Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ......
Transcript of Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ......
![Page 1: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/1.jpg)
1
Systems Design: Process Costing
M. En C. Eduardo Bustos Farías
![Page 2: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/2.jpg)
2
Types of Costing Systems Used to Determine Product Costs
Job-orderCosting
ProcessCosting
Many units of a single, homogeneous productflow evenly through a continuous productionprocess.One unit of product is indistinguishable from anyother unit of product.Each unit of product is assigned the sameaverage cost.
Many units of a single, homogeneous productflow evenly through a continuous productionprocess.One unit of product is indistinguishable from anyother unit of product.Each unit of product is assigned the sameaverage cost.
![Page 3: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/3.jpg)
3
Types of Costing Systems Used to Determine Product Costs
Job-orderCosting
ProcessCosting
Typical process cost applications:Petrochemical refineryPaint manufacturerPaper mill
Typical process cost applications:Petrochemical refineryPaint manufacturerPaper mill Fabricación de papel
![Page 4: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/4.jpg)
4
Differences Between Job-Order and Process Costing
Job order costingMany jobs are worked during the period.Costs are accumulated by individual jobs.Job cost sheet is the key document.Unit cost computed by job.
Job order costingMany jobs are worked during the period.Costs are accumulated by individual jobs.Job cost sheet is the key document.Unit cost computed by job.
Process costingA single product is produced for a long period of time.Costs are accumulated by departments. Department production report is key document. Unit costs are computed by department.
Process costingA single product is produced for a long period of time.Costs are accumulated by departments. Department production report is key document. Unit costs are computed by department.
![Page 5: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/5.jpg)
5
An Operational Process System
TabletingTabletingMixingMixing BottlingBottling
LoadingCountingCappingPackaging
LoadingPressingCosting
SelectingSiftingMeasuringBlending
![Page 6: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/6.jpg)
6
Quick Check
Process costing is used for products that are:a. Different and produced continuously.b. Similar and produced continuously.c. Individual units produced to customer
specifications.d. Purchased from vendors.
Process costing is used for products that are:a. Different and produced continuously.b. Similar and produced continuously.c. Individual units produced to customer
specifications.d. Purchased from vendors.
![Page 7: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/7.jpg)
7
Quick Check
Process costing is used for products that are:a. Different and produced continuously.b. Similar and produced continuously.c. Individual units produced to customer
specifications.d. Purchased from vendors.
Process costing is used for products that are:a. Different and produced continuously.b. Similar and produced continuously.c. Individual units produced to customer
specifications.d. Purchased from vendors.
![Page 8: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/8.jpg)
8
Job-Order CostingJob-Order Costing
Direct MaterialsDirect MaterialsDirect LaborDirect LaborApplied OverheadApplied Overhead
Job 206Job 206Job 205Job 205 Job 207Job 207
Estrella CompanyEstrella
CompanyManufacturing Costs
Finished GoodsFinished GoodsFinished GoodsFinished Goods Finished GoodsFinished Goods
![Page 9: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/9.jpg)
9
Process CostingProcess Costing
Direct MaterialsDirect MaterialsDirect LaborDirect LaborApplied OverheadApplied Overhead
TabletingTabletingPickingPicking BottlingBottling
Finished GoodsFinished Goods
Manufacturing CostsEstrella CompanyEstrella
Company
![Page 10: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/10.jpg)
10
Process Costing
DirectMaterials
Type of Product Cost
Dol
lar A
mou
nt
DirectLabor
Conversion
Direct labor costsmay be small
in comparison toother product
costs in processcost systems.
Direct labor costsmay be small
in comparison toother product
costs in processcost systems.
![Page 11: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/11.jpg)
11
Process Costing
Type of Product Cost
Dol
lar A
mou
nt
Conversion
So, direct labor and manufacturing overhead are oftencombined into one product cost called conversion.
So, direct labor and manufacturing overhead are oftencombined into one product cost called conversion.
