T-76.115 Project Review
-
Upload
hadassah-duke -
Category
Documents
-
view
18 -
download
3
description
Transcript of T-76.115 Project Review
![Page 1: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/1.jpg)
T-76.115 Project Review
eGoI2 Iteration
11.2.2004
![Page 2: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/2.jpg)
2
T-76.115 Project ReviewT-76.115 Project Review
Agenda
Project status (15 min) achieving the goals of the iteration project metrics
Used work practices (5 min) Completed work (10 min)
demo Plans for the next iteration (5 min) Open discussion (10 min)
![Page 3: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/3.jpg)
3
T-76.115 Project ReviewT-76.115 Project Review
Status of planned goals of the iteration
GOAL 1 Working prototype of the system – OK!
GOAL 2 Interview part of the esurvey system – OK!
GOAL 3 User Interface heuristic evaluation – OK!
GOAL 4 Automated unit tests – NOT OK! Automated unit tests are dropped because of huge
amount of work demanded and little amount of advantages gained from tests. Testing is decided to be implemented differently
![Page 4: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/4.jpg)
4
T-76.115 Project ReviewT-76.115 Project Review
Realization of the tasks
Lot of meetings Internal and Customer. Although lot of time were spend benefits were also substantial
WEB interface also took a lot of time but very satisfactory product was build.
DS:Write/update tech. specs 6,50 20,00 -13.5
GE:Meetings (customer) 24.00 35,00 -11,00
GE:Meetings (internal) 55.00 38,00 17,00
GE:Meetings (status/mentor) 7.00 14,00 -7,00
IM:GUI 32.50 20,00 12,50
IM:update project plan 32,50 15,00 -9.5
IM:Use Case 1 13.50 15,00 -1.5
IM:Use Case 2 54.50 15,00 39,5
IM:Use Case 3 24.00 15,00 9,00
IM:Use Case 4 12,50 15,00 -2.5
IM:Use Case 6 34.50 25,00 9,50
IM:Use Case 7 38.50 25,00 13,50
IM:Use Case 8 11.00 25,00 -14,00
IM:Use Case 9 21.00 20,00 1,00
PM:Other project management 22.50 20,00 2,50
PM:Personal SE practice 20.00 25,00 -5,00
PM:Plan the next iteration 6.00 10,00 -4,00
PM:Write progress report 4.00 5,00 -1,00
TE: Module Testing 8,50 15,00 -6.5
TE:Execute and report tests 20.00 20,00 0,00
TE:Prepare testing 9.00 15,00 -6,00
![Page 5: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/5.jpg)
5
T-76.115 Project ReviewT-76.115 Project Review
Working hours
Over 75% of project is done Only 300 hours left little over 1000 hours used
during the PP+I1+I2
Everybody has done something during I2
Differencies between persons caused by different field knowledge
PP + I1 + I2
I3
DE
0 10 20 30 40 50 60 70 80
aha
hjt
jjk
jka
lhe
sle
sll
Series1
![Page 6: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/6.jpg)
6
T-76.115 Project ReviewT-76.115 Project Review
Quality metrics
Team is now familiar with BugZilla Most of the bugs were found outside ”disciplined” testing
I1 I2 I3 DE TotalReported 3 20 23Closed 1 10 11Open 2 10 12
Bug metrics
Blockers Critical Major Minor Trivial TotalTotal open 0 0 5 5 2 12This iteration reported
0 0 2 5 3 10
![Page 7: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/7.jpg)
7
T-76.115 Project ReviewT-76.115 Project Review
Quality assessment
Feedback from the Quality Department The tests covered all the requirements that were set for
this iteration Overall state of the components is good The group is now familiar with Bugzilla Additional bug reporting tools used: TODO-lists, email,
Messenger, ICQ...
