Surface Water Drainage Strategy (SWDS) 5601
Transcript of Surface Water Drainage Strategy (SWDS) 5601
Surface Water Drainage Strategy (SWDS) 5601
55 Mountain Echo Avenue
London
E4 7JX
Reference: 5601_SWDS Final v1.0
2
Document Issue Record
Please Note:
This report has been prepared for the exclusive use of the commissioning party and may not be reproduced without prior written
permission from AMBIENTAL Environmental Assessment. All work has been carried out within the terms of the brief using all
reasonable skill, care and diligence. No liability is accepted by AMBIENTAL for the accuracy of data or opinions provided by others
in the preparation of this report, or for any use of this report other than for the purpose for which it was produced.
Contact Us: Ambiental Environmental Assessment
Science Park Square
Brighton, BN1 9SB
www.ambiental.co.uk
UK Office: +44 (0) 20 3857 8530 or +44 (0) 20 3857 8540
Project: Surface Water Drainage Strategy (SWDS)
Prepared for: Heritage Estate Group LTD
Reference: 5601 SWDS
Site Location: 55 Mountain Echo Avenue, London, E4 7JX
Proposed
Development:
The development is for the construction of a block of flats to replace an existing
dwelling.
Consultant Date Signature
Author Tom Vine 29/07/20
Document Check Lydia Sayers 19/08/2020
Authorisation Mark Naumann 20/08/2020
Reference: 5601_SWDS Final v1.0
3
Contents
Document Issue Record ............................................................................................................................. 2
Please Note: ........................................................................................................................................... 2
Contact Us:............................................................................................................................................. 2
Contents ..................................................................................................................................................... 3
1. Introduction ....................................................................................................................................... 4
Existing Drainage Infrastructure and Nearby Watercourses ................................................................ 4
Geology and Infiltration Potential ......................................................................................................... 5
Flood Zone and Vulnerability ................................................................................................................. 5
2. SUDS Assessment .............................................................................................................................. 6
Rainwater Harvesting ............................................................................................................................ 8
Geocellular System ................................................................................................................................ 8
Permeable Paving .................................................................................................................................. 8
3. Surface Water Drainage Strategy ...................................................................................................... 9
Runoff rates ........................................................................................................................................... 9
Climate Change .................................................................................................................................... 10
Long Term Storage ............................................................................................................................... 10
Urban Creep ......................................................................................................................................... 10
Attenuation Storage ............................................................................................................................ 10
4. Design Exceedance .......................................................................................................................... 10
5. Water Quality .................................................................................................................................. 11
6. Adoption and Maintenance ............................................................................................................. 11
7. Conclusion ....................................................................................................................................... 13
Appendix 1 – Supporting Information ..................................................................................................... 15
Appendix 2 – Preliminary Surface Water Drainage Strategy Layout ...................................................... 16
Appendix 3 – Calculations ........................................................................................................................ 17
Appendix 4 – CCTV report ....................................................................................................................... 18
Reference: 5601_SWDS Final v1.0
4
1. Introduction
Ambiental Environmental Assessment has been appointed by Heritage Estate Group LTD c/o Neil
Squires to undertake a Surface Water Drainage Strategy for the proposed development at 55
Mountain Echo Avenue, London, E4 7JX.
The existing site compromises of a residential building and a garage toward the south of the site.
The redline application boundary area is approximately 1110m2 (0.111ha). The existing
hardstanding area associated with the respective buildings and adjacent paths/driveway totals
approximately 160m2.
Figure 1: Site Location
The development is for the construction of a block of flats to replace an existing dwelling and
garage.
Following development, the total hardstanding area of the site would increase to approximately
640m2 (0.074ha).
The purpose of this assessment is to demonstrate that the development proposal outlined above
can be satisfactorily accommodated without worsening flood risk for the area and without placing
the development itself at risk of flooding, as per National guidance provided within the National
Planning Policy Framework (NPPF) 2018 the National Planning Practice Guidance (NPPG), DEFRA’s
National Standards for Sustainable Drainage and London Borough of Waltham Forest local policy
relating to Sustainable Urban Drainage Systems (SUDS).
Existing Drainage Infrastructure and Nearby Watercourses
The nearest watercourse to the site is the William Grilling Reservoir and is located at approximately 600m to the west.
Site
Reference: 5601_SWDS Final v1.0
5
The Thames Water sewer asset plan for the wider site area indicates that the site drains into a public foul sewer located on Mount Echo Avenue. See map in Appendix 1.
There are surface water sewers on Mountain Echo Drive and Mountain Echo Avenue, it is assumed there is an existing connection to the surface water sewer. There are no invert/depths indicated for the storm sewer in Mount Echo Avenue so levels of this drain may need confirmation prior to detailed design. See map in Appendix 1.
A CCTV survey has been undertaken by the client (see appendix 4) but the surveyors were unable to locate access to the storm drainage system.
Geology and Infiltration Potential
The British Geological Survey (BGS) Geology of Britain Viewer indicates that the bedrock underlying
the site is London Clay Formation - Clay, Silt And Sand. The superficial soil deposits in the wider area have not been recorded on the BGS viewer.
Based on the BGS geology information infiltration is not considered to be feasible.
Flood Zone and Vulnerability
The EA’s Flood Map for Planning (Figure 2) demonstrates that the site would be located in Flood Zone 1 (Low Risk). According to the NPPF vulnerability guidance, the proposed residential development would be classified as ‘More Vulnerable’ and is not required to implement the Exception Test.
Figure 2: EA Flood Map for Planning
A review of the EA flood risk from surface water map (Figure 3) has demonstrated that the site is entirely located at ‘Low’ risk of surface water flooding.
Reference: 5601_SWDS Final v1.0
6
Figure 3: EA Flood risk from surface water
2. SUDS Assessment
In accordance with the SuDS management train approach, the use of various SuDS measures to reduce and control surface water flows have been considered in detail for the development.
Paragraph 80 of the Planning Practice Guidance of the National Planning Policy Framework (NPPF) states that: Generally, the aim should be to discharge surface run off as high up the following hierarchy of drainage options as reasonably practicable, see Table 2.
The management of surface water has been considered in respect to the SuDS hierarchy (below)
(as detailed in Building Regulations Part H and within the the CIRIA 753 ‘The SUDS Manual’, Section
3.2.3):
To achieve the reduction in site run off rates, the use of various SuDS have been considered for the
development as follows:
SuDS Drainage Hierarchy
Suitability Comment
1. Infiltration x
Due to the geology at the site, infiltration is not
considered to be feasible
2. Discharge to Surface Water x No open waters are located near the site.
3.
Discharge to Surface Water
Sewer, Highway Drain or
another Drainage System
Surface water sewer/drain is located in close
proximity to the site.
4. Discharge to Combined
Sewer x ‐
5.
Discharge to a foul sewer
(should not be considered
as a possible option)
x ‐
Table 1: SuDS Hierarchy
Reference: 5601_SWDS Final v1.0
7
Suitability of SuDS Components
SuDS Component
Description Suitability
Infiltrating SuDS Infiltration can contribute to reducing runoff rates and volumes while supporting baseflow and groundwater recharge processes. The suitability and infiltration rate depends on the permeability of the surrounding soils.
x
Permeable Pavement
Pervious surfaces can be used in combination with aggregate sub‐base and/or geocellular/modular storage to attenuate and/or infiltrate runoff from surrounding surfaces and roofs. Liners can be used where ground conditions are not suitable for infiltration.
