Technical Referee Report - Domestic Builder Limited to …...(Carpentry) registration application...

7
1/7 TECHNICAL REFEREE REPORT DOMESTIC BUILDER LIMITED (CARPENTRY) This report must be completed by the referee and accompanies the Domestic Builder Limited (Carpentry) registration application form. To be a referee you should be a registered Domestic Builder Limited (Carpentry) or be registered in the class of building work for which the applicant is applying. You must have directly supervised the applicant carrying out the work listed in the reference. Use this form to tell us about domestic building work that the applicant carried out under your supervision. The VBA uses your referee report to help determine whether an applicant should be registered as a building practitioner. We may contact you to confirm the information in this reference. PART A ABOUT YOU (THE TECHNICAL REFEREE) Title: Mr Mrs Ms Miss Other_____________________________ First name Middle name Surname Date of birth / / Your registration number Your contact number If you are not a registered building practitioner, were you the applicant’s: Site supervisor Construction manager Your email address PART B EMPLOYER DETAILS Name of company that employed the applicant during supervision period ABN Address Street no. and name Suburb State Postcode Employer contact number Employer email address

Transcript of Technical Referee Report - Domestic Builder Limited to …...(Carpentry) registration application...

Page 1: Technical Referee Report - Domestic Builder Limited to …...(Carpentry) registration application form. To be a referee you should be a registered Domestic Builder Limited (Carpentry)

1/7

TECHNICAL REFEREE REPORT

DOMESTIC BUILDER LIMITED (CARPENTRY)

This report must be completed by the referee and accompanies the Domestic Builder Limited (Carpentry) registration application form.

To be a referee you should be a registered Domestic Builder Limited (Carpentry) or be registered in the class of building work for which the applicant is applying. You must have directly supervised the applicant carrying out the work listed in the reference.

Use this form to tell us about domestic building work that the applicant carried out under your supervision.

The VBA uses your referee report to help determine whether an applicant should be registered as a building practitioner. We may contact you to confirm the information in this reference.

PART A

ABOUT YOU (THE TECHNICAL REFEREE)Title: ☐Mr ☐Mrs ☐Ms ☐Miss ☐Other_____________________________First name Middle name Surname Date of birth

/ /

Your registration number Your contact number

If you are not a registered building practitioner, were you the applicant’s: ☐ Site supervisor ☐ Construction manager

Your email address

PART B

EMPLOYER DETAILSName of company that employed the applicant during supervision period

ABN

Address Street no. and name Suburb State Postcode

Employer contact number Employer email address

Page 2: Technical Referee Report - Domestic Builder Limited to …...(Carpentry) registration application form. To be a referee you should be a registered Domestic Builder Limited (Carpentry)

2/7 SD

Do mestic Builder Limited (Carpentry) - Technical Referee Report SD-TRR-028 V1.1

PART C

APPLICANT DETAILS (FOR WHOM YOU ARE PROVIDING THIS REPORT)First name Surname

PART D

EXPERIENCE Supervised building experience (for up to three projects) Please complete detail for the applicant’s domestic building project experience that you supervised.

Applicant’s role (e.g. Project manager, Supervisor,

Subcontractor, or other)

Period of supervision: From – To (mm/yyyy)

Project site address From To

Project 1

Project 2

Project 3

0BExplanation of terms

Please indicate the components of building work relevant to Domestic Builder Limited (Carpentry) that the applicant either assisted, carried out or managed under your supervision (may be one project only).

Did the applicant assist, or manage any of the following components of building work per project?

Component of building workProject 1 Project 2 Project 3

Assisted Managed Assisted Managed Assisted Managed

Prel

imin

ary

Area of Experience (AoE) 1 - Apply for a building permit for the work

Determined requirement for building permit ☐ ☐ ☐ ☐ ☐ ☐

Obtained building permit/approvals from other authorities ☐ ☐ ☐ ☐ ☐ ☐

Continue over page

Assisted Is when the applicant has assisted a competent and qualified practitioner in the carrying out of a particular component of building work.

Carried out The actual hands-on carrying out of building work. It refers to when the applicant has been solely responsible for that component of building work.

Managed The management of building work. It refers to when the applicant was not involved in the actual carrying out of that component other than engaging a competent practitioner to do so; however, they as the manager/supervisor were responsible for the quality and compliance of that component of work.

/ - /

/ - /

/ - /

Page 3: Technical Referee Report - Domestic Builder Limited to …...(Carpentry) registration application form. To be a referee you should be a registered Domestic Builder Limited (Carpentry)

3/7 SD

Do mestic Builder Limited (Carpentry) - Technical Referee Report SD-TRR-028 V1.1

Did the applicant assist or manage any of the following components of building work per project?

Component of building workProject 1 Project 2 Project 3

Assisted Managed Assisted Managed Assisted Managed

Prel

imin

ary

wor

k co

ntin

ued

Area of Experience (AoE) 2 - Apply for a building permit for the work

Prepared contracts for the building work ☐ ☐ ☐ ☐ ☐ ☐

Administered appropriate contracts for the building project ☐ ☐ ☐ ☐ ☐ ☐

Managed contract variations and defects ☐ ☐ ☐ ☐ ☐ ☐

Arranged / attended mandatory inspections ☐ ☐ ☐ ☐ ☐ ☐

Completed handover including certificates of compliance ☐ ☐ ☐ ☐ ☐ ☐

Managed the building work from start to finish ☐ ☐ ☐ ☐ ☐ ☐

Area of Experience (AoE) 3 - Produce cost estimates and apply business financial management skills

Conducted business and financial aspects for projects ☐ ☐ ☐ ☐ ☐ ☐

Prepared cost estimates and quotations for project/part of project ☐ ☐ ☐ ☐ ☐ ☐

Area of Experience (AoE) 4 - Co-ordinate onsite construction works

Site

supe

rvisi

on

Developed and monitored progress schedules for the work ☐ ☐ ☐ ☐ ☐ ☐

Provided on-site day to day supervision of the project ☐ ☐ ☐ ☐ ☐ ☐

Supervised subcontractors/trades to ensure work is conducted safely & to standard ☐ ☐ ☐ ☐ ☐ ☐

Area of Experience (AoE) 5 - Ensure works are planned and conducted safely

Managed site safety throughout the project ☐ ☐ ☐ ☐ ☐ ☐

Did the applicant assist, carry out, or manage any of the following components of building work per project?