Direct labor costsmay be small
in comparison toother product
costs in processcost systems.
Direct labor costsmay be small
in comparison toother product
costs in processcost systems.
DirectMaterials
![Page 12: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/12.jpg)
12
Comparing Job-Orderand Process Costing
FinishedGoods
FinishedGoods
Cost of GoodsSold
Cost of GoodsSold
Work inProcess
Direct MaterialsDirect
Materials
Direct LaborDirect Labor
ManufacturingOverhead
ManufacturingOverhead
![Page 13: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/13.jpg)
13
Comparing Job-Orderand Process Costing
FinishedGoods
FinishedGoods
Cost of GoodsSold
Cost of GoodsSold
Direct LaborDirect Labor
ManufacturingOverhead
ManufacturingOverhead
JobsJobs
Costs are traced andapplied to individualjobs in a job-order
cost system.
Costs are traced andapplied to individualjobs in a job-order
cost system.Direct
MaterialsDirect
Materials
![Page 14: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/14.jpg)
14
Comparing Job-Orderand Process Costing
FinishedGoods
FinishedGoods
Cost of GoodsSold
Cost of GoodsSold
Direct LaborDirect Labor
ManufacturingOverhead
ManufacturingOverhead
ProcessingDepartmentProcessingDepartment
Costs are traced and applied to departments
in a process cost system.
Costs are traced and applied to departments
in a process cost system.
Direct MaterialsDirect
Materials
![Page 15: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/15.jpg)
15
Characteristics of Process Costing
Characteristics of Process Characteristics of Process CostingCosting
Homogeneous units pass through a series of similar processes.Each unit in each process receives a similar dose of manufacturing costs.Manufacturing costs are accumulated by a process for a given period of time.
![Page 16: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/16.jpg)
16
Characteristics of Process Costing
Characteristics of Process Characteristics of Process CostingCosting
There is a work-in-process account for each process.Manufacturing cost flows and the associated journal entries are generally similar to job-order costing.The departmental production report is the key document for tracking manufacturing activity and costs.Unit costs are computed by dividing the departmental costs of the period by the output for the period.
![Page 17: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/17.jpg)
17
Equivalent Units of Production
Equivalent units are partially completeand are part of work in process inventory. Partially completed
products are expressed in terms of a smaller number of fully completed
units.
![Page 18: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/18.jpg)
18
Equivalent Units of Production
Two half completed products are equivalent to one completed product.
+ = 1
So, 10,000 units 70 percent completeare equivalent to 7,000 complete units.So, 10,000 units 70 percent complete
are equivalent to 7,000 complete units.
![Page 19: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/19.jpg)
19
Cost of Production ReportCost of Production ReportCost of Production Report
Unit InformationUnit InformationUnits to be accounted for:
Units in beginning work in process 0Units started and completed 24,000Units to be accounted for 24,000
Physical Flow Equivalent UnitsUnits accounted for:
Units 20,000 20,000 20,000Units in ending work in process
(25% complete) 4,000 1,000Units accounted for 24,000
Work completed 21,000
1.Analysis of the flow of physical units
2.Calculation of equivalent units
3.Computation of unit cost4.Valuation of inventories
(goods transferred out and ending work in process)
5.Cost reconciliation
![Page 20: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/20.jpg)
20
Cost of Production ReportCost of Production ReportCost of Production Report
Unit InformationUnit InformationUnits to account for:
Units in beginning work in process 0Units started 24,000Total units to account for 24,000
Physical Flow Equivalent UnitsUnits accounted for:Units completed 20,000 20,000Units in ending work in process
(25% complete) 4,000 1,000Units accounted for 24,000
Work completed 21,000
ContinuedContinuedContinued
![Page 21: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/21.jpg)
21
Cost of Production ReportCost of Production ReportCost of Production Report
Cost InformationCost InformationCosts to account for:
Beginning work in process $ 0Incurred during the period 168,000Total costs to account for 168,000
Divided by equivalent units ÷ 21,000Cost per equivalent unit $ 8
Cost accounted for:Goods transferred out ($8 x 20,000) $160,000Ending work in process ($8 x 1,000) 8,000Total costs accounted for $168,000
![Page 22: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/22.jpg)
22
Quick Check
For the current period, Jones started 15,000 units and completed 10,000 units, leaving 5,000 units in process 30 percent complete. How many equivalent units of production did Jones have for the period?
