Technical Specification

136
MMOPL Tender TW Series 1000 TRACKWORK TENDER DOCUMENTS (Versova - Andheri - Ghatkopar Corridor) VOLUME - III EMPLOYER’S REQUIREMENTS: TECHNICAL SPECIFICATION Technical Specification July 2007

description

ballastless trackwork

Transcript of Technical Specification

Page 1: Technical Specification

MMOPL Tender TW Series 1000

TRACKWORK

TENDER DOCUMENTS

(Versova - Andheri - Ghatkopar Corridor)

VOLUME - III

EMPLOYER’S REQUIREMENTS:TECHNICAL SPECIFICATION

MUMBAI METRO ONE PRIVATE LIMITED

July, 2007

Technical Specification July 2007

Page 2: Technical Specification

MMOPL Tender TW Series 1000

CONTENT

1. INTRODUCTION.........................................................................................11.1 EMPLOYERS REQUIREMENTS – TECHNICAL SPECIFICATION.........................................11.2 DEFINITIONS AND ABBREVIATIONS.............................................................................21.3 DESIGN AND PERFORMANCE REQUIREMENTS...............................................3

2. QUALIFICATIONS OF MANUFACTURER...............................................122.1 MATERIAL..............................................................................................................122.2 EMPLOYER’S REPRESENTATIVES IN CHARGE OF TRACKWORK...................................12

3. SCOPE OF WORK....................................................................................133.1 SCOPE................................................................................................................. 133.2 GENERAL CRITERIA AND TRACK PARAMETERS...........................................153.3 SCHEDULE OF DIMENSION...............................................................................173.4 RESPONSIBILITY OF THE CONTRACTOR........................................................17

4. INTERFACES............................................................................................184.1 INTERFACE MATRICES......................................................................................18

5. INSTALLATION AND CONSTRUCTION SCHEDULE.............................195.1 REQUIREMENTS.................................................................................................19

6. CODES AND STANDARDS......................................................................216.1 INTRODUCTION..................................................................................................216.2 CODES AND STANDARDS.................................................................................21

7. MATERIALS AND COMPONENTS..........................................................277.1 MATERIAL TO BE SUPPLIED BY THE EMPLOYER OR CONTRACTOR..............................277.2 RAILS................................................................................................................... 287.3 TRACK COMPONENTS.......................................................................................287.4 TURNOUTS, CROSS-OVERS AND DIAMONDS................................................327.5 RAIL EXPANSION JOINTS..................................................................................337.6 BUFFER STOPS..................................................................................................337.7 L- XINGS................................................................................................................347.8 CONCRETE PLINTH/SLAB TRACKFORM (BALLASTLESS TRACK)..................................347.9 ALUMINO-THERMIC WELDING PORTION.........................................................367.10 SIGNAL AND TRACTION RETURN RAIL BONDS..............................................36

8. SURVEY AND SETTING OUT..................................................................378.1 FUNCTIONAL RESPONSIBILITIES.....................................................................378.2 SURVEY CONTROLS IN GENERAL...................................................................378.3 SECONDARY SURVEY CONTROLS..................................................................378.4 SETTING OUT.....................................................................................................388.5 CONTROL OF TRACK WORKS..........................................................................398.6 SURVEY INSTRUMENTS....................................................................................408.7 QUALITY PLAN....................................................................................................40

9. INSTALLATION........................................................................................419.1 INTRODUCTION..................................................................................................419.2 METHODS OF WORKING...................................................................................419.3 FINAL CONDITION OF TRACK...........................................................................439.4 TRACK INSTALLATION.......................................................................................449.5 BALLASTED TRACK INSTALLATION.................................................................469.6 BALLASTLESS TRACK INSTALLATION.............................................................499.7 TURNOUTS, CROSSOVERS, DIAMOND CROSSINGS, AND RAIL EXPANSION JOINTS (BALLASTED AND BALLASTLESS TRACK)................529.8 DESTRESSING OF CWR....................................................................................539.9 RAIL WELDING....................................................................................................549.10 PERMANENT MARKERS....................................................................................579.11 TRACK TOLERANCES........................................................................................57

Technical Specification July 2007

Page 3: Technical Specification

MMOPL Tender TW Series 1000

9.12 RECORDS............................................................................................................61

10. TESTING AND INSPECTION.........................................................6210.1 GENERAL (FOR THE MATERIALS TO BE SUPPLIED BY THE CONTRACTOR)................6210.2 MATERIAL AND COMPONENTS SUPPLIED BY THE CONTRACTOR..................................6310.3 SWITCHES, CROSSINGS AND RAIL EXPANSION JOINTS..............................6410.4 BUFFER STOPS..................................................................................................6410.5 TESTS ON COMPLETION...................................................................................64

11. CONCRETE: PLAIN & REINFORCED...........................................6711.1 MATERIALS.........................................................................................................6711.2 BLENDING OF AGGREGATES:...................................................................................7111.3 ADMIXTURES:.........................................................................................................7111.4 BATCHING PLANTS, MIXERS AND VIBRATORS:..........................................................7211.5 GRADE OF CONCRETE:...........................................................................................7211.6 MIX DESIGN:..........................................................................................................7211.7 PERMEABILITY TEST FOR CONCRETE:......................................................................7311.8 BATCHING OF CONCRETE INGREDIENTS:..................................................................7411.9 PLACING TEMPERATURES:.......................................................................................7511.10 TRANSPORTING, PLACING, COMPACTING AND CURING, :...........................................7511.11 CONSTRUCTION JOINTS:.........................................................................................7811.12 COVER AND COVER BLOCKS:..................................................................................7911.13 CRACKS:................................................................................................................7911.14 DEFECTIVE CONCRETE:..........................................................................................8011.15 EXPOSED FACES, HOLES AND FIXTURES:................................................................8011.16 FINISHES:...............................................................................................................8011.17 CONCRETE FOR FLOORING ON GRADE:....................................................................8011.18 GROUTING OF BASE PLATES & BOLT HOLES:............................................................8111.19 PRE-CAST CONCRETE:............................................................................................8211.20 READY MIX CONCRETE AND PUMPING:....................................................................8311.21 ADDITIONAL SPECIFICATIONS FOR CONCRETE M60..................................................8611.22 MEASUREMENT.......................................................................................................86

12. REINFORCEMENT.........................................................................8812.1 INSPECTION & TESTING:..........................................................................................8812.2 BAR BENDING AND BAR BENDING SCHEDULE:..........................................................8812.3 LAPPING & WELDING:.............................................................................................8912.4 SPACING, SUPPORTING AND CLEANING:...................................................................8912.5 WELDING:..............................................................................................................8912.6 MEASUREMENT:......................................................................................................90

13. FORMWORK..................................................................................9113.1 THESE SPECIFICATIONS SHALL BE READ IN CONJUNCTION WITH THE CPWD SPECIFICATIONS 1996, MOST SPECIFICATIONS AND OTHER RELEVANT

SPECIFICATIONS DESCRIBED IN THE CLAUSE 6.2.3 OF THESE SPECIFICATIONS........9113.2 MATERIALS:............................................................................................................9113.3 DESIGN & DRAWINGS:............................................................................................9113.4 ERECTION OF FORMWORK:.....................................................................................9113.5 CONCRETE FINISHES:.............................................................................................9213.6 EXPOSED CONCRETE WORK:..................................................................................9313.7 AGE OF CONCRETE AT REMOVAL OF FORMWORK:....................................................9413.8 Reuse of Forms:...................................................................................................94

Technical Specification July 2007

Page 4: Technical Specification

MMOPL Tender TW Series 1000

1. INTRODUCTION

1.1 Employer’s Requirements – Technical Specification

1.1.1 This specification defines the objectives, guidelines and requirements for

Design, Supply, Installation, Testing and Commissioning of Trackwork on

ballasted and ballastless sections for Versova –Andheri – Ghatkopar (VAG)

Corridor of the Mumbai MRTS.

1.1.2 Subject to the Employer’s decision to supply item under Part: B1 of Bill Of

Quantities (BOQ), the contract shall include manufacture & supply of all

materials including turn outs, cross-overs & scissors cross-overs complete with

their fittings, rail fastenings, restraining rails, and the running rails for all tracks –

main line & depot required for trackwork and shall include verification, delivery,

survey, setting out, installation, testing, including Integrated Testing and

Commissioning, technical support, training of Employer’s Representative‘s staff

and documentation for a complete system necessary to deliver the requirements

of this specification. Scope of work may also include maintenance of tracks for a

period of 5 years.

1.1.3 This Employer’s requirements – Technical Specification for the Trackwork

shall be read in conjunction with the following documents:

a) Instructions to Tenderers (including Annexures)

b) Form of Tender (including Appendices)

c) Form of Contract Agreement along with Schedules

d) Conditions of Contract along with Schedules

e) Employer’s Requirements - General Specification (GS)

f) Employer’s Requirements - Technical Specification (TS)

g) Tender Drawings

h) Safety, Health and Environment Conditions

i) Quality Assurance

j) System Assurance

k) Contract for Maintenance

1.1.4 In the event of a conflict between this Specification and any other standards or

specification quoted herein, the requirements of this Specification shall prevail.

The order of precedence, with item a) having the highest priority, is:

a) Employer’s Requirements - Technical Specification

b) Employer’s Requirements - General Specification

c) Indian Standards to the extent applicable for Standard gauge, if any

d) International Standards referenced herein.

e) Other International Standards

Technical Specification Page 1 of 94 July 2007

Page 5: Technical Specification

MMOPL Tender TW Series 1000

f) Other National Standards.

Notwithstanding the precedence specified, the Contractor shall always immediately seek advice from the Employer in the event of conflicts between above items.

1.1.5 The responsibility for the design of Trackwork lies with the Employer, however

the Contractor shall notify the Employer’s Representative of any shortcomings in

the design as soon as it comes to their notice.

1.2 Definitions and Abbreviations

1.2.1 Capitalised terms used and to the extent not defined herein, shall have the

respective meanings assigned to them under the Employers Requirements -

General Specification and/ or the Conditions of Contract.

1.2.2 Abbreviations used in this Employer’s Requirements - Technical Specification

for the Trackwork are listed as stated here. Also refer to the Conditions of Contract and the Employers Requirements - General Specification.

Trackwork Abbreviations

CWR Continuous Welded Rail

EVA Ethyl Vinyl Acetate

FC Flangeway Clearance

GIRJ Glued Insulated Rail Joint

HDPE High Density Polyethylene

HH Head Hardened

HVN High Viscosity Nylon

LWR

PSC

Long Welded Rail

Pre-stressed Concrete

P&C Point & Crossing

REJ Rail Expansion Joint

Standards Abbreviations

AREA American Railway Engineering Association

DIN German Standards

EN European Standards

IEC International Electrotechnical Commission

UIC International Union of Railways

USFD Ultra-sonic Flaw Detection

Other Abbreviations

BEC Burried Earth Conductor

DFF Direct fixation fastener

E&M Electrical and Mechanical

ETU Electric traction unit

HTS High Tensile Strength

OCS Overhead Catenary System RCC Reinforced Cement Concrete

Technical Specification Page 2 of 94 July 2007

Page 6: Technical Specification

MMOPL Tender TW Series 1000

1.3 DESIGN AND PERFORMANCE REQUIREMENTS

1.3.1 General

1.3.1.1 The Trackworks shall meet the design and performance requirements within

the Environmental Considerations specified in GS and TS in such a way that the

Trackwork/Equipment should function to its full capacity within the

Environmental Considerations.

1.3.2 Environmental Considerations

1.3.2.1 Environmental Considerations/Climatic Conditions/Operating Environment

stipulated in clause 1.13 of Employers Requirements - General Specification

shall apply.

1.3.2.2 The Trackwork equipment will be exposed to extreme weather conditions such

as heat, dust, humidity, salinity, rainfall and occasional seepage. The system

design shall take into consideration all of the above conditions and ensure that

the performance of the system remains unaffected due to such conditions.

1.3.2.3 Special consideration shall be made by the Contractor for corrosive

environment of Mumbai.

1.3.3 Basic Design Philosophy and Requirements

1.3.3.1 Proven Design

(a) The Contractor can develop the design based on this Specification. The

design details shall be submitted with the technical data and

calculations to the Employer for his approval.

(b) The Trackwork including all equipments shall be of proven design. The

Trackwork equipment, hardware and software proposed by the

Contractor shall have been in use and established their satisfactory

performance over a period of at least two years on two MRTS systems

during the last five years or such period as may be specified in this

specification for any particular component or subject of the Trackwork.

(c) Where similar Trackwork equipments of a different rating are already

proven in service, then the design shall be based on such equipment. In

case these stipulations are not fulfilled, the Contractor shall furnish

sufficient information to prove the basic soundness and reliability of the

offered Trackwork equipment.

1.3.3.2 The design philosophy should meet the following criteria:

(i) Application of state-of-the-art Technology

(ii) Service proven design

Technical Specification Page 3 of 94 July 2007

Page 7: Technical Specification

MMOPL Tender TW Series 1000

(iii) Design life 35 years

(iv) Minimum life cycle cost

(v) Ease of maintainability

(vi) Use of interchangeable, modular components

(vii) Extensive and prominent labelling of parts, cables and wires

(viii) Use of unique serial numbers for traceability of components

(ix) High reliability

(x) Energy efficiency

(xi) System safety

(xii) Adequate redundancy and factor of safety.

(xiii) Use of fire retardant materials

(xiv) Lowest possible emission of noise and vibration

(xv) Adherence to functional, operational and performance requirements

(xvi) Open Architecture for integration with other Systems

(xvii) Ease of expansion and integration

1.3.3.3 Adequate margin shall be built into the design particularly to take care of the

environmental considerations prevailing in Mumbai.

1.3.4 Performance Requirements

1.3.4.1 The reliability and maintainability processes and procedures shall be planned,

integrated and developed in conjunction with the operating environment, and the

design, development and production functions shall allow the most effective and

economical achievement of the systems and equipment design objective.

1.3.4.2 The systems shall meet or exceed the RAMS requirements specified in the

System Assurance document. The reliability of the system designed, supplied

and installed is the principal element for availability. It is essential that system

reliability is as high as reasonably practicable.

1.3.4.3 A high design standard incorporating redundancy if practicable, flexible

system arrangement, together with good quality products, and adherence to

strict manufacturing standards, are required to ensure high reliability of systems

installed.

1.3.5 Conformity with Governing Specifications and other Statutory

Requirements

1.3.5.1 The Contractor shall comply with all Applicable Laws and regulations.

1.3.5.2 The Contractor shall furnish all information upon request by statutory bodies

(e.g. Commissioner of Safety, etc.) in particular format as directed by Employer.

Technical Specification Page 4 of 94 July 2007

Page 8: Technical Specification

MMOPL Tender TW Series 1000

1.3.6 Interface Activities

1.3.6.1 Interfaces exist between the Contractor and the Designated Contractors for

systems, where the systems are mutually dependent, or interactive for

satisfactory and safe operation. The Contractor shall maintain close

coordination/interface during design, manufacturing, testing, commissioning,

Integrated Testing & Commissioning, trial run and defect liability period with the

Designated Contractors and consultants who may be working on the Project,

whether or not specifically mentioned in the Contract. The Contractor shall

perform all design duties and provide all materials, equipment and labour to

ensure the satisfactory accomplishment of interface of the systems for which the

Contractor is responsible.

1.3.6.2 The Contractor shall approach the Employer for the general interface

information such as interface requirements, contact points of the Designated

Contractors, and once information is received, would coordinate with them for

interface activities including the Employer in the information loop.

1.3.6.3 The Contractor shall submit and maintain an agreed Interface Management

Plan. At all stages of the work, all interfaces shall be discussed and agreed

upon, through the Employer between the Contractor and the Designated

Contractors. Interfaces should essentially be with Civil Infrastructure, Power

Supply & Traction, E & M, Telecommunications and other Designated

Contractors advised by the Employer. The Employer’s Requirements - General

Specification outlines the requirements of the Interface Management Plan.

1.3.6.4 The Contractor shall liaise with the Designated Contractors directly to discuss

and agree on interfaces. However, the Contractor shall keep the Employer

apprised in writing of all such discussions, agreements and conclusions.

1.3.6.5 It will be the responsibility of the Contractor that interface requirements be

finalised as early as possible. Contractual delays and consequential

implications as a result of delay in such co-ordination on account of reasons

attributable to the Contractor, as concluded by Employer, shall be the sole

responsibility of the Contractor.

1.3.6.6 It would be the responsibility of the Contractor to settle all disagreements with

the Designated Contractors. If such disagreement cannot be resolved by the

Contractor, despite all reasonable efforts, then the decision of the Employer

shall be final and binding on both parties.

1.3.6.7 Broad interface requirements between the Contractor and the Designated

Contractors detailing the interfacing issues and division of responsibility are

summarised in the Employers Requirements - General Specification.

1.3.6.8 The above interface obligations placed on the Contractor shall be read in

conjunction with the interface obligation mentioned in GS, Conditions of

Contract and other Contract documents.

Technical Specification Page 5 of 94 July 2007

Page 9: Technical Specification

MMOPL Tender TW Series 1000

1.3.7 Quality Assurance

1.3.7.1 The Contractor shall comply with the requirements of the Quality Assurance document (Volume -IV).

1.3.8 System Safety Assurance

1.3.8.1 The Contractor shall comply with the requirements of the System Assurance document (Volume -IV).

1.3.9 Hazard Analysis

1.3.9.1 The Contractor shall produce a Hazard Analysis Schedule for the complete

System and shall interface with the Designated Contractors to obtain all the

information necessary, from their hazard analysis, to complete the analysis.

1.3.9.2 The Contractor shall, as part of the safety analysis, prepare analysis to identify

Hazards and ensure their satisfactory resolution. The following analysis shall

be prepared and submitted by the Contractor for the Employer’s acceptance.

i) Preliminary hazard analysis

ii) Interface hazard analysis.

iii) Subsystem hazard analysis

iv) Operating hazard analysis including maintenance

v) Quantitative fault tree analysis

vi) Failure modes effects and criticality analysis (FMECA)

1.3.9.3 The Hazard Analysis shall be carried out in accordance with EN50126 as the

primary standard, or any other internationally accepted equivalent standard, in

areas not adequately addressed by the former standard.

1.3.9.4 The Contractor shall compile a list of safety critical and non safety critical

items identified as a result of hazard analysis, FMECA or by other means. The

Contractor shall carryout the Hazard Analysis and FMECA for key equipment /

sub-systems / systems.

1.3.9.5 All hazard resolution by procedural control shall be cross-referenced from the

safety critical and non safety critical Items List to the appropriate manuals.

1.3.9.6 Component failure or procedural deficiencies shall not result in injury to

personnel, occupational health or damage to the system.

Technical Specification Page 6 of 94 July 2007

Page 10: Technical Specification

MMOPL Tender TW Series 1000

Unless specified otherwise in the System Assurance document, the Contractor

shall submit a for Hazard Analysis Schedule Submissions within 30 days of

Commencement Date (CD) and the Preliminary Hazard Analysis shall be

submitted within 3 months of Commencement Date. This draft shall include a

comprehensive assessment of potential equipment failure modes during normal

operating and overload conditions. The final draft shall be submitted well in

advance of Detailed Design Completion date of final design.

1.3.9.7 The Contractor shall prepare a Fire Safety Design Report for review and

acceptance by the Employer. This shall be submitted within 2 months of the

Commencement Date, revised and updated based on any comment from

Employer.

1.3.9.8 Materials used shall comply to National/International Standards of fire safety.

1.3.9.9 The procedures for Operation, Maintenance, Training and the Contractor

Quality Assurance manuals shall incorporate resolution of hazards so identified

from this Hazard Analysis. Proper cross-referencing to the hazards and

resolution measures shall be provided in all these aforementioned documents.

1.3.9.10 Source of all failure rates employed to be indicated in the Hazard Analysis.

1.3.9.11 All Hazard Analysis submitted to the Employer are to be standardised by the

Contractor such that format and forms employed by all sub-Contractors are the

same.

1.3.10 Reliability, Availability and Maintainability: General

1.3.10.1 Reliability, Availability and Maintainability (RAM) requirements and goals shall

be developed in terms of Mean Time Between Failures (MTBF), percentage

Availability and Mean Time To Repair (MTTR). The Contractor shall perform

RAM analysis up to the point of interface with the Designated Contractor

systems.

1.3.10.2 The Contractor shall also comply with the guidelines of IEC 60300-1, IEC

60300-2 and IEC 60571 for electronic equipment, and IEC 60605-1 in meeting

the reliability, availability and maintainability requirements of equipment or as

specified in the System Assurance document.

1.3.10.3 The Contractor shall submit a Reliability, Availability and Maintainability Plan as

specified in the System Assurance document. The Contractor shall verify, after

system design have been completed, that the reliability, availability and

maintainability requirement will be met.

1.3.11 Quantitative Reliability

1.3.11.1 The Contractor shall demonstrate by quantitative methods achievement of the

specified levels of reliability for the system as a whole and specific individual

items of equipment.

Technical Specification Page 7 of 94 July 2007

Page 11: Technical Specification

MMOPL Tender TW Series 1000

1.3.11.2 An evolving reliability model consisting of reliability block diagrams and

probability of success equations shall be developed and submitted to the

Employer for acceptance. This model shall show the relationships required for

system and equipment to operate successfully. The reliability block diagrams

shall include all elements essential to the successful performance of the system

and their interrelationships and interfaces.

1.3.11.3 Reliability apportionment and prediction analysis shall be in accordance with

established techniques or standards, which will be submitted for acceptance by

the Employer. The analysis shall provide predictions for each major equipment

and sub-system. Predictions shall be based on actual revenue service results

for identical equipment operating under service conditions and duty cycles

similar to the proposed Mumbai MRTS. The relevant apportionment and

prediction figures shall be part of the design submission documents for the

individual equipment, sub-system and system.

1.3.11.4 Reliability Apportionment and Prediction Report shall be completed prior to

manufacture commencing and reports shall be submitted at this stage for

acceptance by the Employer.

