Table of Contents Sr.No. Particulars Page...

download Table of Contents Sr.No. Particulars Page No.dswcpunjab.gov.in/contents/pdf_forms/Earthen_WHS.pdf · Table of Contents Sr.No. Particulars Page No. 1. ... 1×11.12 =0.1798=0.18 !˘ˇ

If you can't read please download the document

Transcript of Table of Contents Sr.No. Particulars Page...

  • DESIGN & DRAWING OF EARTHERN WATER HARVESTING DAM

    Table of Contents

    Sr.No. Particulars Page No.

    1. Design data of Earthen Dam 1-2

    2. Storage Capacity 3

    3. Calculation of Earth work 4

    4. Detailed Estimate of Key Trench & Corewall 5

    5. Labour Cost of Dam Body 6

    6. Section of Dam Body 7-13

    7. Detailed Estimate of Spillway 14

    8. Calculation of MS Bar & Material of Spillway 15

    9. Cost Analysis of Spillway 16

    10. L-Section of Spillway 17

    11. Detailed Estimate of Antiseep Collars 18

    12. Material Statement of Antiseep Collars 18

    13. Cost Analysis of Antiseep Collars 18-19

    14. Drawing of Antiseep Collar 20

    15. Detailed Estimate of Intake Structure & Control Chamber 21

    16. Material Statement of Intake Structure 22

    17. Cost Analysis of Intake Structure & Control Chamber 23

    18. Drawing of Intake Structure & Control Chamber 24

    19. Summary of Cost 25

    20. Plan 26

  • Typical Design of Earthen Water Harvesting Structure

    I. Technical Data:

    a. Hydraulic Data

    Catchment Area : 16 ha

    Type of Soil : Loam to silt loam

    Elevation difference : 8 m

    Top of HILL R.L : 109.50 m

    Bed level R.L (Deepest) : 101.50 m

    Average rainfall : 1300 mm/year

    Type of Land : Sloping Forest Land with flatter

    valley

    Level of Top of Dam : 109.50 m

    Full Reservoir Level : 108.00 m

    b. Calculation for Peak Discharge

    Catchment area (A) : 16 ha

    Coefficient of Runoff (C) : 0.35

    Intensity of rainfall (I) : 140 mm/hr

    Using rational formula

    = 360 =0.35 140 16

    360 =784360 = 2.19

    c. Water Yield

    Total Average Rainfall : 1707 mm

    Rainfall Received in monsoon period (80%) : 1366 mm

    Runoff producing rainfall (60%) : 819.60 Say 820 mm

    Runoff coefficient : 0.35

    Maximum water yield : 16 x 0.82 x 0.35= 4.59 ha m

    d. Hydrological Data

    Design of Spillway for peak discharge of runoff

    Q= 1.711 LH 3/2

    = 2.191.71 0.75

    = 2.191.11 = 1.97 2.00

    Designed crest length = 2.00 m

    Height of the weir = 0.75 m

    Free board = 0.50 m

    Velocity of Flow

    = 1.8 = 1.8 9.81 7 = 123.60 = 11.12 /!"# Assume width of conduit section 1 m

  • = = $ %

    = $ % =2

    1 11.12 = 0.1798 = 0.18 ! 0.30

    Size of Conduit Section

    Breadth = 1 m

    Depth = (0.30 + 0.20 = 0.50 m)

    Basin Section

    ' = 2

    = 11.122 9.81 0.18

    = 11.123.53

    = 11.121.88 = 5.91

    Depth of hydraulic jump d2

    (

    = 1 2 )1 + 8' 1,

    = ( 1 2 )1 + 8' 1,

    =0.18

    2 )1 + 5.91 1, = 0.182 -280.42 1. = 16.74 1

    = 15.74 0.182 = 1.42 1.50

    II. General

    Catchment Area : 16 ha

    Maximum Length of Catchment Area : 600 m

    Average Width of Catchment Area : 255 m

    Peak Flood Discharge : 2.19 cumec

    Type of Soil : Sandy Loam

    Total Height of Earthen Dam : 8.00 m

    Height of Earthen Dam upto FSL : 6.50 m

    Depth of Key Trench : 2.00 m

    Side Slope of the Earthen Structure D/s : 2.0:1

    Side Slope of the Earthen Structure u/s : 2.50:1

    Top width of the Structure : 3.00 m

    Size of Spillway

    o Control Section : 2.0 x 1.5 x 5.0 m

    o Conduit Section : 1.0 x 0.50 x 10.80 m

    o Basin Section : 1.0 x 4.50 x 5.0 m

  • III. Storage Capacity

    RL Area Average Area (Sq M) HT Volume of

    Water (m2)

