Technical Specifications of Roads_part4

download Technical Specifications of Roads_part4

of 19

Transcript of Technical Specifications of Roads_part4

  • 8/12/2019 Technical Specifications of Roads_part4

    1/19

    All rivet and boltholesshall be edge-sealed

    with clear lacquer

    after the application of

    the plastics sheeting.

    Rivets shall be spacedat not more than 150

    mm apart, around the

    outside edge of the

    sign plate and on

    cross braces the

    spacing shall be not

    more than 300 mm.

    Any rivet broughtthrough the sign face

    shall be colored to

    match the sign face.

    Any rivet or other

    device fixing sign

    plates to their

    framework shall have

    protective washer of

    nylon or other

    approved insulating

    material inserted

    where they would be

    in contact.

    8. All materials shall be supplied innew and unused condition except in

    4-34

  • 8/12/2019 Technical Specifications of Roads_part4

    2/19

    4.7

    ExecutionAll operations shall be performed in accordance with the specification, and in conformity

    with the lines, grades, thickness and typical cross Section shown on the plans or established

    by the Engineer. Only approved material shall be used in the construction. The embankment

    and sub grade in fill shall be constructed utilizing only suitable material obtained from

    roadway excavation or imported fill material from sources previously approved by the

    competent authority.

    4.7.1 Placement of fill1. Prior to the placement of any fill

    materials, the Contractor shall

    conduct trial compaction tests as

    directed by the Engineer.

    Fill material used in the trials shall be with the proposed borrow orexcavated material.

    Compaction equipment to be used shall be that specified andacceptable to the Engineer.

    The object of these trials shall be to determine the optimum moisturecontent and the relationship between the number of compaction

    equipment passes and density for the proposed borrow materials.

    2. Compaction of fills shall be carriedout at the moisture content

    determined by the trials.

    Fill material, which does not contain sufficient moisture to obtain therequired compaction, shall have additional water incorporated therein

    by the use of approved sprinklers and mixing.

    Material containing an excess of the amount of moisture required toobtain the necessary compaction shall not, without written approval of

    the Engineer, be incorporated in the fill until it has been allowed to dry

    4-35

  • 8/12/2019 Technical Specifications of Roads_part4

    3/19

    During construction of the roadway, the roadbed shall be maintained insuch a condition that it will be well drained at all times.

    The Contractor shall make allowances in the height and width of thework for any swelling or shrinkage.

    3. Fill materials shall be placed inhorizontal layers of uniform

    thickness.

    Work shall be carried out to adhere to the designated slopes, levels anddepths.

    After adjustment of the moisture content to that required to attainmaximum density, the loose material shall be compacted to obtain the

    specified density.

    Maximum layer thickness shall be 150mm, unless otherwise agreed bythe Engineer.

    4. Placement of fill materials at pointsinaccessible to normal compaction

    equipment shall be made in

    horizontal layers of loose material

    not exceeding 100 mm in depth and

    thoroughly compacted by the use of

    mechanical tampers.

    5. When fill materials are to be placedand compacted on slopes steeper than

    1H : 3V the following shall apply,

    unless otherwise approved by the

    Engineer. If the embankment shall

    be benched in steps or prepared as

    directed by the Engineer. The width

    of the benching shall be enough to

    permit the operations of placing

    equipment.

    4-36

  • 8/12/2019 Technical Specifications of Roads_part4

    4/19

    6. If the original surface upon which theembankment is to be placed is an old

    roadbed, the surface shall be

    ploughed, scraped and broken upregardless of the height of the

    embankment and compacted as

    directed by the Engineer.

    7. G. If backfill is to be placed belowstanding water, only approved

    granular material meeting the

    requirements of free draining

    material shall be deposited. Placing

    of aggregates may be with or without

    the associated use of compaction

    plant.

    8. H. If the foundation on which theembankment or the subgrade

    materials are to be laid is unstable,

    crushed aggregate or stabilizing rock

    fill meeting the requirements of

    stabilizing material shall be placed

    and compacted as directed by the

    Engineer.

