swissMon – An approach to 4D Monitoring of Tunnels in ... swissmon 4D... · swissMon – An...
Transcript of swissMon – An approach to 4D Monitoring of Tunnels in ... swissmon 4D... · swissMon – An...
swissMon – An approach to 4D Monitoring of Tunnels in Urban Environments
Christian Meyer, Stephan Schütz
terra monitoring ltd., Zurich (Switzerland)
1 Introduction
Swiss Railways (SBB) have been constructing the Cross-City-Link in Zurich since 2007.
The heart of this project is the new underground station being constructed 16m below
the existing tracks and the river Sihl. From 2014, trains will be able to approach and
leave through the new 11.2m diameter twin track, mainly TBM-drilled, Weinberg tunnel.
It passes under the existing station, the River Limmat and parts of downtown Zurich and
continues for five kilometres to Oerlikon. Tunnelling projects within urban areas, such as
this, need special supervisory measures to meet safety requirements. A broad
monitoring project, using state of the art sensors and digital data communication, has
been deployed to identify potential hazards and mitigate their impact.
This paper introduces swissMon, the web based monitoring platform deployed
throughout the project to automatically gather, analyse and display over 390’000
datasets generated by geotechnical and geodetical sensors every day. By way of
example, 3D-Surface Monitoring using Total Stations and tShape Inplace Deformation
Monitoring (two of the core sensor technologies used with swissMon) are presented.
SwissMon has now been in use for 4 consecutive years at Zurich Central Station,
handling large data traffic 24 hours a day, 7 days a week, under tough construction site
conditions and with an exceptional success.
2 The Project
Swiss Railway Company (SBB) have commissioned a 2 billion Euro infrastructure
project, the Cross-City-Link, Zurich. Starting at Altstetten, the 9.6 km railway link will
pass below ground through Zurich Central Station and will continue as far as Oerlikon.
Zurich Central Station is at the core of the Swiss railway network, where commuter flow
is constantly increasing. Up to 300’000 passengers travel through Zurich Central Station
each day. SBB estimate that, the number of daily passengers can be expected to
increase to 500’000 by 2020. These passenger numbers cannot be handled using
standard supporting measures, such as optimising train flow rates, as they will exceed
the station’s capacity limits. Based on this knowledge, a decision was taken to
significantly extend the existing infrastructure.
Figure 1: Overview Cross-city link Zurich [1]
The heart of the Cross-City-Link is the second underground through-station,
Löwenstrasse. To the West, tracks pass across two new bridges (“Letzigrabenbrücke”
and “Kohledreieckbrücke”) to reach Zürich Altstetten. To the East, the “Weinbergtunnel”
connects Zurich’s Central Station with Oerlikon. The two new bridges between the
Central station and Altstetten will help to reduce congestion on the tracks to the West of
the station. The “Weinbergtunnel” will significantly increase the station’s capacity
towards the East. From 2014, trains using the new “Durchgangsbahnhof Löwenstrasse”
will be able to pass directly through the Central Station without having to change
direction.
The new “Löwenstrasse” through-station is being built 16 metres below the Central
Station’s tracks (platforms 4 to 9) and directly under the Sihl riverbed. As the existing
station is already operating close to its full capacity, SBB could not allow the
construction works to affect the existing train flow rates. Due to this, one of the most
important project prerequisites was that the construction method of the new station
should minimise its impact on the existing traffic. Therefore, it was necessary to choose
a top-down construction method for the buried structure.
Figure 2: Cross Section and Longitudinal Section showing “Löwenstrasse” Station [1]
Heading east, trains will leave the through-station on two tracks, entering the
“Weinbergtunnel”. The first part of the tunnel passes under the 150 year old landmark
Central Station building. Due to the complexity of the construction, this part of the tunnel
had to be drilled using a manually driven boring machine for approximately 220m. The
remainder of the 5km tunnel was drilled using a Herrenknecht convertible S-451
Mixshield (an 11.2m diameter TBM). Starting at Oerlikon, the TBM ran through Molasse
rock in an open mode for the first 4.1Km. During the final 245m the machine faced
unconsolidated soft rock and had to be converted to closed mode in order to pass under
the Limmat River. On the 22nd November 2010 the successful breakthrough of the TBM
into the target shaft was celebrated, completing the first important part of the new rail
link, which will be opened in 2014.