    Cumulative

    Volume

    101.50 - - - - - -

    102.50 600 0+600

    2

    300 1.0 300 300

    103.50 2375 600+2375

    2

    1487.50 1.0 1487.50 1787.50

    104.50 3750 2375+3750

    2

    3050.00 1.0 3050.00 4837.50

    105.50 5625 3750+5625

    2

    4687.50 1.0 4687.50 9525.00

    106.50 8100 5625+8100

    2

    6862.50 1.0 6862.50 16387.50

    107.50 11150 8100+11150

    2

    9625.00 1.0 9625.00 26012.50

    108.00 13800 11150+13800

    2

    12475.00 0.50 6237.50 32250.00

    Say 3.22 ha m

    Total storage capacity = 32250 m3 = 3.22 ha m

    IV. Estimated Cost: Rs. 14,82,450/-

  • V. Calculation of Earthwork of Dam Body Water Harvesting Earthen Dam

    RD HT Top

    Width

    Base

    Width

    Average Width X-Section

    Area

    Average X-Sectional Area Distance Volume Cumulative

    Volume

    0 - - - - - - - - - - -

    10 5.39 3.0 32.00 32+3

    2

    =17.50 =94.33 0+94.33

    2

    =47.17 10

    471.70 471.70

    20 7.09 3.0 34.50 34.50+3

    2

    =18.75 =132.94 94.33+132.94

    2

    =113.64 10 1136.40 1608.10

    30 7.96 3.0 39.00 39.00+3

    2

    =21.00 =167.16 132.94+167.16

    2

    =150.05 10 1500.50 3108.60

    40 7.15 3.0 34.50 34.50+3

    2

    =18.75 =134.06 167.16+134.06

    2

    =150.61 10 1506.10 4614.70

    50 4.75 3.0 23.50 23.50+3

    2

    =13.25 =62.94 134.06+62.94

    2

    =98.50 10 985.00 5599.70

    60 0 3.0 0 - - - 62.94+0

    2

    =31.47 10 314.70 5914.40

    S.

    =o

    Particular =o L B H Content

    1 Removal of Organic Matter

    Av Length = 24+50+60+49+38 = 44.20 m

    5

    Av Width = 32+34.50+39+34.50+23.50= 32.70 m

    5

    1

    44.20

    32.70

    0.30

    722.67

    Say 723 Cum

    2 Excavation of earthwork in foundation

    Key Trench 26-44

    1 18 2+4

    2

    2.00 108 cum

    Excavation of Earthwork for anchoring for corewall

    Left Side

    Right Side

    Total

    1

    1

    28

    21

    2

    2

    2

    2

    112

    84

    196 Cum

  • L D

    m m

    1 Earthwork filling of Key Trench 1 18.00 2.00 + 4.00 2.00 108.00 Cum

    2

    1 Earthwork filling of Corewall

    Part A 1 17.40 4.00 + 3.70 1.00 66.99

    2

    Part B 1 26.00 3.70 + 3.40 1.00 92.30

    2

    Part C 1 31.80 3.40 + 3.10 1.00 103.35

    2

    Part D 1 36.00 3.10 + 2.80 1.00 106.20

    2

    Part E 1 44.60 2.80 + 2.50 1.00 118.19

    2

    Part F 1 51.00 2.50 + 2.20 1.00 119.85

    2

    Part G 1 52.40 2.20 + 2.00 0.75 82.53

    2

    Total 689.41 Cum

    3 Corewall foundation filling

    Left Side 1 28.00 2.00 112.00

    Right Side 1 21.00 2.00 84.00

    Total 196.00 Cum

    Total Filling

    Say 993 Cum

    Total Earthwork

    Cum

    Say 4617 Cum

    Less Earthwork Key Trench & Corewall -993.00

    Total Earthwork 4617.40

    Less Earthwork Excavation of Key Trench &

    Corewall (196+208 = 304)-304.00

    Balance Earthwork of Dam Body 4921.40

    Total Earthwork 993.41

    2.00

    2.00

    Earthwork of Dambody 5914.40

    Key Trench Filling 108.00

    Corewall Filling 689.41

    Corewall Foundation Filling 196.00

    Detailed Estimate of Keytrench and Corewall

    S. (o Particular (o B Contents

    m m3

  • S. o Particular Qty Rate Amount

    1 Excavation in foundation, trenches etc in earth work,

    lift upto 1.50 m, stacking the excavated soil not more

    than 3 m clear from the edge of excavation and their

    returning the stacked soil in 15 cm layers, where

    required, into plinth, sides of foundation etc.