    9. Density to which suitable fill layersshall be compacted is 95% MDD,

    unless other wise approved by the

    Engineer.

    10.When an embankment or filled areahas achieved settlement and requires

    additional material to bring it up to

    the required formation level, the top

    of the borrow or fill shall be

    4-37

  • 8/12/2019 Technical Specifications of Roads_part4

    5/19

    4.7.2

    Subgrade preparation1. After site clearing the upper portion

    (300mm below formation level) of

    the existing subgrade (cut area) shall

    be sampled and tested to confirm

    suitability of the material.

    If the upper portion of the subgrade is found to be unsuitable, suchsubgrade material shall be removed and replaced with suitable

    subgrade material as directed by the Engineer. The ground after

    cutting shall be treated and prepared as existing ground.

    When the existing ground in the cut (within 300mm of the formationlevel) is found to be suitable, the subgrade surface shall be completely

    broken up by scarifying, watered and mixed to achieve a uniform

    moisture content between 2% of the OMC for the full depth of

    150mm.

    The top 300mm below formation level in fill area shall be constructedwith approved sub grade material and each layer shall be compacted to

    98% of the MDD. The moisture content shall be within 2%of the

    OMC.

    2. After the foregoing work has beenaccomplished, the entire subgrade

    shall be shaped to a smooth uniform

    surface. Excess material which

    cannot be disposed of by normal

    drifting to the low spots during

    shaping operations shall be removed

    and placed in other areas deficient in

    materials or disposed of in an

    approved manner.

    4-38

  • 8/12/2019 Technical Specifications of Roads_part4

    6/19

    3. Once prepared, the subgrade shall bemaintained in the finished condition

    until the first succeeding course of

    subbase or base material has beenplaced.

    Contractor shall take all precautions necessary to protect subgradefrom damage.

    Hauling over finished subgrade shall be limited to that which isessential for construction purposes.

    Contractor shall protect the prepared subgrade from both his own andpublic traffic.

    Contractor shall maintain the subgrade by rolling as frequently as maybe necessary to preserve the subgrade in a completely satisfactory

    condition.

    The Contractor shall be responsible for reinstatement (to thesatisfaction of the Engineer) of any layer damaged or disturbed after

    the compaction and approval, before placing the next layer.

    Finished surface of the formation level shall not vary at any point bymore that 10 mm above or 30mm below the grade shown on the

    drawing or established by the Engineer.

    An inspection request shall be sent to the Engineer prior to proceedingto the next operation.

    4.7.3 Compaction1. Contractor shall carry out the compaction of fills as specified after grading

    and leveling the surface to be compacted.

    In areas to be filled, compaction shall include adding necessary fill,water, and other materials as required, and compacting the first layer in

    addition to subsequent layers up to the proposed levels.

    In areas already excavated down to the required level, compactionshall include adding the necessary water, etc., and compacting the

    surface, in accordance with the procedure outlined hereinafter.

    4-39

  • 8/12/2019 Technical Specifications of Roads_part4

    7/19

    Procedure outlined below shall not relieve the Contractor of his dutiesto determine the most suitable procedure for compaction. All such

    procedures shall be subject to the approval of the Engineer.

    2.

    After carrying out the grading, leveling, scarifying, pulverizing, and otherwork as required, the Contractor shall add the necessary amount of water

    (within 3% of the MDD) to obtain a suitable moisture content for

    compaction. Fill shall be thoroughly turned over after adding each lot of

    water so as to achieve a homogeneous moisture content throughout the

    whole thickness of the layer.

    3. Before compacting, samples from the pulverized fill will be taken andtested according to standard procedures in order to establish the moisture

    content.

    Field testing using "Speedy Moisture Device" or similar instrumentgiving direct readings for the field moisture content may be used for

    guidance only.

