SUPERFAST BROADBAND EXTENSION PROGRAMME AUGUST … · Broadband Project £4.07m in August 2011,...
Transcript of SUPERFAST BROADBAND EXTENSION PROGRAMME AUGUST … · Broadband Project £4.07m in August 2011,...
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 1
http://www.cswbroadband.org.uk August 2014
SUPERFAST BROADBAND EXTENSION PROGRAMME
AUGUST 2014
PUBLIC CONSULTATION
Executive Summary
This document sets out the current understanding of where minimum 2Mbps and superfast
(>24Mbps) broadband services are currently available or will be provided over the next 3 years
across Coventry, Solihull and Warwickshire, and thereby where, under state aid rules, intervention
using public funds to increase superfast broadband coverage can be permitted.
This consultation is intended to inform interested parties of our intention to progress a final
Intervention Area for submission to the BDUK National Competence Centre for clearance, taking on
board the outcome of the public consultation. It follows on from our previous Open Market Review
conducted during June-July 20141, where commercial operators were invited to provide details of
any formal investment plans for the proposed target areas over the next three years. The results
from this review have been used to establish the proposed intervention areas for the project set out
in section 8 of this document. This consultation provides an opportunity for broadband suppliers,
residents and businesses to feed back on the proposed intervention areas, particularly in relation to:
any broadband not- or slow-spots (i.e., areas unable to access minimum 2Mbps services) not
included in the proposed intervention areas, or the reverse; i.e., locations listed as
broadband not- or slow-spots, when 2Mbps or faster services are in fact available;
any locations where the current availability of superfast (above 24Mbps) services as
described in this document is known to be incorrect (i.e. areas listed as having superfast
services but where these are in fact unavailable, or the reverse);
any proposed intervention areas where plans are already in place to deliver minimum
2Mbps and/or superfast broadband services but these were not reported as part of the
previous Open Market Review.
1 http://www.cswbroadband.org.uk/whats-happening/procurement-2014/open-market-review-omr/
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 2
http://www.cswbroadband.org.uk August 2014
Businesses and residents are also encouraged to complete our broadband surveys in addition to
responding to this consultation. This document will be used to validate the proposed extent of the
intervention areas and inform the project’s final intervention area and tender processes.
Proposed Project Timetable
Activity Date
Public consultation period 18 August – 18 September 2014
Award superfast broadband contract December 2014
Broadband roll-out projected completion End 2017
Background – the importance of superfast broadband
It is now widely recognised that reliable, high-speed broadband access is now essential for homes,
businesses and public services. From the Governments’ National Infrastructure Plan2, published in
December 2013:
“Digital communications capability is an essential part of the UK’s core infrastructure and an
increasingly significant enabler for economic growth. The current revolution in the capability of
information and communications technology is transforming the way we live and work. The
government’s overarching ambition for digital communications is to harness the benefits of this
revolution, equipping the UK to succeed in the global race by moving first to secure a stronger
economy and a fairer society for all.”
In November 2013, the Government published its UK Broadband Impact Study – Impact Report3. Key
findings on the impact of broadband include:
for every £1 the government is investing in broadband, the UK economy will benefit by £20;
a significant short-term boost to the UK economy as the network construction adds around
£1.5 billion to the economy; adding £0.5 billion and about 11,000 jobs in 2014 alone;
long-term growth to the UK economy with public investment increasing annual GVA (gross
value added, a measure in economics of the value of goods and services produced in an
area, industry or sector of an economy4) by £6.3 billion and causing a net increase of 20,000
jobs in the UK by 2024.
2
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/263159/national_infrastructure_plan_20
13.pdf 3 https://www.gov.uk/government/news/the-benefits-of-broadband 4 http://en.wikipedia.org/wiki/Gross_value_added
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 3
http://www.cswbroadband.org.uk August 2014
Government funding for superfast broadband
In pursuit of these benefits and to ensure the widest possible availability of superfast broadband,
the Government has to date allocated £790m to extend roll-outs beyond the commercial
deployments that will reach around two thirds of UK premises to reach 95% of premises by 2017 and
99% by 2018. This breaks down as follows:
A first wave totalling £530m (match-funded locally) for local authorities in England to ensure
superfast broadband reaches 90% of premises in each local authority area by 2015-165;
An additional £250m for local authorities in England announced in June 2014 (again match-
funded locally) to extend superfast broadband from current coverage plans to 95% of
premises by 20176;
A £10m fund to support innovative approaches to superfast broadband provision in the
hardest to reach areas of the UK, to support strategies to ensure 99% coverage across the
UK by 2018.
