TECHNICAL NOTE 1 FLOOD RISK & DRAINAGE · TECHNICAL NOTE 1 FLOOD RISK & DRAINAGE Project Park Farm,...
Transcript of TECHNICAL NOTE 1 FLOOD RISK & DRAINAGE · TECHNICAL NOTE 1 FLOOD RISK & DRAINAGE Project Park Farm,...
TECHNICAL NOTE 1
FLOOD RISK & DRAINAGE
Project Park Farm, Blyth
Document
Number PFB-BWB-EWE-XX-RP-YE-0001_Drainage Technical Note BWB Ref BMW-2322-TN1
Author Catherine Thorpe Status S2
Checked Ben Fleming Revision P01
Approved Ben Fleming Date 30/05/2018
1
INTRODUCTION
Summary Information
This Flood Risk & Drainage Report summarises a desktop study into the possible sources of flood risk to
a potential development site located at Park Farm, Blyth. It has been prepared on behalf of Planit
Planning and Development to advise on the development potential of the site from a flood risk and
drainage perspective.
This report is based on readily available information, and has not included consultation with the
Environment Agency or other flood risk consultees.
A summary of pre-mitigation sources of flood risk is available as Table 1.1.
Table 1.1– Pre-Mitigation Sources of Flood Risk
Flood Source Potential Risk
Description High Medium Low None
Fluvial X
The site is in Flood Zone 1: land
defined as being at low risk of
river/sea flooding.
Canals X The nearest canal is approximately
5km from the site.
Groundwater X
The site is not thought to be
susceptible to ground water
flooding.
Reservoirs and
waterbodies X
The site is located 0.5km away from
the nearest identified reservoir flood
risk area.
Pluvial runoff X
Surface water mapping does not
identify any risk zones within or near
to the site.
Sewers X
Due to the local topography, sewer
flooding is unlikely to pose a risk to
the site.
Site Details
The site is in Blyth, Nottinghamshire, and accessed off the Worksop Road (B6045). A site location plan
is included as Figure 1.1.
The site is bound to the north and east by east by agricultural fields and paddocks, the Worksop Road
to the south and agricultural buildings to the west.
TECHNICAL NOTE 1 FLOOD RISK & DRAINAGE
2
Figure 1.1 – Site Location Plan
Relevant Policy and Guidance
Strategic Flood Assessment
The Strategic Flood Risk Assessment for North Nottinghamshire1 has been reviewed in the production
of this report. The SFRA provides information specific to the site location in the form of fluvial, surface
water and groundwater flood risk mapping, as well as records of historic flooding. The SFRA does not
make specific reference to Blyth.
Preliminary Flood Risk Assessment
The Nottinghamshire Preliminary Flood Risk Assessment2 was completed as a high-level screening
exercise to identify areas of significant flood risk within the county. The local area of Blyth is located
within a region above the flood risk threshold.
1 Bassetlaw District Council Strategic Flood Risk Assessment, July 2009 2 Nottinghamshire Preliminary Flood Risk Assessment, June 2011
TECHNICAL NOTE 1 FLOOD RISK & DRAINAGE
3
SOURCES OF FLOOD RISK
Fluvial Flood Risk
Flood Zones
The Flood Map for Planning has been prepared by the Environment Agency. This identifies areas
potentially at risk of fluvial of tidal sources. An extract of the mapping is included as Figure 2.1. The
Environment Agency Flood Map for Planning shows the site to be located entirely within Flood Zone 1
(Low Probability). This Flood Zone is defined in the National Planning Policy Framework (NPPF) as land
assessed as having less than a 1 in 1000 annual probability of river or sea flooding in any year.
Figure 2.1 - Environment Agency Flood Map for Planning (Rivers and Sea)
Watercourses
The nearest Main River is the River Ryton however, as shown in Figure 1, this does not pose a significant
risk to the site.
There are no further watercourses near the study site.
TECHNICAL NOTE 1 FLOOD RISK & DRAINAGE
4
Canal Flood Risk
The nearest canal is the Chesterfield Canal which is over 5km from the site and therefore does not
pose a significant risk.
