gas and electrical systems.

4 1 Construction Survey Layout

(Add clause 4.1.3 as follows): The Contractor is responsible for all staking and survey layout required for the completion of all Work, as shown on the Drawings or as directed by the Contract Administrator, and to affect incidental field adjustments, such as staking of embankments and culverts to match post-stripping ground lines and actual field drainage patterns.

4 9 Materials (Add clause 4.9.3 as follows): The Contractor shall:

(1) Be responsible for storing all the materials supplied for the Work either by the Contractor or the Owner, in a matter which will prevent damage from the weather, dirt, foreign matter, vandalism and theft;

(2) Arrange for and/or verify the time of delivery of all materials to be supplied by the Contractor or the Owner to ensure that delivery will coincide with the Contractor’s work schedule.

(3) Replace all materials supplied by the Contractor or the Owner which are found to be stolen, missing or damaged while under the Contractor’s care; and

(4) Replace all materials found to be defective in manufacture which have been supplied by the Contractor.

13 9 Liquidated Damage for Late Completion

(Delete clause 13.9.1 (1) and replace with the following): as a genuine pre-estimate of the Owner’s increased costs for the Contract Administrator and the Owner’s own staff caused by such delay an amount of $1000.00 per day or pro rata portion for each Day that actual Substantial Performance is

SGC – Page 3 District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

achieved after the Substantial Performance Milestone Date; plus

18 2 Supporting Documentation

(Add clause 18.2.3 as follows): If requested in writing by the Contract Administrator, the Contractor shall provide the Contract Administrator, as a precondition of the Payment Certificate, a signed letter from each supplier and sub-contractor that all amounts relating to the Work, due and owning as of the end of the month covered by the Payment Certificate, have been paid.

20 4 Environmental Laws

(Add clause 20.4.2 as follows): The Contractor shall indemnify the Owner for any costs, fines, expenses and penalties that the Owner is required to pay on account of the Contractor performing the Work in breach of any applicable Federal or Provincial or Municipal environmental laws, regulations or orders.

25 1 Correction of Defects

(Add clause 25.1.4 as follows): Upon failure of the Contractor to perform the work in accordance with the Contract Documents, and after ten (10) days’ written notice to the Contractor, or without notice if an emergency or danger to the Work or public exists, the Owner may, without prejudice to any other remedy he may have, correct such deficiencies. The cost of work performed by the Owner in correction deficiencies shall be paid by the Contractor.

District of Squamish Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

Supplementary Contract Specifications

District of Squamish SCS – Page 1 Powerhouse Springs Production Well – Pump and Piping Installation Contract No. 2019-026

SUPPLEMENTARY CONTRACT SPECIFICATIONS

SUPPLEMENTARY SPECIFICATIONS, STANDARDS AND DETAIL DRAWINGS

The District of Squamish has adopted the Master Municipal Construction Documents – Volume II, Platinum Edition, published by The Master Municipal Construction Documents Association and printed in 2009 for use on all Engineering Department contracts. Development Works and Services shall be constructed in accordance with the MMCD Specifications and Standard Drawings as amended herein. To bring these Specifications in conformance with practices within the District, the following and additional clauses and Standard Drawings are to be considered part of the General Specifications and Standard Detail Drawings. These amendments take precedence of the Master Municipal Specifications. The following Supplemental Specifications are Included:

Section Title

Mechanical 15010 Mechanical General Requirements 15015 Work Summary 15100 Piping Systems 15160 Coatings 15420 Submersible Vertical Turbine Pumps 15900 Well Decommissioning Electrical 26 05 00 Common Work Results – Electrical 26 05 05 Electrical Demolition 26 05 10 Testing and Commissioning 26 05 20 Wire and Box Connectors 0-1000V 26 05 22 Connectors and Terminations 26 05 28 Grounding & Bonding 26 05 29 Hangers and Supports for Electrical Systems 26 05 31 Splitters, Junction, Pull Boxes and Cabinets 26 05 32 Outlet Boxes, Conduit Boxes and Fittings 26 05 34 Conduits, Conduit Fastenings and Conduit Fittings 26 05 44 01 Installation of Cables in Trenches and Ducts 26 27 15 Electrical and Controls Components 26 28 16 02 Moulded Case Circuit Breakers

District of Squamish Section 15015

Powerhouse Springs Production Well – Pump and Piping Installation

Work Summary

Contract No. 2019-026 Page 1 of 3

Section 15010 Mechanical General Requirements

1 General

1.1 Basic Requirements

1. All mechanical equipment and piping materials supplied under this Contract shall be new and of current

manufacture.

2. All workmanship shall be of the highest quality and sub-standard work will be rejected.

1.2 Familiarity with Project Requirements

1. The Contractor shall become familiar with all building plans including those of all sub-trades, and arrange

equipment with due regard to all architectural, structural and electrical fixtures.

2. The architectural, structural and electrical plans shall be consulted for final locations of walls, doors, equipment, etc.

3. The Contractor is warned that conflicts may be encountered and is advised to confirm the nature of the work required prior to submitting a tender.

4. No claim for additional work on the grounds that the Contractor did not anticipate actual requirements will be considered.

5. The Contractor shall be responsible for providing complete and workable systems as outlined in the specifications and on drawings. The Engineer will not recognize any sub-contractor as such, but will consider all persons engaged on the work to be under the control of the Contractor.

6. The Engineer will not, under any circumstances, enter into discussions concerning the responsibility of subtrades or the apportionment of work. No claim based on the division of work between specification sections will be considered.

7. The Contractor shall be responsible for site safety.

1.3 Permits and Inspection

1. The Contractor shall make himself fully acquainted with all codes and bylaws relating to the installation of

equipment. He shall obtain and pay for all permits required for the execution and inspection of his work and pay all charges relating to such permits.

1.4 Substitutions

1. Supply approved equipment exactly as indicated by the drawings and specifications. Tender shall be based

upon utilizing an approved manufacturer.

2. Alternate manufacturers will only be considered if offered as an option at time of tendering. Any reduction in cost shall be indicated at that time.

3. The acceptance of any such alternate manufacturer shall be at the option of the District.

4. Alternate materials may be substituted by the Contractor only if such substitutions have been approved in writing by the Engineer.

2 Products

2.1 Shop Drawings

District of Squamish Section 15015

Powerhouse Springs Production Well – Pump and Piping Installation

Work Summary

Contract No. 2019-026 Page 2 of 3

1. As soon as possible after the award of the Contract, but not later than fifteen (15) days, the Contractor shall

supply drawings illustrating external dimensions and major structural details for the (pumps, valves, fittings, piping) and all associated equipment to the Engineer for review.

2. In addition, supply a bill of material listing the significant items of mechanical equipment proposed shall be provided.

3. The materials used in the principal parts of the (pumps, valves, fittings, piping) and the materials specification to which these comply shall also be listed.

4. Wiring diagrams shall be supplied where applicable.

5. The reviewed drawings will be returned to the Contractor as an electronic file.

6. When submitting the required drawings and bill of material, the Contractor shall advise the Engineer in writing of any changes or exceptions therein to the specification or related drawings.

7. The Engineer will review the drawings or mark them with such corrections as are necessary and the submitted drawings and bill of material will be returned to the Contractor stamped "reviewed" or as otherwise pertinent.

8. Any attached comments provided by the Engineer regarding the submittal shall be forwarded by the Contractor to the appropriate supplier.

9. The Contractor shall allow at least 1 week for the Engineer to review shop drawings. Any manufacturing done before approval of the drawings by the Engineer will be at the Contractor's risk.

10. The review of the Contractor drawings and bill of material shall be for determining the general conformance of the equipment with the design concept and shall not relieve the Contractor of any obligation in the Contract nor of his responsibility for any errors or omissions.

2.2 Handling and Storage of New Equipment

1. All equipment shall be adequately protected from damage during handling and from dust, dampness or any

other injurious substance during delivery to the site, while at the site and after construction.

2. Any damage which may occur during handling, shipping, or installation shall be made good by the Contractor at his expense.

3. Equipment stored in unheated or open areas on the site shall be covered and provided with thermostatically controlled heaters of sufficient size to keep temperature of the equipment above the dew point.

4. Storage areas shall be made accessible to the Engineer at any time for the determination of the condition of storage.

2.3 Inspection

1. The Engineer reserves the right to inspect and test any material to be supplied under this specification at

the manufacturer's plant or after arrival at the location specified for delivery.

2. All materials, components, or parts which do not meet these specifications, the standards, or are defective, shall be replaced by the Contractor at his expense to the satisfaction of the Engineer.

3 Execution

3.1 Methodology

1. As the station is an integral part of the District water distribution system:

District of Squamish Section 15015

Powerhouse Springs Production Well – Pump and Piping Installation

Work Summary

Contract No. 2019-026 Page 3 of 3

a) Upon award the Contractor shall provide a brief of how the completion of work is proposed, to assure

minimum interruption of operation of the water distribution system. b) Any work done before the review and approval of proposed methodology will be at the Contractor's

risk. c) Any shutdown of existing equipment shall be at the convenience of the District. Each shutdown shall

have prior approval. d) The Contractor shall fully collaborate with operations staff and observe required protocols before

commencing construction. Lockout procedures shall be established and employed. Contractor shall provide an emergency response plan, and a 24-hour contact in case of emergency.

3.2 Record Drawings

1. The Contractor shall keep an accurate record of all field changes and modifications on a clean set of

drawings as required, using accepted drafting techniques.

2. At the completion of the job, return these corrected drawings to the Engineer.

3.3 Operation and Maintenance Manuals

1. The Contractor shall furnish the Engineer with three (3) complete bound sets of typewritten or printed

instructions, covering the proper method of operating and maintaining the equipment and systems included in this contract. It is recommended that the Contractor retain a fourth copy of the manual for future reference.

2. Included within the manual shall be a spare parts list for each item. Also included shall be manufacturer original printed operation and maintenance manuals on all pumps, valves and equipment.

3. The manual shall also include all finalized shop drawings in 280 mm by 430 mm format, catalogue numbers of all electrical equipment installed and manufacturer's parts lists.

4. Binders shall be easily opened and reasonable space shall be available for the inclusion of design criteria and background information by the Engineer.

5. In addition, the contractor shall provide an electronic copy of the manual in portable document format (.pdf) on a USB drive.

6. Copies of basic operation and maintenance manuals shall be made available by the Contractor at site during commissioning.

End of Section

District of Squamish Section 15015

Powerhouse Springs Production Well – Pump and Piping Installation

Work Summary

Contract No. 2019-026 Page 1 of 1

Section 15015 Work Summary

1 General

1.1 General

1. The Contractor shall supply, install and test all equipment and piping necessary to properly and fully

complete the operating systems as specified herein and as shown on drawings, unless otherwise indicated. All materials, labour, tools and appliances necessary for this work shall be furnished by the Contractor.

1.2 Included Mechanical Work

1. The Mechanical work shall include but not be limited to: a) Supply and installation of one submersible vertical turbine pumps. b) Supply and installation of all necessary piping, fittings and appurtenances as detailed. c) Supply and installation of check valves. d) Installation of magnetic flowmeters, as specified in Division 16. e) Installation of pressure transmitters, as specified in Division 16. f) Startup and commissioning.

End Of Section

District of Squamish Section 15100

Powerhouse Springs Production Well – Pump and Piping Installation

Piping Systems

Contract No. 2019-026 Page 1 of 8

Section 15100 Piping Systems

1 General

1.1 Description

1. This section describes the pipe materials, fittings, appurtenances, of the process mechanical and plumbing.

2. Piping supports and seismic bracing are generally not shown on the mechanical layout drawings. Piping supports and seismic bracing, if shown on drawings, are for reference only.

3. Design, select, locate and provide piping supports, pipe guides, seismic bracing, expansion joints and anchors required for final piping layout. Typical details and acceptable attachments shown on the drawings are provided only for general guidance.

4. The Contractor must provide the necessary submittals and ensure the piping systems and system components as fabricated in accordance to ANSI B31.3, Normal Fluid Service.

5. For Testing, Flushing and Disinfection procedures refer to Development Bylaw, 2011 and Master Municipal Contract Documents.

1.2 Definitions

1. Pressure terms used in this and other related sections are defined as follows:

a) Maximum pressure: The greatest constant pressure at which the piping system operates. b) Test pressure: The hydrostatic pressure used to determine system compliance.

2. Pipe and appurtenance location terms used in this and other related sections are defined as:

a) Pump Houses, Valve Chambers and Buildings: Within an environmentally controlled enclosure where

temperature is maintained above 5°C.

b) Exposed, Aboveground: Outside or within an enclosure which is not environmentally controlled so that

the temperature is maintained above 5°C. For the purpose of defining exterior protection systems, this

definition is extended to vertical piping to a point of 0.5 metres below finished ground level. c) Underground (or buried): Placed in soil and not tied to structures. d) Below Structures: Below concrete slabs such as tanks, channels, buildings, pipe chases, foundation

slabs, etc.; but not including roadways or walkway structures. e) Submerged: Regularly or occasionally immersed in liquid; inside tanks and/or channels, and within 3.0

metres above maximum water level of open tankage. Includes pipe and appurtenances within manholes, vaults and chambers.

1.3 Submittals for Review

1. Submit in accordance with MMCD General Requirements.

2. For each piping system, submit document listing pipe, fittings, flexible connectors, linings, coatings, and valving to be used for each pipe size and category.

3. For all pipe greater than or equal to 50mm diameter, submit isometric drawings, to indicate the assembly details, the welds, flanges, valve placement, cathodic protection, seismic restraint system, expansion joints, guides, anchors, hangers, supports, and the provisions for thrust restraint, as well as any other pertinent details.

4. Submit piping layout and section drawings by plant area which indicate location and placement of valves, fittings and other appurtenances for all piping, greater or equal to 50 mm diameter, in that area. Indicate overall and centre-centre dimensions and location and clearances from structures and other utilities (ductwork, conduit, electrical tray, etc.)

District of Squamish Section 15100

Powerhouse Springs Production Well – Pump and Piping Installation

Piping Systems

Contract No. 2019-026 Page 2 of 8

5. Where specified or directed by the Engineer, provide mill test results or product samples.

6. Detail all the pipe supports required on this project and provide shop drawings with the location of supports and details of all the hangers, expansion joints, guides and support systems. Drawings shall be signed and stamped by a Professional Engineer registered in British Columbia.

7. For expansion joints submit manufacturer’s catalogue data, shop drawings and assembly drawings confirming general arrangement, dimensions, and tolerances, materials of construction, weights and installation details. Submit calculations to substantiate expansion joint selection and amount of pre-compression, stamped and signed by a Professional Engineer registered in the province of British Columbia.

8. Welding: Prior to commencing any welding of stainless steel pipe of any size or steel pipe 600 or larger prepare and submit to the Engineer a written description of welding techniques including but not limited to materials, methods, and quality control. Identify differences in shop and field techniques. Written procedures to be stamped and sealed by a Professional Engineer registered in the province of British Columbia and qualified for welding design.

1.4 Coordination

1.4.1 Pipe Sleeves

1. Coordinate with other divisions and, prior to construction, locate, and place sleeves in cast-in-place concrete, and masonry building elements.

1.5 Quality Assurance

1.5.1 Welding Certification

1. All welders to be certified under the Government of British Columbia Boiler and Pressure Vessels Act. As a minimum, welders will hold a Level B Journeyman Welders Certificate.

2. All welders who work on this project must provide the correct documentation.

1.5.2 Weld Tests

1. Submit the name and qualifications of an independent firm for the radiographic weld testing to be undertaken by the Contractor. The selected firm will be subject to the review and acceptance of the Engineer.

2. Provide for 2 radiographic inspections and magnetic particle testing for all remaining joints. All sizes and types of pipe welds to be tested at locations identified by the Engineer.

3. Have weld test results submitted directly to the Engineer

1.5.3 Conflicts

1. Review the drawings prior to installation of piping, conduit services, and fixtures by this or any other

division. Identify any conflicts and cooperate with the Engineer to determine the adjustments necessary to resolve these conflicts.

2. Confirm the routing of each section of pipework with other services prior to commencement of installation. Advise the Engineer of any conflicts with existing services or services yet to be installed. Where necessary, amend the routing of pipework to avoid conflict and confirm with the Engineer.

1.6 Shipment, Protection and Storage

1. Deliver pipe, fittings, and specials to site using loading methods which do not damage pipe or coatings.

2. Piping materials delivered to site will be clearly marked to indicate size, type, class/schedule and coatings.

District of Squamish Section 15100

Powerhouse Springs Production Well – Pump and Piping Installation

Piping Systems

Contract No. 2019-026 Page 3 of 8

3. Until ready for incorporation in the work, store on site as recommended by the piping materials

manufacturer to prevent damage, undue stresses, or weathering.

4. Store materials at least 200 mm above ground with sufficient supports to prevent undue bending.

5. Protect non-UV light inhibited plastic from sunlight.

1.7 Reference Sections

1. None

2 Products

2.1 General

1. Provide the pipe materials, fittings, and appurtenances as described below, for the piping systems shown.

2.2 Pipe Materials - General

1. All pipe materials to be new, free from defects.

2. Where any standard referenced has been superseded prior to bidding, the Contractor shall comply with the new standard.

2.3 Non-Threaded Steel Piping

1. All non-threaded piping shall be fabricated from schedule 40 ASTM A-53 black steel pipe.

2. Branch outlets shall be fabricated utilizing FNPT Threadolet (Bonney Forge) connection fittings.

3. Grooved ends of 300 mm or smaller pipe shall be roll grooved per Victaulic Standard Groove specifications.

4. All grooved fittings, when available, shall be of ductile or malleable iron and as shown on drawings. Victaulic approved.

