Summer Internship Report
-
Upload
mihir-rambhia -
Category
Documents
-
view
79 -
download
11
description
Transcript of Summer Internship Report
`
Prepared by:
SUMMER INTERNSHIP REPORT
JULY 2014
Mihir Rambhia
3rd Year Civil Engineering
Pandit Deendayal Petroleum University
Gandhinagar
Hardik Soni
3rd Year Civil Engineering
Pandit Deendayal Petroleum University
Gandhinagar
MIHIR
2
DECLARATION
This is to declare that the report submitted regarding the Summer
Internship undergone in the project entitled “FEASIBILITY ANALYSIS OF
USING ALUMINIUM FORMWORK FOR RESIDENTIAL PROJECTS” is a
bonafide work carried out by us, under the guidance of Mr. Aniket Save,
Managing Director, Dan Aluform Consultancy Limited and Mr. Nilesh
Nikam, Design Head, Dan Aluform Consultancy Limited.
Further, we declare that the data and information collected
during our Summer Internship will not been submitted or used
anywhere else.
Mihir Rambhia
3rd Year Civil Engineering,
Pandit Deendayal Petroleum University,
Gandhinagar.
Hardik Soni
3rd Year Civil Engineering,
Pandit Deendayal Petroleum University,
Gandhinagar.
MIHIR
3
ACKNOWLEDGEMENT
This training owes its completion to the guidance and contributions of
many without whose help it would not have been possible for us to learn and
understand so many things.
We are truly thankful to DAN ALUFORM CONSULTANCY LIMITED for
providing us with the opportunity to undertake our Summer Training.
We would like to convey our sincere thanks to Mr. Aniket Save,
Managing Director, DAN for his constant support which helped us in achieving
our learning objectives successfully. Also, we would like to extend our gratitude
to Mr. Nilesh Nikam, Design Head who guided and encouraged us throughout
the summer training and imparted in-depth knowledge of the project.
Also we would like to convey our special thanks to Mr. Dayanand
Poojari, Production Head for devoting his precious time to assist and advise us
whenever we needed help.
We are also highly indebted to Mr. Imran Shaikh, Officer, Accounts &
Admin for generously helping us throughout the training period.
The Managers, Engineers and the support staff working at DAN have
always extended their warm support and helped us in every possible way.
Entire staff is so friendly and cheerful that work stress was never experienced.
So we extend our sincere thanks to each and every one of them.
MIHIR
4
PROJECT TITLE – FEASIBILITY ANALYSIS
OF USING ALUMINIUM FORMWORK FOR
RESIDENTIAL PROJECTS.
Under the guidance of:
Mr. Aniket Save, Managing Director, DAN
Mr. Nilesh Nikam, Design Head, DAN
Mr. Dayanand Poojari, Production Head, DAN
MIHIR
5
CONTENTS
1. SUMMARY ...................................................................................................... 6
1.1 BACKGROUND .............................................................................................. 6
1.2 OBJECTIVE OF THE STUDY ......................................................................... 6
2. COMPANY PROFILE ...................................................................................... 7
2.1. BACKGROUND OF DAN ALUFORM ............................................................. 7
2.2. QUALITY POLICY .......................................................................................... 8
2.3. QUALITY OBJECTIVES ................................................................................. 8
2.4. MANAGEMENT HIERARCHY ........................................................................ 8
2.5. PROJECTS COMPLETED.............................................................................. 9
2.6. SERVICES OFFERED .................................................................................... 9
3. JOB DESCRIPTION ...................................................................................... 10
3.1. ROLES AND RESPONSIBILITIES ................................................................ 10
3.2. ESSENTIAL DUTIES .................................................................................... 10
3.3. ANCILLARY DUTIES .................................................................................... 10
4. PROJECT ..................................................................................................... 11
4.1 PROJECT RATIONALE ................................................................................ 11
4.2 WHAT IS FORMWORK? .............................................................................. 11
4.3 LOADS ACTING ON FORMWORK .............................................................. 12
4.4 TYPES OF FORMWORK ............................................................................. 13
4.5 ALUMINIUM FORMWORK SYSTEM ............................................................ 13
4.6 FORMWORK COMPONENTS ...................................................................... 15
4.7 PRODUCTION LINE ..................................................................................... 21
4.8 ADVANTAGES OF THE SYSTEM ................................................................ 23
4.9 WORK FLOWCHART ................................................................................... 23
4.10 METHODOLOGY OF CALCULATION .......................................................... 24
4.11 CALCULATIONS FOR ALUMINIUM FORMWORK SYSTEM ....................... 25
4.12 CALCULATIONS FOR TRADITIONAL FORMWORK SYSTEM .................... 31
5. COMPARATIVE ANALYSIS .......................................................................... 42
5.1. COST COMPARISON .................................................................................. 42
5.2. CONCLUSION .............................................................................................. 44
6. ANNEXURES ................................................................................................ 45
7. REFERENCES .............................................................................................. 71
MIHIR
6
1. SUMMARY
1.1 BACKGROUND The report has been prepared to summarize the things learnt during the
summer internship undertaken at DAN. The primary goal of this
internship program is to provide an opportunity for translation of
theoretical concepts in real life situation. This practical exposure helps
the students in refining their knowledge and exploring there area of
interest. For this, students are placed in enterprises, organizations,
research institutions as well as development projects.
1.2 OBJECTIVE OF THE STUDY To enhance our academic knowledge by working on real time
projects.
To gain practical experience of working in a corporate environment.
To improve our understanding and know-how regarding Aluminium
formwork technology.
To find out whether Aluminium formwork is an economic viable
solution for speedy construction or not.
Improving our know-how regarding the technologies available for
constructing Low Cost Houses and effective solutions for delivering
Mass Housing Projects on time.
MIHIR
7
2. COMPANY PROFILE
2.1. BACKGROUND OF DAN ALUFORM
The DAN Aluminium Formwork System for concreting is
probably the most versatile modern construction system. Unlike other
systems it is equally suited to both high and low rise construction.
Specifically designed to allow the rapid construction of
multiple unit projects at optimum productivity, the DAN Aluminium
Formwork can be used for a broad range of applications, from
straightforward panels to more complicated structures involving bay
windows, stairs and A/C hoods.
The degree of pre engineering and inherent simplicity of
the DAN Aluminium Formwork enables unskilled labour to be used.
Every component is light enough to be handled by one operative,
minimizing the need for heavy lifting equipment.
MIHIR
8
2.2. QUALITY POLICY
DAN Aluform consultancy service to achieve customer satisfaction by
delivering quality product in specified time. We are committed for
continual improvement to achieve TOTAL QUALITY MANAGEMENT.
2.3. QUALITY OBJECTIVES
To deliver quality product by adopting set specifications.
To achieve customer satisfaction through cost-effective and timely
completion.
To motivate and train staff for continual improvement of quality
standards.
2.4. MANAGEMENT HIERARCHY
Managing Director
Accounts & Admin Officer
Marketing Officer
Production Head
Production Supervisor
Welders and Fitters
Unskilled Worker
Design Head
Draftsmen and Quantity Surveyor
Site
Technician
MIHIR
9
2.5. PROJECTS COMPLETED
Aliens Space Station – I ,
Hyderabad
BSUP, Nasik Municipal
Corporation
Veda by Omkar-phase I
Prakashwadi Andheri, SRA
Project by Omkar
MAN Opus at Mira Road
EWS Housing - Thipasandra
BSUP Housing by Pawar
Patkar
Veda by Omkar-phase II
EWS Housing by AMC
EWS Housing - Gunjur
DSIIDC Project - Substructure
DSIIDC Project - Superstructure I
The Jewel of NOIDA
EWS Housing at Kaniminike
EWS Housing at Gunjur-II
VERTU, Wadala
Vishrani, Matunga
2.6. SERVICES OFFERED
END TO END FORMWORK SOLUTIONS
DESIGNING
MANUFACTURING
ONSITE ERECTION
REFURBISHING
MIHIR
10
3. JOB DESCRIPTION
3.1. ROLES AND RESPONSIBILITIES
1. Understanding Aluminium Formwork system and its applicability
for mass housing and residential projects.
2. To learn how the system is designed, produced and erected on
construction site.
3. Collection of data from DAN-Chinchani project for performing a
comparative analysis between Plywood formwork system
(referred as traditional formwork system) and aluminium
formwork system.
3.2. ESSENTIAL DUTIES
1. Discussion with production engineers and site supervisors for
understanding the system.
2. Calculating the quantity of formwork required for any project.
3. Estimating the quantity of materials required for any project.
4. Perform a study between Aluminium Formwork System and
Traditional formwork for an identical plan.
5. Draft a comparative study report of the respective project clearly
describing advantages, disadvantages and limitations of this
system.
3.3. ANCILLARY DUTIES
1. Observing and interacting with employees working at Production
unit.
2. Understanding how day to day issues are handled in an industry.
MIHIR
11
4. PROJECT
4.1 PROJECT RATIONALE
Objective: The objective of this project is to examine the financial
viability and feasibility of using Aluminium formwork system for different
residential projects. The project comprises of cost comparative study
between projects constructed with traditional formwork system vs with
aluminium formwork system.
Scope: The scope of the study includes the following activities:
Different types of formwork system.
Aluminium formwork system, its designing, production and
erection.
Quantity of formwork required by any project.
Cost estimation for constructing any project, including material,
labour and formwork cost.
Assess major advantages of using Aluminium formwork system in
terms of savings in money, time and improved quality.
4.2 WHAT IS FORMWORK?
Formwork is the term given to either temporary or permanent moulds
into which concrete or similar materials are poured.
Forms or moulds or shutters are the receptacles in which concrete is
placed, so that it will have desired shape or outline when hardened. Once
concrete develops the adequate strength to support its own weight they
can be taken out.
MIHIR
12
When concrete is placed, it is in plastic state. It requires to be supported
by temporary supports and castings of desired shape till it becomes
sufficiently strong to support its own weight. This temporary casting is
known as formwork or forms or shuttering or false work.
4.3 LOADS ACTING ON FORMWORK
During the construction formwork has to bear the following loads:
Self-weight
Weight of concrete
Live load due to labour
Impact load due to pouring of concrete
Impact due to workmen working on it
Vibration caused due to vibrators used for compaction of the
concrete
Thus, proper designing of formwork system is an essential and important
part of any building project.
For the design of planks and joists in bending & shear, a live load including
the impact may be taken as 370kg/m². It is however, usual to work with
a small factor of safety in the design of formwork. The surfaces of
formwork should be dressed in such a manner that after deflection due
to weight of concrete and reinforcement, the surface remains horizontal,
or as desired by the designer. The sheathing with full live load of 370
kg/m² should not deflect more than 0.25 cm and the joists with 200kg/m²
of live load should not deflect more than 0.25cm.
