Technical Handbook

79
Precast Construction Handbook www. ƟltliŌ.com.au T : 1300 845 854 (Australiawide) MARCH 2012 The Precast & Tilt-Up Experts

description

Tilt-up

Transcript of Technical Handbook

Page 1: Technical Handbook

Precast Construction Handbook

www. ltli .com.au T : 1300 845 854 (Australia‐wide) 

MARCH  2012 

The Precast & Tilt-Up Experts

Page 2: Technical Handbook

1

March 2012 

The Precast & Tilt-Up Experts Company Profile 

Tilt Lift Equipment (TLE) is a proud pioneer in the introduction of tilt-up precast concrete technology into Australia. During the 1970’s Brian Hilbert, a registered builder, sought a solution to Australia's growing shortage of bricklayers. Aware of new methods in concrete panel construction being implemented overseas, Mr Hilbert began importing the necessary materials and developing the expertise to introduce this new form of concrete panel construction into the Victorian building industry. Established in 1981, Tilt Lift has expanded rapidly and today is one of the country’s few national suppliers, providing the precast and tilt-up industries with a complete service from start to finish. With offices in Victoria, Queensland, New South Wales and Western Australia TLE offers a personalised service that incorporates in-house engineering & drafting, custom designed bracing, and a comprehensive product range (including brace hire) Australia-wide. Tilt Lift stocks over 5000 product lines including SRB’s Aluminium Formwork System, and is an authorized distributor of Powers Fasteners products, and is the exclusive distributor of Dayton Superior’s range including the reputable J-6 bond breaker. Tilt Lift supplies and manufactures exclusively many of the precast and tilt-up industries’ most innovative products. This product range is backed by providing our customers with a personalised service that includes quick and efficient project quoting and, where required, complementary certified lifting and bracing designs by qualified Professional Engineers. Tilt Lift is an active industry participant in practical and technical matters relating to precast concrete construction in all forms. TLE is a member of NPCAA (National Precast Concrete Association Australia), TCA (Tilt-Up Concrete Association - USA). We also contribute on technical matters via CIA (Concrete Institute Australia), the Code Committee for AS3850 Prefabricated Concrete Elements, AEFAC (Australian Engineered Fasteners & Anchor Certification), fib (International Federation for Structural Concrete - Europe), and PCI (Precast/Prestressed Concrete Institute - USA). TLE provides customers with the ease of dealing with one supplier from engineering and shop drawings through to finished product. With over 30 years of experience, our team will ensure that your next project is managed and supplied with the best products and engineered lifting & bracing solutions available in Australia. Our customers range from small to medium size contractors through to many of Australia’s largest construction companies.

PRECAST & TILT‐UP ACCESSORIES     ~     LIFTING & BRACING ACCESSORIES     ~     ENGINEERING & DESIGN 

Cover image, top right : Apartment pool at Newstead Qld for Torre Developments

  WHAT’S  NEW?        WHAT’S  NEW?        WHAT’S  NEW?        WHAT’S  NEW? Tilt Li  Equipment (TLE) is commi ed to innova on and developing improved products and service for industry needs. In this March 2012  issue of the Precast Construc on Handbook  ‐ marking 30 years of TLE opera on ‐ you will find NEW informa on about : 

Expanded reference to Precast, Civil and Tilt‐Up industries throughout, and the Na onal Code of Prac ce (p7). 

New 3t P‐82 Olive  Edge Li  Anchor (p26) 

New Threaded Bar systems including new TB Couplers and Ø12 TB Star Ferrule (p51).  Note that this Handbook is intended to be an introductory reference for Tilt Li  informa on as relevant to construc on and design personnel.  It is not and cannot be an exhaus ve text for all that is required for specific projects.  We look forward to your enquiry about your next project and offering a total solu on from Tilt Li ! 

Page 3: Technical Handbook

2

March 2012 

The Precast & Tilt-Up Experts

TABLE  OF  CONTENTS 

Safety Informa on  3 

General & Technical Informa on  4 

Panel‐Erec on Problem Areas  6 

Li  & Brace :   Erec on Engineering  7 

Li  & Brace :   Panel Erec on Informa on  8 

Li  & Brace :   Rigging Set‐up  11 

Li  & Brace :   Strongbacks  13 

Li  & Brace :   T‐75 Emergency Li ing Plate  14 

Li  & Brace :   T‐14 Precast Panel Brace  15 

Li  & Brace :   Knee, Lateral & End Bracing  17 

Li  & Brace :   Corner Bracing  19 

Li  & Brace :   Brace Capacity Charts  20 

Li  & Brace :   Bracing Inserts  24 

Li  & Brace :   B‐14 Coil Bolts  25 

Precast :   P‐82 Olive  Edge Li  Anchor System  26 

Precast :   P‐833 Ring Clutch  30 

Precast :   How to use the Olive  Edge Li  Anchor and Void Former  32 

Civil :   P‐53 Eye Anchor, Tension Bar  33 

Civil :   P‐52 Foot Anchor  35 

Civil :   How to use the Foot Anchor Void Former  38 

Civil :   P‐50 Universal Li ing Eye  40 

Civil :   How to use the P‐50 Universal Li ing Eye  41 

Civil :   P‐51 Li ing Eye  42 

Tilt‐Up :   T‐41 Ground Release Insert  43 

Tilt‐Up :   How to remove the Ground Release Recess Plug  44 

Tilt‐Up :   T‐43‐R Ground Release Li ing hardware  45 

Tilt‐Up :   How to use the Ground Release System  46 

Tilt‐Up :   T‐42 Double Ground Release System  47 

Tilt‐Up :   T‐52 Edge Li  Anchor  48 

Connec ons :   Metric Ferrules ‐ Round & Star  49 

Connec ons :   Threaded Bar & TB Couplers  51 

Connec ons :   TB Star Ferrules  52 

Appendix A J‐6 Sure Li  Bond Breaker—Tech Data Sheet & MSDS J‐6WB Sure Li  Water‐based Bond Breaker—Tech Data Sheet & MSDS 

55 

Contents 

Page 4: Technical Handbook

3

March 2012 

The Precast & Tilt-Up Experts Safety Informa on 

Safety nota ons used in this publica ons:  1.  DANGER  ‐  Indicates immediate hazard that will result 

in severe personal injury, death or property damage. 2.  WARNING  ‐  Indicates  immediate  hazard  that  could 

result  in  severe  personal  injury,  death  or  property damage. 

3.  CAUTION  ‐  Indicates a hazard or unsafe prac ce that could  result  in  minor  personal  injury  or  property damage. 

  

Tilt Li  Equipment products are intended for use by trained, qualified and experienced personnel only.  Misuse or lack of supervision  and  inspec on  can  contribute  to  serious accidents or death.  Any applica on other than those shown in this Handbook should be carefully field tested before use.   The user of Tilt  Li  Equipment products must evaluate  the product  applica on,  determine  the  correct  working  loads and  control  all  field  condi ons  to  prevent  applica ons  of loads  in excess of the Working Load Limit.   Safety factors as shown are approximate.  Working Load Limits must never be exceeded.  

Shop or Field Welding  Welding  of  lt‐up  accessories  can  be  hazardous.    Knowledge  of materials,  heat  treatment  and welding  procedures  is necessary for proper welding.  Consult your local welding supply dealer for assistance in determining the required welding procedures.  DO NOT WELD TO ANY CASTING unless approved by a qualified metallurgical engineer.   Welding  to  iron cas ngs causes carbides and extreme bri leness near the weld point and destroys most of the cas ng's load value.  Since we cannot control either the workmanship or condi ons under which this work is done, Tilt Li  Equipment cannot be responsible for any product altered in the field by 

Interchangeability Many of the products that Tilt Li  Equipment manufactures and supplies are designed as a system for li ing and bracing of lt‐up panels.  Tilt Li  Equipment cannot be certain that the components from systems supplied by other manufacturers are 

completely  interchangeable with components supplied by Tilt Li  Equipment.   Used properly and  in accordance with our Handbook instruc ons, Tilt Li  Equipment products have proven to be among the best designed and safest in the industry.  Used  improperly, or with  components  supplied by other manufacturers,  the  li ing or bracing  system may be  rendered unsafe. NEVER MIX COMPONENTS from different WLL‐rated systems unless specified by Tilt Li  Equipment. Tilt Li  Equipment reserves the right to alter product designs, dimensions and Working Load Limits  at any  me.  

Worn Working Parts  For safety,  lt‐up accessories must be properly used and maintained.   The  li ing hardware units shown  in this handbook may be subject to wear, overloading, corrosion, deforma on, inten onal altera on and other factors which may affect the hardware's Working Load Limit.   All hardware units must be  inspected regularly by the user to determine  if they may be used at the rated Working Load Limit or removed from service.  The frequency of inspec on depends upon factors such as frequency of use, period of use and environment.  It shall be the responsibility of the user to set up a schedule to inspect li ing hardware units for wear and to discard the parts when excessive wear is noted.  

Falling panels, bracing or hardware can cause severe injury or death.

Read, understand and follow the information and instructions in this Handbook before using any Tilt Lift Equipment accessory.

When in doubt about the proper use or installation of any Tilt Lift Equipment accessory, immediately contact the nearest Tilt Lift Equipment office for clar-

ification.

WARNING

PRECAST & TILT‐UP  CONSTRUCTION (PTUC)  HANDBOOK 

Page 5: Technical Handbook

4

March 2012 

The Precast & Tilt-Up Experts

Number of Inserts  To simplify calcula ons, inserts for  lt–up panels may be selected according to the following criteria:  Face  Li ing: Panel weight with suc on  forces added, divided by number of  inserts must not exceed the  inserts’ Working Load Limit shown in this manual.  Edge Li ing: 65% of panel weight mul plied by the suc on coefficient divided by the number of inserts must not exceed the edge li ers’ shear Working Load Limit. Also panel weight divided by the number of inserts must not exceed the Working Load Limit of the insert.  Impact Loading: Typically the impact loading of a panel is 20% higher then the panel’s dead weight.  Note that the impact loading may be significantly higher  if the panel  is to be “walked” to  its posi on.   Engineers should take this  into account when designing the li  for a panel like this.  Suc on Load: AS3850 states that a MINIMUM suc on load of 50% should be used when li ing off from a concrete cas ng bed.   Note: The impact and suc on loads are not cumula ve.   Usually, more than the above considera ons are required in order to not to overstress the panel.

General & Technical Informa on 

Engineering Services  Many of the products used for successful construc on with precast concrete require competent engineering input for each specific  applica on  and  project.    The Na onal  Code  of  Prac ce  for  Precast,  Tilt‐Up  and  Concrete  Elements  in  Building Construc on  and  current Workplace Health &  Safety  legisla on places  significant  safety‐based obliga ons on designers, manufacturers, suppliers and  installers of precast concrete and accessory products.   Addi onal engineering guidance and requirements are detailed  in AS3850.   Tilt Li  Equipment employs Professional Engineers  to do engineering and provide engineering service to customers, par cularly with regard to safe li ing and bracing of precast and  lt‐up elements.  Tilt  Li   also  contributes  at  industry  and  technical  levels  via  Na onal  Precast  Concrete  Associa on  Australia,  Concrete Ins tute Australia, Standards Australia and others.  TLE services Include: 

Consulta on / Recommenda ons 

Panel Li ing & Erec on Details 

Bracing Requirements 

Addi onal li ing reinforcement, if required 

Strongback requirements, if required 

Page 6: Technical Handbook

5

March 2012 

The Precast & Tilt-Up Experts General & Technical Informa on 

Safety Factors   Tilt  Li   Equipment  recommends  the  following minimum  safety  factors  iden fied  by  AS3850.  Tilt‐up  construc on may require addi onal safety considera ons. Many field condi ons may warrant higher safety factors, eg. adhesion of the panel to  the  cas ng  surface,  jerking  the  crane  during  li ,  inadequate  crane  size,  improper  handling  of  an  erected  panel, transpor ng an erected panel over rough surfaces, exceeding boom capacity, etc.  The minimum safety factors listed below should be adjusted accordingly when any of the above condi ons are known to exist.          Tilt‐Up Wall Braces      2 to 1         Cast‐in Brace Anchors     2.5 to 1         Li ing Inserts       2.5 to 1         Reusable Li ing Hardware    5 to 1  If a higher factor of safety to the one shown is required for any reason then the allowable working load must be changed accordingly by the user.  The following equa on can be used the alter the allowable working load.  The Working Load Limit published in this handbook should never be exceeded. 

Load WorkingNewSafety ofFactor Required

Safety ofFactor Published WLL

Safety Notes and Product Applica on:  All  Working  Load  Limits  shown  in  this  publica on  were established with the following factors considered:   1. All  products  are  in  new  or  "as  new"  condi on.    The Working Load Limit is considered the greatest load that will be applied to a product.   2. Inserts are correctly embedded in sound concrete and are firmly bolted or wired in place so that the ver cal axis of the inserts is perpendicular to the li ing surface.   3. Concrete compressive strength (fcm) at  me of  ini al  li  is at least the strength listed in the insert selec on chart for the insert being used.   4. Bolted hardware has full bearing on the concrete surface, and a achment bolts bear fully on the hardware.  5.  Cau on  must  be  taken  so  that  the  hardware  is  not subjected  to  a  side  loading  that  will  cause  an  addi onal, unintended loading.    

6. Erec on and a achment bolts are the proper  length and are well  ghtened  to  prevent  hardware  slippage  and  bolt bending.   7.  Coil  bolts  have minimum  coil  penetra on  through  the insert coil, but are not bearing on concrete at the bo om of the void.   8.  Inserts are properly  located  in rela on to edges, corners and  openings,  and  are  at  distances  that  permit  the development of a full shear cone. Minimum edge distances are noted throughout this publica on.   9. No field welding  to  the  li ing  inserts or  li ing hardware has taken place. Welding may cause bri leness and result in premature  failure.   Since Tilt Li  Equipment cannot control field  condi ons  or  field  workmanship,  Tilt  Li   Equipment does  not  guarantee  any  product  altered  in  any way  a er leaving the factory.  

Page 7: Technical Handbook

6

March 2012 

The Precast & Tilt-Up Experts Panel‐Erec on Problem Areas 

Field Condi ons, Equipment & Panel Sizes  Become  familiar with field condi ons and equipment available  for  the  lt‐up project.   Actual crane capacity depends on crane loca on, panel weight and the panel’s centre of li .  For rigging and li ing efficiency, Tilt Li  Equipment recommends that for panel heights < 7.5 m panel widths should be < 10.5 m.  For panel heights > 7.5 m widths should be < 6.0m. 

Panel Openings  Posi on  openings  in  the  centre  of  the  panel.    If  this  is  not possible, maintain a 600mm leg of concrete.  Less than 600mm of concrete will usually require a strongback. 

Foo ng Heights  When  foo ng  heights  vary,  always  keep  the  bo om  of  the  panel horizontal. (See Fig.1) Avoid panel designs  similar  to figures 2 &  3. Designs  such  as  these will require strongbacks and/or special handling to prevent panel twis ng and spalling. 

Headers  Avoid  panel  designs  that  have large  centre  of  gravity  shi s.  If  a header  is  required,  the  example on  the  right  is  the  preferred design. 

Page 8: Technical Handbook

7

March 2012 

The Precast & Tilt-Up Experts Erec on Engineering 

Erec on Design Engineer & Bracing  The Na onal Code of Prac ce  for Precast, Tilt‐Up  and Concrete  Elements  in Building Construc on  (NCoP)  is  now  the  peak regulatory document governing design and construc on prac ce for precast and  lt‐up in  Australia.    It  supplements  the  technical provisions  of  AS3850  Prefabricated Concrete  Elements.   Tilt Li  can assist with any  enquiries  about  these  industry guidance resources.   An essen al direc on of the NCoP is se ng the  standard  for  engaging  adequate engineering  input  for  construc ng  with precast concrete.   The  role of  the  required Erec on  Design  Engineer  (EDE)  is  detailed and  includes  responsibility  for  correct applica on  of  engineering  controls  for  the li ing  and  bracing  of  precast  panels  and other elements.   Tilt  Li   is an ac ve member of  the NPCAA (Na onal  Precast  Concrete  Associa on Australia) which has published this ar cle at right  in  its  quarterly  magazine  Na onal Precaster No.63 (Feb 2012).  The mandated role  of  the  EDE  in  rela on  to  the engineering  of  bracing  solu ons  and systems  is  clear.    Tilt  Li   can  supply  all engineering  support  for  approval  by  the EDE  including  fully  compliant  braces  and accessories.   

Page 9: Technical Handbook

8

March 2012 

The Precast & Tilt-Up Experts Panel Erec on Informa on 

Rigging and the Crane  

General The most important phase during the construc on of a  lt up building is the erec on of the wall panels. It is extremely important for the designers and 

contractors to plan and replan this por on of the job. They should direct their efforts to ensure that this important phase of construc on is performed safely and efficiently. Since there must be a close, coopera ve rela onship between the panel contractor and the erec on subcontractor, it is advisable to select an erec on sub–contractor during the early days of the project. The erec on sub–contractor and crew should be well experienced in  lt–up, as pan‐el  l ng and handling is a very specialised skill. 

Prior To Construc on 

  Prior to the actual start of construc on, an inspec on of the site should be made by the contractor. The loca on of the job site may be such that special permits will be required to gain access to the site for heavy equipment such as the crane. These projects are usually built in residen al areas where weight and size restric ons may exist. 

  It is advisable for the contractor to inves gate restric ons on early daily start–up  mes. Many areas have noise abatement and dust control regu‐la ons. Also, the panel contractor and erec on contractor should walk the site and determine a suitable loca on for the crane assembly and rigging make–up. Some local governments will not allow this ac vity on public streets. It is also advisable that any problems with uneven terrain be noted at this  me and dealt with prior to bringing the crane onto the jobsite. 

The panel contractor and the erec on contractor should always agree on a loca on for both the crane entrance onto the floor slab as well as the exit ramp off the floor slab. If necessary, plans should be made to thicken the floor slab at these ramp loca ons so the crane weight will not damage the edge of the slab. 

Underground tunnels, trenches and sewer lines are a very common occurrence and can create problems. It is necessary to know the loca on of these un‐derground hazards and to avoid those that may need strengthening in order to support the crane's weight. We have o en found that the loca on of these underground hazards is not always noted on the architect/engineer's plans. Further inves ga on by the panel contractor should be made in an effort to discover these types of unknown hazards. 

Overhead electric or telephone wires can be a common problem on both urban and rural job sites. It may be necessary to shut off the power in some over‐head wires in order to safely operate the crane during panel erec on. Safety regula ons dictate that cranes will keep a minimum distance from power‐lines. 

The quality of the floor slab on a  lt–up project cannot be over emphasized due to the heavy weights that the slab will be expected to support early in its life. Equally as important as the slab, is the sub–base under the floor slab. When it comes to suppor ng the combined weight of the crane and  lted panel, the floor slab is no be er than its sub–base. Even a thick, properly engineered floor slab with two layers of reinforcing steel will not support the weight of the crane if the sub base is unstable. 

To insure an efficient construc on procedure, careful considera on must be given to the cas ng loca on of the panels. The following two important criteria must be met if the contractor expects to have a successful project: 

Panels must be located for efficient CASTING.  

Panels must be located for efficient and safe LIFTING. 

The panel contractor should work with the erec on subcontractor in developing the panel cas ng layout. The erector's advice should be sought so that the panels are cast in such a posi on that a properly sized crane can safely reach and erect them. 

Crane selec on should not be looked on as merely rou ne. General rules for sizing the crane state that the crane capacity should be a minimum of two to three  mes that of the heaviest panel including the weight of the rigging gear. However, in the final analysis not only the panel weight, but also the crane's posi on rela ve to the panel must be considered. The following ques ons must be answered before final determina on of crane size can be es‐tablished:   

How far must the crane reach to li  the panel? 

How far will the crane have to reach to set the panel? 

Crane Cer fica on  The crane that is finally selected for the project should be property cer fied. In addi on too the commonwealth standards many, if not all states have 

standards with which erec on sub–contractors must comply. Prudent contractors make certain they have available at the jobsite documenta on a es ng to the crane's cer fica on. The contractor should also obtain a cer ficate of liability insurance from the erec on sub–contractor. 

Site Inspec on  A er the panels are cast and cured, the panel contractor, erec on sub–contractor, and the accessory supplier should again walk the site. The terrain 

upon which the crane will travel should be inspected and any further correc ons noted. Correc ve ac ons shall be taken prior to erec on of the panels. Entrance and exit ramps should be checked. The entrance ramp should be built up so the crane descends slightly down onto the slab instead of crawl‐

ing up onto it. The exit ramp should be built in the same manner. On some buildings, architectural openings are large enough for the crane to exit. In any case, do not let the crane's weight bear at the extreme edge of the slab. This is of par cular importance if the crane is walking out with the added weight of the closure panel. 

Page 10: Technical Handbook

9

March 2012 

The Precast & Tilt-Up Experts

Equipment & Crew  The panel contractor and the erec on contractor must itemise the rigging and equipment that will be needed for a prop‐

er and safe li . This booklet contains specifica on on rigging  configura on and cable lengths, please note that occasionally the li ing design engineer will specify a different set off cable lengths for a par cular panel or set off panels. These details should be rigidly adhered to, since they are an integral part of the erec on stress calcula ons.  TILT–LIFT EQUIPMENT DOES NOT SPECIFY THE DIAMETER OR SAFE WORKING LOAD OF THE CABLE as this is the responsi‐

bility of the erec on contractor. The panel contractor should also make a list of required tools. The list should include, but not be limited to, correct number of li ing clutches, expansion bolts, a compressor, drills, wrenches, ladders and mis‐cellaneous hand tools.  