2.4 Threaded Stainless Steel Piping

1. All threaded piping, unless otherwise specified, shall be fabricated from Schedule 40, 316L stainless steel

pipe.

2.5 Joints - General

1. Connect piping using joints not readily disassembled only where shown and where not otherwise specified.

Provide joints which may be readily disassembled at the minimum within 1.0 m of any connection to equipment, on both sides of structural penetrations, within 0.6 m of all threaded end valves, and at the spacing specified in detailed piping specification sheets.

2. For steel piping equal to or greater than 75 mm in diameter, use grooved couplings or butt welds as shown on the drawings; predominately grooved couplings are to be used for above ground steel piping, butt welded, steel pipe for underground services. Flanges are to be used around equipment and valves conforming to AINSI B16.5, Class 150. Unless otherwise indicated (on the drawings) where disassembly is required, flanges shall be used.

3. For steel piping less than 75 mm in diameter, butt-weld or use threaded couplings. Use unions where disassembly is required.

4. For copper or brass piping, use soldered couplings. Where disassembly is required, use compression unions.

5. For thin wall or schedule rated stainless steel pipe equal to or greater than 75 mm in diameter, butt-weld pipe or use Victaulic grooved couplings as shown.

District of Squamish Section 15100

Powerhouse Springs Production Well – Pump and Piping Installation

Piping Systems

Contract No. 2019-026 Page 4 of 8

6. For schedule rated stainless steel pipe smaller than 75 mm in diameter, socket-weld pipe. Where

disassembly is required, use threaded unions.

7. Where not shown or otherwise specified, use solvent weld joints for PVC piping. Provide flanges or unions where disassembly is required.

8. For stainless steel tubing use stainless steel compression fittings.

2.6 Flanges

1. Welded flanges shall be Class 150 slip-on or weld-neck type with continuous weld.

2. General requirements for flanges are as follows: a) Compatible flanges for mating to equipment or valves. b) Provide flat-faced flanges on each side of butterfly valves. c) Provide weld neck flanges on both sides of wafer or lug body valves.

2.7 Threaded Couplings

1. Make screwed joints using American Standard threads to ANSI B1.20.1.

2. Use Teflon tape as thread lubricant for threaded joints.

3. Conform to ASTM A182 or ASTM A276, Class 150, for threaded connections to stainless steel pipe, threadolets to be shop welded to the pipe at the locations specified.

4. Provide threaded-end to flanged-end adaptors where required to connect to flanges.

2.8 Compression Couplings

1. Furnish compression couplings for stainless steel tubing of the same material as the pipe. Couplings to be capable of withstanding the maximum pressure to which the tubing is designed for.

2. Furnish compression couplings for copper and brass tubing of copper, designed for the maximum pressure of the pipe, conforming to ANSI B16.26.

2.9 Flange Assembly Bolts

1. Flange assembly bolts and all non-specialized bolts in the station shall be hexagon head machine bolts with hexagon nuts.

2. Bolt material shall be 300 series stainless steel, installed with anti-seize lubricant. Threads shall conform to CSA B.1.1 coarse thread series, Class 2 fit.

3. All bolted connections are to include washers on both sides of flange connection.

2.10 Conventional Flange Gaskets

1. Conventional flange gaskets shall be die-cut and material shall consist of aramid fibers in a nitrile elstomeric

binder with a minimum continuous temperature rating of 2000C.

2. Thickness shall be 1.6 mm (1/16”) for flanges up to 600 mm, 3.2 mm (1/8”) for larger flanges.

3. Shall be Garlock Multi-Swell 3760 as available from Custom Gaskets (604-263-1426).

2.11 Pipe Supports

1. Contractor is to design, supply and install all pipe supports and anchors. Piping drawings to be signed and sealed by a Professional Engineer registered in British Columbia to meet all applicable building and seismic codes.

District of Squamish Section 15100

Powerhouse Springs Production Well – Pump and Piping Installation

Piping Systems

Contract No. 2019-026 Page 5 of 8

2. All pipe supports shall be of AISI Type 316 stainless steel construction unless otherwise shown on the

drawings.

3. Threaded rods are not to be painted and shall be of corrosion resistant materials compatible with the service to which they are being provided.

2.12 Fittings

1. For steel pipelines 75 mm in diameter or greater, fittings to conform to ANSI B16.9, ANSI B16.11 or ANSI B16.5. Provide fittings with a wall thickness equal to or greater than the pipe. In steel pipelines less than 75 mm in diameter provide threaded malleable iron fittings, conforming to ANSI B16.3.

2. Provide butt welding fittings in steel pipelines less than 75 mm of the same class as the pipe, conforming to ASTM A403 and ANSI B16.11. Provide socket welding fittings in steel pipelines less than 75 mm to Cl. 3000, same material as the pipe, and ANSI B16.11. Fabricate fittings in steel pipelines equal to or greater than 75 mm in diameter using similar materials and classes as the pipe and conform to ASTM A774.

3. Provide ductile iron fittings in PVC pipelines that conform to AWWA C110 or provide PVC to CSA B137.3, of the same material and class as the pipe.

3 Execution

3.1 Preparation

1. Prior to installation, inspect and field measure to ensure that previous work is not prejudicial to the proper installation of piping.

2. Make all minor modifications to suit installed equipment and structural element locations and elevations.

3. Piping arrangements indicated on the drawings have been established on the basis of the "Design Standard" listed in the specific process equipment sections. If the equipment to be provided is not the Design Standard, at no additional expense to the District, modify the piping arrangement as necessary.

4. Advise the Engineer of all modifications. Do not commence work on the related piping until all modifications have been reviewed by the Engineer.

5. Include any piping modifications in the shop drawings submitted prior to fabrication or installation.

3.2 Pipe Handling

1. Inspect each pipe and fitting prior to installation. Do not install damaged pipe or pipe with damaged protective coatings.

2. Remove all foreign matter from inside of pipe prior to installation.

3. Repair pipe with damaged protective coatings with material similar to the original in accordance with the manufacturer's directions and to the satisfaction of the Engineer.

4. Damaged glass lining cannot be repaired. Damaged pipe must be replaced.

5. Use proper implements, tools, and facilities for the proper protection of the pipe. Exercise care in the installation so as to avoid damage to pipe or coatings.

3.3 Sleeves

1. Unless otherwise noted or approved by the Engineer, provide sleeves where piping passes through a wall, floor or ceiling.

2. Locate and place sleeves prior to construction of cast-in-place elements and prior to the construction of concrete and masonry building elements.

3.4 Piping Installation - General

District of Squamish Section 15100

Powerhouse Springs Production Well – Pump and Piping Installation

Piping Systems

Contract No. 2019-026 Page 6 of 8

1. The types and sizes of pipes to be used shall be as specified and shown. Where sizes of small pipe are

omitted from the drawings and not mentioned in the specifications, the sizes to be used shall be determined by the Engineer.

2. All pipe shall be carefully placed and supported at the proper lines and grades, and where possible shall be sloped to permit complete drainage. Piping runs shown on the drawings shall be followed as closely as possible, except for minor adjustments to avoid architectural and structural features. If major relocations are requested, they shall be submitted to the Engineer for approval.

3. In erecting the pipe a sufficient number of screwed unions, flanged or grooved end type joints shall be used to allow any section or run of pipe to be disconnected without interfering with, or removal or adjacent pipe runs. Flanged, grooved end type, and mechanical pipe coupling joints shall be employed on pipelines 75 mm in diameter and larger.

4. Provide the required number of take-down fittings, along straight runs of pipe.

5. Provide take-down fittings, after every second bend or fitting.

6. Provide take-down fittings to allow for the removal of valves, strainers, equipment, in-line instrumentation, and all other appurtenances along the piping rows.

7. Provide take-down fittings where-ever a pipe passes through a concrete or masonry wall.

3.5 Installation Of Pipe Underground/Buried And Below Structures

1. Refer to the drawings and Part 1.

2. Trenching and backfill for buried pipe: conform to Section 02315.

3. Pipe laying and bedding: conform to Section 02500 and 02501.

4. Unless otherwise shown, protect pipe laid below structures with a concrete surround having a minimum coverage of 100 mm all around the pipe and extend concrete surround to undisturbed ground.

a) Install pipe in straight alignment. Do not exceed 10 mm variance from the true alignment in any direction.

b) Ensure the pipe alignment stays true during and after placement of concrete surround. c) Ensure that the method used to prevent pipe uplift during placement of concrete surround results in a

level invert and crown. d) Maintain pipe circular cross section.

5. Provide lean concrete to within 150 mm of the underside of the slab or footing for backfill over pipe laid below structures, except as detailed otherwise.

6. Place concrete in accordance with Structural Drawings.

7. Tapewrap on all fittings and flanged, grooved, plain end and welded joints underground and below structures.

8. Use anti-seize compound with maximum friction factor of 0.16 with all stainless steel nuts and bolts.

3.6 Interior Installation

1. Make adequate provision in piping and pipe support systems for expansion, contraction, slope, and anchorage.

2. Install a pipe support system to adequately secure the pipe and to prevent undue vibration, sag or stress.

3. Install expansion joints where shown and at other locations as necessary to allow for piping expansion and contraction.

4. Provide temporary supports as necessary during construction to prevent overstressing of equipment, valves or pipe.

District of Squamish Section 15100

Powerhouse Springs Production Well – Pump and Piping Installation

Piping Systems

Contract No. 2019-026 Page 7 of 8

5. Accurately cut all piping for fabrication to field measurements.

6. Install pipes in straight alignment. Do not exceed 10 mm in 10 metres variance from the true alignment, in any direction. Fabricate and assemble pipe runs so that the pipework is not stressed to achieve the desired alignment and that no stresses are transferred to equipment or equipment flanges. The "springing" of pipework to ensure alignment is not permitted. Undo and subsequently remake all pipework connections where so instructed by the Engineer to ensure that springing does not occur. Take care not to damage equipment, valves or flanges.

7. Slope instrument air piping condensate traps. Provide condensate traps as recommended by the manufacturer of the instrument air compressor.

8. Do not cut or weaken the building structure to facilitate installation.

9. In parallel pipe runs, offset flanges and/or grooved joint fittings by a minimum of 200 mm.

10. In vertical pipe runs of diameter greater than 250 mm, provide 200 mm long spool piece on lower side of each valve.

3.7 Threaded Joints

1. Conform to the requirement of ANSI B31.1.

2. Ream the end of all pipes to remove all burrs and cuttings when fabricating threaded joints.

3. Clean out pipe and repair linings and coatings prior to joining.

4. Apply Teflon tape to male threads and then apply Loctite Food Grade Anti-Seize Lubricant prior to joining pipe.

5. Use both Teflon tape and Loctite Food Grade Anti-Seize Lubricant on stainless steel pipe threads. Do not use extra tape to make up for slack in the joint.

3.8 Flanged Joints

1. Clean flanges and gaskets prior to connection.

2. Lubricate gaskets with soapy water and apply anti-seize compound to the bolts.

3. Bring flanges into close parallel and lateral alignment.

4. Tighten bolts according to ASME PCC-1.

5. Bolt length shall be such that after the joints are made up the bolts shall protrude at least two threads past the nut, but not more than 12 mm.

6. Washers are to be used on each side of bolted flange connections.

7. Washers may not be used to take up excess bolt length.

8. When joining steel to cast iron flanges, take care to avoid damage to the cast iron flange. Ensure both flanges are flat-faced and use full face gaskets.

9. Align flanges which connect piping to mechanical equipment to close parallel and lateral alignment prior to tightening bolts. Do not place undue strain on the equipment.

10. Allow a minimum of 150 mm to face or 200 mm to edge of flange from wall, floor or ceiling unless otherwise shown.

3.9 Grooved End Gaskets

1. All grooved end gaskets shall be fully lubricated both inside and out with a manufacturer approved lubricant.

District of Squamish Section 15100

Powerhouse Springs Production Well – Pump and Piping Installation

Piping Systems

Contract No. 2019-026 Page 8 of 8

2. Evidence of improper lubrication at any connection shall be grounds for requiring all joints to be

disassembled and relubricated. Alternatively, approved dry lubricated gaskets may be utilized. VicPlus gasket system approved.

3.10 Rigid Grooved End Couplings

1. The nuts of rigid type couplings shall be tightened to within manufacturer’s specified torque range utilizing a torque wrench.

2. Evidence of improper torque on any rigid coupling shall be grounds for requiring all rigid couplings to be disassembled and retorqued.

End of Section

District of Squamish Section 15160

Powerhouse Springs Production Well – Pump and Piping Installation

Coatings

Contract No. 2019-026 Page 1 of 3

Section 15160 Coatings

1 General

1.1 Preparation and Coating of the Internal and External of Pipe

1. Shall include the categories:

a) Potable Immersed Applications or Internal of Potable Water Pipe.

Inside of piping and fittingsb) External of Non Buried/Exposed Potable Water Pipe

Outside of piping and fittingsc) External of Buried Potable Water Pipe

Outside of piping and fittings 2. All pipe internals and externals are to be prepared, coated and inspected/tested in accordance with the

latest version of AWWA C210.

3. Prior to abrasive blast cleaning, surfaces shall be inspected and if required cleaned according to SSPC-SP1 to remove oil, grease, or other foreign matter.

4. Pipe surfaces shall be abrasive blast cleaned in accordance with:

a) SSPC-SP10 for the internal and external of potable immersed, sewage immersed or buried pipe. b) SSPC-SP6 for the external of non-buried or exposed sewage or potable water pipe.

5. The blast anchor pattern or profile depth shall be 2.0 mils to 4.0 mils.

6. Coatings and Linings for the internal and external of potable immersed, sewage immersed or buried pipe to consist of the following:

a) Two or more coats of the same two-part, chemically cured epoxy coating or a single coat of a chemically cured epoxy coating.

d) Minimum thickness. Unless otherwise specified below or by the purchaser, the minimum DFT provided shall be at least 16 mils.

7. Coatings and Linings for the external of non-buried or exposed sewage or potable water pipe shall be high durability (15+ year) rated and suitable for a classification C4 high corrosivity according to ISO Standard 12944. It is to consist of the following:

a) Two or more coats of the same two-part, chemically cured epoxy coating or a single coat of a chemically cured epoxy coating.

b) One final coat of acrylic polyurethane to provide gloss and colour retention. c) Minimum thickness. Unless otherwise specified below or by the purchaser, the minimum DFT provided

shall be at least 16 mils. 8. Any addition requirements or changes to the requirements of AWWA C210 shall be referenced below

where required for the specific application. Only products referenced below shall be used.

2 Products

2.1 Potable Immersed Applications or Internal of Potable Water Pipe

1. In addition to the requirements AWWA C210, all products shall be applied to meet the latest NSF 61 listing.

2. Immediately following surface preparation spray apply one of the following:

a) Two coats of Epoxy - Bar Rust 233H or Interseal 670HS, as available from International Paint. Coatings are to be “white” colour.

3. The Total DFT of the applied coatings system shall be a minimum 14 mils.

2.2 External of Non Buried/Exposed Potable Water Pipe

1. Immediately following surface preparation spray apply one of the following:

District of Squamish Section 15160

Powerhouse Springs Production Well – Pump and Piping Installation

Coatings

Contract No. 2019-026 Page 2 of 3

a) Two coats of Epoxy - Bar Rust 233H or Bar Rust 236 or Interseal 670HS, as available from International

Paint. Prime coating is to be “tan” colour and final coating to be “safety blue” colour. b) One coat of Epoxy - Interzone 954, as available from International Paint. Coating to be “safety blue”

colour. 2. Immediately following epoxy application, spray apply one of the following to provide gloss and colour

retention:

a) One coat of Acrylic Polyurethane - Devthane 379UVA / Interthane 990 (990HS used for field touch up), as available from International Paint.

2.3 External of Buried Potable Water Pipe

1. Immediately following surface preparation spray apply one of the following:

a) Two coats of Epoxy - Bar Rust 233H or Bar Rust 236 or Interseal 670HS as available from International Paint. Prime coating is to be “tan” colour and final coating to be “safety blue” colour.

b) One coat of Epoxy - Bar Rust 234P or Interzone 954 as available from International Paint. Coating to be “safety blue” colour.

3 Execution

3.1 Application Quality

1. The Contractor shall be responsible for self-inspection of the coating systems as outlined, but subject to

independent inspection at all times.

2. The Contractor shall employ a NACE certified coating inspector, acceptable to the Engineer, to inspect the work and provide written progress reports and digital photographs.

3. Inspection shall be conducted immediately after surface preparation as well as each coating step.

4. Only an approved applicator shall be utilized for surface preparation and coating systems. Approved applicators are:

Dynacor Coatings 2004 Ltd. (604) 946-0136

Seaside Painters & Sandblasters Inc. (604) 583-6758

Mainland Painting (604) 589-7949

CorrCoat Services (604) 881-1268

Certified Coating Services (CCS) (604) 255-1001

Clara Industrial Services (604) 882-8608 Midvalley Sandblasting (250) 766-1323

5. The NACE certified coating inspector shall, through the Contractor, provide the Engineer with a letter of

verification upon completion of all required coating applications.

3.2 Caution Areas

1. Grooved end piping and fittings for use with Victaulic couplings and flange adapters shall be coated for immersed service internally as well as on the gasket seating surface and in each groove at the end of the pipe or fitting. Coating applied to the gasket seating surface and within the groove on pipe and fitting exteriors shall not exceed 0.25 mm (0.010 inches), or as recommended by the manufacturer

2. Flexible rubber jacketed cables, liquid tight flexible conduit, nameplates, aluminium and stainless steel components and valve internals shall not be painted.