In the design of formwork for columns or walls, the hydrostatic pressure
of the concrete should be taken into account. This pressure depends
upon the quantity of water in the concrete, rate of pouring and the
temperature
MIHIR
13
4.4 TYPES OF FORMWORK
Timber formwork
Plywood formwork
Steel formwork
Aluminium formwork
Composite formwork
Plastic formwork
4.5 ALUMINIUM FORMWORK SYSTEM
The basic element of Aluminium Formwork System is the panel made
from a high strength aluminium alloy. This aluminium panel is produced
from specially designed extruded sections welded to 4 mm thick sheet to
form a robust component framework. This produces a lightweight panel
with an excellent stiffness to weight ratio, yielding minimal deflections
under concrete loading. Panels are manufactured in standard sizes with
non-standard elements made in the sizes and shapes to suit the
requirements of specific projects.
The panels are held in position by a simple pin and wedge arrangement
system that passes through holes in the outside rib of each panel. The
panel fits precisely, securely and requires no bracing. The walls are held
together with high strength wall ties, while the decks are supported by
beams and props.
Since the equipment is made of aluminium, it has sections that are large
enough to be effective, yet light enough in the weight to be handled by a
single worker. Individual workers can handle all the elements necessary
for forming the system with no requirement for heavy lifting equipment
or skilled labour.
MIHIR
14
By ensuring repetition of work tasks on daily basis it is possible for the
system to bring assembly line techniques to construction site and to
ensure quality work, by unskilled or semi-skilled workers. Trial erection
of the formwork is carried out in factory conditions which ensure that all
components are correctly manufactured and no components are missed
out. Also, they are numbered and packed in such a manner so as to
enable easy site erection and dismantling.
The steel reinforcement is placed within the formwork as they are being
erected and concrete is poured into the moulds. When the concrete is
set according to the required strength, the moulds are dismantled. Its
advantages over the traditional construction method include, low skill
requirement, speedy construction, low maintenance, durable structure
and less cost.
MIHIR
15
4.6 FORMWORK COMPONENTS
1. Wall Components:
1.1 Standard Wall Panel – It forms the face of the wall. It is an
extruded aluminium sheet precisely cut to the dimension to fit
the exact size of the wall.
1.2 Rocker – It is a supporting component of the wall panel. It is L-
shaped panel having allotment holes for stub pin.
1.3 Kicker – It forms the wall face at the top of the panels and acts
as a ledge to support.
MIHIR
16
1.4 Stub pin – It helps in joining two wall panels through joints made
as per the design.
2. Slab Components:
2.1 Deck panel – It forms the horizontal surface for casting of slabs.
It will be used to support the concrete weight during concrete
pouring and casting.
2.2 Deck prop – It forms a V – shaped prop head. It supports the
deck and bears the load coming on the deck panel. The pipe
support will be placed under the prop head.
MIHIR
17
2.3 Prop length – It is the length of the prop. Total length depends
on the floor to floor height of the project.
2.4 Deck Mid beam – Used to join the prop heads, the middle beam
supports the slab panels.
2.5 Soffit length (Slab Corner) – It provides support to the edge of
the deck panels at their perimeter of the room. It will act as a
connection between wall panel and slab panel
MIHIR
18
2.6 Deck beam bar – It is the deck for the beam. The component
supports the deck and beam.
3. Beam Components:
3.1 Beam side panel – It forms the side of the beams. It is a
rectangular structure and is cut according to the size of the beam.
3.2 Prop head for Soffit beam – It forms the soffit beam. It is a V-
shaped head for easy dislodging of the formwork.
MIHIR
19
3.3 Beam Soffit panel – It supports the soffit beam. It is a plain
rectangular structure of aluminium.
4. Other Components:
4.1 Internal Soffit corner (Slab in-corner) – It forms the internal
corner and act as a connection between the Wall panel and Slab
panel (inside).
4.2 External Soffit corner (Slab out-corner) – It forms the external
corner and act as a connection between the Wall panel and Slab
panel (outside).
MIHIR
20
4.3 External corner – It forms the external corner of the formwork
system.
4.4 Internal corner – It connects two pieces of vertical formwork
pieces at their exterior intersections.
MIHIR
21
4.7 PRODUCTION LINE
Raw Material
Cutting
Punching
MIHIR
22
Welding
Cleaning
Labeling
Packing &
Dispatch
MIHIR
23
4.8 ADVANTAGES OF THE SYSTEM
The Formwork is specifically designed to allow rapid construction on all types of architectural layouts.
Total system forms the complete concrete structure.
Custom designed to suit project requirements.
Unsurpassed construction speed.
High rigidity so deflection is within permissible limits.
High quality finish.
Cost effective for mass production.
Panels can be reused over 150 times.
Erected using unskilled labour.
Light weight, easy to handle.
Low waste generation.
High recycle ability makes it environment friendly.
4.9 WORK FLOWCHART
PROJECT DRAWING
COLLECTION
QUANTITY ESTIMATION BY
EXPERTS
QUOTATION GIVEN TO CLIENTS
FORMWORK DESIGN
PRODUCTION
ON SITE ERECTION UNDER
EXPERIENCED SUPERVISOR
MIHIR
24
4.10 METHODOLOGY OF CALCULATION
For performing a feasibility analysis of using Aluminium formwork system
for residential projects, we selected one project. Project details are as
follows:
Site Location – Chinchani
Client Name- Dan Aluform
Built up Area per flat – 514 ft2
Type of Building – G + 4
Total number of buildings to be constructed – 20
Total built up area of Project – 205456 sq2
Now for comparative study we will select the same plan but with
different type of structures. Load bearing structure is to be constructed
in case of Aluminium Formwork system and Framed Structure will be
constructed in case of Traditional Formwork system (Plywood).
Load bearing structure will be constructed entirely using concrete,
whereas framed structure will be constructed using concrete (for beams,
columns, chajja and slab) and brickwork for the walls.
All the assumptions in the calculations are taken after referring to
Schedule of Rates (2012-13) published by Maharashtra Jeevan
Pradhikaran for pune region (Refer – Annexure 15). Some assumptions
were also derived based on the experience of guide, reliable online and
offline sources and market research.
MIHIR
25
4.11 CALCULATIONS FOR ALUMINIUM FORMWORK SYSTEM
(Plan of the Building – Load Bearing Structure)
Data available from the plan are as follows:
Total Floors (Including G) - 5.00
Total Flats on each floor - 4.00
Total number of Buildings - 20.00
Type of Structure - Load Bearing
Type of Formwork - Aluminium
Built-up Area/ Flat 513.64 ft2
Built-up Area/ Floor 2054.56 ft2
Built-up Area/ Building 10272.80 ft2
Total Built up area of Project 205455.94 ft2
Length Width Height
Slab Thickness - 100.00 mm
Floor to Floor Height - 2900.00 mm
Living Entrance Door - 1000.00 2100.00 mm
Bedroom, Kitchen Door - 900.00 2100.00 mm
Bath, Toilet, WC Door - 750.00 2100.00 mm
Living to Passage Door - 1150.00 2100.00 mm
Living Window - 2000.00 1200.00 mm
Bedroom, Kitchen Window - 1200.00 1200.00 mm
MIHIR
26
Toilet, WC Ventilation - 600.00 900.00 mm
First & Second Floor Bed - 1200.00 2100.00 mm
Wall thickness 1 - 100.00 mm
Wall thickness 2 - 125.00 mm
Following assumptions were taken for performing detailed cost
calculation of the super structure:
Material Assumptions :
1) Grade of Concrete used = 20.00 Mpa
2) Cement : Sand : Aggregate = 1.00 1.50 3.00
3) Density of Cement = 1440.00 kg/m3
4) Cost of Cement bag - 53 Grade OPC = 310.00 INR/bag
Bag size = 50.00 kg
5) Cost of sand = 1150.00 INR/m3
6) Density of Aggregates = 1670.00 kg/m3
7) Cost of Aggregates = 850.00 INR/m3
8) % of Steel per unit volume of Concrete = 1.00 %
9) Density of steel = 7850.00 kg/m3
10) Cost of Steel = 48000.00 INR/tonne
Aluminium Formwork Cost Assumptions :
1 Cost of Aluminium Formwork = 8500.00 INR/m2
2 No of expected Repetitions = 100.00 times
3 Scrap Value = 130.00 INR/kg
4 Weight of Aluminium/m2 25.00 kg
5 Material Available for Scrap = 100.00 %
Assumptions- Formwork Accessories/Consumables:
Unit Loss
Assumption Unit Cost /Unit
1 Pin-Wedge 14.00 pcs/m2 2.00 % per floor 15.00
2 Wall ties 5.00 pcs/m2 2.00 % per floor 20.00
3 Shuttering Oil 0.06 litres/m2 100.00 % per floor 230.00
4 Corrugated Sheet 800.00 mm2 / tie 100.00 % per floor 60.00
5 PVC roll 100.00 mm / tie 100.00 % per floor 1.75
MIHIR
27
Cost Calculation Assumptions :
Electric Fitting Including Wiring @ % of Total Cost 10.00 %
Water Supply Fitting And Sanitary Fitting @ % of Total Cost 10.00 %
Sewerage @ % of Total Cost 5.00 %
Assumptions- Labour Cost:
Rate per
Formwork 150.00 sqm
Steel 8000.00 ton
Concrete 350.00 cum
Skilled 350.00 day
M/C 275.00 day
F/C 270.00 day
BHISHTI 270.00 day
Now taking this asusmptions detailed cost analysis of each component
was done.
1.1 Total quantity of wet concrete required for monolithically
concreting a unit floor of the building will be : 61 m3 (as per
calculations shown in Annexure -2 )
Thus total quantity of dry concrete required will be:
= 61 x 1.54
= 94 m3
So for producing this much concrete, the amount of materials that
will be required is as follows:
Materials required:
1 Cement = 492.22 Bags
2 Sand = 25.64 m3
3 Aggregates = 51.27 m3
4 Steel = 7.38 tonnes
(as per calculations shown in Annexure -3)
MIHIR
28
Thus, total cost of materials required for concreting will be as follows:
Sr No Material Material Required Cost of Material (INR) Total cost
1 Cement 492.22 310.00 152587.64
2 Sand 25.64 1000.00 25636.36
3 Aggregates 51.27 850.00 43581.82
4 Steel 7.38 48000.00 354192.00
Total Material cost of one floor = 575997.82
Total Material cost of project = 57599781.82
2.1 Total material cost for concreting of the super stucture of one floor
will be 5,75,998 INR
3.1 Total formwork quantity required for a unit floor will be : 1031 m2
(as per calculations shown in Annexure -1 )
4.1 Cost incurred due to formwork consumables for the entire project
will be 13,26,501 INR (as per calculations shown in Annexure – 4 )
5.1 Total cost incurred for the grouting of entire project will be 85,885
INR (as per calculations shown in Annexure -5 ).
