Tariff order 2013-14
-
Upload
abhishek-amarnani -
Category
Documents
-
view
215 -
download
0
Transcript of Tariff order 2013-14
-
7/28/2019 Tariff order 2013-14
1/8
Tariff Order FY 2013-14 1
CHHATTISGARH STATE ELECTRICITY REGULATORY COMMISSION
RAIPUR
Petition No. 21 of 2013(T)
Petition No. 22 of 2013(T)
Petition No. 03 of 2013(T)
Present: Manoj Dey, Chairman
Vinod Shrivastava, Member
In the matter of
(1) Approval of Final True up for FY 2006-07 to December, 2008(CSEB Period), FY 2008-09 (January, 2009 to March, 2009) & FY
2009-10, FY 2010-11 and Provisional True up for FY 2011-12 and
Multi-Year Aggregate Revenue Requirement for FY 2013-14 to
FY 2015-16 for Chhattisgarh State Power Generation Co. Ltd.
(2) Approval of Final True up from FY 2006-07 till FY 2010-11 &Provisional True up for FY 2011-12 & Annual Performance Review for
FY 2012-13 & Approval of ARR for MYT Control Period FY 2013-16
for Chhattisgarh State Power Transmission Co. Ltd.
(3) Approval of CSEBs revised true up for FY 2006-07, and final true upFY 2007-08 and FY 2008-09 (Apr to Dec) & CSPDCL period final
True-UP for FY 2008-09 (Jan-Mar 2009), 2009-10, 2010-11 &
Annual Revenue Requirement FOR Control Period from 2013-14 to
2015-16 & Retail Tariff request for FY13-14 for Chhattisgarh State
Power Distribution Co. Ltd.
(4) Implementation of the Hon'ble Appellate Tribunal for Electricityjudgment on previous Tariff Orders related to erstwhile CSEB /
Chhattisgarh State Power Companies.
-
7/28/2019 Tariff order 2013-14
2/8
Tariff Order FY 2013-14 2
ORDER
(Passed on 12.07.2013)
1. As per provisions in the Tariff Policy and the Electricity Act, 2003(hereinafter referred as 'the Act') the Commission framed the Multi
Year Tariff Regulations i.e., the CSERC (Terms and Conditions for
determination of tariff according to Multi-Year Tariff principles and
Methodology and Procedure for determination of Expected revenue
from Tariff and Charges) Regulations, 2012 (hereinafter referred as
'MYT Regulations, 2012').
2. According to provisions of the Regulation 5.2 of the MYTRegulations, 2012, the companies were required to file petition for
approval of Aggregate Revenue Requirement (ARR) for the Control
Period from FY 2013-14 to FY 2015-16 and determination of tariff
for FY 2013-14, latest by 30th November 2012.
3. On requests submitted by the companies from time to time, theCommission extended the date of filing the petition repeatedly and
finally up to 15th January 2013. But the Companies failed to file the
said petition within extended time. Considering the failure of
companies in filing of tariff petition even after the extended date
and in pursuance with the direction of the Hon'ble Tribunal in OP No.
01 of 2011 and powers conferred under Section 62 and 64 of the
Act, MYT Regulations, 2012 and CSERC (Conduct of Business)
Regulation 2009, the Commission initiated the suo motu
proceedings to determine the ARR of Companies for Control Period
from FY 2013-14 to FY 2015-16 and tariff for FY 2013-14 and
registered suo motu petitions No. 04 of 2013 (T) on 23.01.2013 for
-
7/28/2019 Tariff order 2013-14
3/8
Tariff Order FY 2013-14 3
CSPGCL, No. 05 of 2013 (T) dated 23.01.2013 for CSPTCL and No.
03 of 2013(T) on 23.01.2013 for CSPDCL.
4. Subsequently, CSPGCL and CSPTCL filed petitions on 08.02.2013and requested for discontinuance of the suo motu proceedings,
which were registered at No. 21 of 2013(T) and 22 of 2013(T)
respectively. The Commission accepted the request and dropped the
suo motu proceedings against CSPGCL and CSPTCL. CSPDCL also
filed petition on 06.02.2013, however, as the same was found short
of some of the requirements specified in the Regulations, the
Commission decided to merge the petition filed by CSPDCL with the
suo motu petition No. 03 of 2013.
5. The petitions were made available on the website of the Commissionas well as to the petitioners. A public notice along with the gist was
also published in the news papers. Objections/suggestions were
invited as per the procedure laid down in the Regulations. Further,
the Commission conducted a hearing on the Petitions on
16.05.2013. Taking into account all the views / suggestions /
objections and after performing due diligence on each of the issue,
the Commission has finalised its views.