It is also prudent to an cipate material needs for last minute repairs. If a delay is caused for any reason, down  me can add up rapidly.  The panel contractor should provide a clean working area with all obstacles removed. Members of the erec on crew will 

be guiding a panel while it is being moved from the cas ng loca on to its posi on in the structure. Most of the  me these crew members will be looking up at the rigging and inserts. They should not be tripping over loose debris and tools. 

The erec on contractor's minimum crew should consist of the crane operator, rigger foreman, and two qualified riggers. This crew should be augmented, as required, by carpenters and labourers from the panel contractor's work force, primarily to handle braces. In areas of the country where no erec on contractors are available, the minimum crew should consist of crane operator, qualified foreman and four to five labourers. An excep on to this would be with stacked panels which re‐quire an addi onal two to three labourers. Considera on should also be given to having a welder standing by. A properly staffed and well coordinated erection crew is the key to successful li ing. 

 The crane operator must be a qualified and experienced in handling  lt–up panels. He must be able to control three mo‐ons of his crane: hoist, swing and boom hoist. It is quite normal to use all three of these func ons simultaneously. 

Panel Erec on Informa on 

Day of Erec on  A safety mee ng with full crew should be held before any li ing starts. Personnel should be told to never place themselves under the 

panel while it is being  lted or on the blind side of the panel when the crane is travelling with it. The crew should be told to never get be‐tween the crane and the panel. A conscien ous erec on contractor will always advise his crew that horseplay or unnecessary talking will not be allowed.  A standard part of the safety mee ng, which is normally conducted by the rigger foreman, should contain comments about the need 

to remain alert. Each person's safety depends on the safe prac ces of others. The crew should be reminded that safety is everyone's re‐sponsibility and that hard hats, high visibility vest and any other personal protec on equipment that are required. It is advisable for the erec on contractor to create a safety check list and have the crew members sign it at the end of the safety mee ng. 

 The rigger foreman should be clearly iden fied at the safety mee ng. This individual will be the one the crane operator will be looking 

to for all signals. The rigger foreman must be experienced with handling panels and be totally familiar with the precise set of hand and arm signals. This will safely communicate his desires to the crane operator. Verbal instruc ons are all but impossible due to the noise level in the operator's cab.  A competent rigger foreman will create and maintain a confident atmosphere during the li . He will always remain alert to guard 

against overconfidence, and will not allow the crew to become careless.  During the safety mee ng the rigger foreman should demonstrate the proper use of the li ing hardware, bracing hardware and the 

proper way to hold a brace and how to use any necessary tools and equipment. If the crane is using rolling outriggers a warning to the crew to stay clear is in order. 

 The crew should be broken up into teams for handling bracing, rigging, and hardware a achment. Each individual's func on and re‐

sponsibility should be clearly defined. 

Page 11: Technical Handbook

10

March 2012 

The Precast & Tilt-Up Experts Panel Erec on Informa on 

The panel contractor should furnish an individual whose responsibility it is to clean the floor slab cas ng loca on as soon as the crane has li ed a panel 

and cleared the area. Regardless of how good a contractor's housekeeping is prior to the li , there is always a certain amount of debris le  behind. This 

individual should also make certain that all le over forming nails are pulled from the slab.    The rigging details furnished by Tilt‐Li  Equipment in the erec on instruc ons are not merely simple guidelines from which the erector can stray. THE RIGGING DETAILS DEFINE THE PROPER RIGGING FOR EACH PANEL FOR THE ERECTOR. Spreader bar widths and cable angles are integral parts of the erec on stress analysis. Proper cable lengths are important to the success of the li . The use of cables that are shorter than the prescribed length will increase stresses in the panel and could cause the panel to crack. If an erector has a problem with rigging details or cable lengths, as they are shown in the erec on instruc ons, he should not take it upon himself to change them. In‐stead, a call should be made to the technical service centre from which the erec on instruc ons originated. An alternate solu on may be worked out depending on the individual situa on. 

Extra precau ons should be taken when li ing panels with special shapes or special rigging. The erec on instruc ons should be consulted for CAU‐TIONARY NOTES as to how a panel might act during li ing, and to again verify the rigging and the insert loca ons. 

During the Li ‐  Precau ons 

Wind condi ons must be considered prior to li ing a panel. A 40 tonne panel will easily move in a slight breeze when hanging from a crane. All spectators should be kept well away from the li  and not allowed to interfere with the proceedings. 

Panels should be inspected prior to li ing for any reinforcing steel and/or ledgers that may be projec ng beyond the panel edges that will create interference when the panel is being plumbed next to a previously erected panel. This happens most o en at corners. 

A er all a achments are made to the panel, and as the rigging is being raised to take the slack out of the cables, but prior to ini al loading of the inserts, all rigging gear must be inspected for proper alignment and be free of snags. If non swivel type sheaves are used, make certain the sheaves are properly aligned. As cables are being tensioned, they invariably tend to twist and possibly rotate the li ing hardware causing side loading on the hardware. The rigger foreman should be alert for this condi on and if it does happen, SHOULD HALT THE LIFT AND REALIGN THE HARDWARE. 

It is the rigger foreman's responsibility to be alert to all obstacles in the path of the crane and crew. He should be alert for panels that may be stuck to the cas ng surface. Under such condi ons, loads transferred to the li ing inserts could be more than doubled causing possible insert failure. Carefully posi oned. pry bars and wedges can o en be successful in helping the crane release the panel from the cas ng surface. Any wedges that are applied to help release the panel should be posi oned at the insert lines. 

Braces are almost always a ached to the panel prior to li ing. Cau on must be taken to be certain the braces will not be trapped by the rigging when the panel is in the upright posi on. 

Plumbing the Panels— Precau ons 

Be alert when plumbing panels to their final upright posi on. Cau on must be taken to make certain the panel being plumbed does not strike a previously erected panel. All personnel should be cleared of those cri cal areas around a panel when plumbing is being done. If the panel being plumbed is a closure panel, measurements should be taken prior to li ing to make certain the panel will fit. 

Tilt–up  panels  should  be  as  plumb  as  possible  prior  to  a aching  the  brace  to  the  floor  a achment  anchor.  Temporary  out–of–plumb SHOULD NOT EXCEED 100 mm measured at the top of the panel.  It  is generally more prac cal to "fine tune" the panel plumbness with the pipe braces a er the li  is completed. 

There are two commonly occurring condi ons that dictate that the panels be braced perfectly plumb prior to releasing the crane: 

1 ) If the panel is going to support an adjacent spandrel or lintel panel, the suppor ng panel should be in an accurate final posi on to prevent having to adjust it later when it is suppor ng another panel. 

2) If the bracing design calls for a sub support system of knee, lateral, and end or cross bracing, then the panel should be accurately plumbed prior to a aching the sub support system. Panels requiring sub support systems must not be plumbed later as the brace sub sup‐port system, if not removed, must be at least loosened in order to adjust the main brace, thus placing the panel in a dangerous posi on. 

Bracing  Do not release the crane load if, for any reason, the bracing does not appear adequate. Crane loads should always be released slowly, keep‐

ing an eye on the panel and bracing for any unusual ac vity. For knee and lateral bracing it is desirable that all bracing components be com‐pletely installed before releasing the crane. That is, all knee, lateral, and end or cross bracing, if required, be in place. However, this is not al‐ways possible. You should always be able to install the knee bracing, however, the crane's posi on near the panel may prevent the lateral brac‐ing from being a ached. 

Once the crane is clear of the area, the panel contractor must complete the lateral and end or cross bracing. He must complete this phase of the bracing while remaining no more than one panel behind the erec on crew. All bracing should be completed on all erected panels at the end of the work day. 

Page 12: Technical Handbook

11

March 2012 

The Precast & Tilt-Up Experts

The following diagrams show various types of rigging configura ons, although a 3 row li  has been shown here, it is recom‐mended by both Tilt‐Li  Equipment and Australian Standards 3850 to be avoided whenever possible due to the complex rig‐ging that is involved; the difficultly in rigging these kind of panels can be seen in the diagram below. Unless otherwise speci‐fied on li ing design drawings, the following rigging configura ons should always be used. Contractors must always use cen‐tre pick style spreader beams, as shown in the diagrams, as well as sheaves as required. This is to ensure that all li ers are loaded equally and that the panel will correctly rotate as the panel is been li ed. This is par cularly important on panels where li ers have been offset from each other. The following rigging setups represents those setups which will be used most of the  me, very rarely for complicated panels the rigging setup may vary slightly, in these cases the li ing engineer will indicate the type of rigging on the li ing design drawing. For panels that are edge li ed the rigging setup is the same as for R‐11, R‐12 or R‐14. 

Rigging Set‐up 

Page 13: Technical Handbook

12

March 2012 

The Precast & Tilt-Up Experts

 Minimum sling lengths are also shown on the diagram below, although only 2 across setups have been shown below these lengths apply if the rigging setup is 1, 2, 4 or 8 across. Please note that the li ing design engineer may specify different length slings for any panel or any set panels and it is extremely important that those specifica ons are adhered to.  

It is important that both the correct rigging configura on and sling lengths are used when li ing  lt up panels. Failure do to so may result in li ers been unequally loaded, meaning that the panel may not rotate correctly and/or a li er may fail. Sling lengths are extremely important in calcula ng the stresses in a panel, as such the use of a sling that is too short will result in stresses that are higher then calculated and poten ally cause cracking of the panel during the li ing process. 

Page 14: Technical Handbook

13

March 2012 

The Precast & Tilt-Up Experts Strongbacks 

When large openings are required in panels, they will nor‐mally create extreme bending stresses in the remaining con‐crete sec ons. The purpose of strong backs is to increase the s ffness of the panel, thus reducing the bending stress‐es. Internal reinforcing steel can o en be used by applying normal reinforced concrete design techniques.  

Another efficient and economical method of strongbacking is external wood, aluminium or steel beams, as they provide greater sec on modulus to resist bending. A er a panel has been erected, the strongbacks are normally no longer re‐quired and may be removed and used on other panels.  

Tilt‐Li  Equipment’s technical Service Department will se‐lect the proper type of strong back insert, size and number of strongbacks as well as loca ons of strong‐ backs on jobs submi ed for detailing.  

Tilt‐Li  Equipment offices have RMD slim shores which are available for use as strongbacks, these have a capacity to withstand 36 kNm bending moment for those that are a complete unit and 18 kNm if two are joined together. They are available in 1.8 and 3.6 metres long, they can be joined together to make any combina on length of those sizes. Other sizes are available directly from RMD. The strong‐backs are bolt to the panels using T‐6‐A’s and 19mm coil bolts. 

The strongback‐shore system is used to reduce stresses during the li ing process and stabilize the panel during and a er erec on. Generally, this system should be u lized on panels where an offset opening is equal to or greater than 1/2 the panel width. The concrete leg sec on must be checked for stresses to determine if addi onal reinforcing steel or strong‐backs are needed.  

Strongback size should be of sufficient width and depth to car‐ry erec on loads and consist of material strong enough to withstand repeated use. The shore depth should be the same nominal size as the panel thickness, i.e., a 150 mm panel would require a 100mm x 150mm or 150mm x 150mm shore.  

Strongback ‐ Shore 

Page 15: Technical Handbook

14

March 2012 

The Precast & Tilt-Up Experts T–75 Emergency Li ing Plate 

The T–75 Emergency  Li ing Plate  is designed and  tested for  use  as  an  emergency  repair  li   plate  in  special  situa ons where a normal cast–in–place  lt–up face pickup insert is missing, pped over, improperly located or otherwise unusable.  

   The li  plate is to be installed so that it is centred over the original  insert  loca on. When the  li  plate cannot be  installed at the original insert loca on, contact Tilt–Li  Equipment.    When  installing  the T–75 Emergency Li ing plate, always check to make certain the  li ing  lug  is aligned  in the direc on of the cables. DO NOT apply loads at an angle to the flat side of the li ing lug!     The T–75 Emergency Li ing Plate  is to be a ached to the face of the precast concrete  lt–up wall panel using either four or six properly  installed Power Bolts. Bolts must be  ghtened  to a torque  of  160 Nm.  Ensure  appropriate  sized washers  are  used. Minimum edge distance from each of the anchor bolts is 240 mm. Edge distances of less than 240 mm may result in a reduced li ing capacity.   Using compressed air,  just before  installa on of the Pow‐erbolt, clean out all of the drilled holes. Failure to properly clean the holes may result in a reduced li  plate load carrying capacity.  

  To install the T–75 Emergency Li ing plate, set the plate in its proper posi on and mark the hole loca ons. Drill the required number of holes using a new 20 mm diameter carbide‐ pped drill bit.  

Insert the assembled Powerbolt, with square washer (65 x 65 x 5 mm,  hole  should  be  no  bigger  then  22 mm),  through  the holes  in  the  li  plate  into properly drilled and cleaned holes. Using a hammer, tap the  bolt all the way into the hole so that the washer and bolt head comes to rest on the top surface of the li  plate.     Tighten the Powerbolt using a torque wrench, the bolts must  ghtened to a torque of 160 Nm. Use the crane to place a  light  load onto  the  li  plate. Release  the  load and check all bolts to make certain they are s ll  ghtened to 160 Nm. Bolts that have a lower torque value will have a reduced load carry‐ing capacity.    The working load limits (WLL) of these power bolts and li  plate are shown below. The working  load  limits are deter‐mined by panel thickness and the number of powerbolts actu‐ally used to a ach the li  plate to the  lt–up panel. 

NOTE: Insert WLL’s are based on approximately a 2.5 to 1 fac‐tor of safety. Li  plate develops approximately a 5 to 1 factor of safety based on a maximum WLL of 5 ton.       The above WLL’s are based on the li ing plate being in‐stalled so that the raised li ing lug is aligned with the direc on of the li ing cables.     In order to develop the safe working loads of the T–75 Emergency  li ing  Plate,  the  normal  weight  concrete  in  the panel must have a ained a minimum compressive strength of 25 MPa. These safe working  loads assume that the Powerbolt have  been  properly  installed.  The  base  of  the  li   plate measures 16 mm x 305 mm x 305 mm and has six 30 mm di‐ameter holes drilled at 100 mm centres ver cally and 200 mm centres horizontally.  

Minimum 

Embedment Depth85 mm 100 mm

Maximum Drilled 

Hole Depth

Panel Thickness150 mm and 

greater

RBHN20108 

(20 mm x 108)

RBHN20133 

(20 mm x 133)Powerbolt Size

125 mm

100 mm 120 mm

Tennsion & Shear

Working Load Limit

6 Bolts(3 per side, 

RBHM20133)

4 Bolts1 in each corner 

(RBHM20108)

125 mm thick panel

Number of 

Powerbolts

5 tonne

3.5 tonne

Page 16: Technical Handbook

15

March 2012 

The Precast & Tilt-Up Experts T‐14 Precast Panel Brace 

The Tilt Li  Equipment Precast Panel Brace is a  me tested accessory which has become the standard in panel construc on. Its proper re‐la on of strength to weight permits ease of handling while providing a rugged brace which is easily adjusted.  In compliance with AS3850 and the Na onal Code of Prac ce for Precast, Tilt‐Up and Concrete Elements in Building Construc on (NCoP) each model of Tilt Li  brace has been test‐rated for load  / extension performance and carries an appropriate ra ng plate.  The panel brace is a ached to the panel before  l ng by means of a 19mm diameter coil bolt threaded into the brace anchor. When the panel is  lted into its final posi on, the floor bracket is normally bolted to the floor slab with a M20 x 133 powerbolt.  Good construc on prac ces dictate the use of a spring washer under the head of any coil bolts. A slo ed hole on the floor and wall base plate provides easy a achment and has raised stops to prevent the brace from sliding sideways once the coil bolts have been  ghtened. The slot on the standard brace foot is 20 mm wide, brace feet can be swap over with brace feet that have a slot that is 24mm wide, if a bolt that can gain a higher load is required. Both brackets remain flat at all  mes as pivo ng ac on is provided in both the floor and wall brackets.   A er the panel is  lted to the approximate ver cal posi on, Tilt Li  Equipment’s Panel Brace is used to align and hold the panel un l it is permanently anchored by further construc on.   The floor bracket of Tilt Li  Equipment’s pipe brace hardware is a ached to a 38 mm diameter threaded rod. This galvanised threaded rod has a 3.5 mm contour threads to the inch that are fast and non–clogging. A weld spot at the top of the threaded adjus ng rod pre‐vents accidental removal.   Tilt–Up braces are designed for use only in connec on with bracing  lt–up precast concrete construc on against wind loads. Due to the problems involved in bracing masonry walls,  Tilt–Li  Equipment assumes no responsibility if braces are used to support concrete block, brick or other masonry.  The telescoping pipe braces can be rough adjusted in increments of 150 mm by aligning the pin holes in the two pipes. Finer adjustments can be a ained by simply rota ng the en re pipe assembly clockwise or counter clockwise as required. Ease of rota on is guaranteed by the ball bearing coupler a ached to the pipe brace at the wall bracket. Due to circumstances beyond Tilt–Li  Equipment’s control maxi‐

mum brace lengths and styles may vary slightly from loca on to loca on. It is good construc on prac ce to consider the working length of pipe braces to be 150 mm more then mini‐mum length and 150 mm less then the maximum length. 

Shear Pin 

The various safety authori es around Australia vary in what they consider is an acceptable method to prevent the shear pin from accidental dislodgement. In some cases as risk analy‐sis may need to be carried out by the contractors to deter‐mine which method can be used. Tilt‐Li  Equipment recom‐mends the use of the lockable shear pin for bracings, these pins have a lock that can only be opened with a key. This method is currently accepted by all of the worksafe authori‐es and in our opinion is the safest of the currently available 

op ons.   Tilt‐Li  Equipment also has available the use of normal shear pins, that can be refrained using a variety of methods. Local contractors should contact there local worksafe authori es to find out which method is acceptable. The contractor should also carry out a risk assessment in accordance with OH&S guidelines and regula ons to see if this method is safe to use on any given worksite. Precau ons must also be taken to en‐sure that any nails or R‐clips do not become a safety hazard on site. 

Tilt–Li  Equipment Tilt–Up pipe braces are for the sole purpose of bracing the  lt–up panel in the fully erected posi on against wind loads only. Braces are not to be used as props in the support of concrete formwork, or panels that have an earth load applied too them, braces are not designed to sustain high dead loads.    Bracing anchors and braces are not designed to sustain impact loads. Precau on must be taken to arrange the panel erec on se‐quence so as to avoid the poten al for impac ng panels or braces. Bracing recommenda ons for other loads or forces that might be ap‐plied to brace anchors and braces are beyond the scope of Tilt–Li  Equipment. 

Telescoping Pipes

Adjusting Screw

Brace Foot

Shear PinDanger!See notes

Brace Foot

Ball Bearing Coupler

Page 17: Technical Handbook

16

March 2012 

The Precast & Tilt-Up Experts

T‐14 Precast Panel Brace 

Brace design must be carried out on each project to ensure that the braces being used will be within their Working Load Limit. Many fac‐tors need to be considered when calcula ng which brace is required. The “Whatever Length Will Fit” approach is not acceptable. If draw‐ings are not available showing bracing design Tilt‐Li  Equipment can provide such as service. 

The factors that need to be considered for each panel:  

•  Panel Area 

•  Wind Terrain Category of Project 

•  Design Wind Speed 

•  Height of Panel 

•  Centre of Surface Area of the Panel 

•  Angle of Brace 

•  Length of Brace 

•  Number of Braces per Panel 

•  Floor Height/ Deadmen Height 

Danger! Bracing must be installed 90°  ± 5° to plane of panel or brace safe working load will be greatly reduced. 

Danger! For safety, and unless specifically designed otherwise, all braces must be installed at least 600 mm above the panels centre of gravity. Brace loca‐ons other than those shown may reduce the braces SWL dras cally. Brace angles over 60° from the horizontal result in poor mechanical advantage and 

excessive ver cal kick, while brace angles under 50° decrease brace buckling strength due to greater length and excessive sag.  

  Without knee brace means that brace type can be adjusted for various lengths of "B" shown, and brace may be used without knee, lateral or end bracing.       With knee brace means that brace type can be adjusted for various lengths of "B" shown and requires the use of knee, lateral and end bracing to obtain the WLL. “B” = Brace Length 

Brace Anchor Loca on  The loca on of both brace anchors is cri cal in determining the loads that are applied to any brace system. Shop drawings will most of me will show the loca on of the wall panel cast in brace point. 

However just as important as the loca on of this point is the loca on of the floor brace point. This will normally be indicated on the draw‐ing or perhaps another engineering sheet. On Tilt‐Li  Equipment bracing designs it is located in the lower le  corner known as the “F” measurement. In our experience this measurement is overlooked by many panel erectors. This measurement is important because it de‐termines three things: 1. The brace load 2. The brace length  3. The load that is been applied to floor brace anchor.    If this brace point is too close the panel it will increase the brace load as well as the tension load applied to the floor brace point. Possible taking either one beyond their working load limit, too far away from the panel increases the brace length, as the brace gets long‐er it also reduces its working load limit, once again it could poten ally take the applied load beyond its working limit. As such the distance out should always be remember when bol ng down the braces. Floor brace loca ons should always be within 150mm of the distance out shown by the appropriate engineering drawing. The braces must always be within 5 degrees of perpendicular of the panel, as shown in the plan view drawing above. 

Page 18: Technical Handbook

17

March 2012 

The Precast & Tilt-Up Experts

WARNING! IT IS COMMON TO REFER TO THE SECONDARY BRACING SUPPORT SYSTEM OF THE MAIN PIPE BRACES AS KNEE BRACING. HOWEVER,  THE USER  IS  TO  BE  AWARE  THAT WHEN  KNEE  BRACING  IS  REQUIRED,  IT MEANS  THAT  LATERAL BRACING  AND  END  BRACING MUST  ALSO  BE  INCLUDED.  THIS  SECONDARY  BRACING  SUPPORT  SYSTEM  IS  NEEDED  TO REDUCE THE BUCKLING LENGTH OF THE MAIN PIPE BRACES AND MUST HAVE FIRM CONNECTIONS AT ALL POINTS. BOTH THE KNEE BRACE AND THE END BRACE MUST BE CONNECTED AT ITS BOTTOM END. 