    In the event that moisture is more than Optimum Moisture Content, thearea represented by the sample shall be scarified and aerated until the

    moisture content is within 3% of the optimum moisture content.

    The fill shall then be leveled for compaction.

    4. After primary leveling, compaction shall be commenced by means ofapproved rollers depending on the type of material being compacted in

    order to obtain the required dry density.

    Placement and compaction of materials shall be in layers notexceeding 150 mm compacted thickness, unless otherwise approved by

    the Engineer.

    Each layer of fill material shall be compacted to 95% of the MDD.

    5. Rolling shall be carried out in the direction of the road axis until the fillreaches the required density.

    In crowned sections, rolling shall start from both edges of the road inthe direction of the axis.

    4-40

  • 8/12/2019 Technical Specifications of Roads_part4

    8/19

    If the road is super elevated, rolling shall commence from the lowerside and continue to the higher side.

    In order to compensate for the amount of water lost in evaporation inthe course of compaction, additional quantities of water shall be addedas required.

    6. The surface shall thereafter be leveled longitudinally and transversely bymotor graders and finally rolled to achieve uniform compaction, free from

    undulations, soft spots and depressions.

    7. No layer shall be covered by the next layer until it has been tested,inspected and approved by the Engineer.

    8. Saline water for earthworks shall only be permitted if the percentage ofwater soluble salts in the compacted fill does not exceed 3% by weight of

    dry soil.

    4.7.4 Installation of precast concrete curbsPrecast curbs shall be set to the lines and grades as shown on the Drawings, unless otherwise

    agreed with the Engineer.

    Under no circumstances will it be permitted for levels to be set bydirect measurement from pavement layers.

    Any excavated surface for the concrete bedding shall be watered andcompacted to a minimum of 95% MDD.

    Unless otherwise indicated, elements shall be laid either directly onto awet concrete base or on to a cement/sand (1:3) mortar bedding, 25 mm

    thick placed on a previously laid concrete base on approved sub-grade.

    Dimensions of the base and backing shall be as shown on theDrawings.

    Concrete base shall be constructed with Grade 20 Concrete. Unless otherwise indicated, after curb units have been laid a

    continuous backing of Grade 20 Concrete shall be poured for the

    elements using steel forms.

    4-41

  • 8/12/2019 Technical Specifications of Roads_part4

    9/19

    No pavement layers shall be laid against curbing until such time as thebacking is complete, back filled and approved by the Engineer.

    Joints between radius curbs, shall have a width not greater than 4mmand be filled with a cement / sand (1:3) grout with 1/5 part hydratedlime and sufficient water to make the mixture plastic and easily

    smoothed.

    A grooving tool shall be used to produce a smooth, circular sectiongroove not more than 3 mm deep in all joints.

    Grouted joints shall be cured by an approved method to the Engineerssatisfaction.

    Joints between straight curbs shall have a width of 4mm and be filledwith the above specified grout, unless otherwise directed by the

    Engineer.

    Immediately after any concrete is in place and for 7 days thereafter thecurbs, base backing and mortared joints shall be fully cured and

    protected from drying out and against the harmful effects of weather,

    including rain and rapid temperature changes.

    Method of protection shall be subject to the Engineers approval. Use of colored curing membranes will not be permitted. Concrete not properly cured and protected will be rejected and shall be

    removed from the works.

    Expansion joints shall be placed as shown on the Drawings, unlessotherwise approved by the Engineer.

    Every 9 meters (or as directed by the Engineer) the joint between curbsshall be filled with an approved joint filler 10mm thick. The filler

    shall extent through the curbs, bed, backing and channel and shall be

    trimmed to the finished slope of the curb and channel.

    At access points the curbs (including the bed backing) shall be droppedto shown a face of 75mm or as shown on the drawing.

    At the end of any curb run, the end element shall be sloped down toground level and angled away from the road at 30 degrees.

    Curbs shall be level within a tolerance of 3mm at each end of theelement, to the designated lines and grades.