6. In the tariff order 2011-12 passed on 31.03.2011, the Commissionhad decided the final true up of FY 2005-06 and FY 2006-07 and
provisional true up of ARR for the FY 2007-08 and FY 2008-09 (post
facto ARR approval) for CSEB up to 31.12.2008 and for the State
Power Companies for the period 01.01.2009 to 31.03.2009.
Provisional true up for the power companies was also carried out for
FY 2009-10. Further, vide the tariff order for FY 2012-13 passed on
28.04.2012 provisional true up of FY 2010-11 and APR for FY 2011-
12 was undertaken.
-
7/28/2019 Tariff order 2013-14
4/8
Tariff Order FY 2013-14 4
7. The companies have, in this petition, prayed for final true-up of ARRof CSEB for FY 2007-08 and 2008-09 (till December 2008) for which
statutory audit has been completed by the Accountant General
(Audit) (AG audit, for short). The companies have also prayed for
final true-up of ARR for FY 2008-09 (January-Mar 2009), final true
up for FY 2009-10 and FY 2010-11 and provisional true up for FY
2011-12.
For this purpose the companies have jointly submitted the
true-up data including accounts pertaining to the period of CSEB i.e.
up to 31st December, 2008 and have submitted company-wise data
for the period from 1st January, 2009.
The Commission in this tariff order has also complied the
directions given by the Honble Tribunal in appeal No. 89 of 2011
and RP No. 10 of 2012 filed by CSPDCL against the Tariff Order for
FY 2011-12. The final true up for FY 2005-06 and FY 2006-07 have
also been revisited for the said purpose. This order is also subject to
the outcome of appeal No. 173 of 2012 filed by CSPDCL against the
Tariff Order for FY 2012-13. Further, the allocation of surplus
revenue available for the CSEB period, in accordance to Honble
Tribunal judgment dated 14.08.2012, has been revisited by this
Commission vide suo motu P. No. 47 of 2012 (M). The prior period
surplus has been redistributed accordingly.
8. For the purpose of revised true-up for FY 2005-06 and 2006-07, theCommission has followed the Honble Tribunal Judgment. For True
up from FY 2007-08 to FY 2009-10, the Commission has followed its
CSERC (Terms and Conditions for Determination of Tariff)
Regulations, 2006. For Final True up of FY 2010-11 and provisional
-
7/28/2019 Tariff order 2013-14
5/8
Tariff Order FY 2013-14 5
True up of FY 2011-12, the CSERC (Terms and Conditions of
determination of tariff according to Multi-Year Tariff principles)
Regulations, 2010 have been applied and the MYT Regulations, 2012
have been applied for determination of ARR for FY 2013-14 to FY
2015-16 and tariff for FY 2013-14. These Regulations embody the
principles for determination of tariff, enunciated in the Act. In
passing this order, the Commission has also been guided by the
National Electricity Policy (NEP), 2005 and Tariff Policy, as mandated
under the provisions of the Act. The Commission has taken care to
ensure that the revenue requirements of the companies are based,
on reasonable and prudent expenditure required to serve the
consumers efficiently and effectively.
9. As per the petitioners submission, truing up for the CSEB periodresults in a surplus of Rs 1212 Crore. Following the ratio decidendi
of the Honble Tribunal judgment in appeal No. OP 01 of 2011, the
Commission has considered carrying cost for the revenue gap. At
the same time, following the corollary, gains from revenue surplus
held by the CSEB / successor companies have also been accounted.
The Commission, after prudence check, and accounting for gains
from revenue surplus, has approved a surplus of Rs. 1880 Crore for
the period till 31.12.2008. In accordance to the Commissions order
dt 11.07.2013 in suo motu P. No. 47 of 2012, the surplus has been
allocated to the CSPGCL, CSPTCL and CSPDCL in the ratio 52.57%,
15.69% and 31.74% respectively. The surplus so allocated to the
three companies along with their cumulative surplus / deficit for the
period FY 2008-09 (January to March), FY 2009-10, FY 2010-11 and
FY 2011-12 have been adjusted to meet the revenue gap of CSPDCL
at the end of FY 2012-13.