6.1 Number of labours required for achieving a 4 Day Slab cycle:
Work Description Skilled M/C F/C BHISHTI
Concreting 3 6 18 12
Reinforcement 14
Formwork 8 24
Grouting 1
Thus, Labour Cost per day will be 26,833 INR (as per calculations
shown in Annexure -6 ).
MIHIR
29
Now for constructing this project, using one set of Aluminium formwork
system is suggested as follows:
Formwork Cycle Assumptions:
Initial set up time required 15.00 days
Floor cycle = 4.00 days
Section to Section work cycle = 2.00 days
No of Buildings to be constructed using Aluminium formwork = 20.00
Transfer time between building 8.00 days
Working days in Month 26.00 days
Set Proposal
Block Typical floor /
building
Total No of
buildings Repetition
Initial Set up time
(days)
Cycle time (days per
floor)
Time for Transfer
B/w Building (Days)
Total days
Months (Considering
Working days)
Set 1 Typical Floor 5 20 100 15 4 8 487 18.73
Total Built up Area
Formwork Quantity Required
Formwork Cost (Formwork +
Consumables) Cost/ft2
Estimated Scrap Value
Net Cost (Formwork + Consumables – Scrap)
Net Cost/ft2
205455.94 1030.63 10086837.91 49.09 3349540.74 6737297.17 32.79
Total sets required = 1.00
Repetitions per set = 100.00 times
Initial Expense = 8760337.33 INR
Total Expense = 6737297.17 INR
Time period required for completing the concrete work of all the Buildings = 487 days
Time period required for completing the concrete work of all the Buildings = 18.73 months
So with using one Aluminium formwork set concreting work of
superstructure of entire project can be completed within 487 days or
18.73 months.
Total formwork cost is estimated to be 32.79 INR/ft2 (Considering the
return on scrap).
MIHIR
30
TOTAL COST BREAK UP OF THE SUPERSTRUCTURE IS AS FOLLOWING:
Description Unit
Total Built up Area/ floor 2054.56 ft2
Formwork/Built-up ratio 5.40
Cost Calculations per Built up Area
Category Total
Concreting Material Cost 280.35 INR/ft2
Formwork Cost 42.64 INR/ft2
Formwork Consumables 6.46 INR/ft2
Grouting Material Cost 0.42 INR/ft2
Labour Cost 63.60 INR/ft2
Subtotal 393.47 INR/ft2
Electric Fitting Including Wiring @ 10% of Total Cost 39.35 INR/ft2
Water Supply Fitting And Sanitary Fitting @ 10% of Total Cost 39.35 INR/ft2
Sewerage @ 5% of Total Cost 19.67 INR/ft2
Total 491.83 INR/ft2
MIHIR
31
4.12 CALCULATIONS FOR TRADITIONAL FORMWORK SYSTEM
(Plan of the Building – Framed Structure)
Data available from the plan are as follows:
Total Floors (Including G) - 5.00
Total Flats on each floor - 4.00
Total number of Buildings - 20.00
Type of Structure - Framed Structure
Type of Formwork - Traditional
Built-up Area/ Flat 513.64 ft2
Built-up Area/ Floor 2054.56 ft2
Built-up Area/ Building 10272.80 ft2
Total Built up area of Project 205455.94 ft2
Length Width Height
Slab Thickness - 0.00 0.00 100.00 mm
Floor to Floor Height - 0.00 0.00 2900.00 mm
Living Entrance Door - 1000.00 0.00 2100.00 mm
Bedroom, Kitchen Door - 900.00 0.00 2100.00 mm
Bath, Toilet, WC Door - 750.00 0.00 2100.00 mm
Living to Passage Door - 1150.00 0.00 2100.00 mm
MIHIR
32
Living Window - 2000.00 0.00 1200.00 mm
Bedroom, Kitchen Window - 1200.00 0.00 1200.00 mm
Toilet, WC Ventilation - 600.00 0.00 900.00 mm
First & Second Floor Bed - 1200.00 0.00 2100.00 mm
Wall thickness - 0.00 150.00 0.00 mm
Column dimension 900.00 230.00 0.00 mm
Beam dimension 0.00 230.00 600.00 mm
Balcony Beam dimension 700.00 200.00 450.00 mm
Following assumptions were taken for performing detailed cost
calculation of the super structure:
Material Assumptions :
1) Grade of Concrete used = 20.00 Mpa
2) Cement : Sand : Aggregate = 1.00 1.50 3.00
3) Density of Cement = 1440.00 kg/m3
4) Cost of Cement bag - 53 Grade OPC = 310.00 INR/bag
Bag size = 50.00 kg
5) Cost of sand = 1150.00 INR/m3
6) Density of Aggregates = 1670.00 kg/m3
7) Cost of Aggregates = 850.00 INR/m3
8) % of Steel per unit volume of Concrete = 1.00 %
9) Density of steel = 7850.00 kg/m3
10) Cost of Steel = 48000.00 INR/tonne
11) Assumed Brick Wastage = 10.00 %
12) Mortar mixture ( Cement : Sand) = 1.00 4.00
13) Bricks density = 500.00 pcs/m3
14) Cost of Brick = 6.90 INR/pc
Traditional Formwork Cost Assumptions :
1 Cost of Traditional Formwork = 750.00 INR/m2
2 No of expected Repetitions = 10.00 times
3 Scrap Value = 0.00 INR/kg
4 Material Available for Scrap = 0.00 %
Formwork Accessories/Consumables Assumptions:
Unit Loss Assumption Unit Cost /Unit
1.00 Nails 0.22 kg/m2 100.00 % per floor 80.00
2.00 Shuttering Oil 0.06 litres/m2 100.00 % per floor 50.00
MIHIR
33
Cost Calculation Assumptions :
Electric Fitting Including Wiring @ % of Total Cost 10.00 %
Water Supply Fitting And Sanitary Fitting @ % of Total Cost 10.00 %
Sewerage @ % of Total Cost 5.00 %
Assumptions- Labour Cost:
Rate per
Formwork 150.00 sqm
Steel 8000.00 ton
Concrete 350.00 cum
Skilled 350.00 day
M/C 275.00 day
F/C 270.00 day
BHISHTI 270.00 day
Now taking this asusmptions detailed cost analysis of each component
was done as following:
1.1 Total quantity of wet concrete required for monolithically
concreting a unit floor of the building will be : 54 m3 (as per
calculations shown in Annexure - 8 )
Thus total quantity of dry concrete required will be:
= 54 x 1.54
= 84 m3
So for producing this much concrete, the amount of materials that
will be required are as follows:
So materials required:
1 Cement = 439.85 Bags
2 Sand = 22.91 m3
3 Aggregates = 45.82 m3
4 Steel = 6.59 tonnes
(as per calculations shown in Annexure - 9)
MIHIR
34
Thus, total cost of materials required for concreting will be as follows:
Sr No Material Material Required
Cost of Material (INR) Total cost
1 Cement 439.85 310.00 136354.91
2 Sand 22.91 1150.00 26345.45
3 Aggregates 45.82 850.00 38945.45
4 Steel 6.59 48000.00 316512.00
Total Material cost per floor = 518157.82
Total Material cost of project = 51815781.82
2.1 Total material cost for concreting of the super stucture of one
floor will be 5,18,157 INR
3.1 Total formwork quantity required for a unit floor will be : 434 m2
(as per calculations shown in Annexure -7 )
4.1 Cost incurred due to formwork consumables for the entire project
will be 8,87,200 INR (as per calculations shown in Annexure – 12 )
5.1 Total quantity of brickwork required per floor will be : 34 m3 (as per
calculations shown in Annexure - 10 )
So for doing this quantity of brickwork, the amount of materials
that will be required are as follows:
Materials required:
1 Cement = 80.66 Bags
2 Sand = 10.89 m3
3 Bricks = 18718.47 pcs
(as per calculations shown in Annexure - 11)
MIHIR
35
Thus, total cost of materials required for brickwork will be as follows:
Sr No Material Material Required
Cost of Material (INR) Total cost
1.00 Cement 80.66 310.00 25004.47
2.00 Sand 10.89 1150.00 12524.36
3.00 Bricks 18718.47 6.90 129157.45
Total Material cost per floor = 166686.29
Total Material cost of project = 16668628.62
6.1 Total material cost for brickwork of the super stucture of one floor
will be 1,66,686 INR
7.1 Total material required for plastering of one floor will be as
follows:
So materials required:
1.00 Cement = 452.00 Bags
2.00 Sand = 72.73 m3
(as per calculations shown in Annexure - 11)
Thus, total cost of materials required for plastering will be as follows:
Sr No Material Material Required Cost of Material (INR) Total cost
1.00 Cement 452.00 310.00 140120.95
2.00 Sand 72.73 1150.00 83642.85
Subtotal = 223763.81
3.00 Labour 10% of cost (Subtotal) 22376.38
Total Material cost per floor = 246140.19
Total Material cost of project = 22376380.54
MIHIR
36
8.1 Total material cost for plastering of the super stucture of one floor
will be 2,46,140 INR
9.1 Now for doing Comparative analysis, following two cases are
taken:
1. Buying one set of traditional formwork at a time.
2. Buying sufficient sets of traditional formwork to complete the
project in same amount of time as Aluminium formwork system.
CASE 1:
i. Number of labours required/day for achieving a 25 Day Slab cycle:
Work Description Skilled M/C F/C BHISHTI
Concreting 0.43 0.87 2.61 1.74
Reinforcement 3.96
Formwork 0.84 2.51
Brickwork 1.50 1.50
Thus, Labour Cost per day will be 5,106 INR (as per calculations shown
in Annexure -13 ).
ii. For constructing this project, using one set of Traditional formwork
system at a time:
Formwork Cycle Assumptions :
Initial set up time required 25.00 days
Floor cycle = 25.00 days
No of Buildings to be constructed using traditional formwork = 20.00
Transfer time between building 25.00 days
Working days in Month 26.00 days
MIHIR
37
Block Typical floor /
building
Total No of
buildings Repetition
Initial Set up
time (days)
Cycle time (days per
floor)
Time for
Transfer B/w
Building (Days)
Total days
Months (Considering
Working days)
Typical Floor 5 2 10 25 25 25 250 10
Typical Floor 5 2 10 25 25 25 250 10
Typical Floor 5 2 10 25 25 25 250 10
Typical Floor 5 2 10 25 25 25 250 10
Typical Floor 5 2 10 25 25 25 250 10
Typical Floor 5 2 10 25 25 25 250 10
Typical Floor 5 2 10 25 25 25 250 10
Typical Floor 5 2 10 25 25 25 250 10
Typical Floor 5 2 10 25 25 25 250 10
Typical Floor 5 2 10 25 25 25 250 10
Total Built up
Area
Formwork Quantity Required
Formwork Cost
Cost/ft2 Estimated
Scrap Value
Net Cost Net
Cost/ft2
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
Total sets required = 10.00
Repetitions per set = 10.00 times
Initial Expense = 414417.67 INR
Total Expense = 4144176.72 INR
Time period required for completing the concrete work of all the Buildings = 2500 days
Time period required for completing the concrete work of all the Buildings = 96.15 months
So with using one set of traditional formwork set, concreting work of
superstructure of entire project can be completed within 2500 days
or 96.15 months. Total formwork cost is estimated to be 20.17 INR/ft2
(Considering the return on scrap).
