SUBTERRANEAN FAUNA MANAGEMENT PLAN 1 ......1 The Subterranean Fauna Management Plan is a subset of...
Transcript of SUBTERRANEAN FAUNA MANAGEMENT PLAN 1 ......1 The Subterranean Fauna Management Plan is a subset of...
Extension to the Wiluna Uranium Project
Public Environmental Review Page 3-1
SUBTERRANEAN FAUNA MANAGEMENT PLAN1
1 Environmental Factor
To maintain stygofauna and troglofauna representation, diversity, viability and ecological function at
the species, population and assemblage level.
2 Relevant Legislation and Standards
Subterranean fauna are protected under the following State and Federal legislation:
Wildlife Conservation Act 1950 (WC Act) (WA);
Environmental Protection Act 1986 (EP Act) (WA); and
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) (Cwlth).
The Environmental Protection Authority of Western Australia (EPA) has developed two key documents
to guide the assessment process for activities that could potentially impact on subterranean fauna:
Guidance Statement No. 54a Sampling Methods and Survey Considerations for Subterranean
Fauna in Western Australia (Technical Appendix to Guidance Statement 54) (2007); and
Environmental Assessment Guideline (EAG) 12 for consideration of Subterranean Fauna in
Environmental Impact Assessment in Western Australia (2013).
These documents provide advice to proponents and the public on the EPA’s minimum requirements
for environmental impact assessment (EIA) and management of subterranean fauna.
3 Project Background
Toro was granted approval in October 2012 by the Western Australian Minister for Environment,
to develop and operate the Wiluna Uranium Project (the Project), located near Wiluna
(Ministerial Statement No: 913). In April 2013, Federal approval was also granted by the Federal
Minister for Sustainability, Environment, Water, Population and Communities (EBBC 2009/5174).
The approved Project consisted of two uranium deposits, Centipede and Lake Way, and the West
Creek borefield (Figure 1). As part of the approval, Ministerial Statement No. 913 imposed two
1 The Subterranean Fauna Management Plan is a subset of the Environmental Management Plan
Extension to the Wiluna Uranium Project
Public Environmental Review Page 4-2
conditions related to stygofauna: Condition 7 Management of Groundwater Drawdown Impacts
on stygofauna, Tecticornia and inferred groundwater dependent vegetation located within the
groundwater drawdown (0.5 mRL) area); and Condition 11 The assessment and management of
potential impacts to stygofauna (Appendix A).
Since both State and Federal approvals were granted for the Project, Toro acquired two additional
deposits, Millipede and Lake Maitland, and proposes to integrate both deposits into an extended
Wiluna Uranium Project (Environmental Protection Authority 2014) (Figure 1). The Millipede
deposit is directly adjacent to the previously approved Centipede deposit that is associated with
the Hinkler Well calcrete on the western margin of the Lake Way playa. The Lake Maitland
deposit is approximately 105 km southeast of the Millipede deposit and associated with the
Barwidgee calcrete system on the north western margin of Lake Maitland playa.
The Barwidgee, Hinkler Well, Lake Violet, and Uramurdah calcrete systems that are associated with
the Project areas are known to host diverse stygofauna and troglofauna assemblages (Figures 2 to 5).
The stygofauna assemblages associated with each of the calcrete systems are listed as Priority
Ecological Communities (PECs). These PECs are recognised due to the assemblages of stygofauna
invertebrates recorded from the groundwater within each calcrete system. The areas are classified as
a priority 1, under the Western Australian Wildlife Conservation Act (1950), due to the ‘poorly known
ecological communities’ that are ‘known from very few occurrences with a very restricted distribution’.
4 Scope and Objectives
This Subterranean Fauna Management Plan (SFMP) outlines the potential impacts on subterranean
fauna posed by the proposed development of the Millipede and Lake Maitland deposit areas and
management measures to manage and minimise any such impacts. The SFMP will aim to align and
integrate with Ministerial Conditions 7 and 11, where applicable.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 4-3
Figure 1: Wiluna Uranium Project area locations relative to neighbouring calcrete systems and associated stygofauna PECs.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 4-4
Figure 2: Overview of stygofauna sample locations for Lake Way associated Project areas.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 4-5
Figure 3: Overview of troglofauna sample locations for Lake Way associated Project areas.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 4-6
Figure 4: Overview of stygofauna sample locations for Lake Maitland associated Project areas.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 4-7
Figure 5: Overview of troglofauna sample locations for Lake Maitland associated Project areas.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 5-8
5 Subterranean Fauna: General Information
5.1 Definition
The term ‘subterranean fauna’ refers to both terrestrial (troglofauna) and aquatic (stygofauna)
organisms, predominantly comprised of invertebrates that occur in underground environments.
