TE/MPE/MI OP section meeting 29th September 2009
HCC 2009 Frequently Asked Questions
0v1
M. Zerlauth
[email protected] Interlock Systems
Outline HCC campaign 2009 is progressing very well with >> number of tests
performed / shift
Many changes and improvements of test plans, powering procedures, powering specifities, tools, … have/had to be done for this years campaign LHC powering system + commissioning tools by now a rather complex
construct
Presentation summarizes and answers/provides hints to some FAQ to further minimize number of failing tests and (avoidable) test repetition
Focus on operational procedure Not included are implementation-issues: ie, errors in sequences, test-
plan, LSA, etc…
[email protected] Interlock Systems
Conditions before starting a test Next step not correctly proposed by sequencer (especially for PIC1 / PIC2 of
mains) Login as lhcop SOC needs to be reserved for your console Circuit must not be locked (ie due to previous failure) Is previous test completed? Ie the analysis signed Check correct short status in SOC editor and Simulation/normal mode
of power converter
[email protected] Interlock Systems
Conditions for starting a test Circuit not being ready for testing is most frequent reason for a ‘failed’ test
Multitude of conditions required, most frequent missing (>90%) are Circuit still locked / super-locked -> PIC supervision QPS controller not yet ready (ie a reset is needed) or 13kA switches are
still open -> PIC supervision / Circuit synoptic CRYO conditions (temporarily) lost -> PIC supervision UPS conditions (temporarily) lost -> PIC supervision
What the sequencer is capable/allowed doing in 2009 Closing of 600A switches Resetting of faults in PIC/PC
[email protected] Interlock Systems
Conditions for starting a test To avoid unnecessary repetition (and follow-up) of failed tests, it is strongly
recommended to verify the correct state of the circuit before launching ANY test, e.g. using Circuit Synoptic
[email protected] Interlock Systems
Conditions for starting a test To avoid unnecessary repetition (and follow-up) of failed tests, it is strongly
recommended to verify the correct state of the circuit before launching ANY test, e.g. using Circuit Synoptic
[email protected] Interlock Systems
Conditions for starting a test To avoid unnecessary repetition (and follow-up) of failed tests, it is strongly
recommended to verify the correct state of the circuit before launching ANY test, e.g. using PIC Supervision
[email protected] Interlock Systems
Conditions for starting a test Be careful with Circuits that have already been frequently repeated
(especially tests where heaters are fired, etc..) ‘Dangerous tests’: PIC2 CIRCUIT QUENCH, PLI*.f*, PNO*.f* Check in HCC pages history, now # of test repetition also in overall view
[email protected] Interlock Systems
New version of HCC show now the current repetition number for the test currently under execution By default, green as long as # rep <=2, red if repeated more often
New MPP strategy: 2 training quenches allowed, afterwards open NC and change I_PNO
Conditions for starting a test
[email protected] Interlock Systems
Reasons for failures during sequence In addition to quenches, trips, etc… the following things might make a
sequence fail/time-out
Wrong login in sequencer, resulting in RBAC exception -> PIC + FGC is now under RBAC, only lhcop will work from CCC island
QPS controller not reset -> Error message like ‘QPS.PVSS ST_LOGGING not OK’ -> Reset QPS controller before test
Mismatch of parameters in LSA and power converter (out of limits exception) -> ask EPC expert to re-synchronize or CO to correct LSA
Exceeding I_ERR or I_EARTH limits: Considered as warning only (sequence will halt but not fail) -> Confirm with EPC expert and in case accepted skip step in sequence
CRYO conditions (only CRYO_MAINTAIN), UPS conditions (only HW signal) -> Can be checked in PIC supervision or PIC history buffer
[email protected] Interlock Systems
Reasons for failures during sequence Asserting pop-ups too quickly (ie if action not yet completed) might result in
timeouts at a later stage Re-trip of agent after automatic reset (e.g. in RQ6.R7B1 ) -> Circuit synoptic PM acquisition in agent blocks (RQ4.L8) -> Circuit synoptic
[email protected] Interlock Systems
Signing a test Overall outcome of a HCC test is logical AND between successfully performed
sequence + PMA comments Thus if sequence failed for any reason, even a passed PMA will not alter the
test outcome For special cases (ie long sequences that failed with minor errors), outcome
should be altered by CO expert BEFORE signing the test
Automated analysis Automated path introduces additional 10 minute delay to make sure
data is present Currently only PIC2 for 120A and 600A signed automatically Test should normally be signed 15 minutes after the end-time of test If after this time test does not appear in PMEA nor in history -> Call LV-
expert If test is signed by experts (not visible in PMEA anymore) but not updated in
HCC pages (ie next step proposed) -> Call LV-expert
[email protected] Interlock Systems
Unlocking of Circuits after Failing test Test execution must be sequential, when UNLOCKING circuits in SOC editor
after failure, make sure no PMA is pending Test repetition before completion of analysis of previous test could be
dangerous and breaks MTF upload (requires for sequential upload)
[email protected] Interlock Systems
Re-commissioning of circuit Pointer defines commissioning status of a circuits = LAST_PASSED_TEST If circuit should be re-commissioned (e.g. after HW change)
Request point owner to move back this pointed in the SOC editor to the required step (where to start re-commissioning)
[email protected] Interlock Systems
Cleaning-up If sequences have been e.g. repeated by mistake (and step was already
performed correctly) Complete the test (if not long test, critical, etc..) Abort test + immediately tell CO expert to delete test in LSA before
signed and copied to MTF
Others…? I’d be happy for your feedback of other reoccurring issues Try to include new things + answers in these slide & publish on HCC