a. 10,000b. 11,500c. 13,500d. 15,000
For the current period, Jones started 15,000 units and completed 10,000 units, leaving 5,000 units in process 30 percent complete. How many equivalent units of production did Jones have for the period?
a. 10,000b. 11,500c. 13,500d. 15,000
![Page 23: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/23.jpg)
23
Quick Check
For the current period, Jones started 15,000 units and completed 10,000 units, leaving 5,000 units in process 30 percent complete. How many equivalent units of production did Jones have for the period?
a. 10,000b. 11,500c. 13,500d. 15,000
For the current period, Jones started 15,000 units and completed 10,000 units, leaving 5,000 units in process 30 percent complete. How many equivalent units of production did Jones have for the period?
a. 10,000b. 11,500c. 13,500d. 15,000
10,000 units + (5,000 units × 0.30) = 11,500 equivalent units
![Page 24: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/24.jpg)
24
Calculating and Using Equivalent Units of Production
To calculate the cost perequivalent unit for the period:
Cost perequivalent
unit
Costs for the periodEquivalent units of production
for the period
=
![Page 25: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/25.jpg)
25
Quick Check
Now assume that Jones incurred $27,600 in production costs for the 11,500 equivalent units of production. What was Jones’ cost per equivalent unit for the period?a. $1.84b. $2.40c. $2.76d. $2.90
Now assume that Jones incurred $27,600 in production costs for the 11,500 equivalent units of production. What was Jones’ cost per equivalent unit for the period?a. $1.84b. $2.40c. $2.76d. $2.90
![Page 26: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/26.jpg)
26
Quick Check
Now assume that Jones incurred $27,600 in production costs for the 11,500 equivalent units of production. What was Jones’ cost per equivalent unit for the period?a. $1.84b. $2.40c. $2.76d. $2.90
Now assume that Jones incurred $27,600 in production costs for the 11,500 equivalent units of production. What was Jones’ cost per equivalent unit for the period?a. $1.84b. $2.40c. $2.76d. $2.90
$27,600 ÷ 11,500 equivalent units
= $2.40 per equivalent unit
$27,600 ÷ 11,500 equivalent units
= $2.40 per equivalent unit
![Page 27: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/27.jpg)
27
PELICULA
![Page 28: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/28.jpg)
28
Equivalent Units of Production –Weighted Average Method
The weighted average method . . .Makes no distinction between work done in prior and current period.Blends together units and costs from prior period and current period.
Let’s see how this works!
