Supplier Onboarding Lean 90-Day 092715 - UW...

38
Supplier Onboarding Lean 90-Day Step Back September 28, 2015

Transcript of Supplier Onboarding Lean 90-Day 092715 - UW...

Page 1: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Supplier Onboarding Lean90-Day Step Back

September 28, 2015

Page 2: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Launch Scope• Problem Statement:

• It can take up to 5 weeks from registering a new supplier until a payment can be issued

• During onboarding the status is not very visible to campus departments or the supplier

• Background:• The onboarding process is complex, misunderstood,

time-consuming and not transparent• Orders that could be placed in eProcurement are

stalled or routed through other methods because of onboarding and Ariba Network enablement delays

• Lack of transparency causes communication problems and increases administrative burden to campus and central office

Page 3: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Current State Map & Steps• Process Steps: 133• Process Times

• Touch (Ideal) Time: 12 hours – 18 hours 45 minutes• Process (Current) Time: 11.5 days – almost 10 weeks• Wait Time (Between Steps) : 10 weeks – over 28 weeks

• Complete Accurate Correct: 50% - 95% • Rework Loops: 5• Pain Point Categories: 11• Ideas for Improvement: 145

Page 4: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Goals1. Reduce the onboarding time for a new supplier from first

contact through being ready to transact within eProcurement (Ariba) to 2 weeks

2. Provide visibility of supplier status within the onboarding process at key milestones for all stakeholders

Page 5: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Supplier Management Systems Integration

Team Members: Angela Battle (Lead), Claudia Christensen, Karen Ericksen, Laurie Hunt, Ernie Jones, Aron Knapp, Kyle Richard, Tina Padilla and Don Wilcox

Aligns with Goals 1 & 2

Page 6: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Current State

Page 7: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Value• Modernize systems• Consolidate systems• Increase automation• Improve timeliness of data• Improve quality control/error checking• Improve visibility• Improve reporting/metrics• Reduce time/steps/systems in supplier onboarding• Reduce need for human data transport processes

Page 8: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Proposal• Consolidate Systems (into Single Workflow Web Service)

• Supplier Registration Form (SuRF)• Vendor Control

• Automate • Data Transfers• Campus Ariba Network Enablement Request

• Supplier/UW Notifications• Modify PAS• New Status Codes• Time/Date Stamps

Page 9: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Future State

Page 10: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Increase Visibility in the Supplier Onboarding Process

Team Members: Karen Ericksen, Meg Frazer (Lead), Laurie Hunt, Ernie Jones, Aron Knapp, Tina Padilla and Don Wilcox

Aligns with Goal 2

Page 11: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Current State

• No visibility to where new supplier is in the onboarding process• No information at the address level• Terminology unclear

Page 12: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Milestone Current State Future State

Supplier has completed the SRF NO YES

Vendor File Created YES YES

Payment instructions sent to the supplier

NO YES

Tax ID Verified NO YES

Supplier has set up a payment method YES YES

Department submitted request to initiate Ariba Enablement

NO YES

Trading relationship request (TRR) sent to supplier

NO YES

Supplier has accepted the trading relationship

NO YES

PO and Invoice routing completed NO YES

Campus can initiate a Blanket Purchase Order

YES YES

Page 13: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Future State

• Recommendations to include:• Date when critical process starts (Supplier file created, TRR sent)• Tax ID Number (TIN) verification results• Sequence/address level detail• Separate the different paths (Ariba vs. Payment registration)

• Recommendations to remove:• Catalog attribute

Page 14: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Define Roles & Improve Workflow

Team Members: Karen Ericksen, Elise Glassman, Laurie Hunt, Tina Padilla, Heidi Tilghman and Felix Velasco (Lead)

Aligns with Goal 1

Page 15: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party
Page 16: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party
Page 17: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

• Condense number of teams involved in supplier onboarding from 5 teams to 2 teams

• Eliminate redundant hand-offs• Increase efficiency• Increase knowledge base

Page 18: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

1 2 3 4 50 6 7 8 9 10 11 12 14 161513 22212018 19 23 27262524 30292817

Supplier OnboardingCurrent State average: 26 Business Days

Range:  5‐63

Create Supplier RecordAvg:  4 Days

Start DelayWait for PAS 

Record

Avg:  3 Days

Payment SetupAvg 14 Days

CRDAvg: 9 Days

ACHAvg: 16 Days

Tax VerificationAvg: 2 Days

Ariba RegistrationAvg: 10 Days

FollowingWednesday

FollowingMonday

Business Days

Why is there a 14-day wait time for requesting that a supplier be enabled in Ariba? Why does it take 16 days for the ACH payment setup process to be completed?

