1 What is an RFI?....................................................................................................................................... 3
2 Accessing the Ariba Sourcing System........................................................................................... 4
3 Responding to an RFI........................................................................................................................... 5
3.1 Accessing the RFI.......................................................................................................................... 5
3.2 Review Agreement – Accepting/Declining Participation................................................ 6
3.3 Review RFI Content ...................................................................................................................... 8
3.4 Downloading Documents........................................................................................................... 8
3.5 Message Board .............................................................................................................................. 9
3.6 Preparing Your Answers...........................................................................................................10
3.6.1 Uploading Documents ..........................................................................................................10
3.6.2 Replacing and Deleting Documents ................................................................................10
3.6.3 Exporting RFI Content into Excel and Respond Online .............................................11
3.7 Saving Your Answers.................................................................................................................11
3.8 Submitting Your Answers ........................................................................................................12
3.9 Revising Your Response ...........................................................................................................13
3.10 Response History.........................................................................................................................13
4 Event Status ...........................................................................................................................................15
4.1 Open.................................................................................................................................................15
4.2 Paused.............................................................................................................................................15
4.3 Pending Selection .......................................................................................................................15
4.4 Completed......................................................................................................................................15
5 Logout from Ariba ...............................................................................................................................17
PEP 2015 – Processes and Systems Error! Reference source not found.
Version 1.0 / October 2010 Page 3/17
1 What is an RFI?
RFI (Request for Information) is typically designed as a questionnaire for suppliers to
complete. In an RFI, Buyers gather information prior to receiving pricing information and
judge suppliers’ capabilities based on their responses.
An RFI event is used to gather non-competitive data, information, comments, and
reactions from potential participants. Participants typically do not respond to an RFI with
pricing information. Instead, RFIs usually precede other events (RFPs or Auctions) that
include price.
PEP 2015 – Processes and Systems Error! Reference source not found.
Version 1.0 / October 2010 Page 4/17
2 Accessing the Ariba Sourcing System
When the RFX opens, you automatically receive an email message containing a link to
the Roche Ariba Sourcing website. You can either click on the indicated URL or open an
internet browser and type in the following website address:
http://rsmsourcing.roche.com
Enter your user name and password, which were sent out to you in a separate system
generated email. Then click the Login button.
PEP 2015 – Processes and Systems Error! Reference source not found.
Version 1.0 / October 2010 Page 5/17
3 Responding to an RFI
3.1 Accessing the RFI
To access the RFI you have been invited to, simply select it from the Event List that
appears after login.
If you have been invited to only one event, you will be taken directly to that project after
logging in. In case you have been invited to multiple events, you will see them grouped
on your screen, based on their status: Completed, Open, Pending Selection.
You may expand the panels by clicking on the arrow located on the very left of the page.
You can enter the event by simply clicking on the event name.
In the upper right hand corner there is the countdown clock, which shows you how
much time is remaining to complete the RFI and submit your responses.
In the Event Details panel you can check the message board of the event and
download tutorials. The Introduction part will give you a general overview of the event.
Below that, you can see the owner of the event and the timelines in the Event Overview
and Timing Rules panel.
PEP 2015 – Processes and Systems Error! Reference source not found.
Version 1.0 / October 2010 Page 6/17
Please always pay particular attention to the timing rules and never leave bidding for the
last couple of hours.
3.2 Review Agreement – Accepting/Declining Participation
Before participating in an event, you will need to review and accept the bidder
agreement. Normally you will not be able to see the event details unless you accept the
agreement and state your intentto respond.
This agreement is separate from the initial agreement you see when you first log in to
the site, and must be agreed to on a per event basis. To access the bidder agreement,
click Review Agreement.
Accept the terms of the agreement if you agree to them and want to participate in the
event. Decline the terms of the agreement if you do not want to participate.
Select I accept… or I do not accept… and click OK.
PEP 2015 – Processes and Systems Error! Reference source not found.
Version 1.0 / October 2010 Page 7/17
If you click on Decline to Respond a pop-up window will appear where you can add
the reason for declining.
PEP 2015 – Processes and Systems Error! Reference source not found.
Version 1.0 / October 2010 Page 8/17
3.3 Review RFI Content
RFIs consists of different sections. Normally there is an introductory part where you may
see instructions posted by the Buyer, and any documents that may have been uploaded
for you to review.
You can switch to view all content or select only one section to review.
3.4 Downloading Documents
To download any documents attached by the Buyer, click on title of document and select
either Download this attachment or Download all attachments.
PEP 2015 – Processes and Systems Error! Reference source not found.