In addition, the Government is investing £150m in 22 Super-Connected Cities (of which Coventry is
one) across the UK and £150m to improve the coverage and quality of mobile services, bringing the
total investment in fixed and mobile telecommunications across the UK to more than a billion
pounds.
Funding for superfast broadband in Coventry, Solihull & Warwickshire
The Government initially allocated the Coventry, Solihull & Warwickshire (CSW) Superfast
Broadband Project £4.07m in August 2011, later revised upwards to £4.45m7. Following a formal
procurement process, a £15.47m contract was awarded to BT In June 2013 to deliver superfast fibre
broadband to around 91% of CSW premises by spring 20168. BT is contributing £5.67m whilst the
CSW Broadband Project is contributing £4.45m – of which £3m is from Warwickshire with the
balance coming from other local authorities, with a further £4.45m from Government funds.
Approximately 40,000 additional premises should have access to superfast broadband and every
premise should be able to access minimum 2Mbps services by the end of this phase of the project9.
In February 2014, it was announced that the CSW Broadband Project would receive £3.68m from the
additional £250m announced in June 2013 to extend the reach of superfast broadband10. In June
2014, the Government offered the CSW Broadband Project an additional £6m, subject to local
match-funding being available; potential match funding options are currently being explored by the
5 https://www.gov.uk/government/news/363-million-for-broadband-roll-out-in-england-and-scotland 6 https://www.gov.uk/government/news/14-million-more-premises-to-get-superfast-broadband-after-250-million-capital-
investment 7 https://www.gov.uk/government/news/363-million-for-broadband-roll-out-in-england-and-scotland 8 http://news.warwickshire.gov.uk/blog/2013/06/07/multi-million-partnership-to-bring-superfast-broadband-to-91-per-
cent-of-homes-and-businesses-across-coventry-solihull-and-warwickshire/ 9 The rolling 12 month deployment plan for the CSW Superfast Broadband Project is available at
http://www.cswbroadband.org.uk/where-when/rolling-12-month-plan 10 https://www.gov.uk/government/news/250m-boost-taking-superfast-broadband-further-and-faster--251
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 4
http://www.cswbroadband.org.uk August 2014
CSW Superfast Broadband Project Team11. If successful, this will create a total fund of more than
£19m to extend superfast broadband provision across CSW beyond the 91% that will be reached by
the current roll-out.
State Aid: identifying additional intervention areas
The European Commission (EC) requires that public investment only occurs in ‘white areas’: areas
where there is no current, or planned (i.e. within the next three years) deployment of either basic or
superfast broadband. As part of the procurement process an application to invest in these areas,
following public consultation, must be submitted to the Department for Media Culture and Sport
(DCMS).
The EC Guidelines12 distinguish between geographic areas on the basis of current or planned (next 3
years) broadband infrastructures thus:
• ‘White’ areas are those in which there is no qualifying broadband infrastructure and none is
likely to be developed in the near future (within 3 years);
• ‘Grey’ areas are those where one network operator has a qualifying presence and another
qualifying network is unlikely to be developed in the near future; and
• ‘Black’ areas are those where there are, or there will be in the near future, at least two
qualifying network operators.
The geographic mapping of White/Grey/Black areas has been carried out separately for both Basic
Broadband and Superfast Broadband. The criteria used to classify areas as black, grey or white in
relation to basic and NGA broadband coverage are set out as an appendix to this document. In
accordance with the EC Decision on the National Broadband Scheme for the UK13, proposed NGA
and Basic Broadband Intervention Areas have been defined to target NGA ‘White’ areas and Basic
Broadband ‘White’ areas, respectively.