Reservoir Failure Flood Risk
Reservoir failure has been prepared by the Environment Agency. This shows the largest area that
might be flooded if a reservoir were to fail and release the water it holds. This map displays a worst-
case scenario and is only intended as a guide. An extract of the mapping is included as Figure 2.2.
Figure 2.2- Risk of Reservoir Flooding Mapping
The site is located approximately 0.5km from the closest inundation area from reservoir failure/breach.
It is therefore considered to not pose a significant risk to the site.
Surface Water Flood Risk
Surface water (pluvial) flooding can occur during prolonged or intense storm events when the
infiltration potential of soils and/or the capacity of drainage infrastructure is overwhelmed, leading to
the accumulation of surface water and generation of overland flow routes.
TECHNICAL NOTE 1 FLOOD RISK & DRAINAGE
5
Risk of surface water flood mapping has been prepared by the Environment Agency. This shows the
potential flooding which could occur when rainwater does not drain away through the normal
drainage systems or soak into the ground, but lies on or flows over the ground instead. An extract of
the mapping is included as Figure 2.3.
Figure 2.3 - Environment Agency Surface Water Flood Risk Map
The mapping does not identify any areas within the site or in its immediate vicinity at risk from pluvial
flooding.
Groundwater Flood Risk
Online British Geological Survey (BGS) geological mapping shows the geology of the site to comprise
of the Chester Formation (sandstone, pebbly) with no superficial deposits. The soil is reported to be
freely draining and sandy in texture.
There is no groundwater flood risk to Blyth identified within the SFRA.
Sewer Flood Risk
Sewer assets near the site are owned and maintained by Severn Trent. Sewer asset plans are included
for reference in Appendix 1.
TECHNICAL NOTE 1 FLOOD RISK & DRAINAGE
6
There is a 150mm diameter foul sewer running along the Worksop Road in an easterly direction and
the storm water sewer runs in a northerly direction along the High Street.
Due to the topography of the surrounding ground, the absence of overland flow routes and the flow
direction of the sewers, sewer flooding is determined to pose a low risk to the development site.
TECHNICAL NOTE 1 FLOOD RISK & DRAINAGE
7
SURFACE WATER DRAINAGE
Drainage Requirements
The Lead Local Flood Authority (LLFA) as statutory consultees have a duty to ensure that surface water
flood risk is not increased because of the development.
The LLFA does not have any specific SuDS guidance to inform planning applications and in the
absence of further information, the Non-Statutory Technical Standards for Sustainable Drainage
Systems3 (as published by DEFRA) should be utilised to inform a drainage strategy.
If discharging to an existing sewer or drain, evidence will be required to demonstrate that the owner
of the sewer or drain (sewerage undertaker for sewers, highways authority for highway drains, or
private owner) has accepted the point and rate of discharge, and that there is capacity to
accommodate these flows. The owner may request improvements to the sewer or drain, or for
discharge rates to be reduced below the Greenfield rate or other rate agreed by the LLFA.
If discharging to the wider network, surface water attenuation will be required at the site so that water
can be stored and released at a controlled rate. Storage volumes should be designed so that the 100-
year storm can be accommodated within the site, including a 40% allowance for climate change.
Source control measures should be implemented as far as possible with the appropriate levels of water
treatment provided prior to water leaving the site.
Drainage Hierarchy & Potential Storm Water Drainage Strategy
The drainage hierarchy outlined in statutory guidance states that surface water should be discharged
from development sites to a receptor in the following order of preference:
(i) Soakaway/infiltration; or
(ii) Local watercourse; or
(iii) Sewer network.
In view of the underlying ground conditions, it is likely that the existing building drains via infiltration
because there are no localised watercourses near the site or an adjacent surface water sewer.
It is therefore considered that infiltration can provide a solution to the disposal of surface water from
the proposed development. Conducting future soakaway tests would confirm that the site is suitable
for disposal of surface water via infiltration. It should be noted that the proposed conversion would
result in a reduction in the area of current built development (through the introduction of garden
green space) and subsequently there would be a decrease in surface water runoff generated.