MIHIR
38
TOTAL COST BREAK UP OF THE SUPERSTRUCTURE FOR CASE 1 IS AS
FOLLOWING:
Description Unit
Total Built up Area/ floor 2054.56 ft2
Formwork/Built-up ratio 5.40
Cost Calculations per Built up Area
Category Total
Material Cost
Concrete 252 INR/ft2
Brickwork and Plaster 190 INR/ft2
Formwork Cost 15.85 INR/ft2
Formwork Consumables 4.32 INR/ft2
Labour Cost 62.13 INR/ft2
SUBTOTAL 524.54 INR/ft2
Electric Fitting Including Wiring @ 10% of Total Cost 52.45 INR/ft2
Water Supply Fitting And Sanitary Fitting @ 10% of Total Cost 52.45 INR/ft2
Sewerage @ 5% of Total Cost 26.23 INR/ft2
TOTAL 655.68 INR/ft2
MIHIR
39
CASE 2:
For constructing this project, in similar time as Aluminium formwork
system we require five sets of traditional formwork system at a time.
i. Number of labours required/day for for working with five sets at a
time and achieving 25 Day Slab cycle:
Labour Required/ Day:
Sr No Work Description Skilled M/C F/C BHISHTI
1 Concreting 2.17 4.34 13.03 8.68
2 Reinforcement 19.78
3 Formwork 4.18 12.53
4 Brickwork 7.49 7.49
Thus, Labour Cost per day will be 24,874 INR (as per calculations shown in
Annexure -14 ).
ii. For constructing this project, using five set of Traditional formwork
system at a time:
Formwork Cycle Assumptions :
Initial set up time required 25.00 days
Floor cycle = 25.00 days
No of Buildings to be constructed using traditional formwork = 20.00
Transfer time between building 25.00 days
Working days in Month 26.00 days
MIHIR
40
Set Propos
al Block
Typical floor /
building
Total No of buildi
ngs
Repetition
Initial Set up time
(days)
Cycle time (days per
floor)
Time for Transfer
B/w Building (Days)
Total days
Months (Consid
ering Working days)
Set 1 Typical Floor 5 2 10 25 25 25 250 10
Set 2 Typical Floor 5 2 10 25 25 25 250 10
Set 3 Typical Floor 5 2 10 25 25 25 250 10
Set 4 Typical Floor 5 2 10 25 25 25 250 10
Set 5 Typical Floor 5 2 10 25 25 25 250 10
Set 6 Typical Floor 5 2 10 25 25 25 250 10
Set 7 Typical Floor 5 2 10 25 25 25 250 10
Set 8 Typical Floor 5 2 10 25 25 25 250 10
Set 9 Typical Floor 5 2 10 25 25 25 250 10
Set 10 Typical Floor 5 2 10 25 25 25 250 10
Total Built up
Area
Formwork Quantity Required
Formwork Cost
Cost/ft2 Estimated
Scrap Value
Net Cost Net
Cost/ft2
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
20550 434 414418 20.17 0 414418 20.17
Total sets required = 10.00
Repetitions per set = 10.00 times
Initial Expense = 2072088.36 INR
Total Expense = 4144176.72 INR
Time period required for completing the concrete work of all the Buildings = 500.00 days
Time period required for completing the concrete work of all the Buildings = 19.23 months
So with using five set of traditional formwork set, concreting work of
superstructure of entire project can be completed within 500 days or
19.23 months. Total formwork cost is estimated to be 20.17 INR/ft2
(Considering the return on scrap).
MIHIR
41
TOTAL COST BREAK UP OF THE SUPERSTRUCTURE FOR CASE 2 IS AS
FOLLOWING:
Description Unit
Total Built up Area/ floor 2054.56 ft2
Formwork/Built-up ratio 5.40
Cost Calculations per Built up Area
Category Total
Material Cost
Concrete 252 INR/ft2
Brickwork and Plaster 190 INR/ft2
Formwork Cost 15.85 INR/ft2
Formwork Consumables 4.32 INR/ft2
Labour Cost 60.53 INR/ft2
SUBTOTAL 522.94 INR/ft2
Electric Fitting Including Wiring @ 10% of Total Cost 52.45 INR/ft2
Water Supply Fitting And Sanitary Fitting @ 10% of Total Cost 52.45 INR/ft2
Sewerage @ 5% of Total Cost 26.23 INR/ft2
TOTAL 653.68 INR/ft2
MIHIR
42
5. COMPARATIVE ANALYSIS
5.1. COST COMPARISON
Cost when constructed using Aluminium formwork system:
Formwork Repetition 100
Days 487.00
Cost
Formwork 8760337.33
Consumables 1326500.58
Material 57599781.82
Labour 13067804.93
Grouting 85884.78
Cost when constructed using Traditional formwork system Case 1:
Formwork Repetition 10
Days 2500.00
Cost
Formwork 4144176.72
Consumables 88720.04
Concrete 51815781.82
Brickwork & Plaster 39045009.16
Labour 12765207.48
Cost when constructed using Aluminium formwork system Case 2:
Formwork Repetition 10
Days 500.00
Cost
Formwork 3256976.36
Consumables 887200.36
Concrete 51815781.82
Brickwork & Plaster 41282647.21
Labour 497482.44
MIHIR
43
Graph: Time required vs Cost incurred for different formwork system
- Denotes the Break-Even point of Aluminium formwork system
(40 Repetitions)
Observations
Description Aluminium Formwork
Traditional Formwork Case-1
Traditional Formwork Case 2
Initial Cost Very High Very low Low
Floor to Floor cycle Very fast ( 4 days) Slow ( 25 days) Slow ( 25 days)
Approx. Repetitions High (100) Less (10) Less (10)
Time taken to complete project Fast (487 days) Very slow (2500 days) Fast (500 days)
Labour required Unskilled Skilled Skilled
Overall Cost of Project (Comparison)
7,74,90,769 (Lowest)
10,43,02,386 (Highest)
9,41,83,579 (Medium)
Remarks: Suitable for large scale construction (Repetitions - >50)
Suitable for small scale project
(Repetitions - <20)
Suitable for medium scale projects
(Repetitions – 20-50)
77490769
104302386
94183579
0
20000000
40000000
60000000
80000000
100000000
12000000025
125
225
325
425
525
625
725
825
925
1025
1125
1225
1325
1425
1525
1625
1725
1825
1925
2025
2125
2225
2325
2425
2500
Cost Comparative Analysis
Aluminium FormworkTraditional Formwork Case 1Traditional Formwork Case 2
Days
Cost
MIHIR
44
5.2. CONCLUSION
COST: Use of this formwork in load bearing design gives an average
of 25 per cent cost saving in the structure of the building and
increased usable floor space of 8 per cent over RCC design.
TIME: For 100 per cent work, construction through slab beam wall
construction takes X time and through Aluminium Formwork
technology the time required is 1/5th of the X time.
ENVIRONMENT FRIENDLY: The technology is environment friendly
as there is no use of timber. Also aluminium is a recyclable product,
hence it is highly eco-friendly.
EARTHQUAKE RESISTANCE: The formwork gives the box or cellular
design resulting in the walls giving support to the super structure
in two directions. As a result, the structures are more resistant to
earthquakes than the traditional RCC column and beam designs.
LIFTING: As the Aluminium Formwork is lightweight and easy to
handle, no tower cranes are required for the same. Even high rise
towers can be constructed very easily without help of any lifting
mechanisms.
LABOURS: Due to simplicity of the assembly, only unskilled labours
are required with minimal supervision.
REPETITIONS: The Aluminium Formwork System is removable and
can be reused over hundred times with little maintenance.