    consolidating each deposited layer by ramming and

    watering and then disposing of all surplus excavated

    earth as directed with in a lead of 20 m.

    Excavation in Earthwork in foundation of Dam Body

    Spade Work Manually (Removal of organic matter)

    723 50.50 36511.50

    Excavation of Key Trench and corewall anchoring

    (Pick Work)

    304 62.70 19060.80

    Excavation of impervious/heavy soil from selected

    area to refill the Key Trench, Core wall anchoring and

    core wall. Pick Work

    993 62.70 62261.10

    2 Carriage of heavy soil from selected area to fill the

    key trench, corewall, corewall anchoring lead by

    tractor trolly lead 1 km

    993 64.44 63988.92

    3 Spreading excavated heavy soil in 15 to 25 cm layer

    including watering/puddling/ramming and dressing

    complete. Spade Work

    993 65.30 64842.90

    4 Excavation and filling of Dam body with average lead

    100 m in 20 cm layer watering ramming to achieve

    DBD 1.76 tonne/m3

    Dam Body-Key Trench-

    Corewall=5631.17-993= 4638.17

    4617 62.70 289485.90

    5 Lift extra for every additional lift 1.5 m or part

    thereof upto 1.50 m lift

    1st lift 920 Cum 1x4 4 3680.00

    2nd lift 830 Cum 2x4 8 6640.00

    3rd lift 750 Cum 3x4 12 9000.00

    4th lift 680 Cum 4x4 16 10880.00

    5th lift 505 Cum 5x4 20 10100.00

    6 Extra for Lead of 20 m or part thereof

    100- 20 = 80/20 = 4 Leads 4617/2=2308

    2308 4x3.40

    =13.60

    31388.80

    Total 607839.92

    607839.92

    A Total 1215679.84

    Add 3 % Contingency 36470.40

    Grand Total 1252150.24

    Cost Analysis of Earthen Water Harvesting Structure

    Unit

    * The rates applied are general in nature. To calculate the exact cost, appropriates rates may please be

