TCE - Gasification
Transcript of TCE - Gasification
-
8/10/2019 TCE - Gasification
1/446 www.tcetoday.com april 2012
tce GASIFICATION
Peter Fagianoexplainshow the humble lumpof coal could be theanswer to securingdelivery of SouthAustralias futureenergy needs
IN recent years, theres been tremendous
volatility in the cost of crude oil,
culminating in prices reaching US$147/
bbl in July 2008. Due to the global recession,
the price fluctuated downwards, but as a
result of political instability in the Middle
East and North Africa, the crude oil price
currently sits around US$111/bbl. As its
unlikely in the medium term that prices
will stabilise or come down, many nations
are seeking security of supply at more
economic levels by diversifying their
sources and type of energy supply.
The situation is compounded by the fact
that conventional cheap sources of oil are
declining and hence international energy
exploration and production companies are
now seeking oil sources in areas of higher
political risk, with higher exploration and
production costs. This resulted in an 8%
growth in the natural gas market in 2010.
But what other options exist?
The exploitation of the huge shale gas
reserves in the US will mean that the country
will now become an exporter of LNG asopposed to an importer.
Nuclear is now facing many challenges as an
energy alternative following the 2011 tsunami
in Japan.
Renewable energy sources such as biofuels
and wind energy grew by 16% but overall
represent less than 2% of the global energy
consumption.
Coal consumption grew globally in 2010
at the same rate as natural gas with some
48% of world demand being consumed in
China. The growth in coal demand has not
been solely for generation of electricity but
also in the conversion of coal into synthetic
transportation fuels and petrochemicals.
energy in South Australia
missing a trick?South Australia currently relies on
importation of all of its transportation fuels
primarily from Singapore with bulk fuel
shipments arriving every three days at Coode
Island Terminal.
With synfuel production gaining pace in
other areas around the world (see box), an
opportunity to develop South Australias
coal reserves for the production of electricity
and synthetic transportation fuels lies onits doorstep in the form of the Arckaringa
basin. Arckaringas coal assets of 7.8b t
represent more than 10% of Australias total
coal reserves and with this in mind, Altona
-
8/10/2019 TCE - Gasification
2/4
april 2012 www.tcetoday.com 47
CAREERS tceGASIFICATIONCAREERS tceGASIFICATION
Synfuel from coal
Synfuel plants are operational or are
being built in North America, Europe
and Asia.
All international airlines that refuel
in Johannesburg or Cape Town fly on
50:50 synfuel:refinery aviation fuel.
China is following suit and is building
synfuel plants as well as developing
coal-based petrochemicals.
Korea is proceeding on major coal
gasification projects for the production
of electricity and synthetic natural
gas (SNG).
Figure 1: South Australia mines, including
Arckaringa coal asset
Energy decided to investigate the feasibility
of exploiting these currently undeveloped
reserves.
In November 2005, Altona acquired the
mineral exploration licence in the coal-
bearing areas in the Arckaringa basin,
covering 2,500 km2and including three
coal deposits Westfield, Wintinna and
Murloocoppie containing over 7.8b t of coal.
These coal deposits are effectively one of the
worlds largest undeveloped energy banks,
capable of conversion into clean liquid fuels,
low-cost power and high value industrial
feedstocks. We carried out process feasibility
studies (PFSs) for the mine development and
the proposed coal to liquids plant. Sufficient
technical and economic data was developed
to select suitable technology licences. In2010 we formed a joint venture with Chinas
CNOOC as a strategic partner. In return for
financial investment, CNOOC owns 51% of
the mineral exploration licences.
coal-to-liquids for Australia?South Australia can also develop its energy
economy based on indigenous coal reserves.