MIHIR
45
6.ANNEXURES
Annexure - 1 – Formwork Quantity for Aluminium Formwork System
Length Width Height
Total Floors (Including G) - 5 Slab Thickness - 0 0 100 mm
Total Flats on each floor - 4 Floor to Floor Height - 0 0 2900 mm
Total number of Buildings - 20 Living Entrance Door - 1000 0 2100 mm
Type of Structure -
Load Bearing Bedroom, Kitchen Door - 900 0 2100 mm
Type of Formwork - Aluminium Bath, Toilet, WC Door - 750 0 2100 mm
Living to Passage Door - 1150 0 2100 mm
Living Window - 2000 0 1200 mm
Bedroom, Kitchen Window - 1200 0 1200 mm
Toilet, WC Ventilation - 600 0 900 mm
First & Second Floor Bed - 1200 0 2100 mm
Wall thickness 1 - 0 100 0 mm
Wall thickness 2 - 0 125 0 mm
Total Formwork Area Requirement
Sr Part of
Building Component Length Width Height Quantity Area
Total Flats
Net Quantity Required
1 Bed Room Internal Wall 3050 2800 2 17080000 4 68320000
Bed Room Internal Wall 3050 2800 2 17080000 4 68320000
Bed Room Window 1200 1200 2 2880000 4 -11520000
Bed Room Jamb 1200 100 4 480000 4 1920000
Bed Room Jamb 100 1200 4 480000 4 1920000
Bed Room Door 900 2100 1 1890000 4 -7560000
Bed Room Jamb 900 100 1 90000 4 360000
Bed Room Jamb 100 2100 2 420000 4 1680000
Bed Room Slab 3050 3050 1 9302500 4 37210000
Bed Room Chajja 1400 450 1 630000 4 2520000
Bed Room Chajja 1400 100 1 140000 4 560000
Bed Room Chajja 450 100 2 90000 4 360000
MIHIR
46
2 Living Room Internal Wall 5000 2800 2 28000000 4 112000000
Living Room Internal Wall 3050 2800 2 17080000 4 68320000
Living Room Window 2000 1200 1 2400000 4 -9600000
Living Room Jamb 2000 100 2 400000 4 1600000
Living Room Jamb 100 1200 2 240000 4 960000
Living Room Main Door 1000 2100 1 2100000 4 -8400000
Living Room Jamb 1000 125 1 125000 4 500000
Living Room Jamb 125 2100 2 525000 4 2100000
Living Room Passage Door 1150 2100 1 2415000 4 -9660000
Living Room Jamb 1150 100 1 115000 4 460000
Living Room Jamb 100 2100 2 420000 4 1680000
Living Room Slab 5000 3050 1 15250000 4 61000000
Living Room Chajja 2200 450 1 990000 4 3960000
Living Room Chajja 2200 100 1 220000 4 880000
Living Room Chajja 450 100 2 90000 4 360000
3 Kitchen Internal Wall 2200 2800 2 12320000 4 49280000
Kitchen Internal Wall 1850 2800 2 10360000 4 41440000
Kitchen Window 1200 1200 1 1440000 4 -5760000
Kitchen Jamb 1200 100 2 240000 4 960000
Kitchen Jamb 100 1200 2 240000 4 960000
Kitchen Door 900 2100 1 1890000 4 -7560000
Kitchen Jamb 900 100 1 90000 4 360000
Kitchen Jamb 100 2100 2 420000 4 1680000
Kitchen Slab 2200 1850 1 4070000 4 16280000
Kitchen Chajja 3800 450 1 1710000 2 3420000
Kitchen Chajja 3800 100 1 380000 2 760000
4 Bathroom Internal Wall 1500 2800 2 8400000 4 33600000
Bathroom Internal Wall 1100 2800 2 6160000 4 24640000
Bathroom Ventilation 600 900 1 540000 4 -2160000
Bathroom Jamb 600 100 2 120000 4 480000
Bathroom Jamb 100 900 2 180000 4 720000
Bathroom Door 750 2100 1 1575000 4 -6300000
Bathroom Jamb 750 100 2 150000 4 600000
Bathroom Jamb 100 2100 2 420000 4 1680000
Bathroom Slab 1500 1100 1 1650000 4 6600000
Bathroom Chajja 2200 300 1 660000 4 2640000
Bathroom Chajja 2200 100 1 220000 4 880000
5 W.C. Internal Wall 1000 2800 2 5600000 4 22400000
W.C. Internal Wall 1000 2800 2 5600000 4 22400000
W.C. Ventilation 600 900 1 540000 4 -2160000
MIHIR
47
W.C. Jamb 600 100 2 120000 4 480000
W.C. Jamb 100 900 2 180000 4 720000
W.C. Door 750 2100 1 1575000 4 -6300000
W.C. Jamb 750 100 2 150000 4 600000
W.C. Jamb 100 2100 2 420000 4 1680000
W.C. Slab 1000 1000 1 1000000 4 4000000
6 Passage Internal Wall 1650 2800 2 9240000 4 36960000
Passage Internal Wall 1000 2800 2 5600000 4 22400000
Passage Bed room Door 900 2100 1 1890000 4 -7560000
Passage W.C. Door 750 2100 1 1575000 4 -6300000
Passage Slab 1650 1000 1 1650000 4 6600000
Passage Passage Door 1150 2800 1 3220000 4 -12880000
Passage Internal Wall 1200 2800 2 6720000 4 26880000
Passage Internal Wall 1150 2800 1 3220000 4 12880000
Passage Living-Passage
Door 1150 2100 1 2415000 4 -9660000
Passage Bath Door 750 2100 1 1575000 4 -6300000
Passage Slab 1200 1150 1 1380000 4 5520000
7 Balcony Beam 3250 450 1 1462500 4 5850000
Balcony Beam 3250 200 1 650000 4 2600000
Balcony Beam 3250 350 1 1137500 4 4550000
Balcony Slab 200 450 2 180000 4 720000
Balcony Slab 3250 700 2 4550000 4 18200000
8 Floor Passage Internal Wall 2500 2800 2 14000000 1 14000000
Floor Passage Internal Wall 2300 2800 1 6440000 1 6440000
Floor Passage Slab 2500 2300 1 5750000 1 5750000
Floor Passage Main Door 1000 2100 1 2100000 4 -8400000
Floor Passage Window 2300 1200 1 2760000 4 -11040000
Floor Passage Jamb 2300 100 2 460000 4 1840000
Floor Passage Jamb 100 1200 2 240000 4 960000
9 Staircase Tread 250 1100 8 2200000 2 4400000
Staircase Riser 161 1100 9 1593900 2 3187800
Staircase Mid-Landing 813 2300 1 1869900 1 1869900
Staircase Internal Wall 3200 2900 2 18560000 2 37120000
Staircase Stair 1175099 1 1175099 1 -1175099
Staircase Wall 2300 900 1 2070000 1 2070000
2300 1225 1 2817500 1 2817500
MIHIR
48
Staircase Inclined Slab 2446 1100 1 2690600 1 2690600
2677 1100 1 2944700 1 2944700
Beam 2300 200 1 460000 1 460000
2300 200 1 460000 1 460000
10 External Wall Wall 83900 2900 1 243310000 1 243310000
External Wall Kitchen Chajja 3800 2900 1 11020000 2 -22040000
External Wall Kitchen Chajja 3800 2800 1 10640000 2 21280000
External Wall Bath-W.C. Chajja 2800 2900 1 8120000 4 -32480000
External Wall Bath-W.C. Chajja 2800 2800 1 7840000 4 31360000
External Wall Living Window 2000 1200 1 2400000 4 -9600000
External Wall Window 1200 1200 3 4320000 4 -17280000
External Wall Ventilation 600 900 2 1080000 4 -4320000
External Wall Staircase 2300 1675 1 3852500 1 -3852500
External Wall Staircase 1200 1200 1 1440000 1 -1440000
11 Kicker External wall 83900 125 1 10487500 1 10487500
Column1 SUMMARY QUANTITY (m2) 5 % Inc.
1.00 Bed Room 164.09 172.29
2.00 Living Room 226.16 237.47
3.00 Kitchen 101.82 106.91
4.00 Bathroom 63.38 66.55
5.00 W.C. 43.82 46.01
6.00 Passage 68.54 71.97
7.00 Balcony 31.92 33.52
8.00 Floor Passage 9.55 10.03
9.00 Staircase 56.85 59.69
10.00 External Wall 204.94 215.18
11.00 Kicker 10.49 11.01
981.55 1030.63
MIHIR
49
Annexure - 2 – Concrete Quantity for Aluminium Formwork System
Length Width Height
Total Floors (Including G) - 5 Slab Thickness - 0 0 100 mm
Total Flats on each floor - 4 Floor to Floor Height - 0 0 2900 mm
Total number of Buildings - 20 Living Entrance Door - 1000 0 2100 mm
Type of Structure - Load
Bearing Bedroom, Kitchen Door - 900 0 2100 mm
Type of Formwork - Aluminium Bath, Toilet, WC Door - 750 0 2100 mm
Construction time (Months) - 24 Living to Passage Door - 1150 0 2100 mm
Living Window - 2000 0 1200 mm
Bedroom, Kitchen Window - 1200 0 1200 mm
Toilet, WC Ventilation - 600 0 900 mm
First & Second Floor Bed - 1200 0 2100 mm
Wall thickness 1 - 0 100 0 mm
Wall thickness 2 - 0 125 0 mm
Total Concrete Requirement
Sr No
Part of Building Component Length
Width
Height
Quantity Volume
Total Flats
Net Quantity Required
1 Bed Room Internal Wall 3250 50 2800 2 910000000 4 3640000000
Bed Room Internal Wall 50 3050 2800 2 854000000 4 3416000000
Bed Room Window 1200 50 1200 2 144000000 4 -576000000
Bed Room Door 900 50 2100 1 94500000 4 -378000000
Bed Room Slab 3050 3050 100 1 930250000 4 3721000000
Bed Room Chajja 1400 450 100 1 63000000 4 252000000
2 Living Room Internal Wall 5000 50 2800 1 700000000 4 2800000000
Living Room Internal Wall 5000 63 2800 1 875000000 4 3500000000
Living Room Internal Wall 50 3275 2800 2 917000000 4 3668000000
Living Room Window 2000 50 1200 1 120000000 4 -480000000
Living Room Main Door 1000 63 2100 1 131250000 4 -525000000
Living Room Passage Door 1150 50 2100 1 120750000 4 -483000000
Living Room Slab 5000 3050 100 1 1525000000 4 6100000000
Living Room Chajja 2200 450 100 1 99000000 4 396000000
3 Kitchen Internal Wall 2200 50 2800 2 616000000 4 2464000000
Kitchen Internal Wall 50 1850 2800 2 518000000 4 2072000000
MIHIR
50
Kitchen Window 1200 50 1200 1 72000000 4 -288000000
Kitchen Door 900 50 2100 1 94500000 4 -378000000
Kitchen Slab 2200 1850 100 1 407000000 4 1628000000
Kitchen Chajja 3800 450 100 1 171000000 2 342000000
4 Bathroom Internal Wall 1500 50 2800 2 420000000 4 1680000000
Bathroom Internal Wall 50 1100 2800 2 308000000 4 1232000000
Bathroom Ventilation 600 50 900 1 27000000 4 -108000000
Bathroom Door 750 50 2100 1 78750000 4 -315000000
Bathroom Slab 1500 1100 100 1 165000000 4 660000000