1.3.12 Reliability Requirements

1.3.12.1 Reliability Requirements and Targets shall be assessed by the details specified

in the System Assurance document (Volume-IV)

1.3.13 Reliability Demonstration

1.3.13.1 The Contractor shall collect and maintain data on every Service Failure along

with the data indicating the probable failure. The Contractor shall submit monthly

Reliability Demonstration Reports based on service failure data.

1.3.13.2 In case the Contractor is not able to achieve specified/provided reliability target

of MTBF/MTBCF, the Contractor shall take necessary corrective measures

either by way of change of design of the relevant equipment/ component,

software modification or change in maintenance regime.

1.3.13.3 The Contractor shall analyse each and every failure/defect of components of

various equipment to determine the cause of failure and to propose corrective

measures, which would be reviewed by the Employer.

1.3.13.4 A record shall be maintained for each and every defect/failure in accordance

with the Failure Reporting Analysis and Corrective Action System (FRACAS) as

stated in Clause 1.3.13.1 to be submitted by the Contractor and approved by the

Employer.

Technical Specification Page 8 of 94 July 2007

Page 12: Technical Specification

MMOPL Tender TW Series 1000

1.3.13.5 Reliability shall be monitored during revenue service operation. The Contractor

shall collect and collate data on each and every deficiency and failure observed

both by him and the Employer, from handing over the System to the end of the

Defect Liability Period. Each and every failure, whether of component, sub-

system or system, during this period shall be subject to a failure analysis to

determine the cause of the failure. The Contractor shall submit investigation

reports for review and approval by the Employer.

1.3.13.6 Correction shall be made to components or subsystems that either fail to attain

predicted reliability levels or show Pattern Failure, at no additional cost to the

Employer.

1.3.14 Availability Requirements

1.3.14.1 Availability Requirements and Targets shall be assessed by the details specified

in the System Assurance document (Volume-IV)

1.3.15 Availability Demonstration

1.3.15.1 The average availability of the System in the first year of revenue service and

from start of second year onwards shall be assessed.

1.3.15.2 In the event that the availability target as specified in the System Assurance

document is not achieved, the Contractor shall, at his own expense, take

whatever action is deemed necessary to meet the availability target.

1.3.16 Maintainability Requirements

1.3.16.1 Maintainability Requirements and Targets shall be assessed by the details

specified in the System Assurance document (Volume-IV)

1.3.16.2 Simplicity case of maintenance, operation and emergency procedures, ease of

repair of damaged equipment, are most important.

1.3.16.3 Particular attention shall be paid during the design and supply of the equipment

to ensure that scheduled maintenance tasks are achieved in minimum time and

using minimum manpower.

1.3.16.4 Those components, systems and assemblies which require routine

maintenance, frequent attention or unit replacement, shall be easily accessible

for in-situ maintenance and or removal.

1.3.16.5 The Contractor shall develop a comprehensive maintenance programme for the

each equipment and System as a whole.

1.3.16.6 The Tenderer shall submit the expected MTTR in accordance with EN 50126 of

the identified key systems.

Technical Specification Page 9 of 94 July 2007

Page 13: Technical Specification

MMOPL Tender TW Series 1000

1.3.16.7 During the design stage, the Contractor shall submit periodicity, downtime and

manpower requirements for the maintenance inspections and services

considered necessary for maintaining the System under maximum operational

conditions.

1.3.17 Maintainability Demonstration

1.3.17.1 The Contractor shall carry out tests to demonstrate that all maintainability

predictions are achieved. In the event that any maintainability target is not

achieved, the Contractor shall at his own expense take whatever action is

deemed necessary to meet the maintainability targets.

1.3.18 Safety-related Systems Interference

1.3.18.1 Special attention must be given to the interference with safety-related operations

and equipment such as the Power Supply and Traction systems. Adequate

safety margins must be ensured between the immunity levels of these safety-

related systems and the emission levels of the Trackwork specified by prevailing

international standards.

1.3.18.2 The subsystems and components which could possibly give rise to the level of

emissions under both normal and fault conditions (conducted, induced or

radiated) that may affect the safety-related systems must be identified. The

quantified risk assessment must be carried out as part of the Hazard Analysis to

determine the probabilities and effects of such interference. Measures must be

taken to reduce such emissions. The reliability of subsystems and as well as the

additional measures, e.g., filter, must be investigated.

1.3.18.3 The probabilities of various conditions which could lead to an unsafe operation

must be determined. A technical construction file suitable for safety audit must

be developed to demonstrate to the Employer.

1.3.19 Installation and Mitigation Guidelines

1.3.19.1 IEC61000-5 Installation and Mitigation Guidelines must be observed wherever

applicable.

1.3.20 Fire Performance

1.3.20.1 General

i) Each equipment shall be designed using fire retardant material to minimise the risk of fire.

ii) Enclosures for control and critical equipment shall be located to provide protection against environmental contamination and mechanical damage.

iii) Materials used in the construction of equipment shall be selected to reduce to the maximum extent practicable - the heat load, rate of heat

Technical Specification Page 10 of 94 July 2007

Page 14: Technical Specification

MMOPL Tender TW Series 1000

release, propensity to ignite, rate of flame spread, smoke emission and toxicity of combustion gases.

iv) The equipment shall be designed to prevent fire propagation through the use of fire resistant equipment housings.

v) The Contractor shall submit a plan to the Employer for approval which shall describe the process that will be used to systematically identify and eliminate fire hazards, to avoid the use of combustible materials whenever practical and to reduce to the extent practical the energy content and heat release rates of the combustible material that are used.

vi) The plan shall include the Standards to be followed and the tests to be completed and shall be submitted for approval by the Employer.

1.3.21 Life Cycle Cost

1.3.21.1 The Contractor shall develop a life cycle cost plan in accordance with IEC

60300-3-3 with an aim to optimise the overall life cycle cost whilst meeting the

safety, quality and reliability requirement of this Employers Requirements -

Technical Specification.

Technical Specification Page 11 of 94 July 2007

Page 15: Technical Specification

MMOPL Tender TW Series 1000

2. QUALIFICATIONS OF MANUFACTURER

2.1 Material

2.1.1 All materials and equipment to be provided for the Trackwork shall be of

proven design by a manufacturer who has manufactured and supplied similar

material and equipment for Trackwork projects for a period of at least five (5)

years in the Railway Industry..

2.2 Engineers in Charge of Trackwork

2.2.1 All Trackwork designs shall be executed by well trained and qualified

engineers under the leadership of an experienced Trackwork design manager

with not less than 10 years of design experience. Curriculum Vitae of the design

manager of the Contractor shall be provided to the Employer for approval prior

to the commencement of the Execution of the Works.

2.2.2 All Trackwork testing shall be carried out by well trained and qualified

engineers under the leadership of an experienced Trackwork testing manager

with not less than 10 years of testing experience. Curriculum Vitae of the

Trackwork testing manager shall be provided to the Employer for approval prior

to the commencement of the Execution of the Works.

Technical Specification Page 12 of 94 July 2007

Page 16: Technical Specification

MMOPL Tender TW Series 1000

3. SCOPE OF WORK

3.1 SCOPE

3.1.1 Subject to the Employer’s decision to supply items under Part: B1 of BOQ, this

specification establishes the requirements for the design, manufacture, supply,

installation, Integrated Testing and Commissioning of track work for Versova –

Andheri – Ghatkopar (VAG) corridor of Mumbai MRTS and the at grade depot at

DN Nagar. The track alignments and details of curves, turnouts, x-overs,

gradients, etc. are shown in the alignment drawings for the main lines and in the

layout drawings for the depot. The coordinated alignments will be issued to the

Contractor not less than 1 month before start of construction of trackwork for the

main lines and for the depot. All such information shall be verified by the

Contractor for its geometrical correctness before setting out and survey checks

shall be made before and after laying the tracks to ensure clearance is provided

to all infrastructure works in compliance with the Structure Gauge given in the

Schedule of Dimension attached herewith in Volume IV.

3.1.2 A work base area for execution of this Contract will be provided by the

Employer at a suitable location. If required by the Contractor, other work areas

along the corridor shall be arranged and established by the Contractor as

necessary at no cost to the Employer.

3.1.3 The track work in DN Nagar Depot shall be installed according to the

mathematised depot layout after duly interfacing with the Employer’s

Representative and the Designated Contractors.

3.1.4 The Contractor shall arrange his own mobile flash butt welding plant which

can be used on elevated viaduct.

3.1.5 For the ballasted trackwork in the depot the Contractor shall arrange to use

off track tamper capable of tamping both plain line and turnouts.

3.1.6 The Contractor shall be required to interface closely with the various Detailed

Design Consultants and the Designated Contractors.

3.1.7 The scope of work shall include, but not be limited to, the following:

Supply of all track and other materials, including running rails, turnouts, cross-

overs and scissors cross-overs (complete with their fittings), rail fastenings,

restraining rails, which may be supplied by the Employer. The Contractor will

make arrangements for the handling and transportation of all materials to the

Site.

Survey control and setting-out at all stages of the Works.

A. Ballastless Track

I. Transporting rails and welding them into long panels, testing by Ultra

Sonic Flaw Detection, painting of rail welds, weld markings,

Technical Specification Page 13 of 94 July 2007

Page 17: Technical Specification

MMOPL Tender TW Series 1000

II. Linking of rails to the line and level with fastenings, assembly of

Points & Crossings,

III. Fixing reinforcement in position, fixing Over Head Equipment,

Signalling & Telecommunication fixtures,

IV. Erection & subsequent striking of form work,

V. Concreting of plinth beam and track slabs,

VI. Removing dummy plates and complete rear work & reassembly of

rail panels,

VII. Recording and correction of track parameters

VIII. Destressing & welding of Long Welded Rail strings to form

Continuous Welded Rail, and adjusting Rail Expansion Joint gaps,

IX. Fixing Km, Gradient, Fouling Mark, Turnout posts, Curve posts &

other posts,

X. Final checking of track parameters,

XI. Integrated Testing & Commissioning of track.

B. Ballasted Track

I. Inspect prepared formation & maintain condition suitable for track

laying,

II. Ballasting (6”) and light compaction by roller,

III. Spreading sleepers,

IV. Linking welded panels, Turnout,

V. Ballasting,

VI. Tamping, squaring of sleepers, boxing of ballast, adjusting line & level,

VII. Final tamping with off-track tampers,

VIII. Recording and correction of track parameters,

IX. Destressing of Long Welded Rail, adjusting Rail Expansion Joint gap,

X. Fixing Fouling Mark etc

XI. Final checking of track parameters,

XII. Integrated Testing & Commissioning of track.

Technical Specification Page 14 of 94 July 2007

Page 18: Technical Specification

MMOPL Tender TW Series 1000

3.2 GENERAL CRITERIA AND TRACK PARAMETERS

3.2.1 General Criteria

CRITERIA DIMENSION

1 Gauge 1435 mm

2 Max. operating speed 80 Kmph

3 Max. axle load, loaded condition 17 tonne

4 Max. gradient running track

Max. gradient depot connecting track

3%

3%

5 Minimum vertical curve radius

Minimum horizontal curve radius

1500m

100 m (main line track)

80 m (depot track)

6 Traction power collection Overhead Catenary system

(OCS) at 25kV(AC)

Rails shall be used for traction

return current.

7 Inclination of Rail 1 in 20

8 Wheel tread profile UIC 510-2 (S1002)

9 Rail profile UIC 60 (861-3)

Technical Specification Page 15 of 94 July 2007

Page 19: Technical Specification

MMOPL Tender TW Series 1000

3.2.2 Track Structure Parameters

Description Metro Corridor

Ballasted Ballastless(DFF)Rail type main line

---UIC 60, 880 grade and1080 grade Head Hardened

Rail type depot UIC 60, grade 880 & grade 1080 grade HH

UIC 60, 880 and 1080 grade HH

Nominal Sleeper/base plate SpacingStraight TrackCurved Track

700 +/- 25 mm600 +/- 25 mm

625 +/- 5mm625 +/- 5mm

Minimum Ballast cushion depth Depot – 200mm ---Formation cross fall 1 in 20 ---Standard Rail length Main lineDepot line

--26 m

26 m 26 m

Maximum cant50mm 125mm

Maximum cant deficiency:Plain LineTurnouts

100 mm100 mm

110 mm100 mm

Desirable cant gradientMaximum cant gradient

1 in 7201 in 400

1 in 7201 in 400

Rate of change of cant/cant deficiency

Maximum Desirable

55 mm/sec35 mm/sec

55 mm/sec35 mm/sec

Type of turnout(i) Main line

(ii) Depot lines

---

100-1:6 (25km/h)

190-1:9 (40km/h) and 190-1:7 (40km/h)

---

Technical Specification Page 16 of 94 July 2007

Page 20: Technical Specification

MMOPL Tender TW Series 1000

3.2.3 Vertical Alignment

3.2.3.1 Points and Crossing

No change of grade shall be permitted within points and crossing, and vertical

curves shall be separated from turnouts by at least 3m.

3.2.4 Continuous Welded Rail

Long welded rail strings shall be joined to form continuous welded rails and

finally fastened so that the zero thermal stress rail temperature lies within the

range of (mean-rail-temperature + 5) to (mean-rail-temperature + 10) degree

Celsius using a mean-rail-temperature value of 37 ゚C.

3.3 SCHEDULE OF DIMENSION

The Contractor shall ensure that no permanent structure is within the Structure

Gauge profile and the material & installation of track work shall comply with the

provisions of Schedule of Dimensions. The Schedule of Dimensions is tentative

and any change to it shall be advised to the Contractor.

The Schedule of Dimension is attached herewith in Volume – IV.

3.4 RESPONSIBILITY OF THE CONTRACTOR

3.4.1 The Contractor shall be responsible for all trackwork which includes the main

running lines, the connection tracks and the tracks in the Depot (about 6km. of

track).

3.4.2 Rail access to the elevated sections for track laying will only be possible using

the ramped connections tracks from DN Nagar Depot. In the case where access

is necessary, by crane from adjacent public roads, the Contractor shall be

responsible for arranging all necessary permits and the traffic management

measures, as required.

3.4.3 The tracks on elevated structures shall be ballastless and friction sliding buffer

stops shall be provided for all track ends.

3.4.4 There are approximately 6kms of tracks in DN Nagar Depot which shall be

ballasted, embedded/paved, plinthed or pitted as required and as indicated in

the relevant drawings. All track ends in buildings shall be fitted with wheel stops.

All other track ends shall be equipped with fixed concrete buffer stops. Level

crossings are envisaged in the depot as indicated in the depot layout drawings

Technical Specification Page 17 of 94 July 2007

Page 21: Technical Specification

MMOPL Tender TW Series 1000

4. INTERFACES

4.1 INTERFACE MATRICES

Interface Matrices are included in the General Specification. These describe the

principal interfaces between the Contractor and the Designated Contractors.

These matrices shall be developed, updated and expanded as necessary to

encompass all the relevant interface issues encountered during the execution of

Contract.

Technical Specification Page 18 of 94 July 2007

Page 22: Technical Specification

5. INSTALLATION AND CONSTRUCTION SCHEDULE

5.1 REQUIREMENTS

5.1.1 General Requirements

5.1.1.1 The Contractor shall comply with all Applicable Laws in executing the works,

including but not limited to all Statutory provisions on occupational health and

safety.

5.1.1.2 The Contractor shall co-ordinate with the Designated Contractors in the

execution of the Works.

5.1.1.3 The Contractor shall also co-operate with all Relevant Authorities in the

execution of the works.

5.1.1.4 All machinery and equipment shall be properly maintained and operated at all

times by suitably trained and competent employees of the Contractor and to the

satisfaction of the Employer’s Representative.

5.1.1.5 Only appropriate tools, plant, machinery and equipment and vehicles shall be

used.

5.1.1.6 The Contractor shall, prior to starting any installation and construction work,

identify any possible hazards, and implement measures of eliminating and/or

mitigating such potential hazards, in line with safe working practices.

5.1.1.7 Further details on Site Safety management are described in Safety Health

and Environment Conditions (Volume IV). The Contractor shall ensure that all

areas of work are sufficiently illuminated for the works to be undertaken and that

a safe system of work is employed for all activities.

5.1.1.8 The Contractor shall comply with all its obligations with respect to ensuring

Security of the Works at the Site. This comprises a suitable system for the

control of persons entering or working on the Site. The system shall include as a

minimum:

Register of all employees

Personal identification with photograph and signature/thumb impression

Levels of competence;

Date of joining

Date of discharge;

Register of all visitors.

Technical Specification Page 19 of 94 July 2007

Page 23: Technical Specification

MMOPL Tender TW Series 1000

5.1.1.9 The Contractor shall co-operate, at all times, with the Employer’s

Representative and the Designated Contractors to ensure that the Site is

protected from unauthorised admission, either wilfully or otherwise.

5.1.1.10 The Contractor shall make due provisions for safe access to and egress from

the Site for its staff and subcontractors. This access shall be maintained such

that it is free of all hazards and is in a safe condition throughout the duration of

the works.

5.1.1.11 The Contractor shall provide the survey equipment, track measuring equipment

and other accessories as per the instructions of Employer’s Representative as

and when required. He shall also provide all necessary help and manpower as

required by the Employer’s Representative for checking the works, whenever

required.

5.1.2 Specification Requirements:

5.1.2.1 The installation and construction work pertaining to this contract shall include,

but not be limited to the following: -

Survey on site and review the technical requirements shown in this

specification and the Employer’s Representative’s drawings.

Finalisation of the construction and installation program

Production of the calculation sheets and installation drawings for site

installation.

Installation in accordance with the finalised installation drawings.

Co-ordination with the Designated Contractors.

Submission of the installation reports and records.

Testing and commissioning as per finalised protocol and programme.

Production of as built drawings, documents, calculations sheets, and

records.

Technical Specification Page 20 of 94 July 2007

Page 24: Technical Specification

MMOPL Tender TW Series 1000

6. CODES AND STANDARDS

6.1 INTRODUCTION

6.1.1 This Materials and Workmanship Specification for Track work shall be read in

conjunction with all the documents forming part of the Contract.

6.1.2 No Permanent Works shall be carried out until all methods and materials have

been approved.

6.1.3 Unless noted otherwise in the Contract, all components and materials shall be

handled, transported and stored, in accordance with the manufacturer’s

recommendations with prior approval of Employer’s Representative.

6.1.4 The test results of each test to be carried out as per Employer’s

Representative’s requirement shall be recorded and submitted in a format

approved by the Employer’s Representative and shall include graphical

presentation of results as well as numerical base data where ever required.

6.2 CODES AND STANDARDS

Track work materials, components and assemblies shall comply with the

requirements and Standards given in the present Specification. However, it shall

be the responsibility of the Contractor to adopt the latest version of the technical

specification with all correction slips.

6.2.1 International Union of Railways Standard Codes (UIC)

UIC Code 860 – 0 Technical Specification for the supply of Rails

UIC Code 861 – 3 Standard 60 kg/m Rail Profiles

Types : UIC 60 and 60 E

UIC Code 864 – 2 Technical Specifications for Supply of Steel Track Bolts

UIC Code 864 – 3 Technical Specifications for the supply of spring steel washers for use in Permanent Way.

UIC Code 864 – 4 Technical Specification for supply of Fishplates or sections for Fishplates made of rolled steel

UIC Code 864 – 5 Technical Specification for the Supply of Rail Seat Pads

UIC Code 864 – 8 Rolled Profiles for Fishplates for 54 kg/m and 60 kg/m Rails

UIC Code 866 – 0 Technical Specification for the supply of cast manganese steel crossings for switch and crossing work

6.2.2 International Organisation for Standardisation (ISO)

ISO 1113 Information Processing – Representation of the 7 bit coded character set on punched tape

ISO 1191 Plastics – Polyethylene and Polypropylenes in dilute Solution-Determination of viscosity number and of limiting

Technical Specification Page 21 of 94 July 2007

Page 25: Technical Specification

MMOPL Tender TW Series 1000

viscosity number.

6.2.3 Indian Standards (IS)

6.2.3.1 Cement

IS : 269 Specification for 33 grade ordinary portland cement.

IS : 650 Specification for standard sand for testing of cement.

IS : 4031 Methods of physical tests for hydraulic cement

IS : 4032 Method of chemical analysis of hydraulic cement

IS : 6925 Methods of test for determination of water soluble chlorides in concrete admixtures

IS: 8112 Specification for 43 grade ordinary portland cement.

IS : 12269 Specifications for 53 grade ordinary portland cement.

6.2.3.2 Concrete

IS : 383 Specification for coarse and fine aggregates from natural

sources for concrete.

IS : 456 Code of practice for plain and reinforced concrete.

IS: 516 Methods of test of strength of concrete.

IS : 1199 Methods of sampling and analysis of concrete.

IS : 2386 Parts i to vii. methods of tests for aggregates for concrete.

IS : 7861 Parts i and ii. code of practice for extreme weather

Technical Specification Page 22 of 94 July 2007

Page 26: Technical Specification

MMOPL Tender TW Series 1000

concreting.

IS : 10262 Recommended guidelines for concrete mix design

IRS Concrete bridge code

IRC : 21-1987 Standard specifications and code of practice for road bridge

section – III cement concrete (plain & reinforced (first

revision)

IS : 9103 Specifications for admixture for concrete

BS : 14 (Revised)

6.2.3.3 Formwork

IS : 456 Code of practice for plain and reinforced concrete

IS: 4990 Plywood for concrete shuttering work

IRC: 87 Guidelines for design & erection of false work for road

bridge.

IS: 806 Code of practice for use of steel tubes in general building

construction.

IS: 1161 Specification of steel tubes for structural purposes.

IS: 1239 Specification of mild steel tubes. tubular and other wrought

steel fittings.

IS: 2750 Specification for steel scaffoldings.

6.2.3.4 Steel

IS: 280 Mild steel wire for general engineering purposes.

Technical Specification Page 23 of 94 July 2007

Page 27: Technical Specification

MMOPL Tender TW Series 1000

IS: 432 Part I mild steel and medium tensile steel bars.

Part II hard drawn steel wire.

IS: 456 Code of practice for plain and reinforced concrete.

IS: 814 Parts I & II electrodes for metal arc welding of structural

steel.

IS: 816 Code of practice for use of metal arc welding for general

construction in mild steel.

IS: 1566 Hard-drawn steel wire fabric for concrete reinforcement

IS: 1786 Specification for high strength deformed steel bars and

wires for concrete reinforcement.