Knee, Lateral and End Bracing 

In order to properly strengthen the main pipe brace, knee bracing, lateral bracing and end must be installed at the midpoint of the main pipe brace. All these components are cri cal for the brace to develop its full working load. Tilt‐li  Equipment designates its sec‐ondary bracing system as K1 or K2, K1 represents a B1 to be used as the knee brace while K2 means a B2 is used. K0 means that  no knee, lateral or end bracing is required. 

Knee Bracing  The knee brace is a B1 or B2 pipe brace with a Knee Bracket A ached. The knee brace must be installed inline with the main brace (looking at the face of the panel). Looking at the bracing from the side the knee brace must be installed at a 90º ±15º to the main brace (see diagram to right). Foot should be bolted to panel with a T–6–A, Ferrule or expansion bolt, such as the M20 power bolt. 

Lateral Bracing  All  mber connec ons must be 100 x 50 F8 seasoned  mber (with a minimum joint group of JD3)*, that is free of all cracks, splits and oth‐er defects.   Lateral bracing should be a ached to the knee brace bracket with two nails 3.75 x 50. (Preferably duplex nails so they are easier to re‐move). Each nail should be 20 mm from the edge of the  mber.  Overlapping sec ons of  mber in the lateral bracing must overlap by a minimum of 500 mm. 4 nails 3.75 x 100 should be used to nail the two sec ons of lateral bracing together. Each nail must 100 mm apart and the last nail must 100 mm from the end of the  mber.  *Any type of seasoned  mber can be used for lateral bracing on the condi on it is listed as JD1, JD2 or JD3 in Australian Standards AS 1702.2 and has a stress grade of at least F8.  Distance between each brace when running lateral bracing between them should be no more then 2 meters. If the distance is over two meters then an end brace should be installed on each of those braces.  Scaffolding pipe connected to the main brace with the appropriate size swivel couplers is an acceptable alterna ve to mber lateral brac‐ing, the end bracing must s ll be installed as per specifica ons. All lateral bracing must be supplied by contractor. 

Page 19: Technical Handbook

18

March 2012 

The Precast & Tilt-Up Experts End Bracing 

The end bracing is the same as the Knee bracing a B1, B2 or mini brace is used with a knee bracket a ached to one end of the end brace. The knee bracket is installed around the main brace , the other end of the end brace is bolted to either the ground or if there is a corner panel it can be bolted to the corner panel. Looking at the face of the panel the end brace must be installed between 30º to 90º to the main brace. Looking from above, the end bracing should be at 90º ± 15º. End bracing must be installed every 35 meters and at each end of the lateral bracing to prevent lateral movement and to provide total brace stability. 

Note: End braces to ground and/or cross braces must be installed eve‐ry 35 meters and at the ends of lateral bracing to prevent lateral movement of braces and to provide total brace stability.  

Warning! Main pipe braces must installed 90° ± 5° to plane of panel or brace safe working load will be dras cally reduced. Panel stability may be jeopardised when braces are skewed. 

Danger! Tilt–Up braces are designed to resist a specific wind load only. Do not remove or release any part of the brace sup‐port system un l the panel has been permanently anchored. Premature removal of bracing may result in a panel falling with serious injury or death to workers in the vicinity of the job site. 

Danger! A er winds of 7m/s (25 km/h) or more have been experienced at the job site, the  lt–up contractor must check the ghtness of the bolts that secure the wall and foot plates to the concrete. Re ghtening of such bolts to the proper torque 

will assure that the pipe braces are secure. 

Using a  73 mm diameter rounded U–bolts (Thread M12). A ach a small piece a 350 long piece of 50 x 100 F8 Timber to the braces at the height specified in the diagram le .   Then nail the cross bracing members to these small pieces of  mbers using two 3.75 x 100 nails. Nails must be at least 20 mm from the edge of the  mber and at least 100 mm from the ends of the  mbers. The nails should also be at least 20 mm apart.  If cross bracing is used it must supplied by contractor.  *Any type of seasoned  mber can be used for lateral bracing on the condi on it is listed as JD1, JD2 or JD3 in Australian Standards AS 1720.2 and has a stress grade of at least F8. 

Cross bracing is an acceptable alterna ve to lateral bracing and end bracing. This method system provides stability when the erec on se‐quence dictates the there are no adjacent panels that would make con nuous lateral bracing possible. 

Cross Bracing 

Lateral Bracing

Top off panel

End Brace

90 +/- 15 Degrees

Main Brace

Face off Panel

Lateral Bracing

End brace bolted to ground

End brace boltedto corner panel

36°

90.2°

End brace (B1, B2 or Mini)Installed between 30 to 90degress to main brace.

90 degrees

30 degrees

View of face off panel

View of top off panel

Page 20: Technical Handbook

19

March 2012 

The Precast & Tilt-Up Experts Corner Bracing 

The proper method of bracing corner panels shown above. A achment of braces to deadmen in the leave–out area allows the braces to be properly located without having to skew the braces for a achment to the floor slab. Corner brace lengths must be adjusted to eliminate pipe interference. 

Warning! Panel must be secured at the bo om, to prevent the panel from “walking” off the panel foo ng in gusty condi ons and to pre‐vent extremely strong winds or construc on loads from kick out the bo om of the panel. 

Point Summary of Bracing Installa on 

Install braces perpendicular to panel face.  Always check distance out or “F” measurement  Panel should be plumb with braces and knee brac‐

es installed before crane releases panel.  Lateral bracing should be install as soon as crane 

and crew are clear and should not be more than one panel behind the last panel erected. 

Lateral bracing must be con nuous, connected at each brace, and  ed off with end brace at the end of each line or at 35 meters. 

All members of the brace system must always be in place and secured at the end of each day. 

Knee and lateral bracing must be located at mid‐length of pipe brace. 

Panels requires a minimum of two braces per pan‐el. 

Do not erect panels or con nue working during ex‐cessive windy or adverse weather condi ons 

All braces inserts should a minimum of 300 mm from any panel edge, opening, control joint or con‐struc on joint.  

Panel bracing is designed to withstand specified wind loads un l panels are connected to the struc‐tural system of the building do not remove any 

members of the brace system un l all structural members of the building are completed. 

Use only the brace type specified. No subs tute brace hardware shall be used and all braces must be posi oned at the specified loca ons. 

Knee and end bracing must firmly a ached at each end  prevent  buckling of main braces. 

Panel bracing is designed to withstand specified wind loads un l panels are incorporated into the structural system of the building.  

Welding or bol ng the precast or  lt–up elements in place might preclude the uses of braces. 

T–14 Tilt–up braces are not recommended for bracing concrete block, brick or other types of ma‐sonry. 

DO NOT allow earth loads to be applied to panels that are been support by braces 

Always use bracing connec ons as specified.  For special condi ons contact Tilt–Li  Equipment 

for recommenda ons. 

Page 21: Technical Handbook

20

March 2012 

The Precast & Tilt-Up Experts Brace Capacity Charts 

S2 Brace 

Factor of Safety: 2:1 

Factor of Safety: 2:1 

S1 Brace 

B1 Brace 

Factor of Safety: 2:1 

Note: Not all brace types are available in each state, contact your local Tilt‐Li  Equipment office to find out which are availa‐ble locally. 

3400 40

3500 40

3600 40

3700 40

3800 39.7

3900 38.0

4000 37.0

4100 36.0

4200 35.0

4300 34.0

4400 33.0

4500 31.3

4600 29.6

4700 27.9

4800 26.2

4900 24.5

5000 23.3

5100 22.0

5200 20.8

5300 19.5

5400 17

Brace Length 

(mm)

Working Load 

Limit (kN)

Brace Length 

(mm)

Working Load Limit 

(kN)2500 40

2600 40

2700 40

2800 40

2900 40

3000 40

3100 40

3200 40

3300 40

3400 40

3500 38.3

3600 36.7

3700 35

Brace Length 

(mm)

Working Load 

Limit (kN)

2500 20.6

2600 20.6

2700 20.6

2800 20.6

2900 20.6

3000 20.6

3100 17.5

Page 22: Technical Handbook

21

March 2012 

The Precast & Tilt-Up Experts Brace Capacity Charts 

S3 Brace 

Factor of Safety: 2:1 

B4 Brace 

Factor of Safety: 2:1 

Note: Not all brace types are available in each state, contact your local Tilt‐Li  Equipment office to find out which are availa‐ble locally. 

Brace Legth 

(mm)

Working Load 

Limit (kN)4600 40

4700 38.3

4800 36.5

4900 34.8

5000 33

5100 31.3

5200 29.5

5300 27.8

5400 26

5500 24.3

5600 22.5

5700 20.8

5800 19

5900 17.9

6000 16.7

6100 15.6

6200 14.9

6300 14.3

6400 13.6

6500 13

6600 12.3

6700 12.7

Brace Length 

(mm)

Working Load 

Limit (kN)4900 37.6

5000 35.1

5100 32.5

5200 30

5300 27.4

5400 24.9

5500 23.4

5600 21.9

5700 20.5

5800 19

5900 17.5

6000 16

6100 15.3

6200 14.7

6300 14

6400 13.4

6500 12.7

6600 11.9

6700 11.2

6800 10.4

Page 23: Technical Handbook

22

March 2012 

The Precast & Tilt-Up Experts

Factor of Safety: 2:1 

S6 Brace 

Brace Capacity Charts 

Factor of Safety: 2:1 

S5 Brace 

Note: Not all brace types are available in each state, contact your local Tilt‐Li  Equipment office to find out which are availa‐ble locally. 

Brace Length 

(mm)

Working Load 

Limit (kN)6800 25.4

6900 24.1

7000 23

7100 21.8

7200 20.7

7300 19.5

7400 18.9

7500 18.3

7600 17.7

7700 17.1

7800 16.4

7900 15.8

8000 15.2

8100 14.6

8200 14

8300 13.4

8400 12.8

8500 12.2

8600 11.6

8700 11

8800 10.4

8900 9.8

9000 9.4

9100 9.1

9200 8.7

9300 8.3

9400 7.9

Brace Length 

(mm)

Working Load 

Limit (kN)6400 42.9

6500 41.7

6600 40.5

6700 39.3

6800 38.1

6900 37

7000 35.8

7100 34.6

7200 33.5

7300 32.5

7400 31.4

7500 30.3

7600 29.3

7700 28.2

7800 27.1

7900 26.1

8000 25

8100 24

8200 22.9

8300 21.8

8400 20.8

8500 19.7

8600 18.6

8700 17.6

8800 16.5

8900 15.8

9000 15.1

9100 14.4

9200 13.7

9300 13.1

9400 12.4

9500 11.7

9600 11

9700 10.3

Page 24: Technical Handbook

23

March 2012 

The Precast & Tilt-Up Experts

Factor of Safety: 2:1

S8 Brace

Note: Not all brace types are available in each state, contact your local Tilt‐Li  Equipment office to find out which are availa‐ble locally. 

Brace Capacity Charts 

Brace Length 

(mm)

Working Load 

Limit (kN)8700 23.2

8800 22.6

8900 21.9

9000 21.3

9100 20.7

9200 20

9300 19.4

9400 18.8

9500 18.1

9600 17.5

9700 17.1

9800 16.6

9900 16.2

10000 15.8

10100 15.3

10200 14.9

10300 14.3

10400 13.6

10500 13

10600 12.3

10700 11.7

10800 11

10900 10.4

11000 9.9

11100 9.5

11200 9

11300 8.5

11400 8.1

11500 7.6

11600 7.1

Page 25: Technical Handbook

24

March 2012 

The Precast & Tilt-Up Experts

T‐6‐A Wall Brace Anchor  The T‐6‐A is a hexical wire coil type bracing insert as spec‐ified in AS3850.1 4.3 (a) iv (A). For use in panels where the brace is to be a ached to the “up‐face” of the panel as it lies on the cas ng slab. These anchors are o en re‐ferred to as “standard” brace anchors.  Available in 19 mm coil diameter.  Uses standard coil threaded bolts.  Available in the following sizes: 125 mm, 150 mm, 

175 mm and 200 mm.  Recommended minimum distance from edge dis‐

tance of 300 mm.  The minimum bolt engagement in this insert: 50 

mm. (See diagram lower right)  Working Load Limit of the T‐6‐A is 23 kN in direct 

tension. (25 MPa concrete)  The torque of the coil bolts in the T‐6‐A should be 

set to the following. (Min: 135 nM; Max: 190 nm) 

Bracing Inserts 

Page 26: Technical Handbook

25

March 2012 

The Precast & Tilt-Up Experts B‐14 Coil Bolts 

Bolt Technical Informa on 

Tilt–Li  Equipment supplies two different types of coil bolts, one is used for the F–44 coil ferrule and the other is used for the hexical type brace inserts such as the T–6–A and the T–4. They are easily dis nguishable from each other by a number of factors. The coil bolts used for the coil ferrule is a silver zinc plated bolt it has a threaded length of 75 mm, as well as a flanged head. The coil bolt for the T–6–A is a black bolt, has a threaded length of 90 mm and does not have a flanged head. The silver bolt should never be used in a T–6–A or a T–4 as it does not have adequate engagement  for this type of insert .Before each use bolts should be measured to ensure they have not been shortened and that there length is adequate to ensure it achieves the correct engagement length.  The B–14 coil bolt is designed so that in can be reused on a number of occasions and is easy to install and remove. B–14 Coil bolts have a fast–ac ng, self–cleaning coil thread and has a diameter of 19 mm. The bolts may be reused  – but will wear and must be regularly inspected.  Must be kept clean and lubricated.  Minimum coil penetra on shown in the charts below must strictly ad‐hered to on all wire coil products. Minimum coil penetra on values represent the bolts minimum pene‐tra on through the T–6–A, T–4 etc, from the top of the device as shown in the next figure. The distance from the top coil to the concrete should be taken into account into account.  

Silver Coil Bolt Black Coil Bolt

 75 mm Threaded Length 90mm Threaded Length

Insert Type F‐43 Coil Ferrule Hexical Insert (T‐6‐A; T‐4)  F‐43 M20 x96 Ferrule

Bolt Diameter 19 mm 19 mm 20mm

Colour Silver Black Silver

Flange Diameter 39 mm  No Flange No Flange

Overall Bolt Length 90 mm 100 mm 70 mm

Threaded Length 75 mm 90 mm 60 mm

Bolt Grade 8.8 4.6 8.8

Steel Strength 800 mPa 400 mPa 800 mPa

Hex Head Socket Type 1 1/8" 1 1/8" 30 mm

Tightening Torque 135 ‐ 190 Nm 135 ‐ 190 Nm 155‐190 Nm

B‐14 Coil Bolt with Integrally Formed HeadM20x60 Grade 8.8 Zinc 

Plated Bolt

Page 27: Technical Handbook

26

March 2012 

The Precast & Tilt-Up Experts P‐82 Olive  Edge Li  Anchor System 

The P‐82 Olive  Anchor  is engineered from high strength steel and designed to be used with the P‐81 Olive  ring clutch for edge li ing of precast and  lt‐up panels.  All P‐82 Olive  Anchors have a special head designed to control ring clutch pressure so  it never bears on the concrete, helping to eliminate spalling during edge  li ing.  All Olive  Anchors are designed to accept a Tension Bar where specified for addi onal capacity. 

** A 3t WLL Olive  Anchor is also being added to the range.  Enquire directly for technical data. ** 

P-82 9t Olivetti Anchor

A

O C

O D

B

P-82 7t Olivetti Anchor

A

B

O C

P‐82 Olive  Anchor 

Size (t) Product Code 

Dimensions (mm) 

Mass (kg) 

A (Overall Length) 

B (Width) 

C (Clutch Hole Diameter) 

D (Tension Bar Hole Diameter) 

Thickness mm 

9t  P829  365  78  22  24  16  2.07 

7t  P827  245  78  22  (24)*  16  1.46 

*  The 7t Olive  Anchor is also available with a second hole to accept the Tension Bar where specified. 

Page 28: Technical Handbook

27

March 2012 

The Precast & Tilt-Up Experts

C

D

Deformed Reinforcing Bar 500 MPa to AS/NZS 4671 ‐ 2001

A B A

Pin for bending reinforcing

P‐88 Shear bar must be installed in all P‐82 anchors that are to be used in shear. These are to be installed on the same side of the an‐chor as the direc on of li , see diagram to side. If the anchor is to have a shear load applied in both direc ons then the P‐88‐S shear bar must be installed on both side of the anchor. Anchors musted be installed at the centre of the panel.  

P-82 Olivetti Tension Bar (for 7t,9t anchors)

Rebar Size

Dimension (mm)

A B C Mass

N16 250 700 64 2.2kg

Pin Diameter: 4 x db 

Bar size db 

P‐88 Olive  Edge Li  Anchor Shear Bar 

Direction of Load

P‐82 Olive  Anchor Tension Bar 

The  P‐82  Olive   Anchor  is  manufactured  with  meandering  legs  that  resists pullout during normal erec on situa ons. The working load limit chart on the next page  lists  two  sets  of  tension  values.  A  higher  tension  load  is  achievable  by installing a tension bar, this must installed through the lower hole.  The tension bar must be made from deformed grade N reinforcing bar (500 MPa) that complies to AS/NZS 4671—2001. Precau ons must be taking bending the bar, the bar must be bent around a pin with a diameter no smaller  then 4 x  the bar diameter. 

A

B

O C

Bar size db 

P‐88 Shear Bar 

Anchor Size (t) 

Rebar Size (db) 

Dimension (mm)  Mass (kg) A  B   C  D 

7, 9  N16  250 (min)  210  90 (min)  710 (min)  1.23 

Page 29: Technical Handbook

28

March 2012 

The Precast & Tilt-Up Experts P‐82 Olive  Edge Li  Anchor 

Olive  Anchor with tension bar installed 

Factor of Safety: 2.5 to 1 Minimum Panel Reinforcement: SL82, N16 Perimeter Bar (Central) 1 No tension bar required 2 Tension Bar Required Min: N16x1400(Overall Length) Minimum Edge Distance: 950mm, Minimum Spacing 1900mm

Olive  9 tonne anchor 

Concrete Strength (MPa)  15  20  25  30 

Panel Thickness   Type of Li   Addi onal Reinforcing Required  Working Load Limit (t) 

150mm 

Shear  N16 Shear Bar  1.9  2.1  2.3  2.5 

Tension1     6  6.2  6.4  6.7 

Tension2  N16 x 1400 Tension Bar  8.2  8.4  9  9 

175mm Tension1     6  6.3  7.1  7.8 

Tension2  N16 x 1400 Tension Bar  8.6  8.8  9  9 

200mm Tension1     6  6.9  7.7  8 

Tension2  N16 x 1400 Tension Bar  9  9  9  9 

Olive  7 tonne anchor 

Concrete Strength (MPa)  15  20  25  30 

Panel Thickness   Type of Li   Addi onal Reinforcing Required  Working Load Limit (t) 

Tension1     2.9  3.3  3.7  4 

Tension2  N16 x 1400 Tension Bar  7  7  7  7 150mm  

Perimeter Bar Formwork 

P‐88 Shear Bar 

Mesh 

Void Former 

P‐82TB Tension Bar 

P‐82 Olive  Anchor 

Page 30: Technical Handbook

29

March 2012 

The Precast & Tilt-Up Experts P-830 Olivetti Void Former

The Olive  P‐830 void former lug is moulded from an elastomeric thermal‐set urethane for mul ple reuse.  Embedded in the void former is a steel stud that has a M8 female thread used to pro‐vide a posi ve connec on to the form during the placement of concrete. A achment to the form is accomplished with a P‐831 Fixing Plate and P‐84 Holding Rod. P‐830 Void Formers are resistant to release agents encountered in a precast plant.

Section View

E

F

Metric Threaded Insert

A

B

C

D

P830 Olivetti Void Former Selection Chart

Load Range

Product Code

Dimensions (mm)

Mass (g) A B C D E F

7-9 P830 68 76 180 16 100 50 620

P831 Fixing Plate & P84 Holding Rod

The P-831 fixing plate can be used to fix the P-831 Void Former to metal forms. It is also used in conjunction with the P-84 holding rod to ensure the void cannot open during concrete placement.

A

D

B

C

O E

P831 Olivetti Void Former Fixing Plate Selection Chart

Load Range

Product Code

Dimensions (mm) Mass (g)

A B C D E

7-10 P831 130 37 3 20 13 131

Fixed Wing Nut

100m Typical

P831 Fixing Plate

P84 Holding Rod

Page 31: Technical Handbook

30

March 2012 

The Precast & Tilt-Up Experts P-833 Ring Clutch

Rotation of the standard bail is 360°. Once engaged and supporting a load of more than 500 kg, the ring clutch cannot be released by hand.

P-833 Ring Clutch Selection Chart Working

Load Limit* (t)

Load Range

(t)

Prod-uct

Code

Dimensions (mm) Mass (kg) A B C D E F G

10 7-10 P833 144 72 415 134 275 103 56 9.2

P833 Ring

Using P-833 Ring Clutch

The P-833 Ring Clutch is located directly of the head of the anchor.

The ring clutch is pushed down onto the anchor head and the curved bolt is rotat-ed through the engagement hole of the anchor. Ensure that the arm of the curved bolt sits parallel and touches the horizontal surface of the concrete. The process of engaging ring clutch with the anchor is completed in seconds.

The P-833 Olivetti Ring Clutch consist of a body, curved bolt and a high strength steel bail. Attachment is a simple as sliding the curved bolt to the open position, placing it over the anchor head and sliding the bolt to the fully closed position.