The coal is ideally suited for gasification
and for the coproduction of synfuels and
electricity. Firstly the coal is gasified to
produce raw syngas from which carbon
dioxide is captured before the treated syngas
is converted into synthetic liquid fuels asfollows:
syngas can be converted into long chain
liquid hydrocarbons (wax) (by the Fischer
Tropsch process) which are then refined to
produce primarily diesel, aviation fuel and
naptha; or
syngas can be converted into methanol,
which is then polymerised into gasoline orolefins.
multiple benefits at
ArckaringaIn 2006 we carried out drilling programmes
to confirm the coal quality and quantity and
subsequently develop the design of the mine
and synfuel plant (CTL). Due to the enormous
size of the coal reserves, the coal extraction
rate can be increased, so that there is ability to
also co-produce gasoline and petrochemicals.
The technologies required to produce
synthetic fuels are well proven and the coal
gasification process allows for the efficient
and economic capture of carbon dioxide for
sequestration, thus minimising greenhouse
gas emissions.
Also, the plant produces sufficient electricity
to meet the operational needs as well as to
export electricity into the transmission grid.
The water from the mine development and
the coal processing plant are treated to allow
use in the plant and export of the water to the
local farming communities and the mining
enterprises.
Our work to date using technical
engineering companies in Australia, Europeand the US indicate that we could produce
liquid fuels at a sale price of A$0.33/l,
which is extremely competitive at todays
international pricing, thus even providing
-
8/10/2019 TCE - Gasification
3/4
tce GASIFICATION
48 www.tcetoday.com april 2012
the future opportunity for export once theneeds of the South Australian market have
been met. These costs will only be subjected
to inflationary costs and are not exposed to
international oil market volatility. The general
public and industry at large would benefit
from implementing the Arckaringa mine and
CTL plant.
Synfuel quality is superior to that
produced from conventional crude oil.
These properties include:
lower specific gravity which results in lower
payload, especially important for the aviation
industry;no aromatics orcarcinogenic compounds;
reduced sulphur and nitrogen emissions.
There are minimal carbon dioxide emissions
in the overall process with emission levels
similar to natural gas power plant due to the
carbon capture scheme.
Were considering building a plant to
convert some of the carbon dioxide into
methanol, which can be directly added to the
gasoline pool; there are favourable economics
Combined cycle
power plant
Fischer-Tropsch
synthesisCleanup
Tail gas
LPsteam
Refining
Diesel
Naptha
Other fuels
By
products
Sulphur
Inert slag
Coal
O2
Syngas
CO+2H2
Gasification
CO2
Figure 2: Synfuel process schematic
for conversion of methanol into gasoline.The Arckaringa Project is ideally placed to:
supply fuel and chemicals to new resources
and industrial projects;
enhance power supply to the state grid and
the national electricity market;
distribute water to the region from mine
dewatering and plant processes; and
be a catalyst for regional development and
employment.
can it be done?The Arckaringa Project design was developed
from prefeasibility technical studies, coveringCTL plant design and costing, open cut mine
design and costing, a field drilling programme
and follow up hydrogeological modelling,
geotechnical evaluation and coal quality
testing and analysis. From these studies and
the large body of work from past evaluations
of the Wintinna coal resource, we derived a
project base case.
A field drilling programme commenced in
2006 and was completed in 2008, with the
associated geotechnical, hydrogeological,
coal testing and analysis and resources
statements. During 2007, we commissioned
CTL and power plant options optimisation
work on mine costs and constructed a
project economic model. Studies on fuel and
electricity markets were also undertaken.
These studies, together with the historical
database and the field drilling and associated
technical programmes, constituted a
prefeasibility body of work at a standard
which permitted an informed decision on
proceeding to the bankable feasibility stage
(BFS).
where were at
Along with CNOOC we started the two-yearBFS programme for the mine and CTL plant
development in October 2010.
To date, major milestones achieved include:
the Chinese authorities have confirmed the
Left to right: Arckaringa Creek and hillsnear Wintinna, April 2010; Investigations
underway
-
8/10/2019 TCE - Gasification
4/4
april 2012 www.tcetoday.com 49
CAREERS tceGASIFICATION
key findings
Key findings from the pre-feasibility level studies are
described below:
geology and coal resourcesThe Wintinna Deposit contains up to 3,900m t of coal
resources. The resources statement incorporating the results
of the field drilling programme show a Joint Ore Reserves
Committee (JORC) compliant resource estimate of 1,287m t
which covers only about 25% of the area of the deposit.
mine design and costsThe Wintinna deposit can be mined as a conventional open cut and back fill
operation.
