In this class, you are going to:
• Receive a high level overview of the Supply Chain Management System (SCMS).
• Receive a slightly more detailed overview of the SCMS Procurement Module.
• Perform as many of the following tasks as time will allow:– Create a Purchase Requisition (Role of Program Manager).– Review and approve purchase requisition (role of Budget
Holder)– Review and accept purchase requisition (role of Local
Procurement Manager)– View available inventory (role of Guest)
2
SCMS Master Class
SCMS Overview
The Vision: A supply chain management system that
facilitates significant improvements in the management of ALL material resources, including:
• Food Commodities• Non-Food Commodities (NFIs, etc)• In-kind Donations • Etc (even office supplies!)
3
SCMS Overview: Goals • Increase Supply Chain Visibility
– Know where material is in the supply chain– Detect problems earlier– Improve accounting for material receipt and distribution
• Improve Decision Making– More efficient use of resources– Enhanced tools for SCM planning
• Increase Operational Efficiency– Reduce supply chain costs– Improve donor reporting– Eliminate one-off system implementations
4
SCMS Overview: Scope • Provision and implementation of a single global
IT application system to manage the CRS supply chain
• Standardization of Global Supply Chain Management operating processes
This will entail a Significant Change Management & Communication Effort!!!
5
6
SCMS Overview
PLAN
Forecast Demand
SOURCE
Request Materials
Assess Inventory
Purchase Materials
FULFILL
Ship Materials
Receive & Store
Materials
Distribute Materials
Manage Payments
MANAGE
Manage Inventory
Manage Vehicle
Fleet
Manage Fixed
Assets
NOTIFY & REPORT
Workflow & Events
Trace & Track
Report
Phase 1 SCMPhase 1 and Phase 2 SCM*
Phase 2 SCM
Plan Logistics Network
Forecast Supply
Reconcile Demand &
SupplyManage
Donations
SCMS OVERVIEW
• The SCM System will be piloted and rolled out across the agency in two phases.
• Phase 1 includes basic Warehouse and Procurement modules (with potential for Fleet Management module to be added).
• Phase 2 includes more advanced functionality, including things like Planning/Forecasting, Asset Management and Distribution.
7
SCMS Status Update, Highlights
All four country pilots (Ethiopia, Kenya, JWBG and Burkina Faso) are now live! They were launched between October and December 2012.
Warehouse and procurement (online and offline modes) are being used in the pilot locations. Fleet is being tested in three locations.
Staff were sufficiently trained to be able to use these modules correctly and have been working independently with the system.
8
SCMS Status Update, Highlights
• Based on Pilot Success Criteria (20/25 fully met, remaining 5 partially met), pilots were judged a success.
• Pilot participants voted 29/30 to roll out the system once threshold issues are addressed (remaining vote was in favour of immediate rollout).
• Steering Committee also voted in favour of rollout.
• Intensive efforts are underway with AM to resolve the threshold issues.
• Additional next steps are being determined (including budget review/revision). 9
Phase 1 Pilots: Initial phase of pilots completed (Jan ‘13).Continuation of pilots and preparation for pilot CP rollout (Feb-June ‘13)
System Deployment: Final System Configuration: Jan—May ‘13Deployment to Production: June ‘13
Phase 1 Rollout: Remote Training and Prep to begin in May ‘13, and system implementation to begin Jul ‘13. New 4 CPs to be on-line FY13; Remaining CPs in FY14.
Phase 2: TBD
SCMS Schedule Details
10
•HQ will support 1 Launch/Training per region (to include ToT)•Training participants will include:•Regional rollout teams, composed of DRD/MQ, RISA,
Commodity RTA and 3-6 selected CP staff.•Relevant staff of the Launch CP.
• We expect that each CP will require: •1-2 visits by a regional rollout team.•Significant remote support by regional rollout teams for at
least one month around each CP launch (support for some CPs could be simultaneous).
SCMS Rollout Plan
Header Info
Header Info
Line Item Details
Summary
Step 1 Step 2 Step 3 Step 4
PR Summary
PO Summary
Submit to LPM
Enter Summary Bid Information
Generate RFQs
Assign Winner
PO Approved
Generate PO
Pre-Receive Summary
PM/Requestor
LPM
BH/Finance
PR Approved
Assign Suppliers
Edit?
Submit to BH
Accepted?
Receive Quotes
BH
Purchase Requisition Wizard
SCMS Procurement Module
Task One: Create a Purchase Requisition (Role of Program Manager).Step 1: Input all required information.Step 2: Verify all information, and finalize requisition.Step 3: Submit to Budget Holder (select the one you have been provided).
Task Two: Review and approve purchase requisition (role of Budget Holder)Step 1: Find your purchase requisition in the purchase requisition summary.Step 2: Review and approve it.Step 3: Submit to Local Procurement Manager.
Task Three: Review and accept purchase requisition (role of LPM)Step 1: Find your purchase requisition in the purchase requisition summary.Step 2: Review and accept it.
Task Four: View Available Inventory (role of Guest)13
SCMS: Class Tasks
Please Note:
• Pilots were successful, but issues were identified that are being addressed---this version is the one that was piloted, so issues are still there.
• We are still finding occasional bugs/defects, and Aidmatrix prioritizes them for fixing. (This is not uncommon for a system that is undergoing significant change.)
14