IS: 2502 Code of practice for bending and fixing of bars for concrete

reinforcement.

IS: 2629 Recommended practice for hot-dip galvanising of iron &

steel

IS: 4759 Hot-dip zinc coating of structural steel and other allied

products.

IS: 2751 Code of practice for welding of mild steel plain and

deformed bars for reinforced concrete construction.

IS: 9417 Recommendations for welding cold-worked steel bars for

reinforced concrete construction.

IS: 800 Code of practice for General Construction in Steel.

Technical Specification Page 24 of 94 July 2007

Page 28: Technical Specification

MMOPL Tender TW Series 1000

6.2.4 European Standards (EN)

EN 1561 Founding – Grey Cast Iron

EN 1562 Founding – Malleable Cast Irons

EN 1563 Founding – Spheroidal Graphite Cast Irons

prEN 13230-1 Concrete sleepers and bearers – Part 1

General requirements

prEN 13230-2 Concrete sleepers and bearers – Part 2

Prestressed monoblock sleepers

prEN 13230-3 Concrete sleepers and bearers – Part 3

Prestressed bearers for switches and crossings

6.2.5 German Standard (DIN)

DIN 53455 Testing of Plastics – Tensile Test

DIN 53479 Testing of Plastics and Elastomers – Determination of Density

DIN 53508 Testing of rubber - Accelerated ageing

6.2.6 Indian Railway Standards

IRS T-1 Fish plate

IRS T-10 Switches, crossing and REJs

IRS T-12 Rails

IRS T-19 Fusion welding of rails by Alumino-Thermic process

IRS T-23 Fish bolts and nuts

IRS T-28 High Tensile steel fish bolts and nuts

IRS T-29 CMS crossings

IRS T-31 ERC

IRS T-37 GR sole plate (for 6 mm sole plate pad and any other relevant specification)

IRS T-39 PSC sleepers for plain track

IRS T-44 GFN-66 liners

Technical Specification Page 25 of 94 July 2007

Page 29: Technical Specification

MMOPL Tender TW Series 1000

IRS T-45 PSC sleeper for turnouts

IRS T-46 SGCI inserts

Indian Railway Manual for Alumino-Thermic Welding 1998

Indian Railway Manual for flash butt Welding 1996

Indian Railway Manual for Ultra Sonic Testing of Rails and Welds 1998

Indian Railway Manual of instructions on Long welded rails 1996

Indian Railway Manual for Glued Insulated Joint 1998

The technical specifications and manuals etc. of Indian Railways which are mentioned in

clause 6.2.6, shall be used only as far as they are applicable to a Standard Gauge

system. The Contractor shall be responsible for collecting the latest revision of all relevant

technical specifications to be used, including any correction slips and alterations, from the

issuing body at his own cost and shall submit them to the Employer’s Representative for

his approval before starting of work.

Technical Specification Page 26 of 94 July 2007

Page 30: Technical Specification

7. MATERIALS AND COMPONENTS

7.1 Material to be supplied by the Employer or Contractor

7.1.1. The 1080 grade HH running rails, turnouts, cross-overs & scissors cross-overs

complete with their fittings, UIC 33 restraining rails and rail fastenings for the

ballastless, tracks may be procured by the Employer for installation by the

Contractor.

7.1.2. Materials supplied by the Employer or the Contractor above shall be imported CIF

Mumbai port, and in this case, the Contractor shall be responsible for all the

remaining activities on arrival of these materials at Mumbai port such as taking

delivery of these materials including coordination with the customs authorities,

shipping lines, port authorities etc. The Contractor shall also be responsible for

their safe transportation from Mumbai port to Site without causing any damage to

them taking proper care & precaution & following appropriate methods including

loading, unloading, local transport and temporary storage at Mumbai (if required),

handling/rehandling, coordination with port and transport authorities, obtaining

necessary transport permits, transit insurance and proper stacking/storage with

proper accountal etc. as directed by Employer’s Representative.

7.1.3. For the materials imported by the Employer or the Contractor Mumbai Port, the

Contractor shall assess the damage to the materials, if any, and advise the

Employer’s Representative about the same immediately. The material, which in

the opinion of the Employer is damaged, shall not be transported to site, instead

shall be kept in Contractor custody in the Contractor temporary storage area in

Mumbai for a period not exceeding 28 days. Any damage to the materials which

have been transported by the Contractor to site shall be on Contractor account to

rectify.

7.1.4. The material, which in the opinion of the Employer is damaged, shall be jointly

inspected by the Employer’s Representative and the Contractor at the Contractor

storage area in Mumbai (The Contractor shall arrange required tools /equipment,

labour etc. for such joint inspections) and the acceptance /rejection of such

materials shall be as finally decided by the Employer’s Representative. The

rejected material shall remain in the safe custody of the Contractor at Mumbai till

its final disposal by the Employer’s Representative within 28 days.

7.1.5. Similarly the 880 grade rails may be procured by the Employer for installation by

the Contractor.

7.1.6. The 880 grade rails supplied by the Employer as described in 7.1.5 above or by

the Contractor shall be delivered to DN Nagar depot, and in this case the

Contractor shall be responsible for coordinating their unloading including

receiving, acknowledging the necessary vouchers without causing any delay and

proper accountal thereof etc. as directed by the Employer’s Representative. The

location/area for stacking of these materials shall have to be identified,

Technical Specification Page 27 of 94 July 2007

Page 31: Technical Specification

MMOPL Tender TW Series 1000

demarcated and got approved by the Contractor well in advance of actual arrival

of these materials so that no delay is caused on this account.

7.1.7. For the 880 grade rails supplied by the Employer or the Contractor, the joint

inspection for all the materials, equipments, goods etc, supplied by either the

Employer or the Contractor under the contract, the provision of handling, inland

transportation, damage checking etc shall be the same as mentioned above in

clause 7.1 shall be done on arrival of these materials at Site.

7.2 RAILS

7.2.1 Rail Sections

7.2.1.1 The rail section shall be;

Item Rail type Rail profile

(i) Running rails in tangent

track and curves with

radius> 400m.

(ii) Running Rails in curves on

main line and depot lines

with R <= 400m

(iii) All REJs, and glued

insulated joints on main

lines and depot lines

UIC 60, 880 grade

UIC 60, 1080 grade,

Head Hardened

UIC 861-3

UIC 861-3

All turnouts and abutting rail

within 26m of turnouts

Head hardened UIC 60,

1080 grade running

rails and switch rails :

Standard grade check

rails

UIC 861-3

Zu60 switch rails

U33 check rails

Check rails on mainline curves

with R < 190m and which carry

passenger traffic and depot

curves with sufficient length.

UIC 33 grade 880 U33 check rails

7.2.1.2 The Contractor shall take necessary approval/permission from concerned

authority for transportation of rails in Mumbai by Road.

7.2.1.3 The Contractor shall be responsible for preparing the firm and level ground for

stacking of Rails as approved by the Employer’s Representative. The Contractor

shall also arrange the required wooden battens/spacers for keeping rails in

layers as directed by the Employer’s Representative.

Technical Specification Page 28 of 94 July 2007

Page 32: Technical Specification

MMOPL Tender TW Series 1000

7.3 TRACK COMPONENTS

7.3.1 Rail Fastening System for Ballasted Track

All ballasted plain line track laid on PSC sleepers shall be installed with a

proprietary fastening system, which shall have a satisfactory proven service

record of not less than 5 years in conditions similar to those found on the

Project.

7.3.2 Ballastless Track Structure

7.3.2.1 All plain line ballastless track for the main lines and the tracks on the depot

approach ramp viaducts shall be installed on cast in-situ reinforced concrete

plinths, the design for which shall be provided by the Employer, using a

proprietary fastening system, which shall have a satisfactory service proven

record of not less than 5 years in conditions similar to those found on the Project

and which complies with all relevant requirements of EN13481.

7.3.2.2 The fastening system shall facilitate track adjustments of +/- 10mm

horizontally and up to +10mm vertically, with a minimum requirement of extra

components and time to adjust.

7.3.2.3 The fastening system shall be designed to minimise noise and vibration whilst

maintaining track gauge and stability both on tangents and on curves down to

100m radius.

7.3.2.4 The fastening system shall provide support to the rails sufficient to resist the

anticipated lateral and overturning forces on straight track and on curves down

to the minimum radius of 100m. The toe load applied to the rails by the fastening

system shall provide restraint to the rails, sufficient to limit potential pull-apart

gaps to less than 50mm and to resist the anticipated longitudinal braking and

traction forces on the steepest gradients whilst allowing the continuously welded

rails to distribute thermal forces across the viaduct expansion joints without the

need for rail expansion joints and without the build up of excessive rail stresses.

7.3.2.5 No components of the fastening system shall be susceptible to excessive

deterioration due to the climatic or environmental conditions prevailing in

Mumbai and the fastening system shall remain in serviceable condition for a

stated and warranted period as offered by the supplier.

7.3.3 Standard Fishplates and Fish bolts

Standard fishplates and fish bolts shall be suitable for use with UIC60 rail

section and shall be of four bolt type and shall be manufactured in accordance

with the relevant technical specifications of Indian Railway as mentioned in

clause 6.2.6.

Technical Specification Page 29 of 94 July 2007

Page 33: Technical Specification

MMOPL Tender TW Series 1000

7.3.4 Glued Insulated Rail Joints

The Glued Insulated Rail Joints (GIRJ) shall be manufactured by using UIC 60

grade 1080 HH rail G-3 (L) type in accordance with the RDSO Drawing no. T -

5843 and relevant Technical Specifications/manuals of Indian Railways as

mentioned in clause 6.2.6 for the Supply of Glued Insulated Rail Joints.

7.3.5 Ballast

7.3.5.1 Basic Quality: The 50mm nominal size ballast shall be hard durable and as

far as possible angular along edges/corners, free from weathered portions of

parent rock, organic impurities and inorganic residues.

7.3.5.2 Particle Shape: Ballast shall be cubical in shape as far as possible individual

pieces shall not be flaky and shall have generally flat faces with not more than

two rounded /sub rounded faces.

7.3.5.3 Mode of Manufacture: The Ballast shall be machine crushed.

7.3.5.4 Physical Properties:

Ballast sample shall satisfy the following physical properties when tested in

accordance with IS: 2386 Pt IV-1963

- Aggregate Abrasion Value: 30% Max.

- Aggregate Impact Value: 20% Max.

7.3.5.5 Size and Gradation:

7.3.5.5.1 Contractor shall ensure that Ballast is well graded between 65mm & 20mm size.

The Contractor shall further ensure the following size & gradation of ballast:a) Retained on 65mm Sq. mesh sieve 5% Maximum

b) Retained on 40mm Sq. mesh sieve 40 - 60%

c) Retained on 20mm Sq. mesh sieve Not less than 98%

7.3.5.5.2 Before commencing the supply of ballast the Contractor shall get the source /

quarry approved by the Employer’s Representative duly submitting the samples

and impact & abrasion test result values (to be conducted in a mutually agreed

independent lab/institution of repute) along with the proposed gradation of the

ballast to demonstrate compliance with specifications.

Once the source / quarry is approved by the Employer’s Representative the

Contractor shall ensure that the supply is taken from the same source /

quarry to ensure that the supply conforms to the same standards /

specifications as initially approved by the Employer’s Representative. Any

change of source/quarry shall be subject to approval by the Employer’s

Representative following the same procedure as mentioned above.

Technical Specification Page 30 of 94 July 2007

Page 34: Technical Specification

MMOPL Tender TW Series 1000

The Contractor shall set up his own quality assurance procedures to ensure

the compliance to the stipulated specifications.

To ensure /demonstrate that the supply of ballast achieve the requisite

standards the test results for gradation, impact and abrasion values shall be

submitted to the Employer’s Representative for every 2000 m3 of ballast

supply.

Such of those tests for which Employer’s Representative has opined to

witness, shall be carried out only in the presence of Employer’s

Representative. However, Employer’s Representative may at his discretion

conduct test checks to be organized by the Contractor for validation of test

results. The cost of such tests shall be borne by the Contractor.

The quantity of ballast for payment shall be calculated based on cross

section taken after installation of track. For this purpose the ballast

cushion/ballast depth (average of values of ballast cushion/ballast depth at

both rail seats) below the sleeper shall be recorded @ 20 m interval. The

ballast profile shall also be recorded at these locations, to work out the

volume of ballast duly making deduction for volume of sleepers embedded

in ballast. For calculating the quantity of ballast in turnout portion, the cross

section shall be plotted at three locations i.e. at SRJ, behind crossing and in

the middle. For ballast cushion between 200 – 250mm under rail seat, the

payment shall be made on the actual quantity as worked out above. The

shoulder profile shall strictly be maintained as shown on the relevant

drawings. Except as may be ordered by the Employer’s Representative in

written instructions, ballast dumped in excess of stipulated shoulder profile

and ballast cushion in excess of 250 mm shall not be paid. For canted

track on curves, actual ballast profile shall be plotted duly measuring

individual ballast cushion at both rail seats.

Technical Specification Page 31 of 94 July 2007

Page 35: Technical Specification

MMOPL Tender TW Series 1000

7.3.6 PSC SLEEPERS / BEARERS

7.3.6.1 The Contractor shall be responsible to design and supply mono block PSC

sleepers for the standard gauge ballasted plain line tracks with 1:20 rail

inclination to be compatible with the fastening system supplied.

7.3.6.2 The Contractor shall be responsible to design and supply PSC bearers for the

ballasted turnouts and crossovers compatible with the approved fastening

details and arrangements of the turnout manufacture. Turnout bearers shall be

arranged in a fan layout and to the greatest extent possible, the fastenings shall

incorporate similar components to those provided for the plain line.

7.3.6.3 PSC sleepers or PSC bearers for turnouts and crossovers shall be in

accordance with the relevant Technical Specification for manufacturing and

supply of turnout PSC sleepers as mentioned in clause 6.2.4

7.3.6.4 Sleepers shall be stacked/stored duly separated by hardwood dunnage placed

on each rail seat in such a manner as to avoid damage to the sleeper or its

fittings.

7.3.6.5 The Contractor shall ensure his proposed handling and transportation

methods do not cause any damage to the sleepers and /or its fittings. The

damaged sleepers as decided by Employer’s Representative may be

appropriately repaired by the Contractor, but no repaired sleepers shall be

incorporated in the works without the Employer’s Representative’s approval.

Any repaired sleepers which are rejected by the Employer’s Representative

shall be indelibly marked as rejects and shall not be incorporated in the works,

but shall be removed from the site forthwith.

7.3.7 Approved Manufacturers

The Contractor shall submit to the Employer’s Representative for each item or

component to be manufactured, the proven service record of the components

and full details of the previous relevant experience of the proposed

manufacturer in the production of that item, and also previous experience of

manufacturing similar products for the Railway industry as well as for MRTS

Projects. The major items that require particular and specific previous

manufacturing expertise and require prior approval of the Employer’s

Representative are as follows:

(a) Friction buffer stops;

(b) Wheel stops;

(c) Concrete sleepers for plain line and turnouts;

(d) Track fastening system components;

Technical Specification Page 32 of 94 July 2007

Page 36: Technical Specification

MMOPL Tender TW Series 1000

(e) Turnouts and crossovers, in general and in particular any previous

manufacture of turnouts and crossovers of the type specified.

7.4 TURNOUTS, CROSS-OVERS AND DIAMONDS

7.4.1 General

7.4.1.1 On the main line, the following types of turnouts and diamond crossing shall

be provided, and installed on reinforced concrete track slabs, as indicated in the

relevant drawings attached herewith in Volume IV.

a) UIC60-100-1:6 turnouts individual

b) UIC60-190-1:7 turnouts in crossover layouts

c) UIC60-190-1:9 turnouts in crossover and scissors layouts

d) UIC60-1:4.444 diamond crossings in scissors layouts

7.4.1.2 On DN Nagar Depot lines, the following types of turnouts and diamonds shall

be provided, with two turnouts installed on track slabs and the rest on ballast, as

indicated in the relevant drawing.

a) UIC60-100-1:6 turnouts in individual, crossover and fan layouts

b) UIC60-1:2.9167 diamond crossing in scissors layout

7.4.1.3 All ballasted turnout layouts, and the scissors x-over shall be provided on

PSC sleepers/bearers.

7.4.1.4 The Contractor shall be responsible to make provisions on PSC sleepers /

reinforced concrete slab for fixation of point driving machines, and any other

arrangements required for fixation of S & T equipment duly interfacing with the

Designated Signalling Contractor with prior approval of Employer’s

Representative.

7.4.1.5 Turnouts on main lines and depot lines shall be designed to take the CWR

through turnouts.

7.4.1.6 All turnouts and diamond crossings on main lines and depot lines shall be

designed and installed with canted rails with an inward slope of 1 in 20. The

detailed design drawings shall be supplied to the Employer’s Representative for

approval.

7.5 RAIL EXPANSION JOINTS

REJs for a maximum movement of 120 mm may be required on the viaducts

subject to the requirement of the civil works design. Such REJs shall be

Technical Specification Page 33 of 94 July 2007

Page 37: Technical Specification

MMOPL Tender TW Series 1000

designed as per drawing No. RDSO – T - 2653 and installed by the Contractor

on the non-ballasted mainlines at locations and to details approved by the

Employer’s Representative.

7.6 BUFFER STOPS

Track ends in the Workshop and inspection bay shall be fitted with wheel stops

capable of stopping a 6-car empty train travelling at 5km/h without damage to

the wheel stop. The wheel stops shall be designed such that they are

compatible with the wheel diameter of the vehicle to avoid or minimise damage

to the vehicle. All other track ends in the depot shall be protected by massive

concrete fixed buffer stops as shown on the Employer’s Representatives

drawings. All track ends on viaducts shall be provided with friction sliding buffer

stops with impact absorption material (non-hydraulic type) on the face. Sliding

buffer stops shall incorporate features to prevent the train from overriding and to

facilitate resetting after impact. The design and specification of wheelstops and

friction buffers shall be submitted by the Contractor for Employer’s

Representative’s approval. The Contractor shall interface with the Designated

Rolling Stock Contractor for the details required for the design of friction buffer

stops (confirmation of train mass and coupler data). However the following

provisional details shall be followed, until confirmed by interfacing with the

Rolling Stock supplier.

252 tonnes shall be allowed for the mass of an empty 6-car train (W0

loading)

408 tonnes shall be allowed for the mass of a fully loaded 6-car train (W4

loading).

The stopping performance required for empty trains on the viaduct

(Depot/Mainline Transfer Track) shall be;

stop from 15 km/h in 15m without damage to the train or buffer

stop from 25 km/h in 15m regardless of damage to the train or buffer

The stopping performance required for fully loaded trains on the viaduct

(at the Versova and Ghatkopar ends of the mainline) shall be;

stop from 10 km/h in 15m without damage to the train or buffer

stop from 25 km/h in 15m regardless of damage to the train or buffer

7.7 Level Crossings

The Contractor shall be responsible to provide the road level crossings in the

depot as embedded tracks with associated under-track transition slabs at the

locations and to the details as given in the Employer’s Representative’s

drawings MMO/EPMC/P/D/TW/D1210, MMO/EPMC/P/D/TW/D1170 and

Technical Specification Page 34 of 94 July 2007

Page 38: Technical Specification

MMOPL Tender TW Series 1000

MMO/EPMC/P/D/TW/D1170. The Pedestrian level crossings of 1.2m width shall

also be provided by the Contractor at the locations given in the drawings and to

details which shall be designed by the Contractor and submitted to the

Employer’s Representative for approval.

7.8 Concrete Plinth/Slab Trackform (Ballastless Track)

7.8.1 General

On viaduct structures plain line tracks shall be supported by reinforced concrete

plinths with integral derailment walls constructed on the outside of the running

rails clear of the track fastenings and to the same height as the top of the rails.

The plinths shall be discontinuous, no more than 5m long, with gaps of

100~200mm to permit drainage and cabling and to limit structural interaction

with the viaduct decks. On the inside of curves as specified, the plinths will be

widened as necessary to accommodate the fixings for U33 profile check rails.

The check rail supports shall be located between the running rail fasteners, and

shall be installed after final alignment adjustment of the running rails on grouted

pads.

Turnouts and crossover layouts on the viaducts will be resiliently mounted on

reinforced concrete track slabs, which themselves shall be constructed on a

resilient elastomeric isolation layer to reduce noise and vibration. The slabs will

be discontinuous, approximately 8m long and shall be kept in alignment by

internal reinforced concrete key slabs, approximately 1mx1mx0.15m high. The

key slabs will be isolated from the track slab by a resilient elastomeric layer on

top and elastomeric bearing layers on all sides. The key slabs will be

monolithically connected to the viaduct by the shear reinforcements provided by

Civil Contractor. The Contractor shall interface with the Designated Contractors

for the mounting of systems equipment and the provision of cable ducts on and

within the track slabs. The Contractor shall interface with the designated Civil

works Contractor for the shear connectors and for the track slab drainage

arrangements.

7.8.2 Concrete

The concrete for plinths and slabs shall be of M45 grade as per the Indian

Standard IS-456 – 2000, for PRC track sleeper M55 and for PRC turnout

sleeper M60

Technical Specification Page 35 of 94 July 2007

Page 39: Technical Specification

MMOPL Tender TW Series 1000

7.8.3 Reinforcement

7.8.3.1 Reinforcement shall be of Fe: 500 as per IS1786 in accordance with relevant

IS Codes.

7.8.3.2 Electrical Interface:

The plinth / RCC slab electrical continuity shall be ensured by the Contractor.

The Contractor shall supply and weld a connecting galvanised M.S. flat to the

plinth / RCC slab reinforcement. This galvanised M.S. flat shall be 160x40x8 mm

and bent to L-shape, pre-drilled with a 6-mm diameter hole, and shall be

installed at each plinth / RCC slab unit extremity. The galvanised M.S. flats shall

be connected by the Contractor using steel cable of adequate size to provide

electrical continuity between consecutive plinths / RCC slab duly interfacing with

the designated Power Supply & Traction (PST) Contractor.