*Factor of Safety: 5:1

Page 32: Technical Handbook

31

March 2012 

The Precast & Tilt-Up Experts Inspection and Maintenance of Ring Clutch

Note: Destroy all units if found to be worn, damaged, bent or twisted. The proper method for use in destroying a Ring Clutch is to cut off and remove the bail and cut through the donut section of the clutch so it can no longer be used. No repair or welding on Ring Clutches is permit-ted.

W

10 7‐10 P833 20

W  

(mm)

Working Load 

Limit (t)

Load 

Range (t)

Product 

Code

The P-833 Ring Clutch may be subject to wear, misuse, overload-ing and many other factors that may affect a Ring Clutch’s working load limit. The users must establish a program for inspection of their Ring Clutches based on their frequency of use. Inspections should consist of the following: Determine the general overall condition and wear. Make certain the bail can rotate freely in all directions. If evidence of heat application is found, the clutch must be

destroyed. Check for bent or twisted bails. Check for worn or bent curved bolt. Check for worn or deformed main clutch body. Check for enlarged engagement slot.

During inspection of the clutch body, if engagement is found to exceed W, remove the clutch from service and destroy it.

Page 33: Technical Handbook

32

March 2012 

The Precast & Tilt-Up Experts How to use the Olivetti Edge Lift Anchor and Void Former

Installing an Anchor in the Void Former (A) Open the slot of the recess plug by placing a holding rod or screwdriver into an outside hole and squeeze the recess “open.” (B) Place the anchor over the rubber stud and close the recess plug. The assembly is ready for installation.

Attaching the Assembly to the Form: (A) Place the assembly against the form and position over the predrilled hole. (B) Insert the M8 holding rod through the hole and thread into the void former. (C) Pull the assembly tight to the form by firmly tightening the wing nut on the holding rod.

Attachment Using a Fixing Plate (A) Position and attach the fixing plate to the form by tack welding. (B) Slide the anchor assembly over the holding plate studs and firmly against the form. (C) Installation is complete.

Page 34: Technical Handbook

33

March 2012 

The Precast & Tilt-Up Experts P–53  Eye Anchor 

The P–53 SL Li ing Eye Anchor is designed for use with a P‐60 Tension reinforcing bar to be placed through the eye of the anchor. This combina on of P–53 SL Eye Anchor and P–60 Rebar is an excellent system to use for se ng precast columns and thin narrow walls into posi on. The eye anchor is designed so that the total anchor force is transferred into the con‐crete via a reinforcement bar. The reinforcement bar is to be installed so that it is firmly fixed in the lower anchor opening and in contact with it.  The anchor should be located at the centre line of the wall. When two or more anchors are required, the minimum spacing between anchors must be equal to the minimum panel width.  Never Use the P‐53 Eye anchor for li ing thin panels in shear. 

P–53 SL Eye Anchor for Li ing & Handling 

WLL provides a factor of safety of 2.5 to 1 with a concrete strength of 25 MPa Anchor must be used in conjunc on with P‐60 Tension Bar in order to develop its published rate working loads. 

The Tilt‐Li  Equipment SL Eye Anchor (P‐53) is similar to the P‐52 anchor but has an eye at the foot to accept P‐60 Tension Bars. The P‐53 anchor is used primarily in thin sec ons, thin panels of lightweight concrete or shapes that must be handled at concrete compressive strengths as low as  15 MPa. P‐53 anchors are available in 1.3, 2.5, 5, 10 and 20‐ton capaci es and each has its load ra ng embossed on the head.  

P‐53 SL Eye Anchor Selec on Chart 

Anchor Rated 

Load (tonnes)

Anchor 

Length

Minimum Thickness or 

Depth (2de)

Actual Edge 

Distance (de)

Minimum Corner 

Distance

Minimum Panel 

Width

Working Load 

Limit

1.3 50/65 mm 75 mm 40 mm 200 mm 400 mm 1.3 tonne

2.5 90 mm 75 mm 40 mm 100 mm 200 mm 2.5 tonne

5 120 mm 95 mm 48 mm 125 mm 250 mm 5 tonne

10 180 mm 120 mm 60 mm 175 mm 350 mm 10 tonne

20 250 mm 180 mm 90 mm 215 mm 430 mm 20 tonne

P‐Direc on of Load 

Page 35: Technical Handbook

34

March 2012 

The Precast & Tilt-Up Experts

Reinforcing Bar Dimensions

Reinforcing bar to be 500 MPa Steel, Complying with Australian Standards AS/NZS 4671‐2001 

P–60 Eye Anchor Tension Bar 

The tension bar is designed to be used with the P‐53 Eye Anchor in order for the eye anchor to develop its published rate working load limits. Reinforcing bar should always be bent a round the correct diameter pin.  

1.3t eye anchor only

P‐60 SL Tension Bar Installa on   The proper installa on of a tension bar is as follows:   1)  Place the tension bar through the eye of the anchor in such a manner that 

the tension bar contacts the bo om of the eye.  2)  Make certain the legs of the tension bar are equal on either side of the an‐

chor.  3)  Wire the tension bar into posi on so that the tension bar stays in contact 

with the bo om of the eye. (See diagram to right.)   Use bars that have been bent by the reinforcing bar supplier as per the dimension above. Reinforcing bars must be bent around the correct diameter pin as per man‐ufacturers specifica ons.  WARNING: DO NOT a empt to use field‐bent bars. Field bending may result in an improperly shaped tension bar, an incorrect radius and/or a cracked bar. A prob‐lem, such as this, can cause the field‐bent tension bar to fail prematurely.

A

B

O C

Bar size db 

1.3 N10 1000 355 ‐ 500 40

2.5 N12 1100 125 190 550 48

5 N16 1400 160 250 700 64

10 N20 1900 240 380 950 80

20 N32 4000 320 500 2000 128

Dimension 

"B" (mm)

Anchor 

Rated 

Load

Pin 

Diameter 

ØC (mm)

Reinforcing 

Bar Size db

Overall Rebar 

Length  (mm)

Dimension "A" (mm)

Standard Maximum

Right 

Wrong 

Page 36: Technical Handbook

35

March 2012 

The Precast & Tilt-Up Experts

The P-52 SL Foot Anchor is forged from carbon steel that obtains the minimum 2.5 factor of safety as set out in AS3850. Both ends of the anchor are hot forged, the head designed to suit the P-50 Lifting Eye, while the disc shaped foot creates a large shear cone in the concrete when under load. The anchor also meets the V–notch charpy test min-imum 27J requirements for L15 steels as set out in AS 3850. The an-chors are hot dipped galvanised for corrosion protection and are avail-able in grade 316 stainless steel upon request.

Tilt-Lift Equipment anchors can be identified through the unique mark-ing that is on top of the Foot Anchor. The diagram opposite shows the typical head of a standard foot anchor. The initials “TLE” identify this as one of our foot anchors. Also marked on the head of the foot anchor is the load group of the anchors, as well as the overall length of the an-chor. Please note that the load group represents the strength of the steel of the anchor and not necessarily the concrete failure of the anchor.

P-52 Foot Anchor

Tilt‐Lift Identifier

Anchor Size

Anchor Length

Page 37: Technical Handbook

36

March 2012 

The Precast & Tilt-Up Experts

Anchor lengths are standard stock sizes, other sizes are available on request. All anchors stocked in hot-dipped galvanised finish. Anchors in Grade 316 Stainless Steel available on request (items in bold are stocked).

P‐52 SL Foot Anchor 

A

B

C

D

Anchor Length

Product Code

Anchor Size

Anchor Length mm

Dimension (mm) Clutch Size

Mass g

Box Quantity A B C D

P52135 1.3 35 19 5 10 24 1.3 44 350 P52145 " 45 " " " " " 50 300 P52155 " 55 " " " " " 56 250 P52165 " 65 " " " " " 62 250 P52185 " 85 " " " " " 75 200 P521120 " 120 " " " " " 96 200 P521240 " 240 " " " " " 170 75

P52255 2.5 55 25 7 14 33 2.5 121 125 P52275 " 75 " " " " " 145 100 P52285 " 85 " " " " " 157 60 P522120 " 120 " " " " " 199 50 P522170 " 170 " " " " " 260 50 P522280 " 280 " " " " " 392 50

P52575 5 75 36 9 20 48 5 333 50 P52595 " 95 " " " " " 382 50 P525120 " 120 " " " " " 444 50 P525140 " 140 " " " " " 493 30 P525170 " 170 " " " " " 566 25 P525240 " 240 " " " " " 739 25

P5210150 10 150 46 13 28 65 10 1057 25 P5210200 " 200 " " " " " 1297 N/A P5210340 " 340 " " " " " 1972 10

P5220250 20 250 68 15 39 95 20 3345 N/A P5220340 " 340 " " " " " 4187 6 P5220500 " 500 " " " " " 5684 N/A

Page 38: Technical Handbook

37

March 2012 

The Precast & Tilt-Up Experts

The table below lists the working load of the P-52 SL Foot Anchor for various lengths and concrete strengths. When the P-52 SL anchors is properly embedded in normal weight concrete, the tabulated working loads are ap-plicable for any direction of loading. This applies even if the direction of load is parallel to the axis of the anchor, perpendicular or any other direction.

Working Load Limits 

Minimum edge distance is 3 x anchor length; Minimum anchor spacing is 6 x anchor length Do not attempt to use the foot anchor in concrete that is less then 15 MPa. Factor of Safety: 2.5 to 1 Italics represents those condition that are limited by steel and clutch strength

Working Load Limit (Tonnes) Anchor

Size

Anchor Length (mm)

Concrete Compressive Strength @ Lift (MPa)

15 20 25 30 1.3 35 0.47 0.55 0.61 0.67 1.3 45 0.93 1.08 1.2 1.30 1.3 55 1.21 1.30 1.30 1.30 1.3 65 1.26 1.30 1.30 1.30 1.3 85 1.30 1.30 1.30 1.30 1.3 120 1.30 1.30 1.30 1.30

2.5 55 1.08 1.30 1.40 1.52 2.5 75 1.70 1.98 2.2 2.40 2.5 85 2.15 2.40 2.50 2.50 2.5 120 2.50 2.50 2.50 2.50 2.5 170 2.50 2.50 2.50 2.50 2.5 280 2.50 2.50 2.50 2.50 5 75 2.13 2.46 2.75 3.01 5 95 2.92 3.37 3.77 4.13 5 120 4.03 4.65 5.00 5.00 5 140 5.00 4.63 5.00 5.00 5 170 5.00 5.00 5.00 5.00 5 240 5.00 5.00 5.00 5.00

10 150 4.95 5.72 6.4 7.01 10 340 10.0 10.0 10.0 10.0

20 250 14.0 17.0 19.8 20.0 20 340 20.0 20.0 20.0 20.0 20 500 20.0 20.0 20.0 20.0

Page 39: Technical Handbook

38

March 2012 

The Precast & Tilt-Up Experts How to use the Foot Anchor Void Former

P‐55 SL Void Former The P‐55 SL Recess void former is used to form a cavity around the SL foot anchor. The recess void form is bolted to the form using a stud and wing nut combina on (P‐63 Male Connector) or a tapped plate and bolt (P‐66 Female Connector). It posi ons the anchor for easy a ach‐ment and removal of the clutch.  The SL recess void former has slit which facilitates inser on of the anchor head and withdrawal when the formwork is stripped or the concrete has achieved final set. When removing the void former plain rods or screwdrivers can be introduced into the two holes provided in the top sur‐face of the recess void former which is then pried open and removed from the concrete. 

P‐55 Round Void Former 

P‐63 Male Connector The stud and wing nut is used to bolt the P‐55 SL Void former to formwork used in situa ons were the formwork can be removed by pulling the formwork directly out from the concrete surface. The formwork will slide out over the threaded stud.  

P‐63 Male Connector 

P‐64 Female Connector The threaded tapped plate is used to bolt the P‐55 SL Void former to formwork used in situa‐ons were the formwork cannot be removed horizontally and must be stripped ver cally. The 

formwork needs to be slide directly up along the surface on the concrete and requires a smooth surface. A standard metric bolt is used to bolt the void former to the form. 

P‐64 Female Connector 

Tie the SL Anchor to reinforcing steel to insure anchor support dur‐ing concrete placement. 

Sec on Through Form 

P‐63 Male Connector P‐55 Round Void Former 

SL Anchor 

With the male or female connectors installed grasp the void former across the top diam‐eter of the plug. Applica on of pressure by the thumb and fingers on the out edge of the plug will cause the plug to open up to allow inser on of the anchor. 

How to install P‐55 Recess Void Formers on P‐52 Anchors 

How a ach the P‐55 Recess Void Former and P‐52 Anchors to Formwork 

The stud or bolt is inserted through the form,  ghten wing nut or bolt firmly against the form. This will close the slit in the void former ensuring no concrete can enter the void former which may otherwise pose a problem when a aching the clutch 

Page 40: Technical Handbook

39

March 2012 

The Precast & Tilt-Up Experts How to use the Foot Anchor Void Former

Void former removal 

P‐55 void former plugs provide two holes in the top surface that are used in the remov‐al process. Insert two screw drivers or steel rods in the holes and simply level the two across the plug for easy removal. 

P‐57 Steel Void Former 

The P‐57 steel void former is designed for permanent or semi permanent a ach‐ment to a repe ve use precast forms, such as ba ery moulds, steel forms that have a collapsible stripping feature etc. This void former is drilled and tapped for easy a achment  to the form or may be held in place by tack welded or glued. 

P‐58 Rubber Ring 

The P‐58 Rubber ring is placed on the sha  of the SL Anchor and is seated into the steel void former providing a holding ac on for the anchor. 

P‐57 Round Void Former 

P‐58 Rubber Ring 

P‐57 Steel Void former 

P‐58 Rubber Ring Form Face 

Tie wire to nearby reinforcing steel 

It is recommended that when the P‐57 steel void former is used that the end of the anchor be supported to prevent dislodgement. Dislodgement may result in the anchor si ng lower in void than normal making it impossible to engage the clutch. 

“Wet Se ng” P‐52 SL Anchors 

SL Anchor assembly a ached to template board 

When a SL anchor is to be posi oned in the top surface of the flat precast sec on, wet se ng the anchor is best done immediately a er the concrete has been placed.  The anchor/void former assembly is a ached to a small template board and pressed into the fresh concrete un l the template board lies flush on the surface of the concrete.  Light vibra on of the fresh concrete will assure proper embedment and anchorage. 

Page 41: Technical Handbook

40

March 2012 

The Precast & Tilt-Up Experts P–50 Universal Foot Anchor Universal Li ing Eye 

The SL Universal Li ing Eye consists of a flat sided spherical li ing body and a high strength bail. The li ing body has a T–shaped slot which permits rapid a achment and release of the li ing eye onto the anchor, even while wearing work gloves.  The design of the P–50 Universal Li ing Eye permits the bail to freely rotate 180°, while the complete eye may rotate through a 360º arc. As such once the li ing eye is correctly installed and under load it can operate in any direc on. This design feature allows your precast concrete elements to be turned,  lted and/or rotated under load. The SL Li ing range of products have been designed so that the incorrect size clutch cannot be used on the  wrong anchor. The SL Universal Li ing Eye should not be used to run a pulley, especially when upside down. 

Factor of Safety: 5 to 1

Inspec on While appreciable wear does not normally occur, the general condi on and degree of wear should be checked at least eve‐ry three months. The upper limits of dimensions “H” and the lower limits of dimension “M” are shown below.   

Working Load "H" "M" 

Limit Maximum Minimum

1.3 13 mm 5.5 mm 47 mm 75 mm 56 mm 32 mm 71 mm 188 mm

2.5 18 mm 6.0 mm 59 mm 91 mm 68 mm 41 mm 86 mm 230 mm

5 25 mm 8.0 mm 70 mm 118 mm 88 mm 57 mm 88 mm 283 mm

10 32 mm 12.0 mm 88 mm 160 mm 112 mm 72 mm 115 mm 401 mm

20 46 mm 18.0 mm 106 mm 180 mm 152 mm 110 mm 135 mm 506 mm

P‐50 SL Universal Lifting Eye P‐50 SL Universal Lifting Eye

A B D F G L

Limiting Dimensions on General Dimensions on

Page 42: Technical Handbook

41

March 2012 

The Precast & Tilt-Up Experts

1. To install the P-50 Universal Lift-ing Eye, hold the unit upside down with the T-shaped slot of the body directly over the head of the foot anchor.

2. Lower the body of the lifting eye until the T-shaped slot engages the head of the anchor.

3. Rotate the body until the extended lip of the body touches the horizontal concrete surfaces.

The bail of the P-50 lifting eye can move through a 180° useable range.

Note the main body of the lifting eye has a 360º rotational range.

The lifting eye may be safely used with the T-shaped slot fac-ing away or towards the direction of applied load.

How to use the Universal Lifting Eye

To disengage the lifting eye, the crane hook is lowered and the body removed by rotating the extended lip upward.

Prior to lifting a precast element, apply an initial cable tension to make certain that the bail and body of the lifting eye are aligned in the direction of the cable pull.

When applying the initial cable tension on edge lift applications, make sure that the cables are at a 90° angle (or larger) to the surface of the precast element.

Warning: Do not allow the crane lines to form an angle less than 900 during an edge lift application. This condition can bend the lifting eye bail and could lead to a premature failure.

Warning: The crane line and bail of the lifting hardware must be turned in the direction of the cable forces before the lifting operation begins. The crane line must not be allowed to apply a sideward force on the bail. This condition is dangerous and could lead to premature failure of the hardware or insert. Warning: Do not modify, weld or alter in any way the Swift Lift Universal Lifting Eye.

Page 43: Technical Handbook

42

March 2012 

The Precast & Tilt-Up Experts

Inspec on While appreciable wear does not normally occur, the general condi on and degree of wear should be checked at least eve‐ry three months. The upper limits of dimensions “H” and the lower limits of dimension “M” are shown below.  Prior to each use of the clutch the safety pin should be checked to ensure that the safety pin is in good condi on and moves freely at all 

How to use the P–51 SL Li ing Eye    To engage the P–51 SL Li ing Eye onto the head of the SL anchor, posi on the P–51 SL Li ing Eye so that the front face is toward the concrete, then raise the SL Li ing Eye into the posi on and engage the li ing hook. The safety will drop into posi on to prevent accidental release of the SL Li ing Eye. 

Factor of Safety: 5 to 1 

The P–51 SL Li ing Eye is a high quality steel cas ng, hardened and tempered. Its ball shaped lower end fits into the recess formed in the concrete and has a T–shaped slot which engages the spherical head of the anchor. Con‐nec on to the anchor head can only be made when the li ing eye posi oned face downwards to the concrete. In the working posi on, release is impossible. Accidental disengagement is prevented by a gravity–ac on safety pin which must be raised before the SL Li ing Eye can be removed.  

P–51 Li ing Eye 

1.3 13 mm 5.5 mm 50 mm 92 mm 45 mm 75 mm 170 mm

2.5 18 mm 6.0 mm 67 mm 115 mm 60 mm 95 mm 215 mm

5 25 mm 8.0 mm 76 mm 129 mm 72 mm 126 mm 260 mm

10 32 mm 12.0 mm 90 mm 152 mm 94 mm 143 mm 325 mm

Limiting Dimensions on P-51 SL Lifting Eye

General Dimensions on P-51 SL Lifting Eye

Working Load Limit

"H" Maximum "L" Minimum A B D I L

Page 44: Technical Handbook

43

March 2012 

The Precast & Tilt-Up Experts T‐41 Ground Release Insert 

The ground  release  insert  is a  simple and  fast method of  li ing concrete  lt‐up wall panels  into posi on and allows  the hardware to be easily released from the ground.   Ladders are normally not required during the hardware release process which greatly increases worker safety and produc vity. 

Features of the T‐41 Ground Release Insert are:  

Flexible plas c antenna folds over when screed passes, but springs back to indicate insert loca on. 

 

Plas c  Recess  plug  creates  a  void  for  a aching  the  Ground  Release Li ing Hardware  to  the  insert head The expendable plas c  recess plug  is easily removed from hardened concrete. 

 

Direc onal label indicates correct panel thickness and direc on of plas c recess plug in rela on to top & bo om of panel. 

 

Ground Release Anchor. This hot forged anchor permits rapid hardware a achment and allows smooth rota on of the hardware during the release opera on. 

 

Support  Chair  is  sized  for  appropriate  panel  thickness.  Each  leg  has  a plas c  p which protects  the wire  legs  from exposure and poten al  rust problems.  

 

Ground Release Inserts are shipped assembled, ready to use and are size 3 mm less than panel thickness. 

Working Load Limit for T-41 Ground Release Insert

The li ing anchors used in the T‐41 Ground release insert meet the V‐notch charpy test minimum 27J requirements for L15 steels as set out in AS3850.  Tilt‐Li  Equipment anchors also have the iden fying marks as required by various Worksafe industry codes of prac ce for Precast and Tilt–Up industries.  The tonnage of the anchor, anchor length and Tilt Li  Equip‐ment iden fying mark are all visible on the top of the li ing head. “TLE” is the iden fying mark for Tilt Li  Equipment.   Note: Although the tonnage of the anchor may be 5 tonne, the Working Load Limit of the li ing anchor will in most situa‐ons will be determined by the concrete strength, edge distance and overall length off the anchor.  The Working Load Limit 

for the T‐41 ground release insert, is set out in the table below. (Note: No addi onal reinforcing is required to achieve these working loads, addi onal reinforcing is required for li er stability only.) 

Factor of Safety: 2.5 to 1 Italics Represents Safe Working Load determined by Lifting Hardware Minimum Edge Distance 3 x Anchor Length Sling must be in line with lifter to achieve WLL, otherwise reductions must be considered. Danger! Do not use for edge lifting of panels, as insert is not designed for such use. Do not use with top surface seeded exposed aggregate 18 mm or larger as aggregate will pop out during erection resulting in reduced working load limit.

