Teaching Teaching AssistantAssistant: B. Berk : B. Berk ...teymurb/projectpresentation.pdf ·...
Transcript of Teaching Teaching AssistantAssistant: B. Berk : B. Berk ...teymurb/projectpresentation.pdf ·...
28.02.2013
1
Teaching Teaching AssistantAssistant: B. Berk : B. Berk AyraçmaAyraçma
RoomRoom No: 258 No: 258
�A Housing Estate in Arıköy, Istanbul is planned to be
constructed.
2
TERM PROJECT
İTÜ, 2017
28.02.2013
2
TERM PROJECT
3İTÜ, 2017
The contractor is responsible for;
The geotechnical design and time&cost
analysis of the support and foundation system
including
� Retaining wall design where needed
� The design of the deep excavation support system
� The Foundation system design
4
TERM PROJECT
İTÜ, 2017
28.02.2013
3
� The contract value is 2,000,000 TL
� The project duration is 30 days.
� The contractor should pay a penalty of 10,000 TL/day in
the case of a delay.
� The contractor will receive an early finish bonus of 5,000
TL /day if the project is completed before the promised
due date.
5
TERM PROJECT
İTÜ, 2017
TERM PROJECT
6
Number of Storeys and recommended structural loads for the
buildings
Building Code
Dimensions of eachbuilding
Properties Load per storey (kPa)
B1
17.0m x 14.0mInteraction between
the adjacent buildings will be ignored!
2B+G+14F 13
B2 2B+G+13F 13
B3 1B+G+12F 14
B4 1B+G+12F 14
B5 1B+G+13F 13
İTÜ, 2017
28.02.2013
4
7
Production Rates and Unit Prices for the construction activities
Activity
IDDescription Unit
Production Rate
(per day)
Unit Price
(TL)
1 Bored Pile Φ65 cm m 100 190
2 Bored Pile Φ80 cm m 100 240
3 Bored Pile Φ100 cm m 100 310
4 Raft Foundation (H=2m) m2 150 500
5 Jet Grout III Φ65 cm m 150 70
6 Gravity type retaining wall m³ 30 150
7 RC retaining wall m³ 40 200
8 Sheet-Pile wall-cantilever type m2 80 210
9 Sheet-Pile wall-anchored type m2 60 250
10 Land acquisition m² 150 -
11 Excavation m³ 16 100
12 Earth fill m³ 14 100
İTÜ, 2017
The most important step in geotechnical design is to conduct
an adequate subsurface investigation. The number, depth,
spacing and properties of borings, sampling and testing
involved in an exploration program are all dependent upon
site conditions and the properties of the structures. In fact,
there exists no rigid rules for the extent of a soil exploration
program.
8
In the beginning
İTÜ, 2017
28.02.2013
5
9
In the beginning
• Request the borehole data for the
site from your instructor
• Ask the instructors for the values of the
soil parameters that you need to know
during your design.
İTÜ, 2017
How to decide for the extent of a soil exploration
program?
10
• Field testing : The number and location of borings
• Laboratory testing
İTÜ, 2017
28.02.2013
6
11
Borehole Location and number
İTÜ, 2017
1. Introduction and the description of the problem
2. The number and location of borings
3. Evaluation of Borehole data:
Soil Profile, GWT location,
Evaluation and correction of SPT-N
4. Soil Parameters and Laboratory Data
5. Deciding on the values of design parameters
12
1st Report
İTÜ, 2017
28.02.2013
7
1st REPORT
13
Report Format Content
1. Introduction • Introduce your project. Write the description and content of the
problem.
2. Soil profile • Determination of the Soil profile: By taking 2 cross-sections draw the
layering of soil strata, ground water elevation, etc.
• Analyze in-situ test data, correct SPT-N values.
• Evaluate the laboratory test data
• Determine the index and engineering properties of each soil layer by
considering both SPT-N values and laboratory test results-Design
parameters.
• Report all of your findings, calculations, drawings and decisions (i.e. I
choose the design parameter values as.... because…).
İTÜ, 2017
14
1st Report- Soil Profile
İTÜ, 2017
28.02.2013
8
1st Report- Soil Profile
15İTÜ, 2017
2nd REPORT
16
Report Format Content
3. Geotechnical
Engineering
Design (a)
By also conducting time&cost analyses;
• Design an adequate retaining wall for the most critical section by evaluating alternative options.
• Design a support system for the foundation excavation by considering alternative support types.