    4-42

  • 8/12/2019 Technical Specifications of Roads_part4

    10/19

    4.7.5 In-situ concrete curb layingIn-situ curbs shall be laid to the lines and grades as shown on the drawings.

    In-situ curbs shall be laid by an approved automatic curbing machine,unless otherwise approved by the Engineer.

    The curbs shall be dense with regular sides, arises and chamfers andfinished to a fine surface free from blow holes.

    The concrete used for the curbs shall be grade C40, except as modifiedby the Engineer.

    Curbs shall be cut to form expansion and contraction joints as shownon the drawings or as directed by the Engineer.

    The joints shall be filled with suitable compressible board or othersuitable material as approved by the Engineer.

    The maximum deviation of the top of the curb under a straight edgeshall be not greater than 3mm in 3m.

    The vertical alignment of the finished curb shall not depart from thetrue level more than 6mm at any point.

    The horizontal alignment shall not depart from that shown on thedrawing by more than 13mm nor deviate from the straight by more

    than 3mm in 3m.

    4.7.6 Granular sub-base1. After the formation has been inspected and accepted by the Engineer,

    granular sub-base shall be placed, as shown on the drawings.

    Material shall be delivered to the roadbed as a uniform mixture. Shall be spread in layers. Segregation shall be avoided. Shall be free from pockets of coarse or fine materials. Spread by finisher, or grader or other approved mechanical methods as

    approved by the Engineer.

    Watered, shaped to a compacted thickness not exceeding 150 mm andcompacted to the required grade and cross-section.

    4-43

  • 8/12/2019 Technical Specifications of Roads_part4

    11/19

    Compaction procedure and plant shall be to the satisfaction of theEngineer. At the time of compaction the moisture content of the laid

    material shall not vary by more than + 2% of the optimum moisture

    content. The grading of the placed materials shall be checked bytaking samples from an area 0.5m x 0.5m from the full depth of the

    layer for every 1000m3of material laid.

    No road mixing of subbase shall be permitted. Before using in the works subbase material shall be stockpiled in a

    manner to prevent segregation.

    2. Sub-base shall be compacted to not less than 98% of the maximum drydensity as determined in accordance with BS 1377: Part 4 : Method 3.6,

    unless otherwise agreed by the Engineer.

    The surface on completion of compaction shall be well-closed, freefrom movement under compaction plant and free from ridges cracks or

    loose material.

    Finished surfaces of the road sub-base shall not vary at any point morethan 10 mm above or below the grade established by the drawings.

    The surface shall be maintained in a condition satisfactory to receiveany subsequent base or surfacing material.

    Any sub-base, which does not conform to the specified requirementsshall be reshaped, removed or reworked, watered and thoroughly re-

    compacted to conform to the specified requirements.

    At any stage in the mixing, transportation, spreading or compactionprocess the Engineer may instruct specified tests to be carried out.

    An inspection request shall be sent to the Engineer prior to proceedingwith the next operation.

    4.7.7 Aggregate road-basea. Compaction Trials

    If directed by the Engineer, prior to the commencement of theaggregate road base operations, the Contractor shall construct trial

    lengths as directed by the Engineer. Materials used in the trials shall

    4-44

  • 8/12/2019 Technical Specifications of Roads_part4

    12/19

    Trial lengths may not form part of the permanent works but may be

    permitted in the construction of temporary detours of sufficient length.

    Object of these trials is to determine:a. Adequacy of the Contractors equipment.

    b. Loose depth measurements necessary to determine suitable compacted

    layers depths.

    c. Field moisture content.

    d. Relationship between the number of compaction passes and the resulting

    density of the material.

    Contractor may proceed with the aggregate road-base work only afterthe methods and procedures established in the compaction trials have

    been approved by the Engineer.

    2. After the previous work has been inspected andaccepted by the Engineer, approved road-base material

    shall be placed as shown on the drawings.

    Road-base material shall be delivered to the road as a uniform mixturecomplying with the specific requirements.