This document provides an overview of the CSW Superfast Broadband Project and sets its objectives
against the wider context of broadband initiatives, policies and frameworks within the UK. The
Public Consultation follows on from our previous Open Market Review conducted in June-July 2014,
where broadband suppliers were invited to share their plans for future investment in broadband
infrastructure across Coventry, Solihull and Warwickshire over the next three years. The information
from this review has informed our understanding, as set out in this document, of the extent of
existing broadband provision across the three local authorities and all known future developments
by the telecoms market to deploy superfast broadband in these areas (see section 8), both solely
commercially funded deployments and deployments subsidised by the CSW Superfast Broadband
Project.
It is not the intention of Warwickshire County Council to duplicate or compete with the provision of
services by operators who may be operating outside of the on-going project, nor is it the intention to
11 The additional funding options being explored for the CSW Superfast Broadband Project are described in the June 2014
project newsletter available at http://www.cswbroadband.org.uk/newsletter-june-2014/ 12 http://eur-lex.europa.eu/LexUriServ/LexUriServ.do?uri=OJ:C:2013:025:0001:0026:EN:PDF 13 http://ec.europa.eu/competition/state_aid/cases/243212/243212_1387832_172_1.pdf
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 5
http://www.cswbroadband.org.uk August 2014
provide subsidy where it is not needed. This consultation therefore seeks additional feedback from
broadband providers as to whether there will be any changes to basic and superfast broadband
provision as shown in this document, due to additional rollouts through private investment. It is
imperative that any operator already delivering or planning to deliver services that exceed what has
been detailed in this document make their plans known to us, if they have not already done so via
the previous Open Market Review.
This consultation also seeks feedback from local residents and businesses in relation to the proposed
intervention areas for the project, particularly in relation to:
any broadband not- or slow-spots (i.e., areas unable to access minimum 2Mbps services) not
included in the proposed intervention areas, or the reverse; i.e., locations listed as
broadband not- or slow-spots, when 2Mbps or faster services are in fact available;
any locations where the current availability of superfast services (above 24Mbps) as
described in this document is known to be incorrect (i.e. areas described as having superfast
services but where these are in fact unavailable, or the reverse);
any proposed intervention areas where plans are in place to deliver minimum 2Mbps and/or
superfast broadband services but these were not reported as part of the previous Open
Market Review.
How to respond
If you are a provider of broadband services and wish to make us aware of your plans to offer services
in the proposed intervention areas set out in section 8 of this document, please send your response
to this consultation to [email protected] identifying them as CSW Broadband
Public Consultation in the subject, or send them via post to
CSW Broadband Project
Warwickshire County Council
Wedgnock House
Wedgnock Lane
Warwickshire
CV34 5AP
Please address the request for information from suppliers set out in section 10 of this document
Comments from local businesses and residents in relation to these proposals are also welcome to
the email and postal addresses above. If you are responding as a member of the public and/or on
behalf of a business or other organisation, please also complete our residential and/or business
broadband surveys at:
http://www.cswbroadband.org.uk
If you work or run a business from home please complete both surveys.
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 6
http://www.cswbroadband.org.uk August 2014
A link to this State Aid public consultation is also available on the BDUK website at:
https://www.gov.uk/broadband-delivery-uk
1 Introduction
The CSW Superfast Broadband Project aims to deliver the Government’s 2017 targets, as set out in
Britain’s Superfast Broadband Future14 (December 2010) and Investing in Britain’s Future15 (June
2013), that every premise should be able to access broadband at speeds of at least 2Mbps and that
superfast broadband (defined as providing more than 24Mbps) should be available to at least 95% of
premises in each local authority area. The intention is to procure network services that:
are available to any Internet service provider so that it can use to deliver retail superfast
broadband services to residential and business customers;
can assist businesses by helping to connect premises and mobile workers to the services
they require;
any community network can use for backhaul.
Our future aspirations are in keeping with the European Commission’s 2020 targets that fast
broadband coverage at 30Mbps should be available to all EU citizens, with at least half European
households subscribing to broadband access at 100Mbps16. The project will endeavour to deliver
infrastructure and services that can scale appropriately to keep pace with the increasing bandwidth
demands of new applications and services.