Panel AnchorThickness

(mm)Length (mm)

25 30 32

100 - 120 75 2.75 3 3.1

125 - 145 95 3.7 4.1 4.18

150 - 170 120 5 5 5

170+ 140 5 5 5

T-41 Working Load Limit (Tonnes)

Concrete Strength (MPa)

Page 45: Technical Handbook

44

March 2012 

The Precast & Tilt-Up Experts How to Remove the Ground Release Recess Plug 

1. The Ground Release Inserts loca‐on in the panel is easily found by loca ng the antennae which will project through the surface of the concrete. 

2. Using an ordinary claw hammer tap lightly around the antennae break‐

ing through the thin skin on concrete to expose the insert. Avoid striking the con‐crete to hard so as not to break through the plas c recess plug. 

3. Drive claws of the hammer down about 10 mm between the end of 

the recess plug and the concrete 

5. Repeat Steps #3 & #4 to loosen the opposite half of the recess plug.  6. Grasp both halves of the recess plug between the thumb and finger and squeeze. 

7. Both halves of the recess plug should now be easily removed, exposing the insert. 

8. If one half the recess plug should be hard to remove , drive the claws of the hammer as deeply as possible, be‐tween the insert plug and top of the insert, as shown above. Push forward on the ham‐mer with one quick mo on. This will re‐move the recess plug. 

9. Use a blower to remove all debris from around the insert and the 

recess plug. The insert is now ready to receive the li ing hardware. 

4. Pry up on the end of the recess plug un l one half of it “pops up” to a point where it is about a third of the way out of the concrete. For the  me being leave it as is and proceed with step #5.

Page 46: Technical Handbook

45

March 2012 

The Precast & Tilt-Up Experts T‐43‐R Ground ReleaseII Li ing Hardware 

The new T‐43‐R Ground ReleaseII Li ing Hardware unit offers the  lt‐up contractor the latest and easiest‐to‐use  lt‐up li ing hardware  unit  on  the market  today.    This  new  li ing  hardware  unit  is  a  simplified  design  and when  combined with  a superior system for the quick and efficient erec on of  lt‐up concrete wall panels. 

Bail  will  accept  all  conven onal  crane  a achments.  Units moves easily as it follows line of ac on of crane cable. 

Li ing  Body  a aches  to head of  insert. Whenever diagonal  loads are applied to the bail, the result is a combina on of a compression load  applied  to  the  concrete  and  a  tension  load  applied  to  the insert. 

Release  Line  is  a  12  mm  hollow  braided  polyethylene  cord  of sufficient length to reach the ground. 

Working Load Limit is 5 tonne with a minimum safety factor of 5. 

Minimum Insert Distances

Warning!  Inserts must also be properly  located  in rela on to the centre  of  gravity  of  the  panel.    This work  should  be  performed under the direc on of a professional engineer. 

Safety Notes  For safe use of the Ground ReleaseII System,  it  is necessary for  the  inserts  to be posi oned  so  that  the  arrows on  the direc onal  label point to the top/bo om of the panel.   You may also posi on direc onal arrows so  they are parallel  to the ver cal sides of the panel.  Inserts  must  be  properly  located  in  rela on  to  edges, corners,  openings  and  ledgers  and  at  such  a  distances  to permit  the  development  of  a  full  concrete  shear  cone.  These  minimum  distances  are  shown  in  the  illustra ons above.  Embedment of inserts closer to an edge on concrete than the minimums shown may reduce the effec ve area of 

the  resis ng  concrete  shear  cone  and  thus  reduces  the inserts working  load  limit.   During  placement  of  concrete, displacement of inserts must be avoided.  Inserts must be properly embedded  in sound concrete and shall be properly wired  in place  so  that  the ver cal axis of the insert is perpendicular to the li ing surface.  Do not weld to the ground release anchor as welding causes embi erment and can result in a premature failure. 

Page 47: Technical Handbook

46

March 2012 

The Precast & Tilt-Up Experts

Do Not Use For Edge Li ing Do Not Use This System On Top Surface, Seeded, Exposed Aggregate 19 mm or Larger 

Precheck all insert holes with hardware prior to erec on date, following instruc on steps 2,3 and 4, so that during  l ng proper hardware ac on is assured. 

1. Place plas c recess plug with arrow poin ng to top or bo om of panel with two  legs of  insert against  the ver cal  reinforcement. Wire  e  those  legs of 

insert  to  rebar. Place 12 mm x 450 mm  long  re‐bar diagonally,  tying  to horizontal and ver cal re‐bars and third  leg of  insert. Place addi onal re‐bar supports around insert as  shown  to prevent ver cal displacement. Please note  the addi onal  rein‐forcing bars are for stability only they are not required to develop the working load limit of the li ing anchor. 

2. The various parts of the T‐43‐R Ground ReleaseII Li ing Hardware are shown above. 

3. To  install the  li ing hardware onto the insert,  hold  the  hardware  by  the  bail 

release arm and lower it onto the head of the insert. Check to make certain that the release arm points to the top of the panel.  

4. Lower  the  release  arm  un l  the arm  comes  into  contact  with  the 

panel.  Lay  the  release  line  along  side of the panel of  the  li ing hardware so  that the line goes to the bo om of the panel. With  the  crane  lines a ached,  the panel is now ready for li ing.  

5. As  the panel  is li ed,  the  re‐lease  arm  is  trapped between  the  panel and  the  crane  line, which  insures  that the  li ing  hardware cannot  be  prema‐turely  released. Brace  and  secure into posi on. 

6. The  crane  line should  be slackened  slightly  to permit the release of the  li ing  hardware. To  release  the  li ing hardware,  apply  a single  downward force  to  the  release the line.  

WARNING! The crane line and bail of the li ing hardware must be turned in the direc on of the cable forces before the li ing opera on begins. The crane line must not be allowed to apply a sideward force on the bail, as this condi on is dangerous and could lead to premature failure of the hardware or insert. 

How to use the Ground ReleaseII System 

7. The  li ing  hard‐ware  remains  in 

the open posi on ready to  be  lowered  to  the ground and a ached to the next panel. 

Proper Hardware Usage Prior to li ing any  lt‐up panel, apply an ini al load to the crane lines making certain that the hardware is properly a ached to the head of the T‐41 Ground Release Insert and that the bail of the li ing hardware is aligned with the crane line. DO NOT apply a sideward load to the bail of the li ing hardware. 

Page 48: Technical Handbook

47

March 2012 

The Precast & Tilt-Up Experts

T‐46 Ground ReleaseII Spreader Beam with Twin Shackles 

The T‐46 Ground ReleaseII Spreader Beam is supplied with two 5  tonne shackles required to a ach the spreader beam to the T‐41 Ground Release Inserts. The use of this system will eliminate many of the rigging changes that have been required on projects with very large or extremely heavy panels.  

The larger hole in the centre of the spreader beam will accept the many different sizes of li ‐ing shackles that the  lt‐up panel erector may elect to use.  The T‐46 Spreader Beam has a maximum Working Load Limit of 10 tonne with a factor of safety be er then 5 to 1. 

T‐42 Double Ground ReleaseII System 

Over the last few years a trend has developed towards the use of heavier  lt‐up wall panels on many  projects.  In an effort to  reduce  the  number of  rigging  changes  required, when  these heavier  panels  are  to  be  erected, Dayton  Superior  has developed and test a new, double insert li ing system for increased li ing capacity.  The new li ing system consists of two T‐41 Ground Release Inserts, two T‐43‐R Ground ReleaseII Li ing hardware units and our T‐46 Ground ReleaseII Spreader Beam with twin 5 tonne shackles.  In  order  to  develop  the  safe working  loads  list  in  the  T‐42  load  table,  our  T‐41  inserts must  be  spaced  by  the  panel contractor at 305mm centres.  A spacing of less the 305mm greatly reduce the li ing capacity of the system and the use of wider spacing is not recommended.   

A er the  lt‐up panel has been li ed into posi on and properly braced off, the two T‐43‐R Ground ReleaseII Hardware Units are released from the panel in the very same manner used to release a single unit. 

Working Load Limit Based on concrete strength of 25 MPa Factor of Safety 2.5 to 1 

410

O 35O 45

O 35

305

125 ‐ 145 95 5.6

150 ‐ 170 120 7.25

175+ 140 8.8

Double Ground Release Insert

Anchor Length 

(mm)

Panel Thickness 

(mm)

Working Load 

Limit (tonnes)

Page 49: Technical Handbook

48

March 2012 

The Precast & Tilt-Up Experts

The T–52 edge li  anchor comes complete with a 6.3 mm round shear bar. A ach the assembled T–52 recess plug and anchor to the formwork in its predetermined loca on with the two hooks of the shear bar in the down posi on. Always install the edge li  unit below the perimeter bar of the panel  as shown in the diagram. Use common nails in the upper three tabs of the recess plug. Provide bar supports around the anchor as shown to prevent displacement during the cas ng process.  Perimeter must extend at least 500mm to either side of the anchor, and must installed hard against anchor sha  and void former. The 5 tonne edge li er comes with a 5 tonne x 240 mm li ing anchor. The 2.5 tonne edge li er comes with 2.5 t x 170 mm li ing anchor. In panels less then 125 mm thick the round shear bar that comes with the 2.5t P‐52 edge li  anchor should be removed completely and a P‐59 Shear bar must be installed in its place. Either the P‐50 SL Li ing Clutch or the P‐51 Li ing Eye can be used to edge li  panels into posi on.   DO NOT use the T‐43‐R Ground Release Clutch for edge li ing panels. 

T‐52 Edge Li  Anchor 

P‐59 Shear Bar To gain extra load in shear, a P–59 Shear can be added above the anchor. As the diagram below shows, install the P–59 shear bar against the 6.3 mm round bar. Please note that the P–59 shear bar has no impact on tension loads. 

Working Load Limits Represent a factor of safety of 2.5 to 1. Concrete strength 25 MPa Minimum Corner Distance: 3 x Anchor Length; Minimum Spacing: 6 x Anchor Length  

Anchor Size

A B C RRebar Size

1.3 tonne 180 mm 127 mm 64 mm 25 mm R10

2.5 tonne 230 mm 180 mm 75 mm 37 mm N12

5 tonne 254 mm 229 mm 95 mm 44 mm N16

10 tonne 305 mm 254 mm 97mm 57 mm N20

P - 59 Shear Bar Dimensions

Without P-59 Shear Bar

With P-59 Shear Bar

1.3 tonne 120 95 N/A 0.8 1.05

100 N/A 1.2 1.4

125 1.5 1.8 1.9

150 1.7 2 2.25

150 2 2.2 3.2

175 2.2 2.5 4

Shear

2.5 tonne 170

5 Tonne 240

Panel Thickness

Anchor Length

Anchor Size

Tension

Page 50: Technical Handbook

49

March 2012 

The Precast & Tilt-Up Experts F–43 Standard Ferrule Inserts 

Designed for heavy duty anchoring, F–43 Ferrule inserts are cast–in anchors, available in both round and hex, finishes in‐clude zinc plate, galvanized and also available in stainless steel. Standard Ferrules requires an N12 x 300 mm rebar to be installed through the cross hole to obtain the full working load. 

*(Fc=0.6; Fs=0.8  Ul mate) Concrete Compressive strength: 30 MPa Minimum edge distance: 300 mm, Minimum Spacing: 600 mm Bolt shear capacity and concrete strength will determine shear capacity. Bolt capacity may be lower than ferrule or concrete capacity. Load represents ul mate load at each end of the ferrule. 

F‐46 Double Ended Ferrules  

Double ended Ferrules are the ideal solu on when fixing is required on both side of the panel. Double end ferrules requires an N12 x 300 mm rebar to be installed through the cross hole to obtain the full working load. 

M12 x 75 28 75 15 35 N12 x 300 24.2

M12 x 96 28 96 15 40 N12 x 300 29.3

M16 x 75 28 75 15 35 N12 x 300 32.5

M16 x 96 28 96 15 40 N12 x 300 45.7

M20 x 75 28 75 15 35 N12 x 300 32.5

M20 x 96 28 96 15 40 N12 x 300 45.7

M24 x 100 37 100 15 40 N12 x 300 45.7

Standard Ferrule with N12 x 300 Cross Bar

Ferrule Size OD (mm) L (mm) H (mm) TL (mm) Rebar SizeUltimate Tensile 

Load* (kN)

Ferrule Size

OD (mm) L (mm) H (mm) TL (mm) A (mm) Rebar SizeUltimate Tensile

Load* (kN)M16 x 140 M20 x 140

28 140 15 40 70 N12 x 300 30

M16 x 170 M20 x 170

28 170 15 40 85 N12 x 300 30

Double Ended Ferrules With N12 x 300 Cross Bar

Page 51: Technical Handbook

50

March 2012 

The Precast & Tilt-Up Experts

AS 3850 uses permissible stress design for the calcula on of brace forces in temporarily braced  lt‐up and precast panels. This standard dictates that cast‐in brace fixings have a factor of safety of 2.5 to 1. 

***Coil ferrule or M20 ferrules used for temporary panel bracing. (FOS 2.5:1)  Concrete Compressive Strength: 25 MPa Minimum edge distance a: 300 mm, Minimum Spacing: 600 mm Bolt shear capacity and concrete strength will determine shear capacity. Bolt capacity may be lower than ferrule or concrete capacity. 

F–44 Star Ferrule 

Also  designed  for  heavy  duty  anchoring,  F–44  Star  Ferrule  inserts  are  cast–in  anchors  available  in  zinc  plate finished or stainless steel. Star Ferrules do not require a cross bar to be installed to obtain the full working load. However a cross hole is provided to allow a 300mm long bar to be installed if required for duc lity performance. 

*(Fc=0.6; Fs=0.8  Ul mate) Concrete Compressive strength: 30 MPa Minimum edge distance: 300 mm, Minimum Spacing: 600 mm Bolt shear capacity and concrete strength will determine shear capacity. Bolt capacity may be lower than ferrule or concrete capacity. Load without cross bar.  All ferrules stocked in hot‐dipped galvanised finish. Grade 316 available for M12x55, M16x85, M20x85.  

Ferrules used for Temporary Bracing 

Ferrule Size OD (mm) L (mm) H (mm) TL (mm)Rebar Size

Working Load Limit Tension (kN)***

M20 x 96 Standard Ferrule

28 96 15 40 N12 x 300 27

M20 x 85 Star Ferrule

28 96 15 40Not

Required27

Coil Ferrule 28 96 15 40 N12 x 300 27

Ferrules For Temporary Bracing

Page 52: Technical Handbook

51

March 2012 

The Precast & Tilt-Up Experts F47 TB Coupler 

Tilt Lift Equipment's TB coupler is available in 3 sizes to suit N12, N16 and N20 Threaded Bar It is designed as an in-line full strength connector for 2 lengths of the reinforcing Threaded Bar screwed in with minimal effort to achieve the full breaking strength of the reinforcing bar. NB: The coupler will not fail!

100

65

2327

150

3540.4

28

30

12024

35.5

N12 Threaded Bar Coupler (F47TB12)

N16 Threaded Bar Coupler (F47TB16)

N20 Threaded Bar Coupler (F47TB20)

F47 Threaded Bar couplers will develop the full breaking strength of the bar

Installation: Screw in both lengths of Threaded Bar by hand until they stop, tighten both lengths of bar using a 300mm wrench. Ensure both ends have been installed with the minimum thread engagement length.

Bar Size Product CodeMinimum Thread 

Engagement Length (mm)Mass (kg)

N12 F47TB12 45 0.23

N16 F47TB16 55 0.38

N20 F47TB20 70 0.68

F47 TB Couplers

Bar Size fy (MPa) Fy (kN) Fu (kN)

N12 500 56 61

N16 500 100 108

N20 500 157 169

Characteristic TB bar capacities

Page 53: Technical Handbook

52

March 2012 

The Precast & Tilt-Up Experts

Tilt-Lift Equipment's threaded bar Star Ferrules are currently available in 2 sizes to suit 12mm and 16mm Threaded Reinforcing Bar. Ideally suited for starter bar connections to floor slabs and mezzanine floors. Can easily be installed in the near face, far face and side of tilt-up and precast concrete panels. No ad-ditional cross bar required to develop this ferrules working load limit.

Description Reinforcing Bar Size

Overall Length (L)

mm

Effective Depth (he)

mm

Base Width mm

Part Number

Min Thread En-gagement Length

(mm)*

N12 x 86 Threaded Bar Star

N12 86 84 55 F541286 50

N16 x 110 Threaded Bar Star

N16 110 108 55 F5416110 80

F‐54 Threaded Bar Star Ferrule 

L

55d

*Reinforcing bar must be fully installed until it stops and tightened into position with a 300mm wrench.

Page 54: Technical Handbook

53

March 2012 

The Precast & Tilt-Up Experts

Reduced characteristic ultimate concrete tensile capacity

фc=0.6; f’c=32 MPa, minimum edge distance 3 x effective depth minimum spacing 6 x effective depth

Influence of Concrete Strength in Tension (fc,n)

Influence of Edge Distance in Tension (fe,n)

Influence of Spacing in Tension (Overlapping 1 Anchor) (fse,n)1

Ferrule Type Tensile Capacity φNu,c

N12 x 86 33.1 N16 x 110 55.4

f'c (MPa) 15 20 25 30 32 35 40 Fc,n 0.68 0.79 0.88 0.97 1 1.05 1.12

Edge Distance, e (mm) N12x86 N16x110

65 0.66 70 0.69 80 0.74 85 0.77 0.66 90 0.80 0.68

100 0.86 0.72 121 1.00 0.81 125 0.83 150 0.95 166 1.00

Spacing, a (mm) N12x86 N16x110

80 0.66 90 0.69

100 0.71 0.66 125 0.76 0.69 150 0.81 0.73 175 0.86 0.77 200 0.91 0.81 225 0.96 0.85 250 1.00 0.89 275 0.93 300 0.97 325 1.00

a

e

F‐54 Threaded Bar Star Ferrule 

Tensile Strength Calculations

Page 55: Technical Handbook

54

March 2012 

The Precast & Tilt-Up Experts

Influence of Spacing in Tension (Overlapping 2 Ferrules, one on each side) (fsi,n)1

a a

Spacing, a (mm) N12x86 N16x110

80 0.33 90 0.37

100 0.41 0.31 125 0.51 0.39 150 0.62 0.47 175 0.72 0.55 200 0.82 0.62 225 0.93 0.70 250 1.00 0.78 275 0.86 300 0.93 325 1.00

Designed Reduced ultimate tensile capacity: φNn=φNu,c * fc,n * fe,n* (fse,n or fsi,n)

F‐54 Threaded Bar Star Ferrule 

1. For ferrules in a row loads must be evenly distributed along all ferrules.

Page 56: Technical Handbook

55

March 2012 

The Precast & Tilt-Up Experts

Appendix A  

J‐6 Sure Li  Bond Breaker   Tech Data Sheet & MSDS  J‐6WB Sure Li  Water‐Based Bond Breaker   Tech Data Sheet & MSDS 

Page 57: Technical Handbook

Sure Lift (J-6) Premium Bond Breaker Technical Data Sheet

 Contact your nearest Tilt‐Lift Equipment branch for the latest Technical and MSDS sheets 

2 Arnold St, Cheltenham, Vic 3192. Phone: 03 9583 0115 Fax: 03 9583 2112 www.tiltlift.com.au 

 12 February 2008         For Commercial / Industrial Use Only                 Page 1 of 3 

Product description Sure-Lift (J-6) is a reactive and membrane forming premium bond breaker for tilt-up construction. Sure-Lift is a special formula of polymers and propriety ingredients designed to provide clean easy lifting of tilt panels. J-6 has a fugitive dye for ease of visual inspection during application. Use J-6 is designed to allow for easy lifting of tilt wall panels from a properly designed, finished and cured concrete casting beds. Benefits

• Chemically Reactive • Good resistance to rain and weather • Panels lift cleanly • Minimal panel residue • Resists construction foot traffic

NOTE: Prior to application, read and follow all current (verify literature is current) literature instructions, limitations and precautions in this data sheet, on the MSDS and on the label of the container prior to use. The instructions provided by this technical data sheet to general average site conditions such as concrete mix designs, finishing techniques, and site ambient conditions. Test applications should always be made by the end user prior to overall use of the bondbreaker. This is at a minimum necessary to verify that the amounts of bondbreaker purchased and anticipated to be applied is sufficient to result in the correct application coverage rates and end performance of the product based upon the specific site conditions. The concrete casting slab, waste slabs and tilt wall panels must be properly designed, finished and cured in accordance with industry standards and guidelines. Spray Equipment The (J-6) Bondbreaker must be applied by a high quality “low-pressure pump-up type sprayer” such as manufactured by Chapin or others. The tip size must be able to produce a well atomized spray pattern. The sprayer must be kept under sufficient pressure to correctly atomize the (J-6) without streaming, tailing, or spitting. A 1.9 litre/minute tip is generally recommended for most applications. The use of an improper sprayer, a dirty sprayer, lower than adequate pressures or wrong tip can result in an uneven application, and either over or under application.