    applied

    Rs. Twelve Lakh Fifty Two Thousand One Hundred and Fifty Only

    Add 100% enhancement on items above

    Cum

    Cum

    cum

    cum

    Cum

    cum

    cum

    Say 12,52,150/-

  • L B

    m m

    1 Excavation of earthwork in foundation

    Control Section RD 0-5 1 5.00 2.46 1.50 + 0.93 14.94

    2

    5--10 1 5.00 2.46 0.93 + 0.57 9.22

    2

    Cutoff wall between spillway and dambody

    (Toewall)1 4.00 0.50 2.60

    10--15 1 5.00 1.46 0.57 + 1.07 5.98

    2

    15-20 1 5.00 1.46 3.00 + 0.85 14.05

    2

    Wing wall of control wall 2 0.77 0.23 0.53

    Cutoff walls

    Control Section 1 2.46 0.30 0.37

    Conduit Section 3 1.46 0.30 0.65

    Basin Section 2 0.77 0.23 0.30

    Total 48.65

    Say 49 Cum

    2 RCC work 1:2:4

    Base Slab

    Control Section 1 5.00 2.46 2.46

    Conduit Section 1 10.80 1.46 3.15

    Basin Section 1 5.00 1.46 1.46

    Vertical Position of Basin Section 1 1.46 0.20 0.88

    Cutoff Walls

    Control Section 1 2.46 0.30 0.36

    Conduit and Basin Section 3 1.46 0.30 0.65

    Cutoff wall between spillway and dambody

    (Toewall)1 4.00 0.50 2.60

    Total 11.56 Cum

    3 Brick Work 1:4

    Side walls Control Section 2 6.00 0.23 4.14

    Wing wall of control Section 2 0.77 0.23 0.53

    Conduit Section 2 9.80 0.23 2.25

    Basin Section 2 5.00 0.23 10.35

    Toewall and Toewall Extension 1 3.00 0.23 0.69

    Toewall Extension 2 1.00 0.23 2.07

    Total 20.03 Cum

    4 10 mm thick cement plaster 1:4

    Side walls Inside

    Control Section 2 6.00 - 18.00

    Top of Control Section 2 6.00 0.23 2.76

    Conduit Section 2 9.80 - 9.80

    Top of Conduit Section 2 9.80 0.23 4.51

    Basin Section 2 5.00 - 45.00

    Top of Control Section 2 5.00 0.23 2.30

    Outside of Basin Section 2 5.00 - 35.00

    Front Side 2 0.23 - 1.61

    Total 118.98

    Say 119 Sq M

    1.30

    0.20

    3.00

    0.50

    -

    0.50

    1.50

    1.50

    4.50

    1.00

    4.50

    1.30

    0.50

    0.50

    0.50

    0.50

    1.50

    0.20

    0.20

    Detailed Estimate of Spillway

    1.50

    -

    4.50

    -

    3.50

    3.50

    S. #o Particular #o Contents

    m3

    H

    m

    0.85

  • 10 mm dia 15 cm c/c & f/f W o L

    Control Section Long Bars 246 16 5 = 80 x 2 = 160

    15

    Conduit Section Long Bars 146 10 10.80 = 108 x 2 = 216

    15

    Basin Section Long Bars 146 10 8.00 = 80 x 2 = 160

    15

    Cross Bars

    Control Section 500 33 2.46 = 81 x 1 = 81

    15

    Control Section 500 17 3.00 = 51 x 1 = 51

    15

    Conduit Section 1080 72 1.46 = 105 x 1 = 105

    15

    Conduit Section 1080 72 2.00 = 144 x 1 = 144

    15

    Basin Section 800 53 2.46 = 130 x 2 = 261

    15

    1178

    Vertical Bars 10 mm dia 15 cm c/c & f/f

    Cutoff Walls W o L

    Control Section 246 16 0.80 = 12.80 x 2 x 2 = 51

    15

    Conduit & Basin Section 146 15 0.80 = 12.00 x 2 x 3 = 72

    15

    Cross Bars

    Control Section 50 3 2.46 = 7.38 x 2 = 15

    15

    Conduit & Basin Section 50 3 1.46 = 4.38 x 3 = 13

    15

    151

    10 mm dia Bars= 1178 + 151 = 1329 x 0.62 = 823.98 Say 824 Kg

    Bajri Bricks

    (Cum) os

    1 RCC Work 1:2:4 11.56 10.40 -

    2 1st Class Brick Work 1:4 20.03 - 9614

    3 10 mm thick Cement Plaster 1:4 119.00 - -

    10.40 9614

    Say 10

    Cum

    osSay 12

    Cum

    11.62

    1.42

    5.00

    5.20

    Total

    Particulars Qty

    Kg

    824

    -

    -

    824

    Say 122

    Bags

    122.30

    10.71

    36.45

    75.14

    (Bags)

    Cement

    Calculation of MS Bar for Spillway

    Material Statement

    (Kg)

    MS BarsS. o

    Total

    Total

    (Cum)

    Sand

  • S. o Particular Qty Unit Rate Amount

    1 Excavation in foundation, trenches etc in earth work, lift upto

    1.50 m, stacking the excavated soil not more than 3 m clear

    from the edge of excavation and their returning the stacked soil

    in 15 cm layers, where required, into plinth, sides of foundation

    etc. consolidating each deposited layer by ramming and

    watering and then disposing of all surplus excavated earth as

    directed with in a lead of 20 m. Pick Work

    49 cum 62.70 3072.30

    2 Reinforced Cement Concrete RCC Work 1:2:4 I/c curing

    complete but excluding cost of form work ad reinforcement.

    Walls (any thickness but not less than 0.10 m thick) I/c

    attached pilasters, buttresses, plinth and string courses from top

    of foundation up to floor two level

    11.56 Cum 209.20 2418.35

    3 Mild Steel for steel reinforcement for RCC work including

    bending and placing in position complete upto floor two level

    I/c cost of binding wire

    8.24 Qtl 250.60 2064.94

    4 First Class brick work 1:4 in cement or lime mortar in

    foundation and plinth.