The initial box cut will take approximately 2 years to uncover first coal, thereafter
mining is virtually steady state through dewatered overburden and gently dipping,
consistent coal seams.
The mine footprint after 30 years at 1015m t/y of coal will be around 20 km
2
.Groundwater modelling shows that average dewatering volumes are significant,
estimated at up to 600m l/d in early years reducing to 300m l/d.
CTL and power plant design and costsThe base case CTL plant comprises gasification, FischerTropsch liquids and
combined cycle power generation. It is a complex but integrated facility that
combines to produce 30,000 bbl/d (10m bbl/y) of diesel products and naptha, and
the export of 560 MWh
(4m MWh/y) of electricity to the grid and/or third parties.
infrastructure requirementsThe mine and CTL plant site is remote from large regional centres but has the prime
advantage of proximity to the Adelaide Darwin railway and the Stuart Highway.
The costs of normal mine site infrastructure, with the exception of the grid
transmission link, have already been factored into project economic model.
Connecting the power plant to the national electricity grid will benefit the grid
system in terms of load balancing, especially if the plant operates in base load mode.
fuels and electricity marketsThe fuel market in SA and NT can absorb all of 10m bbl/y of liquid fuels from the
CTL plant:
the SA and NT market relies totally on imports of diesel fuel and is estimated at
9m bbl/y currently and forecast to rise steadily to around 12m bbl/y by 2014
fuels can be exported via the nearby rail link to Darwin to supply markets in Asia,
particularly China
It is anticipated that the lower density specification for CTL diesel (0.77) compared
to conventional refinery diesel (0.83) will be accommodated in future within the Diesel
Fuel Standard.
Electricity market studies show costs of generating power at Arckaringa are
sufficiently low to enable the power plants export capacity to be dispatched into the
national grid.
environmental issues and approvalsThe key issues are the impact of mine dewatering on regional water sources,
mound springs associated with the Great Artesian Basin (GAB) and aquifer systems,
and CO2mitigation.
The management plan for pumping, diversion and disposal of groundwater will
require a water allocation licence (WAL) from state government authorities to ensure
it protects local water supplies, GAB mound springs, flora and fauna species etc.
CO2mitigation plans include plant capture, compression and storage at asequestration site already identified in the East Officer Basin, around 100 km from
the proposed CTL plant site, for long-term sequestration under a gas storage
licence.
Arckaringa coal asset in terms of both qualityand quantity;
South Australian government approval for
the field programme commencing this year
for the specification and location of coal and
geotechnical boreholes and hydrological
tests wells;
reconfirmation of the suitability of the coal
for gasification; and
re-evaluation of the mine and CTL plant
development options and project economics.
The BFS will further optimise the
configuration of the overall complex in
respect of the project economic model,compliance with environmental legislation
and overall logistics for products export.
Were confident that South Australias coal
reserves can allow it to become a regional
leader in synfuels production and offset its
reliance on imported fuels, thus achieving
economic benefits and homeland security.
tce
Peter Fagiano(pfagiano@altonaenergy.
com) is director at Altona Energy.
Miracles can happen even
to those who are small,
flammable and dressed all
in black.*The miracle isthat coal can be convertedinto synthetic fuels andpetrochemicals whileminimising any effluentsor emissions into theenvironment.
* From Lemony Snickets book
The Lump of Coal
IChemE EVENTS
Gasification 11
Cagliari, Sardinia, Italy
811 May
Gasification technology provides an
attractive conversion route to fuels
and chemicals from a wide range of
primary energy sources. Most of the
undesirable by-products created by
conventional combustion processes are
either eliminated, converted into saleable
products, or can be captured for safe
storage. Gasification 11 will take a close
look at the latest developments in the field.
Register now: www.icheme.org/
events/gasi11