3.3 Field Touch Up Procedures

1. Damage to shop applied coatings occurring in storage, erection or installation shall be repaired to standards equal to the project specifications.

District of Squamish Section 15160

Powerhouse Springs Production Well – Pump and Piping Installation

Coatings

Contract No. 2019-026 Page 3 of 3

2. Immediately prior to repairing damaged or unpainted surfaces, and before the specified surface preparation is carried out, all grease, oil, dirt, and foreign matter shall be removed as per SSPC SP1.

3. Edges of sound remaining coating on the surface shall be feathered by sanding/grinding prior to painting.

4. Gloss paint surfaces shall be sanded or abraded to provide a bond for successive coats.

5. The minimum coating requirements for spot coating repairs shall be as follows: a) No corrosion, primer exposed:

Apply one or more finish coats to restore specified film thickness.

b) No corrosion, primer damaged: Clean area to substrate and reapply the specified system

c) Rusted areas: After cleaning to the original standard of surface cleanliness, reapply specified system

d) All areas to be repaired shall be inspected by the coating inspector before, during and after such repairs to confirm compliance with the foregoing and /or the project specifications.

End of Section

District of Squamish Section 15420

Powerhouse Springs Production Well – Pump and Piping Installation

Submersible Vertical Turbine Pumps

Contract No. 2019-026 Page 1 of 4

Section 15420 Submersible Vertical Turbine Pumps

1 General

1.1 Work Included

1. The work required under these specifications is for the supply and delivery of one (1) submersible vertical turbine pumping unit including the complete supply, fabrication, testing, installation and commissioning and include pump bowls, pump columns, shafts, discharge heads, pump inlet barrels, couplings, seals, motors and all other related and associated new components required to provide a complete working pump installation.

2. The installation of the well pump shall be directly supervised by a qualified pump installer certified through the Industry Training Authority, Province of British Columbia.

1.2 General Description

1. This specification is for the supply and installation of one (1) submersible vertical turbine pump for the

operating condition provided in Table 1 of this specification. This pump will operate into its pressure zone using adjustable speed drives (ASD’s) for motor speed control. Motor speed will be varied to maintain a set flowrate. Pump starting and stopping control will be based on Reservoir level set points.

2. System Description

a) The pump is to provide 90 L/s at 47.0m total dynamic head (TDH).

3. The submersible pumping unit shall be water lubricated, multi stage, submersible motor driven and designed for installation within a groundwater well (borehole) and have a maximum external diameter of 219 mm.

4. The pump shall operate at the specified duty point and from the minimum continuous flow to the right end of the pump curve within this pressure range without cavitation, passing through a critical or Reed frequency or experiencing vibration in excess of allowable Hydraulic Institute standards.

5. Shutoff head of the pump shall not be more than 70 m and design point pump hydraulic operating efficiency shall not be less than 75%.

6. The pump is to be installed within the well casing as shown on the drawings.

7. The pump bowls, impellers, pump columns, shafts, discharge heads, inlet barrel, couplings, seals, motors and all associated components are to be supplied by the selected OEM pump manufacturer. Local fabrication of any component is not acceptable.

8. The operating condition for the pump is:

Table 1: Pump Parameters

Pump Location

Rated Capacity (L/s)

Total Dynamic Head (m)

Minimum Bowl Efficiency (%)

Speed (rpm)

Maximum Motor Size (kW)

Drive Type

Size (mm)

Stages

Powerhouse 3 90 47 75 1800 60 ASD 216 TBD

a) Operating conditions are to be at the top of the submersible pump. b) The BEP is to be at or to the right of the operating condition. c) The pumps are to operate from 70-120% of BEP while using ASD’s to maintain pump discharge

flowrate. 9. Performance curves for the bowl assemblies showing pump capacity, head, efficiency and horsepower shall

be provided. Calculated column and discharge head friction losses shall be provided.

District of Squamish Section 15420

Powerhouse Springs Production Well – Pump and Piping Installation

Submersible Vertical Turbine Pumps

Contract No. 2019-026 Page 2 of 4

10. The pump supplier is to have an in-house service department with factory trained technicians who will be

responsible for all inspection, commissioning and repair services.

1.3 Reference

1. Hydraulic Institute Standards

2. Section 15100 – Piping Systems

3. Section 15160 – Coatings

2 Products

2.1 Inlet

1. Pump first stage bowl assembly shall be fitted with a suction bell.

2.2 Bowl Assembly

1. Bowls shall be of cast iron construction and be free of blow holes, sand holes and other detrimental effects.

2. Impellers shall be polished bronze.

2.3 Riser Pipe

1. Discharge riser pipe shall be random length (4.8m-6.7m, or 16'-22') nominal 150 mm diameter, schedule 40 steel with standard merchant taper tapped threaded couplings. Note that check valve to be installed one pipe length above pump.

2. All threaded riser pipe ends shall be checked utilizing an NPT screw ring gauge, and this shall be demonstrated to the Engineer on request.

3. Ensure that riser pipe penetration into each coupling end is at least:

Pipe Size Minimum End Penetration

50 mm 19 mm 80 mm 25 mm 100 mm 29 mm 150 mm 33 mm

200 mm 37 mm 4. Pump cable shall be attached to the discharge riser pipe by means of vinyl electrical tape applied in a 50mm

wide multi-wrap band a minimum of every 2m.

2.4 Discharge Riser Pipe Coating

1. Coating system shall be suitable for exposure in immersed environments at ambient temperatures. All surfaces should be assessed and treated in accordance with ISO 8504:1992. Oil or grease shall be removed per SSPC-SP-1 solvent cleaning.

2. Immersed surfaces shall be surface prepared (inside and out) to SSPC-SP-10 near white blast. If oxidation has occurred between blasting and application, the surface shall be reblasted to the specified visual standard. Surface defects revealed by the blast cleaning process, shall be ground, filled, or treated in the appropriate manner.

3. Immediately following surface preparation a prime coat of 2-component, white coloured high build epoxy shall be applied by spray to a dry film thickness of 6.0 – 8.0 mils. All epoxy must be meet AWWA C-210 standards and have NSF 61 Certification.

4. This shall be followed by a final coat of 2-component, “Light Tan” coloured epoxy applied by spray to a dry film thickness of 6.0 - 8.0 mils.

District of Squamish Section 15420

Powerhouse Springs Production Well – Pump and Piping Installation

Submersible Vertical Turbine Pumps

Contract No. 2019-026 Page 3 of 4

2.4.1 Application Quality

1. The Contractor shall be responsible for self-inspection of the coating systems as outlined, but subject to independent inspection at all times.

2.4.2 Field Touch Up Procedures

1. Damage to shop applied coatings occurring in storage, erection or installation shall be repaired to standards equal to the project specifications.

2. Immediately prior to repairing damaged or unpainted surfaces, and before the specified surface preparation is carried out, all grease, oil, dirt, and foreign matter shall be removed as per SSPC SP1.

3. Edges of sound remaining coating on the surface shall be feathered by sanding/grinding prior to painting.

4. Gloss paint surfaces shall be sanded or abraded to provide a bond for successive coats.

5. The minimum coating requirements for spot coating repairs shall be as follows:

a) No corrosion, primer exposed: a. Apply one or more finish coats to restore specified film thickness.

b) No corrosion, primer damaged: a. Clean area to substrate and reapply the specified system

c) Rusted areas: a. After cleaning to the original standard of surface cleanliness, reapply specified system

6. Exposed threads shall be finish coated after each joint is assembled. Drying time may be disregarded.

2.5 Level Transmitter Insert Tube

1. Extending from grade level to just above the pump discharge, a tube made of solvent coupled 25mm Schedule 40 PVC pipe (26.6 mm ID) shall be attached to the discharge riser pipe, along with the pump cable. The bottom of this insert tube shall terminate in a cap, to serve as a transmitter end stop, about which a minimum of two 6mm vent holes are drilled.

2.6 Fasteners

1. All fasteners to be stainless steel.

2.7 Factory Testing

1. The following tests are to be performed the new pump:

a) The pump bowl assembly shall be given a standard non-witnessed factory test per Hydraulic Institute 14.6-2011 Grade 1U.

b) The pump discharge head and bowl assembly shall be subject to a hydrostatic test as per Hydraulic Institute standards.

c) Copies of the test data and certified performance curves shall be provided to the Contract Administrator within 3 weeks of completion of the tests.

2. Performance curves shall show pump capacity, head, efficiency and horsepower.

2.8 Driver

1. The driver provided shall be in full compliance with the Pump Motor.

2.9 Motor

1. Integrally mounted with the pump shall be a water filled 75 HP Franklin #239613 submersible motor with 1.15 service factor, silicon carbide based sealing system and sufficient continuous thrust capacity. Motor operating efficiency shall not be less than 85% and the nameplate rating of the motor shall not be exceeded. Mounting base and shaft extension shall be to NEMA standards. Motor shall be suitable for 575 Volt, 60 Hz, three phase service.

2. Minimum acceptable water flow velocity past the motor for cooling shall not be more than 150 mm/s (0.5 f/s). (Motor shall be rated for no flow past motor operation in liquid of up to 30°C.)

District of Squamish Section 15420

Powerhouse Springs Production Well – Pump and Piping Installation

Submersible Vertical Turbine Pumps

Contract No. 2019-026 Page 4 of 4

2.10 Acceptable Manufacturers

1. The following pump model is approved for the supply of the new pump installations:

a) Franklin 9STS-1200-01 b) Peerless 14MC-2 Stage

2. Alternate pump models will be considered.

2.11 Submersible Pump Cable

1. Motor leads shall be protected for the entire length of the bowl assembly by a 300 series stainless steel cable guard supplied with the pump. Some 50m of Type TWU or RWU, minimum #1/0 stranded submersible pump cable shall be provided, spliced to the motor leads using crimp connectors and heavy duty heat shrink insulation with adhesive. T&B HS Series approved. Included shall be a #4 ground conductor terminating at a motor stud ring connector.

3 Execution

3.1 Installation

1. The contractor is to coordinate with the pump supplier for all installation, commissioning and testing requirements.

2. Prior to start-up and commissioning, the pump supplier shall be responsible for ensuring that the installation of pumping equipment fully complies with the requirements of the pump manufacturer, including alignment, and shall provide a letter of certification that these requirements have been met.

3. Installed pump vibration covering the stated flow ranges, as measured by the supplier during commissioning, shall be within the limitations defined by the current standards of Hydraulics Institute. If the limitations are exceeded, the Contractor shall be fully responsible for any corrective measures then necessary to attain those limitations. The contractor is to provide vibration test results report as part of the commissioning services.

4. The pump supplier is responsible for start-up and commissioning services for the new pumps and shall provide a letter upon completion of each pump commissioning that all pump manufacturer and Hydraulic Institute requirements have been met.

5. New pump start-up and commissioning services will be performed into the distribution system through open hydrants. The contractor is to provide a clamp-on type ultrasonic flowmeter, or approved alternate, to confirm new pump flowrates during testing. The contractor is to provide a field measured pump curve as part of the commissioning services.

6. The pump supplier is responsible to provide training to District personnel. Training session to be a separate from commissioning period at a date agreed upon by the District.

End of Section

District of Squamish Section 15900

Powerhouse Springs Production Well – Pump and Piping Installation

Well Decommissioning

Contract No. 2019-026 Page 1 of 2

Section 15900 Well Decommissioning

1 General

1.1 Description

1. The work shall consist of furnishing and installing materials to decommission a water supply well.

1.2 Reference Documents

a) Conform to the following reference documents: b) Water Sustainability Act (WSA) Bill 18-2014 c) Groundwater Protection Regulation (GWPR) 39/2016 d) BC Ground Water Associations, “Groundwater Protection Regulation Handbook”, Version 1

(September 2017).

1.3 Definitions

1. Well Deactivation - When any well is temporarily removed from service.

2. Well Decommissioning – Decommission/abandon wells when no future use of the well is intended.

1.4 License Required

1. Well abandonment shall be accomplished under the direct supervision of a currently licensed water well driller or pump installer who shall be responsible for verification of the procedures and materials used.

2 Products

2.1 Acceptable Materials

1. Neat cement grout, sand cement grout, un-hydrated bentonite, or bentonite grout shall be used to abandon wells and boreholes. Drilling mud or drill cuttings shall not be used as any part of a sealing materials for well abandonment.

3 Execution

3.1 Removals

1. Prior to well or borehole abandonment, all pump equipment, piping, and other debris shall be removed to the extent possible. If equipped, the pitless adapter casing is to be cut below ground (or cut below the discharge fitting) and is to be fully disconnected from the discharge watermain. The well shall also be sounded immediately before it is plugged to make sure that no obstructions exist that will interfere with the filling and sealing. If the well contains lubricating oil that has leaked from a turbine shaft pump, it shall be removed from the well prior to abandonment and disposed of in accordance with applicable local, provincial and federal regulations.

2. Sealing materials shall be introduced at the bottom of the well or required sealing interval and placed progressively upward to the top of the well. The sealing material shall be placed by the use of a grout pipe, tremie line, dump bailer or equivalent in order to avoid freefall, bridging, or dilution of the sealing materials or separation of aggregates from sealants. Sealing material shall not be installed by freefall (gravity) unless the interval to be sealed is dry and no deeper than 30 feet below ground surface. The well should be capped by means of a welded steel plate immediately after placement of seal materials to allow the seal material to set up and not flow out of the well.

District of Squamish Section 15900

Powerhouse Springs Production Well – Pump and Piping Installation

Well Decommissioning

Contract No. 2019-026 Page 2 of 2

3. Bentonite-based abandonment products shall be mixed and placed according to manufacturer's

recommended procedures and result in a seal free of voids or bridges. Granular or powered bentonite shall not be placed under water. When placing un-hydrated bentonite, a sounding or tamping tool shall be run in the sealing interval during pouring to measure fill-up rate, verify a continuous seal placement, and to break up possible bridges or cake formation.

4. The uppermost five (5) metres of the well shall be abandoned via a plug installed to within 0.3 m of the ground surface.

5. Abandonment materials placed opposite any non-water bearing intervals or zones shall be at least as impervious as the formation or strata prior to penetration during the drilling process.

6. Verification shall be made that the volume of sealing and fill material placed in a well during decommissioning operations equals or exceeds the volume of the well or borehole to be filled and sealed.

3.2 Termination of Casing

1. The casings of wells to be abandoned shall be severed a minimum of one (1) metre below either the natural ground surface adjacent to the well or at the collar of the hole, whichever is the lower elevation. A minimum of 600 mm of compacted native material shall be placed above the abandoned well upon completion.

3.3 Surface Seal

1. The interval between the native soil cap and the top of cut off casing shall be sealed with sealing materials that consist of alternating layers of Bentonite (fanned out) and bedding sand throughout the excavated area.

2. The interval between the ground surface and the top of the cut off casing shall be filled with soil material that achieves an in-place hydraulic conductivity equivalent to or less than the surface soil surrounding the well. The ground surface at the sealed well site shall be mounded and graded in a manner that prevents ponding of surface runoff.

3. The soil is to be compacted to 90% MPDD after each layer of Bentonite and sand backfill.

3.4 Reporting

1. Provide a well commissioning report in accordance with the GWPR.

End of Section

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 1 of 14

Part 1 General

1.1 GENERAL

.1 This Section covers items common to Sections of Divisions 26. This section supplements

requirements of Division 1.

1.2 RELATED REQUIREMENTS

.1 Section 26 05 00 – Common Work Results – Electrical

.2 Section 26 05 05 – Electrical Demolition

.3 Section 26 05 10 – Testing and Commissioning

.4 Section 26 05 20 – Wire and Box Connectors 0-1000V

.5 Section 26 05 21 – Wires and Cables 0-1000V

.6 Section 26 05 22 – Connectors and Terminations

.7 Section 26 05 28 - Grounding & Bonding

.8 Section 26 05 29 – Hangers and Supports for Electrical Systems

.9 Section 26 05 31 – Splitters, Junction, Pull Boxes and Cabinets

.10 Section 26 05 32 - Outlet Boxes, Conduit Boxes and Fittings

.11 Section 26 05 34 – Conduits, Conduit Fastenings and Conduit Fittings

.12 Section 26 05 44 01 – Installation of Cables in Trenches and Ducts

.13 Section 26 27 15 – Electrical and Controls Components

.14 Section 26 28 16 02 – Moulded Case Circuit Breakers

1.3 REFERENCES

.1 Definitions:

.1 Electrical and electronic terms: unless otherwise specified or indicated, terms

used in these specifications, and on drawings, are those defined by IEEE

SP1122.

.2 Reference Standards:

.1 CSA Group

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 2 of 14

.1 CSA C22.1-15, Canadian Electrical Code, Part 1 (23nd Edition), Safety

Standard for Electrical Installations.

.2 CSA C22.2 No. 1-10, General Requirements - Canadian Electrical Code,

Part 2.

.3 CAN3-C235-83(R2015), Preferred Voltage Levels for AC Systems, 0 to

50,000 V.

.2 Institute of Electrical and Electronics (IEEE)/National Electrical Safety Code

Product Line (NESC)

.1 IEEE SP1122-2000, The Authoritative Dictionary of IEEE Standards

Terms, 7th Edition.

1.4 SUMMARY OF WORK

.1 This project involves the removal, modification, supply, and installation of electrical

infrastructure in the existing Control Building 2, existing Well 3, and new Well 3

locations. The electrical scope of the project includes, but is not limited to, the following

items of work:

.1 Removal and disposal of existing Well 3 VFD and associated electrical

accessories within the MCC in Controller Building 2.

.2 Modification of the MCC section containing the existing Well 3 VFD and

accessories to accept a 100HP VFD and associated pump starter accessories

including DV/DT filter, line reactor, main circuit breaker, terminal strips, and

low voltage fan transformer.