Antes de
mezcla
![Page 29: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/29.jpg)
29
Weighted Average Example
Smith Company reported the following activity in Department A for the month of June:
Percent CompletedUnits Materials Conversion
Work in process, June 1 300 40% 20%
Units started into production in June 6,000
Units completed and transferred out 5,400 of Department A during June
Work in process, June 30 900 60% 30%
![Page 30: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/30.jpg)
30
Weighted Average Example
Equivalent units are calculated as follows:
Materials ConversionUnits completed and transferred out of Department A in June 5,400 5,400
![Page 31: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/31.jpg)
31
Weighted Average Example
Equivalent units are calculated as follows:
Materials ConversionUnits completed and transferred out of Department A in June 5,400 5,400 Work in process, June 30:
900 units × 60% 540
Equivalent units of Production in Department A during June 5,940
![Page 32: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/32.jpg)
32
Weighted Average Example
Equivalent units are calculated as follows:
Materials ConversionUnits completed and transferred out of Department A in June 5,400 5,400 Work in process, June 30:
900 units × 60% 540 900 units × 30% 270 Equivalent units of Production in Department A during June 5,940 5,670
![Page 33: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/33.jpg)
33
Weighted Average Example
Materials ConversionUnits completed and transferred out of Department A in June 5,400 5,400 Work in process, June 30:
900 units × 60% 540 900 units × 30% 270 Equivalent units of Production in Department A during June 5,940 5,670
Equivalent units of production always equals:Units completed and transferred
+ Equivalent units remaining in work in process
Equivalent units of production always equals:Units completed and transferred
+ Equivalent units remaining in work in process
![Page 34: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/34.jpg)
34
BeginningWork in Process
300 Units40% Complete
EndingWork in Process
900 Units60% Complete
6,000 Units Started
Weighted Average Example
MaterialsMaterials
5,400 Units Completed
5,100 Units Startedand Completed
5,400 Units Completed540 Equivalent Units 900 × 60%
5,940 Equivalent unitsof production
![Page 35: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/35.jpg)
35
6,000 Units Started
Weighted Average Example
ConversionConversion
5,400 Units Completed
5,100 Units Startedand Completed
270 Equivalent Units 900 × 30%
5,670 Equivalent unitsof production
BeginningWork in Process
300 Units20% Complete
EndingWork in Process
900 Units30% Complete
![Page 36: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/36.jpg)
36
PELÍCULA
![Page 37: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/37.jpg)
37
Production Report
Shows the flowof units and coststhrough work in
process
Becomes thejob cost sheet
in processcosting
ProductionReport
Helps managerscontrol theirdepartments
Provides costinformation for
financialstatements
![Page 38: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/38.jpg)
38
Production Report
A computation ofcost per equivalent unit.
A computation ofcost per equivalent unit.
Section 1
Section 2
Section 3
Production ReportA quantity schedule
showing the flow of units and the computation of
equivalent units.
A quantity schedule showing the flow of units and the computation of
equivalent units.
![Page 39: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/39.jpg)
39
Production Report
A reconciliation of cost flows for the period,including:
Total cost for unitscompleted andtransferred from theprocessing department.Total cost for partiallycompleted unitsremaining in work inprocess.
A reconciliation of cost flows for the period,including:
Total cost for unitscompleted andtransferred from theprocessing department.Total cost for partiallycompleted unitsremaining in work inprocess.
Section 1
Section 2
Section 3
Production Report
![Page 40: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/40.jpg)
40
Production Report Example
Double Diamond Skis uses process costing to determine unit costs in its Shaping and Milling Department.
Double Diamond uses the weighted averagecost procedure.Using the following information for the month of May, let’s prepare a production report for Shaping and Milling.
Double Diamond Skis uses process costing to determine unit costs in its Shaping and Milling Department.
Double Diamond uses the weighted averagecost procedure.Using the following information for the month of May, let’s prepare a production report for Shaping and Milling.
Formado y molido
![Page 41: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/41.jpg)
41
Production Report Example
Work in process, May 1: 200 unitsMaterials: 55% complete. $ 9,600Conversion: 30% complete. 5,575
Production started during May: 5,000 unitsProduction completed during May: 4,800 units
Costs added to production in MayMaterials cost $ 368,600Conversion cost 350,900
Work in process, May 31: 400 unitsMaterials 40% complete.Conversion 25% complete.
Work in process, May 1: 200 unitsMaterials: 55% complete. $ 9,600Conversion: 30% complete. 5,575
Production started during May: 5,000 unitsProduction completed during May: 4,800 units
Costs added to production in MayMaterials cost $ 368,600Conversion cost 350,900
Work in process, May 31: 400 unitsMaterials 40% complete.Conversion 25% complete.