Supplier Onboarding Analysis Questions:

Page 19: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

1 2 3 4 50 6 7 8 9 10 11 12 14 161513 22212018 19 23 27262524 30292817

Supplier OnboardingCurrent State average: 26 Business Days

Range:  5‐63

Create Supplier RecordAvg:  4 Days

Start DelayWait for PAS 

Record

Avg:  3 Days

Payment SetupAvg 14 Days

CRDAvg: 9 Days

ACHAvg: 16 Days

Tax VerificationAvg: 2 Days

Ariba RegistrationAvg: 10 Days

FollowingWednesday

FollowingMonday

Business Days

If the 14-day wait-time for Ariba registration requests is eliminated…

Page 20: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

1 2 3 4 50 6 7 8 9 10 11 12 14 161513 22212018 19 23 27262524 30292817

Supplier OnboardingFuture State Average: 12 Business Days

Create Supplier RecordAvg:  4 Days

Start DelayWait for PAS 

Record

Avg:  3 Days

Payment SetupAvg 14 Days

CRDAvg: 9 Days

ACHAvg: 16 Days

Tax VerificationAvg: 2 Days

Ariba RegistrationAvg: 10 Days

FollowingWednesday

FollowingMonday

Business Days

… the number of days to onboard a supplier may be reduced from 26 to 12 days.

Page 21: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

1 2 3 4 50 6 7 8 9 10 11 12 14 161513 22212018 19 23 27262524 30292817

Supplier OnboardingFuture State Average:  12 Business Days

Create Supplier RecordAvg:  4 Days

Start DelayWait for PAS 

Record

Avg:  3 Days

Payment SetupAvg 14 Days

CRDAvg: 9 Days

ACHAvg: 16 Days

Tax VerificationAvg: 2 Days

Ariba RegistrationAvg: 10 Days

FollowingWednesday

FollowingMonday

BUSINESS DAYS

How can the ACH payment setup process be shortened to 10 days or less?

Page 22: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

1 2 3 4 50 6 7 8 9 10 11 12 14 161513 22212018 19 23 27262524 30292817

Supplier OnboardingFuture State Average:  12 Business Days

Create Supplier RecordAvg:  4 Days

Start DelayWait for PAS 

Record

Avg:  3 Days

Payment SetupAvg 14 Days

CRDAvg: 9 Days

ACHAvg: 16 Days

Tax VerificationAvg: 2 Days

Ariba RegistrationAvg: 10 Days

FollowingWednesday

FollowingMonday

BUSINESS DAYS

Hold Lean event to:• Investigate obstacles of ACH payment setup process• Determine solutions to reduce setup time

Page 23: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

RecommendationsSingle Team with Integrated Onboarding & Maintenance Processes

Determine the process and role of an integrated team, to ensure:

• Cross-functional collaboration• Ownership & empowerment• Single point of contact

Workflow ImprovementsTo reduce supplier onboarding process time:

• Eliminate separate Ariba registration request process• Improve ACH payment setup process (Lean event)• Eliminate redundant tasks uncovered during analysis

Page 24: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Develop Supplier-Focused Strategy

Team Members: Claudia Christensen (Lead), Steve Ebling, Kassy Ellefson, Meg Frazer and Kyle Richard

Aligns with Goals 1 & 2

Page 25: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Current StatePAS Supplier Database as of July 31, 2015

31,504 Records

1,607 Ariba-Network Enabled• January 17, 2013 – July 31, 2015

1,309 Transacting in Ariba

175 New Suppliers Added Monthly• Not all complete the full enablement process

Page 26: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Current State

73% of suppliers have five transactions or lessHighest percentage of suppliers – Only one transaction

Page 27: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Recommendations Suppliers register by invitation only

Change SRF to Supplier Application Form (SAF)• The form is an application, not a registration

Ensure SAF captures all desired/required information• Add commodity information• Require supplier to accept Ariba and UW terms when applying