The project aims to subsidise a private company to deploy network infrastructure to provide a
wholesale service, to many different ISPs, into areas where it is not financially viable. Hence it is
imperative that areas that are selected for this intervention, which is classified as State Aid by the
EU, do not cover an area where any private company or community enterprise plans to build an
equivalent facility. This would clearly be a waste of public money and would undermine the viability
of the other network. We aim to make every effort to minimise the risk of this happening and this
consultation, together with the previous Open Market Review in June-July 2014, are key steps in
that process.
Warwickshire County Council is acting as lead authority for the initiative. Coventry City Council and
Solihull Metropolitan Borough Council are supporting partners. The project is formally supported by
Coventry and Warwickshire Local Enterprise Partnership. The Greater Birmingham and Solihull Local
Enterprise Partnership also support Solihull Metropolitan Borough Council’s inclusion in this
Coventry, Solihull and Warwickshire Partnership.
Other partners we are working with:
14 https://www.gov.uk/government/publications/britains-superfast-broadband-future 15
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/209279/PU1524_IUK_new_template.pdf 16 http://ec.europa.eu/unitedkingdom/press/press_releases/2010/pr1095_en.htm
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 7
http://www.cswbroadband.org.uk August 2014
North Warwickshire Borough
Nuneaton and Bedworth Borough Council
Rugby Borough Council
Stratford-on-Avon District Council
Warwick District Council
Community Groups via Community Forums and Parish Councils
Coventry and Warwickshire Chamber of Commerce
Coventry, Solihull and Warwickshire Federation of Small Businesses
2 The case for investment in CSW
Despite restricted availability and late roll-out of current generation broadband, take-up within
Warwickshire is above average with Coventry and Solihull being average. This is indicative of a
strong case for investment in superfast broadband across the sub-region which our demand
registration and stimulation activities are promoting further.
Coventry City Council, Solihull Metropolitan Borough Council and Warwickshire County Council are
committed to transforming the delivery of public services and online access via superfast broadband
is instrumental to this. Effective online public services will help to drive demand for and take-up of
superfast broadband.
All three upper tier local authorities have a strong track record of successfully procuring and
implementing wide area network infrastructure. Demand for and usage of broadband by public
sector sites (for example, schools, local government and health) continues to increase year on year.
This expected future demand for broadband will provide a guaranteed return for investors, above
and beyond the take-up of superfast services by new domestic and business customers.
The decline of traditional manufacturing means the knowledge economy is increasingly important to
the sub-region’s economic growth. The knowledge sector has experienced phenomenal growth in
the last five years, which has contributed significantly to the local economy and is also leading to
increased employment in the region. There are 1,300 ICT and software companies in the CSW sub-
region, concentrated in six major science parks located in and around the CSW Software Triangle.
These companies represent a vibrant base of high growth indigenous companies underwritten by
many of the world’s leading global ICT and software companies. The importance of a world-class
communications infrastructure to this sector’s continued growth is clearly apparent.
3 The project area
Coventry is at the heart of the sub-region, and is surrounded by Solihull to the west, and the five
districts of Warwickshire – North Warwickshire, Nuneaton & Bedworth, Stratford-Upon-Avon,
Warwick and Rugby.
Solihull is one of the seven West Midlands Metropolitan Boroughs, located between Birmingham (to
the west) and Coventry and Warwickshire (to the east). It covers an area of almost 18,000 hectares,
two-thirds of which is rural farmland. Much of the rural area is designated green belt. Solihull has
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 8
http://www.cswbroadband.org.uk August 2014
two main built-up areas, in the north around Chelmsley Wood and in the south-west around Solihull
town.
Warwickshire is generally more rural in nature, interspersed with a variety of market towns and
major centres, such as Stratford-on-Avon and Rugby. Around one third of the population live in rural
areas.
The project encompasses all of the areas encompassed by Coventry City Council, Solihull
Metropolitan Borough Council and Warwickshire County Council. We are working closely with
neighbouring authorities to co-ordinate with their broadband procurement activities. Our seven
neighbouring local authorities are:
Staffordshire
Leicestershire
Northamptonshire
Oxfordshire
Gloucestershire
Worcestershire
Birmingham
In addition, the northern tip of Warwickshire is only 3 miles (5 km) from the Derbyshire border.