Component of building work

Project 1 Project 2 Project 3 Assisted Carried

out Managed Assisted Carried

out Managed Assisted Carried

out Managed

Pre

-bas

e w

ork Area of Experience (AoE) 6 - Domestic Building work that the applicant carried out

Interpreted architectural plans, drawings and specifications ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Interpreted engineering designs, plans, drawings and specifications ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Page 4: Technical Referee Report - Domestic Builder Limited to …...(Carpentry) registration application form. To be a referee you should be a registered Domestic Builder Limited (Carpentry)

4/7 SD

Do mestic Builder Limited (Carpentry) - Technical Referee Report SD-TRR-028 V1.1

Did the applicant assist, carry out, or manage any of the following components of building work per project?

Component of building work

Project 1 Project 2 Project 3 Assisted Carried

out Managed Assisted Carried

out Managed Assisted Carried

out Managed

Pre

-bas

e w

ork

cont

inue

d

Area of Experience (AoE) 6 – cont. Domestic Building work that the applicant carried out

Carried out excavation work ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Established the construction site ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Provided protection works for the adjoining property ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Set out the site for construction/carpentry work ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Base

wor

k

Constructed retaining walls ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Constructed stump and pad footing systems ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Constructed sub-floor framing ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed bored piers ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed screw piles ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Constructed formwork for concrete slabs on-ground ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Constructed formwork for concrete suspended slabs ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed concrete reinforcement ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed damp-proofing ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed termite protection ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Fram

e w

ork

Constructed wall framing – stick build ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Constructed wall framing - prefabricated ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed structural steel elements ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Constructed roof framing – stick build ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Constructed roof framing - prefabricated truss ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Page 5: Technical Referee Report - Domestic Builder Limited to …...(Carpentry) registration application form. To be a referee you should be a registered Domestic Builder Limited (Carpentry)

5/7 SD

Do mestic Builder Limited (Carpentry) - Technical Referee Report SD-TRR-028 V1.1

Did the applicant assist, carry out, or manage any of the following components of building work per project?

Component of building work

Project 1 Project 2 Project 3 Assisted Carried

out Managed Assisted Carried

out Managed Assisted Carried

out Managed

Fram

e w

ork

cont

inue

d

Area of Experience (AoE) 6 – cont. Domestic Building work that the applicant carried out

Selected and installed bracings/fixings ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Constructed fire rated party walls ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Constructed and erected metal wall frames and roof frames ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed sheet flooring, plywood flooring, waterproof cement sheet flooring ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Straightened internal walls ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Lock

-up

wor

k

Installed windows and doors including appropriate flashings ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed insulation ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Internal/external services rough-in ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Constructed eaves framing and installation of eaves lining ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed timber weatherboard or other external cladding ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Fix

wor

k

Selected and installed waterproofing ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed architraves and skirtings ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Constructed cabinets and components on site ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed cabinets and joinery ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Manufactured, assembled and installed internal stairs ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Oth

er w

ork

Constructed external decks with sub-floor framing ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Constructed fences and gates ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Landscaped – including structural landscaping work ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Page 6: Technical Referee Report - Domestic Builder Limited to …...(Carpentry) registration application form. To be a referee you should be a registered Domestic Builder Limited (Carpentry)

6/7 SD

Do mestic Builder Limited (Carpentry) - Technical Referee Report SD-TRR-028 V1.1

Did the applicant assist, carry out, or manage any of the following components of building work per project?

Component of building work

Project 1 Project 2 Project 3 Assisted Carried

out Managed Assisted Carried

out Managed Assisted Carried

out Managed

Oth

er w

ork

cont

inue

d

Area of Experience (AoE) 6 – cont. Domestic Building work that the applicant carried out Demolished an existing bathroom, kitchen or laundry ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed fixtures such as baths, shower bases, spas ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed wall and ceiling linings, including wet area lining ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Selected and applied appropriate waterproofing systems ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Altered window and/or door openings ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed joinery for basins, sinks, troughs ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Installed shower screens and mirrors ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Constructed swimming pool or safety barriers and/or other gates and fences ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐

Continue over page

Page 7: Technical Referee Report - Domestic Builder Limited to …...(Carpentry) registration application form. To be a referee you should be a registered Domestic Builder Limited (Carpentry)

7/7 SD

Do mestic Builder Limited (Carpentry) - Technical Referee Report End of form

PART E

REFEREE DECLARATIONThe information provided in this form must be true and correct. It is an offence under section 246 of the Building Act 1993 to give false or misleading information in relation to an application for registration, and this offence carries a maximum penalty of 120 penalty units.

To see how the VBA uses and discloses your personal information view the full VBA Privacy Policy.

☐ I declare that the information contained in this form is true and correct to the best of my knowledge.

☐ I understand that the VBA may make enquiries to verify the information I have provided, and I consent for thisinformation to be shared with any other third party for that purpose.

Referee name

Referee signature: Date of signature:

/ /(must be handwritten)