Application to be evaluated and approved by buying team

Develop rosters of qualified suppliers for high-volume, low-differentiation purchases – should be mandatory use

Use new commodity information in SAF, block registration of suppliers within “roster” codes unless a special exemption is granted

Purge supplier file regularly - Scheduled for Fall 2015

Page 28: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Future StateTo accomplish this, we will need:

A mandate from leadership that spend within roster categories must be on contract

• Procedures for exceptions

Programming to ensure additional data is added to the application

• i.e. Commodity Information

Page 29: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Improve Communications and Training with Stakeholders

Team Members: Maya Beal, Monica Cohn, Meg Frazer, Elise Glassman, Heidi Tilghman (Lead) and Felix Velasco

Aligns with Goals 1 & 2

Page 30: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Key PrinciplesAll communications originating in PS regarding Supplier Registrations should be:

Concise Clear

Precise Transparent

Timely

Specifically, all stakeholders should always: Understand policy and logic behind each step in the process;

Know which steps in the process have been completed; Know what the next steps in the process are;

Know where/how to find additional information; and Know whom to contact with questions/problems

Page 31: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Key Findings (Current State)Suppliers, campus partners and Procurement Services staff need…

1. Clear, pithy, accessible sources of information targeted for distinct audiences and learning styles

Challenge: Current website has become unwieldy, having grown organically as systems have evolved

Challenge: Email is overused, inconsistent and inefficient Challenge: Ariba support documentation is ineffective Challenge: ACH policy and workflow is opaque

2. Tracking tools for supplier onboarding actions Challenge: Suppliers and campus partners have no easy

access to registration milestones or status updates Challenge: Procurement Services has no system beyond

Outlook for tracking registration requests Challenge: Procurement Services has no standard follow-up

procedure or escalation plan for vexing registrations

Page 32: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Recommendations (Future State)1. Fundamentally reassess and recreate Procurement Service’s website,

focusing on the differing needs of each stakeholder group

Page 33: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Recommendations (Future State)1. Fundamentally reassess and recreate Procurement Service’s website,

focusing on the differing needs of each stakeholder group

2. (Re)Introduce ticketing system to capture, assign, and track each supplier registration and maintenance/update request

3. Improve strategic use of email correspondence

4. Design a simple milestone visualization tool for suppliers and campus partners that addresses the needs of both visual and linguistic learners

Figure 2: Sample/Generic Tool

Page 34: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Recommendations (Future State)1. Fundamentally reassess and recreate Procurement Service’s website,

focusing on the differing needs of each stakeholder group

2. (Re)Introduce ticketing system to capture, assign, and track each supplier registration and maintenance/update request

3. Improve strategic use of email correspondence

4. Design a simple milestone visualization tool for suppliers and campus partners that addresses the needs of both visual and linguistic learners

5. ACH presents challenges beyond the scope of our Kaizen

Improvements in communication can only occur after the ACH process itself is re-examined

To that end, Procurement Services should establish a new, short-term Lean team focused specifically on the ACH process

Page 35: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

People + Process + Technology = The Winning Solution

Page 36: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Open Items1. Kaizen recommendations are still separate2. How to implement recommended improvements

• Improve existing systems/reports now and implement new systems/visualization tools later?

• Spend all time & resources on new systems/visualization tools?

• Need to take action on short-term goals without losing sight of long-term future state

3. Scope, requirements and budget not yet defined

Page 37: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Next Steps1. Set a defined timeline for kaizens to align and prioritize

recommendations2. Present Lean proposal to sponsors3. Sponsors communicate date for final decisions4. Investigate requirements and cost with teams that will

program them5. Define requirements, scope and budget in detail6. Take action!

Page 38: Supplier Onboarding Lean 90-Day 092715 - UW Financefinance.uw.edu/ps/sites/default/files/Supplier... · Lessons Learned • Supplier onboarding is a very complex, multi-system, multi-party

Lessons Learned• Supplier onboarding is a very complex, multi-system, multi-

party process• Commonality of themes and issues – everyone generally

had the same ideas• Complexity of the current state systems and processes

required detailed analysis• Kaizens had to change scope/expectations during the

Lean event to be successful• Everyone participating is invested in simplifying and

improving the process• Focused objectives had to be separated to investigate

issues in detail and develop specific recommendations, but must also now collaborate to provide a unified future vision