Supplier Bootcamp SessionElectricity & Gas Procurement
RM6011 & RM6012
Tuesday, 13th Feb 2018
Agenda
• Welcome
• Introduction to CCS
• Overview of Requirement
• Scope of Agreement
• Available Opportunity
• The Procurement Process
• Next Steps
CCCCS
2
Welcome to Crown Commercial Service
3
Crown Commercial Service
The Crown Commercial Service (CCS) brings together policy, advice and direct buying; providing
commercial services to the public sector and saving money for the taxpayer.
Executive Agency of the Cabinet Office operating as a Trading Fund
We work with over 17,000 customer organisations in the public sector and our services are provided by
more than 5,000 suppliers.
Our roles include:
● make savings for customers in both central government and the wider public sector
● achieve maximum value from every commercial relationship
● improve the quality of service delivery for common goods and services across government
4
5
Goals and Drivers
Strengthening the UK economy through effective
policy delivery
Maximising commercial benefits
Focusing on our customers
£12.4bn spend
£6bn CG £6.4bn
WPS
£430m of CG
Commercial
Benefits
£295m of WPS
Commercial
Benefits
Welcome to Utilities and Fuels
6
The areas CCS deliver
£520m
savings by
2019/20
£420m
savings by
2019/20
£520m
savings by
2019/20
£540m
savings
by
2019/20
Facilities management
Utilities & fuels
Property maintenance
Construction
Professional services
Workforce
Employee & people services
Cloud & digital
Network services
Software licensing
Technology products & services
Fleet
Financial services
Travel
Office solutions, print, post & storage
Marketing & communications
Contact centres
7
£725m commercial
benefits including savings
Identifying new opportunities to deliver superior customer
savings across power, gas, fuels, demand reduction
£2.3bn spend and £110m savings across CG and WPS
(15/16)
Percentage Split of Customers – 34% CG, 35% NHS, 31%WPS
7 current frameworks and 5 in the pipeline, 14 people in Strategic
Category, and 12.5 people in Customer Operations
1100 Customers across all products
CCS Utilities and Fuels Team
8
Category Structure
9
Overview of Procurement
• We have two agreements in the market for the Supply of Half Hourly Electricity (RM1075) and
Natural Gas (RM1076). The current agreements expire in April 2019
• Requirement is for a Gas and Electricity Supplier to provide the following services:
• the supply of Electricity and Gas (including Interim Supply)
• the Customer Administration Services and the Partnering Services
• Access to a range of Ancillary Services
10
Contractual Arrangements
Tripartite Agreement
11
Framework Structure
The framework Agreement is the agreement between yourselves and Crown Commercial Service outlining the
requirements and expectations for the delivery of the Agreement.
It is made up of:
● Terms and Conditions
● The Model Contract
● Ancillary Services Schedule
● Schedule 3 - Trading Requirements
● Schedule 5 - Customer Administration Services
● Schedule 6 - Framework Management
● Schedule 7 - Key Performance Indicators
● Customer Access Agreement
We will be issuing a copy of the current redacted Framework Agreement for your review and comment
as part of our engagement processes.
12
What does success look like?
● Desirable product in the marketplace to retain current customers and stimulate
growth of customer base;
● High quality supplier(s) appointed to deliver best in class solution to public sector;
● Value for Money route to market;
● Access to trading desks and support to facilitate market transactions on wholesale
energy market;
● CCS to establish a close strategic relationship with the successful supplier(s) to
drive continuous improvement and innovation during the life of the agreements.
13
Customer Benefits
14
Customers continually use the Crown Commercial Service Utilities and Fuel offering
because:
Trading Requirements
15
Trading Requirements
CCCCS
• Overview - Contracts, CCS Products
• HH Framework
• Gas Framework
• Supplier Requirements - what does all this
mean for you?