    20.03 Cum 298.00 5968.94

    5 Cement plaster skirting (upto 300 m height) with cement

    mortar 1:3 finished with a floating coat of neat cement

    including rounding of junction with floor. 15 mm Thick

    119.00 Cum 23.70 2820.30

    6 Carriage of Cement from Store to site. Lead 5 km including

    unloading and stocking (122/20=6.10 Tonne)

    6.10 Tonne 61.36 374.30

    upto 5 Km = 61.36

    7 Carriage of Sand & Bajri from crusher to site of work by

    Tractor trolly lead 10 km (Sand + Bajri = 12 + 10 = 22 Cum)

    22 Cum 123.86 2724.92

    0-5 km = 92.06

    6-10 @ 6.36 = 31.80

    Total = 123.86

    8 Hiring and operating charge for Concrete mixer 11.56 Cum 12.50 144.50

    Total 19588.55

    19588.55

    A Total 39177.10

    1 Cement 122 bag 176 21472.00

    2 Crusher Aggregate (12-15 mm) 10 Cum 400 4000.00

    3 River Sand 12 Cum 200 2400.00

    4 MS Bars including carriage 824 Kg 35 28840.00

    5 Bricks including carriage 9614 Per Thousand

    4000 38456.00

    B Total 95168.00

    Total (A+B) 134345.10

    Add 3 % Contingency 4030.35

    Grand Total 138375.46

    * The rates applied are general in nature. To calculate the exact cost, appropriates rates may please be

    applied

    Rs. One Lakh Thirty Eight Thousand Three Hundred and Seventy Five Only

    Cost Analysis of Spillway

    Add 100% enhancement on items above

    Cost of Material

    39177.10+95168

    Say 1,38,375/-

  • Detailed Estimate of Anti-seep Collar

    S.

    o

    Particular o L

    M

    B

    M

    H

    M

    Contents

    m3

    1 Excavation of earthwork in foundation 6 1.20 0.40 0.30 0.86 cum

    2 CC work 1:4:8 in foundation 6 1.20 0.40 0.10 0.29 cum

    3 1st Class Brick Work 1:4 6 1.00 0.23 1.00 1.38 Cum

    Material Statement of Anti-Seep Collar

    S. o Particular Quantity Cement River

    Sand

    Crusher

    Bajri

    Bricks

    Bags Cum Cum os

    1 CC 1: 4:8 0.29 cum 0.99 0.13 0.27

    2 Brick Work 1:4 1.38 2.51 0.34 - 662.40

    Total 2.50 Say 3

    Bags

    0.47 Cum 0.27 Cum 662 os

    Costing of Anti-Seep Collar

    S.

    o

    Item o of

    S.R 2002- 03

    Particular Qty Unit Rate

    Rs

    Amount

    Rs.

    1 Chapter V

    (A)ii

    Dept CSR

    Excavation in foundation, trenches etc in

    earth work, lift up to 1.50 mtrs, stacking the

    excavated soil not more than 3 mtrs clear

    from the edge of excavation and their

    returning the stacked soil in 15 cm layers,

    where required, in to plinth, sides of

    foundation etc. consolidating each deposited

    layer by ramming and watering and then

    disposing of all surplus excavated earth as

    directed with in a lead of 20 mtr. Pick work

    0.86 Cum 62.70 53.92

    2 Chapter -V

    (C) ii Laying of Plain CC 1:4:8 in foundation

    Reinforced Cement Concrete

    Walls (any thickness but not less than 0.10

    m thick) I/c attached pilasters, buttresses,

    plinth and string courses from top of

    foundation up to floor two level

    0.29 Cum 254.40 73.77

    3 Chapter 5 E

    (a) I

    First Class Brick work in 1:4. First class

    brick work in cement or lime mortar in

    foundation and plinth

    1.38 Cum 298 411.24

    4 PWD CSR

    0604000000

    Carriage of Cement from Store to site of

    work. Lead 5 km including unloading and

    stocking (3/20=0.15 Tonne)

    upto 5 Km = 61.36

    0.15 Tonne 61.36 9.20

    5 0601020102

    & 101

    Carriage of Sand & Bajri from crusher to

    site of work by Tractor trolly lead 10 km.