Bathroom Chajja 2200 300 100 1 66000000 4 264000000
5 W.C. Internal Wall 1000 50 2800 2 280000000 4 1120000000
W.C. Internal Wall 50 1000 2800 2 280000000 4 1120000000
W.C. Ventilation 600 50 900 1 27000000 4 -108000000
W.C. Door 750 50 2100 1 78750000 4 -315000000
W.C. Slab 1000 1000 100 1 100000000 4 400000000
6 Passage Internal Wall 1650 50 2800 2 462000000 4 1848000000
Passage Internal Wall 50 1000 2800 2 280000000 4 1120000000
Passage Bed room Door 900 50 2100 1 94500000 4 -378000000
Passage W.C. Door 750 50 2100 1 78750000 4 -315000000
Passage Slab 1650 1000 100 1 165000000 4 660000000
Passage Passage Door 1150 50 2800 1 161000000 4 -644000000
Passage Internal Wall 1200 50 2800 2 336000000 4 1344000000
Passage Internal Wall 50 1150 2800 1 161000000 4 644000000
Passage Living-Passage
Door 1150 50 2100 1 120750000 4 -483000000
Passage Bath Door 750 50 2100 1 78750000 4 -315000000
Passage Slab 1200 1150 100 1 138000000 4 552000000
7 Balcony Beam 3250 200 450 1 292500000 4 1170000000
700 200 450 2 126000000 4 504000000
Balcony Slab 3250 700 100 1 227500000 4 910000000
8 Floor Passage Internal Wall 2500 63 2800 2 875000000 1 875000000
Floor Passage Internal Wall 50 2300 2800 1 322000000 1 322000000
Floor Passage Slab 2500 2300 100 1 575000000 1 575000000
Floor Passage Main Door 1000 63 2100 1 131250000 4 -525000000
Floor Passage Window 2300 50 1200 1 138000000 4 -552000000
9 Staircase Left 484603 1100 1 533063300 1 533063300
MIHIR
51
Staircase Right 484603 1100 1 533062860 1 533062860
Staircase Mid-Landing 150000 2300 1 345000000 1 345000000
Staircase Internal Wall 3200 63 2900 2 1160000000 2 2320000000
Staircase Landing Wall 2300 50 900 1 103500000 1 103500000
Staircase 2300 50 1225 1 140875000 1 140875000
Staircase Beam 2300 200 100 1 46000000 1 46000000
10 External Wall Wall 83900 50 2900 1 1216550000
0 1 12165500000
External Wall Kitchen Chajja 3800 50 2900 1 551000000 2 -1102000000
External Wall Kitchen Chajja 3800 50 2800 1 532000000 2 1064000000
External Wall Bath-W.C. Chajja 2800 50 2900 1 406000000 4 -1624000000
External Wall Bath-W.C. Chajja 2800 50 2800 1 392000000 4 1568000000
External Wall Living Window 2000 50 1200 1 120000000 4 -480000000
External Wall Window 1200 50 1200 3 216000000 4 -864000000
External Wall Ventilation 600 50 900 2 54000000 4 -216000000
External Wall Staircase 2300 50 1675 1 192625000 1 -192625000
External Wall Staircase Window 1200 50 1200 1 72000000 1 -72000000
Sr No SUMMARY QUANTITY (m3) 5 % inc
1.00 Bed Room 10.08 10.58
2.00 Living Room 14.98 15.72
3.00 Kitchen 5.84 6.13
4.00 Bathroom 3.41 3.58
5.00 W.C. 2.22 2.33
6.00 Passage 4.03 4.23
7.00 Balcony 2.58 2.71
8.00 Floor Passage 0.70 0.73
9.00 Staircase 4.02 4.22
10.00 External Wall 10.25 10.76
58.10 61.01
MIHIR
52
Annexure - 3 – Materials required for concreting in Aluminium Formwork System
Assumptions- Materials:
Unit
1) Grade of Concrete used = 20.00 Mpa
2) Cement : Sand : Aggregate = 1.00 1.50 3.00
3) Density of Cement = 1440.00 kg/m3
4) Cost of Cement bag - 53 Grade OPC = 310.00 INR/bag
Bag size = 50.00 kg
5) Cost of sand = 1000.00 INR/m3
6) Density of Aggregates = 1670.00 kg/m3
7) Cost of Aggregates = 850.00 INR/m3
8) % of Steel per unit volume of Concrete = 1.00 %
9) Density of steel = 7850.00 kg/m3
10) Cost of Steel = 48000.00 INR/tonne
So, total volume of dry concrete required = 94.00 m3
Sr No Material Material Required
(m3) Density of Material
(kg/m3) Material Required
(kg) No. of Bags
1 Cement 17.09 1440.00 24610.91 492.22
2 Sand 25.64
3 Aggregates 51.27 1670.00 85625.45
4 Steel 0.94 7850.00 7379.00
So materials required:
1 Cement = 492.22 Bags
2 Sand = 25.64 m3
3 Aggregates = 51.27 m3
4 Steel = 7.38 tonnes
MIHIR
53
Annexure - 4 – Consumables required in Aluminium Formwork System and its cost
incurred
Assumptions- Formwork Accessories/Consumables:
Unit Loss Assumption Unit Cost /Unit
1 Pin-Wedge 14.00 pcs/m2 2.00 % per floor 15
2 Wall ties 5.00 pcs/m2 2.00 % per floor 20
3 Shuttering Oil 0.06 litres/m2 87
4 Corrugated Sheet 800.00 mm2 / tie 60
5 PVC roll 100.00 mm / tie 1.75
Total Formwork quantity = 1030.63 m2
Total Floors (Including G) - 5.00 1st Supply
from Company
Total number of Buildings - 20.00
Sr Material Material Required
Total quantity required
Additional Material/Floor
Total Additional Material Unit
1 Pin-Wedge 14.00 14428.79 288.58 28569.01 pcs
2 Wall ties 5.00 5153.14 103.06 10203.22 pcs
3 Shuttering Oil 0.06 66.58 66.58 6657.86 litres
4 Corrugated Sheet 800.00 4122511.68 4122511.68 408.13 m2
5 PVC roll 100.00 515313.96 515313.96 51531.40 m
So additional cost incurred due to consumables:
Sr Material Additional Material Cost/Unit Total Cost
1 Pin-Wedge 28569.01 15.00 428535.09
2 Wall ties 10203.22 20.00 204064.33
3 Shuttering Oil 6657.86 87.00 579233.50
4 Grease 0.00 0.00 0.00
5 Corrugated Sheet 408.13 60.00 24487.72
6 PVC roll 51531.40 1.75 90179.94
13,26,500.58
MIHIR
54
Annexure - 5 – Cost incurred due to Grouting in Aluminium Formwork System
Grouting Assumptions:
Length Width Height
1 Grout Dimension = 100.00 50.00 8.00
2 Cost of grouting material per mm3 =
3 Grouting to be done with mortar(Cement : Sand) = 1.00 4.00
Sr No Material Material Required/ Grout (mm3)
Total Material (m3)
Cost of Material
Total cost
1 Grouting 40000.00 20.61
31.74
1 Cement 6.35 310.00 56680.91
2 Sand 25.39 1150.00 29203.87
85884.78
Net Grouting Cost = 85884.78
MIHIR
55
Annexure - 6 – Labors required to achieve 4 day work cycle in Aluminium Formwork
System and cost calculations
Work to be done in one day:
Total volume of concreting to be done = 15.25 m3
Total volume of Reinforcement to be done = 0.60 tonnes
Total formwork quantity to be done = 257.66 m2
Total grouting quantity to be done = 0.01 m3 Skilled M/C F/C BHISHTI Unit
Worker output for Concreting = 5.00 m3 1.00 2.00 6.00 4.00 Man/day
Worker output for Reinforcement = 1.00 tonnes 15.00 Man/day
Worker output for formwork = 8.00 m2 1.00 Man/day
Worker output for grouting = 0.01 m3 1.00 Man/day
Slab to Slab Work cycle = 4.00 days
Section to Section Work cycle = 2.00 days
Labour Required/ Day
Sr Work to be done Material Skilled M/C F/C BHISHTI
1 15.25 Concreting 3.05 6.10 18.30 12.20
2 0.60 Reinforcement 8.98
3 128.83 Formwork 8.05 24.16
4 0.01 Grouting 1.00
Labour Cost / Day
Sr No Material Skilled M/C F/C BHISHTI TOTAL
1 Concreting 1067.50 1677.50 4941.00 3294.00 10980.00
2 Reinforcement 4844.00 4844.00
3 Formwork 2817.50 6644.00 9461.50
4 Grouting 270.00 270.00
Per day Labour Cost = 25555.50
Per day Labour Cost (5%inc) = 26833.28
MIHIR
56
Annexure - 7 – Formwork Quantity required for Traditional Formwork System
Length Width Height
Total Floors (Including G) - 5 Slab Thickness - 0 0 100 mm
Total Flats on each floor - 4 Floor to Floor Height - 0 0 2900 mm
Total number of Buildings - 20 Living Entrance Door - 1000 0 2100 mm
Type of Structure - Framed
Structure Bedroom, Kitchen Door - 900 0 2100 mm
Type of Formwork - Traditional Bath, Toilet, WC Door - 750 0 2100 mm
Column Formwork Set Use 3 times Living to Passage Door - 1150 0 2100 mm
Living Window - 2000 0 1200 mm
Bedroom, Kitchen Window - 1200 0 1200 mm
Toilet, WC Ventilation - 600 0 900 mm
First & Second Floor Bed - 1200 0 2100 mm
Wall thickness 1 - 0 150 0 mm
Column dimension 900 230 0
Beam dimension 0 230 600 mm
Balcony Beam dimension 700 200 450 mm
Total Formwork Area Requirement
Sr Compone
nt Part of Building Length Width Height
Quantity
Total Area Total Flats
Net Quantity Required
1 Columns Bedroom 900 2300 2 4 16560000 4 66240000
230 2300 2 4 4232000 4 16928000
Kitchen 900 2300 2 1 4140000 4 16560000
230 2300 2 1 1058000 4 4232000
Living Room 900 2300 2 2 8280000 4 33120000
230 2300 2 2 2116000 4 8464000
Staircase Passage 900 2300 2 2 8280000 1 8280000
230 2300 2 2 2116000 1 2116000
2 Beams Vertical Bedroom 3250 230 1 1 747500 4 2990000
2120 600 1 1 1272000 4 5088000
2120 500 1 1 1060000 4 4240000
MIHIR
57
Vertical Flat to Flat 7600 230 1 1 1748000 2 3496000
7600 600 1 1 4560000 2 9120000
7600 500 1 1 3800000 2 7600000
Vertical Flat to Flat 8335 230 1 1 1917050 2 3834100
8335 600 1 1 5001000 2 10002000
8335 500 1 1 4167500 2 8335000
Vertical Flat to Flat 7140 230 1 1 1642200 2 3284400
7140 600 1 1 4284000 2 8568000
7140 500 1 1 3570000 2 7140000
Horizontal 5680 230 1 1 1306400 4 5225600
5680 600 1 1 3408000 4 13632000