7.8.4 Noise and Vibration Mitigation

The track fastening system shall be selected to have a high capacity to mitigate

the emission of noise and vibration from the wheel / rail interface to a level that

will not cause undue complaint and annoyance. In particular sections of the

alignment the emission of noise and vibration will be further reduced by the

construction of the plinthed tracks on a vibration isolation layer of microcellular

polyurethane elastomeric material. The Exterior Noise Levels should not be

more than those specified as under:

Location (Section)Exterior Noise Measurements

Stationary dB(A) Running dB(A)

Viaduct with maximum operating speed on a curve portion.

70 80

Where:

i) Noise level measurement to be done at a location 3.5m horizontally from the track centreline on a horizontal plane passing through the axle centrelines at any point along the length of the vehicle on either side.

ii) For running conditions the specified limits shall be met for the entire speed range up to 80 km/h with all equipment operating simultaneously. Noise level measurement to be done at a location 20-25m horizontally from the track centreline on a horizontal plane passing through the axle centrelines.

7.9 ALUMINO-THERMIC WELDING PORTION

The welding portion and equipment required for the Alumino-Thermic rail welding

process shall be manufactured and tested in accordance with relevant Technical

Specifications for approval of the process and supply of portions for Fusion

Technical Specification Page 36 of 94 July 2007

Page 40: Technical Specification

MMOPL Tender TW Series 1000

welding of rails and performance and acceptance of Alumino-Thermic welding of

rails of Indian Railways as mentioned in clause 6.2.6.

7.10 SIGNAL AND TRACTION RETURN RAIL BONDS

At locations provided by PST and signalling contractors, Trackwork and/or

traction return rail bonds are to be attached to the rail through thermo welding or

any other suitable technique by the Designated Contractors as approved by

Employer’s Representative. However, during installation process in depot, the

Contractor shall drill 18 mm diametre holes in rails of depot track for temporary

bonding of return current, wherever required. The temporary bonds with

required lugs and flats etc. shall be connected by the Designated Contractor.

Technical Specification Page 37 of 94 July 2007

Page 41: Technical Specification

8. SURVEY AND SETTING OUT

The setting out of alignment for track construction shall be the responsibility of

the Contractor. The following principles shall be adopted for setting out and

execution.

8.1 FUNCTIONAL RESPONSIBILITIES

8.1.1 The planning organisation and process of surveys for transferring the alignment

for track construction shall be the sole responsibility of the Contractor. He shall

at all times maintain common survey interface with the Civil Contractors.

8.1.2 Survey and setting out of works shall be carried out by surveyors of appropriate

experience and qualification as approved by the Employer’s Representative.

8.1.3 The Employer’s Representative may carry out random checks to verify the

accuracy of the setting out and Contractor compliance of the completed works

with given alignment and the specifications. Provisions and arrangement shall

be made by the Contractor to facilitate the checks. However, full responsibility

lies with the Contractor for the accuracy of line and level of the tracks.

8.2 SURVEY CONTROLS IN GENERAL

The Contractor shall interface with designated Civil Contractors to take over the

reference co-ordinates system (x,y,z) of the project area as defined by the

MRTS project. The Secondary Survey Control Markers are additional points to

be established by the Contractor along alignment or in the depot from the

reference coordinate system including bench mark thus providing survey control

for the work areas. The Contractor may also establish additional survey control

Markers as local grids or reference system for setting out particular sub-set of

work.

8.3 SECONDARY SURVEY CONTROLS

8.3.1 As each section of track or depot becomes available the Contractor shall submit

a schedule of secondary Control Markers and Bench marks for that area duly

interfacing with the Designated Contractors. The Survey Control Markers and

Bench Marks shall be used for the control of the Works. The Contractor shall

verify the relative accuracy of the Survey Control Markers and Benchmarks prior

to use.

8.3.2 All the Survey control markers and Benchmarks provided within the project area

by the designated Civil Contractors shall be surveyed, with survey computations

based on the adopted co-ordinates system. Any changes in values shall be

supported by technical evidence and on consultation with all affected parties.

8.3.3 In particular, any changes in co-ordinate values of Secondary Survey Markers

shall only be adopted with the concurrence of the Employer’s Representative.

Technical Specification Page 38 of 94 July 2007

Page 42: Technical Specification

MMOPL Tender TW Series 1000

The Contractor shall be responsible to prepare modified drawings/proposals in

this regard for information to all concerned parties and for approval of the

Employer’s Representative.

8.3.4 It shall be the Contractor’s responsibility to protect and preserve the integrity of

all the Control Markers during the period of construction of the trackworks. In the

event that any of the Secondary Control Markers or Benchmarks is damaged,

the Contractor shall replace and re-establish the points at his own cost to the

satisfaction of the Employer’s Representative.

8.4 SETTING OUT

8.4.1 Setting out points shall be established by transfer from the survey control

Markers. The Contractor shall establish physically on site such track siting

marks that may be grid or offset points to be used as the reference system for

the track work. In the event the original structural grid line are destroyed or

rendered unusable, the Contractor shall re-establish them at his own cost

without delay.

8.4.2 At each site, the position of the site main reference setting out points shall be

maintained throughout construction period. Such markers shall be checked

against the Survey Control markers by the Contractor at regular intervals to

ensure reliability of subsequent works.

8.4.3 The track siting marks corresponding to both the theoretical centre of the track

and to the theoretical level of the track running surface, as defined by the

relevant topographical data on the documents relating to track layout shall be

marked at the beginning and end of each circular curve, transition curve and

vertical curve both in the longitudinal and cross directions. The following track

siting marks shall be established:

- In straight sections: every 25-m,

- In curved sections: every 10-m.

The track siting marks for the centre of the tracks shall be shown by plates or

nails sealed on the viaducts and in the depot as approved by Employer’s

Representative. They shall be referenced by the Cartesian co-ordinates of each

point identified in this manner, and registered in the topographical logbook.

Should there be any discrepancy found by the Contractor with reference to the

geometry of civil structure, the same should be interfaced with the Civil

Contractor. The Contractor shall be responsible to prepare details duly making

necessary modifications in layout, if required as a solution to the discrepancy

and submit the same to the Employer’s Representative for his final decision.

The track siting marks for the vertical siting of the track running surface shall be

shown by angle plates sealed onto the viaduct sidewalls. They shall be

Technical Specification Page 39 of 94 July 2007

Page 43: Technical Specification

MMOPL Tender TW Series 1000

referenced with respect to the theoretical track level as approved by Employer’s

Representative.

Given that the precision of the spatial siting of track laid directly on concrete is of

the utmost importance, the Contractor shall position the above markings as

follows.

8.4.3.1 Levelling

The markings show the track altitude, shall be placed on the viaduct side walls,

at a constant height in relation to the theoretical level of the track running

surface. They shall be placed at every temporary support frame of track or 5 m,

whichever is less.

8.4.3.2 Layout

The markings show the centre line of each track, shall be fitted on the viaduct at

every temporary support frame of track or 5 m whichever is less in straight

sections, in circular curves and in transition curves.

8.4.4 The inner rail for curve and any rail for straight shall first be set out in its absolute

position from track siting marks using co-ordinates computed from the alignment

geometry, the elevation of the rail shall be checked using a level, the other rail

shall be set correctly relative to cross level and gauge from the first rail.

8.5 CONTROL OF TRACK WORKS

8.5.1 The Contractor shall ensure that critical dimensions for the Mumbai MRTS project

are met. Regular checking should be carried out during the construction stages

to ensure that the specified permissible deviations are not exceeded.

8.5.2 The Contractor shall ensure that all survey and track siting marks shall be

established on Site to required accuracy. He shall also be responsible for each

stage of the setting out work and for verifying compliance before construction

starts.

8.5.3 The Contractor shall develop a detailed Surveyed Track Analysis spread sheet

on Microsoft EXCEL. The detailed format of the Surveyed Track Analysis

spreadsheet shall be submitted to the Employer’s Representative for

Acceptance at least one month prior to the commencement of track laying.

8.5.4 The surveyed Track Analysis spread sheet shall tabulate against chainage, the

vertical difference (high or low) and horizontal difference (left or right) between

the actual surveyed track centre line position and the design alignment

computed from latest accepted alignment geometry. Derived cant, gauge and

twist values shall also be compared against design values on the same

spreadsheet.

8.5.5 Any out of tolerance condition shall be flagged up on the spreadsheet.

Technical Specification Page 40 of 94 July 2007

Page 44: Technical Specification

MMOPL Tender TW Series 1000

8.6 SURVEY INSTRUMENTS

8.6.1 Survey instruments used and the methodology adopted shall be appropriate to

the intended measurement task and accuracy specifications. Test

measurements and instrument calibration shall be carried under local field

conditions.

8.6.2 It is essential that before starting any initial surveys, and at frequent intervals of

not more than three months, all measuring equipment should be tested for their

accuracy.

8.6.3 All instrument deployed in the Contract shall be in good condition and properly

calibrated. Calibration certificates and/or statements of services by local

authorised instrument agents of not more than six months shall be the proof that

the instruments are in good service conditions.

8.6.4 Notwithstanding the above, instruments shall again be checked to ensure good

condition before the Contractor proceeds to carry out a critical survey task.

8.6.5 Horizontal control traverses shall be carried out with modern precise digital

survey instruments consisting of co-axial total station with an accuracy not

inferior to 2” arc and (2+2ppmxD)mm. Precise levelling runs shall be carried out

in both directions using digital level with an accuracy not inferior to 1.5mm per

Km double run. Digital data from the above instrument shall be recorded

electronically in the field. For track surveys non co-axial total station shall not be

permitted. Total stations used for track surveys shall have onboard software

permitting setting out and checking of points along a calculated alignment in the

field. Survey instruments used by the Contractor shall meet such standards.

8.7 QUALITY PLAN

The Contractor shall submit to the Employer’s Representative, for acceptance a

separate quality plan related specifically to survey matters. The plan shall

address the following:

Identification of the Contractor key survey staff and the lines of

communication

Scope of the surveying section including interface with designated

Contractors

List of proposed surveying equipment & computer hard/software;

List of surveying procedures;

List of detailed method statements for all critical surveying activities;

Survey test and inspection plan;

Control of survey data and records;

Technical Specification Page 41 of 94 July 2007

Page 45: Technical Specification

MMOPL Tender TW Series 1000

9. INSTALLATION

9.1 INTRODUCTION

9.1.1 General

9.1.1.1 The proposed method statements, installation procedures and installation

plans for the Works shall be submitted for the Approval of the Employer’s

Representative in accordance with this Chapter 9. These submissions shall be

summarised and detailed in the Contractor Submission Schedule (CSS). The

documents forming the submissions shall use a standard format which shall be

submitted by the Contractor for the approval of the Employer’s Representative.

9.1.1.2 Notwithstanding the nominal track to viaduct dimensions indicated on the

Drawings, the as constructed dimensions may vary subject to the allowable

tolerances. In addition the viaducts may contain ramps, steps, channels, drains,

anchor bolts, and the like. The methods of construction shall accommodate

these constraints.

9.1.1.3 All temporary/service tracks, if required for track work on main lines and depot

lines, shall be arranged & laid by the Contractor only with prior approval of the

Employer’s Representative. The Contractor shall remove these

temporary/service tracks after completing the permanent track work as

approved by Employer’s Representative.

9.1.2 Track forms

9.1.2.1 The ballastless trackform on main lines shall be direct fixation on reinforced

concrete plinth for plain track and on RCC slab for all turnouts.

9.1.2.2 The ballastless track in depot areas shall be of the following types as shown

on the Drawings

a) Embedded rail,

b) Discretely supported on concrete pedestal,

c) Ballastless plinth type track form for washable apron (low height plinth

without derailment guards).

d) Pit tracks with discrete rail supports on each side of the pit.

9.1.2.3 Ballasted track shall be laid on monoblock pre-stressed concrete sleepers.

Technical Specification Page 42 of 94 July 2007

Page 46: Technical Specification

MMOPL Tender TW Series 1000

9.2 METHODS OF WORKING

9.2.1 Method statements

9.2.1.1 Method statements detailing the proposed methods of working and

incorporating all temporary works required shall be submitted to Employer’s

Representative for his approval. No Permanent Work shall commence until the

method statements are approved by the Employer’s Representative.

9.2.1.2 Method statements for track laying shall, as a minimum cover the following items, where ever applicable:

(a) handling & transport (including for materials to be supplied by

Employer’s Representative)

(b) stacking/storage/accountal / reconciliation of materials (including for

the materials to be supplied by the Employer)

(c) pre-assembly/assembly

(d) delivery

(e) surveying

(f) setting out

(g) welding, USFD testing of rails & welds, weld tests upto failure,

planning for appropriate length of rail panels

(h) track installation

(i) ballasting

(j) tamping

(k) lining & levelling

(l) concreting

(m) as-constructed records

(n) cleaning

(o) destressing

(p) cutting of rails, which may render generation of unusable small cut

pieces.

9.2.1.3 Method statements shall, as a minimum, incorporate hold points, tolerances,

finishes required, temporary works, false works, formworks, test and inspection

plans and shall include safety and quality control requirements for each activity.

9.2.1.4 Method statements are also required as a minimum for the following

production or installation activities:

(a) Each trackform

Technical Specification Page 43 of 94 July 2007

Page 47: Technical Specification

MMOPL Tender TW Series 1000

(b) Turnouts, crossovers, and scissors cross over

(c) Rail welding

(d) Buffer Stops

(e) Surveying

(f) Recording track parameters, unevenness etc.

(g) Tests on Completion

9.2.1.5 Method Statements shall be prepared and submitted in a standard format as

described in Clause 9.1.1 with descriptions under the following minimum

headings:

(a) Safety

(b) Plant, Equipment & Tools

(c) Construction Method

(d) Protection to existing drainage facilities, cast-in items, etc.

(e) Tolerances & finishes

(f) Hold Points

(g) Proforma/check sheets

(h) Falsework/Formwork

(i) Temporary Works

(j) Reference Drawings

(k) Reference Documents/Clauses

9.2.1.6 Method Statements shall be itemized and have Document/Clause reference

column at the right hand side margin.

9.2.1.7 Each method statement shall be referenced to the relevant clauses of the

documents forming the Contract.

9.2.1.8 Method statements which require the use of any specific/specialised

equipment or Constructional Plant shall clearly specify the equipment or

Constructional Plant and the operator’s experience required.

9.3 FINAL CONDITION OF TRACK

9.3.1 Throughout construction generally and immediately after installation of the track,

the rails, rail fastenings, the concrete track base, including ducts, track drains

and any exposed support structure shall be made clean. This cleaning shall

include the use of air/water pressure jetting and vacuum cleaners as necessary.

Technical Specification Page 44 of 94 July 2007

Page 48: Technical Specification

MMOPL Tender TW Series 1000

9.3.2 Once a section has been cleaned, tested and the required track parameters &

insulation values (as required by the relevant interfacing parties) have been

accepted by the Employer’s Representative, that section’s accepted level of

cleanliness and insulation shall be maintained until the taking over of the

section.

9.4 TRACK INSTALLATION

9.4.1 General

9.4.1.1 The track gauge throughout shall be 1435 mm on straights and 1435-0 mm +

gauge widening on curves measured between the running edge gauge point of

each rail and normal to the centre line of the track 14 mm below top of Rail.

9.4.1.2 All main line & depot line track including turnout, x-over and diamond xing

shall be laid with 1:20 inward rail slope.

9.4.1.3 The Contractor shall take due cognisance of his proposed rail jointing system

and the rail fastening assembly spacing in the selection of the appropriate length

of long welded rail panels.

9.4.1.4 The minimum closure rail length in plain line shall be 6 metre except for

specific locations as shown on the drawings or as Approved by the Employer’s

Representative.

9.4.1.5 No wastage allowance shall be permitted for the various materials supplied by

the Employer’s Representative except for the rails. The wastage allowance for

rails shall be permitted in accordance with the provisions of paragraph No. 9.4.2.

4 of Technical Specification.

Technical Specification Page 45 of 94 July 2007

Page 49: Technical Specification

MMOPL Tender TW Series 1000

9.4.2 Rail Jointing

9.4.2.1 All rail joints throughout the main lines & depot lines, including turnouts,

except at locations approved by the Employer’s Representative, shall be

welded.

9.4.2.2 The welding of nominal rail lengths into long welded rail panels for main lines

and depot lines shall be by mobile flash butt welding plant. Alumino-Thermic

welding shall only be used in exceptional circumstances with prior approval of

the Employer’s Representative. Temporary joints between HH rails shall be by

fish plates & clamps without drilling of holes in rails.

9.4.2.3 All the welded joint for welding less than 26m rail length on main line and

depot lines shall have prior approval of Employer’s Representative.

9.4.2.4 The Contractor shall obtain Employer’s Representative’s prior approval for any

rail cutting, which may render generation of unusable small cut pieces. These

cut pieces shall also be properly accounted, collected and stacked in DN Nagar

Depot at a place approved by the Employer’s Representative before its handing

over in acceptable condition.

9.4.3 Locations of Welds

The spacing of welds and joints shall not be less than 6.0 m between any two

welds and for any deviation to this, specific approval of Employer’s

Representative shall be required in each case. No welds shall be permitted

closer than 100 mm to a rail seat as measured between the centre of the weld

and the closest edge of any rail fastener. No welds shall be permitted in the

working length of the friction sliding buffer stops.

9.4.4 Long Welded Rails

Long welded rail panels (LWR) shall generally be as long as possible. Short

panels shall only be permitted when dictated by site conditions/site constraints

and as Approved by the Employer’s Representative.

Technical Specification Page 46 of 94 July 2007

Page 50: Technical Specification

MMOPL Tender TW Series 1000

9.4.5 Fishplated Rail Joints

9.4.5.1 Standard fishplated joints shall only be used in the depot tracks for locations

where welded joints cannot be made and only as approved by the Employer’s

Representative.

9.4.5.2 Standard fishplated joints shall be installed centrally between two adjacent

fastenings and shall be manufactured and installed to permit the use of standard

rail fastening assemblies.

9.4.5.3 All fishplated joints shall be fitted with the nuts with spring washer.

9.4.6 Glued Insulated Rail Joints

9.4.6.1 All glued insulated rail joints shall be shop manufactured using minimum 6 m

long rails. Site fabricated glued insulated joints shall be provided only with prior

approval of the Employer’s Representative,

9.4.6.2 Except in the case of glued insulated joints in the turnout zone, the positioning

of the glued insulated joint with respect to the approach track (adjoining track)

shall be such as to keep a minimum distance of 4.00 m from an existing weld in

the rail.

9.4.7 Rail Expansion Joints

9.4.7.1 Rail expansion joints shall be installed only at locations as instructed by the

Employer’s Representative.

9.4.7.2 Particular attention shall be given to ensure that rail expansion joints are

assembled and installed as per drawing No. RDSO – T – 2653.

9.4.7.3 Immediately prior to completion of a section, all sliding surfaces of rail

expansion joint shall be cleaned and greased.

9.4.8 Rail Temperature

Rail temperatures shall be measured using appropriate embedded type rail

thermometers. The minimum number of thermometers required to be used of a

segment of track shall be proposed by the Contractor for the prior approval of

Employer’s Representative.

Technical Specification Page 47 of 94 July 2007

Page 51: Technical Specification

MMOPL Tender TW Series 1000

9.4.9 Cutting of Rails

9.4.9.1 Rails shall only be cut by using disc type rail cutting machines. The proposed

method and equipment for the cutting of rails shall have the prior approval of the

Employer’s Representative.

9.4.9.2 Rails required to be cut shall be cold sawn square and vertical across the rail.

A deviation from square or vertical of more than 0.50 mm, measured about the

rail head, shall not be permitted. All burrs shall be removed from the rail ends.

9.4.9.3 Quality of cutting shall be such as to ensure tolerances in flash butt and

Alumino–Thermic welding manual.

9.4.10 Drilling of Rails

9.4.10.1 All fish bolt holes in rails, wherever required shall be drilled by using proper jigs

and drilling machines. The proposed method and equipment for the drilling of

rails shall have the prior approval of Employer’s Representative

9.4.10.2 All holes in the rails shall be chamfered using chamfering kit & procedure

approved by the Employer’s Representative.

9.4.11 Pre-Bending of UIC60 & U33 Rails

Pre bending of rails for installation in sharp curves is not mandatory. However if

considered necessary or desirable by the Contractor to facilitate the installation,

the pre-bending of rails shall only be done using methods and equipment as

proposed by the Contractor and approved by the Employer’s Representative.

9.5 BALLASTED TRACK INSTALLATION

9.5.1 General

9.5.1.1 The components of ballasted track shall include:

(a) Compacted Sub-ballast track support layer with 1:20 drainage cross

falls (to be done by civil work depot contractor)

(b) Bottom ballast and infill/shoulder ballast

(c) Sleepers and approved fastening system

(d) Rail

9.5.1.2 The completed track shall have the following minimum ballast cushion under the sleeper or bearer:

(a) Ballast cushion :

Technical Specification Page 48 of 94 July 2007

Page 52: Technical Specification

MMOPL Tender TW Series 1000

- Depot 200 mm minimum

(b) Ballast Shoulders profile shall be as shown in the contract Drawing

No.MMO/EPMC/P/D/TW/D1130.

9.5.1.3 Sleepers shall be spaced in ballasted depot track at the following centres:

(a)700 mm in straight tracks

(b)600 mm in curves ,

(c) Sleeper centres shall be measured along the track centre line for

straight track and along the high rail in curved track.

9.5.1.4 A “Request for Inspection” complete with all necessary information to allow

assessment, shall be submitted to the Employer’s Representative for the

following activities and Approval must have been received prior to commencing

any follow-on activity:

(a) Acceptance of supporting structure,

(b) Acceptance of bottom ballast

(c) Acceptance of the track and turnouts for the movement of plant,

machinery & equipment

(d) Acceptance of track/turnout for in situ welding

(e) Acceptance of track for tamping

(f) Acceptance of track for destressing

Technical Specification Page 49 of 94 July 2007

Page 53: Technical Specification

MMOPL Tender TW Series 1000

9.5.2 Bottom Ballast

9.5.2.1 The Contractor shall check the formation level with reference to required level

to achieve proper ballast cushion at rail seat below bottom of sleeper. Any

discrepancy in level of formation shall be brought to the notice of the Employer’s

Representative with details for final decision.