Overall quality is good
Functional area Coverage Quality Comments
Web UI 3 Re-tested in I2 phase, works fine now
Questionnaire creation
3 Apart from minor enhancements it is ready
Screening with WAP 2 Good progress, but still not enough testing made
Legend
Coverage:
0 = nothing
1 = we looked at it
2 = we checked all functions
3 = it’s tested
Quality:
= quality is good
= not sure
= quality is bad
![Page 8: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/8.jpg)
8
T-76.115 Project ReviewT-76.115 Project Review
Peer testing
Peer group (Muuntaja) has been contacted and schedule has been negotiated
Peer testing will be performed on week 10, covering: questionnaire creation & upload web UI functionalities WAP interviewing web interviewing
8 man-hours of work by peer group is allocated for us
![Page 9: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/9.jpg)
9
T-76.115 Project ReviewT-76.115 Project Review
Software size (Java)
We chose to use Number of Statements, since it gives a better view of the software
Configuration work, web resources, excel macros etc not included here VM pages are also not included (both web and wap)
PP I1 I2 I3 DELines of Code in Methods (LOCm) 0 368 722Number of statements (NOS) 0 261 572Number of Lines 0 2859 6838
![Page 10: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/10.jpg)
10
T-76.115 Project ReviewT-76.115 Project Review
Risks
Risk management is done by three the members of the group attending risk management module
Following conclusions have been made during the I2-iteration Some minor setbacks in technology sector Time is luxury that we don’t have. Good risk management has been efficent and risk factors have decreased
![Page 11: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/11.jpg)
11
T-76.115 Project ReviewT-76.115 Project Review
Work practices
The group has used all the mandatory practices demanded by the course Version control system has worked well via eclipse. Time reporting has been working well. Difficult to report for progress report
beacuse not all the hours are done when progress report has to be handed in. Long period of time has also caused some hours to be forgotten
Bugzilla has been used to report bugs. The amount of use has been increased from I1 period. All founded bugs are not yet reported through bugzilla but use has been increases
Members have been studying and documenting their own personal practices GUI has been tested by end users Some advantage has been gained through more efficent internal
communicating The use of Heuristic Evalution practice is shortly briefed by Sampo
During the next iteration Final touch to personal assigments
![Page 12: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/12.jpg)
12
T-76.115 Project ReviewT-76.115 Project Review
Results of the iteration
Working implementation of use cases 6.1-6.9 ( not 6.5 demo):
New deliverables for the iteration were User guides torsos (three different versions)
![Page 13: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/13.jpg)
13
T-76.115 Project ReviewT-76.115 Project Review
User Guide wap
On-going projects can be browsed When logged in ongoing projects will show in the list Choose the right project and open link Brief summary of project is shown and link to start interviewing is also
shown On-going projects can be monitored
The quotas that need to filled and brief description of those can be read form start page of the project
Choose the quota to see it's desctription The quota shows the results in format 1/30(on is founded and
interviewed, the total amount of quota is 30) Interview of certain project can be delivered
If interview link is choosed interview will start Pressing back button will return you to earlier quoestion and empty
the result of the question When finished the phone will print results Abort button will abort interview session After interview updated quotas will be shown
![Page 14: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/14.jpg)
14
T-76.115 Project ReviewT-76.115 Project Review
Test Documentation
Test planning Started in PP phase Testing practices and responsibilities are now planned and documented
Test cases Test cases are grouped into test suites after use cases in addition to just verifying that functionalities are implemented, defects are
looked for by testing limits for input values Test cases (total 16 in this iteration) were documented and run, see test
specification for details Test specification = test log
Test report concludes the results of testing
QA in the future Heavy system testing to be done by eGo, customer and peer group automate the tests
![Page 15: T-76.115 Project Review](https://reader036.fdocuments.net/reader036/viewer/2022072014/56812e35550346895d939e37/html5/thumbnails/15.jpg)
15
T-76.115 Project ReviewT-76.115 Project Review
Plan for the next iteration
Goals Pilot case (after/before winter holidays) Working product Data export
Deliverables Fully operational product Installing instructions User guide wep User guide wap List of cell phones that work with the
product
DS:Write/update tech. specs 10 13.2.2004 18.3.2004
GE:Meetings (customer) 21 13.2.2004 18.3.2004
GE:Meetings (internal) 14 13.2.2004 18.3.2004
GE:Meetings (status/mentor) 7 13.2.2004 18.3.2004
IM: Bug fixing 17 13.2.2004 18.3.2004
IM:Use Case 2 8 13.2.2004 29.2.2004
IM:Use Case 6 10 13.2.2004 29.2.2004
IM:Use Case 8 15 13.2.2004 29.2.2004
IM:Use Case 9 10 13.2.2004 29.2.2004
IM:Write user guides 10 13.2.2004 18.3.2004
PM:Other project management 15 13.2.2004 18.3.2004
PM:Personal SE practice 14 13.2.2004 18.3.2004
PM:Plan the next iteration 5 14.3.2004 18.3.2004
PM:Project review and preparation
14 14.3.2004 18.3.2004
PM:Write progress report 6 14.3.2004 18.3.2004
TE:Execute and report peer tests 8 1.3.2004 8.3.2004
TE:Execute and report tests 15 13.2.2004 18.3.2004