Green Roofs
Green Roofs provide areas of visual benefit, ecological value, enhanced building performance and the reduction of surface water runoff. They are generally more costly to install and maintain than conventional roofs but can provide many long‐term benefits and reduce the on‐site storage volumes.
x
Rainwater Harvesting
Rainwater Harvesting is the collection of rainwater runoff for use. It can be collected form roofs or other impermeable area, stored, treated (where required) and then used as a supply of water for domestic, commercial and industrial properties.
Swales
Swales are designed to convey, treat and attenuate surface water runoff and provide aesthetic and biodiversity benefits. They can replace conventional pipework as a means of conveying runoff, however space constraints of some sites can make it difficult incorporating them into the design.
x
Rills and Channels
Rills and Channels keep runoff on the surface and convey runoff along the surface to downstream SuDS components. They can be incorporated into the design to provide a visually appealing method of conveyance, they also provide effectiveness in pre‐treatment removal of silts.
x
Bioretention Systems
Bioretention systems can reduce runoff rates and volumes and treat pollution through the use of engineer soils and vegetation. They are particularly effective in delivering interception, but can also be an attractive landscape feature whilst providing habitat and biodiversity.
x
Retention Ponds and Wetlands
Ponds and Wetlands are features with a permanent pool of water that provide both attenuation and treatment of surface water runoff. They enhance treatment processes and have great amenity and biodiversity benefits. Often a flow control system at the outfall controls the rates of discharge for a range of water levels during storm events.
x
Detention Basins
Detention Basins are landscaped depressions that are usually dry except during and immediately following storm events, and can be used as a recreational or other amenity facility. They generally appropriate to manage high volumes of surface water from larger sites such as a neighbourhoods.
x
Geocellular Systems
Attenuation storage tanks are used to create a below‐ground void space for the temporary storage of surface water before infiltration, controlled release or use. The inherent flexibility in size and shape means they can be tailored to suit the specific characteristics and requirements of any site.
Proprietary Treatment
Systems
Proprietary treatment systems are manufactured products that remove specific pollutants from surface water runoff. They are especially useful where site constraints preclude the use of other methods and can be useful in reducing the maintenance requirements of downstream SuDS
Filter Drains and Filter Strips
Filter drains are shallow trenches filled with stone, gravel that cerate temporary subsurface storage for the attenuation, conveyance and filtration of surface water runoff. Filter strips are uniformly graded and gently sloping strips of grass or dense vegetation, designed to treat runoff from adjacent impermeable areas by promoting sedimentation, filtration and infiltration.
x
Table 2: Suitability of SuDS Components
Reference: 5601_SWDS Final v1.0
8
It has been indicated in Table 3 above, that several SuDS components are deemed appropriate to
be used in the following SuDS management train.
SuDS components should be designed to accommodate and dispose of runoff from storms up to
and including the 1:100 year +40% climate change event without flooding.
Rainwater Harvesting
Rainwater harvesting (RWH) Systems should be considered for rainwater re‐use. Rainwater
harvesting can take various forms including simple water butts to utilise runoff for watering and
irrigation, to more complex pumped RWH systems to be used in grey water uses. It is strongly
recommended that rainwater harvesting is considered, however, the viability and suitability of an
RWH system should be reviewed by a specialist to determine the suitability in context to the rest
of the site proposals. For the purposes of attenuation and storage calculations, it is considered the
harvesting devices are full at the time of the design rainfall event.
Geocellular System
Geocellular Systems are generally built by placing together (e.g. stacking) cuboid plastic structures
with very high void ratios (90‐95%). The formed volume is then surrounded by a permeable
geotextile and backfilled with the excavated soil to form the attenuation tank.
Within the proposed SuDS scheme, the Geocellular tanks are used to provide the storage volume
requirement and infiltrate runoff. They are to be located within the car parking area, however, the
exact layout is to be determined at the detailed design stage.
Permeable Paving
Permeable paving is proposed in many new external hardstanding areas (within the redline
boundary excluding bin store area to avoid the risk of contamination). The permeable paving will
primarily be designed to be self‐draining (to mimic an equivalent area of soft landscaping). The
paving could be formed by the following make up:
Permeable surfacing as required
Laying Course Material
Geotextile filter
Sub‐Base: 6‐20mm clean crushed stone (depths as required to withstand loading
requirements)
Geotextile filter or impermeable membrane depending on infiltration rates
For conservative purposes, should a site have steep topography, permeable paved areas should
only be considered for runoff interception, treatment and conveyance to downstream SuDS.
Reference: 5601_SWDS Final v1.0
9
3. Surface Water Drainage Strategy
In order to mitigate flood risk posed by the proposed development, adequate control measures are required to be considered. This will ensure that surface water runoff is dealt with at source and the flood risk on/off site is not increased over the lifetime of the development.
The drainage strategy proposed herein uses a flow control, geocellular crates and permeable pavement to manage surface water post‐development. The permeable paving would intercept, treat and convey runoff to network while also providing attenuation storage. See proposed preliminary drainage layout in Appendix 2.
Following confirmation of site levels, infiltration tests and wider construction details, the drainage
strategy proposed herein should be reassessed and amended as necessary.
Runoff rates
Greenfield and Brownfield runoff rates have been calculated using Micro Drainage Software and
applying the Institute of Hydrology Report 124 (Marshall and Bayliss, 1994), as recommended in
the CIRIA 753 ‘The SUDS Manual’ for calculating the greenfield runoff rates. See calculations in
Appendix 3.
As DEFRA Report ‘Rainfall runoff management for Developments’ recommends, the design principle is to limit the runoff for events of similar frequency of occurrence to the same peak rate of run as that which takes place from greenfield sites. However, there are two situations where the greenfield flow rate is not actually applied to define the limiting discharge rates:
a) The limit of discharges based on QBAR that are less than 1 l/s/ha for permeable sites as this is seen as being an unreasonable requirement (producing very large storage volumes). QBAR is then set to 1 l/s/ha;
b) Small sites would require impractically small controls to achieve the required flow rates where these are calculated to be less than 5 l/s. In this case a minimum flow of 1 l/s is used as a practical minimum for flow control devices without causing blockage risks.
A minimum flow control opening size of 50mm is provided in Sewers for Adoption 8. In this case a 1 l/s is used as a minimum flow corresponding to a 55mm Hydrobrake. These rates are to be agreed with the relevant planning authority.
The existing runoff rates have also been calculated and summarised in Table 3 below. It can be seen that the proposal is to limit the runoff rates, to rates that will be lower than the existing for all events up to and including 1 in 100 year +CC.
SURFACE WATER DISCHARGE RATES SUMMARY
Area (m2) Discharge Rates (l/s)
1 year QBAR 30 year 100 year
Greenfield Rates 1111 0.4 0.46 1.07 1.74
Brownfield Rates 160 2.40 ‐ 5.90 7.50
Proposed Site (+40% CC) 650 1.00 ‐ 1.00 1.00
Betterment 58% 83% 87%
Table 3: Runoff rates; 40% climate change added to the calculations for the proposed 1:100 event
Reference: 5601_SWDS Final v1.0
10
Climate Change
The design lifetime of a residential site is typically 100 years and an allowance for climate change
should be considered in accordance with published guidance within the NPPF. As such, the ‘upper
end’ allowance 40% climate change allowance has been applied to the drainage and storage
calculations (Table 4).