    Method of mixing and laying of road base material shall be subject tothe approval of the Engineer.

    Layers shall not exceed 150 mm in compacted thickness. Material shall be handled in a manner, which avoids segregation. Segregated materials shall be remixed until uniformity is obtained. Suitable precautions shall be taken to prevent rutting during the

    spreading.

    No hauling or placement of material will be permitted when, in thejudgment of the Engineer, the weather or road conditions are such that

    the hauling operations will cause rutting or contamination of granular

    road-base material.

    4-45

  • 8/12/2019 Technical Specifications of Roads_part4

    13/19

    Road-base, which has been placed without approval of the Engineershall be removed at the Contractors expense.

    Moisture content of the aggregate road-base material shall be adjustedby watering with approved sprinkler trucks or by drying out, to bewithin 2% of the OMC prior to compaction.

    Road base shall be compacted to not less than 100% MDD by meansof approved compaction equipment progressing gradually from the

    outside of the road towards the center with each succeeding pass

    uniformly overlapping the previous pass.

    a. Rolling shall continue until entire thickness of each layer is thoroughly

    and uniformly compacted to the specified density.

    b. Rolling shall be accompanied in a manner approved by the Engineer, to

    ensure a smooth surface free from ruts or ridges is obtained with the

    proper section and crown.

    Surface of the material shall on completion of compaction:a. Be well closed.

    b. Free from movement under the compaction plant.

    c. Free from compaction planes, ridges, cracks, or loose material.

    Any areas inaccessible to normal compaction equipment shall becompacted by means of mechanical tampers, until satisfactory

    compaction is obtained.

    The gradation of the placed material shall be checked by takingsamples from an area 0.5m by 0.5m from the full depth of the layer of

    every 1000m3 of laid material.

    Contractor shall program his operations to avoid the drying out of thesub-base during construction.

    a. At any stage in the mixing, transportation, spreading or compaction process

    the Engineer may instruct the Contractor to carry out the specified tests.

    b. If any layer of aggregate road-base material, or part thereof, is permitted to

    dry out after compaction, or does not conform to the specified

    requirements or finish, the Contractor shall, at his own expense, remove

    water, rework or re-compact the material, as directed by the Engineer,

    4-46

  • 8/12/2019 Technical Specifications of Roads_part4

    14/19

    before the next layer of aggregate road-base or subsequent pavement

    layers are placed.

    3. Finishing

    Before the commencement of each activity an inspection request shallbe sent to the Engineer for inspection and tests.

    Surface of the finished aggregate road base will be tested with a 3 mstraightedge by the Engineer at selected locations. Variations of the

    surface from the testing edge of the straight edge between any two

    contacts with the surface shall at no point exceed 10 mm when placed

    on or parallel or perpendicular to the centerline of the roadway. All

    humps and depressions and thickness deficiencies exceeding the

    specified tolerance shall be corrected by removing the defective work

    or by adding new material as directed by the Engineer. Any work

    necessary to reshape the surface shall be at the contractors expense.

    4.7.8 Placement of asphalt paving course1. Equipment

    Method statement and equipment list shall be according to the type andnumber outlined in the Contractors detailed Program of Work, as

    approved by the Engineer. The Contractor shall furnish to the Engineer

    the manufacturers technical data for each equipment and no

    equipment shall be used without the approval of the Engineer.

    Trucks used for hauling bituminous mix shall have tight, clean, smoothmetal beds which have been coated with a minimal amount of paraffin

    oil, lime solution, or other approved material to prevent the mix from

    adhering to the beds. Excess release agent must be drained from the

    bed prior to loading bituminous materials.

    Each vehicle shall be equipped with a canvas cover or other suitablematerial of such size as to protect the mix from the weather and the

    trucks must be clearly numbered for easy identification.

    4-47

  • 8/12/2019 Technical Specifications of Roads_part4

    15/19

    The pavers shall be self propelled and equipped with hoppers anddistributing screws of the reversing type to place the mixture uniformly

    in front of the electronic controlled screeds.