3 swissMon – Web-based Realtime Monitoring Platform
Tunnelling projects within urban areas have a special requirement for supervisory
measures. As they are constructed near to existing critical infrastructure, including
residential and commercial sites, any kind of incident can have a profound impact on
building structures, human safety and commercial logistics, such as traffic flows.
Furthermore, engineers can face unforeseeable problems and delays due to
archaeological sites and historic infrastructure, which might have been installed without
documentation.
In order to identify potential hazards at a very early stage and mitigate their impact, a
broad monitoring project using state of the art sensors and digital data communication
has been installed for the Cross-City-Link scheme. It is one of the world’s largest
monitoring projects, requiring a large variety of geodetic and geotechnical sensors.
These include:
Automatic Measurements Manual Measurements
- 80 Total Stations covering more than 3000 3D-Targets
- 850 Hydrostatic Settlement Cells - 50 Inclination Sensors - 30 Inplace-Inclinometers - 5 Systems for Water Quality Control - Piezometers - Achor Force Cells - Straingauges - Meteorological Station etc.
- Manual levelling covering more than 1000 targets
- Inclinometer measurements - Manual inclination measurements - Sliding Deformeter measurements - Rod Extensometer measurements - Chemical measurements etc.
The automatic measurements have to be carried out every 30 to 60 minutes
continuously throughout the project.
Additionally, the customer requested online access to the real-time measurement
results. Based on these demands and considering estimated data rates of up to 500’000
datasets per day, a decision was taken to develop swissMon, a cutting edge monitoring
platform. The structure of swissMon is completely modular and can therefore be scaled
to every kind of project and project size. It provides interfaces for all important
geodetical and geotechnical sensors. Due to its modern architecture, new sensors and
features can easily be integrated so long as a digital interface is available. For analog
sensors, a/d-conversion has to be performed by external hardware.
Figure 3: Modular Architecture of swissMon
The SwissMon Monitoring-System is divided into three basic units:
Sensor Unit (tMon):
All on-site sensors which perform automatic measurements are connected to a Node-
Computer. The Nodes are strategically placed near the sensors in order to reach as
many of them as possible. The Nodes take control of the sensors, automatically taking
the measurements within defined time periods and analysing the field data. The
validated datasets are temporarily stored on the tMon-Node and are regularly
transmitted to the database Unit via internet or internal network connection. Internet
connection can either be by telephone earth line or in special cases through a mobile
telephone network with a high bandwith. tMon already provides basic alarming features
by performing simple trigger tests. This makes it possible to provide near real-time
alarming on the site using sirens or flashlights.
Database Unit (tLis):
This unit stores all datasets measured within the project. Datasets can also be updated
with additional information and manually measured datasets. This unit is able to perform
complex triggering tests, which can be individually adapted to project requirements. In
the event that a trigger level is breached, tLis can automatically issue alarms to single
persons or groups of persons through email messages, SMS, facsimiles, pager calls or
voice calls. It can also confirm whether an alarm messages reached the required
recipients. The database unit runs on a server, which is located outside the project
vicinity. It is continuously backed up to ensure all data is secure. It also features a
watchdog functionality to automatically check if all attached tMon-Nodes are still
working.
Web Unit (tWeb):
All data is presented to an online user in a numerical or graphical format. All
stakeholders can access the data at any time by using their preferred Web Browser. By
using their personal login they have access to all necessary information to make
important decisions. tWeb features the following functionality:
Visualisation of data as timeplots, profiles, cross sections, surface plots etc.
Visualisation of trigger breaches.
Storage and access to Team Documents.
Direct access to Webcams on site.
Quicksearch of single measuring points
Selecting of targets by sections, subsections or trigger-status.