PEAK RAINFALL INTENSITY ALLOWANCE IN SMALL AND URBAN CATCHMENTS
Applies across all
of England
Total potential change
anticipated for the
‘2020s’ (2015 to 2039)
Total potential change
anticipated for the
‘2050s’ (2040 to 2069)
Total potential change
anticipated for the ‘2080s’
(2070 to 2115)
Upper End 10% 20% 40%
Central 5% 10% 20% Table 4: Peak rainfall intensity allowance in small and urban catchments
Long Term Storage
Long‐term storage is usually required to address the additional runoff caused by the development
compared to the volume that would be contributed from the site in its Greenfield state. The
drainage strategy proposed discharges runoff to the ground, therefore no long‐term storage is
required.
Urban Creep
Urban Creep has not been applied to this site, given that the site is shared between multiple
occupants and external areas are common areas managed and maintained by the developer.
Attenuation Storage
Attenuation storage is needed to temporarily store water during periods when the runoff rates
from the development site exceed the allowable discharge rates from the site.
Rainfall depths for the 1 in 100 years return period plus 40% of CC were produced using Micro
Drainage software to estimate the largest volume and critical storm, for typical storm durations.
The maximum allowable discharge rate into the surface water sewer is 1.00 l/s
Based on the calculations in Appendix 3 a total of 32.5 m3 of water storage is required on site. The
remaining 38m3 can be stored in 50m2, 0.8m deep, geocellular crate storage. At detailed design
some storage could be located under the permeable car park area if required. Final storage
locations and volumes can be provided at detailed design stage. Details of the location is shown in
Appendix 2.
Guidance about proper use, installation and maintenance of any proprietary system must be
provided by the supplier and incorporated into the site proposals at detailed design stage.
4. Design Exceedance
In the event of drainage system failure under extreme rainfall events or blockage, flooding may occur within the site. In the event of the development’s drainage system failure, the runoff flow will be dictated by topography on site and flow paths.
Design of external ground levels will need to be undertaken at detailed design stage.
Reference: 5601_SWDS Final v1.0
11
Finished Floor Levels should be 150mm above surrounding finished ground levels where feasible.
This is to mitigate against any potential surface water flows, with external ground levels to be
designed to direct water to the main road areas and away from buildings and thresholds where
feasible. See indicative flow routes on drawing in Appendix 2.
5. Water Quality
Adequate treatment must be delivered to the water runoff to remove pollutants through SuDS devices, which are able to provide pollution mitigation. Pollution Hazards and the SuDS Mitigation have been indexed in the CIRIA 753 ‘The SUDS Manual’.
The Pollution Hazard Indices are summarized in Table – Summary of Pollution Hazard Indices for different Land Use below (reference: Table 26.3.CIRIA SuDS Manual 2015).
POLLUTION HAZARD INDICES FOR DIFFERENT LAND USE CLASSIFICATIONS
LAND USE Pollution
Hazard Level
Total suspended Solids (TSS)
Metals Hydrocarbons
Residential Roofs Very Low 0.2 0.2 0.05
Individual property driveways, residential car parks, low traffic roads
Low 0.5 0.4 0.4
Table 5: Summary of Pollution hazard Indices for different Land Use.
The Mitigation Indices of the proposed SuDS techniques are summarized in the Table 6 ‐ Indicative SuDS Mitigation Indices below. It can be seen the water treatment provided by the Permeable Pavement (the SuDS mechanisms proposed), should be enough to remove the pollutants.
INDICATIVE SuDS MITIGATION INDICES FOR DISCHARGES TO SURFACE WATER
SuDS Component Total suspended Solids (TSS) Metals Hydrocarbons
Permeable Pavement 0.7 0.6 0.7
Geocellular Tank ‐ ‐ ‐
Table 6: Indicative SuDS Mitigation Indices
Runoff from roof areas is considered to generally be uncontaminated. However, to prevent any
potential sediment from impacting on the storage structure, Sediments Traps should be provided
on the outlet to the storage structure to prevent sedimentation, with rodding access provided
either side for cleaning and maintenance.
The contamination risk associated with the proposed development site is considered to be very
low, with sediment traps (for the roof runoff) and permeable paving deemed suitable to mitigate
against the potential contamination risk prior to discharging runoff to the ground.
6. Adoption and Maintenance
All onsite SuDS and drainage systems will be privately maintained. A long‐term maintenance regime should be agreed with the site owners before adoption. In addition to a long‐term maintenance regime, it is recommended that all drainage elements implemented on site should be inspected following the first rainfall event post construction and monthly for the first quarter following construction.
Reference: 5601_SWDS Final v1.0
12
Table 7: Proposed Schedule of Maintenance for Below Ground Drainage.
Item Visual
Inspection
Cleanse /
De‐sludge
CCTV
Survey Comments
Surface Water Drainage
System (pipework,
chambers etc.)
5 years 10 years 10 years Cleansing to be carried as
necessary
Gullies/Channels 1 year 1 year N/A Cleansing to be carried as
necessary
Catchpits 1 year As required N/A Cleansing to be carried as
necessary
Permeable Block Paving 1 year
‘Swept’ clean of
debris every 2
years.
N/A
Lift blocks and remove sand
bedding and replace and re‐bed
paving – refer to individual
manufacturers recommendations.
Flow control 1 year As required N/A Cleansing to be carried as
necessary
Geocellular Tanks 1 year As required 5 years
Remove sediment from pre‐
treatment structures (e.g.
Permeable pavement); Inspect
inside of tank for sediment build‐
up and remove as necessary
Reference: 5601_SWDS Final v1.0
13
7. Conclusion
This study has been undertaken in accordance with the principles set out in the NPPF and London
Borough of Waltham Forest local policy SuDS guidance. Providing the development adheres to the
conditions advised in this report, the said development proposals can be accommodated without
increasing flood risk within the locality in accordance with objectives set within the NPPF and
published guidance.
The existing site compromises of a residential building and a garage toward the south of the site.
The redline application boundary area is approximately 1110m2 (0.111ha). The existing
hardstanding area associated with the respective buildings and adjacent paths/driveway totals
approximately 160m2.
The development is for the construction of a block of flats to replace an existing dwelling. Following
development, the total hardstanding area of the site would increase to approximately 640m2
(0.074ha).
There are no nearby watercourses to drain into. There are surface water sewers on Mountain Echo
Drive and Mountain Echo Avenue, it is assumed there is an existing connection to the surface water
sewer. There are no invert/depths indicated for the storm sewer in Mount Echo Avenue so levels
of this drain may need confirmation prior to detailed design.
The British Geological Survey (BGS) Geology of Britain Viewer indicates that the bedrock underlying
the site is London Clay Formation - Clay, Silt And Sand. The superficial soil deposits in the wider area have not been recorded on the BGS viewer. Based on the BGS geology information, infiltration
is not considered to be feasible.
A review of the EA flood map for planning (Figure 2) has demonstrated that the site is located in Flood Zone 1 (Low Risk). The EA surface water flooding risk map indicates that the entire redline application boundary is at ‘Low’ risk of flooding.