9.5.2.2 Bottom ballast shall be laid directly onto the prepared support structure using

methods that keep the amount of road traffic over the support structure to a

minimum

9.5.2.3 On completion of the bottom ballast a survey shall be undertaken to

demonstrate the acceptability of the bottom ballast for track laying.

9.5.2.4 The bottom ballast survey shall be undertaken on a longitudinal grid of 20

metres along the line of the ends of the sleepers and at the extremities of the

specified profile.

9.5.2.5 On completion and acceptance of the bottom ballast for track laying, no

vehicle of any type shall be permitted to run over the bottom ballast.

9.5.3 Ballasted track laying

9.5.3.1 General

The ballasted track laying system shall be as proposed by Contractor and

approved by Employer’s Representative. In addition to this the following

stipulations shall be followed by Contractor.

9.5.3.1.1 In situ flash butt welding shall not be undertaken until the track has sufficient

ballast to hold it to alignment both before and after welding.

9.5.3.1.2 The track laying system shall be such that no pneumatic tyred vehicles shall

travel over the bottom ballast during the track laying operation.

9.5.3.1.3 On entry/exit lines of depot connected to main line, ballasted curves sharper

than 400 m radius shall be provided with extra width of shoulder ballast, as per

Indian Railways Manual of instruction on Long Welded Rails -1996, on outside

of curve to increase the lateral track strength.

9.5.3.1.4 The sleepers shall be laid out on the bottom ballast at the specified spacing. The

sleepers shall be correctly aligned in accordance with the track alignment.

9.5.3.1.5 Once a suitable length of track has been laid and before any further rail

mounted Construction Plant or equipment is allowed to run on that track,

sleepers shall be levelled and packed by off-track tamper or by manual means

Technical Specification Page 50 of 94 July 2007

Page 54: Technical Specification

MMOPL Tender TW Series 1000

as approved by Employer’s Representative, to ensure that the final levels and

line of the track are within acceptable tolerances as approved by Employer’s

Representative. However the Employer’s Representative’s inspection &

approval shall not absolve the Contractor from the responsibility of safety of

track and track components damaged due to running of rail mounted

construction plant and equipment shall be replaced by the Contractor to the

Employer’s Representative’s satisfaction

9.5.3.2 Top ballasting, tamping & lining

9.5.3.2.1 Prior to the placing of top ballast the track shall be marked in preparation for tamping and lining operations with the following information:

All horizontal and vertical tangent points

Transition curve details

Circular curve details

Cant details

chainages

9.5.3.2.2 Once the top ballast is adequately regulated the track shall be lifted, levelled

and aligned as required.

9.5.3.2.3 The finished track with designed line and levels and with designed ballast profile

shall be destressed.

9.5.3.2.4 The Contractor shall deploy his own track tamper for the purpose of tamping of

track.

9.6 BALLASTLESS TRACK INSTALLATION

9.6.1 General

9.6.1.1 The components of ballastless system shall be:

a) support structure

b) shear connector

c) reinforced concrete plinth for plain track & RCC slab for turnouts

d) Fastening system as shown in relevant drawings.

9.6.1.2 A “Request for Inspection” shall be submitted to the Employer’s Representative,

complete with all necessary information to allow assessment, after the following

activities an Approval must be received prior to the commencement of any

follow-on activity:

a) Acceptance of support structure including specified surface treatment

and shear connectors,

Technical Specification Page 51 of 94 July 2007

Page 55: Technical Specification

MMOPL Tender TW Series 1000

b) Acceptance of the plinth reinforcement, slab reinforcement

c) Acceptance of the track for jigs, fixtures, supporting arrangement &

concreting,

d) Acceptance of the track for the movement of construction plant,

equipment and machinery,

e) Acceptance of the track for in situ welding,

f) Acceptance of the track for destressing.

Technical Specification Page 52 of 94 July 2007

Page 56: Technical Specification

MMOPL Tender TW Series 1000

9.6.2 Reinforced Concrete Plinth:

9.6.2.1 The surface of the viaduct deck shall be surveyed to achieve the minimum depth

(300 mm) of plinth / RCC slab below the rail seats. For such of those locations

where minimum depth of 300 mm is not achievable, the Contractor shall, with

complete details, seek Employer’s Representative’s decision.

9.6.2.2 The reinforced concrete plinth/RCC slab shall be connected with structural

support concrete of the viaduct deck through shear connectors as shown in

Drawing No.MMO/EPMC/P/D/TW/M1110.

9.6.2.3 The Contractor shall prepare and clean the surface of supporting structure for

laying of plinth/RCC slab by methods as approved by Employer’s

Representative.

9.6.2.4 The Ballastless track shall be constructed by top down method of construction.

The laying tolerances for the various track parameters required in accordance

with the clause 9.11.2 shall be strictly met. For achieving these tolerances, the

Contractor may propose an alternative method/scheme of construction of

ballastless track along with tender submissions, if he so desires for Employer’s

Representative’s consideration. However the sole responsibility of achieving the

stipulated track laying tolerances lies with the Contractor. The tenderer shall

submit the detailed construction methodology including the method of handling

and transport of material with the details of temporary works, equipment, plant

and machinery, with details of the locations where such method/Scheme has

been used for similar project/conditions to demonstrate its success. If the

alternative method/ scheme as proposed by the tenderer is accepted by

Employer’s Representative, the Contractor shall ensure that same scheme is

adopted for construction of ballastless track on the project. If the alternative

method/ scheme as proposed by Tenderer is not accepted by the Employer’s

Representative, the Contractor shall adopt the top down method for the

construction of ballastless track.

9.6.2.5 The Contractor shall be responsible to workout the actual height of plinth / RCC

slab at each location to maintain the designed rail level as shown in the relevant

drawings and submit the same along with all relevant details for the approval of

the Employer’s Representative. The reinforced concrete plinth/RCC slab shall

be laid on the viaduct duly making the required provision for cant & vertical

curve for all heights worked out above. The indicative values of cant adopted

for horizontal curves are given in the table attached with drawings. However the

exact values of cant for all the horizontal curves shall be obtained by the

Contractor through interface with the designated Rolling Stock Contractors and

shall be submitted for the approval of the Employer’s Representative before

construction.

9.6.2.6 The reinforced concrete plinth shall normally be laid in lengths of 5 m with

intervening gaps of 0.1~0.2 m both in straight alignments and curves

Technical Specification Page 53 of 94 July 2007

Page 57: Technical Specification

MMOPL Tender TW Series 1000

9.6.2.7 During the concreting phase, the track fasteners and the running rails shall be

protected by movable covers against possible splattering of concrete.

9.6.2.8 Each plinth/RCC slab unit shall be completed in one single operation. In the

exceptional cases integral derailment walls may be cast at a later stage, but

under no circumstances shall the pouring of the concrete to the required level

under the rail supports be interrupted.

9.6.2.9 The form work may be removed after 24 hrs of pouring of plinth concrete.

9.6.2.10 In case of top down method, the plinth/RCC slab construction shall be carried

out by using perforated dummy plates of appropriate thickness as approved by

the Employer’s Representative, which shall later be replaced by intermediate

pad and elastomeric pad after the concrete attains sufficient strength.

9.6.2.11 The concreted surfaces of the plinth / RCC slab below the base plates shall be

smooth, devoid of any inclusion, roughness crack, and without showing any

aggregate at the surface. Further the anchor bolts embedded in RCC shall be

firm without showing any sign of looseness.

9.6.2.12 The presence of smooth cavities caused by air bubbles in excess of the value

mentioned below shall not be permitted in case of top down construction

method.

- Total surface area of the cavities: 10,000 mm2 on base plate area

- Maximum dimensions of the inscribing rectangle of a cavity: 20x30 mm,

- Maximum defect depth 5 mm

9.6.3 Depot embedded rail

The rail in the embedded track of running lines shall be inclined to the same

degree as that of the adjoining track. The rail in the embedded tracks of the

workshop and in the wheel lathe building may be installed vertically. The rails

shall be lined, levelled temporarily secured in the slots left by the Depot

contractor and cast with a non-shrink grout by the Contractor as approved by

Employer’s Representative. The required flangeway gap shall be provided to the

running edges on the inside of the rails and on the outside of the rails the grout

shall be stopped 5mm below the top of rail.

Technical Specification Page 54 of 94 July 2007

Page 58: Technical Specification

MMOPL Tender TW Series 1000

9.6.4 Depot rail discretely supported on the concrete pedestal

9.6.4.1 The Pedestal Supporting structure constructed by the Depot Contractor shall be

surveyed and inspected by the Contractor and the Contractor should inform the

Employer’s Representative for acceptance before completion of the pedestal in

conjunction with the track laying. Any misalignment or deficiencies in the

supporting structure shall be referred to the Employer’s Representative for

decision. The rails shall be lined, levelled and fixed using special fastenings to

be manufactured locally as per the drawing provided by Employer’s

Representative. The M45 grade concrete shall be placed in the remaining depth

of 200mm of pedestal and rail seat to be epoxy grouted. No concrete shall be

placed to complete the pedestals until the final alignment has been approved by

the Employer’s Representative.

9.6.4.2 The components of the track form for the pedestals column shall be as shown in

the Drawing No.MMO/EPMC/P/D/TW/D1160.

9.6.5 Drainage

The Contractor shall be responsible for maintaining clear longitudinal & cross

drainage paths within ballastless plinth track to the main drainage system

provided by the designated Civil Contractors. The proposed track drainage

arrangement and design for crossover and scissors track slabs shall be proposed

by the Contractor for each location for the approval of the Employer’s

Representative. The Contractor shall suitably adapt and connect to the drains

provided by designated Civil Contractor.

Technical Specification Page 55 of 94 July 2007

Page 59: Technical Specification

MMOPL Tender TW Series 1000

9.7 TURNOUTS, CROSSOVERS, DIAMOND CROSSINGS, AND RAIL EXPANSION JOINTS (BALLASTED AND BALLASTLESS TRACK)

9.7.1 General

9.7.1.1 Turnouts on ballastless track shall be so set out that the line and level of both

straight and turnout track are within designed tolerances as approved by

Employer’s Representative

9.7.1.2 Check rails shall be set and checked to the correct clearance by using the

running edge of the crossing as the datum.

9.7.1.3 The assembly sequence of turnouts, diamond crossings and derailing switches

shall be submitted for Employer’s Representative’s Approval as part of the

overall method statement for preassembly, handling, storage, transportation,

unloading and installation.

9.7.1.4 On completion of a turnout, the Contractor shall immediately scotch the switches

with a purpose made hardwood timber scotch and securely clamp the switches

for the through route with an appropriate clamp to be arranged by the Contractor

and as approved by the Employer’s Representative. The clamp shall be capable

of being padlocked with the switch in the closed position.

9.7.1.5 No on-track Constructional Plant, equipment and machinery shall be allowed to

operate over a turnout until it has been inspected and approved by the

Employer’s Representative.

9.7.1.6 The Contractor shall interface & ensure the designed switch opening while

fixation of the first stretcher bar by designated signalling contractor.

9.7.1.7 All stretcher bars for switches except first stretcher bar shall be installed by the

Contractor duly interfacing with designated signalling contractor and approved

by the Employer’s Representative.

9.7.1.8 Switches shall be installed to provide adequate flange way clearance between

the stock rail and the switch rail with the switch rail in open position. The

minimum flange way clearance in switch portion shall not be less than 60 mm.

The Contractor shall provide arrangements for mounting of point operating

mechanism and shall co-ordinate and interface with designated signalling

contractor to ensure full compatibility with regards to installation requirements

and point operating mechanism. The opening of switch at toe of switch shall be

kept as 160 mm.

9.7.1.9 The Contractor shall provide all gauges and measuring equipment and labour

necessary to completely check the preassembled turnouts, crossovers, diamond

crossings and rail expansion joints

9.7.2 Installation (Ballasted)

The turnouts, crossovers, diamond crossings and derailing switches shall be laid

on bottom ballast prepared as described in clause 9.5.2 - Bottom Ballast. They

shall be installed in accordance with the Approved method statement

Technical Specification Page 56 of 94 July 2007

Page 60: Technical Specification

MMOPL Tender TW Series 1000

9.7.3 Installation (Ballastless)

Installation of ballastless turnouts, crossovers, and diamond crossings on RCC

slab as shown in Drawing No. MMO/EPMC/P/D/TW/M1130 shall be done

observing the provision of clause 9.6.2.

The turnouts, x-overs and diamond x-ing shall be installed without dummy plates,

instead galvanised steel plates of appropriate thickness and dimensions shall be

supplied & provided below the intermediate pad on all base plates by the

Contractor at the time of assembling these for installation. Concreting shall be

done up to 25 mm below bottom of these plates and the gap shall be grouted

with an appropriate epoxy grout material as approved by the Employer’s

Representative.

9.8 DESTRESSING OF CWR

9.8.1 General

9.8.1.1 The destressing of rails shall not be undertaken until it has been demonstrated

to the Employer’s Representative’s satisfaction that the track has been

completed to the specified standard & specification and the method of working

for destressing of the relevant trackform has been approved by the Employer’s

Representative.

9.8.1.2 The final welding of joints within turnouts shall be undertaken as per sequence

as approved by Employer’s Representative and within the stress free

temperature range.

9.8.1.3 The elementary long welded rail shall be laid on rollers placed on the metal base

plates or sleeper rail table, with the rollers at maximum 6.00-m intervals and

appropriate side rollers in curves. The rollers shall have suitable diameter to

avoid contact between rail and intermediate sleepers/metal base plates.

9.8.1.4 After placing the long welded rail on rollers, it shall be stress relieved by hitting

the rail on each side of the head with wooden mallets as approved by

Employer’s Representative.

9.8.1.5 For destressing of CWR, guidance may be taken from LWR manual of Indian

Railways.

9.8.1.6 The rails for continuously welded track shall be destressed in accordance with

temperature conditions as per Clause 3.2.4.

9.8.2 Buffer stops

9.8.2.1 The installation details for friction buffers stops shall be submitted by Contractor

as per manufacturer’s guideline for Employer’s Representative’s approval.

9.8.2.2 Friction buffer stops shall not be installed until the track is at the design line and

level, as approved. The following requirements shall be complied with:

There shall be no Thermit weld within the rail length of the buffer stop or the rail

Technical Specification Page 57 of 94 July 2007

Page 61: Technical Specification

MMOPL Tender TW Series 1000

sliding length of the buffer. Any weld that fall within the friction buffer stop rail

sliding length shall be ground to produce a smooth and uniform standard rail

cross section to ensure that the performance of the buffer stop is unaffected.

Friction buffer stops shall be assembled and installed with the friction elements

properly spaced and the bolts torqued strictly in accordance with the

manufactures instructions.

9.9 RAIL WELDING

9.9.1 General

9.9.1.1 All main lines and depot lines shall be USFD tested and welded into a LWR by

flash butt welding process except at location as approved by the Employer’s

Representative. Alumino-Thermic welding shall only be permitted in exceptional

circumstances when dictated by site conditions/ constraints and as approved by

the Employer’s Representative. Only RDSO approved welders and approved &

renowned welding firms shall be detailed to do welding.

9.9.1.2 The welding process shall be suitable for UIC60, 880 grade & 1080 grade HH

rails.

9.9.1.3 Weld records of all welds shall be submitted at intervals not exceeding 1 km of

rail welded into long lengths The proforma for the weld records plan shall be

submitted by Contractor for Employer’s Representative’s approval. This record

shall contain, as a minimum, the following information:

(a) Weld chainage to the nearest metre,

(b) Weld number,

(c) Rail grade and section,

(d) Date welded,

(e) Weld test record sheet reference (if different to the weld

number),

(f) USFD test results

(g) Dimensional check results

(h) Rail weld paint

(i) Name (code) of welder

Technical Specification Page 58 of 94 July 2007

Page 62: Technical Specification

MMOPL Tender TW Series 1000

9.9.1.4 Arrangements shall be made to have test welds and their testing for proving of

the flash butt welding technique, the Alumino-Thermic weld process and

competence of welders deployed for welding work.

9.9.1.5 The welds shall be finished to final profile by controlled profile grinding as

approved by Employer’s Representative. The finished weld alignment shall be

as per specified tolerances. Rail head profile grinding to produce the finished

alignment shall not extend more than 300mm either side of the weld.

9.9.1.6 All welds shall be marked and painted as per the provisions of the relevant

welding manuals as mentioned in clause 6.2.6.

9.9.2 Flash-butt welding

9.9.2.1 General

9.9.2.1.1 The Flash Butt Welding of rail joints shall be undertaken in accordance with the

relevant Indian Railways Manual for Flash Butt Welding of rail as mentioned in

clause 6.2.6 and as supplemented in this section.

9.9.2.1.2 For 1080 grade HH rails, the minimum breaking load and minimum deflection

as mentioned in the relevant clause of Indian Railway manual for flash butt

weld shall be such that the weld shall not show any sign of cracking up to the

specified rail deflection and the load at this deflection shall be more than

specified minimum breaking load. The values of specified deflection and

specified minimum breaking load shall be as mentioned in the Indian Railway

manual for flash butt weld 1996.

9.9.2.1.3 Three (3) samples of flash butt weld shall be made and tested for fatigue test in

laboratory approved by the Employer’s Representative. The test scheme and

arrangements should have prior approval of the Employer’s Representative.

9.9.2.1.4 Rails outside the required end straightness tolerance shall not be welded. Rail

ends that are out of tolerance for straightness after welding may be

straightened by the use of a purpose made rail end straightener as approved

by Employer’s Representative and cause no damage/indentation to the rails,

Alternatively the rail ends may be cut and rewelded, in which case the payment

of such weld shall not be made to the Contractor and the cost of associated rail

length shall be recovered from the Contractor.

9.9.2.2 Welder qualification

All flash-butt welding machine operators shall be trained and certified either by

the manufacturer of the machine or by an independent Institution as approved

by the Employer’s Representative

9.9.2.3 Flash-butt welding quality control

Depending upon the cause of any defective weld it may be necessary to

test sample welds from the previous shift production run as directed by the

Employer’s Representative. The necessary tests, as instructed by the

Employer’s Representative, shall be at the Contractors expense. If any of

Technical Specification Page 59 of 94 July 2007

Page 63: Technical Specification

MMOPL Tender TW Series 1000

these welds fails in testing, welding shall immediately stop until the cause is

identified and rectified. After rectification it shall be demonstrated by the

Contractor to the Employer’s Representative that all similarly affected welds

have been removed from the track.

9.9.2.4 Flash-butt welding plant

9.9.2.4.1 The flash-butt welding machine shall be mobile type capable of making in situ

welds.

9.9.2.4.2 The welding clamps of rail shall provide contact area along the entire web of

rail and shall be fitted with spring loaded balls for optimum alignment of rail

ends.

9.9.2.4.3 The welding head shall be equipped with an integrated shearing device for

shearing of the weld seam automatically, immediately after the welding process

has been finished suitable for UIC 60, 880 grade & UIC 60, 1080 HH grade

rails.

9.9.2.4.4 A recorder system shall be provided for the simultaneous recording of butting

pressure, upset, and magnitude of current and duration of welding. Any

abnormal recordings shall be investigated and the relevant weld shall be

closely inspected visually and ultrasonically to ensure the weld is not defective.

The records for all the flash butt welds shall be made available to the

Employer’s Representative on a daily basis.

9.9.3 Alumino-Thermic welds

9.9.3.1 General

9.9.3.1.1 An Approved Alumino-Thermic short preheat controlled cooled welding process

as per Indian Railway manuals shall be used for the welding of joints. The weld

shall be undertaken in accordance with the relevant technical specification for

approval of the process and portions supplied for Thermit welding of rails and

relevant technical specification for performance and acceptance of Thermit

welding of rails of Indian Railways as mentioned in clause 6.2.6. Each weld

should be painted according to relevant code. All welds should be USFD

tested.

9.9.3.1.2 Where rails of dissimilar rail steel grade are welded together the weld portion

used shall be that of the higher grade rail and should be welded taking into

account the rapid cooling of higher grade (air quenching).

9.9.3.2 Qualification of welders for Alumino-Thermic welds

All Alumino-Thermic welders shall have competency certificate issued by

manufacturer of the approved welding process or by an independent institution

as approved by the Employer’s Representative.

Technical Specification Page 60 of 94 July 2007

Page 64: Technical Specification

MMOPL Tender TW Series 1000

9.10 PERMANENT MARKERS

9.10.1 General

9.10.1.1 As the track is completed permanent markers shall be provided and installed

on both sides as follows:

(a) Kilometre markers,

(b) Change of gradient markers, Vertical & horizontal curve marker,

(c) Curve Reference markers, cant, versine marked on rail web,

(d) LWR/CWR reference markers

(e) Fouling point markers,

(f) Turnout markers,

(g) REJ

9.10.1.2 All permanent marker plates/boards made of aluminium and supporting angle

to be made of galvanised steel including colour scheme comprising reflective

paints and fixation arrangement proposed to be used shall have prior approval

of Employer’s Representative.

9.10.1.3 All information to be marked on the markers shall be submitted by the

Contractor for Employer’s Representative’s approval

9.10.1.4 All markers required to be painted on rail for curves, turnouts and REJs etc.

shall be paint marked by the Contractor. The scheme for which shall be

submitted by the Contractor for Employer’s Representative’s approval.

9.11 TRACK TOLERANCES

9.11.1 General

9.11.1.1 The track parameters of completed track work, shall be measured by Contractor

in the presence of the Employer’s Representative and the measurement

recorded shall be in a format approved by the Employer’s Representative and

submitted both in hard and electronic copy.

9.11.1.2 The variations in horizontal alignment, vertical alignment, versine, cross

level/cant, twist and gauge shall not exhibit cyclic patterns.

9.11.1.3 All the track parameter measurements shall be taken in the floating condition of

the track. The base of measurement shall be as below:

Each sleeper or base plate for the gauge,

3 metres for the cant, cross-level and twist,

20 metres (half overlapping) for lining and

10 metres (half overlapping) for vertical profile

Technical Specification Page 61 of 94 July 2007

Page 65: Technical Specification

MMOPL Tender TW Series 1000

9.11.1.4 The Contractor shall be solely responsible for complying with the track

tolerances stipulated in clause 9.11.2 with the materials supplied by the

Contractor and the Employer’s Representative as per contract.