We have provided coverage maps and a list of postcodes for the sub-region17. Our data is derived
from a number of sources identified over the course of the project to date, including operators’ roll-
out plans, crowd-sourced information18 and data from Broadband Delivery UK (BDUK). Whilst we
believe we have built up a good overall understanding of coverage across our region, we recognise
that this is a complex and fast-changing area so any further input is most welcome.
4 Broadband services in CSW
a) Current provision in CSW
CSW as a whole is reasonably well provided for in terms of current generation broadband. However
there are a number of slow-spots and not-spots where speeds are less than 2Mbps or where no
broadband services are available at all. The majority of these are in CSW’s rural areas. The gap
between CSW’s urban and rural areas is set to increase as service providers’ next generation
broadband upgrade plans focus on CSW’s densely populated urban areas.
This is the key issue facing CSW: how to enable the transition from current to next generation
services in a way that benefits as many people as possible. We want to ensure superfast broadband
services are extended as far into our rural areas as our funding allows, in accordance with the
Government’s targets that superfast services should be available to at least 95% of premises by 2017
and 99% by 2018.
17 http://www.cswbroadband.org.uk/procurement2014 18 http://4sfb.crowdmap.com
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 9
http://www.cswbroadband.org.uk August 2014
We therefore need to identify and focus on the areas broadband providers will not reach without
additional subsidy. Such instances of market failure arise when costs are too high (chiefly because of
distance) and returns are too low (because of the limited number of potential subscribers) to
support the provision of affordable broadband services.
The current CSW superfast broadband roll-out will ensure that around 40,000 additional premises
will have access to superfast broadband; in total 91% of the area’s homes and businesses will be able
to access superfast broadband by the end of this stage of the project. Historical information on the
situation prior to the CSW Superfast Broadband Project roll-out is available in the CSW Local
Broadband Plan19, which was approved in March 2012 and published in May 2012.
The first communities to benefit from the current CSW Superfast Broadband roll-out were
announced in February 201420: from Spring 2014, superfast fibre-based broadband became available
for the first time in parts of Alderminster, Fillongley, Henley-in-Arden, Kineton, Quinton, Long
Marston, Snitterfield and Welford-on-Avon. In addition, fibre will also ‘go live’ in areas of Stratford-
upon-Avon and Wellesbourne not already enabled by any commercial rollout. All CSW premises will
be able to access a minimum of 2Mbps service by the end of the current roll-out.
A rolling 12 month deployment plan is available on the CSW Superfast Broadband Project website21.
The additional £3.68m from central Government announced in February 2014 will be used in
combination with locally matched funding to extend superfast coverage to at least 95% of CSW
premises by 2017 and 99% by 2018. In June 2014 the CSW Broadband Project was offered an
additional £6m central Government funding, subject to local match-funding being available;
potential funding options are currently being explored by the CSW Superfast Broadband Project
Team22.
b) Broadband provision in CSW by 2017
Following the Open Market Review conducted in June-July 2014 we are able to publish preliminary
results which show the areas that the providers have committed to cover by 2017 using their own
funds. BDUK funds will be used to extend the coverage beyond this by investing in the White areas.
The following tables show the expected availability of superfast and basic broadband services (via
solely commercial deployments and deployments subsidised by the CSW Superfast Broadband
Project) throughout the region by 2017:
Superfast Broadband Area type No. of premises % of premises
Black – two or more providers 211,483 43%
Grey – one provider 233,228 48%
19 http://www.cswbroadband.org.uk/local-broadband-plan-redacted/ 20 http://www.cswbroadband.org.uk/first-communities-to-benefit-from-multi-million-pound-coventry-solihull-
warwickshire-superfast-broadband-programme-are-announced/ 21 http://www.cswbroadband.org.uk/where-when/rolling-12-month-plan/ 22 The additional funding being sought for the CSW Superfast Broadband Project are described in the June 2014 project
newsletter available at http://www.cswbroadband.org.uk/newsletter-june-2014/
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 10
http://www.cswbroadband.org.uk August 2014
White 45,313 9%
Total 490,024 100%
Basic Broadband Area type No. of premises % of premises
Black – two or more providers 251,153 51%
Grey – one provider 232,983 48%
White 5,888 1%
Total 490,024 100%
5 Project approach
Our funding will be used to subsidise the successful bidder to extend the reach of superfast
broadband services into such areas, staged appropriately against implementation and performance.