Based upon an assumed impermeable area of 0.08ha (30% of the total site area) approximately 38m³
of soakaway storage would be required to accommodate the 1 in 100 year + 40% climate change
scenario. This could be achieved using a 13m x 8m x 0.4m storage crate with an assumed 95% void
ratio. This is a conservative estimate based upon an assumed permeability of 1x10-5m/s. There is room
within the proposed layout (Appendix 2) to locate this crate within the green space of the
development.
In the unlikely event that infiltration is proved unviable for the site, and in the absence of any
appropriate local watercourses, there is the option to attenuate surface water from the proposed
3 Non- Statutory Technical Standards for Sustainable Drainage Systems, DEFRA, 2015
TECHNICAL NOTE 1 FLOOD RISK & DRAINAGE
8
development within the grounds of the new properties before discharging at a controlled rate to the
storm water sewer to the east the site.
A Developer Enquiry submitted to Severn Trent would confirm capacity within the surface water sewer,
or alternatively highlight any required improvement works necessary to accommodate surface water
flows from the proposed development.
TECHNICAL NOTE 1 FLOOD RISK & DRAINAGE
9
CONCLUSIONS & RECOMMENDATIONS
BWB Consulting have been instructed by Planit Planning and Development to undertake a desk-based
appraisal to advise on the development from a flood risk and drainage perspective. The identified
risks are summarised within Table 5.1.
Table 0.1 - Summary of Flood Risk Mechanisms
Flood Source Risk Description
Fluvial The site is identified to fall within Flood Zone 1, land defined as being at low
risk of river/sea flooding.
Canals The Chesterfield Canal is more than 5km from the site, therefore does not
pose a risk to the site.
Groundwater
In view of the underlying conditions, groundwater flooding is unlikely. If
groundwater is encountered during the construction phase, it is
recommended that an appropriately qualified groundwater contractor is
employed, and the appropriate mitigation measures are employed.
Reservoirs
and
waterbodies
The site is located approximately 0.5km from the closest inundation area from
reservoir failure/breach. It is therefore considered to not pose a risk to the site.
Pluvial runoff The site is not shown to be at risk from pluvial runoff.
Sewers Sewer flood risk is determined to be low.
This summary should be read in conjunction with BWB’s full report. It reflects an assessment of
the desk-based information available to BWB at the time of production.
The proposed method of drainage is soakaways however, infiltration tests should be carried out to
confirm that this is a viable drainage option.
Surface water runoff from the development should be appropriately managed and designed up to
the 100-year storm event, including an 40% allowance for climate change. SuDS should be
incorporated within the development layout and provide a suitable level of on-site storage.
It is recommended that a Developer Enquiry should be submitted to Severn Trent to confirm whether
there is capacity within the local surface water, should soakaways not be viable, to accommodate
flows from the proposed development.
APPENDIX 1
Severn Trent Sewer Records
Abandoned Gravity Sewer
Private Combined Gravity Sewer
Private Foul Gravity SewerPrivate Surface Water Gravity SewerPublic Combined Gravity SewerPublic Foul Gravity SewerPublic Surface Water Gravity SewerTrunk Combined Gravity SewerTrunk Foul Use Gravity SewerTrunk Surface Water Gravity Sewer Combined Use Pressurised SewerFoul Use Pressurised SewerSurface Water Pressurised SewerHighway DrainCombined Lateral Drain (SS)Foul Lateral Drain (SS)Surface Water Lateral Drain (SS)
All Private Sewers are shown in magenta All section 104 sewers are shown in greenAll Sewers that have been transferred to Severn Trent Water after the 1st October 2011, but have not been surveyed and confirmed by Severn Trent Water are shown in orange