First Bondbreaker Coat The casting bed should be free of all foreign material, salts, laitance and the (J-6) protected, while drying, from all contaminants or particulate matter (i.e., dust, dirt, etc.). Just prior to placing the reinforcing steel, and within two weeks of pouring the panels, spray apply the first bondbreaker application of (J-6) at 9.8m2/L to the point of rejection. Specific site conditions may dictate coverage rates other than the normal recommended coverage rates. Adjust the actual applied rates accordingly. Second Bondbreaker Coat Wait until first coat dries, approximately 2 hours depending on temperature and humidity, and apply a second coat right angles to the previous coat. Coverage for the second coat will typically be 13.5-17.2 m2/L. If light or white spots appear within 10-40 minutes after spraying, those areas are extra porous and should be fogged with water followed by a reapplication of the (J-6) 13.5-17.2 m2/L. Specific site conditions may dictate coverage rates other than the normal recommended coverage rates. Adjust the actual applied rates accordingly. The number of bondbreaker coats and coverage rates necessary to achieve a complete uniform coverage is highly dependent on the concrete casting slab mix design as well as its inherent porosity, finishing techniques, and other related site specific ambient conditions. Adequate bondbreaker application is in large part dependent upon development of a uniform soap like feel of the bondbreaker treated surface as well as beading of water. Bondbreaker can also be checked by rolling up a small ball like amount under thumb pressure. Extremely porous or rough casting slabs will necessitate successive additional coats of bondbreaker to achieve a consistent uniform membrane of the correct coverage rate and membrane thickness. Extremely porous or otherwise absorptive slabs can also be fogged with water to a saturated surface dry (SSD) condition prior to application of bondbreaker. Bondbreaker Test To verify the integrity of the bondbreaker coat, sprinkle water on the casting bed. (Water should bead up as on a freshly waxed automobile). The applied, dried material should have a soap like feel, uniformly over the substrate. The application should appear uniform and continuous, with light areas requiring re-application. Failure to verify proper uniform application and coverage rates can result in panel sticking. Testing must be performed over a large enough surface area in an adequate testing frequency to provide accurate and meaningful results.

Page 58: Technical Handbook

Sure Lift (J-6) Premium Bond Breaker Technical Data Sheet

 Contact your nearest Tilt‐Lift Equipment branch for the latest Technical and MSDS sheets 

2 Arnold St, Cheltenham, Vic 3192. Phone: 03 9583 0115 Fax: 03 9583 2112 www.tiltlift.com.au 

 12 February 2008         For Commercial / Industrial Use Only                 Page 2 of 3 

It is entirely the contractor’s responsibility to verify that the bondbreaker has been evenly and uniformly applied at the recommended application/coverage rates given the various concrete mix design, densities, finishes, and porosity conditions on each project Hot Weather Procedures In hot weather, the casting slab must be flooded with water to reduce its porosity and cool it down prior to the first bond breaker application of (J-6). Thoroughly saturate the slab with water, and then squeegee off the excess, removing all the free standing water from the surface, then immediately proceed with applying the first application of the (J-6). Delaying the application of the bondbreaker after wetting of the slab will result in over penetration and lessen bondbreaker effectiveness and panel sticking may result. Prior to concrete placement wet down the casting slab with cool water; excessive water should be blown out immediately prior to the concrete placement. Take care when placing concrete to avoid abrading or scouring the bond breaker on the casting bed as braded or scoured spots or areas may result in stuck panels. Discharge the concrete into previously placed fresh concrete. Drying Time Approximately 2 hours at 21°C. Cooler temperatures, higher humidity and thicker bondbreaker coats will extend the dry time. Clean Up Tools and Equipment Use: Mineral Spirits, Naphtha, Xylol Estimated Coverage First Coat 9.8 m2/l Second Coat 13.5 – 17.2 m2/l The above recommended coverage rates are averages based on average site and concrete conditions. Complete and uniform coverage of the casting slab varies considerably with variations in the placing, curing, concrete mix design, density, finishing, and site specific ambient conditions. It is not possible for the recommendations provided by this data sheet to accommodate and account for all variables associated with the coverage rate and application of the bondbreaker. It is the contractor’s responsibility to verify that the applied coverage rates and overall application of the bondbreaker is commensurate with the specific site variables and conditions. Packaging 208 L drums and 20 L pails.

Storage The (J-6) should be stored in a tightly secured original factory container. Store in the horizontal position to prevent moisture accumulation on the drum head. Keep from freezing. Limitations Avoid contamination by storing containers in clean, dry area and keeping lids tightly sealed. The shelf life of (J6) is 12 months when properly stored. Do not spray on reinforcing steel. Not recommended when concrete mix designs using fly ash or other pozzolonic materials without first contacting the Technical Services Dept. for specific recommendations. Fly ash can result in slower concrete strength development. Failure to observe specific application rates and procedures may lead to sticking panels. Not recommended for application to broom finished or otherwise rough, porous or weak unsound concrete. Do not apply in rain or if rain is forecast within 12 hours of the application. Casting slab surfaces exposed to rain may require reapplication of the bondbreaker at a coverage rate at 13.5-17.2 m2/l. Do not apply below 40°F (4°C) or when ambient temperatures are expected to fall below 40°F (4°C) within 12 hours. Not recommended for application to casting slab concrete that has been cured with curing blankets or plastic coverings without first removing the salts from the concrete’s surface before application of the bondbreaker. Surface salts can result in surface defects. Application in two thin coats rather than one thick coat will reduce the dry time. Properly applied, casting beds and tilt panels can normally be coated or sealed after appropriate cleaning and or surface preparation of the surfaces. The manufacture of the coating, paint, sealer, adhesive or other subsequent treatments should be consulted for specific substrate cleaning and preparation requirements and instructions prior to painting. Over application can lead to excessive transfer to the panels and potentially cause problems with subsequent paint adhesion. A mock up test panel and casting surface of any subsequent application of paint, coatings, sealers, hardeners or other membrane forming treatments should

Page 59: Technical Handbook

Sure Lift (J-6) Premium Bond Breaker Technical Data Sheet

 Contact your nearest Tilt‐Lift Equipment branch for the latest Technical and MSDS sheets 

2 Arnold St, Cheltenham, Vic 3192. Phone: 03 9583 0115 Fax: 03 9583 2112 www.tiltlift.com.au 

 12 February 2008         For Commercial / Industrial Use Only                 Page 3 of 3 

always be applied and tested to verify proper coating adhesion and adequate cleaning and surface preparation of the tilt panels. Improper concrete mix designs, overly porous or weak casting slab concrete, failure to properly finish and/or cure the concrete and/or uneven or improper application and insufficient mixing of the bondbreaker can lead to panel sticking. Precautions Harmful if swallowed. DO NOT induce vomiting. If conscious, wash out mouth with water. If swallowed contact a doctor or the Poisons Information Centre immediately (Australia 13 1126; New Zealand 03 4747000) and show container, label or MSDS.

Avoid contact with skin or eyes, wear protective clothing. If eye contact occurs, hold eyelids apart and flush the eye continuously with running water, continue flushing until advised to stop by the Poisons Information Centre or a doctor or for at least 15 minutes. See Material Safety Data Sheet for more detailed information. TECHNICAL SERVICES: Call the technical staff for assistance at:

03 9583 0115 or

Fax: 03 9583 9293                    

WARRANTY Tilt-Lift Equipment (“Tilt-Lift”) warrants for 12 months from the date of manufacture or for the duration of the published product shelf life, whichever is less, that at the time of shipment by Tilt-Lift, the product is free of manufacturing defects and conforms to Tilt-Lift’s product properties in force on the date of acceptance by Tilt-Lift of the order. Tilt-Lift shall only be liable under this warranty if the product has been applied, used, and stored in accordance with Tilt-Lift’s instructions, especially surface preparation and installation, in force on the date of acceptance by Tilt-Lift of the order. The purchaser must examine the product when received and promptly notify Tilt-Lift in writing of any non-conformity before the product is used and no later than 30 days after such non-conformity is first discovered. If Tilt-Lift, in its sole discretion, determines that the product breached the above warranty, it will, in its sole discretion, replace the non-conforming product, refund the purchase price or issue a credit in the amount of the purchase price. This is the sole and exclusive remedy for breach of this warranty. Only a Tilt-Lift officer is authorized to modify this warranty. The information in this data sheet supersedes all other sales information received by the customer during the sales process. THE FOREGOING WARRANTY SHALL BE EXCLUSIVE AND IN LIEU OFANY OTHER WARRANTIES, EXPRESS OR IMPLIED, INCLUDING WARRANTIES OF MERCHANTABILITYAND FITNESS FOR A PARTICULAR PURPOSE, AND ALL OTHER WARRANTIES OTHERWSE ARISING BY OPERATION OF LAW, COURSE OF DEALING, CUSTOM, TRADE OR OTHERWISE. LIMITATION OF LIABILITY Tilt-Lift shall not be liable in contractor in tort (including, without limitation, negligence, strict liability or otherwise) for loss of sales, revenues or profits; cost of capital or funds; business interruption or cost of downtime, loss of use, damage to or loss of use of other property (real or personal); failure to realise expected savings; frustration of economic or business expectations; claims by third parties, or economic losses of any kind; or for any special, incidental, indirect, consequential, punitive or exemplary damages arising in any way out of the performance of, or failure to perform, its obligations under any contract for sale of product, even if Tilt-Lift could foresee or has been advised of the possibility of such damages. The Parties expressly agree that these limitations on damages are allocations of risk constituting, in part, the consideration for this contract, and also that such limitations shall survive the determination of any court of competent jurisdiction that any remedy provided in these terms or available at law fails of its essential purpose.

      

Page 60: Technical Handbook

TILT-LIFT SURE-LIFT WITH DYE J6DChemwatch Independent Material Safety Data SheetIssue Date: 24-Jan-2012 CHEMWATCH 29-98579317SP(cs) Version No:2.0

CD 2011/4 Page 1 of 8

Section 1 - CHEMICAL PRODUCT AND COMPANY IDENTIFICATION

PRODUCT NAMETILT-LIFT SURE-LIFT WITH DYE J6D

PROPER SHIPPING NAMEPETROLEUM DISTILLATES, N.O.S. or PETROLEUM PRODUCTS, N.O.S.(contains Stoddard Solvent)

PRODUCT USE■ Used according to manufacturer's directions.

SUPPLIERCompany: Tilt- Lift Equipment Pty LtdAddress:Unit 4, 24- 27 Olive GroveKEYSBOROUGHVIC, 3173AustraliaTelephone: +61 3 99887701Emergency Tel: +1800 039 008 (24hr)Fax: +61 3 97691039

Section 2 - HAZARDS IDENTIFICATION

STATEMENT OF HAZARDOUS NATUREHAZARDOUS SUBSTANCE. DANGEROUS GOODS. According to the Criteria of NOHSC, and the ADG Code.

RISKRisk Codes Risk PhrasesR10 • Flammable.R51/53 • Toxic to aquatic organisms, may cause long- term adverse

effects in the aquatic environment.R65 • HARMFUL- May cause lung damage if swallowed.R66 • Repeated exposure may cause skin dryness and cracking.

SAFETYSafety Codes Safety PhrasesS23 • Do not breathe gas/fumes/vapour/spray.S24 • Avoid contact with skin.S25 • Avoid contact with eyes.S36 • Wear suitable protective clothing.S37 • Wear suitable gloves.S39 • Wear eye/face protection.S51 • Use only in well ventilated areas.S09 • Keep container in a well ventilated place.S29 • Do not empty into drains.S401 • To clean the floor and all objects contaminated by this material, use water

and detergent.S07 • Keep container tightly closed.S35 • This material and its container must be disposed of in a safe way.S13 • Keep away from food, drink and animal feeding stuffs.S26 • In case of contact with eyes, rinse with plenty of water and contact Doctor or

Poisons Information Centre.S46 • If swallowed, IMMEDIATELY contact Doctor or Poisons Information Centre. (show

this container or label).S57 • Use appropriate container to avoid environmental contamination.S61 • Avoid release to the environment. Refer to special instructions/Safety data

sheets.S60 • This material and its container must be disposed of as hazardous waste.

continued...

Page 61: Technical Handbook

TILT-LIFT SURE-LIFT WITH DYE J6DChemwatch Independent Material Safety Data SheetIssue Date: 24-Jan-2012 CHEMWATCH 29-98579317SP(cs) Version No:2.0

CD 2011/4 Page 2 of 8

Section 3 - COMPOSITION / INFORMATION ON INGREDIENTS

NAME CAS RN %Stoddard Solvent 8052-41-3. 50-75naphtha petroleum, light aromatic solvent 64742-95-6. 10-25

Section 4 - FIRST AID MEASURES

SWALLOWED• If swallowed do NOT induce vomiting.• If vomiting occurs, lean patient forward or place on left side (head-down position, if possible) to maintain open airway and prevent aspiration.• Observe the patient carefully.• Never give liquid to a person showing signs of being sleepy or with reduced awareness; i.e. becoming unconscious.• Avoid giving milk or oils.• Avoid giving alcohol.• If spontaneous vomiting appears imminent or occurs, hold patient's head down, lower than their hips to help avoid possible aspiration of vomitus.

EYE■ If this product comes in contact with the eyes:• Wash out immediately with fresh running water.• Ensure complete irrigation of the eye by keeping eyelids apart and away from eye and moving the eyelids by occasionally lifting the upper and lower lids.• Seek medical attention without delay; if pain persists or recurs seek medical attention.• Removal of contact lenses after an eye injury should only be undertaken by skilled personnel.

SKIN■ If skin contact occurs:• Immediately remove all contaminated clothing, including footwear.• Flush skin and hair with running water (and soap if available).• Seek medical attention in event of irritation.

INHALED• If fumes or combustion products are inhaled remove from contaminated area.• Lay patient down. Keep warm and rested.• Prostheses such as false teeth, which may block airway, should be removed, where possible, prior to initiating first aid procedures.• Apply artificial respiration if not breathing, preferably with a demand valve resuscitator, bag-valve mask device, or pocket mask as trained. Perform CPR if necessary.

NOTES TO PHYSICIAN■ For acute or short term repeated exposures to petroleum distillates or related hydrocarbons:• Primary threat to life, from pure petroleum distillate ingestion and/or inhalation, is respiratory failure.• Patients should be quickly evaluated for signs of respiratory distress (e.g. cyanosis, tachypnoea, intercostal retraction,

obtundation) and given oxygen. Patients with inadequate tidal volumes or poor arterial blood gases (pO2 50 mm Hg) should beintubated.

• Arrhythmias complicate some hydrocarbon ingestion and/or inhalation and electrocardiographic evidence of myocardial injury hasbeen reported; intravenous lines and cardiac monitors should be established in obviously symptomatic patients. The lungsexcrete inhaled solvents, so that hyperventilation improves clearance.

• A chest x-ray should be taken immediately after stabilisation of breathing and circulation to document aspiration and detectthe presence of pneumothorax.

Any material aspirated during vomiting may produce lung injury. Therefore emesis should not be induced mechanically orpharmacologically.

Section 5 - FIRE FIGHTING MEASURES

EXTINGUISHING MEDIA• Foam.• Dry chemical powder.• BCF (where regulations permit).• Carbon dioxide.

FIRE FIGHTING• Alert Fire Brigade and tell them location and nature of hazard.• May be violently or explosively reactive.

continued...

Page 62: Technical Handbook

TILT-LIFT SURE-LIFT WITH DYE J6DChemwatch Independent Material Safety Data SheetIssue Date: 24-Jan-2012 CHEMWATCH 29-98579317SP(cs) Version No:2.0

CD 2011/4 Page 3 of 8Section 5 - FIRE FIGHTING MEASURES

• Wear breathing apparatus plus protective gloves.• Prevent, by any means available, spillage from entering drains or water course.

FIRE/EXPLOSION HAZARD• Liquid and vapour are flammable.• Moderate fire hazard when exposed to heat or flame.• Vapour forms an explosive mixture with air.• Moderate explosion hazard when exposed to heat or flame.Combustion products include: carbon monoxide (CO), carbon dioxide (CO2), other pyrolysis products typical of burning organicmaterial.Contains low boiling substance: Closed containers may rupture due to pressure buildup under fire conditions.

FIRE INCOMPATIBILITY• Avoid contamination with oxidising agents i.e. nitrates, oxidising acids, chlorine bleaches, pool chlorine etc. as ignition may

result.

HAZCHEM3Y

Section 6 - ACCIDENTAL RELEASE MEASURES

MINOR SPILLS• Remove all ignition sources.• Clean up all spills immediately.• Avoid breathing vapours and contact with skin and eyes.• Control personal contact by using protective equipment.

MAJOR SPILLS• Clear area of personnel and move upwind.• Alert Fire Brigade and tell them location and nature of hazard.• May be violently or explosively reactive.• Wear breathing apparatus plus protective gloves.

Personal Protective Equipment advice is contained in Section 8 of the MSDS.

Section 7 - HANDLING AND STORAGE

PROCEDURE FOR HANDLING• Containers, even those that have been emptied, may contain explosive vapours.• Do NOT cut, drill, grind, weld or perform similar operations on or near containers.Contains low boiling substance:Storage in sealed containers may result in pressure buildup causing violent rupture of containers not rated appropriately.• Check for bulging containers.• Vent periodically• Always release caps or seals slowly to ensure slow dissipation of vapours.• DO NOT allow clothing wet with material to stay in contact with skin.• Electrostatic discharge may be generated during pumping - this may result in fire.• Ensure electrical continuity by bonding and grounding (earthing) all equipment.• Restrict line velocity during pumping in order to avoid generation of electrostatic discharge (<=1 m/sec until fill pipe submerged to twice its diameter, then <= 7 m/sec).• Avoid splash filling.• Avoid all personal contact, including inhalation.• Wear protective clothing when risk of overexposure occurs.• Use in a well-ventilated area.• Prevent concentration in hollows and sumps.

SUITABLE CONTAINER• Packing as supplied by manufacturer.• Plastic containers may only be used if approved for flammable liquid.• Check that containers are clearly labelled and free from leaks.• For low viscosity materials (i) : Drums and jerry cans must be of the non-removable head type. (ii) : Where a can is to be used as an inner package, the can must have a screwed enclosure.• For materials with a viscosity of at least 2680 cSt. (23 deg. C)• For manufactured product having a viscosity of at least 250 cSt. (23 deg. C)• Manufactured product that requires stirring before use and having a viscosity of at least 20 cSt (25 deg. C).

continued...

Page 63: Technical Handbook

TILT-LIFT SURE-LIFT WITH DYE J6DChemwatch Independent Material Safety Data SheetIssue Date: 24-Jan-2012 CHEMWATCH 29-98579317SP(cs) Version No:2.0

CD 2011/4 Page 4 of 8Section 7 - HANDLING AND STORAGE

STORAGE INCOMPATIBILITY• Avoid reaction with oxidising agents.

STORAGE REQUIREMENTS• Store in original containers in approved flammable liquid storage area.• Store away from incompatible materials in a cool, dry, well-ventilated area.• DO NOT store in pits, depressions, basements or areas where vapours may be trapped.• No smoking, naked lights, heat or ignition sources.

Section 8 - EXPOSURE CONTROLS / PERSONAL PROTECTION

EXPOSURE CONTROLS

MATERIAL DATANAPHTHA PETROLEUM, LIGHT AROMATIC SOLVENT:STODDARD SOLVENT:TILT-LIFT SURE-LIFT WITH DYE J6D:

■ Sensory irritants are chemicals that produce temporary and undesirable side-effects on the eyes, nose or throat.Historically occupational exposure standards for these irritants have been based on observation of workers' responses to variousairborne concentrations.

NAPHTHA PETROLEUM, LIGHT AROMATIC SOLVENT:STODDARD SOLVENT:TILT-LIFT SURE-LIFT WITH DYE J6D:

■ Odour threshold: 0.25 ppm.The TLV-TWA is protective against ocular and upper respiratory tract irritation and is recommended for bulk handling of

gasoline based on calculations of hydrocarbon content of gasoline vapour.

STODDARD SOLVENT:TILT-LIFT SURE-LIFT WITH DYE J6D:

■ For white spirit:Low and high odour thresholds of 5.25 and 157.5 mg/m3, respectively, were considered to provide a rather useful index of odour

as a warning property.The TLV-TWA is calculated from data on the toxicities of the major ingredients and is intended to minimise the potential for

irritative and narcotic effects, polyneuropathy and kidney damage produced by vapours.<</>.

NAPHTHA PETROLEUM, LIGHT AROMATIC SOLVENT:

REL TWA: 25-100 ppm*, 125 mg/m3* [Various Manufacturers]CEL TWA: 50 ppm, 125 mg/m3

PERSONAL PROTECTION

RESPIRATOR•Type A Filter of sufficient capacity. (AS/NZS 1716 & 1715, EN 143:2000 & 149:2001, ANSI Z88 or national equivalent)

EYE• Safety glasses with side shields.• Chemical goggles.• Contact lenses may pose a special hazard; soft contact lenses may absorb and concentrate irritants. A written policy document,

describing the wearing of lens or restrictions on use, should be created for each workplace or task. This should include areview of lens absorption and adsorption for the class of chemicals in use and an account of injury experience. Medical andfirst-aid personnel should be trained in their removal and suitable equipment should be readily available. In the event ofchemical exposure, begin eye irrigation immediately and remove contact lens as soon as practicable. Lens should be removed atthe first signs of eye redness or irritation - lens should be removed in a clean environment only after workers have washedhands thoroughly. [CDC NIOSH Current Intelligence Bulletin 59], [AS/NZS 1336 or national equivalent].

HANDS/FEET• Wear chemical protective gloves, eg. PVC.• Wear safety footwear or safety gumboots, eg. Rubber.Suitability and durability of glove type is dependent on usage. Important factors in the selection of gloves include:• frequency and duration of contact,• chemical resistance of glove material,• glove thickness and• dexterity.

continued...

Page 64: Technical Handbook

TILT-LIFT SURE-LIFT WITH DYE J6DChemwatch Independent Material Safety Data SheetIssue Date: 24-Jan-2012 CHEMWATCH 29-98579317SP(cs) Version No:2.0

CD 2011/4 Page 5 of 8Section 8 - EXPOSURE CONTROLS / PERSONAL PROTECTION

OTHER• Overalls.• PVC Apron.• PVC protective suit may be required if exposure severe.• Eyewash unit.• Some plastic personal protective equipment (PPE) (e.g. gloves, aprons, overshoes) are not recommended as they may produce

static electricity.• For large scale or continuous use wear tight-weave non-static clothing (no metallic fasteners, cuffs or pockets), non sparking

safety footwear.