The wholesale assets created through this investment will be owned and maintained by the
successful bidder and will be available to any provider to support the delivery of retail broadband
services. Our approach acknowledges the Government’s intention that superfast broadband is
available as widely as possible, reaching at least 95% of premises in each local authority area by 2017
and 99% by 2018.
We will as far as possible seek to ensure that the infrastructure put in place by the successful bidder
can scale to benefit from any additional funding made available in the future to support both the
further roll-out of superfast broadband and higher speeds. Our focus will therefore be on
developing the underlying broadband infrastructure across CSW, to ensure we have a roadmap for
improving both fixed and mobile/wireless broadband coverage and performance over the longer
term post 2017-18. The new services offered as a result of this intervention will be required to be
comparable in terms of pricing, performance and contract duration to that already available
elsewhere.
Looking beyond 2017-18, our intention is to ensure that as much funding as possible contributes
towards building the infrastructure required to reach the 2020 Digital Agenda for Europe targets of
universal availability of 30Mbps and 50% take-up of 100Mbps services. We will seek to minimise the
amount of funding allocated to solutions of last resort, thereby maximising the amount of funding
available to support the roll-out of superfast services in a way that will keep pace with the region’s
future requirements for speed, performance and availability.
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 11
http://www.cswbroadband.org.uk August 2014
6 Procurement approach
We are planning to deliver the CSW Local Broadband Plan by using a gap funding approach to
leverage further investment by commercial operators. A further mini-competition will be conducted
under the BDUK Framework to award a second Local Call-off Contract to a supplier to deliver
extended coverage through the additional funding.
The capital grants to the successful commercial operator (with further matched investment by the
operator) will tip the business case for extending superfast broadband from the level of penetration
that is otherwise likely to be achieved by the market alone to 95% of premises in each of the three
local authority areas by 2017. Our plan assumes a platform across the sub-region to enable
competitive retail service provision to Coventry, Solihull and Warwickshire. The assets funded
through this investment will be owned and maintained by the successful bidder.
Areas that do not currently form part of broadband providers published plans but which we believe
will be covered by further investment from the private sector will fall outside of our procurement.
Respondents should submit evidence to the contrary if they believe such areas will not be reached
by commercial deployments.
7 Purpose of this consultation
This public consultation with suppliers is being undertaken in accordance with the European
Commission (EC) guidelines for state aid approval23. The EC requires that the public sector only
invests in areas where there is demonstrably no current or planned (i.e. within the next three years)
investment in broadband. These are termed white areas, those where it is appropriate to use public
subsidy to support the roll-out of broadband infrastructure. Other areas are termed either grey (one
superfast broadband operator) or black (two or more superfast broadband operators). As part of
the procurement process an application to invest in white areas, following public consultation, must
be submitted to the Department for Media Culture and Sport (DCMS).
We have previously conducted an Open Market Review during June and July 2014, where we invited
suppliers to share with us information on their plans for further investment in broadband
infrastructure across Coventry, Solihull and Warwickshire over the next three years. This
information has determined the intervention areas set out in section 8 of this document: these are
the areas we propose to use our funding to support the deployment of broadband infrastructure by
the private sector. We are also inviting feedback from residents and businesses across the sub-
region on our proposed intervention areas and plans. We are particularly interested in feedback in
relation to:
any broadband not- or slow-spots (i.e., areas unable to access minimum 2Mbps services) not
included in the proposed intervention areas, or the reverse; i.e., locations listed as
broadband not- or slow-spots, when 2Mbps or faster services are in fact available;
any locations where the current availability of superfast services (above 24Mbps) as
described in this document is known to be incorrect (i.e. areas described as having superfast
services but where these are in fact unavailable, or the reverse);
23 http://eur-lex.europa.eu/LexUriServ/LexUriServ.do?uri=OJ:C:2009:235:0007:0025:EN:PDF
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 12
http://www.cswbroadband.org.uk August 2014
any proposed intervention areas where plans are in place to deliver minimum 2Mbps and/or
superfast broadband services but these were not reported as part of the previous Open
Market Review.