PDF- oder CSV-download of all data available
Data protection through secure personalised logins
Site engineers and site management staff are not able to address the entire vast
amount of data arriving from the comprehensive monitoring sensors each day (in
Zurich: 390’000 datasets). Allowing the ability to focus on the critical tasks in order to
make decisions at the right time, requires tWeb to provide information in a suitable and
comprehensive way to the pertinent staff.
Figure 4: tWeb Screenshot showing tShape Sensor Positions and Results
Measurement results can be visualised in tWeb in a number of ways:
Figure 5: Borehole Deformation (Inclinometer Measurements)
Figure 6: Real-Time easy to recognize Trigger Breaches
In Addition to the measured data, tWeb can also present secondary information, such
as the TBM advance, in order to facilitate data interpretation.
4 Sensors used with swissMon
The logistics required to operate a monitoring platform for a project of the size of the
Cross-City-Link, such as data communication and data processing need to be
addressed when designing the site specific system. Furthermore, the construction
methods can also provide challenges for the measuring technologies used.
Details about two of the instruments, selected from the many geodetic and
geotechnical instruments used in swissMon at the Cross-City-Link, are provided in
section 4.1 and 4.2.
4.1 Total Stations
This sensor is one of the most advanced instruments available for monitoring tasks. In
summer 2011, total stations were operating in more than 80 locations in Zurich Central
Station, monitoring 2800 Targets.
Significant planning had to be carried out to select the type and number of instruments
to use. The final solution was based on the project requirements, using the following
criteria:
Accuracy: 1 mm at 100 m for all 3 Dimensions.
Speed: 100 targets per 30 minutes in 2 faces considering an urban environment
Data transfer: Easy to use wireless data communication.
Option: Reflector-less distance measurements should be possible.
Operation: Term of Guarantee; Short term reaction for service and spare parts.
Although the operating conditions vary significantly throughout the project, taking into
account efficiency of labour and flexibility, the decision was taken to use a homogenous
fleet of instruments.
Figure 7: Benchmark Test with Total Stations in summer 2007
After a pre selection benchmark test was performed at the construction site in summer
2007 using total stations of 2 manufacturers. As a result of this test, Trimble’s S8 robotic
total station was adopted for the monitoring solution as the instrument has proven to
perform measurements at a higher speed and is more convenient for monitoring issues
than alternative options. Due to its MagDrive Servotechnology (low wear dive with a
rotational speed up to 128gon/sek) the Trimble S8 needs only 6 seconds to measure
one target. It also comes equipped with the Finelock-functionality. This enables the S8
to precisely target prisms located in a building line even over high distances, where
distance in the measuring plane is less than 20mrad. During tests the S8 was able to
automatically track prisms with a minimum distance of 25cm between each other,
located at a distance of 100m from the total station.
Figure 8: Total Stations at Zurich Cross-City-Link
To allow completely automated measurements with total stations, a special emphasis
was given to these instruments during the development of swissMon. Therefore,
SwissMon is able to control these instruments, perform least squares adjustment
(Gauss-Helmert Model) and plausibility checks, apply filters, estimate adaptive
parameters or even dynamically update reference point coordinates. It delivers
coordinates and deduced data.
4.2 tShape – In-Place Deformation Monitoring
Despite the power of total stations the Cross-City-Link project provided challenges
where other innovative measurement systems had to be introduced.
Only 245m before reaching the target shaft, the TBM drilling the Weinbergtunnel leaves
the molasse rock and proceeds into unconsolidated soft rock with only a few meters
overburden. Urban tunnelling has the special challenge requiring that ground
subsidence must be avoided. Therefore special equipment, such as Mixed Shield
TBM’s, are used to maintain the soil pressure during and after the tunnel construction. If
operated properly and the underground conditions are well known, it is possible to these
to reduce the risk of surface subsidence and voids.
During the advance of the machine, all important parameters have to be carefully
monitored. One of these parameters is the deformation (convergence) of the drilled
tunnel. As the main part of these deformations occur very shortly after face advance, it
is necessary to start measuring as early as possible.