Version 1.0 / October 2010 Page 9/17
3.5 Message Board
It is possible to send messages to the Buyer through the system. To do that, click
Compose Message.
Type in a subject and your message in the Compose New Message screen and click
Send.
To see all the messages around the event go to the
Console and click on Event Messages. Here you will have
a list of all messages sent by you, the Buyer and the system.
To view a message select it and click View or click on the
subject. To reply, select message and click the Reply
button.
You will also find here system messages generated when
you submit an answer or when the event status changes.
PEP 2015 – Processes and Systems Error! Reference source not found.
Version 1.0 / October 2010 Page 10/17
3.6 Preparing Your Answers
In every RFI there is a section with questions that should be responded to by the
suppliers. All questions marked with an asterisk are required, which means you cannot
submit your response to the bid unless you answer the required questions. Questions not
marked are optional.
There are several types of answers: text boxes to enter free text or numbers, drop down
lists with predefined answers, and Yes/No answers.
For entering dates you should use the calendar icon instead of entering the date
manually.
3.6.1 Uploading Documents
It might be that you are required to attach documents to any of the questions. To attach
a file click on the Attach file link, and browse for your document. If you need to attach
multiple documents to one question it is better to save them in a zip file.
3.6.2 Replacing and Deleting Documents
To replace an uploaded document with another file, click Update file and browse for the
new document on your computer. To remove a document, simply click on Delete file.
PEP 2015 – Processes and Systems Error! Reference source not found.
Version 1.0 / October 2010 Page 11/17
3.6.3 Exporting RFI Content into Excel and Respond Online
For RFIs that contain a large amount of line items, you can also export the data into an
MS Excel spreadsheet, update it, then import it back to the system. Click Excel Import
to export content or import your offline response.
In Step 1 you can download RFI content and all attachments by clicking on Download
Content and Download Attachments. Attachments will be zipped in a single file.
In Step 3 you can upload responses using the RFI template, downloaded in Step 1.
To finish the upload, click the Upload button. Make sure that you do not change the
format of the template, do not delete or add columns, otherwise the upload will fail.
3.7 Saving Your Answers
Any time you stop working on the RFI, you can save it. Saving will let you leave the event
and return later on, without losing any responses entered previously.. Click Save button
to save your work.
PEP 2015 – Processes and Systems Error! Reference source not found.
Version 1.0 / October 2010 Page 12/17
Once you have saved your response you will see this message on the upper part of your
screen.
Please note that simple saving is not sending your response to the Buyer, it will be
visible only to you. Therefore never forget to submit your response before the event
closes!
3.8 Submitting Your Answers
Once you have completed working on the RFI, you can submit it by clicking on the
Submit Entire Response button.
You will see a pop-up message verifying that you want to submit your response.
Click OK to submit, or Cancel to continue working on your response.
After submitting your bid, you will see this message at the top of the page.
PEP 2015 – Processes and Systems Error! Reference source not found.
Version 1.0 / October 2010 Page 13/17
3.9 Revising Your Response
If you made any errors or you are required to enter additional information, you may edit
your response by clicking on the Revise Response button. Please note that editing an
event is only possible while it is in Open Bidding status.
Click OK to confirm your intention to revise your
response.
While editing you can reload your last submitted bid by clicking on the Reload Last Bid
button.
When ready, submit your answers by clicking on the Submit Entire Response button.
3.10 Response History
You can access all submitted versions of your answers by going
to Response History on the Console.
PEP 2015 – Processes and Systems Error! Reference source not found.
Version 1.0 / October 2010 Page 14/17
Here you will find the list of all your submitted answers. To enter any of them click on the
Reference Number.
This is how submitted answers look.
PEP 2015 – Processes and Systems Error! Reference source not found.
Version 1.0 / October 2010 Page 15/17
4 Event Status
4.1 Open
Open
In Open status you can work on your responses.
4.2 Paused
Paused
The event might be paused by the Buyer for editing reasons. In paused status you cannot
post any answers.
4.3 Pending Selection
When the event has ended, the countdown clock disappears and the event status
changes to Pending Selection. In this status, responses are no longer accepted and the
Buyer is evaluating the responses.
Here there are four actions you can take:
Download Content – download the event with your answers into an excel spreadsheet
Review Agreement – review the agreement you accepted at the beginning
Print Event Information - this is a print version of the event. It contains a summary of
the event and its contents.
Review Bidding – shows your last accepted bid
4.4 Completed
The final status of an event is Completed.
Go to View Award to see the award details. This button is only available if the bid was
partly or fully awarded to your company by the Buyer.