The information gathered from this consultation will also be an input into our invitation to tender.
As such, the information provided by broadband service providers in support of planned investments
must be robust and supported by detailed evidence. Please refer to section 10 for information on
how broadband service providers should respond to this consultation.
It is imperative that any operator already delivering or planning to deliver services that exceed what
has been detailed in this document make their plans known to Warwickshire County Council as lead
authority for the sub-region. It is not Warwickshire County Councils’ intention to duplicate or
compete with the provision of services by operators who may be operating outside of the on-going
procurement, nor is it our intention to provide subsidy where it is not needed.
8 Proposed intervention areas
We have provided coverage maps and a list of postcodes for our proposed intervention area which
you can access at:
http://www.cswbroadband.org.uk/suppliers/procurement
The mapping presented here was developed through our previous Open Market Review (OMR) in
June-July 2014. Details of the OMR were sent to all known broadband infrastructure and internet
providers in the CSW sub-region. The maps, which are fully zoomable, illustrate our current
assessment of the State Aid status (white, grey, black) for each postcode area in the region – pink
has been chosen to represent the “white” areas. The boundary of the region is shown by a thick red
line. The coloured dots on the map represent both business and residential premises, with the
different colours highlighting our current estimate of the distance of the premise from existing
infrastructure (green is near, hence good, red is far away, hence bad).
You will see this evolve as we gather more information from people filling in surveys and
crowdsourcing the existing infrastructure.
The postcode list covers all postcodes in the mapped area.
9 Working with businesses across CSW
As part of the councils’ procurement, engagement with local companies is a priority. Where possible
we want to encourage the use of local companies to form part of the supply chain for broadband
across the three councils. If you represent a company that would like to participate and are happy
to have details passed on to the successful contractor, please register your interest at:
http://www.cswbroadband.org.uk/suppliers/supplier-registration
Please be aware that by providing this information you are allowing these details to be passed to the
successful contractor who may or may not choose to follow-up each expression of interest. This
register of potential suppliers is intended to assist our main contractor to use locally available
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 13
http://www.cswbroadband.org.uk August 2014
businesses and labour. Please note that inclusion in this register does not in any way imply that your
business has been approved or endorsed by the project or any of its member organisations, and
does not guarantee that you will receive work through the project.
10 Information required from broadband service providers
This public consultation is a formal request for information. The information provided will be used
to support a notification to the EC for approval of state aid.
Please provide details and supporting evidence of any current or planned investment in broadband
infrastructure (basic broadband and NGA broadband) in the proposed intervention area for the
project (see section 8).
In the case of planned investment, we are particularly interested in plans for the coming three years
(by date). However, any plans for years beyond that would also be of interest.
Any information provided should include but need not be limited to:
Detailed maps for basic broadband and NGA broadband showing the existing coverage and
separately maps detailing the planned investment in the basic broadband and NGA
infrastructure networks for at least the next three years;
Exact detail of premises passed or covered, i.e. postcodes (at a digit postcode level)
including information on the number of premises passed (in the case of a fixed network) or
covered and able to receive services (in the case of a wireless/satellite network);
A detailed description of the technology solution(s) deployed (or to be deployed) in
your broadband infrastructure, and where these claim to be NGA, demonstrate how
they meet the minimum standards as set-out in the BDUK NGA Technology
Guidelines24;
Description of the services/ products currently offered and separately those to be offered
within the next 3 years;
Installation and rental tariffs for those services/products clearly identifying whether they are
inclusive or exclusive of VAT;
Upload and download speeds typically experienced by end users and how these may vary
by factors such as distance, increased take-up or demand, contention, etc;
Appropriate indicators of quality of the service e.g. contention ratio or bandwidth allocation
per end user including any characteristics (eg latency, jitter) that are required to
support advanced services such as video conferencing or HD video streaming;
24
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/236341/NGA_Technology_Guidelines_3
00813.pdf
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 14
http://www.cswbroadband.org.uk August 2014
Evidence to substantiate actual or planned coverage claims, including business cases
and evidence of available funding to enable plans to be fulfilled.