5680 500 1 1 2840000 4 11360000
Horizontal Bedroom 2250 230 1 2 1035000 4 4140000
2250 600 1 2 2700000 4 10800000
2250 500 1 2 2250000 4 9000000
Horizontal Passage
+ Kitchen 2070 230 1 5 2380500 2 4761000
2070 600 1 5 6210000 2 12420000
2070 500 1 5 5175000 2 10350000
Horizontal Living
Room 2815 230 1 2 1294900 2 2589800
2815 600 1 2 3378000 2 6756000
2815 500 1 2 2815000 2 5630000
2145 230 1 1 493350 2 986700
2145 600 1 1 1287000 2 2574000
2145 500 1 1 1072500 2 2145000
Staircase 2300 230 1 3 1587000 1 1587000
2300 600 1 3 4140000 1 4140000
2300 500 1 3 3450000 1 3450000
3 Slab Bedroom 2790 2920 1 1 8146800 4 32587200
Kitchen 2070 1625 1 1 3363750 4 13455000
Living Room 4805 2815 1 1 13526075 4 54104300
Bath + WC +
Passage 2490 2070 1 1 5154300 4 20617200
Staircase 1265 2300 1 1 2909500 1 2909500
1005 2300 1 1 2311500 1 2311500
4 Staircase Riser 161 1100 9 1 1593900 2 3187800
Mid-Landing 813 2300 1 1 1869900 1 1869900
MIHIR
58
Inclined Slab 2446 1100 1 1 2690600 1 2690600
2677 1100 1 1 2944700 1 2944700
5 Chajja Bedroom 1400 450 1 1 630000 4 2520000
Bedroom 1400 100 1 1 140000 4 560000
Bedroom 450 100 2 1 90000 4 360000
Living Room 2200 450 1 1 990000 4 3960000
Living Room 2200 100 1 1 220000 4 880000
Living Room 450 100 2 1 90000 4 360000
Kitchen 3800 450 1 1 1710000 2 3420000
Kitchen 3800 100 1 1 380000 2 760000
Kitchen 450 100 2 1 90000 2 180000
WC + Bath 2070 300 1 1 621000 4 2484000
WC + Bath 2070 100 1 1 207000 4 828000
WC + Bath 300 100 2 1 60000 4 240000
6 Balcony Vertical Beam 3250 200 1 1 650000 4 2600000
3250 450 1 1 1462500 4 5850000
2850 350 1 1 997500 4 3990000
Horizontal Beam 200 700 1 2 280000 4 1120000
700 450 1 2 630000 4 2520000
700 450 1 2 630000 4 2520000
Slab 2850 700 1 1 1995000 4 7980000
Column1 SUMMARY QUANTITY
(m2) 5 % inc
1 Columns 52 55
2 Beams 182 191
3 Slab 126 132
4 Staircase 11 11
5 Chajja 17 17
6 Balcony 27 28
414 434
MIHIR
59
Annexure - 8 – Concrete Quantity required for Traditional Formwork System
Lengt
h Width Heig
ht
Total Floors (Including G) - 5 Slab Thickness - 0 0 100 mm
Total Flats on each floor - 4 Floor to Floor Height - 0 0 2900 mm
Total number of Buildings - 20 Living Entrance Door - 1000 0 2100 mm
Type of Structure - Framed
Structure Bedroom, Kitchen Door - 900 0 2100 mm
Type of Formwork - Traditional Bath, Toilet, WC Door - 750 0 2100 mm
Construction time (Months) - 3 Living to Passage Door - 1150 0 2100 mm
Living Window - 2000 0 1200 mm
Bedroom, Kitchen Window - 1200 0 1200 mm
Toilet, WC Ventilation - 600 0 900 mm
First & Second Floor Bed - 1200 0 2100 mm
Wall thickness - 0 150 0 mm
Column dimension 900 230 0
Beam dimension 0 230 600 mm
Balcony Beam dimension 700 200 450 mm
Total Concrete Requirement
Sr No
Component Part of Building Length
Width
Height Total Volume
Total Flats
Net Quantity Required
1 Columns Bedroom 900 230 2300 4 1904400000 4 7617600000
Kitchen 900 230 2300 1 476100000 4 1904400000
Living Room 900 230 2300 2 952200000 4 3808800000
Staircase Passage 900 230 2300 2 952200000 1 952200000
2 Beams Vertical Bedroom 3250 230 600 1 448500000 4 1794000000
Vertical Flat to Flat 7600 230 600 1 1048800000 2 2097600000
Vertical Flat to Flat 8335 230 600 1 1150230000 2 2300460000
Vertical Flat to Flat 7140 230 600 1 985320000 2 1970640000
Horizontal 5680 230 600 1 783840000 4 3135360000
Horizontal Bedroom 2250 230 600 2 621000000 4 2484000000
MIHIR
60
Horizontal Passage +
Kitchen 2070 230 600 5 1428300000 2 2856600000
Horizontal Living Room 2815 230 600 2 776940000 2 1553880000
2145 230 600 1 296010000 2 592020000
Staircase 2300 230 600 3 952200000 1 952200000
3 Slab Bedroom 2790 2920 100 1 814680000 4 3258720000
Kitchen 2070 1625 100 1 336375000 4 1345500000
Living Room 4805 2815 100 1 1352607500 4 5410430000
Bath + WC + Passage 2490 2070 100 1 515430000 4 2061720000
Staircase 1265 2300 100 1 290950000 1 290950000
1005 2300 100 1 231150000 1 231150000
4 Staircase Steps up 467881 1100 1 1 514669100 1 514669100
Mid-Landing 137250 2300 1 1 315675000 1 315675000
Steps down 484602 1100 1 1 533062200 1 533062200
5 Chajja Bedroom 1400 450 100 1 63000000 4 252000000
Living Room 2200 450 100 1 99000000 4 396000000
Kitchen 3800 450 100 1 171000000 2 342000000
WC + Bath 2070 300 100 1 62100000 4 248400000
6 Balcony Vertical Beam 3250 200 450 1 292500000 4 1170000000
Horizontal Beam 200 700 450 2 126000000 4 504000000
Slab 2850 700 100 1 199500000 4 798000000
Sr no SUMMARY QUANTITY (m3) 5 % Inc.
1 Columns 14 15
2 Beams 20 21
3 Slab 13 13
4 Staircase 1 1
5 Chajja 1 1
6 Balcony 2 3
52 54
MIHIR
61
Annexure - 9 – Materials required for concreting in Traditional Formwork System
Assumptions- Materials:
Unit
1) Grade of Concrete used = 20.00 Mpa
2) Cement : Sand : Aggregate = 1.00 1.50 3.00
3) Density of Cement = 1440.00 kg/m3
4) Cost of Cement bag - 53 Grade OPC = 310.00 INR/bag
Bag size = 50.00 kg
5) Cost of sand = 1150.00 INR/m3
6) Density of Aggregates = 1670.00 kg/m3
7) Cost of Aggregates = 850.00 INR/m3
8) % of Steel per unit volume of Concrete = 1.00 %
9) Density of steel = 7850.00 kg/m3
10) Cost of Steel = 48000.00 INR/tonne
So, total volume of dry concrete required = 84.00 m3
Sr Material Material Required (m3) Density of
Material (kg/m3) Material Required
(kg) No. of Bags
1.00 Cement 15.27 1440.00 21992.73 439.85
2.00 Sand 22.91
3.00 Aggregates 45.82 1670.00 76516.36
4.00 Steel 0.84 7850.00 6594.00
So materials required:
1.00 Cement = 439.85 Bags
2.00 Sand = 22.91 m3
3.00 Aggregates = 45.82 tonnes
4.00 Steel = 6.59 tonnes
MIHIR
62
Annexure - 10 – Quantity of Brickwork required in Traditional Formwork System
Total Brickwork Requirement
Sr No
Part of Building Component
Length
Width
Height
Quantity Volume
Total Flats
Net Quantity Required
1 Bed Room Internal Wall 2120 150 2300 2 731400000 4 2925600000
Bed Room Internal Wall 2250 150 2300 2 776250000 4 3105000000
Bed Room Window 1200 150 1200 2 216000000 4 -864000000
Bed Room Door 900 150 2100 1 141750000 4 -567000000
2 Living Room Internal Wall 2815 150 2300 1 485587500 4 1942350000
Living Room Internal Wall 2145 150 2300 1 370012500 4 1480050000
Living Room Internal Wall 4135 150 2300 1 713287500 4 2853150000
Living Room Internal Wall 3800 150 2300 1 655500000 4 2622000000
Living Room Window 2000 150 1200 1 180000000 4 -720000000
Living Room Main Door 1000 150 2100 1 157500000 4 -630000000
Living Room Passage Door 1150 150 2100 1 181125000 4 -724500000
3 Kitchen Internal Wall 1450 150 2300 2 500250000 4 2001000000
Kitchen Internal Wall 2070 150 2300 2 714150000 4 2856600000
Kitchen Window 1200 150 1200 1 108000000 4 -432000000
Kitchen Door 900 150 2100 1 141750000 4 -567000000
4 Bathroom Internal Wall 1500 150 2300 1 258750000 4 1035000000
Bathroom Internal Wall 1000 150 2300 1 172500000 4 690000000
Bathroom Internal Wall 1100 150 2300 2 379500000 4 1518000000
Bathroom Internal Wall 2470 150 600 1 111150000 4 444600000
Bathroom Ventilation 600 150 900 1 40500000 4 -162000000
Bathroom Door 750 150 2100 1 118125000 4 -472500000
5 W.C. Internal Wall 1000 150 2300 1 172500000 4 690000000
W.C. Internal Wall 500 150 2300 1 86250000 4 345000000
W.C. Internal Wall 1000 150 2300 1 172500000 4 690000000
W.C. Internal Wall 870 150 2300 1 150075000 4 600300000
W.C. Internal Wall 1740 150 600 1 78300000 4 313200000
W.C. Ventilation 600 150 900 1 40500000 4 -162000000
6 Passage Internal Wall 1520 150 2300 2 524400000 4 2097600000
MIHIR
63
Passage Internal Wall 1000 150 2300 1 172500000 4 690000000
Passage Internal Wall 870 150 2300 1 150075000 4 600300000
Passage Bed room Door 900 150 2100 1 141750000 4 -567000000
Passage W.C. Door 750 150 2100 1 118125000 4 -472500000
Passage Passage Door 1020 150 2800 1 214200000 4 -856800000
Passage Internal Wall 1150 150 2300 2 396750000 4 1587000000
Passage Internal Wall 1150 150 2300 1 198375000 4 793500000
Passage Living-Passage
Door 1020 150 2800 1 214200000 4 -856800000
Passage Bath Door 750 150 2100 1 118125000 4 -472500000
8 Floor Passage Internal Wall 2300 150 2300 2 793500000 1 793500000
Floor Passage Internal Wall 5135 150 2300 2 177157500
0 1 1771575000
Floor Passage Main Door 1000 150 2100 1 157500000 4 -630000000
Floor Passage Window 2300 150 1200 1 207000000 4 -828000000
10 External Wall Wall 6254
0 150 2300 1 107881500
00 1 10788150000
External Wall Living Window 2000 150 1200 1 180000000 4 -720000000
External Wall Window 1200 150 1200 3 324000000 4 -1296000000