16
Overview
CCSSupplier
Customer
Customer Access Agreement (CAA):
● Sets customer commitment to CCS
● Aligned to CCS ‘products’
Framework Agreement includes:
● Supplier requirements to support CCS flexible, aggregated purchasing - price setting, price build up, energy
and non-energy cost reconciliation
Model Contract: sets out
requirements / obligations
between customer & supplier
17
CCS Products
18
CCS Products - Timeline / Volumes
19
HH Framework
Price Setting / Invoicing
Prices set at start delivery year:
Supplier applies CCS price matix to build
meter-specific energy prices
For variable prices where purchasing
ongoing, CCS provides reference baseload
& peak prices
Variable basket energy reconciliation:
● Forecast to actual prices
● Allocated by EAC
● Separate invoice line item
Shaping
CCS provides list of committed customers
for product - “baskets”
Supplier creates aggregated half-hourly
demand for committed customers - the
“provisional shape”
Shape blocked into base & peak
Remaining half hourly volumes = residual
Final committed customer demand shaped
close to delivery start. “Final shape”
At this stage volume risk transfers to
supplier
Flexible Purchasing
CCS Risk set controls (eg stop loss) once
shape agreed
CCS Trading use Supplier desk to transact
base & peak requirements
● Market orders, index trades
● Sell-back
● N2Ex for variable products
● 3rd Party provisions
Residual volumes:
● HH shape trades before delivery
● N2Ex
20
Gas Framework
Price Setting / Invoicing
Locked basket prices set start delivery
year, applying CCS prices applied to meter
profiles - “reference price”
Monthly price actualisation for all baskets:
● Daily balancing - daily demand
estimation applied to SND volumes
● Resulting volumes bought / sold at
DA Heren prices to derive volume
weighted monthly achieved price
Variable baskets invoiced at validated
monthly achieved price - “monthly price
change
Locked baskets annual reconciliation
Shaping
CCS provides list of committed customers
for product - “baskets”
Supplier creates daily demand for committed
customers - the “provisional shape” using
industry data
Final committed customer demand shaped
close to delivery start - “Final shape”
Variable Products only:
● Daily granularity
● Weather corrected daily forecasts
Volume risk retained by customer
Flexible Purchasing
CCS Risk set controls (eg stop loss) once shape
agreed
CCS Trading use Supplier desk to transact base
& peak requirements
● Market orders, ICE settlement, index
● Sell-back
● 3rd Party provisions
Variable Products only - within month contracts
CCS purchase to variable cover % - typically
90% but can be as low as 70%.
Remaining volumes purchased at DA price
21
Key Takeaways?
22
Supplier Considerations?
● Provide (indirect) access to wholesale markets for CCS price setting
activities within Framework period
○ Desk 09:00 - 17:00
○ Range of price setting options - market, trigger, index (eg ICE,
Argus),
● Long Term product purchases sleeve from current providers (we are
already purchasing for April ‘20 baskets)
● Long Term product purchases beyond term
● Credit / GTMA implications?
● Systems to support basket shaping / forecasting, pricing, invoicing,
reconciliation
The Procurement Opportunity
23
24
The Opportunity
Electricity GasStart Date: 27/03/2015
End Date: 26/03/2019
Customers: 855
Start Date: 27/04/2015
End Date: 26/04/2019
Customers: 840
Current Service Requirements
The core service elements to be delivered through the agreement will include:
● Provision of a dedicated customer account manager to deal with queries and
complaints;
● Access to a customer service team for administrative activities;
● Access to Framework Manager responsible for the delivery of the agreement;
● Option for a range of billing and payment terms;
● Provision of reports on request from the customer or CCS;
● Access to an online data portal;
● Provide interim pricing for customers;
● Complete market transactions as determined by the Authority;
● Creation of Final Purchase Shape for the Authority;
● Provide suite of supporting ancillary services including: site works, AMR services and
consumption reduction services.
25
Areas for Consideration
We are also considering a number of potential developments for our current
arrangements including:
● How we can improve our Ancillary Service offering to provide the right services to our
customers?
● How can we offer a more digital or ‘self service’ element to support customers in using
the agreement?
● How can we enhance our current service offering without significantly impacting on
the end cost for customers?
● How can we work to support the government’s and our customers’ sustainability and
social value requirements?
● How can we increase innovation through our agreements?