.3 Supply and installation of a new MCC door for the Well 3 section to

accommodate new 100HP VFD and door controls, main breaker disconnect

handle, fans, and VFD HMI panel.

.4 Supply and installation of 100HP VFD, main circuit breaker, DV/DT filter, 3%

line reactor, low voltage fan transformer, fuses, terminal strips, wiring, and

interconnections to provide a complete starter system.

.5 Supply and installation of pump feeder cables between MCC in Control Building

2 and Well 3 Junction Boxes.

.6 Supply and installation of instrumentation cables (Level and Flow) between

MCC in Control Building 2 and Well 3 Junction Boxes.

.7 Supply an installation of Well 3 Junction Boxes including concrete foundation,

unistrut support structure, and all other miscellaneous parts required to complete

the work.

.8 Supply and installation of Flow Meter transmitter and all associated conduit and

cables between the Flow Meter transmitter, sensor, and MCC in Control

Building 2.

.9 Supply and installation of Flow Meter sensor in Flow Meter chamber including

all terminations and cabling for the Flow Meter sensor.

.10 Supply and installation of Level Transducer in Well 3 including all terminations,

bellows, and cabling for the level transducer.

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 3 of 14

.11 Supply and installation of well pump cables between Well and Well 3 Junction

Boxes.

.12 Termination and testing of all cables and wiring installed as part of this project.

.13 Testing and commissioning of VFD and all associated electrical components

installed as part of this project.

.14 All work shall be performed by qualified personnel.

1.5 MATERIAL AND WORK SUPPLIED BY OTHERS

.1 Associated drilling, casing and well mechanical items.

.2 Programming and Commissioning of SCADA system.

1.6 RESPONSIBILITY AND COORDINATION

.1 Provide all labour, materials, equipment, tools, and incidentals necessary to provide a

complete system as indicated on the Drawings and as set out in these Specifications.

.2 Without relieving the Contractor of his responsibilities, the Specifications have been

divided into approximate trade sections for convenience. These Sections do not,

however, limit the responsibility of any subcontractor or supplier. The Engineer will not

arbitrate on any dispute between the subcontractors' responsibilities. The onus of

defining the extent of the subcontractors' work remains with the Contractor, who, when

awarding subcontracts, will ensure that the area of responsibility of any particular

subcontractor is set out in full detail.

.3 The Contractor shall advise the Engineer during the tender period of any specified

material or equipment which is either no longer available from manufacturers or whose

delivery is likely to exceed the requirements of the anticipated Construction Schedule.

Failure of the Contractor to perform the above shall cause the Contractor to supply, at his

own expense, alternate material or equipment as selected by the Engineer at a later date.

Alternatively, the Contractor shall procure the specified material or equipment at his own

additional expense by means of air freight or other special means of transportation.

.4 The Drawings and Specifications complement each other and what is called for by one is

binding as if called for by both. If there is any doubt as to the meaning or true intent due

to a discrepancy between the Drawings and Specifications, obtain a ruling from the

Engineer prior to tender closing. Failing this, the most expensive alternative is to be

allowed for.

.5 Advise the Engineer of any specified equipment, material, or installation of same which

appears inadequate or unsuitable or which is in violation of laws, ordinances, rules, or

regulations of authorities having jurisdiction. Provide all labour and materials which are

obviously necessary or reasonably implied to be necessary to complete the work as if the

work was shown on the Drawings and/or described in the Specifications.

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 4 of 14

.6 Check Drawings of all trades and coordinate the installation of all material and

equipment to ensure adequate space and free access and to maintain headroom

limitations for all proposed and indicated future work. Work out jointly, with all

Subcontractors on the site, solutions to interference problems. Coordinate all work

before fabricating or installing any material or equipment. It is incumbent on all

Subcontractors on the site to ensure that all materials and equipment fit into the allocated

spaces and that all equipment can be properly inspected, serviced, and replaced if and

when required. Advise the Engineer of space problems before fabricating or installing

any material or equipment. Demonstrate to the Engineer on completion of the work that

all equipment and material installed can be properly and safely serviced and replaced.

Make no deviations from the intent of the design, or any involving additional cost,

without the Engineer's written direction.

.7 Where electrical work and materials are noted as being provided by the Owner or under

other Divisions of these Specifications, the responsibility for integrating, to the extent

required, such work and materials into the complete installation, shall remain within

Division 26.

.8 Ensure that any building structure loaded during the supply of the electrical kiosk is

adequate to carry such load.

.9 Testing in accordance with Section 26 05 10 Testing and Commissioning.

.10 A contractor is entitled to engage in the regulated work for which the contractor is

licensed.

.1 A licensed contractor must not:

.1 Manage or do regulated work that is:

.1 Outside the scope of the license,

.2 Contrary to any term or condition of the license, or

.3 Contrary to any term or condition imposed by the regulations on

the use of the license, or

.2 Permit regulated work to be undertaken by persons under the control of

the licensed contractor if they are not authorized.

.2 A licensed contractor must:

.1 Maintain current knowledge of the Acts, relevant regulations, relevant

directives, relevant safety orders and any other relevant material that the

minister makes publicly available, and

.11 Ensure that individuals who do regulated work for the licensed contractor maintain

similar current knowledge.

1.7 DRAWING NOTATION

.1 The electrical work for this project involves the installation of new electrical and the re-

use or relocation of some existing equipment. In all cases the Contractor shall assume

that it has to supply and install all electrical equipment. Standard notations are used on

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 5 of 14

the Plans to assist the Contractor in identifying what work needs to be done. These

standard notations are defined as follows:

.1 “All equipment is proposed unless noted otherwise” – This notation is used on

Plans where the majority of the equipment on the drawing is to be supplied and

installed by the Contractor. The notation means that the Contractor shall

perform all work shown on the drawing except for equipment shown as existing

(i.e. to remain).

.2 “All equipment is existing unless noted otherwise”: - This notation is used on

Plans where the majority of the equipment is existing. The notation means that

the Contractor shall perform only the work identified.

1.8 CODES AND STANDARDS

.1 Complete installation in accordance with CSA C22.1-2015 except where specified

otherwise.

1.9 CARE, OPERATION AND START-UP

.1 Instruct Consultant and operating personnel in the operation, care and maintenance of

systems, system equipment and components.

.2 Provide these services for such period, and for as many visits as necessary to put

equipment in operation, and ensure that operating personnel are conversant with all

aspects of its care and operation.

1.10 PERMITS, FEES AND INSPECTION

.1 Submit to Electrical Inspection Department and Supply Authority necessary number of

drawings and specifications for examination and approval prior to commencement of

Work.

.2 Pay associated fees.

.3 Notify Consultant of changes required by Electrical Inspection Department prior to

making changes.

.4 Furnish Certificates of Acceptance from authorities having jurisdiction on completion of

work to Consultant.

1.11 DELIVERY, STORAGE AND HANDLING

.1 Deliver, store and handle materials in accordance with manufacturer's written

instructions.

.2 Delivery and Acceptance Requirements: deliver materials to site in original factory

packaging, labelled with manufacturer's name and address.

.3 Storage and Handling Requirements:

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 6 of 14

.1 Store materials indoors in dry location and in accordance with manufacturer's

recommendations in clean, dry, well-ventilated area.

.2 Store and protect equipment from nicks, scratches, and blemishes.

.3 Replace defective or damaged materials with new.

.4 Develop Construction Waste Management Plan related to Work of this Section.

1.12 CLOSEOUT SUBMITTALS

.1 Submittals: in accordance with Conditions of the Contract.

.2 Shop Drawings

.1 Refer to Contract Documents.

.2 Notwithstanding the above, submit shop and setting drawings or diagrams to the

Engineer sufficiently in advance of requirements to allow time for review and

comment. Provide shop drawings in electronic format, Adobe Acrobat "pdf."

The drawing will be retained by the Engineer for their office use and a copy will

be marked and returned to the Contractor for correction if necessary, further

reproduction, and distribution as required. Provide shop drawings in AutoCAD

2017 format where required for major equipment as noted in individual sections

herein.

.3 Shop drawings shall be neatly drafted and shall be complete and detailed and

shall be provided as stipulated elsewhere in these Specifications.

.4 All shop drawings shall use metric dimensions. Scaled drawings shall use metric

scale.

.5 Ensure that all cable pit and cable trench locations are clearly shown and

dimensioned on all shop drawings of high voltage and other switchgear.

.6 Shop drawings shall bear specific names for each and every unit assembly

defined thereon, the name of the project where installation is to take place, the

name of the manufacturer, and the date of the drawing including notation of

latest revision, if any.

.7 Except as may be necessary to indicate operation of switchgear and similar

apparatus and to show field interconnections, detailed wiring diagrams of

component assemblies need not be included with shop drawings unless requested

by the Engineer. However, such wiring diagrams shall be included as part of the

Maintenance Manual as required by these Specifications.

.8 Indicate details of construction, dimensions, locations of cable pits and trenches,

capacities, weights and electrical performance characteristics of equipment and

materials.

.9 Shop drawings may be prepared by the Contractor, or manufacturer's drawings

will be accepted. Drawings required for one and the same system shall be

submitted as a complete package. Incomplete system packages will not be

reviewed and will be returned unmarked.

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 7 of 14

.10 Shop drawings shall be reviewed by the Contractor prior to submission to the

Engineer. Shop drawings not bearing Contractor's approval stamp, approval date,

signature, and project name will be returned without comment.

.11 Manufacturers' brochures (product data) submitted as shop drawings shall clearly

indicate type (i.e., lighting fixture Type AD, intercom station Type B, etc.) and

all features as specified as part of the unit(s).

.12 Facsimile Shop Drawings will not be accepted.

.13 Review of Shop Drawings by the Engineer is for the sole purpose of ascertaining

conformance with the general design intent. The review shall not mean approval

of the detail design inherent in the shop drawings, responsibility for which shall

remain with the Contractor submitting same, and such review shall not relieve

the Contractor of his responsibility for errors or omissions in the shop drawings

or of his responsibility for meeting all requirements of the Contract Documents.

The Contractor is responsible for dimensions to be confirmed and correlated at

the job site, for information that pertains solely to fabrication processes or to

techniques of construction and installation and for coordination of the work of

all sub-trades.

.14 Ensure that copies of all shop drawings are available at the job site.

.3 Test Procedures in accordance with Section 26 05 10 Testing and Commissioning.

.4 "As-Built" Drawings

.1 Refer to Contract Documents.

.2 Notwithstanding the above, maintain in the job site office in up-to-date

condition, one (1) complete set of whiteprints of each of the Electrical

Contract Drawings and one (1) set of Specifications, including Revision

Drawings, marked clearly and indelibly in red, indicating "As-Built"

conditions where such conditions deviate from the original directions of

the Contract Documents, and indicating final installation of feeders and

branch circuits.

.3 "As-Built'' drawing markings shall include but shall not be limited to the

following:

.1 All changes in circuiting.

.2 Size and routing of all conduits for branch circuits including

power, lighting, and systems. Note that branch circuit wiring is

generally not shown on Drawings. Accurately record on "As-

Built" drawings the size and routing of all installed raceways

and cables.

.3 Number and size of conductors in raceways and cables

.4 Location of all junction and pull boxes

.5 Location of all access panels

.6 Location of all conduit or duct stubs, installed equipment,

devices, and fixtures

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 8 of 14

.7 All changes to electrical installation resulting from Addenda,

Change Orders, and Field Instructions (Architectural /

Engineering Instructions)

.8 Exact location of all services left for future work

.9 Location by accurate horizontal and vertical dimensions of the

routes and terminations of all raceways and cables installed

underground beyond the building.

.10 Exact labeling of each communication system cable at each data

outlet location. Locate label numbers adjacent each

communication outlet indicated on drawings. Label numbers to

match those at the Communication Room cable end.

.11 Where extensive changes have been made to an area to the point

where it is not practical to update the original tender drawing,

the area in question shall be enclosed with a heavy dotted line

and reference made to the applicable Change Order, Instruction,

and/or associated Revision Drawing.

.12 For each and every "As-Built" drawing, reference shall be neatly

drawn inside the framed space above the title block, listing all

Contemplated Change Orders, Instructions, and Revision

Drawing Numbers applicable to the particular "As-Built"

drawing in question.

.13 Each "As-Built" drawing as defined above shall bear the

Contractor's identification and signature, the date of record, and

the notation: "We hereby certify that these Drawings represent

the building as built."

.14 All Addenda and Revision Drawings not having their details

transferred onto the submitted "as-built" drawings shall be

included in the submission using the same drawing format as

previously described.

Part 2 Products

2.1 DESIGN REQUIREMENTS

.1 Operating voltages: to CAN3-C235.

.2 Motors, electric heating, control and distribution devices and equipment to operate

satisfactorily at 60 Hz within normal operating limits established by above standard.

.1 Equipment to operate in extreme operating conditions established in above

standard without damage to equipment.

.3 Language operating requirements: provide identification nameplates for control items in

English.

.4 Use one nameplate for each language.

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 9 of 14

2.2 MATERIALS AND EQUIPMENT

.1 Equipment and material to be CSA certified. Where there is no alternative to supplying

equipment which is not CSA certified, obtain special approval from Electrical Inspection

Department.

.2 Factory assemble control panels and component assemblies.

2.3 ELECTRIC MOTORS, EQUIPMENT AND CONTROLS

.1 Verify installation and co-ordination responsibilities related to motors, equipment and

controls, as indicated.

2.4 WARNING SIGNS

.1 Warning Signs: in accordance with requirements of authority having jurisdiction and

Consultant.

.2 Decal signs, minimum size 175 x 250 mm.

2.5 WIRING TERMINATIONS

.1 Ensure lugs, terminals, screws used for termination of wiring are suitable for either

copper or aluminum conductors.

2.6 EQUIPMENT IDENTIFICATION

.1 Identify equipment cabinets with nameplates as follows:

.1 Nameplates:

Lamicoid 3 mm thick plastic engraving sheet, white face, black core,

mechanically attached with self-tapping screws or permanent self-adhesive, 20 x

90 mm, 1 line, 8 mm high letters.

.2 Identify electrical equipment with labels as follows:

.1 Labels:

Embossed plastic labels with 6mm high letters unless specified otherwise.

.3 Allow for average of twenty-five (25) letters per nameplate and label.

.4 Nameplates for terminal cabinets and junction boxes to indicate system.

.5 Terminal cabinets and pull boxes: indicate system.

2.7 WIRING IDENTIFICATION

.1 Identify wiring with permanent indelible identifying markings, either numbered or

coloured plastic tapes, on both ends of cable.

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 10 of 14

.2 Colour code: to CSA C22.1.

.3 Use colour coded wires in communication cables, matched throughout system.

2.8 CONDUIT AND CABLE IDENTIFICATION

.1 Colour code conduits, boxes and metallic sheathed cables.

.2 Code with plastic tape or paint at points where conduit or cable enters wall, ceiling, or

floor, and at 15 m intervals.

.3 Colours: 25 mm wide prime colour and 20 mm wide auxiliary colour.

Prime Auxiliary

Communication Systems Green Blue

Security Systems Red Yellow

2.9 MANUFACTURERS AND CSA LABELS

.1 Visible and legible, after equipment is installed.

2.10 FINISHES

.1 Shop finish metal enclosure surfaces by application of rust resistant primer inside and

outside, and at least two coats of finish enamel.

.2 Clean and touch up surfaces of shop-painted equipment scratched or marred during

shipment or installation, to match original paint.

.3 Clean and prime exposed non-galvanized hangers, racks and fastenings to prevent

rusting.

Part 3 Execution

3.1 EXAMINATION

.1 Verification of Conditions: verify that conditions of substrate previously installed under

other Sections or Contracts are acceptable for installation in accordance with

manufacturer's written instructions.

.1 Visually inspect substrate in presence of Consultant.

.2 Inform Consultant of unacceptable conditions immediately upon discovery.

.3 Proceed with installation only after unacceptable conditions have been remedied

and after receipt of written approval to proceed from the Consultant.

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 11 of 14

3.2 INSTALLATION

.1 Do complete installation in accordance with CSA C22.1 except where specified

otherwise.

.2 Do overhead and underground systems in accordance with CAN/CSA-C22.3 No.1 except

where specified otherwise.

3.3 NAMEPLATES AND LABELS

.1 Ensure manufacturer's nameplates, CSA labels and identification nameplates are visible

and legible after equipment is installed.

3.4 CONDUIT AND CABLE INSTALLATION

.1 Install conduit and sleeves prior to pouring of concrete.

.1 Sleeves through concrete: schedule 40 plastic, sized for free passage of conduit,

and protruding 50 mm.

.2 If plastic sleeves are used in fire rated walls or floors, remove before conduit installation.

.3 Install cables, conduits and fittings embedded or plastered over, close to building

structure so furring can be kept to minimum.

3.5 MOUNTING HEIGHTS

.1 Mounting height of equipment is from finished floor to centreline of equipment unless

specified or indicated otherwise.

.2 If mounting height of equipment is not specified or indicated, verify before proceeding

with installation.

3.6 CO-ORDINATION OF PROTECTIVE DEVICES

.1 Ensure circuit protective devices such as overcurrent trips, relays and fuses are installed

to required values and settings.

3.7 CLEANING

.1 Progress Cleaning: Leave Work area clean at end of each day.

.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools and

equipment.

.3 Waste Management: Remove recycling containers and bins from site and dispose of

materials at appropriate facility.

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 12 of 14

3.8 FIELD QUALITY CONTROL

.1 Conduct following tests in accordance with Conditions of the Contract and Section 1

Specification Section:

.1 Power distribution system including phasing, voltage, grounding and load

balancing.