    (Sand + Bajri = 0.47 + 0.27 = 0.74 Cum)

    0-5 km = 92.06

    6-10 @ 6.36 = 31.80

    Total = 123.86

    0.74 Cum

    123.86 91.65

    Total 639.99

  • S.

    o

    Item o of

    S.R 2002- 03

    Particular Qty Unit Rate

    Rs

    Amount

    Rs.

    Add 100% enhancement on items above 639.99

    Total 1279.98

    1

    COST OF MATERIAL

    Cement

    3

    Bag

    176

    528.00

    2 Crusher Bajri 0.27 Cum 400 108.00

    3 River Sand 0.47 Cum 200 94.00

    4 Bricks including carriage 662 Per Thousand

    4000 2648

    Total 3378

    Total A+B 1279.98+3378 4657.98

    Add Contingency @ 3% 139.74

    Grand Total 4797.72

    Say 4,798/-

    Rs. Four Thousand Seven Hundred and inety Eight Only

    * The rates applied are general in nature. To calculate the exact cost, appropriates rates may

    please be applied

  • L H

    m m

    1 Excavation of earthwork in foundation

    (i) Control Chamber 1 2.26 0.60 3.06

    (ii) Intake Structure 1 1.76 0.75 2.32

    Total 5.38 Cum

    2 CC 1:4:8 in foundation Control Chamber 1 2.26 0.15 0.76

    Intake Structure 1 1.76 0.15 0.46

    Total 1.22 Cum

    3 CC 1:2:4 above 1:4:8

    Intake Structure 1 1 0.05 0.05

    Control Chamber 1 1.50 0.05 0.11

    Total 0.16 Cum

    4 1st Class Brick Work

    Intake Structure

    Long Walls 2 1.46 3.00 2.01

    Short Walls 2 1.00 3.00 1.38

    Control Chamber

    Long Walls 2 1.96 1.50 1.35

    Short Walls 2 1.50 1.50 1.03

    Total 5.77 Cum

    5 Plaster Work 1:4 15 mm thick

    Intake Structure

    Top of Long Wall 2 1.46 - 0.67

    Short Wall 2 1.00 - 0.46

    Inside of Structure 4 1.00 2.95 11.80

    Outside of Structure 4 1.46 2.25 13.14

    Control Chamber

    Top of Long Wall 2 1.96 - 0.90

    Short Wall 2 1.50 - 0.69

    Inside of Structure 4 1.50 1.45 8.70

    Outside of Structure 4 1.96 0.90 7.05

    Total 43.41 Sq M

    6 Laying and joining of CI Pipe 150 mm dia

    with socket

    1 38 - 38 M

    7 Fixing and Laying of Sluice Valve 150 mm

    dia

    2 - - 2 o

    8 Fixing of MS Bars for stairs in Intake &

    Control Chamber

    10 - - 10 M

    9 Fixing of MS Bar Jal on top of Intake

    Structure ( Size 1.15 x 1.15 m)

    1 - - 1 o

    10 Fixing of MS Sheet on top of control

    chamber with man hole (Size 1.65 x 1.65 m)

    1 - - 1 o

    1.76

    1

    0.23

    2.26

    Detailed Estimate of Intake Structure and Control Chamber

    m

    B

    1.76

    2.26

    S. o Particular o Contents

    m3

    1.50

    0.23

    0.23

    -

    -

    0.23

    -

    -

    0.23

    0.23

    0.23

    0.23

    -

    -

    -

    -

    -

  • Cement Sand Bajri Bricks MS Bars CI Pipe Sluice Valve Pig Lead MS Jal MS Sheet

    150 mm 150 mm

    M !o Kg

    1 CC 1:4:8 1.22 4.14 0.57 1.14 - - - - - - -

    2 CC 1:2:4 0.16 1.04 0.07 0.14 - - - - - - -

    3 1st Class Brick Work 1:4 5.77 10.50 1.44 - 2770 - - -

    4 Plaster Work 1:4 15 mm thick 43.41 4.99 0.69 - - - - - - - -

    5 Laying of CI Pipe 150 mm dia 38 - - - - - 38 - 10.56 - -

    6 Fixing of Sluice valve 150 mm dia 2 - - - - - - 2 - - -

    7 Fixing of MS Bars 12 mm dia 10 m x 0.89

    = 8.90 Say 9 Kg

    10 m / 9

    Kg

    - - - - 9 - - - - -

    8 Fixing of MS Jal on top of Intake

    Structure

    1 - - - - - - - - 1 -

    9 Fixing of MS Sheet on the Control

    Chamber

    1 - - - - - - - - - 1

    Total 20.67 2.77 1.28 2770 9.00 38 2 10.56 1.00 1.00

    Say 21

    Bags

    Say 3

    Cum

    Say 1

    Cum

    Kg Kg M !o Say 11 Kg !o !o

    Kg !o !o!oS. !o Particular Qty Bag Cum Cum

    Material Statement for Intake Structure

  • S.