A state of the art method to determine convergences are geodetic deformation
measurements using high precision total stations. As this method requires a free line of
sight inside the tunnel, it can hardly be used with TBM’s as they fill substantial parts of
the tunnel cross section.
At the Weinbergtunnel the TBM, together with the trailing support decks had a total
length of about 150m. Therefore, it was not possible to measure convergences during
the crucial phases using geodetical methods. As classic methods were unrealisable on
their own, tShape was introduced as an innovative measurement system for in-place
deformation monitoring.
Relying on the modularity of swissMon, tShape uses Measurand’s SAA-technology to
obtain its data. The SAA is a rope-like array of MEMS-based accelerometer sensors
and microprocessors, which fit into a small 30mm diameter casing.
Figure 9: Limited line of sight inside a Tunnel during TBM advance
Mechanically, SAA is an array of rigid segments connected by joints that permit bending
in any direction, but are stiff in torsion. Standard segment length is 305 mm, which
dictates spatial resolution. The hollow segments each contain three orthogonal MEMS
accelerometers. Every eighth segment includes a microprocessor.
Any deformation that moves the casing is accurately measured as a change in shape of
the array. The array was installed on the inner lining covering the upper 120° of the
tunnel full section.
Figure 10: tShape installation behind TBM head (left) / Staff checking installation (right)
Unlike conventional convergence measurements, it is not possible to use fixed point
control when using tShape. This is because all the measurement points within the
tShape “chain” lie within the area of deformation. This fact needs to be taken into
account when processing the data. In addition, the processing of the data needs to
include the following requirements:
Selection of the points to display in the convergence measurement output
Transformation to global (national) coordinates
User choice of transformation control points
tShape measurements are generally recorded in three dimensions. Conventional
convergence measurements are usually only recorded in two dimensions. Therefore,
one of the dimensions can be fixed when using tShape.
The fixed dimension needs to be in the plane of the tunnel cross section. The shifts or
deformations of the individual points can be determined using a 2D-Helmert
transformation.
The following formula is used:
Where:
Translation in x and y direction
Scale factor
Rotation
The transformation is carried out relative to the centre of each of the measured points.
The scale factor and rotation parameters can be calculated separately or combined
during the adjustment. A translation is calculated in each case.
The required number of transformations will vary depending upon the number of
transformation parameters. The maximum number of points is defined by the number of
available measurement points in the tShape chain.
Figure 11: Example of a plot of the transformation residuals
Weighting can be applied to the adjustment in order to modify the quality of the result.
This makes it possible to assign less influence to less reliable points in the calculation.
SwissMon determines the transformation vectors based upon the formulas given
previously. Subsequently, all the points in the measurement chain are transformed and
integrated into the national coordinate system, according to the transformation
parameters. The output data is supplied in the same format as the input data. The
residuals of the transformations are plotted in order to provide data control (see Figure
11). In addition, a log file is created, which also allows interpretation of the translation
outputs.
The system was set up as described to measure convergences during TBM advance.
The data corresponded to the predicted output. The system delivered reliable results
(see Figure 12). Any anomalies were detected and corrected with the help of the
generated log file.
Figure 12: Convergence measurement diagram from tShape data, shown in tWeb
Figure 13: Time Series showing convergences on one point during TBM advance
Even under difficult situations, tShape has shown to be a reliable system for automatic
in-place deformation measurements inside tunnels.
Figure 14: tShape installation in the Weinbergtunnel
References:
[1] Schweizerische Bundesbahnen SBB; Informationsbroschüre und Faktenblätter zu
den Abschnitten der Durchmesserlinie (www.durchmesserlinie.ch)
[2] S. Eisenegger; Alarmzeichen automatisch erkennen, BY RAIL.NOW! 2009,
Sonderpublikation der SWISS Engineering-Reihe.
[3] L. Danish; Measurand ShapeAccelArray (SAA), General description.
Authors
Dipl.-Geol. Christian Meyer
Dipl.-Ing Stephan Schütz
terra monitoring ag
Obstgartenstrasse 7, CH-8006 Zurich
www.terra-monitoring.ch
www.terra.ch