ENGINEERING CONTROLS■ Engineering controls are used to remove a hazard or place a barrier between the worker and the hazard. Well-designedengineering controls can be highly effective in protecting workers and will typically be independent of worker interactions toprovide this high level of protection.The basic types of engineering controls are:Process controls which involve changing the way a job activity or process is done to reduce the risk.Enclosure and/or isolation of emission source which keeps a selected hazard "physically" away from the worker and ventilationthat strategically "adds" and "removes" air in the work environment.

Section 9 - PHYSICAL AND CHEMICAL PROPERTIES

APPEARANCEFlammable liquid with a characteristic odour; does not mix with water.

PHYSICAL PROPERTIESLiquid.Does not mix with water.Floats on water.

State Liquid Molecular Weight Not ApplicableMelting Range (°C) Not Available Viscosity Not AvailableBoiling Range (°C) 162 Solubility in water (g/L) ImmiscibleFlash Point (°C) 40 pH (1% solution) Not AvailableDecomposition Temp (°C) Not Available pH (as supplied) Not A vailableAutoignition Temp (°C) 230 Vapour Pressure (kPa) Not Availa bleUpper Explosive Limit (%) 7.5 Specific Gravity (water=1) 0.77Lower Explosive Limit (%) 0.7 Relative Vapour Density Not Available

(air=1)Volatile Component (%vol) Not Available Evaporation Rate Not Available

Section 10 - STABILITY AND REACTIVITY

CONDITIONS CONTRIBUTING TO INSTABILITY• Presence of incompatible materials.• Product is considered stable.• Hazardous polymerisation will not occur.For incompatible materials - refer to Section 7 - Handling and Storage.

Section 11 - TOXICOLOGICAL INFORMATION

POTENTIAL HEALTH EFFECTS

ACUTE HEALTH EFFECTS

SWALLOWED■ Swallowing of the liquid may cause aspiration into the lungs with the risk of chemical pneumonitis; serious consequences mayresult. (ICSC13733).Accidental ingestion of the material may be damaging to the health of the individual.Ingestion of petroleum hydrocarbons can irritate the pharynx, oesophagus, stomach and small intestine, and cause swellings andulcers of the mucous. Symptoms include a burning mouth and throat; larger amounts can cause nausea and vomiting, narcosis,weakness, dizziness, slow and shallow breathing, abdominal swelling, unconsciousness and convulsions. Damage to the heart musclecan produce heart beat irregularities, ventricular fibrillation (fatal) and ECG changes. The central nervous system can bedepressed. Light species can cause a sharp tingling of the tongue and cause loss of sensation there. Aspiration can cause cough,gagging, pneumonia with swelling and bleeding.

continued...

Page 65: Technical Handbook

TILT-LIFT SURE-LIFT WITH DYE J6DChemwatch Independent Material Safety Data SheetIssue Date: 24-Jan-2012 CHEMWATCH 29-98579317SP(cs) Version No:2.0

CD 2011/4 Page 6 of 8Section 11 - TOXICOLOGICAL INFORMATION

EYE■ There is some evidence to suggest that this material can cause eye irritation and damage in some persons.Direct eye contact with petroleum hydrocarbons can be painful, and the corneal epithelium may be temporarily damaged. Aromaticspecies can cause irritation and excessive tear secretion.The vapour when concentrated has pronounced eye irritation effects and this gives some warning of high vapour concentrations. Ifeye irritation occurs seek to reduce exposure with available control measures, or evacuate area.

SKIN■ Repeated exposure may cause skin cracking, flaking or drying following normal handling and use.The material may accentuate any pre-existing dermatitis condition.Aromatic hydrocarbons may produce sensitivity and redness of the skin. They are not likely to be absorbed into the body throughthe skin but branched species are more likely to.There is some evidence to suggest that this material can cause inflammation of the skin on contact in some persons.Entry into the blood-stream, through, for example, cuts, abrasions or lesions, may produce systemic injury with harmful effects.Examine the skin prior to the use of the material and ensure that any external damage is suitably protected.

INHALED■ Inhaling high concentrations of mixed hydrocarbons can cause narcosis, with nausea, vomiting and lightheadedness. Low molecularweight (C2-C12) hydrocarbons can irritate mucous membranes and cause incoordination, giddiness, nausea, vertigo, confusion,headache, appetite loss, drowsiness, tremors and stupor. Massive exposures can lead to severe central nervous system depression,deep coma and death. Convulsions can occur due to brain irritation and/or lack of oxygen. Permanent scarring may occur, withepileptic seizures and brain bleeds occurring months after exposure. Respiratory system effects include inflammation of the lungswith oedema and bleeding. Lighter species mainly cause kidney and nerve damage; the heavier paraffins and olefins are especiallyirritant to the respiratory system. Alkenes produce pulmonary oedema at high concentrations. Liquid paraffins may producesensation loss and depressant actions leading to weakness, dizziness, slow and shallow respiration, unconsciousness, convulsionsand death. C5-7 paraffins may also produce multiple nerve damage. Aromatic hydrocarbons accumulate in lipid rich tissues(typically the brain, spinal cord and peripheral nerves) and may produce functional impairment manifested by nonspecific symptomssuch as nausea, weakness, fatigue, vertigo; severe exposures may produce inebriation or unconsciousness. Many of the petroleumhydrocarbons can sensitise the heart and may cause ventricular fibrillation, leading to death.Central nervous system (CNS) depression may include general discomfort, symptoms of giddiness, headache, dizziness, nausea,anaesthetic effects, slowed reaction time, slurred speech and may progress to unconsciousness. Serious poisonings may result inrespiratory depression and may be fatal.Inhalation of high concentrations of gas/vapour causes lung irritation with coughing and nausea, central nervous depression withheadache and dizziness, slowing of reflexes, fatigue and inco-ordination.Exposure to white spirit may cause nausea and vertigo.Inhalation of vapours or aerosols (mists, fumes), generated by the material during the course of normal handling, may be damagingto the health of the individual.

CHRONIC HEALTH EFFECTS■ Prolonged or repeated skin contact may cause drying with cracking, irritation and possible dermatitis following.Substance accumulation, in the human body, may occur and may cause some concern following repeated or long-term occupationalexposure.Constant or exposure over long periods to mixed hydrocarbons may produce stupor with dizziness, weakness and visual disturbance,weight loss and anaemia, and reduced liver and kidney function. Skin exposure may result in drying and cracking and redness ofthe skin. Chronic exposure to lighter hydrocarbons can cause nerve damage, peripheral neuropathy, bone marrow dysfunction andpsychiatric disorders as well as damage the liver and kidneys.Immersion of the hands and forearms in white spirits may quickly result in inflammation of the skin and follicles. Workersexposed to white spirit have reported nausea and vomiting and one worker has been reported to develop aplastic anaemia, bonemarrow depression and this person later died from septicaemia. Bone marrow depression may be due to the presence of compoundstoxic to it, for example, benzene.Chronic solvent inhalation exposures may result in nervous system impairment and liver and blood changes. [PATTYS].

TOXICITY AND IRRITATION■ for petroleum:This product contains benzene which is known to cause acute myeloid leukaemia and n-hexane which has been shown to metabolize tocompounds which are neuropathic.This product contains toluene.This product contains ethyl benzene and naphthalene from which there is evidence of tumours in rodentsCarcinogenicity: Inhalation exposure to mice causes liver tumours, which are not considered relevant to humans.

Section 12 - ECOLOGICAL INFORMATION

Toxic to aquatic organisms, may cause long-term adverse effects in the aquatic environment.This material and its container must be disposed of as hazardous waste.Avoid release to the environment.Refer to special instructions/ safety data sheets.

continued...

Page 66: Technical Handbook

TILT-LIFT SURE-LIFT WITH DYE J6DChemwatch Independent Material Safety Data SheetIssue Date: 24-Jan-2012 CHEMWATCH 29-98579317SP(cs) Version No:2.0

CD 2011/4 Page 7 of 8Section 12 - ECOLOGICAL INFORMATION

EcotoxicityIngredient Persistence: Persistence: Air Bioaccumulation Mobility

Water/SoilStoddard Solvent No Data No Data

Available Availablenaphtha petroleum, light No Data No Dataaromatic solvent Available Available

Section 13 - DISPOSAL CONSIDERATIONS

■ Legislation addressing waste disposal requirements may differ by country, state and/ or territory. Each user must refer to laws operating in their area.A Hierarchy of Controls seems to be common - the user should investigate:• Reduction.• DO NOT allow wash water from cleaning or process equipment to enter drains.• It may be necessary to collect all wash water for treatment before disposal.• In all cases disposal to sewer may be subject to local laws and regulations and these should be considered first.• Where in doubt contact the responsible authority.• Recycle wherever possible.• Consult manufacturer for recycling options or consult local or regional waste management authority for disposal if no suitable treatment or disposal facility can be identified.• Dispose of by: burial in a land-fill specifically licenced to accept chemical and / or pharmaceutical wastes or Incineration in a licenced apparatus (after admixture with suitable combustible material).• Decontaminate empty containers. Observe all label safeguards until containers are cleaned and destroyed.

Section 14 - TRANSPORTATION INFORMATION

Labels Required: FLAMMABLE LIQUID

HAZCHEM: 3Y (ADG7)

ADG7:Class or Division: 3 Subsidiary Risk: NoneUN No.: 1268 Packing Group: IIISpecial Provision: 223, AU02 Limited Quantity: 5 LPortable Tanks & Bulk T4 Portable Tanks & Bulk TP1, TP29Containers - Containers - SpecialInstruction: Provision:Packagings & IBCs - None Packagings & IBCs - P001, IBC03, LP01Packing Instruction: Special Packing

Provision:Name and Description: PETROLEUM DISTILLATES, N.O.S. or PETROLEUM

PRODUCTS, N.O.S. (see 3.2.5 for relevant [AUST.] entries) (containsStoddard Solvent)

Land Transport UNDG:Class or division: 3 Subsidiary risk: NoneUN No.: 1268 UN packing group: IIIShipping Name:PETROLEUM DISTILLATES, N.O.S. or PETROLEUM PRODUCTS,

N.O.S. (contains Stoddard Solvent)

Air Transport IATA:ICAO/IATA Class: 3 ICAO/IATA Subrisk: NoneUN/ID Number: 1268 Packing Group: IIISpecial provisions: A3

Shipping name:PETROLEUM DISTILLATES, N.O.S. or PETROLEUM PRODUCTS, N.O.S.(contains Stoddard Solvent)

Maritime Transport IMDG:IMDG Class: 3 IMDG Subrisk: NoneUN Number: 1268 Packing Group: IIIEMS Number: F- E, S- E Special provisions: 223 955Limited Quantities: 5 L Marine Pollutant: YesShipping name:PETROLEUM DISTILLATES, N.O.S. or PETROLEUM PRODUCTS, N.O.S.(contains Stoddard Solvent)

continued...

Page 67: Technical Handbook

TILT-LIFT SURE-LIFT WITH DYE J6DChemwatch Independent Material Safety Data SheetIssue Date: 24-Jan-2012 CHEMWATCH 29-98579317SP(cs) Version No:2.0

CD 2011/4 Page 8 of 8

Section 15 - REGULATORY INFORMATION

POISONS SCHEDULE S5

REGULATIONS

Regulations for ingredients

Stoddard Solvent (CAS: 8052-41-3,64742-47-8) is found on the following regulatory lists;"Australia Hazardous Substances","Australia Inventory of Chemical Substances (AICS)"

naphtha petroleum, light aromatic solvent (CAS: 64742-95-6) is found on the following regulatory lists;"Australia Hazardous Substances","Australia Inventory of Chemical Substances (AICS)"

No data for Tilt-Lift Sure-Lift With Dye J6D (CW: 29-9857)

Section 16 - OTHER INFORMATION

INGREDIENTS WITH MULTIPLE CAS NUMBERSIngredient Name CASStoddard Solvent 8052- 41- 3, 64742- 47- 8

■ Classification of the preparation and its individual components has drawn on official and authoritative sources as well as independent review by the Chemwatch Classification committee using available literature references.A list of reference resources used to assist the committee may be found at: www.chemwatch.net/references.

■ The (M)SDS is a Hazard Communication tool and should be used to assist in the Risk Assessment. Many factors determine whether the reported Hazards are Risks in the workplace or other settings.

This document is copyright. Apart from any fair dealing for the purposes of private study, research, review orcriticism, as permitted under the Copyright Act, no part may be reproduced by any process without writtenpermission from CHEMWATCH. TEL (+61 3) 9572 4700.

Issue Date: 24-Jan-2012Print Date: 24-Jan-2012

This is the end of the MSDS.

Page 68: Technical Handbook

Sure Lift Water Based (J-6WB) Water Based Bond Breaker Technical Data Sheet

 Contact your nearest Tilt‐Lift Equipment branch for the latest Technical and MSDS sheets 

2 Arnold St, Cheltenham, Vic 3192. Phone: 03 9583 0115 Fax: 03 9583 9293 www.tiltlift.com.au 

 29th April 2009          For Commercial / Industrial Use Only                 Page 1 of 3 

Product description  SURE‐LIFT J‐6 WB is a liquid, V.O.C. compliant, water‐based, reactive and membrane forming bondbreaker for use in tilt wall construction. J‐6 WB is a special formula of polymers and propriety ingredients designed to provide clean, easy lifting of tilt panels. J‐6 WB has a fugitive dye for ease of visual inspection during application and is also available without the dye upon special request. Use J‐6 WB is designed to allow for easy lifting of tilt wall panels from properly designed, finished and cured concrete casting beds. Benefits • Water Based •  Very low V.O.C. • Panels lift cleanly • Minimal panel residue • Resists construction foot traffic  VOC Less than 100 grams per litre.  NOTE: Prior to application, read and follow all current (verify literature is current) literature instructions, limitations and precautions in this data sheet, on the MSDS and on the label of the container prior to use.  The instructions provided by this technical data sheet to general average site conditions such as concrete mix designs, finishing techniques, and site ambient conditions. Test applications should always be made by the end user prior to overall use of the bondbreaker.  This is at a minimum necessary to verify that the amounts of bondbreaker purchased and anticipated to be applied is sufficient to result in the correct application coverage rates and end performance of the product based upon the specific site conditions.  The concrete casting slab, waste slabs and tilt wall panels must be properly designed, finished and cured in accordance with industry standards and guidelines.  Spray Equipment The (J‐6WB) Bondbreaker must be applied by a high quality “low‐pressure pump‐up type sprayer” such as manufactured by Chapin or others. The tip size must be able to produce a well atomized spray pattern. The sprayer must be kept under sufficient pressure to correctly atomize the (J‐6WB) without streaming, tailing, or spitting. A 1.9 litre/minute tip is generally 

recommended for most applications. The use of an improper sprayer, a dirty sprayer, lowers than adequate pressure or wrong tip can result in an uneven application, and either over or under application.  APPLICATION Mixing Thoroughly agitate the J‐6 WB prior to each use. Each bondbreaker drum will be supplied with an integral drum mixer. Use only the built in drum mixer to achieve proper mixing. Proper mixing of the bondbreaker prior to use is extremely important. The bondbreaker drum must be in a vertical position to effect proper mixing. Vigorously mix each drum continuously for a minimum of 3 minutes. Re‐mix if left to set overnight. Failure to properly mix and keep the bondbreaker mixed over time will result in sticking panels The casting bed should be free of all foreign material, salts, laitance and the J‐6 WB protected, while drying, from all contaminants or particulate matter (i.e., dust, dirt, etc.).  First Bondbreaker Coat The casting bed should be free of all foreign material, salts, laitance and the (J‐6WB) protected, while drying, from all contaminants or particulate matter (i.e., dust, dirt, etc.). Just prior to placing the reinforcing steel, and within two weeks of pouring the panels, spray apply the first bondbreaker application of (J‐6WB) at 9.8m2/L to the point of rejection. Specific site conditions may dictate coverage rates other than the normal recommended coverage rates. Adjust the actual applied rates accordingly. Second Bondbreaker Coat Wait until first coat dries, approximately 2 hours depending on temperature and humidity, and apply a second coat at right angles to the previous coat. Coverage for the second coat will typically be 13.5‐17.2 m2/L. If light or white spots appear within 10‐40 minutes after spraying, those areas are extra porous and should be fogged with water followed by a reapplication of the (J‐6WB) 13.5‐17.2 m2/L. Specific site  conditions may dictate coverage rates other than the normal recommended coverage rates. Adjust the actual applied rates accordingly.  The number of bondbreaker coats and coverage rates necessary to achieve a complete uniform coverage is highly dependent on the concrete casting slab mix design as well as its inherent porosity, finishing techniques, and other related site specific ambient conditions. Adequate bondbreaker application is in large part dependent upon development of a uniform soap like feel of the bondbreaker treated surface as 

Page 69: Technical Handbook

Sure Lift Water Based (J-6WB) Water Based Bond Breaker Technical Data Sheet

 Contact your nearest Tilt‐Lift Equipment branch for the latest Technical and MSDS sheets 

2 Arnold St, Cheltenham, Vic 3192. Phone: 03 9583 0115 Fax: 03 9583 9293 www.tiltlift.com.au 

 29th April 2009          For Commercial / Industrial Use Only                 Page 2 of 3 

well as beading of water. Bondbreaker can also be checked by rolling up a small ball like amount under thumb pressure. Extremely porous or rough casting slabs will necessitate successive additional coats of bondbreaker to achieve a consistent uniform membrane of the correct coverage rate and membrane thickness. Extremely porous or otherwise absorptive slabs can also be fogged with water to a saturated surface dry (SSD) condition prior to application of bondbreaker.  Bondbreaker Test To verify the integrity of the bondbreaker coat, sprinkle water on the casting bed. (Water should bead up as on a freshly waxed automobile). The applied, dried material should have soap like feel, uniformly over the substrate. The application should appear uniform and continuous, with light areas requiring re‐application. Failure to verify proper uniform application and coverage rates can result in panel sticking. Testing must be performed over a large enough surface area in an adequate testing frequency to provide accurate and meaningful results. It is entirely the contractor’s responsibility to verify that the bondbreaker has been evenly and uniformly applied at the recommended application/coverage rates given the various concrete mix design, densities, finishes, and porosity conditions on each project  Hot Weather Procedures In hot weather, the casting slab must be flooded with water to reduce its porosity and cool it down prior to the first bond breaker application of (J‐6WB). Thoroughly saturate the slab with water, and then squeegee off the excess, removing all the free standing water from the surface, then immediately proceed with applying the first application of the (J‐6WB). Delaying the application of the bondbreaker after wetting of the slab will result in over penetration and lessen bondbreaker effectiveness and panel sticking may result. Prior to concrete placement wet down the casting slab with cool water; excessive water should be blown out immediately prior to the concrete placement. Take care when placing concrete to avoid abrading or scouring the bond breaker on the casting bed as braded or scoured spots or areas may result in stuck panels. Discharge the concrete into previously placed fresh concrete.  Drying Time Approximately 2 hours at 21°C. Cooler temperatures, higher humidity and thicker bondbreaker coats will extend the dry time. 

CLEAN UP For tools & equipment use warm, soapy water. After the product dries, solvents such as xylene or mineral spirits may be necessary to remove the product.  Estimated Coverage First Coat  9.8 m2/L Second Coat  13.5 – 17.2 m2/L  The above recommended coverage rates are averages based on average site and concrete conditions. Complete and uniform coverage of the casting slab varies considerably with variations in the placing, curing, concrete mix design, density, finishing, and site specific ambient conditions. It is not possible for the recommendations provided by this data sheet to accommodate and account for all variables associated with the coverage rate and application of the bondbreaker. It is the contractor’s responsibility to verify that the applied coverage rates and overall application of the bondbreaker is commensurate with the specific site variables and conditions.  Packaging 208 L drums and 20 L pails.   Storage The (J‐6WB) should be stored in a tightly secured original factory container. Store in the horizontal position to prevent moisture accumulation on the drum head. Keep from freezing.  Limitations Avoid contamination by storing containers in clean, dry area and keeping lids tightly sealed. The shelf life of (J6) is 9 months when properly stored. Do not spray on reinforcing steel.  Never apply bondbreaker unless it has been thoroughly and properly mixed before use.  Not recommended when concrete mix designs using fly ash or other pozzolanic materials. Fly ash can result in slower concrete strength development. Failure to observe specific application rates and procedures may lead to sticking panels.  Not recommended for application to broom finished or otherwise rough, porous or weak unsound concrete.  Bondbreaker should be re‐mixed at the start of each day.    

Page 70: Technical Handbook

Sure Lift Water Based (J-6WB) Water Based Bond Breaker Technical Data Sheet

 Contact your nearest Tilt‐Lift Equipment branch for the latest Technical and MSDS sheets 

2 Arnold St, Cheltenham, Vic 3192. Phone: 03 9583 0115 Fax: 03 9583 9293 www.tiltlift.com.au 

 29th April 2009          For Commercial / Industrial Use Only                 Page 3 of 3 

Do not apply in rain or if rain is forecast within 12 hours of the application. Casting slab surfaces exposed to rain may require reapplication of the bondbreaker at a coverage rate at 13.5‐17.2 m2/l.  Do not apply below 4°C or when ambient temperatures are expected to fall below 4°C within 12 hours.  Not recommended for application to casting slab concrete that has been cured with curing blankets or plastic coverings without first removing the salts from the concrete’s surface before application of the bondbreaker. Surface salts can result in surface defects.  Application in two thin coats rather than one thick coat will reduce the dry time.  Properly applied, casting beds and tilt panels can normally be coated or sealed after appropriate cleaning and or surface preparation of the surfaces. The manufacture of the coating, paint, sealer, adhesive or other subsequent treatments should be consulted for specific substrate cleaning and preparation requirements and instructions prior to painting.  Over application can lead to excessive transfer to the panels and potentially cause problems with subsequent paint adhesion. A mock up test panel and casting surface of any subsequent application of paint, coatings, sealers, hardeners or other membrane forming treatments should always be applied and tested to verify proper coating adhesion and adequate cleaning and surface preparation of the tilt panels.  Improper concrete mix designs, overly porous or weak casting slab concrete, failure to properly finish and/or cure the concrete and/or uneven or improper application and insufficient mixing of the bondbreaker can lead to panel sticking.  Precautions Harmful if swallowed. DO NOT induce vomiting.  If conscious, wash out mouth with water. If swallowed contact a doctor or the Poisons Information Centre immediately (Australia 13 1126; New Zealand 03 4747000) and show container, label or MSDS. 

