Tariff order 2013-14

download Tariff order 2013-14

of 8

Transcript of Tariff order 2013-14

  • 7/28/2019 Tariff order 2013-14

    1/8

    Tariff Order FY 2013-14 1

    CHHATTISGARH STATE ELECTRICITY REGULATORY COMMISSION

    RAIPUR

    Petition No. 21 of 2013(T)

    Petition No. 22 of 2013(T)

    Petition No. 03 of 2013(T)

    Present: Manoj Dey, Chairman

    Vinod Shrivastava, Member

    In the matter of

    (1) Approval of Final True up for FY 2006-07 to December, 2008(CSEB Period), FY 2008-09 (January, 2009 to March, 2009) & FY

    2009-10, FY 2010-11 and Provisional True up for FY 2011-12 and

    Multi-Year Aggregate Revenue Requirement for FY 2013-14 to

    FY 2015-16 for Chhattisgarh State Power Generation Co. Ltd.

    (2) Approval of Final True up from FY 2006-07 till FY 2010-11 &Provisional True up for FY 2011-12 & Annual Performance Review for

    FY 2012-13 & Approval of ARR for MYT Control Period FY 2013-16

    for Chhattisgarh State Power Transmission Co. Ltd.

    (3) Approval of CSEBs revised true up for FY 2006-07, and final true upFY 2007-08 and FY 2008-09 (Apr to Dec) & CSPDCL period final

    True-UP for FY 2008-09 (Jan-Mar 2009), 2009-10, 2010-11 &

    Annual Revenue Requirement FOR Control Period from 2013-14 to

    2015-16 & Retail Tariff request for FY13-14 for Chhattisgarh State

    Power Distribution Co. Ltd.

    (4) Implementation of the Hon'ble Appellate Tribunal for Electricityjudgment on previous Tariff Orders related to erstwhile CSEB /

    Chhattisgarh State Power Companies.

  • 7/28/2019 Tariff order 2013-14

    2/8

    Tariff Order FY 2013-14 2

    ORDER

    (Passed on 12.07.2013)

    1. As per provisions in the Tariff Policy and the Electricity Act, 2003(hereinafter referred as 'the Act') the Commission framed the Multi

    Year Tariff Regulations i.e., the CSERC (Terms and Conditions for

    determination of tariff according to Multi-Year Tariff principles and

    Methodology and Procedure for determination of Expected revenue

    from Tariff and Charges) Regulations, 2012 (hereinafter referred as

    'MYT Regulations, 2012').

    2. According to provisions of the Regulation 5.2 of the MYTRegulations, 2012, the companies were required to file petition for

    approval of Aggregate Revenue Requirement (ARR) for the Control

    Period from FY 2013-14 to FY 2015-16 and determination of tariff

    for FY 2013-14, latest by 30th November 2012.

    3. On requests submitted by the companies from time to time, theCommission extended the date of filing the petition repeatedly and

    finally up to 15th January 2013. But the Companies failed to file the

    said petition within extended time. Considering the failure of

    companies in filing of tariff petition even after the extended date

    and in pursuance with the direction of the Hon'ble Tribunal in OP No.

    01 of 2011 and powers conferred under Section 62 and 64 of the

    Act, MYT Regulations, 2012 and CSERC (Conduct of Business)

    Regulation 2009, the Commission initiated the suo motu

    proceedings to determine the ARR of Companies for Control Period

    from FY 2013-14 to FY 2015-16 and tariff for FY 2013-14 and

    registered suo motu petitions No. 04 of 2013 (T) on 23.01.2013 for

  • 7/28/2019 Tariff order 2013-14

    3/8

    Tariff Order FY 2013-14 3

    CSPGCL, No. 05 of 2013 (T) dated 23.01.2013 for CSPTCL and No.

    03 of 2013(T) on 23.01.2013 for CSPDCL.

    4. Subsequently, CSPGCL and CSPTCL filed petitions on 08.02.2013and requested for discontinuance of the suo motu proceedings,

    which were registered at No. 21 of 2013(T) and 22 of 2013(T)

    respectively. The Commission accepted the request and dropped the

    suo motu proceedings against CSPGCL and CSPTCL. CSPDCL also

    filed petition on 06.02.2013, however, as the same was found short

    of some of the requirements specified in the Regulations, the

    Commission decided to merge the petition filed by CSPDCL with the

    suo motu petition No. 03 of 2013.

    5. The petitions were made available on the website of the Commissionas well as to the petitioners. A public notice along with the gist was

    also published in the news papers. Objections/suggestions were

    invited as per the procedure laid down in the Regulations. Further,

    the Commission conducted a hearing on the Petitions on

    16.05.2013. Taking into account all the views / suggestions /

    objections and after performing due diligence on each of the issue,

    the Commission has finalised its views.