Based on the calculations in Appendix 3 a total of 32.5 m3 of water storage is required on site. The remaining 38m3 can be stored in 50m2, 0.8m deep, geocellular crate storage. At detailed design some storage could be located under the permeable car park area if required. Final storage locations and volumes can be provided at detailed design stage. Details of the location is shown in Appendix 2.
The flow control for the system is provided through a Hydrobrake or similar vortex flow control device limiting the flows to the minimum practical peak runoff rate of 1l/s (utilising a 55mm orifice plate).
In the event of drainage system failure, extreme rainfall events or blockage, flooding may occur within the site. In this event, it should be ensured water runoff would not impact on the proposed building or neighbouring properties. To mitigate against potential flooding, the building’s finished floor level should be raised 150mm above adjacent external ground levels, if feasible.
The Treatment train of Permeable Paving and Proprietary Treatment Systems ‐ Sediment Traps, are suitable to offer acceptable contamination treatment to runoff prior to being discharged to the ground.
Reference: 5601_SWDS Final v1.0
14
The proposals demonstrate that a significant reduction in runoff rates post development can be
achieved via implementation of the development and therefore can provide a betterment both in
respect to flood risk and surface water drainage at the site in accordance with NPPF, the London
Borough of Waltham Forest local policy requirements.
The findings and recommendations of this report are for the use of the client who commissioned
the assessment, and no responsibility or liability can be accepted for the use of the report or its
findings by any other person or for any other purpose.
Reference: 5601_SWDS Final v1.0
15
Appendix 1 – Supporting Information
MOUNT ECHO AVENUE
MOUNT ECHO DRIVE
ECHO HEIGHTS
55
62
SEYMO
UR RO
AD34
28
55
53
47
1
9
MO
UN
T ECHO DRIVE
MOUNT ECHO AVENUE
53
No.55 Existing House
No.1 Echo Heights
New Flats Block Gardens
Echo Heights
sightline
1
2
cycl
es
refu
se1
2
3
4
r a m p
Parking
cyclespermeable paving
34 32
(permeable surface)
sightlin
e
30 2826
Communal Gardens
existing trees
(demolished)
retained
(demolished)No.55 Existing Garage
up
cycles
0 20 40
1: 1250
60 80
10 0 10
Scale: Metres
5
1: 200
N
N datedrawn
scale paper size@
drawing no
drawing
projectrev
55 Mount Echo AvenueLondon E4
Block & Site Location Plans
A3
8/2020
SITE LOCATIONPLAN 1:1250
1:200, 1:1250
BLOCK PLAN 1:200
Residential Redevelopment
pB1903 :1A
Proposed
Reference: 5601_SWDS Final v1.0
16
Appendix 2 – Preliminary Surface Water Drainage Strategy Layout
r a m p existing treesretained
up
No.55 Existing House(demolished)
No.55 Existing Garage(demolished)
cycles
1
2
3
4 Parking(permeable surface)
1
2
cycl
es
permeable paving
Echo
Heig
htsM
OU
NT
ECHO
DRI
VE
Gardens Flat
s Blo
ckN
ew
Communal Gardens
No.1Echo Heights
53sightline
refu
se
cycles
sightlin
e
SW
SW SW SW SW SW SW SW SW SW SW SW SW
SWSW
SWSW
SWSW
SWSW
SW
SWSW
SW
50SQM GEOCELLULAR CTORAGE 0.8m DEEPOFFERING 22.8 CUBIC M STORAGE
FINAL SHAPE AND LOCATION TO BE CONFIRMED,POTENTIALLY USE PERMEABLE PAVEMENT FOR
STORAGE AT DETAILED DESIGN STAGE TO REDUCECRATE VOLUME
PERMEABLE PAVEMENTAREA AVAILABLE FOR STORAGE IS
APPROX 113sqmFOR COLLECTION AND
TREATMENT OF RUNOFF
SLOTTED PIPE TO COLLECTRUN OFF FROM CAR PARK
LAY NEW CONNECTION TO PUBLICSURFACE WATER SEWER.
ANY NEW CONNECTION TO OFFSITESEWERS TO BE AGREED WITH LOCAL
WATER AUTHORITY.OFFSITE SEWER DEPTH TO BE
CONFIRMED PRIOR TO DETAILEDDESIGN
HYDROBRAKE MANHOLE WITH 55mmOPENING TO LIMIT FLOWS TO 1l/s AS PER
SURFACE WATER DRAINAGE STRATEGY 5601
SW SW
SW
SWSW
SWSW
SWSW
SW
ACO
SW
SW
IMPERMEABLE LINERSURROUND
(1:20)
GEOCELLULAR STORAGE
750m
m M
IN C
OVER
+52.675 TARMAC SURFACE
50mm DEEP 5mm SINGLE SIZED
125
150mm GEN1 BED AND BACKING125x225 HB KERB WITH
CLEAN CRUSHED STONE.
60mm AQUAFLOW BLOCKS
PERMEABLE PAVING(1:20)
600
340mm
375m
m
150mm
EYE BRACKETFOR OPERATINGROPE
CONCRETE SURROUND GRADE GEN3150THK. (SULPHATE RESISTING)
LIFTING EYES INCONCRETE RINGS TO BEPOINTED
PIVOTING BY-PASS DOOROPERATING STEEL ROPE
HYDRO-BRAKE FLOW CONTROL BY HYDROINTERNATIONAL.SEE DRAINAGE LAYOUT FOR TYPE ANDLIMITED FLOW.
INLET PIPE OUTLET PIPE
50mm CONCRETE BLINDINGSURFACE OF JOINTROUGHENED TO PROVIDEKEY
GRADE GEN3 CONCRETE(SULPHATE RESISTING)
OUTLET SPIGOT
NEOPRENE RUBBER GASKET
CONCRETE SURROUNDGRADE GEN3 150THK.(SULPHATE RESISTING)
N.T.S.
PULL HANDLEACCESS TO BE POSITIONED ABOVEBY-PASS DOOR
600
2-4 COURSES SOLID ENGINEERINGBRICKS, PRECAST CONCRETEMASONARY UNITS OR PRECASTCONCRETE COVER FRAME SEATINGRINGS. MORTAR OR APPROVED RESINCOMPOUND TO BE MIN. 40 KN.
'B'REFER TOTABLE 1
PRECAST CONCRETE MANHOLESECTIONS, AND REINFORCED PRECASTCOVER SLAB AND REDUCING SLAB TOBE BEDDED WITH MORTAR,PROPRIETARY BITUMEN, RESIN,MASTIC OR SEALANT STRIPS THATHAVE THE APPROVAL OF THE PCMANUFACTURERS.