![Page 42: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/42.jpg)
42
Section 1: Quantity Schedule with Equivalent Units
Production Report Example
Units to be accounted for: Work in process, May 1 200 Started into production 5,000 Total units 5,200
Equivalent unitsMaterials Conversion
Units accounted for as follows: Completed and transferred 4,800 4,800 4,800 Work in process, May 31 400
![Page 43: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/43.jpg)
43
Production Report Example
Units to be accounted for: Work in process, May 1 200 Started into production 5,000 Total units 5,200
Equivalent unitsMaterials Conversion
Units accounted for as follows: Completed and transferred 4,800 4,800 4,800 Work in process, May 31 400 Materials 40% complete 160
5,200 4,960
Section 1: Quantity Schedule with Equivalent Units
![Page 44: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/44.jpg)
44
Production Report Example
Units to be accounted for: Work in process, May 1 200 Started into production 5,000 Total units 5,200
Equivalent unitsMaterials Conversion
Units accounted for as follows: Completed and transferred 4,800 4,800 4,800 Work in process, May 31 400 Materials 40% complete 160 Conversion 25% complete 100
5,200 4,960 4,900
Section 1: Quantity Schedule with Equivalent Units
![Page 45: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/45.jpg)
45
Section 2: Compute cost per equivalent unit
Production Report Example
TotalCost Materials Conversion
Cost to be accounted for: Work in process, May 1 15,175$ 9,600$ 5,575$ Costs added in the Shipping and Milling Department 719,500 368,600 350,900 Total cost 734,675$ 378,200$ 356,475$
Equivalent units 4,960 4,900 Cost per equivalent unit
![Page 46: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/46.jpg)
46
Production Report Example
Section 2: Compute cost per equivalent unit
TotalCost Materials Conversion
Cost to be accounted for: Work in process, May 1 15,175$ 9,600$ 5,575$ Costs added in the Shipping and Milling Department 719,500 368,600 350,900 Total cost 734,675$ 378,200$ 356,475$
Equivalent units 4,960 4,900 Cost per equivalent unit 76.25$
$378,200 ÷ 4,960 units = $76.25
![Page 47: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/47.jpg)
47
Production Report Example
Section 2: Compute cost per equivalent unit
TotalCost Materials Conversion
Cost to be accounted for: Work in process, May 1 15,175$ 9,600$ 5,575$ Costs added in the Shipping and Milling Department 719,500 368,600 350,900 Total cost 734,675$ 378,200$ 356,475$
Equivalent units 4,960 4,900 Cost per equivalent unit 76.25$ 72.75$ Total cost per equivalent unit = $76.25 + $72.75 = $149.00
$356,475 ÷ 4,900 units = $72.75
![Page 48: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/48.jpg)
48
Section 3: Cost Reconciliation
Production Report Example
Total Equivalent UnitsCost Materials Conversion
Cost accounted for as follows: Transferred out during May 4,800 4,800 Work in process, May 31: Materials 160 Conversion 100 Total work in process, May 31Total cost accounted for
![Page 49: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/49.jpg)
49
Production Report Example
Section 3: Cost Reconciliation
Total Equivalent UnitsCost Materials Conversion
Cost accounted for as follows: Transferred out during May 715,200$ 4,800 4,800 Work in process, May 31: Materials 160 Conversion 100 Total work in process, May 31Total cost accounted for
4,800 units @ $149.00
![Page 50: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/50.jpg)
50
Production Report Example
Section 3: Cost Reconciliation
Total Equivalent UnitsCost Materials Conversion
Cost accounted for as follows: Transferred out during May 715,200$ 4,800 4,800 Work in process, May 31: Materials 12,200 160 Conversion 7,275 100 Total work in process, May 31 19,475 Total cost accounted for 734,675$
160 units X $76.25
All costs accounted for
100 units X $72.75
![Page 51: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/51.jpg)
51
Operation Costing
Operation costing employs some aspectsof both job-order and process costing.