9.11.2 Dimensional tolerances

9.11.2.1 Track tolerances shall comply with the following limits:

a) Gauge (with reference to 1435 mm)

Maximum rate of variation over the prescribed track gauge

ballastless track : 2 mm

ballasted track : -2 mm to + 5 mm

Mean gauge per 200m : 1435 + 1.5 mm

For ballastless track 1435 – 1 mm

Mean gauge per 200m : 1435 + 3 mm

For ballasted track 1435 – 1 mm

Standard deviation within a 200 m Section less than 1 mm.

b) Maximum difference of any point in relation to the designed layout

(vertical)

ballastless track : -4 mm/+4 mm

ballasted track : -12 mm/+12 mm

c) Difference of any point in relation to the designed layout (horizontal)

Straight

ballastless track : +/-4 mm

ballasted track : +/- 10 mm

On straight and curve, deviation of measured versine over its designed

value on a 20 m chord: (half overlapping)

Ballastless : 2 mm

Ballasted : 5 mm

d) On constant grade and vertical curves,

Maximum deviation of measured versine (vertical) over its designed value

on a 10 m chord (half overlapping)

Ballastless : +/- 2 mm

Ballasted : +/- 2 mm

e) Cant/Cross Level (to be measured at every 3m)

Straight track and curved track (ballasted) 3 mm

(ballastless) 2 mm

Technical Specification Page 62 of 94 July 2007

Page 66: Technical Specification

MMOPL Tender TW Series 1000

(Deviation from designed value)

Baseplate to base plate (ballastless)

Variation of cant/x-level 1 mm

f) Twist: maximum value on a base of 3 m (ballasted and ballastless)

Straight and circular portion of curve : 1 mm/m

On transition portion of curve : 0.5 mm/m

(over & above designed value)

g) Turnouts (ballasted and ballastless)

Stock rail joint (longitudinal location) +/-15 mm

Nose to nose of Xing in crossovers 10 mm

(ballastless & ballasted)

Flangeway clearance

at end of the switch planing +5 mm/-0 mm

Switch toe opening +1mm -0 mm

Switch toe squareness 5 mm

Deviation of measured versine over its designed value for switches,

lead track (measured on 6 metre half overlapping chord)

+/- 2mm

h) Sleeper/Base plate

Spacing (from designed spacing) +/- 5 mm -

Sleeper/base plate/ perpendicularity

to rail centre line(out of square) 5 mm

i) Rail joint squareness across the track

(fishplated) 10 mm

9.11.3 Methods of measuring and recording

9.11.3.1 The completed track geometry shall be measured

for the following track parameters as a minimum:

a) Gauge

b) Horizontal Alignment (Versine) of minimum one rail

c) Cross Level/Cant

d) Twist

e) Vertical unevenness (Right hand rail)

Technical Specification Page 63 of 94 July 2007

Page 67: Technical Specification

MMOPL Tender TW Series 1000

f) Vertical unevenness (Left hand rail)

9.11.3.2 The proforma for the measurement of track parameter submitted by Contractor

for Employer’s Representative’s approved shall consist of the following as a

minimum:

g) A common base point for recording of location

h) Cross level/cant

i) Gauge

j) Horizontal alignment (versine)

k) Vertical unevenness both for right & left rail.

The proforma shall show the design figure, actual figure and the difference

between design and actual and shall allow columns for marking of twist.

9.11.3.3 The horizontal versine shall be measured every 10 m (half chord point) using a

20m chord and moving forward at 10 m intervals. The versine shall be

measured on the inside running edge of the outside rail in curves and either rail

of straight tracks at points 14mm below top of rails. Where a recording changes

its measuring rail there shall be a minimum overlap of readings of 60 meters.

9.11.3.4 The as-built recordings of rail level and horizontal alignment along longitudinal

direction with respect to the designed level & alignment shall be obtained by the

use of appropriate electronic survey instruments as directed by the Employer’s

Representative. Horizontal location readings shall be presented as co-ordinates.

Deviation from designed co-ordinates shall also be shown.

9.11.3.5 The vertical and horizontal rail location readings shall be taken with reference to

Kilometre location.

The recordings of rail level and horizontal location shall be taken at the intervals

as proposed by the Contractor and Approved by the Employer’s Representative.

9.11.3.6 Longitudinal locations shall additionally include, but not be limited to, switch and

crossings locations.

9.11.3.7 Rail inclination shall be measured using a purpose made digital rail inclinometer

and the recordings shall be submitted by Contractor for the Employer’s

Representative’s approval.

9.12 RECORDS

The manual records of rail level, cross-level/cant, gauge, twist, unevenness,

versine along longitudinal location and horizontal alignment with reference to the

designed locations shall be presented both electronically and in hardcopy in line

Technical Specification Page 64 of 94 July 2007

Page 68: Technical Specification

MMOPL Tender TW Series 1000

with the requirements given in the Chapter 5 of General Specification (Volume

III)

Technical Specification Page 65 of 94 July 2007

Page 69: Technical Specification

MMOPL Tender TW Series 1000

10. TESTING AND INSPECTION (This is to be read in

conjunction with the documents, “General Specification” Volume III and

“Quality Assurance” Volume IV)

10.1 GENERAL

10.1.1 Laboratory testing

All materials, components and assemblies shall, unless otherwise noted, be

inspected & tested by an Approved independent inspecting agency as approved

by Employer’s Representative on case-to-case basis to demonstrate that they

satisfy the Employer’s Representative’s requirements, when tested in

accordance with the specified procedures. Where no procedure is specified, the

Contractor shall propose suitable standard or particular procedures for

Employer’s Representative's Approval.

Technical Specification Page 66 of 94 July 2007

Page 70: Technical Specification

MMOPL Tender TW Series 1000

10.1.2 Quality assurance

10.1.2.1 The Contractor shall formulate a comprehensive QA plan for the Employer’s

Representative’s approval, which shall then be followed throughout the duration

of the contract.

10.1.2.2 All materials, components or assemblies shall be tested and inspected at the

frequency stated within the latest Specification.

10.1.2.3 A comprehensive schedule of all material inspection/tests at the

required/specified frequency of testing shall be submitted by the Contractor for

Employer’s Representative's approval.

10.1.2.4 A sample Proforma, with typical examples, for the material inspections/tests

shall be submitted by the Contractor for Employer’s Representative’s approval.

10.1.2.5 On receiving approval of the material inspection/test schedule, the Contractor

shall follow the schedule to prepare the required individual test and inspection

plans and submit for Employer’s Representative’s approval.

10.1.2.6 Such of those tests and inspections, for which Employer’s Representative has

opined to witness, shall be carried out only in the presence of Employer’s

Representative. For other tests & inspections test/inspection results and

certification thereof shall be submitted as directed by Employer’s Representative

for his approval. However, Employer’s Representative may at his discretion

conduct test checks to be organised by Contractor for validation of

test/inspection results.

10.1.2.7 Suitable Proforma for the recording and witnessing of all tests and inspections

shall be submitted for Employer’s Representative’s approval. Confirmation of

date of a test or inspection shall be presented on an Approved Proforma, not

less than 21 Days prior to the date for test / inspection.

10.1.2.8 No material, component or assembly shall be shipped until the clearance for this

has been obtained from the Employer’s Representative.

10.1.2.9 Should the items to be tested or inspected fail to meet the requirements of this

Specification, necessitating additional visits to the laboratories or works for

retesting or inspection the costs of these additional visits shall be at the expense

of the Contractor.

10.1.2.10 Periodically, during the currency of Contract the Employer’s Representative

may conduct inspections of manufacturing activities at the premises of the

Contractor and those of his suppliers and subcontractors. Such inspections

shall include quality procedure checks, witness inspections, both routine and

prototype, and shall also be for the purpose of monitoring progress. During

each inspection suitably qualified staff shall be provided by the Contractor.

10.2 Material and components supplied by the Contractor

Technical Specification Page 67 of 94 July 2007

Page 71: Technical Specification

MMOPL Tender TW Series 1000

All material and components supplied by the Contractor shall be inspected and

tested in accordance with the relevant technical specification of Indian Railways

as mentioned in clause 6.2.6.

10.2.1 Welding

10.2.1.1 General

10.2.1.1.1 All Welds (Flash butt and Alumino-Thermic) shall be tested ultrasonically as

per relevant manual for ultrasonic testing of rails and welds as mentioned in

clause 6.2.6.

10.2.1.1.2 All the defective welds whether identified as a result of USFD testing or

otherwise shall be removed from the track and rewelded by the Contractor.

The cost of all the rewelding of the defective/rejected welds and that of

associated rail length including cutting of rails, adjustments and all related

works shall be borne by the Contractor.

10.2.1.2 Welding materials

Welding materials for Alumino-Thermic welding shall be tested in accordance

with the relevant technical specification for approval of the process and portion

supplied for Thermit welding of rails as mentioned in clause 6.2.6.

10.2.1.3 Flash-butt weld tests

Tests for Flash-Butt Welding shall be carried out in accordance with the Indian

Railways Manual for Flash Butt Welding of Rails as mentioned in clause 6.2.6

and as detailed in clause 9.9.2.1of Technical Specification.

10.2.1.4 Alumino-Thermic weld tests

Tests for Alumino-Thermic Welding shall be carried out in accordance with the

Indian Railways Manual for Alumino-Thermic Welding of Rails as mentioned in

clause 6.2.6.

10.3 SWITCHES, CROSSINGS AND RAIL EXPANSION JOINTS

10.3.1 Switch inspection & crossing inspection (installation tests)

10.3.1.1 Switches with fixed heel shall be checked as full sets. Running edge offsets and

gauge shall be checked at coincidental locations, on both the main and turnout

track.

10.3.1.2 Running edge offsets shall be taken at maximum 1000 mm intervals. Running

edge offsets shall be within +2mm/ - 1 mm of their design value.

10.3.1.3 The inspection of switches and derailing switches shall include, but not be

limited to, the following:

(a) The switch rail evenly butts with the stock rail throughout the length of the

switch planing with the switch lying naturally.

Technical Specification Page 68 of 94 July 2007

Page 72: Technical Specification

MMOPL Tender TW Series 1000

(b) The underside of the switches and stock rails bear evenly on all slide base

plates.

(c) All dimensional checks of opening of switch, gauge, alignment, cross level

offset, lead, check and wing rail clearances nose to nose and flangeways

are within tolerance.

(d) The switch rails over their free length are not twisted/bent.

10.3.1.4 The switch toes shall not be out of square/beyond specified tolerances.

10.3.1.5 Crossings shall bear evenly on all base plates.

10.4 BUFFER STOPS

10.4.1.1 The fabricated buffer stops shall be inspected by the Employer’s Representative

before installation. Necessary assistance shall be provided by Contractor to

facilitate the inspections. A minimum of 21 days notice in writing of the dates on

which the buffer stops will be available for inspection shall be given to the

Employer’s Representative.

10.4.1.2 The buffer stops shall have the identification plates fixed, prior to the inspection,

and these identification plates shall be maintained until the acceptance of the

buffer stops in the Works.

10.4.1.3 Inspection sheets shall be prepared and submitted for approval of each

assembly clearly showing the design and actual dimensional checks, item

number and identification marks.

10.5 TESTS ON COMPLETION

10.5.1 General

Tests on Completion are to be undertaken in accordance with the provisions of

Clause 8.4 of General Specification. The Tests on Completion are deemed to

include the submission and approval of all of the documentation identified

therein and in the specified format.

10.5.2 Submissions

Before any Section of the Works is accepted as complete the following

information shall have been submitted for the approval of the Employer’s

Representative:

(a) Records and certification for all the tests and inspections identified in PS.

(b) As-built records/drawings of the following :

Vertical Alignment

Horizontal alignment

Recording unit traces of versine, gauge, twist, cant/crosslevel and rail top

longitudinal profiles

Technical Specification Page 69 of 94 July 2007

Page 73: Technical Specification

MMOPL Tender TW Series 1000

Weld record plan

All weld test results as detailed in this section, destressing records

Distance in kilometres, co-ordinates, offsets of all permanent track

markers

Rail Inclination records

(c) The results and reports of all tests and materials, assemblies and

items/components.

(d) The results of all Tests shall be submitted in hard copy and electronic

format.

10.5.3 Rail insulation to earth test

10.5.3.1 All trackwork shall be subjected to a rail insulation to earth test. The track shall

have a minimum rail-to-earth value to be determined after interfacing with the

Designated Contractors for ballasted and ballastless tracks in worst weather

conditions.

10.5.3.2 The rail to earth test shall be undertaken after the track has been completed and

cleaned but before it is finally formed into a continuously welded system and

before all the bonding is installed.

10.5.3.3 The test shall be undertaken on rail lengths up to maximum length of 1000 m.

10.5.3.4 The track shall not be finally formed into a continuous length, until the rail

insulation to earth tests have been undertaken and approved.

10.5.4 Rail to Rail insulation test

10.5.4.1 Ballast resistance test

10.5.4.1.1 A ballast resistance test shall be undertaken on all track lengths over 50

metres as a check of the leakage of current through the trackbase and rail

fastening system from one rail to the other.

10.5.4.1.2 The ballasted trackbase resistance test shall be undertaken after the track has

been complete and cleaned but before it is finally formed into a continuous

length and all the bonds are attached.

10.5.4.1.3 The testing procedure and the minimum resistance shall comply with the

requirements proposed by interfacing with designated signalling contractor

and as approved by Employer’s Representative.

Technical Specification Page 70 of 94 July 2007

Page 74: Technical Specification

MMOPL Tender TW Series 1000

10.5.4.2 Ballastless trackbase resistance test

10.5.4.2.1 A ballastless trackbase test shall be undertaken on all track lengths over 50

metres as a check of the leakage of current through the trackbase and rail

fastening system from one rail to the other.

10.5.4.2.2 The ballastless trackbase resistance test shall be undertaken after the track

has been complete and cleaned but before it is finally formed into a continuous

length and all the bonds are attached.

10.5.4.2.3 The testing procedure and the minimum resistance shall comply with the

requirements proposed by interfacing with designated signalling contractor.

10.5.5 Rail inclination inspection

10.5.5.1 Both rails of all ballastless running line tracks shall be checked, at maximum 10

m intervals, for inclination using a purpose made approved digital inclinometer in

the presence of the Employer’s Representative.

10.5.5.2 Should any reading show the inclination to be outside the specified limits every

alternate fastening assembly shall be further checked either side of the non-

compliant reading until compliant readings are consistently obtained.

10.5.5.3 If the length of rail outside the specified inclination exceeds 9 m, the out of

tolerance lengths shall be rectified by the Contractor by a method approved by

the Employer’s Representative.

10.5.5.4 The procedure / values mentioned in Para 10.5.3, 10.5.4.1 & 10.5.4.2 are

indicative and these tests are to be carried out by the Designated Contractors.

The actual values / procedure of these tests shall be interfaced by the

Contractor with the Designated Contractors.

11. CONCRETE: PLAIN & REINFORCED

The Contractor will establish a full fledged most modern concrete laboratory

with trained engineers, Quality Control (QC) Manager and technicians at site/in

the casting yard. It will have facilities for testing physical properties of cement,

workability of concrete, cube strength, permeability of concrete, sieve analysis,

Technical Specification Page 71 of 94 July 2007

Page 75: Technical Specification

MMOPL Tender TW Series 1000

RCPT, aggregate tests, tests required for mix design, chloride tests of water and

admixture, concrete temperature, oven, accelerated tests for cement/concrete

strength, flexural strength of concrete. One room shall be air-conditioned to

control temp and humidity for cement tests. A typical layout of the laboratory is

attached as annexure-I

The durability requirements in terms of environment condition, concrete cover,

type and quality of material constituent, cement content and water cement ratio,

workmanship to obtain full compaction and efficient curing, shape and size of

members shall be taken in to account in the structural design as well as in

technical specifications of contract. Design for durability shall be in accordance

with the report: “Durability of Concrete Structure”, ref. Report N°. BS-14

(Revised), published by the Government of India (Ministry of Railways) in

January 2001.

11.1 MATERIALS

All the sources of the materials shall be approved in advance before bringing to

the Site. All materials for making concrete shall be approved by the Employer’s

Representative. All approved samples shall be deposited in the office of the

Employer’s Representative before placing orders for the materials with

suppliers. The materials brought on to the works shall conform in every respect

to their approved samples and specifications.

Fresh samples shall be deposited with Employer’s Representative whenever

type or source of any material changes. The Contractor shall check fresh

consignment of materials as it is brought on to the works to ensure that they

conform to the specifications and/or approved samples.

The Employer’s Representative shall have the option to have any of the

materials tested to find whether they are in accordance with specifications at the

Contractor expense. All bills vouchers and test certificates which in the opinion

of the Employer’s Representative are necessary to convince him as to the

source and quality of materials or their suitability shall be produced for his

inspection when required.

Any materials which have not been found to conform to the specifications and

not approved by the Employer’s Representative shall be rejected forthwith and

shall be removed from the site by the Contractor at his own cost within the time

stipulated by the Employer’s Representative. The Employer’s Representative

shall have the powers to cause the Contractors to purchase and use materials

from any particular source, as may in his opinion be necessary for the quality

Technical Specification Page 72 of 94 July 2007

Page 76: Technical Specification

MMOPL Tender TW Series 1000

execution of work.

Contractor shall also ensure that all constituents of exposed concrete shall be

taken from same sources to achieve a uniform colour and texture.

11.1.1 Cement/blended cement/cementitious material:

They all will mean the same thing.

11.1.1.1 The cement used shall be of the following types:

a) 43 grade Ordinary Portland Cement conforming to

IS: 8112.

b) 53 grade Ordinary Portland Cement conforming to

IS:12269.

c) IRST-40 Indian Railway standard specifications for

special grade cement for use in concrete sleepers.

d) PPC as per IS: 1489 (Part-I)

e) PSC as per IS: 455

f) Fly ash as per IS:3812 (Part I & II)

Technical Specification Page 73 of 94 July 2007

Page 77: Technical Specification

MMOPL Tender TW Series 1000

11.1.1.2 Whenever possible all cements of each type shall be obtained from one

constant source throughout the contract, cement of different types shall not be

mixed together. Different brands of cement, or the same brand of cement from

different sources, shall not be used without prior approval of the Employer’s

Representative.

11.1.1.3 Packaged cement shall be delivered to the site in original sealed bags which

shall be labelled with the weight, name of manufacturer, brand and type.

Cement received in torn bags shall not be used. Cement bags will not be

handled with hooks which allow ingress of moisture. Contractor may obtain

cement in bulk and store it in suitable silos of adequate capacity.

11.1.1.4 Each type of cement shall be stored in a separate silo and it shall be ensured,

that cements of different quality are not mixed up.

11.1.1.5 All cement shall be fresh when delivered and at ambient atmospheric

temperature.

11.1.1.6 In fair faced elements, the cement used in the concrete for any complete

element shall be from a single consignment. All cement for exposed concrete

shall be from the same approved source and uniform in colour.

11.1.1.7 With each and every delivery of cement the Contractor shall provide

manufacturer’s certificate that the cement conforms to the relevant Indian

standard. The Contractor shall provide complete facilities at site for carrying out

the following tests:

a) Setting time by Vicat's apparatus as per IS:4031 and IS:5513.

b) Compressive strength on cement as per IS: 4031, IS:650, IS:10080.

11.1.1.8 Total chloride content in cement shall in no case exceed 0.05 percent by mass

of cement. Also, total sulphur content calculated as sulphuric anhydride (SO3),

shall in no case exceed 2.5 percent and 3.0 percent when tri-calcium

aluminate per cent by mass is upto 5 or greater than 5 respectively.

11.1.1.9 The cement will be blended with processed fly-ash conforming to IS

specifications from Dahanu Thermal power plant upto a maximum of 35%

(depending on the mix design) of cement to improve the durability of

structures. The fly-ash will be transported by the Contractor at his cost and

octori and taxes. The fly ash shall be supplied at Rs1200 per metric ton at

Dahanu plant.

11.1.2 Aggregate

Aggregates from natural sources shall be in accordance with IS:383. The

Technical Specification Page 74 of 94 July 2007

Page 78: Technical Specification

MMOPL Tender TW Series 1000

Contractor shall submit to the Employer’s Representative certificates of grading

and compliance for all consignments of aggregate. In addition at site from time

to time, the Contractor shall allow for carrying out such tests and for supplying

test records to the Employer’s Representative. The aggregates shall be

procured from approved sources only as directed by the Employer’s

Representative from time to time.

For fair faced concrete, the Contractor shall ensure that aggregates are free

from iron pyrites and impurities, which may cause discoloration. Aggregates

shall be stored on paved areas in different compartments according to their

nominal size.

11.1.2.1 Fine Aggregate

The Contractor shall provide complete facilities at site for determining grading of

aggregates by sieves as per IS: 383, IS: 460, IS: 1607, and IS: 2386.

The fine aggregate shall be river sand, manufactured sand of approved grading,

pit sand. It shall be free from clay, loam, earth or vegetable matter, salt or other

harmful chemical impurities. It shall be clean, sharp, strong, angular and

composed of hard siliceous material. Sand dredged from sea, creeks will not be

used. RMC manufactured with sand dredged from sea/creek will not be used.

The grading of fine aggregate when determined as described in IS: 2386 (part I),

shall be within the grading zones I, II, III.

The Contractor shall provide complete facilities at site for carrying out the

following tests:

A) Proportion of clay, silt and fine dust by sedimentation method as per

IS:2386 part II.

B) Moisture content in fine aggregate as per IS: 2386 Part III.

C) Bulk density / Bulkage.

D) Specific Gravity

11.1.2.2 Coarse Aggregate

The coarse aggregate shall be crushed stone.

Crushed gravel, natural gravel or a suitable combination thereof .Coarse

aggregate obtained from crushed or broken stone shall be angular, hard, strong,

dense, durable, clean and free from soft, friable, thin plate, elongated or flaky

pieces and any deleterious material.

Technical Specification Page 75 of 94 July 2007

Page 79: Technical Specification

MMOPL Tender TW Series 1000

The grading of aggregate shall be controlled by obtaining the coarse aggregate

in different sizes and blending them in correct proportions as and when required.

