CLIENT: Zabeel Investement CLIENT: Zabeel Investement CLIENT: Zabeel Investement CLIENT: Zabeel Investement
L.I.CL.I.CL.I.CL.I.C
Planning Departement
Package No. : D0469
Planned Progress % Actual Progress % Variance % Ahead/Behind
Ceiling 60.78% 0.35% -60.43% Behind
Residential Tower N4 63.34% 0% -63% Behind
Residential Tower N3 54.74% 0% -55% Behind
Residential Tower N2 48.83% 0% -49% Behind
Residential Tower N1 46.95% 0% -47% Behind
Residential Tower S3 74.56% 1% -74% Behind
Residential Tower S2 73.06% 1% -72% Behind
Residential Tower S1 71.89% 0.95% -71% Behind
Hotel Tower H1 61.74% 0% -62% Behind
Hotel Tower H2 54.50% 0% -55% Behind
Planned Progress % Actual Progress % Variance % Ahead/Behind
Ceiling 60.78% 0.35% -60.43% Behind
Residentials 61.91% 0.50% -61% Behind
Hotel 58.12% 0% -58% Behind