.2 VFD and SCADA Control Panel System Testing.

.3 Systems: communications.

.4 Insulation resistance testing:

.1 Megger circuits, feeders and equipment up to 350 V with a 500 V

instrument.

.2 Megger 350-600 V circuits, feeders and equipment with a 1000 V

instrument.

.3 Check resistance to ground before energizing.

.2 Provide test results to Engineer.

.3 Provide instruments, meters, equipment and personnel required to conduct tests during

and at conclusion of project.

.4 Manufacturer's Field Services:

.1 Obtain written report from manufacturer verifying compliance of Work, in

handling, installing, applying, protecting and cleaning of product and submit

Manufacturer's Field Reports as described in PART 1 - SUBMITTALS.

.2 Provide manufacturer's field services consisting of product use recommendations

and periodic site visits for inspection of product installation in accordance with

manufacturer's instructions.

.3 Schedule site visits, to review Work, at stages listed.

.1 After delivery and storage of products, and when preparatory Work is

complete but before installation begins.

.2 Twice during progress of Work at 25% and 60% complete.

.5 Upon completion of work, after cleaning is carried out.

3.9 SYSTEM START-UP AND DEMONSTRATION

.1 Demonstrate to and instruct the Owner's representative on operating and maintenance

procedures for all electrical systems using the assistance of specialist sub-trades and

manufacturer's representatives for instruction and include all costs in the tender.

.2 Systems to be demonstrated shall include, but not be limited to, the following:

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 13 of 14

.1 Entire power distribution system including protection systems and interlocking

schemes.

.2 Labeling and identification schemes.

.3 Pump motor control systems.

.4 Use of Maintenance Manuals.

.3 Arrange an acceptable time with the Owner and the Engineer and submit a program of

instruction and demonstration for the Engineer's approval. Assume that the Owner's

representative is not familiar with any of the special equipment and/or systems installed.

.4 Submit to the Engineer, at the time of Substantial Performance inspection, a complete list

of systems stating for each system:

.1 Date instructions were given to the Owner's staff.

.2 Duration of instruction.

.3 Name of persons instructed.

.4 Other parties present (manufacturer's representative, Engineer, etc.).

.5 Signature of the Owner's staff stating that they properly understood the system

installation, operation, and maintenance requirements and identifying any

systems or equipment which were not demonstrated to their satisfaction and

which must be re-demonstrated.

3.10 REPORTS

.1 Contractor shall prepare test reports on the systems tested. Include a copy of each test

report in the Operation and Maintenance Manuals.

.2 The Contractor shall prepare test reports including the following:

.1 Summary of project

.2 Description of equipment tested

.3 Description of test

.4 Test results including re-testing results

.5 Test dates

.6 Tester’s name

.7 Witnesses (when required)

.8 Corrective work

.9 Acceptance criteria

.10 Conclusions and recommendations

.11 Appendix, including appropriate test form

Section 26 05 00

District of Squamish COMMON WORK RESULTS FOR ELECTRICAL

Powerhouse Springs – Well 3 Upgrade Page 14 of 14

END OF SECTION

Section 26 05 05

District of Squamish ELECTRICAL DEMOLITION

Powerhouse Springs – Well 3 Upgrade Page 1 of 2

Part 1 General

1.1 RELATED WORK

.1 This Section of the Specification forms part of the Contract Documents and is to be read,

interpreted and coordinated with all other parts.

1.2 WASTE MANAGEMENT AND DISPOSAL

.1 Separate and recycle waste materials in accordance with Section 26 05 00 Common

Work Results

.2 Avoid using landfill waste disposal procedures when recycling facilities are available.

.3 Place materials defined as hazardous or toxic waste in designated containers.

1.3 ASBESTOS

.1 If during renovations / demolition, asbestos is discovered (or material suspected to be

asbestos), all work in that area shall immediately cease and the General Contractor

advised. The General Contractor shall take appropriate action without delay to verify

presence of friable asbestos and be responsible for the removal of all friable asbestos.

.2 This division will not be entitled to a claim for any delays resulting from the

investigation of or removal of asbestos.

1.4 PCB (POLYCHLORINATED BIPHENYLS)

.1 Carefully remove any electrical items containing PCB’s (e.g. light fixture ballasts) from

equipment or fixtures to be renovated or demolished. Removed items (containing

PCB’s) to be catalogued and stored on site in approved labelled storage containers in

accordance with regulations.

1.5 SCOPE

.1 The Electrical Division to take note that demolition and renovation will be done on a

staged basis in a building that is required to remain operational 24 hours a day, seven

days a week.

.2 Remove equipment as indicated on Drawings including the following:

.1 Existing Well 3 VFD, filter, main circuit breaker, and associated control

elements in the MCC.

.2 Existing Well 3 MCC door, back plane, and associated peripherals in order to

make sufficient space available for the new VFD and controls.

.3 Existing Well 3 feeder cables.

.4 Existing Well 3 instrumentation cables.

Section 26 05 05

District of Squamish ELECTRICAL DEMOLITION

Powerhouse Springs – Well 3 Upgrade Page 2 of 2

Part 2 Products

2.1 STANDARDS

.1 Refer to applicable material standards in other specification sections and/or as detailed

on drawings.

Part 3 Execution

3.1 DEMOLITION

.1 Demolition to be carried out in strict conformance to provincial, local and municipal

authorities and the B.C. Building Code current edition.

.1 Any outages required to facilitate demolition work shall be coordinated with the

District of Squamish.

.2 All removed equipment and materials shall be disposed of off-site in accordance with

Section 26 05 00 Common Work Results unless otherwise noted.

.3 Remove all wiring and cables included in demolition work. Cutting back and

abandoning wire or cable is not acceptable.

3.2 DISRUPTION TO OPERATIONS

.1 Contractor to issue a scheduled shutdown time

.2 Contractor to provide temporary connections to all required equipment for temporary

power during the installation of any new equipment where indicated by the District of

Squamish.

3.3 REUSE OF EXISTING COMPONENTS

.1 Existing components may be reused only where so specifically indicated on the drawings

or in the specifications, however in all cases all wiring shall be new and no splicing shall

be permitted at any location unless otherwise specifically noted.

3.4 EXCAVATION AND CUTTING DAMAGE

.1 Circuits disrupted by cutting or drilling (i.e. in-wall cables) to be brought to the attention

of the consultant. Systems disturbed because due care and attention was not followed,

shall be repaired immediately at no additional cost to owner.

END OF SECTION

Section 26 05 10

District of Squamish TESTING AND COMISSIONING

Powerhouse Springs – Well 3 Upgrade Page 1 of 10

Part 1 General

1.1 SECTION INCLUDES

.1 Testing and commissioning services and equipment to assure that all electrical equipment

is operational within industry manufacturers' tolerances, calibrated per the power system

studies, complies with all applicable codes, is installed in accordance with design

specifications, and functions in the system in the manner designed by the Engineer.

.2 Inspections, calibrations, and acceptance tests for all equipment systems shall be

performed. The inspections and testing activities shall be divided among the following

groups, as specified in this Section:

.1 The original equipment manufacturer's authorized service representative shall

provide special equipment, labour, and technical supervision, when required, in

addition to what is supplied by the Contractor.

.2 Inspections, calibrations, and acceptance tests for equipment and systems not

requiring the services of the manufacturer's representative shall be performed by

the Contractor.

.3 In cases where equipment and systems require the involvement of two or all of the parties,

the parties mentioned above shall coordinate and perform all inspection and testing

requirements. The Contractor shall be responsible for coordination of the work and

ensuring that the requirements of this Section are met.

1.2 RELATED SECTIONS

.1 Section 26 05 00 – Common Work Results – Electrical

.2 Section 26 27 15 – Electrical and Controls Components

1.3 REFERENCES

.1 All inspections and tests shall be in accordance with, but not limited to, the following

applicable codes and standards except as provided otherwise in this Section.

.1 International Electrical Testing Association - NETA

.2 National Electrical Manufacturer's Association – NEMA

.3 Canadian Electrical Manufacturers Association - CEMA

.4 American Society for Testing and Materials - ASTM

.5 Institute of Electrical and Electronic Engineers – IEEE

.1 1584-2015, Guide for Performing Arc-Flash Hazard Calculations

.6 American National Standards Institute – ANSI

Section 26 05 10

District of Squamish TESTING AND COMISSIONING

Powerhouse Springs – Well 3 Upgrade Page 2 of 10

.1 ANSI Z535.4-2011, Product Safety Signs and Labels

.7 Canadian Electrical Code - Parts 1 and 2

.8 Canadian Standards Association – CSA

.1 CSA Z462-15, Workplace electrical safety, provides assistance in

determining the severity of potential exposure, planning safe work

practices, and selecting personal protective equipment to protect against

shock and arc flash hazards.

.9 Insulated Power Cable Engineers Association - IPCEA

.10 National Fire Protection Association - NFPA

.11 ANSI/NFPA 70B: Electrical Equipment Maintenance

.12 WCB Regulations

.13 CANICSA-B72-M87: Lightning Protection Code

.14 Municipal By-Laws

.2 All inspections and tests shall utilize the following references:

.1 Project design drawings and specifications

.2 Shop drawings and submittals

.3 Manufacturer's instruction manuals applicable to each particular apparatus

.4 Applicable NETA acceptance testing work scope sections per NETA ATS 2009

1.4 QUALIFICATIONS

.1 The Contractor shall retain the services of an individual that is qualified to test electrical

equipment and is approved by the Engineer.

1.5 COORDINATION

.1 Coordinate the Acceptance Testing with the Owner and Engineer.

.2 Coordinate the factory field-testing and assistance per the requirements of this Section.

1.6 SUBMITTALS

.1 Submittals shall be in accordance with Conditions of the Contract.

.2 Submit the qualifications of the individual(s) doing testing and commissioning according

to this Section for approval.

.3 Submit the coordinated test schedule for approval.

Section 26 05 10

District of Squamish TESTING AND COMISSIONING

Powerhouse Springs – Well 3 Upgrade Page 3 of 10

.4 Submit detailed test procedures corresponding to the requirements in this Section for

approval. The test procedures shall be detailed test instructions, written with sufficient

step-by-step information to allow a test to be repeated under identical conditions. List all

setpoint values and acceptable results for each condition tested.

.5 Submit a preliminary copy of the hand-written field test results to the Engineer and the

Contractor within one (1) week after the test is completed.

.6 Prior to energization of equipment, submit a letter certifying that the electrical installation

being energized complies with contract documents, applicable codes, and proper system

operation.

.7 The test reports shall be compiled and submitted in formal form with a summary.

1.7 OPERATIONS AND MAINTENANCE (O&M) MANUALS

.1 Operations and Maintenance Manuals shall be in accordance with Conditions of Contract

and Section 26 05 00.

1.8 SCHEDULING

.1 Perform all testing after installation and before energizing. All systems shall pass tests

prior to being put into service.

.2 The Contractor, in coordination with the equipment manufacturer's representatives, shall

confirm the test schedule with the Engineer prior to the test. The Contractor shall

coordinate the test schedule so that the Engineer can witness the testing, if required.

.3 The Contractor shall deliver test results to the Engineer within 7 working days of any

given test.

.4 Testing and calibration of electrical equipment shall be completed prior to the start of

commissioning activities. When required during commissioning, the Contractor shall

retest and re-calibrate equipment to support the commissioning activities.

1.9 MEETINGS

.1 Pre-installation conference: the Contractor shall request a pre-testing conference with the

Engineer (conference calls accepted).

1.10 SAFETY AND PRECAUTIONS

.1 Safety practices shall include, but are not limited to, the following requirements:

.1 Workers' Compensation Board Regulations

.2 Municipal By-Laws

Section 26 05 10

District of Squamish TESTING AND COMISSIONING

Powerhouse Springs – Well 3 Upgrade Page 4 of 10

.3 Canadian Electrical Code

.4 Electrical Safety Act of BC

.5 Municipal, Provincial and Canadian Building Code

.2 Tests shall be performed with apparatus de-energized unless otherwise specified (e.g.,

rotation, phasing).

.3 Power circuits shall have conductors shorted to ground by an approved hotline grounded

device.

.4 In all cases, work shall not proceed until the Contractor's safety representative has

determined that it is safe to do so.

.5 The Contractor shall have sufficient protective barriers and warning signs available, where

necessary, to conduct specified tests safely.

.6 The Project safety procedures shall be reviewed and accepted by the Contractor and all

sub-trades.

1.11 TEST EQUIPMENT

.1 All test equipment shall be furnished by the Contractor.

.2 Test instrument calibration

.1 The Contractor shall have a calibration program which maintains all applicable

test instrumentation within rated accuracy.

.2 The accuracy shall be traceable to the National Bureau of Standards in an

unbroken chain.

.3 Up-to-date calibration labels shall be visible on all test equipment.

.3 Use of torque wrenches

.1 Use calibrated torque wrenches for all bolted connections on buses and power

cable terminations. Mark the head of the bolt with a coloured marking pen after

its being torqued to manufacturer's recommended value.

Part 2 Execution

2.1 REQUIREMENTS

.1 Perform acceptance tests in accordance with manufacturer's recommendations, WCB

regulations, and the latest version of NETA ATS testing specifications.

Section 26 05 10

District of Squamish TESTING AND COMISSIONING

Powerhouse Springs – Well 3 Upgrade Page 5 of 10

.2 Voltage adjustments shall be in accordance with CSA CAN3-C235.83, Preferred Voltage

Levels for AC Systems, to 50,000 V.

.3 The test plan, procedures, test results, and reports shall be reviewed, under the supervision

of and approved by the Engineer.

.4 Division of responsibility

.1 The Contractor shall torque down all accessible bolts, perform routine insulation

resistance and continuity tests on branch and feeder circuits, and perform

rotational tests for all distribution and utilization equipment, prior to, and in

addition to tests performed by the Contractor specified in this Section.

.2 The Contractor shall supply a suitable and stable source of test power at each test

site.

.3 The Contractor shall clean all the electrical equipment prior to testing.

.4 The Contractor shall be responsible for implementing all final settings and

adjustments on protective devices and electrical equipment in accordance with the

Power System Protective Device Studies.

.5 Any questions or concerns identified shall be promptly addressed to the Engineer.

.6 Any system, material, or workmanship which is found defective on the basis of electrical

inspections and tests shall be reported directly to the Engineer.

.7 If a test reveals a fault or problem, the materials of equipment under test will be repaired or

replaced and the entire test will be repeated. Tests will not be accepted until the problem

is corrected. Submit additional written test reports

.8 Maintain a written record of all tests and, upon completion of the project, assemble and

certify a final test report. The field test reports shall be compiled and signed by the

individual performing the testing.

.9 Power systems protective device calibration

.1 Adjustments, settings, and modifications

.1 The Contractor shall calibrate necessary field settings, adjustments, and

minor modifications to conform to the coordination study without

additional cost (examples of minor modifications are trip sizes within the

same frame, the time curve characteristics of induction relays, ranges,

etc.).

.2 Adjust or replace protective devices to the values provided in the

coordination study.

.3 The trip characteristics, when adjusted to setting parameters, shall fall

within the manufacturer's published time-current characteristic tolerance.

Section 26 05 10

District of Squamish TESTING AND COMISSIONING

Powerhouse Springs – Well 3 Upgrade Page 6 of 10

.2 The Contractor shall verify that the protective devices have been adjusted and set

in accordance with the approved Power System Study.

.10 Acceptance criteria

.1 Each function and test shall be performed under conditions which simulate actual

operating conditions as closely as possible.

.1 To that end, the Contractor shall provide all necessary materials,

equipment, and temporary system voltages and currents to simulate fault

conditions on the system being tested in order to prove and verify proper

operation (fuses excepted).

.2 At satisfactory completion of all verified tests, the building electrical

system being tested shall be returned to the condition required by the

contract documents as a complete and operational system.

.2 The Contractor shall perform general inspections at the job site and shall also

review the following:

.1 Assembly of the accessory equipment, and the interconnecting wiring for

control circuits.

.2 General inspection of the following: appearance, finish, alignment of

doors, covers, and similar parts; quality of workmanship; possible

shipping and other damage; missing, broken or incorrectly applied

devices; loose or missing accessories, bushings, or hardware; loose or

broken wires; proper installation of all equipment; verification that shop

drawings and instructions have been shipped with all equipment and are

available.

.3 Support of electrical equipment: inspect and check all electrical

equipment for support and seismic bracing.

.4 Spare equipment: the Contractor shall inspect and verify spare equipment

inventory as specified by Division 26.

.11 System Operational Testing requirements and procedures

.1 The following equipment and systems shall be inspected and tested by the

Contractor per manufacturer's instructions and additional requirements noted.

.2 The following tests require that the Contractor provide materials, tools, and labour

(qualified personnel) to prepare equipment and devices for testing and to perform

tests and to make adjustments and recalibrations for re-testing as necessary and to

reconnect systems after the testing is completed. Include in the Tender, all costs

associated with the provision of labour to remove and re-install panel plates, to

disconnect/reconnect cables, and perform any labour other than testing, and to

provide any materials and tools.

.1 Variable Frequency Drive (VFD):

.1 The Contractor shall test the VFDs for hand operation including

ensuring pump rotation is correct.

Section 26 05 10

District of Squamish TESTING AND COMISSIONING

Powerhouse Springs – Well 3 Upgrade Page 7 of 10

.2 The Contractor shall configure the VFD for ramp operation using

Modbus RTU for remote auto operation.

.3 The Contractor shall configure the VFD ramp, min, max, and

system details per the well pump motor requirements and

manufacturers recommendations.

.2 Level Transducer:

.1 The Contractor shall test the output of the level transducer for

varying levels within the well and compare to actual well level

readings using static measuring tape or other standard recognized

means.