Conversion costsassigned to batches
as in process costing.
Conversion costsassigned to batches
as in process costing.
Material Costs Chargedto batches as in
job-order costing.
Material Costs Chargedto batches as in
job-order costing.
Job-orderCosting
Operation Costing(Products produced in batches)
ProcessCosting
![Page 52: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/52.jpg)
52
PELÍCULA
![Page 53: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/53.jpg)
53
Review exercise
![Page 54: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/54.jpg)
54
1.
Calcular las unidades equivalentes para el período actual utilizando el método depromedios ponderados.
![Page 55: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/55.jpg)
55
![Page 56: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/56.jpg)
56
2. Calculate equivalent units andunderstand how to use them.
![Page 57: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/57.jpg)
57
Five Steps in Process Costing
Step 1: Summarize the flow of physical units ofoutput.
Step 2: Compute output in terms of equivalent units. Step 3: Compute equivalent unit costs.Step 4: Summarize total costs to account for.Step 5: Assign total costs to units completed and to
units in ending work in process inventory.
![Page 58: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/58.jpg)
58
Physical Units (Step 1)
Physical unitsFlow of ProductionWork in process, beginning 0Started during current period 35,000To account for 35,000Completed and transferred out
during current period 30,000Work in process, ending (100%/20%) 5,000Accounted for 35,000
![Page 59: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/59.jpg)
59
Compute Equivalent Units(Step 2)
Equivalent unitsDirect Conversion
Flow of Production Materials CostsCompleted and
transferred out 30,000 30,000Work in process,
ending 5,000 (100%) 1,000 (20%)Current period work 35,000 31,000
![Page 60: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/60.jpg)
60
Compute Equivalent Unit Costs(Step 3)
Direct ConversionMaterials Costs$84,050 $62,000
Equivalent units 35,000 31,000Cost per equivalent unit $2.4014 $2.00
Total production costs are $146,050.
![Page 61: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/61.jpg)
61
Summarize and Assign TotalCosts (Steps 4 and 5)
Step 4: Total costs to account for: $146,050Step 5: Assign total costs:Completed and transferred out
30,000 × $4.4014 $132,043Work in process, ending (5,000 units)Direct materials 5,000 × $2.4014 12,007Conversion costs 1,000 × $2.00 2,000Total $146,050
![Page 62: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/62.jpg)
62
PELÍCULA
![Page 63: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/63.jpg)
63
5. Lexguard Home Paiting
![Page 64: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/64.jpg)
64
![Page 65: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/65.jpg)
65
![Page 66: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/66.jpg)
66
![Page 67: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/67.jpg)
67
![Page 68: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/68.jpg)
68
![Page 69: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/69.jpg)
69
FIFO Costing MethodFIFO Costing Method
Under the FIFO costing method, the equivalent units and manufacturing costs in beginning work in process are excluded from the current-period unit cost calculation. Thus, FIFO recognizes that the work and costs carried over from the prior period legitimately belong to that period.