    6. In the tariff order 2011-12 passed on 31.03.2011, the Commissionhad decided the final true up of FY 2005-06 and FY 2006-07 and

    provisional true up of ARR for the FY 2007-08 and FY 2008-09 (post

    facto ARR approval) for CSEB up to 31.12.2008 and for the State

    Power Companies for the period 01.01.2009 to 31.03.2009.

    Provisional true up for the power companies was also carried out for

    FY 2009-10. Further, vide the tariff order for FY 2012-13 passed on

    28.04.2012 provisional true up of FY 2010-11 and APR for FY 2011-

    12 was undertaken.

  • 7/28/2019 Tariff order 2013-14

    4/8

    Tariff Order FY 2013-14 4

    7. The companies have, in this petition, prayed for final true-up of ARRof CSEB for FY 2007-08 and 2008-09 (till December 2008) for which

    statutory audit has been completed by the Accountant General

    (Audit) (AG audit, for short). The companies have also prayed for

    final true-up of ARR for FY 2008-09 (January-Mar 2009), final true

    up for FY 2009-10 and FY 2010-11 and provisional true up for FY

    2011-12.

    For this purpose the companies have jointly submitted the

    true-up data including accounts pertaining to the period of CSEB i.e.

    up to 31st December, 2008 and have submitted company-wise data

    for the period from 1st January, 2009.

    The Commission in this tariff order has also complied the

    directions given by the Honble Tribunal in appeal No. 89 of 2011

    and RP No. 10 of 2012 filed by CSPDCL against the Tariff Order for

    FY 2011-12. The final true up for FY 2005-06 and FY 2006-07 have

    also been revisited for the said purpose. This order is also subject to

    the outcome of appeal No. 173 of 2012 filed by CSPDCL against the

    Tariff Order for FY 2012-13. Further, the allocation of surplus

    revenue available for the CSEB period, in accordance to Honble

    Tribunal judgment dated 14.08.2012, has been revisited by this

    Commission vide suo motu P. No. 47 of 2012 (M). The prior period

    surplus has been redistributed accordingly.

    8. For the purpose of revised true-up for FY 2005-06 and 2006-07, theCommission has followed the Honble Tribunal Judgment. For True

    up from FY 2007-08 to FY 2009-10, the Commission has followed its

    CSERC (Terms and Conditions for Determination of Tariff)

    Regulations, 2006. For Final True up of FY 2010-11 and provisional

  • 7/28/2019 Tariff order 2013-14

    5/8

    Tariff Order FY 2013-14 5

    True up of FY 2011-12, the CSERC (Terms and Conditions of

    determination of tariff according to Multi-Year Tariff principles)

    Regulations, 2010 have been applied and the MYT Regulations, 2012

    have been applied for determination of ARR for FY 2013-14 to FY

    2015-16 and tariff for FY 2013-14. These Regulations embody the

    principles for determination of tariff, enunciated in the Act. In

    passing this order, the Commission has also been guided by the

    National Electricity Policy (NEP), 2005 and Tariff Policy, as mandated

    under the provisions of the Act. The Commission has taken care to

    ensure that the revenue requirements of the companies are based,

    on reasonable and prudent expenditure required to serve the

    consumers efficiently and effectively.

    9. As per the petitioners submission, truing up for the CSEB periodresults in a surplus of Rs 1212 Crore. Following the ratio decidendi

    of the Honble Tribunal judgment in appeal No. OP 01 of 2011, the

    Commission has considered carrying cost for the revenue gap. At

    the same time, following the corollary, gains from revenue surplus

    held by the CSEB / successor companies have also been accounted.

    The Commission, after prudence check, and accounting for gains

    from revenue surplus, has approved a surplus of Rs. 1880 Crore for

    the period till 31.12.2008. In accordance to the Commissions order

    dt 11.07.2013 in suo motu P. No. 47 of 2012, the surplus has been

    allocated to the CSPGCL, CSPTCL and CSPDCL in the ratio 52.57%,

    15.69% and 31.74% respectively. The surplus so allocated to the

    three companies along with their cumulative surplus / deficit for the

    period FY 2008-09 (January to March), FY 2009-10, FY 2010-11 and

    FY 2011-12 have been adjusted to meet the revenue gap of CSPDCL

    at the end of FY 2012-13.