External Wall Ventilation 600 150 900 2 81000000 4 -324000000
External Wall Staircase 2300 150 1675 1 288937500 1 -288937500
External Wall Staircase Window 2300 150 1200 1 207000000 1 -207000000
Sr no SUMMARY QUANTITY
(m3) 5 % inc
1 Bed Room 5 5
2 Living Room 7 7
3 Kitchen 4 4
4 Bathroom 3 3
5 W.C. 2 3
6 Passage 3 3
7 Floor Passage 1 1
8 External Wall 8 8
32 34
MIHIR
64
Annexure - 11 – Quantity of materials required for Brickwork and Plastering in
Traditional Formwork System
Assumed Brick Wastage = 10.00 %
Mortar mixture ( Cement : Sand) = 1.00 4.00
Bricks density = 500.00 pcs/m3
Cost of Brick = 5.00 INR/pc
So, total volume of bricks required = 34.03 m3
BRICKWORK
Sr No Material Material Required Unit
1.00 Cement 80.66 bags
2.00 Sand 10.89 m3
3.00 Bricks 18718.47 pcs
So materials required:
1.00 Cement = 80.66 Bags
2.00 Sand = 10.89 m3
3.00 Bricks = 18718.47 pcs
INTERNAL PLASTERING
Sr No Material Material Required Unit
1.00 Cement 226.00 bags
2.00 Sand 43.64 m3
EXTERNAL PLASTERING
Sr No Material Material Required Unit
1.00 Cement 226.00 bags
2.00 Sand 29.09 m3
So materials required:
1.00 Cement = 452.00 Bags
2.00 Sand = 72.73 m3
MIHIR
65
Annexure - 12 – Consumables required for in Traditional Formwork System and its
cost incurred
Assumptions- Formwork Accessories/Consumables:
Unit Loss Assumption Unit Cost /Unit
1 Nails 0.22 kg/m2 100.00 % per floor 80.00
2 Shuttering Oil 0.06 litres/m2 100.00 % per floor 50.00
Total Formwork quantity = 434.26 m2
Total Floors (Including G) - 5.00
Total number of Buildings - 20.00
Sr No
Material Material Required
Total quantity required
Additional Material/Floor
Total Additional Material
Unit
1 Nails 0.22 93.37 93.37 9336.67 kg/m2
2 Shuttering
Oil 0.06 28.05 28.05 2805.34 litres/m2
So additional cost incurred due to consumables:
Additional Material Cost/Unit Total Cost
1 Nails 9336.67 80.00 746933.25
2 Shuttering Oil 2805.34 50.00 140267.12
3 Grease 0.00 0.00 0.00
8,87,200.36
MIHIR
66
Annexure - 13 – Labour required in Traditional Formwork System for 25 days cycle
with one set a time
Work to be done in one day:
Total volume of concreting to be done = 2.17 m3
Total volume of Reinforcement to be done = 0.26 tonnes
Total formwork quantity to be done = 17.37 m2
Total brickwork to be done = 748.74 pcs
Total Plastering to be done =
Skilled M/C F/C BHISHTI
Worker output for Concreting = 5.00 m3 1 2 6 4 man per day
Worker output for Reinforcement = 1.00 tonnes 15 man per day
Worker output for formwork = 5.20 m2 1 man per day
Worker output for brickwork = 500 pcs 1 1 man per day
Slab to Slab Work cycle = 25.00 days
Labour Required/ Day
Sr No Work to be done Material Skilled M/C F/C BHISHTI
1 2.17 Concreting 0.43 0.87 2.61 1.74
2 0.26 Reinforcement 3.96
3 8.69 Formwork 0.84 2.51
4 748.74 Brickwork 1.50 1.50
Labour Cost / Day
Sr No Material Skilled M/C F/C BHISHTI TOTAL
1 Concreting 150.50 239.25 704.70 469.80 1564.25
2 Reinforcement 1386.00 1386.00
3 Formwork 294.00 690.25 984.25
4 Brickwork 524.12 404.32 928.44
Per day Labour Cost = 4862.94
Per day Labour Cost (5%inc) = 5,106.08
MIHIR
67
Annexure - 14 – Labour required in Traditional Formwork System for 25 days cycle
with five set a time
Work to be done in one day:
Total volume of concreting to be done = 10.86 m3
Total volume of Reinforcement to be done = 1.32 tonnes
Total formwork quantity to be done = 86.85 m2
Total brickwork to be done = 3743.69 pcs
Skilled M/C F/C BHISHTI
Worker output for Concreting = 5.00 m3 1 2 6 4 man per day
Worker output for Reinforcement = 1.00 tonnes 15 man per day
Worker output for formwork = 5.20 m2 1 man per day
Worker output for brickwork = 500 pcs 1 1 man per day
Labour Required/ Day
Sr No Work to be done Material Skilled M/C F/C BHISHTI
1 10.86 Concreting 2.17 4.34 13.03 8.68
2 1.32 Reinforcement 19.78
3 43.43 Formwork 4.18 12.53
4 3743.69 Brickwork 7.49 7.49
Labour Cost / Day
Sr No Material Skilled M/C F/C BHISHTI TOTAL
1 Concreting 759.50 1193.50 3518.10 2343.60 7814.70
2 Reinforcement 6923.00 6923.00
3 Formwork 1463.00 3445.75 4908.75
4 Brickwork 2021.59 2021.59 4043.19
Per day Labour Cost = 23689.64
Per day Labour Cost (5%inc) = 24,874.12
MIHIR
68
Annexure - 15 – Schedule of Rates (2012-13) Applicable for Pune Region by
Maharashtra Jeevan Pradhikaran
Sr. No.
Description Unit Rate (Rs.)
2012-13
MATERIALS
1 Acetylene gas No 506.00
2 Alum Grade-I ( ex-factory ) MT 8000.00
3 Binding wire Kg 57.00
4 Black enamel paint ( anti-corrosive ) Lit 193.00
5 Bricks No 6.90
6 Bullies, struts ( 125 mm dia 1.5 M long ) RMT 194.00
7 C.C.T.W. planks ( 3" x 6" ) Cum 7400.00
8 Cement ( bags ) Bags 310.00
9 Cement ( MT ) MT 6200.00
10 Cement sulphur resistant MT 6840.00
11 Charcoal Kg 33.00
12 Corrosion resistant steel MT 48300.00
13 Diesel Lit 51.75
14 Epoxy paint Kg 435.00
15 Fuse No 25.00
16 Gun powder Kg 132.00
17 Liquid chlorine ( 100 Kg. Dept. container )
No --
18 Liquid chlorine ( 100 Kg. Supplier container )
No --
19 Liquid chlorine ( 900 Kg. Dept. container )
No 16000.00
20 Lubricant oil Lit 230.00
21 M.S. angle ( 50 mm x 50 mm x 6 mm ) Kg 48.30
22 M.S. bars MT 48000.00
23 M.S. bars (in Kgs. ) Kg 48.00
24 M.S. flats ( 40 mm x 3 mm ) Kg 48.30
25 M.S. plate Kg 49.00
26 Mild steel grill ready Kg 70.00
27 Mild steel grill railing MT 70.00
28 Mobile oil Lit 230.00
29 Murum Cum 340.00
30 Nails Kg 74.00
MIHIR
69
31 Nut bolts Kg 90.00
32 Oxygen gas ( refill ) Cylndr 345.00
33 Poling boards Cum 20000.00
34 Quarry spalls Cum 200.00
35 R.S. joists, channels, etc. MT 51000.00
36 Rapid sand gravity filter media at source ( Godhra sand )
Cum 1265.00
37 Rapid sand gravity filter gravel at source ( Godhra )
Cum 1265.00
38 Ready mixed lead / zinc paint Lit 231.00
39 Ready mixed oil paint Lit 231.00
40 Ready mixed primer for steel Lit 165.00
41 Rubber gasket ( 6 mm thick ) Kg 99.00
42 Sand Cum 1150.00
43 Godhra sand for mortar lining work @ source
Cum 1265.00
44 Spun yarn Kg 88.00
45 Stone aggregate – 10 mm Cum 900.00
46 Stone aggregate – 20 mm Cum 850.00
47 Stone aggregate – 40 mm Cum 800.00
48 Stone at quarry Cum 405.00
49 Structural steel MT 5100.00
50 TCL ( bleaching powder ) Grade - I ( 5 kg pack )
Kg 25.00
51 TCL ( bleaching powder ) Grade - I ( 10 kg pack )
Kg 25.00
52 TCL ( bleaching powder ) Grade - I ( 25 kg pack )
Kg 25.00
53 Teak wood Cum 69200.00
54 Tor steel MT 48500.00
55 Walling ( 100 mm x 100 mm ) Cum 16500.00
56 Welding rod having weight 5.25 kg Box 1450.00
57 Welding rod having weight 5.25 kg - 4.0 M
Box --
58 White cement Kg 33.00
59 White lead Kg 150.00
60 Wire Kg 71.00
61 Plywood commercial (12 mm thk.
Waterproof for centering )
Sqm 720.00
(Taken in analysis for RCC items only)
LABOUR
1 Assistant fitter No 352.00
2 Bandhani No 351.00
3 Bhisti with pakahal No 267.00
MIHIR
70
4 Blacksmith ( IInd class ) No 303.00
5 Breaker No 339.00
6 Carpenter ( Ist class ) No 399.00
7 Carpenter ( IInd class ) No 363.00
8 Chiseller No 339.00
9 Excavator No 303.00
10 Fitter ( Ist class ) No 399.00
11 Glazier No 303.00
12 Helper No 267.00
13 Hole driller No 339.00
14 Mason ( Ist class ) No 436.00
15 Mason ( IInd class ) No 399.00
16 Mazdoor ( female ) No 267.00
17 Mazdoor ( heavy ) No 303.00
18 Mazdoor ( light ) No 267.00
19 Mazdoor ( male ) No 267.00
20 Mistri No 363.00
21 Mukadam No 363.00
22 Painter ( for colouring ) No 333.00
23 Painter No 351.00
24 Polisher No 333.00
25 Pump driver No 339.00
26 Stone cutter or dresser No 399.00
27 Tile layer No 399.00
28 Welder No 399.00
29 Welder for pipeline No 399.00
30 Whitewasher No 333.00
31 Tile turner No 363.00
32 L.M.V. driver No 339.00
33 Electrician No 339.00
MIHIR
71
7.REFERENCES
i. Dan Aluform Consultancy Limited (www.danaluform.com)
ii. Building cost comparison between conventional and formwork system by Nuzul
Azam Haron, Salihuddin Hassim, Mohd Razaliabd Kadir, Mohd Saleh Jaafar.
iii. IS 4990:1993 - Indian Standard “Plywood for concrete shuttering work –
Specification (2nd Revision)” published by Bureau of Indian Standards.
iv. Seminar report on “Mivan – A versatile formwork” by Tilak Bhattacharya,
Rajarambapu Institue of Technology.
v. Report on “Aluminium Formwork System – An Introduction” by Prasanth s,
Grand Edifice Developers.
vi. Maharashtra Jeevan Pradhikaran – Schedule of Rates (2012-13) – Pune Region
vii. Book: “The A to Z of Practical Building Construction and its Management” by
Sandeep Mantri