Details and timing of roll-out for future investment including further investments
required to cope with future increases in take-up and demand; and
Confirmation from an authorised signatory that all information provided is of suitable
accuracy.
Please supplement with supporting evidence as you consider appropriate e.g. public websites.
Please note that the data you provide in your response will be treated as commercially confidential
to Warwickshire County Council25, albeit that it may be necessary to share some/all of your response
data with our professional advisors and/or DCMS/BDUK, Ofcom, BIS State Aid Branch and the
European Commission in the course of seeking State aid approval for our local broadband project. It
should also be noted that it is a state aid requirement to utilise this information to produce state aid
maps to define white, grey and black areas for basic and NGA broadband. These maps will be
published as part of the Public Consultation process and will be utilised to define the intervention
area. However, please note that these published maps will be assimilated utilising data from all
relevant operators and will not be directly attributed to a single source.
When an area is classified as eligible for intervention with State Aid (pink on the maps), it may not
guarantee future coverage as funding is predicated on reaching 95%/99% of premises with superfast
services. However, when an area is classified as currently having a service available (shown on the
maps as grey = one provider, or black = two or more providers) then it does mean that we are
definitely not able to intervene. Because of this we will need to see clear evidence of your financial
provision, the necessary approval being recorded from an appropriate authority in the company or
enterprise and an implementation plan. Clearly we do not want anyone to miss out so due diligence
is necessary here.
If you have any questions about the project or concerns about providing information then please
contact the CSW Broadband Project at [email protected] outlining your
concerns as we do not want to build over your planned deployment.
25 We are also subject to legal obligations to disclose information in certain limited circumstances.
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 15
http://www.cswbroadband.org.uk August 2014
11 Appendix
The following criteria have been used to classify areas into Basic Broadband and NGA
White/Grey/Black areas respectively.
For Basic Broadband, each postcode is turned Grey if:
BT estimate that all premises in the postcode can receive (or are planned to receive) a
broadband speed >2Mbps;
OR, if Virgin Media serve 90% or more of premises within the postcode;
OR, if it is an area served by an alternative fixed infrastructure provider with Access Line
Speeds >2Mbps;
OR, if a wireless service or other qualifying technology is available at >2Mbps to all premises
in the postcode.
Each postcode is turned Black for Basic Broadband if it satisfies at least two of these conditions. All
other postcodes remain White.
For NGA, each postcode is turned Grey if:
BT has upgraded the network infrastructure serving the area AND ALL premises within the
postcode have an estimated (VDSL2 for FTTC) Access Line Speed of >15Mbps;
OR, if Virgin Media serve 90% or more of premises within a postcode;
OR, if it is in an area that is served by an alternative fibre-based, NGA fixed wireless or other
qualifying technology that meets the requirements of the BDUK NGA Technology
Guidelines26.
Each postcode is turned Black for NGA if it satisfies at least two of these conditions. All other
postcodes remain White.
Where 2 operators have declared partial coverage of premises within a postcode, a complete
overlap of coverage is assumed, e.g. if a postcode contains 30 premises and operator A serves 10
premises and operator B serves 15 premises with Superfast Broadband, 15 premises are considered
to be NGA white. This assumption aligns with observations from sample testing of suppliers’ online
availability checkers and aims to ensure that no premise is left behind in the objective to achieve full
Superfast Broadband availability by the end of 2017.
The priority for the Council will be to use the available public funding intervention to
provide a ‘step change’ in broadband capability for premises currently getting relatively
slow broadband speeds (< 15Mbps). Therefore, in the first instance, the focus of the
26
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/236341/NGA_Technology_Guidelines_3
00813.pdf
CSW Superfast Broadband Extension Programme – Public Consultation P a g e | 16
http://www.cswbroadband.org.uk August 2014
forthcoming procurement under the BDUK Framework will be the NGA White areas
identified in the attached State Aid Map. However, the Council reserves the right to
consider extending intervention to the areas classified as “Conditional White” in the event
that the risks of these premises not achieving Superfast Broadband is verified.