![Page 70: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/70.jpg)
70
FIFO Costing MethodFIFO Costing Method
Estrella Company Mixing Department Production and Cost Data for October
Production:Units in process, October 1, 70% complete 10,000Units completed and transferred out 60,000Units in process, October 31, 40% complete 20,000
Costs:Work in process, October 1:
Direct materials $1,000Conversion costs 350Total work in process $1,350
ContinuedContinued
![Page 71: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/71.jpg)
71
Estrella Company Mixing Department Production and Cost Data for October
Costs:Current costs:
Direct materials $12,600Conversion costs 3,050Total current costs $15,650
![Page 72: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/72.jpg)
72
FIFO Costing MethodFIFO Costing Method
Step 1: Physical Flow Analysis
Units accounted for:Units completed and transferred out:
Started and completed 50,000From beginning work in process 10,000 60,000
Units in ending work in process(40% complete) 20,000
Total units accounted for 80,000
Units to account for:Units, beginning work in process 10,000Units started during October 70,000Total units to account for 80,000
![Page 73: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/73.jpg)
73
FIFO Costing MethodFIFO Costing MethodStep 2: Calculation of Equivalent Units
Units started and completed 50,000 50,000Add: Units in beginning work in
process x percentage to complete:10,000 x 0% materials ---10,000 x 30% conversion 3,000
Add: Units in ending work in process x percentage complete:20,000 x 100% materials 20,00020,000 x 40% conversion 8,000
Equivalent units of output 70,000 61,000
Direct Direct MaterialsMaterials
Conversion Conversion CostsCosts
![Page 74: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/74.jpg)
74
FIFO Costing MethodFIFO Costing Method
Step 3: Computation of Unit Cost
Unit direct materials costs = $12,600/70,000 = $0.18
Unit conversion costs = $3,500/61,000 = $0.05
Unit cost = Unit materials cost +Unit conversion costs
= $0.18 + $0.05
= $0.23 per ounce
![Page 75: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/75.jpg)
75
FIFO Costing MethodFIFO Costing MethodStep 4: Valuation of InventoriesCost of ending work in process:
Direct materials ($0.18 x 20,000) $ 3,600Conversion costs ($0.05 x 8,000) 400
Total $ 4,000
Units started and completed ($0.23 x 50,000) $11,500Units, beginning work in process:
Prior period costs $1,350Cost to finish ($0.05 x 3,000) 150 1,500
Total $13,000
![Page 76: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/76.jpg)
76
FIFO Costing MethodFIFO Costing MethodStep 5: Cost ReconciliationCosts to account for:
Beginning work in process $1,350Incurred during the period:
Direct materials $12,600Conversion costs 3,050 15,650
Total costs to account for $17,000Costs accounted for
Goods transferred out:Units, beginning work in process $ 1,500Units started and completed 11,500
Goods in ending work in process 4,000Total costs accounted for $17,000
![Page 77: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/77.jpg)
77
Estrella CompanyEstrella CompanyMixing DepartmentMixing Department
Production Report for OctoberProduction Report for October(FIFO Method)(FIFO Method)
Unit InformationUnits to account for: Units accounted for:Units, beginning work Units completed 60,000in process 10,000
Units started 70,000 Units, EWIP 20,000Total units to account for 80,000 Total units accounted for 80,000
Equivalent UnitsDirect
MaterialsConversion
CostsUnits started and completed 50,000 50,000Units, beginning work in process --- 3,000Units, ending work in process 20,000 8,000Equivalent units of output 70,000 61,000
ContinuedContinuedContinued
![Page 78: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/78.jpg)
78
Costs to account for:Direct Conversion
Materials Costs TotalBeginning work in process $ 1,000 $ 350 $ 1,350Incurred during the period 12,600 3,050 15,650Total costs to account for $13,600 $ 3,400 $17,000
Cost InformationCost Information
Costs per equivalent unit:Current costs $12,600 $ 3,050Divided by equivalent units ÷70,000 ÷61,000Cost per equivalent unit $ 0.18 $ 0.05 $ 0.23
ContinuedContinuedContinued
![Page 79: Systems Design: Process Costing - · PDF filezUnit cost computed by job. Job order costing ... during the period. zCosts are accumulated by individual jobs. zJob cost sheet ... An](https://reader031.fdocuments.net/reader031/viewer/2022013014/5aa6b6c77f8b9a517d8ed647/html5/thumbnails/79.jpg)
79
Costs accounted for:Units transferred out:
Units, beginning work in process:From prior period $ 1.350From current period ($0.05 x 3,000) 150
Units started and completed ($0.23 x 50,000) 11,500 $13,000Ending work in process:
Direct materials (20,000 x $0.18) $ 3,600Conversion costs (8,000 x $0.05) 400 4,000
Total costs accounted for $17,000