Avoid contact with skin or eyes, wear protective clothing.  If eye contact occurs, hold eyelids apart and flush the eye continuously with running water, continue flushing until advised to stop by the Poisons Information Centre or a doctor or for at least 15 minutes. 

See Material Safety Data Sheet for more detailed information.  TECHNICAL SERVICES: Call the technical staff for assistance at:   

03 9583 0115 or 

Fax: 03 9583 9293                        WARRANTY Tilt-Lift Equipment (“Tilt-Lift”) warrants for 12 months from the date of manufacture or for the duration of the published product shelf life, whichever is less, that at the time of shipment by Tilt-Lift, the product is free of manufacturing defects and conforms to Tilt-Lift’s product properties in force on the date of acceptance by Tilt-Lift of the order. Tilt-Lift shall only be liable under this warranty if the product has been applied, used, and stored in accordance with Tilt-Lift’s instructions, especially surface preparation and installation, in force on the date of acceptance by Tilt-Lift of the order. The purchaser must examine the product when received and promptly notify Tilt-Lift in writing of any non-conformity before the product is used and no later than 30 days after such non-conformity is first discovered. If Tilt-Lift, in its sole discretion, determines that the product breached the above warranty, it will, in its sole discretion, replace the non-conforming product, refund the purchase price or issue a credit in the amount of the purchase price. This is the sole and exclusive remedy for breach of this warranty. Only a Tilt-Lift officer is authorized to modify this warranty. The information in this data sheet supersedes all other sales information received by the customer during the sales process. THE FOREGOING WARRANTY SHALL BE EXCLUSIVE AND IN LIEU OFANY OTHER WARRANTIES, EXPRESS OR IMPLIED, INCLUDING WARRANTIES OF MERCHANTABILITYAND FITNESS FOR A PARTICULAR PURPOSE, AND ALL OTHER WARRANTIES OTHERWSE ARISING BY OPERATION OF LAW, COURSE OF DEALING, CUSTOM, TRADE OR OTHERWISE. LIMITATION OF LIABILITY Tilt-Lift shall not be liable in contractor in tort (including, without limitation, negligence, strict liability or otherwise) for loss of sales, revenues or profits; cost of capital or funds; business interruption or cost of downtime, loss of use, damage to or loss of use of other property (real or personal); failure to realise expected savings; frustration of economic or business expectations; claims by third parties, or economic losses of any kind; or for any special, incidental, indirect, consequential, punitive or exemplary damages arising in any way out of the performance of, or failure to perform, its obligations under any contract for sale of product, even if Tilt-Lift could foresee or has been advised of the possibility of such damages. The Parties expressly agree that these limitations on damages are allocations of risk constituting, in part, the consideration for this contract, and also that such limitations shall survive the determination of any court of competent jurisdiction that any remedy provided in these terms or available at law fails of its essential purpose.

 

Page 71: Technical Handbook

J6WBChemwatch Independent Material Safety Data SheetIssue Date: 11-May-2012 CHEMWATCH 15-1582A317LP Version No:2.0

CD 2012/2 Page 1 of 8

Section 1 - CHEMICAL PRODUCT AND COMPANY IDENTIFICATION

PRODUCT NAMEJ-6 WB

PRODUCT USE■ Used according to manufacturer's directions.

SUPPLIERCompany: Tilt- Lift Equipment Pty LtdAddress:Unit 4, 25- 27 Olive GroveKeysboroughVIC, 3173AustraliaTelephone: +61 3 9988 7701Emergency Tel:+1800 039 008 (24hr)Fax: +61 3 9769 1039

Section 2 - HAZARDS IDENTIFICATION

STATEMENT OF HAZARDOUS NATURENON-HAZARDOUS SUBSTANCE. NON-DANGEROUS GOODS. According to NOHSC Criteria, and ADG Code.

RISK•None under normal operating conditions.

Section 3 - COMPOSITION / INFORMATION ON INGREDIENTS

NAME CAS RN %tall oil fatty acids 61790-12-3 <10ingredients nonhazardous, includingwater 7732-18-5 >60

Section 4 - FIRST AID MEASURES

SWALLOWED• If swallowed do NOT induce vomiting.• If vomiting occurs, lean patient forward or place on left side (head-down position, if possible) to maintain open airway and prevent aspiration.• Observe the patient carefully.• Never give liquid to a person showing signs of being sleepy or with reduced awareness; i.e. becoming unconscious.• Give water to rinse out mouth, then provide liquid slowly and as much as casualty can comfortably drink.• Seek medical advice.

EYE■ If this product comes in contact with the eyes:

continued...

Page 72: Technical Handbook

J6WBChemwatch Independent Material Safety Data SheetIssue Date: 11-May-2012 CHEMWATCH 15-1582A317LP Version No:2.0

CD 2012/2 Page 2 of 8Section 4 - FIRST AID MEASURES

• Wash out immediately with fresh running water.• Ensure complete irrigation of the eye by keeping eyelids apart and away from eye and moving the eyelids by occasionally lifting the upper and lower lids.• Seek medical attention without delay; if pain persists or recurs seek medical attention.• Removal of contact lenses after an eye injury should only be undertaken by skilled personnel.

SKIN■ If skin or hair contact occurs:• Flush skin and hair with running water (and soap if available).• Seek medical attention in event of irritation.

INHALED• If fumes, aerosols or combustion products are inhaled remove from contaminated area.• Other measures are usually unnecessary.

NOTES TO PHYSICIAN■ Treat symptomatically.

Section 5 - FIRE FIGHTING MEASURES

EXTINGUISHING MEDIA■ The product contains a substantial proportion of water, therefore there are no restrictions on the type ofextinguishing media which may be used. Choice of extinguishing media should take into account surroundingareas.Though the material is non-combustible, evaporation of water from the mixture, caused by the heat of nearbyfire, may produce floating layers of combustible substances.In such an event consider:• foam.• dry chemical powder.• carbon dioxide.

FIRE FIGHTING• Alert Fire Brigade and tell them location and nature of hazard.• Wear breathing apparatus plus protective gloves in the event of a fire.• Prevent, by any means available, spillage from entering drains or water courses.• Use fire fighting procedures suitable for surrounding area.• DO NOT approach containers suspected to be hot.• Cool fire exposed containers with water spray from a protected location.• If safe to do so, remove containers from path of fire.• Equipment should be thoroughly decontaminated after use.

FIRE/EXPLOSION HAZARD• Non combustible.• Not considered to be a significant fire risk.• Expansion or decomposition on heating may lead to violent rupture of containers.• Decomposes on heating and may produce toxic fumes of carbon monoxide (CO).• May emit acrid smoke.Decomposes on heating and produces toxic fumes of: carbon dioxide (CO2).

FIRE INCOMPATIBILITY■ None known.

HAZCHEMNone

continued...

Page 73: Technical Handbook

J6WBChemwatch Independent Material Safety Data SheetIssue Date: 11-May-2012 CHEMWATCH 15-1582A317LP Version No:2.0

CD 2012/2 Page 3 of 8

Section 6 - ACCIDENTAL RELEASE MEASURES

MINOR SPILLS• Clean up all spills immediately.• Avoid breathing vapours and contact with skin and eyes.• Control personal contact with the substance, by using protective equipment.• Contain and absorb spill with sand, earth, inert material or vermiculite.• Wipe up.• Place in a suitable, labelled container for waste disposal.

MAJOR SPILLS■ Minor hazard.• Clear area of personnel.• Alert Fire Brigade and tell them location and nature of hazard.• Control personal contact with the substance, by using protective equipment as required.• Prevent spillage from entering drains or water ways.• Contain spill with sand, earth or vermiculite.• Collect recoverable product into labelled containers for recycling.• Absorb remaining product with sand, earth or vermiculite and place in appropriate containers for disposal.• Wash area and prevent runoff into drains or waterways.• If contamination of drains or waterways occurs, advise emergency services.

Personal Protective Equipment advice is contained in Section 8 of the MSDS.

Section 7 - HANDLING AND STORAGE

PROCEDURE FOR HANDLING• Limit all unnecessary personal contact.• Wear protective clothing when risk of exposure occurs.• Use in a well-ventilated area.• When handling DO NOT eat, drink or smoke.• Always wash hands with soap and water after handling.• Avoid physical damage to containers.• Use good occupational work practice.• Observe manufacturer's storage and handling recommendations contained within this MSDS.

SUITABLE CONTAINER• Polyethylene or polypropylene container.• Packing as recommended by manufacturer.• Check all containers are clearly labelled and free from leaks.

STORAGE INCOMPATIBILITY■ None known.

STORAGE REQUIREMENTS• Store in original containers.• Keep containers securely sealed.• Store in a cool, dry, well-ventilated area.• Store away from incompatible materials and foodstuff containers.• Protect containers against physical damage and check regularly for leaks.• Observe manufacturer's storage and handling recommendations contained within this MSDS.

continued...

Page 74: Technical Handbook

J6WBChemwatch Independent Material Safety Data SheetIssue Date: 11-May-2012 CHEMWATCH 15-1582A317LP Version No:2.0

CD 2012/2 Page 4 of 8

Section 8 - EXPOSURE CONTROLS / PERSONAL PROTECTION

EXPOSURE CONTROLSThe following materials had no OELs on our records• tall oil fatty acids: CAS:61790- 12- 3 CAS:68187- 99- 5• water: CAS:7732- 18- 5

MATERIAL DATATALL OIL FATTY ACIDS:WATER:

■ No exposure limits set by NOHSC or ACGIH.

J6WB:None assigned.

PERSONAL PROTECTION

EYE• Safety glasses with side shields.• Chemical goggles.• Contact lenses may pose a special hazard; soft contact lenses may absorb and concentrate irritants. A

written policy document, describing the wearing of lens or restrictions on use, should be created for eachworkplace or task. This should include a review of lens absorption and adsorption for the class ofchemicals in use and an account of injury experience. Medical and first-aid personnel should be trained intheir removal and suitable equipment should be readily available. In the event of chemical exposure, begineye irrigation immediately and remove contact lens as soon as practicable. Lens should be removed at thefirst signs of eye redness or irritation - lens should be removed in a clean environment only after workershave washed hands thoroughly. [CDC NIOSH Current Intelligence Bulletin 59], [AS/NZS 1336 or nationalequivalent].

HANDS/FEET• Wear chemical protective gloves, eg. PVC.• Wear safety footwear or safety gumboots, eg. Rubber.NOTE:• The material may produce skin sensitisation in predisposed individuals. Care must be taken, when removing

gloves and other protective equipment, to avoid all possible skin contact.• Contaminated leather items, such as shoes, belts and watch-bands should be removed and destroyed.Suitability and durability of glove type is dependent on usage. Important factors in the selection of glovesinclude:• frequency and duration of contact,• chemical resistance of glove material,• glove thickness and• dexteritySelect gloves tested to a relevant standard (e.g. Europe EN 374, US F739, AS/NZS 2161.1 or nationalequivalent).• When prolonged or frequently repeated contact may occur, a glove with a protection class of 5 or higher

(breakthrough time greater than 240 minutes according to EN 374, AS/NZS 2161.10.1 or national equivalent)is recommended.

• When only brief contact is expected, a glove with a protection class of 3 or higher (breakthrough timegreater than 60 minutes according to EN 374, AS/NZS 2161.10.1 or national equivalent) is recommended.

• Contaminated gloves should be replaced.Gloves must only be worn on clean hands. After using gloves, hands should be washed and dried thoroughly.Application of a non-perfumed moisturiser is recommended.

continued...

Page 75: Technical Handbook

J6WBChemwatch Independent Material Safety Data SheetIssue Date: 11-May-2012 CHEMWATCH 15-1582A317LP Version No:2.0

CD 2012/2 Page 5 of 8Section 8 - EXPOSURE CONTROLS / PERSONAL PROTECTION

OTHER• Overalls.• Eyewash unit.

RESPIRATOR•Type P Filter of sufficient capacity. (AS/NZS 1716 & 1715, EN 143:2000 & 149:2001, ANSI Z88 or nationalequivalent)

The local concentration of material, quantity and conditions of use determine the type of personal protectiveequipment required. For further information consult site specific CHEMWATCH data (if available), or yourOccupational Health and Safety Advisor.

ENGINEERING CONTROLS■ Engineering controls are used to remove a hazard or place a barrier between the worker and the hazard. Well-designed engineering controls can be highly effective in protecting workers and will typically be independentof worker interactions to provide this high level of protection.The basic types of engineering controls are:Process controls which involve changing the way a job activity or process is done to reduce the risk.Enclosure and/or isolation of emission source which keeps a selected hazard "physically" away from the workerand ventilation that strategically "adds" and "removes" air in the work environment. Ventilation can removeor dilute an air contaminant if designed properly. The design of a ventilation system must match theparticular process and chemical or contaminant in use.Employers may need to use multiple types of controls to prevent employee overexposure.

General exhaust is adequate under normal operating conditions. If risk of overexposure exists, wear SAAapproved respirator. Correct fit is essential to obtain adequate protection. Provide adequate ventilation inwarehouse or closed storage areas.

Section 9 - PHYSICAL AND CHEMICAL PROPERTIES

APPEARANCELight brown liquid with slight odour; does not mix with water.

PHYSICAL PROPERTIESLiquid.Does not mix with water.Floats on water.

State Liquid Molecular Weight Not ApplicableMelting Range (°C) Not Available Viscosity Not AvailableBoiling Range (°C) 100 Solubility in water (g/L) ImmiscibleFlash Point (°C) Not Applicable pH (1% solution) Not Availab leDecomposition Temp (°C) Not Available pH (as supplied) Not A vailableAutoignition Temp (°C) Not Available Vapour Pressure (kPa) 2.3 @ 20CUpper Explosive Limit (%) Not Applicable Specific Gravity (water=1) 0.992Lower Explosive Limit (%) Not Applicable Relative Vapour Density Not Available

(air=1)Volatile Component (%vol) VOC 88 g/L Evaporation Rate Not Available

Section 10 - STABILITY AND REACTIVITY

CONDITIONS CONTRIBUTING TO INSTABILITY■ Product is considered stable and hazardous polymerisation will not occur.For incompatible materials - refer to Section 7 - Handling and Storage.

continued...

Page 76: Technical Handbook

J6WBChemwatch Independent Material Safety Data SheetIssue Date: 11-May-2012 CHEMWATCH 15-1582A317LP Version No:2.0

CD 2012/2 Page 6 of 8

Section 11 - TOXICOLOGICAL INFORMATION

POTENTIAL HEALTH EFFECTS

ACUTE HEALTH EFFECTS

SWALLOWED■ The material has NOT been classified by EC Directives or other classification systems as "harmful byingestion". This is because of the lack of corroborating animal or human evidence. The material may still bedamaging to the health of the individual, following ingestion, especially where pre-existing organ (eg. liver,kidney) damage is evident. Present definitions of harmful or toxic substances are generally based on dosesproducing mortality rather than those producing morbidity (disease, ill-health). Gastrointestinal tractdiscomfort may produce nausea and vomiting. In an occupational setting however, ingestion of insignificantquantities is not thought to be cause for concern.

EYE■ Although the liquid is not thought to be an irritant (as classified by EC Directives), direct contact withthe eye may produce transient discomfort characterised by tearing or conjunctival redness (as with windburn).

SKIN■ The material is not thought to produce adverse health effects or skin irritation following contact (asclassified by EC Directives using animal models). Nevertheless, good hygiene practice requires that exposurebe kept to a minimum and that suitable gloves be used in an occupational setting.

INHALED■ The material is not thought to produce adverse health effects or irritation of the respiratory tract (asclassified by EC Directives using animal models). Nevertheless, good hygiene practice requires that exposurebe kept to a minimum and that suitable control measures be used in an occupational setting.

CHRONIC HEALTH EFFECTS■ There is limited evidence that, skin contact with this product is more likely to cause a sensitisationreaction in some persons compared to the general population.

TOXICITY AND IRRITATIONJ6WB:■ Not available. Refer to individual constituents.

TALL OIL FATTY ACIDS:■ unless otherwise specified data extracted from RTECS - Register of Toxic Effects of Chemical Substances.

TOXICITY IRRITATIONOral (rat) LD50: >10000 mg/kg (tall oil rosin)[Manufacturer]Oral (rat) LD50: 7600 mg/kg Eye : Mild: (effects reversible in less than

72 hours) *Skin : Mild (effects reversible in less than72 hours) *

*MeadWestvaco MSDSOleic acid, a component of tall oil fatty acid causes chromosome aberrations in yeast

WATER:■ No significant acute toxicological data identified in literature search.

continued...

Page 77: Technical Handbook

J6WBChemwatch Independent Material Safety Data SheetIssue Date: 11-May-2012 CHEMWATCH 15-1582A317LP Version No:2.0

CD 2012/2 Page 7 of 8

Section 12 - ECOLOGICAL INFORMATION

TALL OIL FATTY ACIDS:Ecotoxicity:Fish LC50: fathead minnow 20 mg/lEnvironmental Fate:BOD5 1249 mg O2/g (estimated)BOD28 2040 O2/g

EcotoxicityIngredient Persistence: Persistence: Air Bioaccumulation Mobility

Water/Soiltall oil fatty acids No Data No Data

Available Available

Section 13 - DISPOSAL CONSIDERATIONS

• Recycle wherever possible or consult manufacturer for recycling options.• Consult State Land Waste Management Authority for disposal.• Bury residue in an authorised landfill.• Recycle containers if possible, or dispose of in an authorised landfill.

Section 14 - TRANSPORTATION INFORMATION

HAZCHEM: None (ADG7)

NOT REGULATED FOR TRANSPORT OF DANGEROUS GOODS: ADG7, UN, IATA, IMDG

Section 15 - REGULATORY INFORMATION

POISONS SCHEDULE None

REGULATIONS

Regulations for ingredients

tall oil fatty acids (CAS: 61790-12-3,68187-99-5) is found on the following regulatory lists;"Australia Inventory of Chemical Substances (AICS)","GESAMP/EHS Composite List - GESAMP Hazard Profiles","IMO IBC Code Chapter 17: Summary of minimum requirements","IMO MARPOL 73/78 (Annex II) - List of Noxious Liquid Substances Carried in Bulk","International Council of Chemical Associations (ICCA) - High Production Volume List","OECD List of High Production Volume (HPV) Chemicals","OSPAR National List of Candidates for Substitution – United Kingdom"

water (CAS: 7732-18-5) is found on the following regulatory lists;"Australia Inventory of Chemical Substances (AICS)","IMO IBC Code Chapter 18: List of products to which the Code does not apply","International Fragrance Association (IFRA) Survey: Transparency List","OECD List of High Production Volume (HPV) Chemicals","OSPAR National List of Candidates for Substitution – Norway"

No data for J6WB (CW: 15-1582)

continued...

Page 78: Technical Handbook

J6WBChemwatch Independent Material Safety Data SheetIssue Date: 11-May-2012 CHEMWATCH 15-1582A317LP Version No:2.0

CD 2012/2 Page 8 of 8

Section 16 - OTHER INFORMATION

INGREDIENTS WITH MULTIPLE CAS NUMBERSIngredient Name CAStall oil fatty acids 61790- 12- 3, 68187- 99- 5

EXPOSURE STANDARD FOR MIXTURES■ "Worst Case" computer-aided prediction of spray/ mist or fume/ dust components and concentration:

■ Composite Exposure Standard for Mixture (TWA) :100 mg/m³.

■ Classification of the preparation and its individual components has drawn on official and authoritative sources as well as independent review by the Chemwatch Classification committee using available literature references.A list of reference resources used to assist the committee may be found at: www.chemwatch.net/references.

■ The (M)SDS is a Hazard Communication tool and should be used to assist in the Risk Assessment. Many factors determine whether the reported Hazards are Risks in the workplace or other settings. Risks may be determined by reference to Exposures Scenarios. Scale of use, frequency of use and current or available engineering controls must be considered.

This document is copyright. Apart from any fair dealing for the purposes of private study, research, review orcriticism, as permitted under the Copyright Act, no part may be reproduced by any process without writtenpermission from CHEMWATCH. TEL (+61 3) 9572 4700.

Issue Date: 11-May-2012Print Date: 11-May-2012

This is the end of the MSDS.

Page 79: Technical Handbook

www. ltli .com.au T :  1300 845 854 (Australia‐wide)    1300 TILT LIFT 

MARCH  2012 

The Precast & Tilt-Up Experts

Tilt Lift branches across Australia : VICTORIA (& Head Office) Unit 4, 25-27 Olive Grove Keysborough VIC 3173 T: 03 9988 7701 NEW SOUTH WALES QUEENSLAND WESTERN AUSTRALIA Unit B, 25 Stennett Road 5 Darnick Street 14 Boulder Road Ingleburn NSW 2565 Underwood QLD 4119 Malaga WA 6944 T: 02 9829 5711 T: 07 3423 1522 T: 08 9249 7255