Task List
• A task list is a non-order-related process for implementing
an activity.• Task lists are used throughout the SAP ERP system to
define a sequence of activities to produce a specific result.
Task lists are used in several application areas, including,
PP-PI, PS, QM, and PM.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 3/33
Task List Types
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 4/33
Task list Type
1. Routing
– Routings describe material-related production and are used in
production planning. – Reference operation sets are not created for a specific material, but can
be used as references within routings or copied into routings. They are
usually activities that are common to many routings and can be created
with either internal or external numbering.
2. Rate Routing
– Rate routings describe material-related production using production
lines and are used mostly by repetitive manufacturing. Reference rate
routings are non-material specific activities that are common to many
rate routings and can be used as references within rate routings or
copied into them to simplify data entry.
3. Master Recipe
– Master recipes describe material specific production and are used in
production planning for process industries.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 5/33
Task List Type
4. Rough-cut Planning profile:
– Rough-cut capacity profiles are used to view resource loads in sales and
operations planning without BOM explosion.
5. Standard Network.
– Networks contain instructions on how to perform tasks in a specific way,in a specific order, and in a specific time period, and are used in project
systems.
6. Inspection Plan
– Inspections plans describe the inspection process for a material and are
used in quality management.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 6/33
Routing• Definition:
• The routing defines the operations (sequence of activity) to be performed as
well as:
– Where the work is performed
– How long the work should take
– What materials to use for each operation
– What special tools, jigs, etc. are to be used
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 7/33
Routing
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 8/33
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 9/33
Structure of a Routing
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 10/33
Routing Structure
• A routing determines the sequence of individual operations that are necessary to produce a finished product.
• A routing contains operations and information about the work centers at whichthe individual operations are to be carried out, as well as standard times.
• Further important information, contained in routings, is for instance, the materialcomponents required for an operation as well as the necessary tools, jigs andfixtures (production resources/tools).
•
If quality is to be inspected during an operation, you can assign inspectioncharacteristics to the operation in a routing. The starting point for doing so is thecharacteristic overview.
• You can assign trigger points to operations in routings, so that later in the production order, certain functions are triggered when certain events occur.Examples of such events are a change in status or the confirmation of anoperation.
• The SAP ERP system stores routings in groups that can be either internally orexternally assigned. There can be many routings in a group, each distinguished
by a different group counter.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 11/33
Routing Integration
• A routing is defined at the plant level. This means that the organizational elements forcompany code, valuation area, and plant all need to be defined prior to creating a routing.
• Work center must exist before creating Routing as work center needed to assigned tooperation.
• The routing integrates with material master data, BOM components, work centers, as wellas product costing, capacity planning, production orders, procurement, and planning.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 12/33
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 13/33
Routing Integration
• A routing is defined at the plant level. This means that the organizational elements forcompany code, valuation area, and plant all need to be defined prior to creating a routing.
• Work center must exist before creating Routing as work center needed to assigned tooperation.
• The routing integrates with material master data, BOM components, work centers, as wellas product costing, capacity planning, production orders, procurement, and planning.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 14/33
Routing Usage
• A routing is independent of an order and is used in the creation of an order.
•
The operations and information from the routing is copied into the order duringorder creation. This includes the planned time for each activity within an
operation (standard value), the work center, and the control key.
• The routing information in the order becomes the basis for lead time
scheduling,product costing, and capacity planning.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 15/33
Creating Simple Routing for material production.
1. Manu path
– Choose Logistics → Production → Master Data → Routings → Routings→Standard Routings→Create or use transaction code CA01.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 16/33
2. Enter the material (Exmple:1430) and Plant 1000 and press enter.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 17/33
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 18/33
4. Click on the Operations Overview icon and enter the work
center,conrol key and description as shown bellow.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 19/33
5. Select all operations and choose Details from the menu bar
and click on operation
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 20/33
6. Enter the Standard Operation Processing Times and click on
to navigate to the next operation detail screen. Continue
until all times have been entered and then choose to return
to the operation overview.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 21/33
7 After return to operation overview screen click header detail andyoucan
see group counter “1” and group number should show black.
8 Save routing by clicking on
9 Routing will be saved with group number as shown bellow.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 22/33
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 23/33
3. Enter Usage# 1 for Production, Status# 1 for Creation Phase,
Planner group 000, and lot size of 1 to 100,000 Pc.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 24/33
4. Click on the Operations Overview icon and enter the data in the
filed of work center,conrol key and description as shown
bellow.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 25/33
5. Select all operations and choose Details from the menu bar and
click on operation
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 26/33
6. Enter the Standard Operation Processing Times and click on
to navigate to the next operation detail screen. Continue until all
times have been entered and then choose to return to the
operation overview.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 27/33
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 28/33
Creating a Routing and Material
Assignment• Objectives
– Assign manufactured items to routings
– Allocate material components to operations
– Maintain cutting measures of variable-size
items
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 29/33
Material Assignment
• Prerequisite
– A material master record must exist in the system
for the material that is to be produced.
– It must have a material type that is allowed for
assignment to a routing or rate routing.
M t i l b li k d t ti f th f ll i
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 30/33
Materials can be linked to routings for the following
scenarios:
I The same routing can be used to produce several different materials. Each product has its
own unique bill of material but is manufactured by a common set of activities with the
same standard times. For example, both red and green chairs can be produced using the
same routing.
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 31/33
8/13/2019 Task List pp sap
http://slidepdf.com/reader/full/task-list-pp-sap 32/33
Component Allocation