All coarse aggregate shall conform to IS: 383 and tests for conformity shall be

carried out as per IS: 2386, Parts I to VIII.

The maximum size of coarse aggregate shall be such that the concrete can be

placed without difficulty so as to surround all reinforcement thoroughly and fill

the corners of formwork. Unless otherwise permitted by the Employer’s

Representative the nominal maximum size shall not exceed 40mm.

11.1.3 Water

Water used in the works shall be potable water and free from deleterious

materials. Water used for mixing and curing concrete as well as for cooling

and/or washing aggregate shall be fresh and clean free from injurious amounts

of oil, salts, acids, alkali, other chemicals and organic matter.

Water shall be from the source approved by the Employer’s Representative and

shall be in accordance with clause 5.4 of IS: 456 However, chloride content in

water shall not exceed 500 mg/litre.

Before starting any concreting work and wherever the source of water changes,

the water shall be tested for its chemical and other impurities to ascertain its

suitability for use in concrete for approval of the Employer’s Representative. No

water shall be used until tested and found satisfactory. Cost of all such Tests

shall be borne by the Contractor.

11.2 Blending of aggregates:

In order to obtain optimum workability, individual aggregates of nominal size

40mm, 20mm, 10mm, 4.75mm and 2.36mm will be blended in such a way that

the grading curve for all aggregates will be a smooth curve from size 0.15mm to

40mm falling within the established envelop grading curve. Contractor shall

establish envelop grading curve for each grade of concrete for given maximum

size of aggregates and get it approved by Employer’s Representative before

finalising the mix design.

11.3 Admixtures:

11.3.1 Chemical admixtures are not to be used until permitted by the Employer’s

Representative. In case their use is permitted, the type, amount and method of

use of any admixtures proposed by the Contractor shall be submitted to the

Employer’s Representative for approval. The minimum cement content specified

Technical Specification Page 76 of 94 July 2007

Page 80: Technical Specification

MMOPL Tender TW Series 1000

shall not be reduced on account of the use of the Admixtures.

11.3.2 The Contractor shall further provide the following information concerning each

admixture to the Employer’s Representative

a. Normal dosage and detrimental effects if any of under dosage and over

dosage.

b. The chemical names of the main ingredients in the admixtures.

c. The chloride content, if any, expressed as a percentage by weight of

admixture.

d. Whether or not the admixture leads to the entrainment of air when used in

the manufacturer's recommended dosage.

e. Where two or more admixtures are proposed to be used in any one mix,

the manufacturer's written confirmation of their compatibility.

11.3.3 In reinforced concrete, the chloride content of any admixture used shall not

exceed 0.1 percent by weight of the admixture as determined in accordance

with IS:6925 and the total chloride and sulphate contents in concrete mix shall

not exceed 0.10 and 4.0 percent respectively by weight of cement.

11.3.4 The admixtures when used shall conform to IS:9103. The suitability of all

admixtures shall be verified by trial mixes.

11.3.5 The addition of calcium chloride to concrete containing embedded metal will not

be permitted under any circumstances.

11.3.6 Retarding admixtures when used shall be poly hydroxyl compounds.

11.3.7 Each batch / consignment shall be tested for specific gravity & performance in

concrete before their use.

11.4 Batching Plants, Mixers and Vibrators:

11.4.1 Unless specified in the schedule of items, for all structural concreting work the

Contractor shall provide automatic weigh-batching plant of suitable capacity.

The plant used shall conform to IS: 4925.

11.4.2 The Contractor shall provide Concrete mixers (IS:1791 – Batch type concrete

mixers, IS:2438 – Roller Pan Mixer) and Vibrators (IS:2505 – Concrete Vibrators

Immersion Type, IS:2506 – Screed board concrete vibrators, IS:4656 – Form

Vibrators for Concrete) supplied by recognised manufacturers.

11.5 Grade of Concrete:

The concrete is designated as follows:

Technical Specification Page 77 of 94 July 2007

Page 81: Technical Specification

MMOPL Tender TW Series 1000

Concrete M 25 / 20

The letter M refers to the mix

The number 25 represents the characteristic compressive strength of 15cm

cubes at 28 days in MPa (Mega Pascal: 1 MPa: 10 kg/cm2 approximately). M25

concrete thus has a characteristic strength of 250 kg/cm2. Other mix design will

also be denoted in same way.

The number 20 represents the nominal size of the aggregate in mm.

11.6 Mix Design:

It is the complete responsibility of the Contractor to design the concrete mixes

by approved standard methods and to produce the required concrete

conforming to the specifications and the strength, durability, workability

requirements approved by the Employer’s Representative.

Mix Design once approved must not be altered without prior approval of

Employer’s Representative. However, should the Contractor anticipate any

change in quality of future supply of materials than that used for preliminary mix

design, he should inform the Employer’s Representative quite in advance and

bring fresh samples sufficiently in advance, to carry out fresh trial mixes. Design

mix will indicate by means of graphs and curves etc., the extent of variation in

the grading of aggregates which can be allowed. Cement will mean

cement/blended cement/cementitious material. The S.D. and coefficient of

variation shall be established for each grade of concrete. SQC graphs shall be

submitted monthly.

Limits of Water and Cementitious material Contents

Maximum water/ cementitious material ratio:

a) For RCC members including piles - 0.40

b) For PSC members - 0.40

10.6.1. Cement/blended cement/cementitious material Content:

Cementitious material in concrete shall not be less than 380 kg/ cum for RCC

work and 400 kg/ cum for PSC work under severe exposure. However, the

quantity of cement (excluding Fly ash) shall be limited to 450kg/ cum of

concrete. Ordinary Portland cement (OPC) of 43 and 53 grade conforming to IS:

8112 and IS: 12269 respectively shall be used. For pre-stressed concrete,

cement conforming to IRS – T – 40 specifications or OPC 53 grade cement with

Fly ash shall be used.

Technical Specification Page 78 of 94 July 2007

Page 82: Technical Specification

MMOPL Tender TW Series 1000

As regards trial mixes, acceptance criteria, acceptance specification, lot size,

sampling and testing and sampling size for piling work, PSC girders (cast-in-situ

and pre-cast post-tensioned) and general work, the requirement of the relevant

codes, standards and directions of the Employer’s Representative shall be

followed.

11.7 Permeability test for Concrete:

No mix shall be approved without satisfactory permeability by RCPT and DIN

1048 tests. Regular permeability tests shall be carried out as per frequency

specified by Employer’s Representative.

11.7.1 The Employer’s Representative shall select random batches of concrete for

examination at his discretion and sampling will generally be done at the point of

discharge from the mixer and at placing point.

11.7.2 From the batches thus selected two concrete cylinders shall be made in

accordance DIN 1048.

11.7.3 All cylinders shall be made, cured, stored, transported and tested in accordance

with DIN-1048 Specifications. The tests shall be carried out in the site

laboratory.

11.7.4 At least two cylinders shall be made on each day’s concreting until 60 cylinders

have been made for each grade of concrete. The cylinders will be tested as per

the procedure, given in Clause 5 next.

11.7.5 Test Procedure:

The permeability of concrete will be verified by the following procedure:

Prepare a cylindrical test specimen 150 mm dia and 160mm

high.

After 28 days of curing, test specimen will be fitted in a machine

such that the specimen can be placed in water under pressure up to 7

bars.

At first a pressure of one bar is applied for 48 hours, followed

by 3 bars for 24 hours and 7 bars for next 24 hours.

After the passage of the above period, the specimen is taken

out and split in the middle by compression applied on two round bars on

opposite sides above and below.

The water penetration in the broken core is measured with

scale and the depth of penetration assessed in mm (max permissible limit

Technical Specification Page 79 of 94 July 2007

Page 83: Technical Specification

MMOPL Tender TW Series 1000

25 mm).

11.7.6 Acceptability Criteria:

Rapid Chloride Penetration Test (RCPT) as per ASTM-C-1202 shall be

carried out under controlled conditions and by trained technicians. The

necessary equipment shall be installed at site laboratory. The RCPT values

should not be more than 2500 Columbs for M-30 and 1500 Columbs for M-45

and higher grades.

No extra payment shall be made for this test and cost of the same will be

included in his rate for concrete works.

11.8 Batching of Concrete Ingredients:

Unless permitted by the Employer’s Representative, all concreting shall be

either produced in automatic weigh batching plant installed at site or Ready Mix

Concrete manufactured in automatic weigh batching plant.

11.9 Placing temperatures:

During extreme hot or cold weather, the concreting shall be done as per

procedures set out in IS: 7861, Parts I & II. The concrete temperature shall not

be more than 30˚C

In hot weather with temperature exceeding 40˚C, the stock piles of fine and

coarse aggregates for concreting shall be kept shaded from direct rays of sun

and the concrete aggregates sprinkled with water for a sufficient time before

concreting in order to ensure that the temperature of these ingredients is as low

as possible prior to batching. The mixer and batching equipment shall be also

shaded and if necessary painted white in order to keep their temperatures as

low as possible. The placing temperature of concrete shall be as low as possible

in warm weather and care shall be taken to protect freshly placed concrete from

overheating by sunlight in the first few hours of its laying. The time of day

selected for concreting shall also be chosen so as to minimise placing

temperatures. In case of concreting in exceptionally hot weather the Employer’s

Representative may in his discretion specify the use of ice either flaked and

used directly in the mix or blocks used for chilling the mixing water. In either

case, the Contractor shall not be paid extra for cost of ice, additional labour

involved in weighing and mixing etc. All salt and saw dust shall be removed from

ice before use. Quality of water used for making ice shall confirm to IS: 456. A

complete record of concrete temperature shall be maintained and submitted.

The temperature shall be recorded both at the mixing & placing point.

Technical Specification Page 80 of 94 July 2007

Page 84: Technical Specification

MMOPL Tender TW Series 1000

11.10 Transporting, Placing, Compacting and Curing, :

Transporting, placing, compacting and curing of concrete shall be in accordance

with IS: 456.

11.10.1 Transporting:

The mix after discharging from the mixer shall be transported by transit mixers,

buckets, pumps etc. or as approved by the Employer’s Representative without

causing segregation and loss of cement slurry and without altering its desired

properties with regard to water cement ratio, slump, air content, cohesion and

homogeneity. It should be ensured that the concrete is moved to its final

destination, placed and compacted before initial set.

The transportation is to be done by agitating transit mixers, pumps or other

approved methods.

11.10.2 Placing :

The method of placing shall be such as to prevent formation of cold joints and

segregation by providing windows in the formwork for pouring concrete or by

tremie pipe. The thickness of horizontal layers shall not exceed 300mm. High

velocity discharge of concrete causing segregation of mix shall be avoided. The

concrete shall be placed in the forms gently and not dropped from a height

exceeding 1.5m. Each layer of concrete shall be compacted fully before the

succeeding layer is placed and separate batches shall follow each other so

closely that the succeeding layer shall be placed and fully compacted before the

layer immediately below has taken initial set.

For all heights, the rate of placing of concrete by using tremie / pumps shall not

be more than 1.5m / hr or as approved by the Employer’s Representative.

Concreting of any portion or section of the work shall be carried out in one

continuous operation and no interruption of concreting work will be allowed

without approval of the Employer’s Representative. A concrete sequence shall

be prepared in advance for each concrete pour and approval of Employer’s

Representative taken.

11.10.3 Compaction:

Internal (needle) and surface (screed board) vibrators of approved make and

size shall be used for compaction of concrete.

Internal vibrators shall be used for compaction of concrete in foundations,

columns, buttresses arch section, slabs etc, and if required surface vibrators

Technical Specification Page 81 of 94 July 2007

Page 85: Technical Specification

MMOPL Tender TW Series 1000

shall also be used. Depending on the thickness of layer to be compacted, 25

mm, 40 mm, 60 mm and 75 mm diametre internal vibrators will be used. The

concrete shall be compacted by use of appropriate diameter vibrator by holding

the vibrator in position until:

Air bubbles cease to come to surface.

Resumption of steady frequency of vibrator after the initial short period of

drop in the frequency, when the vibrator is first inserted.

The tone of the vibrated concrete becomes uniform.

Flattened, glistening surface, with coarse aggregates particles blended into

it appears on the surface.

To secure even and dense surfaces free from aggregate pockets, vibration

shall be supplemented by tamping or tamping by rods in the corners of

forms and along the form surfaces while the concrete is plastic.

A sufficient number of spare vibrators shall be kept readily accessible to

the place of deposition of concrete to assure adequate vibration in case of

breakdown of those in use.

Form vibrators whenever used shall be clamped to the sides of formwork

and shall not be fixed more than 450 mm above the base of the new

formwork and concrete shall be filled not higher than 230mm above the

vibrator. The formwork must be made specially strong and watertight

where this type of vibrator is used.

Care must be taken to guard against over vibration especially where the

workability of the concrete mix is high since this will encourage

segregation of the concrete.

Plain concrete in foundations shall be placed in direct contact with the

bottom of the excavation, the concrete being deposited in such a manner

as not to be mixed with the earth. Plain concrete also shall be vibrated to

achieve full compaction.

Technical Specification Page 82 of 94 July 2007

Page 86: Technical Specification

MMOPL Tender TW Series 1000

11.10.4 Concrete placed below the ground shall be protected from falling earth during

and after placing. Concrete placed in ground containing deleterious substances

shall be kept free from contact with such ground and with water draining there

from during placing and for a period of seven days or as otherwise instructed

thereafter. Approved means shall be taken to protect immature concrete from

damage by debris, excessive loading, abrasion, vibrations, deleterious ground

water, mixing with earth or other materials, and other influences that may impair

the strength and durability of the concrete.

11.10.5 Curing:

Curing of concrete shall be complete and continuous using potable water

free from chlorides and sulphates, water that is free of harmful amounts of

deleterious materials that may attack, stain or discolour the concrete as

per IS 456. Minimum wet curing will be for ten days by ponding water

followed by moist curing by spraying water which shall be maintained up to

a total period for at least 21 days from the date of casting.

Immediately after compaction and completion of any surface finishes the

concrete shall be protected from the evaporation of moisture by means of

polythene sheet, wet Hessian or other material kept soaked by spraying.

As soon as the concrete has attained a degree of hardening sufficient to

withstand surface damage moist curing shall be implemented and

maintained for a period of at least 21 days after casting.

Method of curing and their duration shall be such that the concrete will

have satisfactory durability and strength and members will suffer a

minimum distortion, be free from excessive efflorescence and will not

cause undue cracking in the works by shrinkage.

Steam curing with approved methodology can be adopted if required, for

pre-cast segments. No extra payment will be made for adopting steam

curing.

Curing compounds may be permitted with Employer’s Representative

approval. However it is required to be proved that using curing compound

the concrete shall not have less strength than concrete cured by water

curing. It shall not leave any discolouration on the structural concrete.

11.11 Construction Joints:

Methodology of providing construction joints and their location shall be approved

in advance. Construction joints in all concrete work shall be made as follows:

The laitance shall be removed by wire brush and aggregate exposed to 1/3rd of

Technical Specification Page 83 of 94 July 2007

Page 87: Technical Specification

MMOPL Tender TW Series 1000

its height after the initial setting of concrete, but without dislodging the

aggregate. The mortar around steel and corners shall be removed by air/water

pressure jetting. Before placing new concrete the earlier surface shall be

moistened. Cement water slurry will never be sprinkled.

Alternatively, top surface of concrete can be painted with Plasticizer (retarder)

before initial setting of concrete. This will not allow cement in the top layer to set,

and same if washed before final set of concrete with water will provide a surface

free of laitance. This is preferred method of providing construction joint.

Where vertical construction joints are required, these shall be shuttered as

directed and not allowed to take the natural slope of the concrete.

Before fresh concrete is placed against a vertical joint, the old concrete shall be

chipped by a pneumatic chipping hammer, cleaned and moistened. Alternatively

the shutter can be painted with Plasticizer (retarder) before fixing. This will not

allow cement in contact with shutter to set, and same if washed with water will

provide a surface free of laitance. This is preferred method of providing vertical

construction joint. The shutter is required to be removed before the final setting

of concrete and concrete surface shall be washed with water jet .Trials shall be

made in the site laboratory to decide the methodogy.

No separate payment shall be allowed to the Contractor for forming joints or

chipping and cleaning them. Construction joints in concrete walls and slabs for

liquid retaining structures shall be prepared in a similar manner to normal

construction joints. If use of metal, rubber or plastic water stops is specified, this

shall be cast into joints. Measures shall be taken by the Contractor to ensure

that no displacement or distortion of water stops takes place during placing of

concrete. The construction joints shall ensure proper bond and leak proof joint.

11.12 Cover and Cover blocks:

11.12.1 Minimum Clear Cover:

Plinth Beam / Slabs

Bottom reinforcement 40mm

Sides, top 50mm

Clear cover will mean extent of cover from the outermost steel bar including

binding wire. All binding wire ends shall be bent towards centre of the section.

Technical Specification Page 84 of 94 July 2007

Page 88: Technical Specification

MMOPL Tender TW Series 1000

11.12.2 Cover blocks shall be manufactured on vibrating tables. The grade of mix shall

be same as that of main member. All quality control shall be exercised as for

the main member The cost of cover blocks shall be deemed to have been

included in the rates.

11.13 Cracks:

If cracks, which in the opinion of the Employer’s Representative may be

detrimental to the strength and durability of the construction, develop in concrete

construction, the Contractor at his own expense shall test the structure as

specified in clause 1.1.16 of ‘Loading Tests’ of these Specifications. If under

such test loads the cracks develop further, the Contractor shall dismantle the

construction, carry away the debris, replace the construction and carry out all

consequential work thereto.

If any cracks develop in the concrete construction, which in the opinion of the

Employer’s Representative, are not detrimental to the stability of the

construction, the Contractor at his own expense shall grout the cracks with

epoxy grout or with other composition as directed by Employer’s Representative

and also at his own expense and risk shall make good to the satisfaction of the

Employer’s Representative all other works such as plaster, moulding, surface

finish, which in the opinion of the Employer’s Representative have suffered

damage either in appearance or stability owing to such cracks. The Employer’s

Representative's decision as to the extent of the liability of the Contractor in the

above matter shall be final and binding.

External crack width shall be restricted to 0.1mm. If cracks width is more than

0.1mm or in the opinion of Employer’s Representative may be detrimental to

concrete construction, the Contractor at his own expenses should epoxy grout

the cracks.

11.14 Defective Concrete:

Badly executed work not conforming to requirements shall be removed and shall

not be incorporated in the works. No plastering or repairs will be allowed to

concrete.

11.15 Exposed Faces, Holes and Fixtures:

On no account shall concrete surfaces be patched or covered up or damaged

concrete rectified or replaced until the Employer’s Representative or his

representative has inspected and photographed the works and issued written

instructions for rectification. Failure to observe this procedure will render that

portion of the works liable to rejection.

Technical Specification Page 85 of 94 July 2007

Page 89: Technical Specification

MMOPL Tender TW Series 1000

Holes for foundation or other bolts or for any other purposes shall be moulded

and steel angles, holdfasts or other fixtures shall be embedded, according to the

drawing or as instructed by the Employer’s Representative.

11.16 Finishes:

Unless otherwise instructed the face of exposed concrete placed against

formwork shall be rubbed down immediately on removal of the formwork to

remove irregularities. The face of concrete for which formwork is not provided

other than slabs shall be smoothed with a float to give a finish equal to that of

the rubbed down face, where formwork is provided. The top face of a slab which

is not intended to be covered with other materials shall be levelled and floated to

a smooth finish at the levels or falls shown on the drawings or as directed. The

floating shall be done so as not to bring an excess of mortar to the surface of the

concrete. The top face of a slab intended to be surfaced with other material shall

be left with a spaded finish. Faces of concrete intended to be plastered shall be

roughened by approved means to form key.

11.17 Concrete for flooring on grade:

Concrete for flooring on grade shall be placed in alternate bays not exceeding

more than 4m x 6m or as specified in the drawings including forming the joints

or adjacent bays. The stiff mix shall be thoroughly vibrated and finished to

receive the floor finish.

11.18 Grouting of base plates & bolt holes:

Only branded free flowing, high strength Ferro – grouts shall be used.

Technical Specification Page 86 of 94 July 2007

Page 90: Technical Specification

MMOPL Tender TW Series 1000

11.18.1 Mixing :

Dry grout should be mixed in a mechanical mixer: the conventional 200/400-litre

capacity concrete mixer can be used to mix four bags of dry grout; alternatively,

paddle type mortar mixers can be used. The quantity of grout to be mixed at one

time should not exceed that amount which can be placed in approximately 10 to

15 minutes.

11.18.2 Batching:

Batching of grout by fraction of a bag is not allowed. The quantity of mixing

water should be the minimum commensurate with workability, compaction, and

filling of the grout in all corners and crevices. Mixing should be done for a

minimum of three minutes to obtain a fluid grout of uniform consistency.

11.18.3 Cleaning and preparation of the surface:

The base concrete should be clean and strong, and its surface should be

properly hacked; all dust should be removed suction or compressed air. The

surface should be thoroughly wetted with water for several hours. Before the

grout is poured, all free water should be removed.

11.18.4 Restraint :

Heavy back-up blocks of timber or concrete should be fixed on all sided of the

base plate to prevent escape of the grout, when poured through the openings

provided in the base plate. Adequate restraint must be ensured on all the sides

for a period of 7 days to obtain effective expansion and shrinkage

compensation.

11.18.5 Curing :

The grout should not dry out where external restraint is provided in the form of

form-work, the top opening and all stray openings should be covered with wet

sack for at least 14 days.

11.18.6 Placing and Compaction:

The grout should be placed quickly and continuously either through the holes in

the base plates or from one side only to ensure complete filling without

entrapment of air. Grout should be properly spread and compacted by rodding.

Excessive vibration should be avoided.

Below the bed plates the grout should be compacted using long pieces of

doubled-over flexible steel strapping or chains. The forward and backward

Technical Specification Page 87 of 94 July 2007

Page 91: Technical Specification

MMOPL Tender TW Series 1000

movement of the strap or chain will assist in the flow of the grout into place.

Steps must be taken to keep the grout in full contact with the underside of the

bedplate until the grout sets; maintaining a small head of fresh grout in the

forms.