.2 The Contractor shall ensure the unit is calibrated and provides the

appropriate 4-20mA signal to the site PLC based control system.

.3 Flow Meter:

.1 The Contractor shall test the output of the flow meter for varying

flows from the well and compare to actual flows measured using a

separate flow measuring device.

.2 The Contractor shall ensure the unit is calibrated and provides the

appropriate 4-20mA signal to the site PLC based control system.

.3 The following equipment shall be inspected and tested by the Contractor.

Coordinate activities with the manufacturer's authorized service representatives.

.1 The Contractor shall use his own forces and the forces of his suppliers and

Subcontractors for the following tests:

.1 Control and switching - all circuits shall be tested for the correct

operation of devices, switches, and controls, including sequenced

operation of systems where applicable.

.2 Include in the written reports to the Engineer, the time and date on

which each load was measured and the voltage at time of test.

.2 General power system tests

.1 Megger test all 120 V and higher circuits, feeders, and equipment.

.2 Check resistance to ground before energizing any equipment.

.3 Phase balance - when load conditions are commensurate with

actual operating conditions, measure the load and the voltage on

each phase at each switchboard, splitter, motor control centre,

motor distribution centre, distribution panelboard, and lighting

and power panelboard and report the results, including neutral

currents, in writing to the Engineer. Rearrange circuit

connections as necessary to balance the load on each phase to

within 15% of average load. After making any such changes,

make available to the Engineer marked prints showing the

modified connections.

.4 Motor loading - measure the line current of each phase of each

motor with the motor operating under load and report the results

Section 26 05 10

District of Squamish TESTING AND COMISSIONING

Powerhouse Springs – Well 3 Upgrade Page 8 of 10

along with the motor nameplate current in writing to the

Engineer. Upon indication of any unbalance or overload,

thoroughly examine the electrical connections and rectify any

defective parts or wiring. If electrical connections are correct,

overloads due to defects in the driven machines shall be reported

in writing to the Engineer.

.5 Phase relationship tests: Check connections to all new and

existing equipment, outlets and devices for proper phase

relationship. During such check, disconnect all devices which

could be damaged by the application of voltage or reversed phase

sequence.

.3 Low voltage feeder and branch circuit conductors (600 V and below)

.1 Test for continuity of each lighting and heating circuit originating

from branch distribution panels.

.2 Test for grounds in each circuit; test shall consist of the physical

examination of the installation to ensure that all required ground

jumpers, devices, and appurtenances do exist and are

mechanically firm.

.3 Perform a 500V M-Ohm meter test on each circuit between the

conductor and ground. The insulation resistance shall not be less

than 2 megohms for circuits under 120V, 6 M-Ohms between

conductor and ground on those circuits (120 - 600 V) with total

single conductor length of 2,500 feet and over, nor less than 8 M-

Ohms for those circuits (120 - 600 V) with single conductor

length of less than 2500 feet. If conductor fails test, replace

wiring or correct defect and retest.

.4 Perform torque test for every conductor tested and terminated in

an overcurrent device or bolted type connection; torque all

connections per manufacturer's recommendations.

.4 Grounding systems

.1 Verify that neutrals are grounded only at the main service by

removing the service neutral grounding conductor and meggering

the neutral bus.

.2 Perform point-to-point tests to determine the resistance between

the main grounding system and all major electrical equipment

frames, system-neutral, and/or derived neutral points. Investigate

resistance values, which exceed 0.5 ohm. If this resistance cannot

be obtained with the ground system, notify the Contractor and, in

turn, the Engineer for further instruction.

.5 Technical verification: Purpose to ensure that all systems and devices are

properly installed and free of defects and damage. Technical verification

includes:

.1 Measurements of tension and power.

Section 26 05 10

District of Squamish TESTING AND COMISSIONING

Powerhouse Springs – Well 3 Upgrade Page 9 of 10

.2 Connecting joints and equipment fastening.

.3 Measurements of signals (dB, lux, baud rate, etc).

.4 Compliance with manufacturer's specification, product literature

and installation instructions.

.6 Operational verification: Purpose to ensure that devices and systems'

performance meet or exceed established functional requirements.

Specific Operational Requirements are listed within Section 26 27 15 -

Electrical and Controls Components. Operational verification includes:

.1 Operation of VFDs and pump motors.

.2 Operation of each device individually and within its environment.

.3 Operation of the external devices, including:

.1 Level sensors

.2 Flow meters

.4 Demonstrate:

.1 Integration of Level sensor with level sensor display unit.

.12 Labels

.1 Upon completion of the inspection, calibration, and testing, attach a label to all

devices tested. These labels shall indicate the date tested, the Contractor company

name, and tester's initials.

.13 Re-testing

.1 Any fault in material or in any part of the installation revealed by these tests shall

be investigated, replaced, or repaired by the Contractor and the same test repeated

by the Contractor at Contractor's expense until no fault appears.

2.2 DEMONSTRATION AND TRAINING

.1 Demonstrate and instruct the Owner's personnel on operating and maintenance procedures

for all electrical systems using the assistance of specialist sub-trades and manufacturer's

representatives for instruction, and include all such costs in the Tender. Systems to be

demonstrated and trained on shall include, but not be limited to, the following:

.1 Entire control system and associated components.

.2 Labeling and identification schemes.

.3 Use of Maintenance Manuals.

.2 Arrange an acceptable time with the Owner and the Engineer and submit a program of

instruction and demonstration for the Owner's approval. Assume that the Owner's

personnel are not familiar with any of the special equipment and/or systems installed.

.3 Submit to the Engineer, at the time of Substantial Performance inspection, a complete list

of systems demonstrated and training completed, and state for each system:

Section 26 05 10

District of Squamish TESTING AND COMISSIONING

Powerhouse Springs – Well 3 Upgrade Page 10 of 10

.1 Date that instructions were given to the Owner’s staff.

.2 Duration of instruction.

.3 Names of persons instructed.

.4 Other parties present (manufacturer’s representative, Engineer, etc.).

.5 Signature of the Owner’s staff stating that they properly understood the system

installation, operation, and maintenance requirements and identifying any systems

or equipment which were not demonstrated to their satisfaction and which must be

re-demonstrated.

2.3 REPORTS

.1 Contractor shall prepare test reports on the systems tested. Include a copy of each test

report in the Operation and Maintenance Manuals.

.2 The Contractor shall prepare test reports including the following:

.1 Summary of project

.2 Description of equipment tested

.3 Description of test

.4 Test results including re-testing results

.5 Test dates

.6 Tester’s name

.7 Witnesses (when required)

.8 Corrective work

.9 Acceptance criteria

.10 Conclusions and recommendations

.11 Appendix, including appropriate test forms

END OF SECTION

Section 26 05 20

District of Squamish WIRE AND BOX CONNECTORS (0-1000V)

Powerhouse Springs – Well 3 Upgrade Page 1 of 3

Part 1 General

1.1 RELATED SECTIONS

.1 Section 26 05 00 - Common Work Results for Electrical

1.2 SECTION INCLUDES

.1 Materials and installation for wire and box connectors.

1.3 REFERENCES

.1 Canadian Standards Association (CSA International)

.1 CAN/CSA-C22.2No.18.1-06, Metallic Outlet Boxes

.2 CAN/CSA-C22.2No.18.2-06, Nonmetallic Outlet Boxes

.3 CAN/CSA-C22.2No.18.3-04 (R2011), Conduit, Tubing, and Cable Fittings

.4 CAN/CSA-C22.2No.18.4-04 (R2011), Hardware for the Support of Conduit,

Tubing

.5 CAN/CSA-C22.2No.18.5-02 (R2011), Positioning Devices

.6 CSA C22.2No.65-03(R2008)], Wire Connectors.

.2 Electrical and Electronic Manufacturers' Association of Canada (EEMAC)

.1 EEMAC 1Y-2, 1961 Bushing Stud Connectors and Aluminum Adapters (1200

Ampere Maximum Rating).

.3 National Electrical Manufacturers Association (NEMA)

1.4 WASTE MANAGEMENT AND DISPOSAL

.1 Separate and recycle waste materials in accordance with Contract Requirements.

.2 Remove from site and dispose of all packaging materials at appropriate recycling

facilities.

.3 Collect and separate for disposal paper, plastic, polystyrene, corrugated cardboard and

other recyclable packaging material in appropriate on-site bins for recycling in

accordance with Waste Management Plan.

.4 Divert unused wiring materials from landfill to metal recycling facility as approved by

Engineer.

Section 26 05 20

District of Squamish WIRE AND BOX CONNECTORS (0-1000V)

Powerhouse Springs – Well 3 Upgrade Page 2 of 3

Part 2 Products

2.1 MATERIALS

.1 Pressure type wire connectors to: CSA C22.2No.65, with current carrying parts of copper

sized to fit copper conductors as required.

.2 Fixture type splicing connectors to: CSA C22.2No.65, with current carrying parts of

copper sized to fit copper conductors 10 AWG or less.

.3 Bushing stud connectors: to EEMAC 1Y-2 to consist of:

.1 Connector body and stud clamp for copper conductors.

.2 Clamp for stranded copper conductors.

.3 Stud clamp bolts.

.4 Bolts for copper conductors.

.5 Sized for conductors as indicated.

.4 Clamps or connectors for armoured cable and flexible conduit as required to:

CAN/CSA-C22.2No.18 (all subsections).

Part 3 Execution

3.1 EXAMINATION

.1 Verification of Conditions: verify that conditions of substrate previously installed under

other Sections or Contracts are acceptable for wire and box connectors installation in

accordance with manufacturer's written instructions.

.1 Visually inspect substrate in presence of Consultant or provide photographic

evidence of areas of concern.

.2 Inform Consultant of unacceptable conditions immediately upon discovery.

.2 Proceed with installation only after unacceptable conditions have been remedied.

3.2 INSTALLATION

.1 Remove insulation carefully from ends of conductors and:

.1 Install mechanical pressure type connectors and tighten screws with appropriate

compression tool recommended by manufacturer. Installation shall meet

secureness tests in accordance with CSA C22.2No.65.

.2 Install fixture type connectors and tighten. Replace insulating cap.

.3 Install bushing stud connectors in accordance with EEMAC 1Y-2.

3.3 CLEANING

.1 Progress Cleaning: Leave Work area clean at end of each day.

Section 26 05 20

District of Squamish WIRE AND BOX CONNECTORS (0-1000V)

Powerhouse Springs – Well 3 Upgrade Page 3 of 3

.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools and

equipment.

.3 Waste Management: separate waste materials for recycling in accordance with Contract

Documents.

.1 Remove recycling containers and bins from site and dispose of materials at

appropriate facility.

END OF SECTION

Section 26 05 21

District of Squamish WIRES AND CABLES (0-1000V)

Powerhouse Springs – Well 3 Upgrade Page 1 of 4

Part 1 General

1.1 RELATED SECTIONS

.1 Section 26 05 00 - Common Work Results for Electrical

.2 Section 26 05 20 - Wire and Box Connectors - 0 - 1000 V.

1.2 REFERENCES

.1 CSA C22.2 No .0.3-09, Test Methods for Electrical Wires and Cables.

1.3 PRODUCT DATA

.1 Submit product data in accordance with Section 01 33 00 - Submittal Procedures.

Part 2 Products

2.1 BUILDING WIRES

.1 Conductors: stranded for 10 AWG and larger. Minimum size: 12 AWG.

.2 Copper conductors (Non Pump Cables): size as indicated, with 600 V insulation of cross-

linked thermosetting polyethylene material rated RW90 XLPE, Jacketted.

.3 Copper conductors (Pump Cables): size as indicated, with 1000 V insulation of cross-

linked thermosetting polyethylene material rated RW90 XLPE, Jacketted.

.4 Copper conductors: size as indicated, with thermoplastic insulation type TWU rated at

600 V.

2.2 TECK 90 CABLE

.1 Cable: in accordance with Section 26 05 00 - Common Work Results for Electrical.

.2 Conductors:

.1 Grounding conductor: copper as indicated.

.2 Circuit conductors: copper as indicated, size as indicated.

.3 Insulation:

.1 Cross-linked polyethylene XLPE.

.2 Rating: , 600 V.

.4 Inner jacket: polyvinyl chloride material.

.5 Armour: interlocking galvanized steel.

Section 26 05 21

District of Squamish WIRES AND CABLES (0-1000V)

Powerhouse Springs – Well 3 Upgrade Page 2 of 4

.6 Overall covering: thermoplastic polyvinyl chloride, compliant to applicable Building

Code classification for this project.

.7 Fastenings:

.1 One hole aluminum straps to secure surface cables 50 mm and smaller. Two hole

steel straps for cables larger than 50 mm.

.2 Channel type supports for two or more cables at 300 mm centers.

.3 Threaded rods: 6 mm diameter to support suspended channels.

.8 Connectors:

.1 Watertight approved for TECK cable.

2.3 CONTROL CABLES

.1 Type: LVT: [2] soft annealed copper conductors, sized as indicated:

.1 Insulation: thermoplastic.

.2 Sheath: thermoplastic jacket.

.2 Type: low energy 300 V control cable: stranded annealed copper conductors sized as

indicated LVT: [2] soft annealed copper conductors, sized as indicated:

.1 Insulation: polyethylene.

.2 Shielding: braid and foil over each pair.

.3 Overall covering: PVC jackets.

.3 Type: 600 V stranded annealed copper conductors, sizes as indicated:

.1 Insulation: polyethylene.

.2 Shielding: braid over each pair of conductors.

.3 Overall covering: PVC.

2.4 STANDARDS (UTP AND DATA CABLING)

.1 Except where specifically modified within this specification, the installation shall, as

minimum, comply with the latest issues of the following standards:

.1 CAN/CSA-T527, “Commercial Building Grounding and Bonding Requirements

for Telecommunications”

.2 CAN/CSA-T528-93(R2001), “Design Guideline for Administration

Telecommunications Infrastructure in Commercial Buildings”

.3 CAN/CSA-C22.2 No. 182.4, “Plugs, Receptacles, and Connectors for

Communication Systems”.

.4 EIA/TIA Bulletin TSB-36, Technical Systems Bulletin Additional Cable

Specifications for Unshielded Twisted Pair Cables, Electronic Industries

Association (USA), November 1991.

.5 The installation shall, as minimum, comply with the latest issues of the following

Building Codes: All municipal By-laws, Provincial Codes, The BC Building

Section 26 05 21

District of Squamish WIRES AND CABLES (0-1000V)

Powerhouse Springs – Well 3 Upgrade Page 3 of 4

Code, The Canadian Electrical Code, Canadian Labour Code, and the BC Fire

Code. In the case of conflict or discrepancy the more stringent code shall apply.

.6 TIA/EIA-606-A

Part 3 Execution

3.1 FIELD QUALITY CONTROL

.1 Perform tests in accordance with Section 26 05 00 - Common Work Results for

Electrical.

.2 Perform tests using method appropriate to site conditions and to approval of Consultant

and local authority having jurisdiction over installation.

.3 Perform tests before energizing electrical system.

3.2 GENERAL CABLE INSTALLATION

.1 Terminate cables in accordance with Section 26 05 20 - Wire and Box Connectors - (0-

1000 V).

.2 Cable Colour Coding: to Section 26 05 00 Common Work Results for Electrical.

.3 All cabling shall be installed in conduit except in electrical/mechanical rooms where

cabling is terminated.

3.3 INSTALLATION OF BUILDING WIRES

.1 Install wiring as follows:

.1 In conduit systems in accordance with Section 26 05 34 - Conduits, Conduit

Fastenings and Conduit Fittings.

3.4 INSTALLATION OF TECK90 CABLE (0 -1000 V)

.1 Group cables wherever possible on channels.

.2 Install cable exposed, securely supported by straps or hangers.

3.5 INSTALLATION OF ARMOURED CABLES

.1 Group cables wherever possible on channels.

3.6 TESTING GENERAL

.1 Cabling and connectors to be tested by an experienced company employing

trained technicians with a minimum of 5 years experience in the cabling industry.

Provide at the initial project meeting, the name of the company to be performing

Section 26 05 21

District of Squamish WIRES AND CABLES (0-1000V)

Powerhouse Springs – Well 3 Upgrade Page 4 of 4

the connection and testing of cables, and a listing of the qualifications of the

technicians to be performing the work.

.2 The Departmental Representative reserves the right to approve or reject any

company being proposed to perform this work based on that company’s previous

experience or training.

.3 Testing to include verification of cable configurations between connected

equipment.

END OF SECTION

Section 26 05 22

District of Squamish CONNECTORS AND TERMINATIONS

Powerhouse Springs – Well 3 Upgrade Page 1 of 2

Part 1 General

1.1 RELATED SECTIONS

.1 Section 26 05 00 - Common Work Results for Electrical

1.2 SECTION INCLUDES

.1 Materials and installation for connectors and terminations.

1.3 REFERENCES

.1 Canadian Standards Association (CSA International)

.1 CSA C22.2No.65-03 (R2008) Wire Connectors

.2 CSA C22.2 No.41-07, Grounding and Bonding Equipment.

1.4 PRODUCT DATA

.1 Submit product data in accordance with Contract Documents.

1.5 DELIVERY, STORAGE AND HANDLING

.1 Deliver, store and handle materials in accordance with manufacturer's written

instructions.

.2 Delivery and Acceptance Requirements: deliver materials to site in original factory

packaging, labelled with manufacturer's name and address.

.3 Storage and Handling Requirements:

.1 Store materials indoors in dry location and in accordance with manufacturer's

recommendations in clean, dry, well-ventilated area.

.2 Store and protect hangers and supports from nicks, scratches, and blemishes.