Stygofauna (groundwater fauna) are confined to groundwater aquifers. Troglofauna (air-breathing
subterranean fauna) occur in non-saturated subterranean environments above groundwater
aquifers. Both stygofauna and troglofauna are regarded as short range endemic species (SREs) as
they are often obligate inhabitants of subterranean environments and therefore often have
restricted distributions. Short range endemic species are defined as species that have geographically
restricted ranges of less than 10,000 km2 and are considered more vulnerable to extinction because
of their limited distribution range (Harvey et al. 2011, Harvey 2002).
5.2 Prospective Habitat
The prospective habitat for subterranean fauna is dependent on the presence of underground voids
of suitable size and connectivity to satisfy biological requirements. Subterranean fauna were
previously believed to be mostly restricted to karst landscapes (limestone or calcrete dominated
systems) that are considered to provide optimal habitat conditions. In more recent times
subterranean fauna have been found to occur in various types of non-karstic geologies and aquifer
systems that exhibit suitable voids for colonisation. Stygofauna are now known to occur in non-
karstic aquifers in course alluvial sediments, fractured rock, pisolites and thin rocky regoliths.
Likewise, recent surveys have identified troglofauna from non-karstic geologies such as vuggy pisolite
ore beds, and fractured and weathered rock formations in the Pilbara and Yilgarn regions. A
relatively high humidity is also considered to be a key requirement for troglofauna existence.
The extent of subterranean habitat present is dependent on the interconnection of sub-surface
crevices, fractures and voids, within suitable geological units and aquifer systems. Hydrogeological
studies can give an indication of the extent of stygofauna habitat present using groundwater flow or
yield characteristics (aquifer parameters). For troglofauna, knowledge of the geological facies
present can also give an indication of the extent of habitat.
5.3 Potential Impacts
The main direct potential impacts on subterranean fauna generally associated with mining activities
are:
removal of habitat through mining excavation of proposed pit areas; and
Extension to the Wiluna Uranium Project
Public Environmental Review Page 6-9
drying out of habitat through the lowering of the groundwater table either associated with
the dewatering of mine pits, or groundwater abstraction from proposed production
borefields.
The removal of habitat through mining excavation poses the greater risk to the conservation of
stygofauna and troglofauna species relative to the lowering of the groundwater table only. Mining
excavation will remove potential habitat for good with no prospect for rehabilitation. However,
groundwater drawdowns are considered to be more relatively short term impacts with natural
restoration of groundwater levels post cessation of mining activities.
Groundwater drawdowns are considered to have greater impacts on stygofauna compared to
troglofauna because lowering of the groundwater table can directly reduce the extent of saturated
stygofauna habitat available. In the case of troglofauna, their reliance on stable and relatively high
humid conditions can make them susceptible to artificially changing water tables, particularly if the
lowering of the water table is sufficient to dry out the inhabited zone which could have significant
impacts on any troglofauna species present. However, impacts would be considered negligible if the
proposed groundwater drawdown associated with proposed mining activities were not of a
significant magnitude to deprive the inhabited subterranean environments of a sufficiently high
relative humidity to render them uninhabitable. In addition, the lowering of the water table could
mean that portions of saturated geology containing suitable habitable voids will become unsaturated
and potentially available for colonisation.
Potential indirect impacts posed by proposed mining developments that could impact on aquifers
inhabited by stygofauna include:
fuel spills; and
increase in sediment load in run-off from mining activities that could reduce surface-
subsurface water exchange during flow periods (e.g., lessen input of resources) and alter
groundwater chemistry.
6 Project Area Subterranean Fauna Values
6.1 Millipede/Centipede Project Area
For the environmental impact assessment (EIA) of the proposed Millipede/Centipede
development, 106 stygofauna and 151 troglofauna samples were collected from the Hinkler Well
calcrete system (Figures 6 and 7) (MWH 2015, Outback Ecology 2011, 2012c). The development
Extension to the Wiluna Uranium Project
Public Environmental Review Page 6-10
of the Centipede deposit has been previously approved (refer section 4.1) with Ministerial
Conditions 7 and 11 imposed. The survey effort conducted recorded 32 stygofauna and nine
troglofauna species from the Hinkler Well calcrete system. An additional four stygofauna species
are known from published records to occur in the Hinkler Well calcrete system, with distributions
extending to the non-impact area of the aquifer system, west of the Goldfields Highway. This
brings the known species richness of the Hinkler Well calcrete stygofauna PEC to 36 species in
total.