    If during construction it is found that the spreading and finishingequipment in operation leaves surface tracks in the pavement or

    indented areas or other object able irregularities that are not

    satisfactorily corrected by scheduled operations, the use of such

    equipment shall be discontinued and other satisfactory spreading and

    finishing equipment shall be provided by the Contractor.

    Rolling equipment shall be self-propelled.a. Wheels on the rollers shall be equipped with adjustable scrapers.

    b. Rollers shall have water tanks and sprinkling apparatus, which shall be

    used to keep the wheel wet and prevent the surface material from sticking.

    c. Rollers shall be of steel-wheel and pneumatic tire type and shall be in good

    condition.

    d. Rollers shall be capable of reversing without backlash.

    e. Rollers shall be operated at speeds slow enough to avoid displacement of

    the bituminous mix.

    f. Number and weight of rollers shall be sufficient to compact the mix to the

    required density while it is still in a workable condition.

    g. Use of equipment, which results in excessive crushing of the aggregate,

    will not be permitted.

    h. A minimum of three (3) rollers, two (2) steel-wheel and one (1)

    pneumatic-tire type, shall be used with each spreading operation for each

    lane.

    Contractor shall provide adequate back-up equipment for use in theevent of mechanical failure, all to the satisfaction of the Engineer.

    The Engineer reserves the right to stop the use of any equipment orplant which he deems to be detrimental to the work required and

    instruct its removal and replacement with suitable equipment.

    The Contractor shall not be allowed to use any plant without thepermission of the Engineer.

    4-48

  • 8/12/2019 Technical Specifications of Roads_part4

    16/19

    The Engineer shall have the right to expel any operators, mechanics orlabor and to instruct suitable replacement thereof at any time he deems

    such action is necessary.

    2. Surface Preparation When the Bituminous Mix is placed on a prepared area, (whether or

    not a prime coat is designated on the Drawings) the area shall be even

    and firm and within the construction tolerances specified.

    When the paving layer is constructed on an existing bituminoussurface, the surface shall be cleaned of all foreign material and boomed

    free of dust.

    a. Any loose, broken or shattered bituminous material along the edges of the

    existing surface shall be removed.

    b. Any exposed sub-grade or shoulder adjacent to the edge of the existing

    surface to receive the new bituminous mix shall be shaped, bladed,

    compacted and boomed and primed to provide a uniform firm sub-grade

    for the new surface course.

    Existing bituminous surface, base, or sub-grade shall be removed ifbroken, shattered, or unstable. Areas shall be excavated to a depth as

    directed by the Engineer, and refilled with the Bituminous Mix.

    Prior to the placing of the mix, when designated on the Drawings ordirected by the Engineer, a prime coat or tack coat shall be applied to

    the surface in accordance with the Specification for Prime Coat or

    Tack Coat.

    3. Placing of the mix All bituminous mixes shall be introduced to the paver at a temperature

    not less than 140 C and not more than 163 C. Mixes outside this

    temperature range shall be discarded.

    Bituminous mix shall be spread and finished to crown and grade byautomatically controlled bituminous paves unless otherwise approved

    by the Engineer.

    4-49

  • 8/12/2019 Technical Specifications of Roads_part4

    17/19

    a. Bituminous mix may be spread and finished by hand methods only where

    machine methods are impractical as determined by the Engineer.

    b. Paver shall lay the bituminous mix without tearing the surface and shall

    strike a finish that is smooth, true to cross section, uniform in density andtexture and free from hollows, transverse corrugations or other

    irregularities.

    c. Paver shall be operated at a speed which will give the best results for the

    type of paver being used and which co-ordinates satisfactorily with the

    rate of delivery of the mix to the paver, to provide a uniform rate of

    placement without intermittent operations of the paver.

    Mix shall be delivered to the paver in time to permit completion ofspreading, finishing and compaction of the mix during daylight hours.