.3 Replace defective or damaged materials with new.

Part 2 Products

2.1 CONNECTORS AND TERMINATIONS

.1 Copper compression connectors to CSA C22.2No.65 as required sized for conductors.

Section 26 05 22

District of Squamish CONNECTORS AND TERMINATIONS

Powerhouse Springs – Well 3 Upgrade Page 2 of 2

Part 3 Execution

3.1 INSTALLATION

.1 Install terminations, and splices in accordance with manufacturer's instructions.

.2 Bond and ground as required to CSA C22.2No.41.

END OF SECTION

SECTION 26 05 28

District of Squamish GROUNDING AND BONDING

Powerhouse Springs – Well 3 Upgrade PAGE 1 OF 3

Part 1 General

1.1 Related Work

.1 This Section of the Specification forms part of the Contract Documents and is to be read,

interpreted and coordinated with all other parts.

1.2 Waste Management and Disposal

.1 Avoid using landfill waste disposal procedures when recycling facilities are available.

.2 Place materials defined as hazardous or toxic waste in designated containers.

1.3 Reference Standards

.1 American National Standards Institute (ANSI)/Institute of Electrical and Electronics

Engineers (IEEE)

.2 Transformer grounding shall comply with CSA C22.2 No.41.

.3 All grounding conductors to be stranded soft annealed copper unless otherwise noted.

.4 Install complete grounding and bonding system in accordance with Canadian Electrical

Code and local inspection authority requirements.

1.4 Testing Requirements

.1 Perform ground continuity and resistance tests using method appropriate to site

conditions. Measure ground grid resistance.

.2 Any third party testing agency costs for the testing and reporting shall be included in the

Electrical Division base tender and shall be carried out by a pre-approved testing agency.

1.5 Additional Scope

.1 Refer to drawings for extent of grounding in addition to code requirements.

Part 2 Products

2.1 Materials

.1 Grounding equipment to: CSA C22.2 No.41.

2.2 Equipment

.1 Clamps for grounding of conductor, size as required.

SECTION 26 05 28

District of Squamish GROUNDING AND BONDING

Powerhouse Springs – Well 3 Upgrade PAGE 2 OF 3

.2 System and circuit, equipment, grounding conductors, bare stranded copper, soft

annealed, sized as indicated. Insulation where specified to be green.

.3 Ground bus: copper, size as indicated, complete with insulated supports, fastenings,

connectors.

.4 Non-corroding accessories necessary for grounding system, type, size material as

indicated, including but not necessarily limited to:

.1 Grounding and bonding bushings.

.2 Protective type clamps.

.3 Bolted type conductor connectors.

.4 Thermit welded type conductor connectors.

.5 Bonding jumpers, straps.

.6 Pressure wire connectors.

Part 3 Execution

3.1 Installation General

.1 Install complete permanent, continuous grounding system including, electrodes,

conductors, connectors, accessories.

.2 Install connectors in accordance with manufacturer's instructions.

.3 Protect exposed grounding conductors from mechanical injury.

.4 Use mechanical connectors for grounding connections to equipment provided with lugs.

.5 Soldered joints not permitted.

.6 Install bonding wire for flexible conduit, connected at both end to grounding bushing,

solderless lug, clamp or cup washer and screw. Neatly cleat bonding wire to exterior of

flexible conduit. Provide a ground conductor in all flexible conduit and secure to

system grounding lugs at both the equipment and source.

.7 Install flexible ground straps for bus duct enclosure joints, where such bonding is not

inherently provided with equipment.

.8 Install separate ground conductor to each outdoor lighting standard.

.9 Connect building structural steel and metal siding to ground by welding copper to steel.

.10 Make grounding connections in radial configuration only, with connections terminating

at single grounding point. Avoid loop connections.

.11 Bond single conductor, metallic armoured cables to cabinet at supply end and provide

non-metallic entry plate at load end.

SECTION 26 05 28

District of Squamish GROUNDING AND BONDING

Powerhouse Springs – Well 3 Upgrade PAGE 3 OF 3

3.2 Grounding Busses

.1 Ground items of electrical equipment in electrical room to ground bus with individual

bare stranded copper connections size #3/0 AWG or as indicated.

.2 Copper or bronze lugs required for termination of all copper conductors at ground

busses.

3.3 Equipment Grounding or Bonding

.1 Provide a grounding conductor from the secondary of every distribution transformer to

the grounding system. Ground conductor to be sized and installed in accordance with

Canadian Electrical Code.

3.4 Field Quality Control

.1 Perform tests in accordance with Section 26 05 00 – Common Work Results.

.2 Perform ground continuity and resistance tests using method appropriate to site

conditions.

END OF SECTION

Section 26 05 29

District of Squamish HANGERS & SUPPORTS FOR ELECTRICAL SYSTEMS

Powerhouse Springs – Well 3 Upgrade Page 1 of 2

Part 1 General

1.1 RELATED SECTIONS

.1 Section 26 05 00 - Common Work Results for Electrical

1.2 DELIVERY, STORAGE AND HANDLING

.1 Deliver, store and handle materials in accordance with Contract Documents.

.2 Delivery and Acceptance Requirements: deliver materials to site in original factory

packaging, labelled with manufacturer's name and address.

.3 Storage and Handling Requirements:

.1 Store the materials indoors off of the ground and in accordance with

manufacturer's recommendations in clean, dry, well-ventilated area.

.2 Store and protect hangers and supports from nicks, scratches, and blemishes.

.4 Replace defective or damaged materials with new.

Part 2 Products

2.1 SUPPORT CHANNELS

.1 Select channel as indicated in the drawings:

.1 U shape, galvanized steel, size 41 x 41 mm, 2.5 mm thick, surface mounted and

suspended.

Part 3 Execution

3.1 EXAMINATION

.1 Verification of Conditions: verify that conditions of substrate previously installed under

other Sections or Contracts are acceptable for hangers and supports installation in

accordance with manufacturer's written instructions.

.1 Visually inspect substrate in presence of Consultant or provide photographic

evidence of areas of concern.

.2 Inform Consultant of unacceptable conditions immediately upon discovery.

.3 Proceed with installation only after unacceptable conditions have been remedied.

3.2 INSTALLATION

.1 Secure equipment to poured concrete with expandable inserts.

.2 Secure equipment to hollow masonry walls or suspended ceilings with toggle bolts.

Section 26 05 29

District of Squamish HANGERS & SUPPORTS FOR ELECTRICAL SYSTEMS

Powerhouse Springs – Well 3 Upgrade Page 2 of 2

.3 Support equipment, conduit or cables using clips, spring loaded bolts, cable clamps

designed as accessories to basic channel members.

.4 Fasten exposed conduit or cables to building construction or support system using straps.

.1 One-hole stainless steel straps to secure surface conduits and cables 50 mm and

smaller.

.2 Two-hole stainless steel straps for conduits and cables larger than 50 mm.

.3 Beam clamps to secure conduit to exposed steel work.

.5 Suspended support systems.

.1 Support individual cable or conduit runs with 6 mm dia threaded rods and spring

clips.

.2 Support 2 or more cables or conduits on channels supported by 6 mm dia

threaded rod hangers where direct fastening to building construction is

impractical.

.6 For surface mounting of two or more conduits use channels at 1000 mm on centre

spacing.

.7 Provide metal brackets, frames, hangers, clamps and related types of support structures

where indicated or as required to support conduit and cable runs.

.8 Ensure adequate support for raceways and cables dropped vertically to equipment where

there is no wall support.

.9 Do not use wire lashing or perforated strap to support or secure raceways or cables.

.10 Do not use supports or equipment installed for other trades for conduit or cable support

except with permission of other trade and approval of Engineer.

.11 Install fastenings and supports as required for each type of equipment cables and

conduits, and in accordance with manufacturer's installation recommendations.

3.3 CLEANING

.1 Progress Cleaning: Leave Work area clean at end of each day.

.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools and

equipment.

END OF SECTION

Section 26 05 31

District of Squamish SPLITTERS, JUNCTION, PULL BOXES AND CABINETS

Powerhouse Springs – Well 3 Upgrade Page 1 of 3

Part 1 General

1.1 RELATED SECTIONS

.1 Section 26 05 00 - Common Work Results for Electrical

1.2 REFERENCES

.1 Canadian Standards Association (CSA International)

.1 CSA C22.1-15, Canadian Electrical Code, Part 1, 23th Edition.

1.3 ACTION AND INFORMATIONAL SUBMITTALS

.1 Provide submittals in accordance with Contract Documents.

.2 Product Data:

.1 Provide manufacturer's printed product literature, specifications and datasheet and

include product characteristics, performance criteria, physical size, finish and

limitations.

.3 Provide shop drawings: in accordance with Contract Documents.

1.4 DELIVERY, STORAGE AND HANDLING

.1 Waste Management and Disposal:

.1 Separate waste materials for recycling in accordance with Contract Documents.

Part 2 Products

2.1 SPLITTERS

.1 Construction: sheet metal enclosure, welded corners and formed hinged cover suitable for

locking in closed position.

.2 Terminations: main and branch lugs or connection blocks to match required size and

number of incoming and outgoing conductors as indicated.

.3 Spare Terminals: minimum three spare terminals or lugs on each connection or lug block

sized less than 400 A.

2.2 JUNCTION AND PULL BOXES

.1 NEMA 4X stainless steel construction with screw-on flat covers for surface mounting.

All mounting hardware to be stainless steel.

.2 Provide hinged lockable covers where noted on the drawings.

.3 Covers with 25 mm minimum extension all around, for flush-mounted pull and junction

boxes.

Section 26 05 31

District of Squamish SPLITTERS, JUNCTION, PULL BOXES AND CABINETS

Powerhouse Springs – Well 3 Upgrade Page 2 of 3

.4 Provide Type 10 underground pull boxes that meet the requirements of the Ministry

Electrical and Signing Material Standards Section 201 and the Plans.

2.3 CABINETS

.1 Application: house electrical equipment within Electrical Room providing a degree of

protection from falling dirt, dust, oil, and water.

.2 Enclosures shall be a rigid, wall mounted, and rated CSA Type 12.

.3 Construction:

.1 Enclosures shall be fabricated from 14 gauge steel.

.2 Smooth, continuously welded seams without knockouts, cutouts, or holes.

.3 Welded brackets for enclosure mounting.

.4 Formed lip on door and enclosure to prevent ingress of flowing liquids and

contaminants.

.5 Continuously hinged door with provision for removal by pulling hinge pin.

.6 Door secured with stainless steel clamps including provision for padlocking.

.7 Permanently secured continuous gasket around door.

.8 Removable inner back and side panels, as required.

.9 Bonding studs on door, enclosure, and panels.

.10 Literature pocket located on inside of door.

.11 Heating and ventilation per the drawings.

.4 Finish:

.1 Door and enclosure shall be finished in recoatable smooth ANSI 61 gray powder

coating inside and out.

.2 Inner panels shall be finished with white powder coating.

.5 Enclosure dimensions on Drawings are approximate only. Contractor to determine final

enclosure dimensions to layout all of proposed equipment.

.6 All enclosure assemblies shall be from the same manufacturer, shall bear the C.S.A. seal

of approval, or other certification mark acceptable in the Province of British Columbia,

and be manufactured by an electrical control panel manufacturer regularly engaged in this

type of work.

.7 Shop drawings for the electrical kiosk to be submitted in accordance with Section 26 05 00

Common Work Results - Electrical.

.8 Standard of acceptance: Hammond Manufacturing, or equivalent.

Part 3 Execution

3.1 SPLITTER INSTALLATION

.1 Mount plumb, true and square to building lines.

Section 26 05 31

District of Squamish SPLITTERS, JUNCTION, PULL BOXES AND CABINETS

Powerhouse Springs – Well 3 Upgrade Page 3 of 3

.2 Extend splitters full length of equipment arrangement except where indicated otherwise.

3.2 JUNCTION, PULL BOXES AND CABINETS INSTALLATION

.1 Install pull boxes in inconspicuous but accessible locations.

.2 Mount cabinets with top not higher than 2 m above finished floor.

.3 Install equipment and terminal blocks as indicated in cabinets.

.4 Only main junction and pull boxes are indicated. Install pull boxes so as not to exceed 30

m of conduit run between pull boxes.

3.3 IDENTIFICATION

.1 Provide equipment identification in accordance with Section 26 05 01 - Common Work

Results - Electrical.

.2 Install size 2 identification labels indicating system name, voltage, and phase.

END OF SECTION

Section 26 05 32

District of Squamish OUTLET BOXES, CONDUIT BOXES AND FITTINGS

Powerhouse Springs – Well 3 Upgrade Page 1 of 2

Part 1 General

1.1 RELATED SECTIONS

.1 Section 26 05 00 – Common Work Results - Electrical

1.2 REFERENCES

.1 CSA C22.1-15, Canadian Electrical Code, Part 1 (23nd Edition), Safety Standard for

Electrical Installations.

1.3 WASTE MANAGEMENT AND DISPOSAL

.1 In accordance with Section 26 05 00 – Common Work Results – Electrical

Part 2 Products

2.1 OUTLET AND CONDUIT BOXES GENERAL

.1 Size boxes in accordance with CSA C22.1.

.2 102 mm square or larger outlet boxes as required for special devices.

.3 Gang boxes where wiring devices are grouped.

.4 Blank cover plates for boxes without wiring devices.

.5 240V outlet boxes for 240V switching devices.

.6 Combination boxes with barriers where outlets for more than one system are grouped.

2.2 CONDUIT BOXES

.1 FS or FD RPVC boxes with factory-threaded hubs and mounting feet for surface wiring

of switches and receptacles. Non-threaded hubs for use with teck cable as applicable.

.1 NEMA 12 rating for interior installation.

.2 NEMA 4 rating for exterior locations.

2.3 FITTINGS - GENERAL

.1 Bushing and connectors with nylon insulated throats.

.2 Knock-out fillers to prevent entry of debris.

.3 Conduit outlet bodies for conduit up to 32 mm and pull boxes for larger conduits.

.4 Double locknuts and insulated bushings on sheet metal boxes.

Section 26 05 32

District of Squamish OUTLET BOXES, CONDUIT BOXES AND FITTINGS

Powerhouse Springs – Well 3 Upgrade Page 2 of 2

Part 3 Execution

3.1 INSTALLATION

.1 Support boxes independently of connecting conduits.

.2 Fill boxes with paper, sponges or foam or similar approved material to prevent entry of

debris during construction. Remove upon completion of work.

.3 Provide correct size of openings in boxes for conduit, and armoured cable connections.

Reducing washers are not allowed.

END OF SECTION

Section 26 05 34

District of Squamish CONDUITS, CONDUIT FASTENINGS & FITTINGS

Powerhouse Springs – Well 3 Upgrade Page 11214of 4

Part 1 General

1.1 RELATED SECTIONS

.1 Section 26 05 00 - Common Work Results for Electrical

1.2 REFERENCES

.1 Canadian Standards Association (CSA)

.1 CAN/CSA C22.2 No. 18-98(R2003), Outlet Boxes, Conduit Boxes, Fittings and

Associated Hardware, A National Standard of Canada.

.2 CSA C22.2 No. 45-M1981(R2003), Rigid Metal Conduit.

.3 CSA C22.2 No. 56-04, Flexible Metal Conduit and Liquid-Tight Flexible Metal

Conduit.

.4 CSA C22.2 No. 83-M1985(R2003), Electrical Metallic Tubing.

.5 CSA C22.2 No. 211.2-M1984(R2003), Rigid PVC (Unplasticized) Conduit.

1.3 ACTION AND INFORMATIONAL SUBMITTALS

.1 Provide submittals in accordance with Contract Documents.

.2 Product data: submit manufacturer's printed product literature, specifications and

datasheets.

.1 Submit cable manufacturing data.

.3 Quality assurance submittals:

.1 Test reports: submit certified test reports.

.2 Certificates: submit certificates signed by manufacturer certifying that materials

comply with specified performance characteristics and physical properties.

.4 Instructions: submit manufacturer's installation instructions.

1.4 WASTE MANAGEMENT AND DISPOSAL

.1 Separate waste materials for recycling in accordance with Contract Documents.

.2 Place materials defined as hazardous or toxic waste in designated containers.

.3 Ensure emptied containers are sealed and stored safely for disposal away from children.

Part 2 Products

2.1 CABLES AND REELS

.1 Provide cables on reels or coils.

Section 26 05 34

District of Squamish CONDUITS, CONDUIT FASTENINGS & FITTINGS

Powerhouse Springs – Well 3 Upgrade Page 11214of 4

.1 Mark or tag each cable and outside of each reel or coil, to indicate cable length,

voltage rating, conductor size, and manufacturer's lot number and reel number.

.2 Each coil or reel of cable to contain only one continuous cable without splices.

.3 Identify cables for exclusively dc applications.

.4 Reel and mark shielded cables rated [2,001] volts and above.

2.2 CONDUITS

.1 Rigid metal conduit: to CSA C22.2 No. 45, hot dipped galvanized steel threaded.

.2 Electrical metallic tubing (EMT): to CSA C22.2 No. 83, with couplings.

.3 Rigid PVC conduit: to CSA C22.2 No. 211.2.

.4 Flexible metal conduit: to CSA C22.2 No. 56, liquid-tight flexible metal.

2.3 CONDUIT FASTENINGS

.1 One hole steel straps to secure surface conduits 50 mm and smaller. Two hole steel

straps for conduits larger than 50 mm.

.2 Beam clamps to secure conduits to exposed steel work.

.3 Channel type supports for two or more conduits at 1500 mm oc.

.4 Threaded rods, 6 mm diameter, to support suspended channels.