  • 7/28/2019 Tariff order 2013-14

    6/8

    Tariff Order FY 2013-14 6

    10. For the MYT period FY 2013-14 to FY 2015-16, CSPGCL hassubmitted tariff proposal for its three thermal power stations namely

    KTPS Korba East, HTPS Korba West and DSPM TPS, Korba. It has

    also submitted proposal for hydro power stations HBPS Bango. The

    Annual Fixed Cost (AFC) and Energy Charge rate, as claimed by the

    petitioner and as approved by the Commission, for the aforesaid

    stations is decided as under :-

    Thermal Power Stations

    Particulars FY 2013-14

    HTPS KTPS DSPM

    Annual Fixed Cost Rs. Crore 414.34 294.21 478.46

    Energy Charge Rate for Specific Fuel Oil

    consumption

    Rs./kWh 0.055 0.111 0.055

    Energy Charge Rate for Primary Fuel Rs./kWh 0.879 1.043 0.897

    Energy Charge Rate (ex-bus power plant basis) Rs./kWh 0.934 1.154 0.952

    Hydro Power Station

    Hasdeo Bango FY 2013-14

    Approved ARR Rs. Crore 24.09

    Approved Net Generation MU 271.26

    Approved Tariff for Hasdeo Bango Rs./kWh 0.888

    11. CSPTCL has filed ARR for FY 2013-14 of Rs. 803 Crore. TheCommission after prudence check and due scrutiny has approved

    the same at Rs. 600 Crore. Transmission charge for FY 13-14 shall

    be as under :-

    Particulars FY 2013-14

    ARR for CSPTCL Rs. Crore 600.08

    Monthly Transmission Charges for Medium and Long-term Open

    Access Consumers

    Rs. Crore/Month 50.01

    Short-Term Open Access Charges Rs./kWh 0.233

    Note - Energy losses for transmission: Transmission losses at the rate

    of 4.40% for the energy scheduled for transmission at the point or points

    of injection shall be recoverable from open access customers.

  • 7/28/2019 Tariff order 2013-14

    7/8

    Tariff Order FY 2013-14 7

    12. The Commission has also taken cognizance of Honble Tribunaldecision dated 01.10.2012 in appeal No 31 of 2012 in the case of

    PTC India Ltd Vs GERC & Gujrat Urja Vikas Nigam Ltd., wherein it

    has been held that as per provisions of the Act, Trading Company

    cannot be carved out of unbundling of SEB. The Hon'ble ATE further

    held that as per Section 5.3.4 of the National Electricity Policy, the

    Power Purchase Agreements with the generating companies would

    need to be suitably assigned to the distribution companies and there

    is no provision for a Trading Company to be assigned with the PPAs

    and to be responsible for procuring power for the distribution

    licensees. Transfer Scheme Rules, 2010 notified on 31.03.2010 has

    assigned the concluded short-term PPA of CSPDCL to CSPTrCL and

    CSPDCL for the period 01.01.2009 to 31.03.2010, with retrospective

    effect from 01.01.2009. The preamble of the Act mandates State

    Commission for protection of interest of consumer. Taking into

    cognizance, the spirit of the Act, NEP and Judgment by the Hon'ble

    Tribunal, the Commission has considered the total short-term power

    purchases expenses of concluded contracts (short-term PPAs) for

    period 01.01.2009 to 31.03.2010 in ARR of CSPDCL and has also

    appropriately assigned the gains from trading of surplus power to

    CSPDCL.

    13. Further, it is noted that the State Govt. on its part has issued agrant of Rs. 465 Crore to bridge a part of revenue gap.

    14. CSPDCL in its petition has filed cumulative deficit of Rs 2495 Croreupto FY 2012-13. However, the Commission after prudence check

    and scrutiny has arrived at a conclusion that after adjusting the

    cumulative surplus of CSPGCL and CSPTCL, The gains from trading

    of power and the grant from the State Govt., no revenue gap

  • 7/28/2019 Tariff order 2013-14

    8/8

    Tariff Order FY 2013-14 8

    remains. Accordingly, except for some corrections in methodology to

    be applied in some specific cases, the Commission has decided to

    continue with the prevailing tariff schedule. However, for ready

    reference the tariff schedule to be applicable in reference to this

    order is appended herewith as Annexure-I.

    15. The Commission directs the Companies to take appropriate steps toimplement the tariff Order. A public notice of minimum 7 days be

    given in accordance with the CSERC (Details to be Furnished by the

    Licensees or Generating Company for Determination of Tariff and

    Manner of Making Application) Regulations, 2004 and the MYT

    Regulations, 2012 before implementation of this Tariff Order.

    16. The detailed Order in reference to this joint order shall be issuedshortly.

    Sd/-

    (Vinod Shrivastava)

    MEMBER

    Sd/-

    (Manoj Dey)

    CHAIRMAN

    True Copy

    (P.N. Singh)

    Secretary