520
MANHOLE CONTROL(HYDRODBRAKE) SECTION
TYPE 3 INSPECTION CHAMBER
SW PRIVATE SURFACE WATER DRAIN
PERMEABLE PAVING
OVERLAND FLOW
LEGEND
ATTENUATION SYSTEM
PERFORATED SURFACE WATER DRAIN
ACO CHANNEL DRAIN
1m 2m 3m 4m 5m01:100 @ A1
... ... ...XX.XX.XX##
1. GENERALa. THIS DRAWING IS NOT TO BE SCALED, WORK TO FIGURED DIMENSIONS ONLY,
CONFIRMED ON SITE.b. THIS DRAWING IS TO BE READ IN CONJUNCTION WITH ALL RELEVANT
ARCHITECTURAL DRAWINGS, DETAILED SPECIFICATIONS WHEREAPPLICABLE AND ALL ASSOCIATED DRAWINGS IN THIS SERIES.
c. ANY DISCREPANCY ON THIS DRAWING IS TO BE REPORTED IMMEDIATELY TOTHE PARTNERSHIP FOR CLARIFICATION.
d. THE CONTRACTOR IS RESPONSIBLE FOR ALL TEMPORARY WORKS AND FORTHE STABILITY OF THE WORKS IN PROGRESS.
e. CDM REGULATIONS 2015. ALL CURRENT DRAWINGS AND SPECIFICATIONSMUST BE READ IN CONJUNCTION WITH THE DESIGNER'S HAZARD RISK ANDENVIRONMENT ASSESSMENT RECORD. DESIGN HAS BEEN PRODUCED BASEDON INFORMATION PROVIDED BY THE CLIENT/PRINCIPLE DESIGNERAVAILABLE AT TIME OF ISSUE. CONTRACTOR TO REVIEW DRAWING ANDSPECIFICATION IN CONTEXT WITH THE WIDER SITE AND SPECIFIC SITEINVESTIGATION, CONTAMINATION ASSESSMENT, ASBESTOS SURVEY,ENVIRONMENTAL SURVEY, UXO SURVEY AND ANY OTHER RELEVANTINFORMATION AND MANAGE RISKS RELATING TO THE WORKS OUTLINED INTHE DRAWINGS AND SPECIFICATION. PRINCIPLE CONTRACTOR TO MAKEDESIGNER AND CLIENT AWARE OF SITE SPECIFIC RISKS THAT MAY AFFECTTHE DRAWING AND SPECIFICATION.
f. CDM REGULATIONS 2015. FOR GENERIC MAINTENANCE AND MANAGEMENTRISKS REFER TO CHAPTER 36 OF CIRIA 752 SUDS MANUAL. FORPROPRIETARY SYSTEMS SEE MANUFACTURER'S MANAGEMENT ANDMAINTENANCE DETAILS AND RISK ASSESSMENT WITH REGARDS TOMAINTENANCE OF PROPRIETARY SYSTEMS.
2. CONSTRUCTION NOTEa. THE MAIN CONTRACTOR IS RESPONSIBLE FOR THE DESIGN OF ALL
TEMPORARY WORKS, AND IS ALSO RESPONSIBLE FOR THE SAFEMAINTENANCE AND STABILITY OF EXISTING BUILDINGS AT ALL TIMES.
b. THE MAIN CONTRACTOR IS RESPONSIBLE FOR ALL OCCURRENCES OF GROUNDWATER DURING THE CONSTRUCTION PERIOD.
c. ANY INFORMATION GIVEN REGARDING EXISTING UNDERGROUND SERVICES ISGIVEN IN GOOD FAITH AFTER CONSULTATION WITH THE RELEVANTAUTHORITY, HOWEVER ACCURACY IS NOT CERTAIN. THE MAINCONTRACTOR IS RESPONSIBLE FOR CHECKING ALL INFORMATION ON SITEPRIOR TO WORK COMMENCING AND TAKING DUE CARE AND ATTENTIONWHILST UNDERTAKING THE WORKS.
d. THE CONTRACTOR MUST COMPLY WITH ALL CURRENT LEGISLATION RELATINGTO HEALTH & SAFETY.
e. ALL PRODUCTS SPECIFIED SHALL BE INSTALLED IN STRICT ACCORDANCE WITHTHE MANUFACTURERS RECOMMENDATIONS AND INSTRUCTIONS. IF THEREARE DISCREPANCIES BETWEEN THAT INFORMATION AND THE DETAILS ONANY AMBIENTAL DRAWINGS, THE MANUFACTURERS INSTRUCTIONS MUSTBE USED
3. BELOW GROUND DRAINAGEa. PIPEWORK TO BE UPVC-U PIPES TO BS 4660 : 2000 AND INSPECTION
CHAMBERS TO BS 7158 : 2001.b. ALL ADOPTABLE DRAINAGE TO BE CONSTRUCTED IN ACCORDANCE WITH
'SEWERS FOR ADOPTION' 7TH EDITION AND THE RELEVANT COUNCILDESIGN GUIDE.
c. ALL PRIVATE SURFACE WATER SEWERS TO BE LAID AT 1 IN 100 UNLESSOTHERWISE STATED ON THE DRAWING.
d. ALL PRIVATE FOUL WATER SEWERS TO BE LAID AT 1 IN 40 AT THE HEAD OFPIPE RUNS AND 1 IN 80 ELSEWHERE UNLESS OTHERWISE STATED.
e. ALL PRIVATE FOUL SEWER PIPES TO BE 150MM DIAMETER UNLESSOTHERWISE STATED ON THE DRAWING. ALL PRIVATE SURFACE WATERSEWER PIPES TO BE 100MM DIAMETER FROM DOWNPIPES AND 150MMDIAMETER ELSEWHERE UNLESS OTHERWISE STATED ON THE DRAWING.
f. ALLOW FOR RODDING ACCESS ABOVE GROUND WHERE RAINWATERDOWNPIPES DO NOT HAVE A DIRECT CONNECTION TO AN INSPECTIONCHAMBER. EXISTING SEWER PIPE TO BE RE-USED TO BE SURVEYED ANDLEVELLED PRIOR TO COMMENCEMENT OF THE DRAINAGE WORKS ANDREFURBISHED IF NECESSARY.
g. CONNECTIONS TO AN ADOPTED SEWER ONLY TO BE MADE FOLLOWINGAPPROVAL FROM THE RELEVANT ADOPTING AUTHORITY.
h. ALL DRAINS, SEWER PIPES AND MANHOLES TO BE CLEANED AND TESTED FORWATER TIGHTNESS ON COMPLETION OF CONSTRUCTION.
4. MANHOLE COVERS AND FRAMESa. MANHOLE COVERS TO BE CLASS D400 IN HIGHWAYS, CLASS B125 IN
FOOTWAYS AND VERGES, CLASS A15 IN NON-TRAFFICKED AREAS.b. MANHOLE COVER AND FRAME TO BE BEDDED AND SURROUNDED IN 1:3
MORTAR.
Drawing No. Revision
Drawing Scale:
Drawn by: Date:
Drawing
Project
Client
Draw
ing
No:
REV DATE DESCRIPTIONBY CKD APPD
PRELIMINARY DRAWINGFOR INFORMATION ONLY. NOT FOR CONSTRUCTION.