2.4 CONDUIT FITTINGS

.1 Fittings: manufactured for use with conduit specified. Coating: same as conduit.

.2 Factory "ells" where 90 degree bends are required for 25 mm and larger conduits.

.3 Watertight connectors and couplings for EMT. Set-screws are not acceptable.

2.5 EXPANSION FITTINGS FOR RIGID CONDUIT

.1 Weatherproof expansion fittings with internal bonding assembly suitable for 100 mm

linear expansion.

.2 Watertight expansion fittings with integral bonding jumper suitable for linear expansion

and 19 mm deflection.

.3 Weatherproof expansion fittings for linear expansion at entry to panel.

Section 26 05 34

District of Squamish CONDUITS, CONDUIT FASTENINGS & FITTINGS

Powerhouse Springs – Well 3 Upgrade Page 11214of 4

2.6 FISH CORD

.1 Polypropylene.

Part 3 Execution

3.1 INSTALLATION

.1 Install conduits to conserve headroom in exposed locations and cause minimum

interference in spaces through which they pass.

.2 Conceal conduits except in mechanical and electrical service rooms.

.3 Surface mount conduits except where they are in a secure area designated as a wire chase

already. Concealed conduit may be required in aesthetic locations. If in doubt, consult

Owner and Consultant for direction.

.4 Use rigid hot dipped galvanized steel threaded conduit except where specified otherwise.

.5 Use electrical metallic tubing (EMT) indoors as specified.

.6 Use rigid pvc conduit underground.

.7 Use liquid tight flexible metal conduit for connection to devices.

.8 Bend conduit cold:

.1 Replace conduit if kinked or flattened more than 1/10th of its original diameter.

.9 Mechanically bend steel conduit over 19 mm diameter.

.10 Field threads on rigid conduit must be of sufficient length to draw conduits up tight.

.11 Install fish cord in empty conduits.

.12 Remove and replace blocked conduit sections.

.1 Do not use liquids to clean out conduits.

.13 Dry conduits out before installing wire.

3.2 SURFACE CONDUITS

.1 Run parallel or perpendicular to building lines.

.2 Locate conduits behind infrared or gas fired heaters with 1.5 m clearance.

.3 Run conduits in flanged portion of structural steel.

.4 Group conduits wherever possible on suspended or surface channels.

Section 26 05 34

District of Squamish CONDUITS, CONDUIT FASTENINGS & FITTINGS

Powerhouse Springs – Well 3 Upgrade Page 11214of 4

.5 Do not pass conduits through structural members except as indicated.

.6 Do not locate conduits less than 75 mm parallel to steam or hot water lines with

minimum of 25 mm at crossovers.

3.3 CONCEALED CONDUITS

.1 Run parallel or perpendicular to building lines.

.2 Do not install horizontal runs in masonry walls.

.3 Do not install conduits in terrazzo or concrete toppings.

3.4 CONDUITS UNDERGROUND

.1 Slope conduits to provide drainage.

.2 Waterproof joints (pvc excepted) with heavy coat of bituminous paint.

3.5 CLEANING

.1 Clean all underground ducts with a mandrel prior to pulling cables.

END OF SECTION

Section 26 05 43 01

District of Squamish INSTALLATION OF CABLES IN TRENCHES & IN DUCTS

Powerhouse Springs – Well 3 Upgrade Page 1 of 2

Part 1. General

1.1 RELATED SECTIONS

.1 Section 26 05 00 – Common Work Results – Electrical

.2 Section 26 05 21 – Wires and Cables (0-1000V)

Part 2. Products

2.1 Not Used

.1 Not Used.

Part 3. Execution

3.1 CABLE INSTALLATION IN DUCTS

.1 Install cables as indicated in ducts.

.1 Do not pull spliced cables inside ducts.

.2 Install multiple cables in duct simultaneously.

.3 Use CSA approved lubricants of type compatible with cable jacket to reduce pulling

tension.

.4 To facilitate matching of colour coded multiconductor control cables reel off in same

direction during installation.

.5 Before pulling cable into ducts and until cables are properly terminated, seal ends of lead

covered cables with wiping solder; seal ends of non-leaded cables with moisture seal

tape.

.6 After installation of cables, seal duct ends with duct sealing compound.

3.2 FIELD QUALITY CONTROL

.1 Perform tests in accordance with Section 26 05 00 – Common Work Results - Electrical.

.2 Perform tests using qualified personnel. Provide necessary instruments and equipment.

.3 Check phase rotation and identify each phase conductor of each feeder.

.4 Check each feeder for continuity, short circuits and grounds. Ensure resistance to ground

of circuits is not less than 50 megohms.

.5 Pre-acceptance tests.

.1 After installing cable but before splicing and terminating, perform insulation

resistance test with 1000V megger on each phase conductor.

Section 26 05 43 01

District of Squamish INSTALLATION OF CABLES IN TRENCHES & IN DUCTS

Powerhouse Springs – Well 3 Upgrade Page 2 of 2

.2 Check insulation resistance after each splice and/or termination to ensure that

cable system is ready for acceptance testing.

.6 Acceptance Tests

.1 Ensure that terminations and accessory equipment are disconnected.

.2 Ground shields, ground wires, metallic armour and conductors not under test.

.3 High Potential (Hipot) Testing.

.1 Conduct hipot testing at voltage recommended by manufacturer.

.2 Raise voltage in steps from zero to maximum values as specified by

manufacturer for type of cable being tested.

.3 Hold maximum voltage for specified time period by manufacturer.

.4 Record leakage current at each step.

.7 Provide Engineer with list of test results showing location at which each test was made,

circuit tested and result of each test.

.8 Remove and replace entire length of cable if cable fails to meet any of test criteria.

END OF SECTION

Section 26 27 15

District of Squamish ELECTRICAL AND CONTROLS COMPONENTS

Powerhouse Springs – Well 3 Upgrade Page 1 of 4

Part 1 General

1.1 RELATED SECTIONS

.1 Section 26 05 00 - Common Work Results for Electrical.

.2 Section 26 05 10 - Testing and Commissioning

.3 Section 26 05 31 - Splitters, Junction, Pull Boxes and Cabinets

1.2 SHOP DRAWINGS AND PRODUCT DATA

.1 Submit shop drawings and product data accordance with Section 26 05 00 - Common

Work Results - Electrical.

1.3 WASTE MANAGEMENT AND DISPOSAL

.1 In accordance with Section 26 05 00 – Common Work Results – Electrical.

1.4 CLOSEOUT SUBMITTALS

.1 Provide operation and maintenance data for all equipment for incorporation into manual

specified in Section 26 05 00 - Common Work Results - Electrical.

.2 Include data for each type and style of equipment.

Part 2 Products

2.1 VFD MCC SECTION

.1 Install VFD and associated equipment in MCC.

.1 Standard of Acceptance for VFD: Eaton PowerXL DG1 Drive – DG1-35-100-N-

N-C-21-C.

.2 Modify MCC section for 100HP VFD installation (Similar to Well 7 MCC section).

.3 Coordinate with Manufacturer for determining heat loading and ventilation requirements

for MCC for section containing new Well 3 VFD.

.4 Install new 150A, 600V, main circuit breaker sized to suit 100HP VFD.

.1 Standard of Acceptance for Main CB: Eaton Cutler-Hammer.

.5 Install new Modbus RTU cable interconnections with Well 7 VFD.

Section 26 27 15

District of Squamish ELECTRICAL AND CONTROLS COMPONENTS

Powerhouse Springs – Well 3 Upgrade Page 2 of 4

.6 Install new controls interconnections between Well 7 MCC section and controls

compartment.

.7 Install new door on MCC section complete with VFD HMI panel, main circuit breaker

handle, HOA switch, running and fault indicator lights, and ventilation fans.

.1 Standard of Acceptance: Eaton Cutler-Hammer.

.8 Equipment layouts shown on the Contract Drawings represent approximate locations only.

Contractor shall review site conditions to confirm actual equipment layouts and

interconnection details.

.9 Contractor shall provide wiring and terminations for all required interconnections between

the field equipment and instrumentation and the VFD, and between the VFD section and

Controls Section to provide a complete system.

.10 Contractor shall assist with testing and commissioning of VFD panel to ensure wiring is

completed as required.

2.2 LEVEL MEASUREMENT

.1 Level Transmitter

.1 Provide one (1) level transmitter to meet the following performance requirements:

.1 Water Level Range 0m to 50m

.2 Minimum static accuracy +_1%

.3 316 Stainless Steel wetted materials

.4 60m of ETFE cable attached to probe (confirm cable length required

during shop drawing stage)

.5 Operating temperature range 0-50oC

.6 IP68 and Nema 6P protection rating

.7 4-20mA pressure output

.8 Vent or pressure bellows as required

.2 Standard of acceptance for level transmitter: Measurement Specialties KPSI 705

series or approved alternative.

2.3 FLOW MEASUREMENT

.1 Flow Meter

.1 Provide one (1) flow meter with remote flow meter transmitter.

.1 Magnetic flow sensor

.2 Remote transmitter version

.3 120VAC operation

.4 4-20mA, 2-wire output, 700 ohms loop impedance capacity

.5 Open-collector pulse output, 30VDC @ 250mA, passive, isolated

Section 26 27 15

District of Squamish ELECTRICAL AND CONTROLS COMPONENTS

Powerhouse Springs – Well 3 Upgrade Page 3 of 4

.6 2-line, illuminated display of process and configuration information.

Handheld remote programmer.

.7 Sensor with polyurethane liner for water & wastewater applications

.8 Operating pressure, flow range, sensor diameter and flange type to be as

specified by civil engineer. Confirm with civil engineer prior to purchase.

.9 Cast aluminum EEMAC4X (IP67) transmitter housing c/w ½” NPT cable

entries.

.10 Repeatability: +/- 0.2% of rate

.11 Ambient temperature range: -20C to +60C

.12 Note: Include optional grounding rings (2) for flow sensor flanges when

used with non-conductive forcemain piping (ie. plastic pipe or

lined/coated metal pipe).

.2 Standard of Acceptance for Flow Meter: Endress & Hauser “Promag W400”

series.

2.4 FINISHES

.1 Apply finishes in accordance with Section 26 05 00 - Common Work Results for Electrical

and Section 26 05 31 - Splitters, Junction, Pull Boxes and Cabinets.

2.5 EQUIPMENT IDENTIFICATION

.1 Provide equipment identification in accordance with Section 26 05 00 - Common Work

Results for Electrical.

.2 All nameplates and labels shall be engraved lamecoid style.

.3 Nameplates:

.1 White plate, black letters.

.2 Complete board labeled: "Controls Cabinet"

.3 Other labels to be worded as per the Plans.

Part 3 Execution

3.1 INSTALLATION

.1 Install control panel enclosures as indicated in the drawings.

.2 Apply touch up paint as required.

.3 Make field power and control connections as indicated.

.4 Compliance: Comply with manufacturer's written data, including product technical

bulletins, product catalogue installation instructions, product carton installation

instructions, and datasheet.

Section 26 27 15

District of Squamish ELECTRICAL AND CONTROLS COMPONENTS

Powerhouse Springs – Well 3 Upgrade Page 4 of 4

.5 Supply all necessary equipment and wiring to provide the points connected to the

equipment as shown on the plans.

.6 External sensors and connections:

.1 Include provision for the connection of mechanical control equipment as shown on

drawings including:

.1 Pressure transducer

3.2 CONTROLS

.1 The Contractor shall assist with the demonstration of a fully functional system between the

Control Compartment, VFD Section, and wells.

3.3 FIELD QUALITY CONTROL

.1 Perform tests in accordance with Section 26 05 00 - Common Work Results for Electrical.

.2 Ensure moving and working parts are lubricated where required.

.3 Operate system to prove satisfactory performance of complete system during 24 hour

period.

END OF SECTION

Section 26 28 16 02

District of Squamish MOLDED CASE CIRCUIT BREAKERS

Powerhouse Springs – Well 3 Upgrade Page 1 of 2

Part 1 General

1.1 SECTION INCLUDES

.1 Materials for moulded-case circuit breakers.

1.1 RELATED SECTIONS

.1 Section 26 05 00 - Common Work Results for Electrical

1.2 REFERENCES

.1 Canadian Standards Association (CSA International).

.1 CSA-C22.2 No. 5-09, Moulded-Case Circuit Breakers, Molded-Case Switches

and Circuit-Breaker Enclosures (Tri-national standard with UL 489, tenth

edition, and the second edition of NMX-J-266-ANCE).

1.3 SUBMITTALS

.1 Submit product data in accordance with Submittal Procedures.

.2 Include time-current characteristic curves for breakers with ampacity of 20 A and over or

with interrupting capacity of 22,000 A symmetrical (rms) and over at system voltage.

.3 Include time-current characteristic curves for all 600V breakers.

1.4 WASTE MANAGEMENT AND DISPOSAL

.1 Separate and recycle waste materials in accordance with Construction/Demolition Waste

Management and Disposal Requirements.

.2 Remove from site and dispose of all packaging materials at appropriate recycling

facilities.

.3 Collect and separate for disposal paper, plastic, polystyrene, corrugated cardboard and

other recyclable packaging material in appropriate on-site bins for recycling in

accordance with Waste Management Plan.

.4 Divert unused metal materials from landfill to metal recycling facility as approved by

Engineer.

.5 Fold up metal banding, flatten and place in designated area for recycling.

Part 2 Products

2.1 BREAKERS GENERAL

.1 Moulded-case circuit breakers: to CSA C22.2 No. 5

Section 26 28 16 02

District of Squamish MOLDED CASE CIRCUIT BREAKERS

Powerhouse Springs – Well 3 Upgrade Page 2 of 2

.2 Bolt-on moulded case circuit breaker: quick- make, quick-break type, for manual and

automatic operation with temperature compensation for 40 degrees C ambient.

.3 Common-trip breakers: with single handle for multi-pole applications.

.4 Magnetic instantaneous trip elements in circuit breakers to operate only when value of

current reaches setting.

.1 Trip settings on breakers with adjustable trips to range from 3-8 times current

rating (600V breakers).

.5 Circuit breakers with interchangeable trips as indicated.

.6 Circuit breakers to have the following minimum symmetrical rms interrupting capacity

rating:

.1 600V Breakers 25kA

2.2 THERMAL MAGNETIC BREAKERS

.1 Moulded case circuit breaker to operate automatically by means of thermal and magnetic

tripping devices to provide inverse time current tripping and instantaneous tripping for

short circuit protection.

.1 Circuit breaker for heat trace circuit shall be of the type recommended by the

heat trace manufacturer.

Part 3 Execution

3.1 INSTALLATION

.1 Install circuit breakers as indicated.

END OF SECTION

Existing Well Log

HYDROGEOLOGIC LOG

PURPOSE OF HOLE: PRODUCTION WELL

TYPE OF RIG: CABLE TOOL WELL I.D. PLATE NU.:

DRILLING CONTRACTOR: PERRY'S WELL DRILLING WELL TAG NU.:

DATE CONSTRUCTED: SEPTEMBER / OCTOBER 2000 APPROX. ELEVATION T.O.C.: 109.92 m-geod.

GROUND ELEVATION: 109.3 m-geod. (approximate) DEPTH TO WATER: 6.63 m November 27, 2000

STEEL CASING STICK UP: 0.62m ELEVATION OF WATER: 103.29 m-geod.

Depth

(m)

Ap

roxim

ate

Ele

va

tio

n

(m-g

eo

d.)

DESCRIPTION OF LITHOLOGY

ENCOUNTERED

WELL CONSTRUCTION

MATERIALSWell Diagram

Sa

mp

le

de

pth

s (

m)

0.0 109.3 Ground surface Depth

500mm surface casing

5.0 withdrawn after grouting

Bentonite grout

Static Water Level = 103.29 m-geod.

10.0 387.4mm I.D. steel casing

Grey, well-graded fine SAND to coarse GRAVEL, some left with 0.6m stickup

cobbles and boulders, some red particles,

sub-angular to sub-rounded clasts, some till layers.

15.0

20.0

83.4 25.9

Silty fine to coarse SAND with some gravel

Grey fine-medium SAND,

30.0 some silt to silty, layered.

Grey well-graded SAND, some fine-coarse gravel.

40.0

67.3 Coarse SAND and GRAVEL, v. dense, some fines. 42.0

45.0 NOTE: Shaded zones are considered to be

partially confining layers.

\\h

era

\pro

ject\P

roje

ct\2

84

1\W

ell

Re

co

rds\[W

ell

Lo

gs -

PW

-1 to

PW

-7.x

lsx]P

W0

0-0

3

83608 (?)

PW-3

DISTRICT OF SQUAMISH

HYDROGEOLOGICAL ASSESSMENT FOR

WELL PROTECTION PLAN

POWERHOUSE SPRINGS

SQUAMISH, B.C.

BY: DATE:

LOG OF PRODUCTION ATH/MDP DEC 00

WELL PW-3 APPROVED: FIG:

A-3

68.8 40.5

68.2 Well-graded fine SAND to coarse GRAVEL. 41.1

End of Hole

25.0

82.3

74.6 34.735.0

400mm telescopic bail bottom

1.4m of 2.0mm slot (0.080")0.3m of 2.5mm slot (0.100")

0.9m of 3.6mm slot (0.140")

1.2m of 1.8mm slot (0.070")

0.6m Riser

35.4

34.7

41.1

400mm (333mm I.D.)

TELESCOPIC SCREEN ASSEMBLY

0.3m of 2.5mm slot (0.100")

0.6m of 2.0mm slot (0.080")

0.5m of 3.6mm slot (0.140")

0.6m of 3.6mm slot (0.140")

400mm K-Packer

40.539.939.539.2

37.9

37.036.7

7.0

27.0