İTÜ, 2017
28.02.2013
9
Retaining Wall Design
17İTÜ, 2017
�
18
Retaining Wall Design
İTÜ, 2017
28.02.2013
10
Sheet Pile Wall Design
19İTÜ, 2017
THE FINAL REPORT
20İTÜ, 2017
28.02.2013
11
Design of the Foundation System
21
Start with Shallow Type Foundation.
In case you found out that shallow type is insufficient then proceed with the
Deep Foundation System
İTÜ, 2017
1. Retaining Wall Design
2. Sheet Pile Wall Design for the support of the excavation
3. Design of the Foundation System
4. Time Planning and Cost Accounting
22
Final Report
İTÜ, 2017
28.02.2013
12
FOUNDATION DESIGN
23İTÜ, 2017
İTÜ,2017 24
28.02.2013
13
25İTÜ, 2017
Calculation of total and differential settlements
26
For the design of a raft
foundation
1. Check for safe bearing
capacity requirement
2. Determine whether the
total and differential
settlements are within
tolerable limits
İTÜ, 2017
28.02.2013
14
Final Report
27
Report Format Content
4. Geotechnical
Engineering Design (b)
• Decide for the foundation system:
1) Raft foundation: Calculate the bearing capacity and both total anddifferential settlements
2) In case shallow foundation is not adequate, design a deep foundationsystem by considering both pile and jet-grout construction alternatives.
5. Time Planning and
Cost
Accounting
• Determine the time required for each design.
• Determine the cost for each design.
• Discuss your solutions for alternative choices in terms of time and cost
criteria.
6. Conclusion • Summarize all evaluations and analyses you have done. Indicate the final
results of your analyses. Explain your choices for each process of the
project by discussing your decision in terms of time and cost criteria (i.e.
According to the two criteria given, the cost is higher for …or according to
1st criteria, solution 1 is better or has less cost without paying any penalty.
Therefore I choose…)
7. References • Indicate also all the guidelines, codes and standards used
İTÜ, 2017
� Analyze each phase of the project for two different
engineering solutions.
� Discuss the alternatives according to the two criteria given;
cost and duration of construction.
� Choose the best alternative, explain the reasons for your
choice and write a short method of statement in the
discussion part of your report.
28
TERM PROJECT
28.02.2013
15
�
Criteria
Assignment
CompletenessAccuracy
Demonstrated
Knowledge Requirements Neatness
Gra
din
g
1 Unsatisfactory
Less than 1/2 of all items
attempted.
Less than 1/2 of all items are correct.
Response shows a complete lack of
understanding for the problem.
Has done something
different or did not do
anything
Writing is not legible.
2 Developing
At least 1/2 of the items
attempted.
Between 1/2 and9/10 of items are
correct.
Response showssome
understanding of the problem.
Does not meet the
requirements of the problem.
Writing is not legible in
places.
3 Satisfactory9/10 of items
attempted.9/10 of items are
correct.
Shows substantialunderstanding of
the problem, ideas, and processes.
Meets the requirements of
the problem.
Marginally legible
handwriting, typing, or printing.
4 ExemplaryAll items
attemptedAll items are
correct.
Shows complete understanding of
the questions, mathematical ideas,
and processes.
Goes beyond the
requirements of the problem.
Legible handwriting,
typing, or printing.
29
Evaluation of the Study
İTÜ, 2017
�
This is a Team Work!
30
28.02.2013
16
31
PROJECT GROUPS
Group 1(B1)
Ömer Yasir Küçük
Burcu Bayraktar
Sait Ceylan
Mustafa Köseoğlu
Mert Zileli
Group 2(B2)
Erkan Çam
Kübra Tuğba Keskin
Anıl Yüksel
Emre Ozan Kaymak
Zeynep Esra Gürbüz
Group 3(B3)
Gülcan Çağla Emir
Sernaz Engin
Nurullah Bingölbali
Kaan Dişisağlam
Necmettin Tamgüney
Group 4(B4)
Ahmet Çötoğlu
Anıl Öztürk
Serhat Çağlar
Yılmaz Yılmaz
Yusuf Teski
Group 5(B5)
Hilmi Arısoy
Oğuzhan Akpınar
Mert Aksu
Melih Ayar
Serkan Ülger
Group 6(B1)
Burak Yelken
Güneş Çilingir
Furkan Tozluyurt
Yusuf Aksöz
Oğuz Durur
Group 7(B2)
Bekir Bakır
Mehmet Kömürcü
Mehmet Kaya
Ozan Çavuş
Seyfettin Kenan
Group 8(B3)
Serkan Fidan
Mete Alp Kızılçay
Onur Güney Güven
Serdar Nurduhan
Mehmet Fırat