● How can we work with the supplier(s) to educate and inform the customer during the
life of the agreement?26
27
The Opportunity – London Energy Project
Current Gas Portfolio with CCS:
AQ Volume: 23,500,000 Therms / 0.69TWh
Current Electricity Portfolio with CCS:
EAC Volume: 0.26TWh
28
The Opportunity – London Energy Project
29
The Opportunity – Peer to Peer Trading
● Development of ‘blockchain’ technologies and the option to trade generated electricity, CCS are
looking to understand the potential for creating a public sector energy trading portal.
● Customers who generate energy will be able to set a price and trade with other public sector
customers looking to purchase.
● This will need to include billing options.
● Separate engagement will be taking place to better understand this requirement with dates to be
confirmed.
30
The Opportunity – Utilities Switching Services
● New initiative much like the switching and comparison sites we
use at home - aimed at small and medium sites
● Become an energy supplier via a Dynamic Purchasing
System: quantitative (yes/no) questions only - easy
onboarding for SMEs
● Attract new smaller customers who want tariff flexibility, choice
and ease of use
● Go-live anticipated August 2018, engagement now being
carried out prior to tender
Email us at [email protected] for more information
86 Bluelight sector
covering Policing &
Fire Services
c. 24,000 Schools
within Education
Sector - DfE
endorsement ongoing
c. 390 Local
Authorities / Local
Government
1000+ Charities
/ 3rd Sector
Market opportunity - key customer demographic...
What route is right for you?
31
The Procurement Process
32
33
Procurement ProcessP
re-
Ma
rket
En
gag
em
en
t Supplier Bootcamps
RFI docs
One to one meetings
Customer Stakeholder Panel
Customer Questionnaire
Final Business Case and Procurement Strategy
Te
nd
er
Sta
ge Development of Tender
Documents
Development of T&C’s
Development of Specification
Development of PQQ and Award criteria
Tender Response Evaluation
Framework Award Fra
mew
ork
Ma
na
ge
men
t
Customer onboarding process
Management of Supplier performance
Strategic framework development
Continuous Improvement and Innovation
34
The Procurement Process
Document Description
OJEU Notice Advertisement of TED to notify the market of the opportunity and register their
participation
Framework Agreement Outlines the Terms and Conditions of the Agreement which all Suppliers will
need to adhere and complementary schedules
Customer Access Agreement Customer signed authority that enables CCS to transact and set prices on
their behalf.
Model Contract Document outlining customer requirements from the supplier in the delivery of
their contract e.g. payment terms
Pre-Qualification Questionnaire The qualification of suitable Suppliers to progress to the Award questionnaire
Award Questionnaire Evaluates Suppliers quality and capabilities to select the most capable
Suppliers for Award
Pricing Matrix Suppliers submit their prices to deliver the specified services within the
agreement to assess VFM.
What Happens Next?
35
Timelines
Electricity
Gas
2018
36
2019
PIN
Publication
Jan 18
PIN
Publication
Jan 18
FBC & SD
Approval
May 18
FBC & SD
Approval
May 18
OJEU & PQQ
Publication
Aug 18
OJEU & PQQ
Publication
Sept 18
ITT
Publication
Sept 18
ITT
Publication
Oct 18
Response
Deadline
Oct 18
Response
Deadline
Nov 18
Award
Jan 19
Award
Feb 19
36
Next Steps
Supplier Engagement
Slides will be sent out and available online following meeting
● Supplier Webinar – 22/02/2018
● Supplier RFI release- 20/02/2018
● Supplier 1-2-1’s (London and Liverpool) - March/April 2018
● Project Update Meetings - June - August 2018
We will also be issuing regular updates on our progress on our dedicated webpage
including presented materials.
37
Questions?
38
How to Keep in Touch
Electricity Procurement Inbox:
Gas Procurement Inbox:
Project Webpage:
http://ccs-agreements.cabinetoffice.gov.uk/procurement-pipeline/supply-electricity-
rm6011-and-gas-rm6012-procurements
39
Contact Details
Elaine Malone (Electricity Lead)
Portfolio Development Lead
Kristen Green (Gas Lead)
Category Manager
40