BLUEYONDER
55 MOUNTAIN ECHO AVENUELONDON E4 7JX
SITE LAYOUTSTORM DRAINAGE STRATEGY
5601 - DR01
TV JUL - 2020
-
C:\U
sers
\305
223\
Box\
WAT
-DW
-AEA
Gen
eral
\PRO
JECT
S\56
01_S
quire
s_M
t.Ech
o Av
enue
\Pla
ns\A
mbi
enta
l\560
1 DR
01.d
wg
THAMES WATER SEWERRECORD PLAN EXTRACT
Reference: 5601_SWDS Final v1.0
17
Appendix 3 – Calculations
���������� ���������� ����������������������
�
���������� ���������
��������������������� �� ������������������� ��������
��� �������� ������� ����
��������� �������� ��!"�
����������� #�������$�%&'
()*+,-+*.)/0
#��� ��� �1�2�3%34�5
#��6� ��� ���11$$4�7
8 �������������������� ��6��������� ������������ ������� �����������������������
9��������������������� ���"��������!6�����6 ������:;������ ���������6������
������"��9�����<=����>��13�?��1>@�=�� ��� A����� ���%�>�?���=���1�@�����
� �����B���� �������������������� A��?A����=���1�@��8 ���������������6��������� ��������������
��
� ����������������6��������������� �������6������ ������������� ���������������
;��������� $�%�32�>�%
A���� ! 6���������1���>
CDEFGG,+0*)H.*)FE,.IIJF.KL MN1�$
()*+,KL.J.K*+J)0*)K0
8�������������? �@��111
O+*LFPF/FQR
S ������������� ��� ��� ����������T;������!!;
�T;������������� ������ ����������UM#���9�
(F)/,KL.J.K*+J)0*)K0A��� � �����
�UM#���9��$ $
NU�8������5�! 5�!
�T;��T;NU�8���$% ��$%
VRPJF/FQ)K./,KL.J.K*+J)0*)K0A��� � �����
�!!;�?��@�2�� 2��
N�����6�����6���2 2
����� �� �"���������1���������� ����
����� �� �"���������>�������� ��> ��>
����� �� �"���������1��������� >�13 >�13
����� �� �"������������������� >�%$ >�%$
WF*+0
XYZ,[0,\ ,],̂_̀,/a0aL.b
7 ���S ���c�������� ��� ������6���� ��6������������������
������� ��
X̂Z,dJ+,G/Fe,J.*+0,],f_̀,/a0b
7 ����������������������� ������������������������� ��6���
� ������������������������6�������"�6������������� ��
����������9�������#����������������������������������� ���
� �������6��������������������� ��6��99��9����������6�
��������
XgZ,[0,(hCa(hCVi(j,k,̀_gb
7 ����6�� ���������"������������� 6 �� �� ���������������
����"������ ��6����������� ������������9������������
��9�������� ������������� �����
lJ++EG)+/P,JDEFGG,J.*+0A��� � �����
S �?��@���$2 ��$2
1���1������?��@���$ ��$
1���>��������?��@� 1��% 1��%
1���1��������?��@� 1�$� 1�$�
1�������������?��@� 1�%$ 1�%$8 ����9��������9��� ���� ��6�� ��6��������� �����������"��9������N;�7��6����������"������������ �� ��������8 �� ������� ��������� �m�������� ��no�� A������������������������
�������6��������=�� � �������� ������ ���������� �� ������������B���B��������� ����8 ��� �9 ��������� ����������������������6��������� ������������8 �� ������� ������� ������ �
���9����������� �� ��������� �������5����������������9�������N;�7��6����=�� ����"��������!6����=���N=�N������ �������������� �����6������������� �� ������� ���������� �����6����
�9��������� ������������������������6���� ����
p!;
qdC
p!;
p!;
Ambiental Environmental File: 5601 - Calcs (Brown eld).pfdNetwork: Storm NetworkMark Naumann20-Aug-20
Page 15601_Squires_Mt.Echo Avenuebrown eld calcs
Flow+ v9.1 Copyright © 1988-2020 Causeway So ware Solu ons Limited
Design Se ngs
Rainfall MethodologyReturn Period (years)
Addi onal Flow (%)FSR Region
M5-60 (mm)Ra o-R
CVTime of Entry (mins)
FSR1001England and Wales20.0000.4000.7504.00
Maximum Time of Concentra on (mins)Maximum Rainfall (mm/hr)
Minimum Velocity (m/s)Connec on Type
Minimum Backdrop Height (m)Preferred Cover Depth (m)
Include Intermediate GroundEnforce best prac ce design rules
30.0050.01.00Level So ts0.6000.900✓✓
Nodes
Name Area(ha)
T of E(mins)
CoverLevel(m)
Diameter(mm)
Eas ng(m)
Northing(m)
Depth(m)
1Drained areaGeocellular storage
0.016 4.00 10.00010.000
12001200
-78.01912.034
43.57845.612
1.0001.062
Links (Input)
Name USNode
DSNode
Length(m)
ks (mm) /n
US IL(m)
DS IL(m)
Fall(m)
Slope(1:X)
Dia(mm)
T of C(mins)
Rain(mm/hr)
1.000 Drained area Geocellular storage 5.000 0.600 9.000 8.938 0.062 80.0 100 4.10 50.0
Simula on Se ngs
Rainfall MethodologyFSR Region
M5-60 (mm)Ra o-R
Summer CVWinter CV
FSREngland and Wales20.0000.4000.7500.840
Analysis SpeedSkip Steady State
Drain Down Time (mins)Addi onal Storage (m³/ha)
Check Discharge Rate(s)Check Discharge Volume
Detailedx14400.0xx
Storm Dura ons15 30 60 120 180 240 360 480 600 720 960 1440
Return Period(years)
Climate Change(CC %)
Addi onal Area(A %)
Addi onal Flow(Q %)
130
100
000
000
000
Ambiental Environmental File: 5601 - Calcs (Brown eld).pfdNetwork: Storm NetworkMark Naumann20-Aug-20
Page 25601_Squires_Mt.Echo Avenuebrown eld calcs
Flow+ v9.1 Copyright © 1988-2020 Causeway So ware Solu ons Limited
Results for 1 year Cri cal Storm Dura on. Lowest mass balance: 100.00%
Node Event USNode
Peak(mins)
Level(m)
Depth(m)
In ow(l/s)
NodeVol (m³)
Flood(m³)
Status
Link Event(Upstream Depth)
USNode
Link DSNode
Ou low(l/s)
Velocity(m/s)
Flow/Cap LinkVol (m³)
DischargeVol (m³)
115 minute winter Drained area 10 9.044 0.044 2.4 0.0498 0.0000 OK
15 minute winter Drained area 1.000 Geocellular storage 2.4 0.754 0.355 0.0159 1.0
15 minute winter Geocellular storage 10 8.979 0.041 2.4 0.0000 0.0000 OK
Ambiental Environmental File: 5601 - Calcs (Brown eld).pfdNetwork: Storm NetworkMark Naumann20-Aug-20
Page 35601_Squires_Mt.Echo Avenuebrown eld calcs
Flow+ v9.1 Copyright © 1988-2020 Causeway So ware Solu ons Limited
Results for 30 year Cri cal Storm Dura on. Lowest mass balance: 100.00%
Node Event USNode
Peak(mins)
Level(m)
Depth(m)
In ow(l/s)
NodeVol (m³)
Flood(m³)
Status
Link Event(Upstream Depth)
USNode
Link DSNode
Ou low(l/s)
Velocity(m/s)
Flow/Cap LinkVol (m³)
DischargeVol (m³)
115 minute winter Drained area 10 9.081 0.081 5.9 0.0920 0.0000 OK
15 minute winter Drained area 1.000 Geocellular storage 5.9 0.913 0.872 0.0322 2.6
15 minute winter Geocellular storage 10 9.010 0.072 5.9 0.0000 0.0000 OK
Ambiental Environmental File: 5601 - Calcs (Brown eld).pfdNetwork: Storm NetworkMark Naumann20-Aug-20
Page 45601_Squires_Mt.Echo Avenuebrown eld calcs
Flow+ v9.1 Copyright © 1988-2020 Causeway So ware Solu ons Limited
Results for 100 year Cri cal Storm Dura on. Lowest mass balance: 100.00%
Node Event USNode
Peak(mins)
Level(m)
Depth(m)
In ow(l/s)