Culverted WatercourseCable, EarthingCable Junction
Cable, Optical Fibre/Instrumentation
Cable, Low Voltage
Cable, High VoltageCable, Other
Housing, Building
Housing, Kiosk
Disposal Site
Sewage Treatment Works
Housing, Other
Pipe Support Structure
Sewage Pumping Facility
Sewer Facility Connection Inlet / Outlet
Blind Shaft
Combined Use Manhole
Flushing Chamber
Foul Use Manhole
Grease Trap
Head Node
Hydrobrake
Lamphole
Outfall
Overflow
Penstock
Petrol Interceptor
Sewer Chemical Injection Point
Sewer Junction
Sewerage Air Valve
Sewerage Hatch Box Point
Sewerage Isolation Valve
Soakaway
Surface Water Manhole
Vent Column
Waste Water Storage
Pre-1937 Properties
MATERIALS- - NONEAC - ASBESTOS CEMENTBR - BRICKCC - CONCRETE BOX CULVERTCI - CAST IRONCO - CONCRETECSB - CONCRETE SEGMENTS (BOLTED)CSU - CONCRETE SEGMENTS (UNBOLTED)DI - DUCTILE IRONGRC - GLASS REINFORCED CONCRETEGRP - GLASS REINFORCED PLASTICMAC - MASONRY IN REGULAR COURSESMAR - MASONRY RANDOMLY COURSEDPE - POLYETHLENEPF - PITCHPP - POLYPROPYLENEPSC - PLASTIC STEEL COMPOSITEPVC - POLYVINYL CHLORIDERPM - REINFORCED PLASTIC MATRIXSI - SPUN (GREY) IRONST - STEELU - UNKNOWNVC - VITRIFIED CLAYXXX - OTHER
SHAPE PURPOSEC - CIRCULAR C - COMBINEDE - EGG SHAPED E - FINAL EFFLUENTO - OTHER F - FOULR - RECTANGLE L - SLUDGES - SQUARE S - SURFACE WATERT - TRAPEZOIDALU - UNKNOWN
CATEGORIESW - WEIRC - CASCADEDB - DAMBOARDSE - SIDE ENTRYFV - FLAP VALVEBD - BACK DROPS - SIPHONHD - HIGHWAY DRAINS104 - SECTION 104
Severn Trent Water LimitedAsset Data ManagementPO Box 5344CoventryCV3 9FTTelephone: 0845 601 6616
SEWER RECORDO/S Map scale:
Date of issue:
This map is centred upon:O / S Grid reference:
x :
y :
Disclaimer Statement:1. Do not scale off this Map.2. This map and any information supplied with it is furnished as a general guide, is only valid at the date of issue and no warranty as to its correctness is given or implied. In particular this Map and any information shown on it must not be relied upon in the event of any development or works (including but not limited to excavations) in the vicinity of Severn Trent Water’s assets or for the purposes of determining the suitability of a point of connection to the sewerage or distribution systems.3. On 1 October 2011 most private sewers and private lateral drains in Severn Trent Water's sewerage area, which were connected to a public sewer as at 1 July 2011, transferred to the ownership of Severn Trent Water and became public sewers and public lateral drains. A further transfer takes place on 1 October 2012 (date to be confirmed).Private pumping stations, which form part of these sewers or lateral drains, will transfer to the ownership of Severn Trent Water on or before 1 October 2016.Severn Trent Water does not possess complete records of these assets.These assets may not be displayed on this Map.4. Reproduction by permission of Ordnance Survey on behalf of HMSO. © Crown Copyright and database right 2004. All rights reserved. Ordnance Survey licence number 100018202. Document users other than Severn Trent Water business users are advised that this document is provided for reference purpose only and is subject to copyright, therefore, no further copies should be made from it.
21.05.18462464
386870
1:1250
APPENDIX 2
Proposed Site Layout
Scale on A3:
Checked by:
Drawn by:
Date:Project no:
Revisions The copyright of this drawing and design is vested in the Architects and must not be copied or reproduced without their written consent.All contractors must visit site and be responsible for taking and checking all necessary dimensions relative to this work.
Do not scale: Figured dimensions only to be used. If in doubt ASK
T: 01386 555 166 E: [email protected] W: www.poolephillips.co.ukRegistered No: 3820127
Drawing Number:Title:Project:
for
1 : 500
38011 Issue Date
JD
VAP102Class Q Conversion - Blyth
-
Existing Site Plan
No. Date Description
1 : 500
Site Plan - Proposed
North
VISUAL SCALE 1:500 @ A3
25m5m 20m15m10m0m