    o

    Particular Qty Unit Rate Amount

    1 Excavation in foundation, trenches etc in earth work, lift upto

    1.50 m, stacking the excavated soil not more than 3 m clear from

    the edge of excavation and their returning the stacked soil in 15

    cm layers, where required, into plinth, sides of foundation etc.

    consolidating each deposited layer by ramming and watering and

    then disposing of all surplus excavated earth as directed with in a

    lead of 20 m. Pick Work

    5.38 cum 62.70 337.33

    2 Laying of Plain CC 1:2:4, 1:4:8 in foundation

    Cement/ Lime Concrete in Foundation and Under Floors. Plain

    1:2:4+ 1:4:8 in walls including buttresses pilasters and their caps

    and bases and string courses etc (1.22+0.16 = 1.38)

    1.38 Cum 254.40 351.07

    3 First Class Brick work in 1:4. First class brick work in cement

    or lime mortar in foundation and plinth

    5.77 Cum 298.00 1719.46

    4 15 mm thick cement plaster 1:4 43.41 Sq M 23.70 1028.82

    5 Providing Lead chaulked joints to sand cast iron 150 mm dia (38

    m/ 6 Nos) (20.20 x 2 = 40.40)

    6.00 No 40.40 242.40

    6 Carriage of Cement from Store to site of work. Lead 5 km

    including unloading and stocking (21/20=1.05 Tonne)

    1.05 Tonne 61.36 64.43

    upto 5 Km = 61.36

    7 Carriage of Bajri from crusher to site of work by Tractor trolly

    lead 10 km. (Sand + Bajri = 3+1 =4 Cum)

    4 Cum 123.86 495.44

    0-5 km = 92.06

    6-10 @ 6.36 = 31.80

    Total = 123.86

    8 Laying of CI Pipe 150 mm dia (8.40 x 2 = 16.80) 38.00 M 16.80 638.40

    9 Fixing of Sluice Valve 150 mm dia (68 x 2 = 136) 2.00 No 136.00 272.00

    Total 5149.34

    5149.34

    A Total 10298.68

    1 Cement 21 bag 176 3696.00

    2 Crusher Aggregate (12-15 mm) 1 Cum 400 400.00

    3 River Sand 3 Cum 200 600.00

    4 Bricks including carriage 2770 Per Thousand

    4000 11080.00

    5 MS Bar including carriage 9 Kg 35 315.00

    6 CI Pipe 150 mm dia (MR) 38.00 M 1000 38000.00

    7 Sluice Valve 150 mm dia (MR) 2 No 5000 10000.00

    8 Lead (MR) 11 Kg 200 2200.00

    9 MS Jal (1m x1m) including labour & carriage(MR) 1 No 3000 3000.00

    10 MS Sheet 1.50 x 1.50 1 No 5000 5000.00

    B Total 74291.00

    Total (A+B) 84589.68

    Add 3 % Contingency 2537.69

    Grand Total 87127.37

    Cost Analysis of Intake Structure & Control Chamber

    Add 100% enhancement on items above

    Cost of Material

    10298.68+74291

    Rs. Eighty Seven Thousand One Hundred and Twenty Seven Only

    Say 87,127/-

    * The rates applied are general in nature. To calculate the exact cost, appropriates rates may please be

    applied

  • S. o Particular Amount

    1 Cost of Dam Body 12,52,150.00

    2 Cost of Spillway 1,38,375.00

    3 Cost of Antiseep Collars (6 No) 4,798.00

    4 Cost of Intake Structure & Control Chamber 87,127.00

    Total 14,82,450.00

    Rs. Fourteen Lakhs Eighty Two Thousand Four Hundred and Fifty Only

    Summary of Structure