    Longitudinal joints in successive layers shall be offset not less than300 mm. Width of surface or top course placements shall conform to

    traffic lane edges as shown on the Drawings.

    Leading half of half roadway paving shall not get ahead of the trailinghalf of the pavement by more than one average full-day of paving.

    a. In no case, shall the leading half be more than km ahead of the trailing

    half without the written permission of the Engineer.

    b. If the Contractor fails to comply with this requirement, the Engineer may

    suspend paving on the leading half until such time, as the Contractor shall

    pave the trailing half to a point approximately even with the leading half.

    Unless otherwise directed by the Engineer, where successive layers areto be placed, the surface of the existing layer shall be swept clean with

    a power broom, or by other means as approved by the Engineer, and a

    tack coat applied. Tack coat may not be required where delay between

    laying subsequent courses is less than 48 hours or surface is fresh and

    clean at the discretion of the Engineer.

    Asphalt concrete mixes (except leveling courses) shall be laid at an un-compacted thickness such that after rolling, the thickness of the

    compacted layer shall be :

    4-50

  • 8/12/2019 Technical Specifications of Roads_part4

    18/19

    a. Minimum 2.0 times the maximum aggregate particlesize.

    b. Maximum 4.0 times the maximum aggregate particlesize.

    Maximum thickness for layers may be increased slightly when suchincrease is more adaptable to total pavement thickness and when in the

    opinion of the Engineer it is not detrimental to placement and rolling

    conditions.

    Contractor shall erect and maintain an approved reference string lineand operate the paver to conform to the reference string line for the

    initial layer and/or any other layers as directed.

    a. Elevation control point stakes for the first layer of bituminous paving

    course shall be set at a maximum spacing of 20 m.

    b. For subsequent layers, control points shall be set at 10 m maximum

    spacing.

    4. Compaction of Bituminous Layers After spreading and strike off, and as soon as the mix conditions

    permit, the rolling shall be performed without excessive shoving or

    tearing. If the temperature of the joint falls below 1200C the material

    shall be removed by approved methods to ensure the required

    compaction at the joint. Rolling procedure for each new job must

    consider number of passes, rolling speed, and rolling pattern. Each

    mixture must be thoroughly and uniformly compacted.

    Rolling will not be prolonged to an extent that cracks appear. When rolling a thin lift use the following sequence.

    a. Transverse joints.

    b. Outside edge

    c. Initial or breakdown rolling, beginning on the low side and progressing

    towards the high side.

    d. Intermediate rolling (as above)

    4-51

  • 8/12/2019 Technical Specifications of Roads_part4

    19/19

    e. Finish rolling.

    When placing a thick lift, roll the mix in the following sequence.a. Transverse joints

    b.

    Initial or breakdown rolling,beginning edge 300-380 mm from

    the lower unsupported edge and

    progressing toward the other edge.

    c. Outside edge.d. Intermediate rolling, beginning on the low side and progressing toward the

    high side.

    e. Finish rolling.

    f. When placing thick lifts in echelon, when abutting a previously placed

    lane or other lateral restraint, roll the mix in the following sequence;

    transverse joint, longitudinal joint, and initial or breakdown rolling

    beginning at the longitudinal joint and progressing towards the outside

    edge.

    g. Outside edge. When within 300mm of an unsupported edge, the roller

    should advance toward the edge in approximately 100mm increments in

    successive passes.

    When the transverse joint is made next to an adjoining lane.a. Make the first pass with a static wheeled roller moving along the

    longitudinal joint for a few feet.

    b. Straighten the surface and make corrections if necessary.

    c. Roll the joint transversely with all except about 150mm of wheel width on

    the previously laid material.

    d. Repeat the above with successive passes each covering an additional 150-

    200mm of the new mix until the entire width of a drive wheel is on the

    new mix.

    e. Unless precautions are taken, transverse rolling must stop 150-200mm

    short of the outside edge and the edge must be compacted later during the

    longitudinal rolling.

    4-52