11.18.7 Shrinkage Compensated Grout:

Shrinkage compensated grout or non-shrinkable grout of Associated Cement

Companies Limited or any other approved manufacturer (Fosroc, Apex, Roff,

and Sika), should be used. The batching shall be as per the manufacturer's

specifications, other procedures being as above.

11.19 Pre-cast Concrete:

11.20

The provision in this section shall be considered supplementary to general

provisions for reinforced concrete works.

11.20.1 Handling and Storage:

The pre-cast units shall be stored as directed by the Employer’s Representative.

The area intended for the storage of pre-cast units should be surfaced in such a

way that no unequal settlement can occur.

To prevent deformation of slender units, they should be provided with supports

at fairly close intervals and should also be safeguarded against tilting. Lifting

and handling positions should conform to the Employer’s Representative's

directions and drawings. In addition, location and orientation marks should be

put on the members, as and where necessary. During erection the pre-cast units

should be protected against damage caused by local crushing and chafing

effects of lifting and transport equipment.

11.20.2 Temporary Supports and Connections:

Temporary supports provided during erection should take into account all

construction loads likely to be encountered during the completion of joints

between any combination of pre-cast and in-situ concrete structural elements.

The supports should be arranged in a manner that will permit the proper

finishing and curing of any in-situ concreting and grouting associated with the

pre-cast member being supported when the gaps of joints have to be filled with

concrete or mortar. They should first be cleaned and faces of the joints should

be wetted. The mixing, placing and compacting of cement and mortar should be

done with special care. Mortar of a dry consistency should be in the proportion

Technical Specification Page 88 of 94 July 2007

Page 92: Technical Specification

MMOPL Tender TW Series 1000

of 1:1½ (1 part of cement to 1½ parts of sand) and should be placed in stages

and packed hard from both sides of the joint.

11.20.3 Tolerances:

The following tolerances apply to finished pre-cast products at the time of

placement in the structure. The forms must be constructed to give a casting well

within these limits:

Overall dimensions of members should not vary more than + 6mm per 3m

length with a maximum variation of + 20mm.

Cross-sectional dimensions should not vary more than the following :

+ 3mm for sections less than 150mm thick

+ 4mm for sections over 150mm & less than 450mm

+ 6mm for sections over 450mm to 1000mm

+ 10mm for sections over 1000mm

Deviation from straight line in long sections should not be more than +

6mm up to 3m, + 10mm for 3m to 6m, + 12mm for 6m to 12m.

For tolerances on pre-cast segments for girders please refer Annexure 12.2.

11.21 Ready Mix Concrete and Pumping:

Ready-mixed concrete may be manufactured in a central automatic weigh

batching plant and transported to the place of work in agitating transit mixers.

11.21.1 Coarse aggregates:

The maximum size of coarse aggregate shall be limited to one-third of the

smallest inside diameter of the hose or pipe used for pumping. Provision shall

be made for elimination of over-sized particles by screening or by careful

selection of aggregates. To obtain proper gradation it may be necessary to

combine and blend certain fractional sizes of aggregates. Uniformity of

gradation throughout the entire job shall be maintained.

The quantity of coarse aggregate shall be such that the concrete can be

pumped, compacted and finished without difficulty.

11.21.2 Fine aggregates:

The gradation of fine aggregate shall be such that 15 to 30 percent should pass

the 0.30 mm screen and 5 to 10 percent should pass 0.15 mm screen so as to

obtain pumpable concrete. Sands, which are deficient in either of these two

Technical Specification Page 89 of 94 July 2007

Page 93: Technical Specification

MMOPL Tender TW Series 1000

sizes, should be blended with selected finer sands to produce these desired

percentages. With this gradation, sands having a fineness modulus between 2.6

and 3.1 are generally satisfactory. However, for uniformity, the fineness

modulus of the sand should not vary more than 0.2 from the average value used

in proportioning. Sand from sea bed or creeks shall not be used.

11.21.3 Water, Admixtures and Slump:

The amount of water required for proper concrete consistency shall take into

account the rate of mixing, length of haul, time of unloading, and ambient

temperature conditions.

Additions of water to compensate for slump loss should not be resorted to nor

should the design maximum water-cement ratio be exceeded. Additional dose of

retarder be used to compensate the loss of slump at Contractor cost, when

permitted by Employer’s Representative. Retempering water shall not be

allowed to be added to mixed batches to obtain desired slump. Slump records at

the time and place of concreting shall be maintained and shall conform to the

requirements.

11.21.4 Transportation:

The method of transportation used should efficiently deliver the concrete to the

point of placement without significantly altering its desired properties with regard

to water-cement ratio, slump, and homogeneity.

The revolving-drum truck bodies of approved make shall be used for

transporting the concrete. The numbers of revolutions at mixing speed, during

transportation, and prior to discharge shall be specified and agreed upon.

Reliable counters shall be used on revolving-drum truck units. Standard mixer

uniformity tests, conforming to ASTM standards C 94-69 “Standard

Specifications for Ready Mix Concrete”, shall be carried out to determine

whether mixing is being accomplished satisfactorily.

11.21.5 Pumping of concrete:

Only approved pumping equipment, in good working condition, shall be used for

pumping of concrete. Concrete shall be pumped through a combination of rigid

pipe and heavy-duty flexible hose of approved size and make. The couplings

used to connect both rigid and flexible pipe sections shall be adequate in

strength to withstand handling loads during erection of pipe system,

misalignment, and poor support along the lines. They should be nominally rated

for at least 3.5 MPa pressure and greater for rising runs over 30 m. Couplings

Technical Specification Page 90 of 94 July 2007

Page 94: Technical Specification

MMOPL Tender TW Series 1000

should be designed to allow replacement of any section without moving other

pipe sections, and should provide full cross section with no construction or

crevices to disrupt the smooth flow of concrete.

All necessary accessories such as curved sections of rigid pipe, swivel joints

and rotary distributors, pin and gate valves to prevent backflow in the pipe line,

switch valves to direct the flow into another pipe line, connection devices to fill

forms from the bottom up, extra strong couplings for vertical runs, transitions for

connecting different sizes of pipe, air vents for downhill pumping, clean-out

equipment etc, shall be provided as and where required. Suitable power

controlled booms or specialized crane shall be used for supporting the pipe line.

11.21.6 Field control:

Sampling at both truck discharge and point of final placement shall be employed

to determine if any changes in the slump and other significant mix characteristics

occur. However, for determining strength and durability of concrete, cubes shall

be taken from the placement end of line. The temperature of concrete shall be

recorded at regular intervals.

11.21.7 Planning:

Proper planning of concrete supply, pump locations, line layout, placing

sequence, and the entire pumping operation shall be made and got approved.

The pump should be as near the placing area as practicable, and the entire

surrounding area shall have adequate bearing strength to support concrete

delivery pipes. Lines from pump to the placing area should be laid out with a

minimum of bends. For large placing areas, alternate lines should be installed

for rapid connection when required. Standby power and pumping equipment

should be provided to replace initial equipment, should breakdown occur. The

delivery pipes shall be covered with wet hessian cloth.

The placing rate should be estimated so that concrete can be ordered at an

appropriate delivery rate.

As a final check, the pump should be started and operated without concrete to

be certain that all moving parts are operating properly. A grout mortar should be

pumped into the lines to provide lubrication for the concrete, but this mortar shall

not be used in the placement. When the form is nearly full, and there is enough

concrete in the line to complete the placement the pump shall be stopped and a

go-devil inserted and shall be forced through the line by water under pressure to

clean it out. The go-devil should be stopped at a safe distance from the end of

Technical Specification Page 91 of 94 July 2007

Page 95: Technical Specification

MMOPL Tender TW Series 1000

the line so that the water in the line will not spill into the placement area. At the

end of placing operation, the line shall be cleaned in the reverse direction.

11.22 Additional Specifications for Concrete M60

11.22.1 Mineral admixture in the form of micro silica or condensed silica fume if required

shall be permitted in the design mix. It shall comply with ASTM C 1240

“Specifications for Silica Fume for use in Hydraulic Cement Concrete and

Mortar”. It shall be obtained from proven and reliable manufacturer/supplier to

the satisfaction of the Employer’s Representative.

11.22.2 Adequate and complete dispersal of the micro silica during the concrete mixing

shall be ensured.

11.22.3 When micro silica is used in powder form the Contractor shall take all

precautions against potential health hazards during handling of the material.

11.22.4 Chilled water and/ or ice shall be used in the concrete mix depending on the

ambient temperature, dimensions of the concrete element, rate of pouring and

design mix constituents.

11.22.5 Special profuse curing arrangements shall be made for dissipation of the heat of

hydration. The water curing shall be continued for a period of 21 days.

11.22.6 The concrete design mix and arrangement for mixing, transportation, and curing

of concrete shall be subject to the approval of the Employer’s Representative.

11.22.7 The concrete temperature shall be recorded for 21 days from the time of

placement of concrete.

11.23 Measurement

11.23.1 Measurement shall be made for the finished volume of reinforced cement

concrete (excluding lean concrete) only. All linear dimensions shall be measured

correct to 1cm & restricted to design dimensions, and the volume calculation will

be correct to two decimal places in cubic meter.

11.23.2 No deduction shall be made for volume of steel / sheaths embedded in concrete

or for voids not exceeding 0.03 cum in volume.

Technical Specification Page 92 of 94 July 2007

Page 96: Technical Specification

MMOPL Tender TW Series 1000

Curing Tank

( 10.0 x 2.0 )

Concrete Mixer ( Ribbon Type )

Store

20.0

Typical Layout of Proposed Concrete Laboratory

Main Gate

ANNEXURE - I

Aggregate Storage Bins( 6.0 x 2.0 )

EPMCEngineer

MMOPL Engineer

Contractor QC Engineer

Computer Room

300 T CTM Digital with computer

Control

AC Room for Cement Testing and RCPT

Toilet

Wor

king

Plat

form

100 T CTMDigital

RCPT Equipment

DIN Apparatus

Working Platform

Pantry

Lab

Tech

nici

ans

3.0 3.0 2.0 12.0

3.0

3.0

3.0

3.0

3.0

4.0

11.0

8.0

Working space for casting Concrete Cubes

22.0

16.0

4.0

2.0

3.0

3.0

Sink

Sink

Note: The dimensions shown above for the concrete laboratory are tentative and the Contractor may be asked to accommodate the concrete laboratory in a smaller area as per availability at Site.

Technical Specification Page 93 of 94 July 2007

Page 97: Technical Specification

MMOPL Tender TW Series 1000

12. REINFORCEMENT

Any steel specified for reinforcement shall conform in every respect to the latest

relevant Indian Standard Specifications and shall be of tested quality under the

ISI Certification Scheme.

All reinforcement work shall be executed in conformity with the drawings

supplied and instructions given by the Employer’s Representative and shall

generally be carried out in accordance with the relevant Indian Standard

Specifications IS: 2502- Bending and Fixing of Bars for Concrete

Reinforcement.

The reinforcement steel shall be from primary producers and not re-rolled steel

shall be supplied.

12.1 Inspection & Testing:

12.1.1 Every bar shall be inspected before assembling on the works and any

defective, brittle, rusted or burnt bars shall be removed. Cracked ends of bars

shall be cut out.

12.1.2 Reinforcement steel shall be fresh, free from corrosion. Corroded steel will not

be incorporated in work. If there are traces of corrosion, then the Contractor

have to give the following treatment to steel for which nothing extra shall be

paid.

Cleaning of steel by wire brush for removal of dust and rust.

Apply one coat of cement slurry {1 kg cement + 600 cc of

inhibitor solution (patent No. 109784/67)} by dipping or brushing. Allow it to

dry for 24 hours in shade. The water is not to be used. The inhibitor

solution is prepared in ionized water.

Apply second coat of cement slurry (same as above). Allow

it to dry in shade.

12.1.3 No work shall be commenced without the Employer’s Representative

approval of the bar bending schedule.

12.1.4 Manufacturer's Certificate shall be supplied for each lot of supply.

12.1.5 Specimens sufficient for three Tensile Tests for each different size of bar for

each consignment delivered shall be sampled and tested by the Contractor.

Batches shall be rejected if the average results of each batch are not in

accordance with the specifications.

Technical Specification Page 94 of 94 July 2007

Page 98: Technical Specification

MMOPL Tender TW Series 1000

12.2 Bar bending and Bar Bending Schedule:

All bars will be carefully and accurately bent by approved means in accordance

with IS: 2502, and relevant drawings. It shall be ensured that depth of crank is

correct as per the bar cutting and bending schedule and bent bars are not

straightened for use in any manner that will injure the material.

Prior to starting bar bending work, the Contractor shall prepare bar bending

schedule from the structural drawings supplied to him and get the same

approved by Employer’s Representative. Any discrepancies and inaccuracies

found by the Contractor in the drawings shall be immediately reported to the

Employer’s Representative whose interpretation and decision there to, shall be

accepted.

12.3 Lapping & Welding:

12.3.1 As far as possible bars of the maximum length available shall be used. Laps

shown on drawings or otherwise specified by the Employer’s Representative will

be based on the use by the Contractor of bars of maximum length. Payment for

reinforcement shall be made only for reinforcement shown in such drawings and

such laps. In case the Contractor wishes to use shorter bars, laps shall be

provided at the Contractor cost in the manner and at the locations approved by

the Employer’s Representative.

12.3.2 Bars having butt or lap welds shall be provided as specified in the drawings or

as instructed by the Employer’s Representative.

12.4 Spacing, Supporting and Cleaning:

12.4.1 All reinforcement shall be placed and maintained in the positions shown on

the drawings.

12.4.2 The Contractor shall provide approved types of supports for maintaining the

bars in position and ensuring required spacing and correct cover of concrete to

the reinforcement as specified on the drawings. Cover blocks of required shape

and size, M.S. Chairs and spacer bars shall be used to ensure accurate

positioning of reinforcement.

12.4.3 Bars must be cleaned, before concreting commences, of all scale, rust or

partially set concrete which may have been deposited there during placing of

previous lift of concrete.

12.4.4 Only TMT bars shall be provided.

12.4.5 G.I. wire shall be used for binding reinforcement and their ends to be bent

towards the centre of element.

Technical Specification Page 95 of 94 July 2007

Page 99: Technical Specification

MMOPL Tender TW Series 1000

12.5 Welding:

12.5.1 Wherever specified all lap and butt welding of bars shall be carried in

accordance with IS: 2571. Only qualified welders shall be permitted to carry out

such welding.

12.5.2 For cold twisted reinforcement welding operations must be controlled to

prevent a supply of large amounts of heat larger than that can be dissipated.

The extreme non twisted end portion shall be cut off before welding. Electrodes

with rutile coating should be used.

12.5.3 Bars shall be free from rust at the joints to be welded.

12.5.4 Slag produced in welding after alternative run should be chipped and removed

by brush.

12.5.5 Electrode should not be lighted by touching the hot bar.

12.5.6 The welding procedure shall be approved by the Employer’s Representative

and tests shall be made to prove the soundness of the welded connection.

12.6 Measurement:

The measurement shall be done in MT on the basis of standard weight.

Payment for reinforcement shall be made only for reinforcement shown in

drawings and laps as per Clause 11.3.1 Payments shall not be made for

reinforcement bars used for lifting, hooks, handling, chairs, spacers etc., as cost

of which shall be deemed to be included in item rate.

Technical Specification Page 96 of 94 July 2007

Page 100: Technical Specification

MMOPL Tender TW Series 1000

13. FORMWORK

13.1 These specifications shall be read in conjunction with the CPWD

specifications 1996, MOST Specifications and other relevant specifications

described in the clause 6.2.3 of these specifications.

13.2 Materials:

Formwork shall be of steel or any other suitable material as approved by the

Employer’s Representative. The formwork shall be capable of resisting damage

to the contact faces under normal conditions of erecting forms, fixing steel and

placing concrete. The selection of materials suitable for formwork shall be made

by the Contractor based on the quality consistent with the specified finishes and

safety.

All formwork supports (centering, props, scaffolds etc.) shall only be in structural

steel and preferably of pipes conforming to IS:806, IS:1161, IS:1239, IS:2750.

Wooden ballies shall not be permitted as props/formwork supports. All props

shall be properly braced using x & k bracings.

Steel formwork shall be made of minimum 4 mm thick black sheets

stiffened with angle iron frame made out of M.S. angles 40 mm x 40mm x 6

mm supported at suitable spacing.

13.3 Design & Drawings:

The formwork, falsework, jigs, fixtures and supports etc. shall be designed by

the Contractor and approved by the Employer’s Representative before starting

of work. It shall be constructed so that the concrete can be properly placed and

thoroughly compacted to obtain the required shape, position and level subject to

specified tolerances Approval of the proposed formwork by the Employer’s

Representative will not diminish the Contractor responsibility for the satisfactory

performance of the formwork, nor for the safety and co-ordination of all

operations.

Methodology for removal of form should be planned as a part of total form work

design.

13.4 Erection of Formwork:

The following shall apply to all formwork:

Technical Specification Page 97 of 94 July 2007

Page 101: Technical Specification

MMOPL Tender TW Series 1000

13.4.1 The Contractor shall obtain the approval of the Employer’s Representative for

the design of forms and the type of material used before fabricating the forms.

(Ref. ACI 347 Formwork for Concrete or equivalent I.S. Code).

13.4.2 Provision shall be made for adjustment of supporting struts where necessary.

When reinforcement passes through the formwork care should be taken to

ensure close fitting joints against the steel bars so as to avoid loss of fines

during the compaction of concrete.

13.4.3 Formwork shall be so arranged as to permit removal of forms without jarring

the concrete. Wedges, clamps and bolts shall be used wherever practicable

instead of nails.

13.4.4 Surfaces of forms in contact with concrete shall be oiled with a mould oil of

approved quality or clean diesel oil. If required by the Employer’s

Representative the Contractor shall execute different parts of the work with

different mould oils to enable the Employer’s Representative to select the most

suitable. The use of oil which results in blemishes of the surface of the concrete

shall not be allowed. Oil shall be applied before reinforcement has been placed

and care shall be taken that no oil comes in contact with the reinforcement while

it is being placed in position. The formwork shall be kept thoroughly wet during

concreting and the whole time that it is left in place. Nothing extra shall be paid

to Contractor for oiling.

13.4.5 Immediately before concreting is commenced, the formwork shall be carefully

examined to ensure the following:

Removal of all dirt, shavings, sawdust and other refuse by brushing and

washing.

The tightness of joints between panels of sheathing and between these

and any hardened core.

The correct location of tie bars, bracing and spacers, and especially

connections of bracing.

That all wedges are secured and firm in position.

That provision is made for traffic on formwork not to bear directly on

reinforcing steel.

13.5 Concrete Finishes:

This section deals with the surface of concrete on which forms had been fixed

while concreting.

In the event of finishing not being definitely specified herein or in the drawings,

finishes to be adopted shall be as directed by the Employer’s Representative.

Technical Specification Page 98 of 94 July 2007

Page 102: Technical Specification

MMOPL Tender TW Series 1000

Completed concrete surface shall be tested, where necessary to determine

whether surface irregularities are within the limits specified hereinafter.

Surface irregularities are classified as "Abrupt" or "Gradual". Offsets caused by

displaced or misplaced form sheathing, or form sections or by loose knots or

otherwise defective timber form will be considered as abrupt irregularities, and

shall be tested by direct measurements. All other irregularities shall be

considered as gradual irregularities and will be tested by use of template,

consisting of a straight edge or the equivalent thereof for curved surfaces. The

length of the template shall be 150 cm for testing of formed surfaces and 300

cm for testing of unformed surfaces.

The finish for plinth shall be manufactured in a skilful, workmanlike manner,

accurately to dimensions. There should be no visible offsets, bulges or

misalignment of concrete. At construction joints, the forms shall be rightly set

and securely anchored close to the joint. Abrupt and gradual irregularities shall

not exceed 3mm. Irregularities exceeding this limit shall be reduced by grinding

to a level of 1:20 ratio of height to length. Jute bag subbing or sand blasting

shall not be used.

The top of plinth shall be a trowelled finish and shall be used for tops of

parapets, etc prominently exposed to view. When the floated surface has

hardened sufficiently, steel trowelling shall be started. Steel trowelling on

hardened, floated surface shall be performed with firm pressure to produce a

dense uniform surface free from blemishes and trowel marks and having slightly

glossy appearance. Surface irregularities shall not exceed 5mm.

13.6 Exposed Concrete Work:

Exposed concrete surfaces shall be smooth and even, originally as stripped

without any finishing or rendering. Where directed by the Employer’s

Representative, the surface shall be rubbed with carborundum stone

immediately on striking the forms. The Contractor shall exercise special care

and supervision of formwork and concreting to ensure that the cast members

are made true to their sizes, shapes and positions and to produce the surface

patterns desired. No honeycombing shall be allowed. Honeycombed parts of the

concrete shall be removed by the Contractor as directed by the Employer’s

Representative and fresh concrete placed without extra cost, as instructed by

Technical Specification Page 99 of 94 July 2007

Page 103: Technical Specification

MMOPL Tender TW Series 1000

the Employer’s Representative. All materials, sizes and layouts of formwork

including the locations for their joints shall have prior approval of the Employer’s

Representative.

13.7 Age of Concrete at Removal of Formwork:

In accordance with CPWD Specifications 96 or IS:456. The Employer’s

Representative may vary the periods specified if he considers it necessary.

Immediately after the forms are removed, they shall be cleaned with a jet of

water and a soft brush.

13.8 Reuse of Forms:

The Contractor shall not be permitted reuse of timber facing formwork brought

new on the works more than 5 times for exposed concrete formwork and 8 times

for ordinary formwork. 5 or 8 uses shall be permitted only if forms are properly

cared for, stored and repaired after each use. The Employer’s Representative

may in his absolute discretion order rejection of any forms he considers unfit for

use for a particular item irrespective of no of items the shuttering has been used

and order removal from the site of any forms he considers unfit for use in the

Works. Used forms brought on the site will be allowed proportionately fewer

uses as decided by the Employer’s Representative. Use of different quality

boards or the use of old and new boards in the same formwork shall not be

allowed. If any other type of special or proprietary form work is used, the no. of

times they can be used will be determined by the Employer’s Representative.

Technical Specification Page 100 of 94 July 2007