-
7/28/2019 Tariff order 2013-14
6/8
Tariff Order FY 2013-14 6
10. For the MYT period FY 2013-14 to FY 2015-16, CSPGCL hassubmitted tariff proposal for its three thermal power stations namely
KTPS Korba East, HTPS Korba West and DSPM TPS, Korba. It has
also submitted proposal for hydro power stations HBPS Bango. The
Annual Fixed Cost (AFC) and Energy Charge rate, as claimed by the
petitioner and as approved by the Commission, for the aforesaid
stations is decided as under :-
Thermal Power Stations
Particulars FY 2013-14
HTPS KTPS DSPM
Annual Fixed Cost Rs. Crore 414.34 294.21 478.46
Energy Charge Rate for Specific Fuel Oil
consumption
Rs./kWh 0.055 0.111 0.055
Energy Charge Rate for Primary Fuel Rs./kWh 0.879 1.043 0.897
Energy Charge Rate (ex-bus power plant basis) Rs./kWh 0.934 1.154 0.952
Hydro Power Station
Hasdeo Bango FY 2013-14
Approved ARR Rs. Crore 24.09
Approved Net Generation MU 271.26
Approved Tariff for Hasdeo Bango Rs./kWh 0.888
11. CSPTCL has filed ARR for FY 2013-14 of Rs. 803 Crore. TheCommission after prudence check and due scrutiny has approved
the same at Rs. 600 Crore. Transmission charge for FY 13-14 shall
be as under :-
Particulars FY 2013-14
ARR for CSPTCL Rs. Crore 600.08
Monthly Transmission Charges for Medium and Long-term Open
Access Consumers
Rs. Crore/Month 50.01
Short-Term Open Access Charges Rs./kWh 0.233
Note - Energy losses for transmission: Transmission losses at the rate
of 4.40% for the energy scheduled for transmission at the point or points
of injection shall be recoverable from open access customers.
-
7/28/2019 Tariff order 2013-14
7/8
Tariff Order FY 2013-14 7
12. The Commission has also taken cognizance of Honble Tribunaldecision dated 01.10.2012 in appeal No 31 of 2012 in the case of
PTC India Ltd Vs GERC & Gujrat Urja Vikas Nigam Ltd., wherein it
has been held that as per provisions of the Act, Trading Company
cannot be carved out of unbundling of SEB. The Hon'ble ATE further
held that as per Section 5.3.4 of the National Electricity Policy, the
Power Purchase Agreements with the generating companies would
need to be suitably assigned to the distribution companies and there
is no provision for a Trading Company to be assigned with the PPAs
and to be responsible for procuring power for the distribution
licensees. Transfer Scheme Rules, 2010 notified on 31.03.2010 has
assigned the concluded short-term PPA of CSPDCL to CSPTrCL and
CSPDCL for the period 01.01.2009 to 31.03.2010, with retrospective
effect from 01.01.2009. The preamble of the Act mandates State
Commission for protection of interest of consumer. Taking into
cognizance, the spirit of the Act, NEP and Judgment by the Hon'ble
Tribunal, the Commission has considered the total short-term power
purchases expenses of concluded contracts (short-term PPAs) for
period 01.01.2009 to 31.03.2010 in ARR of CSPDCL and has also
appropriately assigned the gains from trading of surplus power to
CSPDCL.
13. Further, it is noted that the State Govt. on its part has issued agrant of Rs. 465 Crore to bridge a part of revenue gap.
14. CSPDCL in its petition has filed cumulative deficit of Rs 2495 Croreupto FY 2012-13. However, the Commission after prudence check
and scrutiny has arrived at a conclusion that after adjusting the
cumulative surplus of CSPGCL and CSPTCL, The gains from trading
of power and the grant from the State Govt., no revenue gap
-
7/28/2019 Tariff order 2013-14
8/8
Tariff Order FY 2013-14 8
remains. Accordingly, except for some corrections in methodology to
be applied in some specific cases, the Commission has decided to
continue with the prevailing tariff schedule. However, for ready
reference the tariff schedule to be applicable in reference to this
order is appended herewith as Annexure-I.
15. The Commission directs the Companies to take appropriate steps toimplement the tariff Order. A public notice of minimum 7 days be
given in accordance with the CSERC (Details to be Furnished by the
Licensees or Generating Company for Determination of Tariff and
Manner of Making Application) Regulations, 2004 and the MYT
Regulations, 2012 before implementation of this Tariff Order.
16. The detailed Order in reference to this joint order shall be issuedshortly.
Sd/-
(Vinod Shrivastava)
MEMBER
Sd/-
(Manoj Dey)
CHAIRMAN
True Copy
(P.N. Singh)
Secretary