NodeVol (m³)
Flood(m³)
Status
Link Event(Upstream Depth)
USNode
Link DSNode
Ou low(l/s)
Velocity(m/s)
Flow/Cap LinkVol (m³)
DischargeVol (m³)
115 minute winter Drained area 10 9.127 0.127 7.6 0.1437 0.0000 SURCHARGED
15 minute winter Drained area 1.000 Geocellular storage 7.5 0.961 1.108 0.0377 3.3
15 minute winter Geocellular storage 10 9.025 0.087 7.5 0.0000 0.0000 OK
Ambiental Environmental File: 5601 - Calcs.pfdNetwork: Storm NetworkMark Naumann19/08/2020
Page 15601_Squires_Mt.Echo AvenueProposed calcs
Flow+ v9.1 Copyright © 1988-2020 Causeway So ware Solu ons Limited
Design Se ngs
Rainfall MethodologyReturn Period (years)
Addi onal Flow (%)FSR Region
M5-60 (mm)Ra o-R
CVTime of Entry (mins)
FSR10040England and Wales20.0000.4000.7504.00
Maximum Time of Concentra on (mins)Maximum Rainfall (mm/hr)
Minimum Velocity (m/s)Connec on Type
Minimum Backdrop Height (m)Preferred Cover Depth (m)
Include Intermediate GroundEnforce best prac ce design rules
30.0050.01.00Level So ts0.6000.900✓✓
Nodes
Name Area(ha)
T of E(mins)
CoverLevel(m)
Diameter(mm)
Eas ng(m)
Northing(m)
Depth(m)
1Drained areaGeocellular storage4
0.065 4.00 10.00010.00010.000
1200
1200
-78.32612.034
112.753
43.88545.61246.763
1.0501.1121.174
Links (Input)
Name USNode
DSNode
Length(m)
ks (mm) /n
US IL(m)
DS IL(m)
Fall(m)
Slope(1:X)
Dia(mm)
T of C(mins)
Rain(mm/hr)
1.0001.001
Drained areaGeocellular storage
Geocellular storage4
5.0005.000
0.6000.600
8.9508.888
8.8888.826
0.0620.062
80.080.0
150150
4.074.15
50.050.0
Simula on Se ngs
Rainfall MethodologyFSR Region
M5-60 (mm)Ra o-R
FSREngland and Wales20.0000.400
Summer CVWinter CV
Analysis SpeedSkip Steady State
0.7500.840Detailedx
Drain Down Time (mins)Addi onal Storage (m³/ha)
Check Discharge Rate(s)Check Discharge Volume
14400.0xx
Storm Dura ons15 30 60 120 180 240 360 480 600 720 960 1440
Ambiental Environmental File: 5601 - Calcs.pfdNetwork: Storm NetworkMark Naumann19/08/2020
Page 25601_Squires_Mt.Echo AvenueProposed calcs
Flow+ v9.1 Copyright © 1988-2020 Causeway So ware Solu ons Limited
Return Period(years)
Climate Change(CC %)
Addi onal Area(A %)
Addi onal Flow(Q %)
Return Period(years)
Climate Change(CC %)
Addi onal Area(A %)
Addi onal Flow(Q %)
130
4040
00
00
100 40 0 0
Node Geocellular storage Online Hydro-Brake® Control
Flap ValveDownstream Link
Replaces Downstream LinkInvert Level (m)
Design Depth (m)Design Flow (l/s)
x1.001✓8.8880.8001.0
Objec veSump Available
Product NumberMin Outlet Diameter (m)
Min Node Diameter (mm)
(HE) Minimise upstream storage✓CTL-SHE-0049-1000-0800-10000.0751200
Node Geocellular storage Depth/Area Storage Structure
Base Inf Coe cient (m/hr)Side Inf Coe cient (m/hr)
0.000000.00000
Safety FactorPorosity
2.00.95
Invert Level (m)Time to half empty (mins)
8.888280
Depth(m)
Area(m²)
Inf Area(m²)
Depth(m)
Area(m²)
Inf Area(m²)
Depth(m)
Area(m²)
Inf Area(m²)
Depth(m)
Area(m²)
Inf Area(m²)
0.000 50.0 0.0 0.400 50.0 0.0 0.800 50.0 0.0 0.801 0.0 0.0
Ambiental Environmental File: 5601 - Calcs.pfdNetwork: Storm NetworkMark Naumann19/08/2020
Page 35601_Squires_Mt.Echo AvenueProposed calcs
Flow+ v9.1 Copyright © 1988-2020 Causeway So ware Solu ons Limited
Results for 1 year +40% CC Cri cal Storm Dura on. Lowest mass balance: 100.00%
Node Event USNode
Peak(mins)
Level(m)
Depth(m)
In ow(l/s)
NodeVol (m³)
Flood(m³)
Status
Link Event(Upstream Depth)
USNode
Link DSNode
Ou low(l/s)
Velocity(m/s)
Flow/Cap LinkVol (m³)
DischargeVol (m³)
1120 minute winter Drained area 94 9.057 0.107 4.2 0.1205 0.0000 OK
120 minute winter Drained area 1.000 Geocellular storage 4.2 0.966 0.211 0.0775
120 minute winter Geocellular storage 94 9.056 0.168 4.2 8.0028 0.0000 SURCHARGED
120 minute winter Geocellular storage Hydro-Brake® 4 0.9 12.1
15 minute summer 4 1 8.826 0.000 0.8 0.0000 0.0000 OK
Ambiental Environmental File: 5601 - Calcs.pfdNetwork: Storm NetworkMark Naumann19/08/2020
Page 45601_Squires_Mt.Echo AvenueProposed calcs
Flow+ v9.1 Copyright © 1988-2020 Causeway So ware Solu ons Limited
Results for 30 year +40% CC Cri cal Storm Dura on. Lowest mass balance: 100.00%
Node Event USNode
Peak(mins)
Level(m)
Depth(m)
In ow(l/s)
NodeVol (m³)
Flood(m³)
Status
Link Event(Upstream Depth)
USNode
Link DSNode
Ou low(l/s)
Velocity(m/s)
Flow/Cap LinkVol (m³)
DischargeVol (m³)
1180 minute winter Drained area 176 9.387 0.437 7.4 0.4945 0.0000 SURCHARGED
180 minute winter Drained area 1.000 Geocellular storage 7.2 1.063 0.365 0.0880
180 minute winter Geocellular storage 176 9.387 0.499 7.2 23.7086 0.0000 SURCHARGED
180 minute winter Geocellular storage Hydro-Brake® 4 0.9 31.5
15 minute summer 4 1 8.826 0.000 0.9 0.0000 0.0000 OK
Ambiental Environmental File: 5601 - Calcs.pfdNetwork: Storm NetworkMark Naumann19/08/2020
Page 55601_Squires_Mt.Echo AvenueProposed calcs
Flow+ v9.1 Copyright © 1988-2020 Causeway So ware Solu ons Limited
Results for 100 year +40% CC Cri cal Storm Dura on. Lowest mass balance: 100.00%
Node Event USNode
Peak(mins)
Level(m)
Depth(m)
In ow(l/s)
NodeVol (m³)
Flood(m³)
Status
Link Event(Upstream Depth)
USNode
Link DSNode
Ou low(l/s)
Velocity(m/s)
Flow/Cap LinkVol (m³)
DischargeVol (m³)
1240 minute winter Drained area 232 9.572 0.622 7.7 0.7037 0.0000 SURCHARGED
240 minute winter Drained area 1.000 Geocellular storage 7.5 0.994 0.379 0.0880
240 minute winter Geocellular storage 232 9.572 0.684 7.5 32.4928 0.0000 SURCHARGED
240 minute winter Geocellular storage Hydro-Brake® 4 0.9 43.8
15 minute summer 4 1 8.826 0.000 0.9 0.0000 0.0000 OK
Reference: 5601_SWDS Final v1.0
18
Appendix 4 – CCTV report
Ref C0013118 Date 03/08/2020 Heritage Estate Group Ltd 55 Mount Echo Avenue London E4 7JX Dear Sir/Madam 1. DESCRIPTION OF PROPERTY Residential Property 2. DRAINAGE SYSTEM The pipework surveyed is a foul drainage system, accessible by Inspection Chambers. The pipework is circular, 100mm in diameter and both pvc & vitrified clay materials. Further specific variations may be in the report content. 3. SHARED The sections within the property boundary are private; therefore, the responsibility of the site owner to maintain. 4. CIRCUMSTANCES
General investigation Works.
