SOFTWARE MEASUREMENT AND ANALYSIS
Team assignment 13
TEAM 3 – K15T1Hanh Luong – Leader – T095095
Hao Tran – T094442Huy Nguyen – T094016
Hieu Le – T093798Quang Nguyen – T094193
Content
1. Assumption
2. Schedule
3. Budget
4. Summary
AssumptionWith this Viking project, team gives some critical assumptions - 1 ideal day = 8h- 1 week = 6 ideal days- Development team size = 7- The project will be developed on new platform. It include the following: new database structure, new software architecture- About equipment to support project development, they will be reused but mail server is not because the company doesn’t have it.
ScheduleThe table show is the list of user stories and features in Viking project
Story ID User Story Feature
1 Manage Users F1
2 Manage Projects F2
3 Manage Lifecycle F3
4 Manage Roles F4
5 Manage Members F5
6 Manage Permissions F6
7 Log In F7
8 Synchronize Data F8
9 Manage Issues F9
10 Manage Artifacts F10
11 Manage Communications F11
12 Manage Reports F12
Based on above table, team had meeting and the table following hyperlink is the result of estimator in team
The above information is result of estimation in ideal case. But in fact, there are some differences. And the table below will show the rate of ideal time and elapsed time.
Schedule
Human resourceAvailable
Hours/DayIdeal
Hours/Day
Scrum Master 6 8Product owner 5 8
Development team
Team leader 7 8Architect 5 8Developer & Tester 1 7 8Developer & Tester 2 7 8Developer & Tester 3 7 8
Total: 44 56Rate (Available Hours/ Ideal
Hours): 0,79
ScheduleFrom above result, team put stories into sprint. Specific is shown in this below table
Sprint Story IDIdeal days of each story
Ideal days of each sprint
Elapsed days of
each sprint
Sprint 11 2,5
6 72 3
Sprint 23 2,75
5 64 2
Sprint 35 3
5 66 2
Sprint 47 1
5 79 4,25
Sprint 58 2
5 710 3,25
Sprint 611 3
5 712 2,25
Total 31 39
ScheduleFinally, based on all information and result that are analyzed above, this figure is Product Roadmap Release
BudgetThe table below shows overview about Viking budget
VIKING'S BUDGET
Salary $24,856.00
Training $0.00
Equipment $100.00
Software/Tools $2,320.00
Risk & Change $0.00
Facilities/Infrastructure (water, electric, office, etc.) $238.00
Team Building (Entertainment, birthday, bonus, etc.) $200.00
Customer relationship (travel, hotel, etc.) $100.00
Total $27,814.00
BudgetFirst, this table shows salary of Human resource.
Salary table
Role Hourly Rate Salary
Scrum Master 100 3945
Product owner 80 3156
Team leader 90 3551
Architect 90 3551
Developer & Tester 1 90 3551
Developer & Tester 2 90 3551
Developer & Tester 3 90 3551
Total budget 24856
BudgetSecond, this table shows price of equipment, tool and software
No. Content Quantity UnitUnit prize
Total Note
1.Equipment (Hareware) $100
1 Laptop 7 Thing $0Reuse
equipment2 Database Server 1 Thing $03 Modem 1 Thing $0
4Mail server (machine, domain name, etc.) 1 Thing $100 $100
2.Tool (Software) $2.320
1Pragmatic's Defect Tracker 1 License $20 $20
2 Microsoft Project 1 License $1.000 $1.000
3Relational database management system (RDBMS)
MS SQL Server Workgroup Edition 2005
1 License $1.300 $1.300
4 netBean 1 License $0 free
Total: (1) + (2) $2.420
BudgetFinally, this table shows other price (team building, Facilities/Infrastructure and Customer relationship)
Cost category
Month
Detail costTotal cost
Facilities/Infrastructure
(water, electric,
office, etc.)
Electric($35 per month)
Water($15 per month)
Cleaning($100 per
month)
Network($20 per month)
1 $35 $15 $100 $20 $170 2 $18 $8 $50 $10 $68
$35 $23 $150 $30 $238
Team Buildding
(Entertainment, birthday, bonus, etc)
Month Party Bonus Total cost 1 $100 $100
2
$100 $100
$0 $200 $200
Customer relationship
(travel, hotel, etc.)
MonthDetail cost
Total cost
1 $100 $100 2 $50 $150
$100 $100
Resource
Estimations about resource is described in schedule and budget
SummaryInclusion, in this documentation:• About schedule:When apply Scrum process, with an overview, time to develop Viking project is shorter than applying RUP process.• About budget:Familiar with schedule when applying Scrum process, Viking’s budget is less.• About resource:From above analyzing, we can see that Scrum applying require less human resource to develop Viking project.