5. SUMMARY The defects noted in the attached report. 6. Quotation and Specification of Repairs To attend the above site and provide crew, materials, labour and plant to: ‐ Set up barrier protection Repair 1) – Sections 1 & 2 Excavate, remove and replace the defective pipework and realign the new installation to maximise flow. We will be pleased to carry out the above works for the sum of £2185.00 + VAT To make‐good, the above‐described works assuming no further problems found
The pipework will be tested and using CCTV to ensure maximum efficiency has been achieved and left in full working order and made good to BS EN 752. All debris removed from the site, and the site will be in a clean and clear condition on completion. 7. COST SAVINGS The proposed repair methods are specially selected, as the most cost‐effective method and expedient to rectify the defects noted. 8. GUARANTEE Please note that all repair works proposed are guaranteed for up to 5 years for repairs, and our guarantee does not affect your statutory rights. Due to the nature of working underground, it is not possible to state that there will be no further damage discovered. Once the repairs commence, if this occurs, we will make all efforts to mitigate the costs and seek authority through the proper channels before carrying out additional repairs. Please ensure that appropriate access to water and electricity provided on‐site to complete the repair (the engineer will confirm these details with you). If you require more information or wish to discuss this matter, please contact us. Yours sincerely Happy Drains Ltd
55
MOUNT ECHO AV
MO
UN
T E
CH
O D
RIV
E
MH1
MH2(BURIED)
MH3
REAR ELEVATION
SURVEY CARRIED OUT AS A STUDY FOR FUTURE CONSTRUCTION OF FLATSONLY THE PIPELINES SHOWN WERE REQUIRED TO BE SURVEYED
Happy Drains LtdUnit 12A chalex Ind Est, Southwick
Tel. 0800 849 [email protected]
Section Inspection - 22/07/2020 - MH1XSection Inspection Date Client's Ref Contractor's Ref Surface Type PLR
1 1 22. July 2020 C0013118 C0013118 Paving Slabs MH1X
Operator Vehicle Camera Temperature Pre Cleaned WeatherPE62 KTC SOLO PRO 2 Yes No rain or snow
Town or Village: London Inspection Direction: Downstream US MH: MH1
Road: 55 Mount Echo Av Use: Combined US Depth: 0.55 m
Location: Gardens (private) Total Length: 8.04 m DS MH: MH2 BURIED
Post Code: E4 7JX DS Depth: 0.85 m
Inspection Purpose:Routine inspection Pipe Shape: Circular
Surface Defects: Height / Width: 100 / 100mm
Lining Type: None Pipe Material: Polyvinyl Chloride
Lining Material: Standard: WRC MSCC5 Light
Comments:
Recommendations:
Scale: 1:67 Position [m] Code Observation Grade
0.00 MH Start manhole, MH1
0.06 MC Pipe material changes, to vitrified clay A
0.59 CC Circumferential crack from 11 o'clock to 10 o'clock A
A
4.72 JDL Large displaced joint C
A
5.45 JN Junction at 12 o'clock, diameter:100mm A
5.57 FC Circumferential fracture from 12 o'clock to 12o'clock
B
7.04 RJ Roots at joint B
8.04 MHF Finish manhole, MH2 BURIED, the pipe isunserviceable
55 Mount Echo Avenue - London - E4 7JX 1
MH1
MH2 BURIED
MH @ 0.00 m
MC @ 0.06 m
CC @ 0.59 m
JDL @ 4.72 m
MC @ 4.85 m
Happy Drains LtdUnit 12A chalex Ind Est, Southwick
Tel. 0800 849 [email protected]
Section Inspection - 22/07/2020 - MH1XSection Inspection Date Client's Ref Contractor's Ref Surface Type PLR
1 1 22. July 2020 C0013118 C0013118 Paving Slabs MH1X
Operator Vehicle Camera Temperature Pre Cleaned WeatherPE62 KTC SOLO PRO 2 Yes No rain or snow
Pipe Condition Grade: C Service Condition: Not Serviceable
Structural Defects Construction FeaturesService & Operational Observations Miscellaneous Features
55 Mount Echo Avenue - London - E4 7JX 2
JN @ 5.45 m FC @ 5.57 m RJ @ 7.04 m MHF @ 8.04 m
Happy Drains LtdUnit 12A chalex Ind Est, Southwick
Tel. 0800 849 [email protected]
Section Inspection - 22/07/2020 - MH2 BURIEDXSection Inspection Date Client's Ref Contractor's Ref Surface Type PLR
2 1 22. July 2020 C0013118 C0013118 Paving Slabs MH2 BURIEDX
Operator Vehicle Camera Temperature Pre Cleaned WeatherROB PE62 KTC SOLO PRO 2 Yes No rain or snow
Town or Village: London Inspection Direction: Downstream US MH: MH2 BURIED
Road: 55 Mount Echo Av Use: Combined US Depth: 0.85 m
Location: Gardens (private) Total Length: 3.11 m DS MH: MH3
Post Code: E4 7JX DS Depth: 1.00m
Inspection Purpose:Routine inspection Pipe Shape: Circular
Surface Defects: Height / Width: 100 / 100mm
Lining Type: None Pipe Material: Vitrified Clay
Lining Material: None Standard: WRC MSCC5 Light
Comments:
Recommendations:
Scale: 1:50 Position [m] Code Observation Grade
0.00 MH Start manhole, MH2 BURIED
1.05 R Roots B
2.27 RJ Roots at joint B
3.11 MHF Finish manhole, MH3, the pipe is unserviceable
Pipe Condition Grade: B Service Condition: Not Serviceable
Structural Defects Construction FeaturesService & Operational Observations Miscellaneous Features
55 Mount Echo Avenue - London - E4 7JX 3
MH2 BURIED
MH3
MH @ 0.00 m
R @ 1.05 m
RJ @ 2.27 m
MHF @ 3.11 m