6.2 Lake Maitland Project Area
For the assessment of the proposed Lake Maitland development, 165 stygofauna and 110
troglofauna samples were collected (Figures 8 and 9) (Outback Ecology 2012a, b). The survey
effort conducted recorded 27 stygofauna and nine troglofauna species from the Barwidgee
calcrete system. An additional stygofauna species is known from published records to occur in
the Barwidgee calcrete system, with the recorded location occurring in the non-impact area of
the aquifer system, northwest of Little Well. This brings the known species richness of the
Barwidgee calcrete stygofauna PEC to 28 species in total.
6.3 Lake Way and West Creek Borefield Project Areas
The proposed Lake Way deposit and West Creek Borefield developments have been previously
approved (refer section 4.1) with Ministerial Conditions 7 and 11 imposed. For the assessment of
these approved developments, 118 stygofauna and 131 troglofauna samples were collected
(Figures 10 and 11). The assessments, including published records, recorded 36 stygofauna and
nine troglofauna species from the Lake Way project survey area associated with the Uramurdah
calcrete system; and 35 stygofauna and four troglofauna species from the West Creek Borefield
project survey area associated with the Lake Violet calcrete system.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 6-11
Figure 6: Millipede/Centipede stygofauna sampling locations.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 6-12
Figure 7: Millipede/Centipede troglofauna sampling locations.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 6-13
Figure 8: Lake Maitland stygofauna sampling locations.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 6-14
Figure 9: Lake Maitland troglofauna sampling locations.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 6-15
Figure 10: Lake Way and West Creek Borefield stygofauna sampling locations.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 6-16
Figure 11: Lake Way and West Creek Borefield troglofauna sampling locations.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 17
7 Roles and Responsibilities
The roles and responsibilities for subterranean fauna management by Toro are outlined in Table 1. .
Table 1: Roles and Responsibilities
Position Responsibility
Environmental Manager Implementation of this management plan
Review the plan and make changes as required
Environmental Superintendent Ensure staff are aware of their obligations under this plan
Undertake stygofauna and troglofauna monitoring as required
Ensure dewatering monitoring is occurring
Maintain site records of all monitoring
Operations Managers and Site Supervisors
Ensure the plan is being adhered to on site
Participate in the management of this plan as required
Staff, Contractors and Visitors Minimise impacts on the environment
Report all incidents within 24 hours
Clean up all spills
8 Environmental Management
8.1 Project Impacts
Impacts posed by the development of the proposed Millipede/Centipede and Lake Maitland Project
areas can be categorised as being either direct or indirect. Direct impacts, in order of severity of impact
posed, may include:
Mine pit excavation;
Groundwater abstraction;
Dewatering during mining operations;
Contamination of groundwater from spills and leaks; and
Changes to groundwater chemistry.
Indirect impacts may include:
Changes in radionuclide concentrations in the environment above normal background levels;
and
Changes in groundwater flows due to altered sub-surface hydrology during mining.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 18
8.2 Mine Pit Excavation
Subterranean fauna habitat that occurs within the proposed Millipede and Lake Maitland mine pit
boundaries will be lost with mining excavation and will represent a residual impact. Avoidance and
minimisation measures to reduce the impact of mining excavation on components of the
subterranean fauna assemblage recorded are limited. However, proposed mining areas are well
defined and the use of efficient surface mining methods will ensure only target areas will be
disturbed, thereby limiting the area of impact.
8.3 Dewatering
The Millipede and Lake Maitland deposits proposed to be mined require dewatering, the extent of
which is based on the size of the area to be mined, but at the ore bodies themselves local
dewatering could lower the water table by up to 10 m bSWL.
Modelling (RPS Aquaterra, 2010a) was undertaken to ascertain predicted total dewatering volumes
during the life of mine and simulate the use of water barriers to assess their impacts on dewatering.
Prediction Run 1 simulated the mining, without the use of cut-off walls to help decrease inflow to
the open pits, whilst Prediction Run 2 included the simulation of cut-off walls installed around and
within the mine area to help control groundwater inflows (RPS Aquaterra, 2010b). Field trials
undertaken by Toro (2011) and Golder Associates (2011) have confirmed that the barriers have a
similar effect in the field as in the model and can be used to limit water ingress. Field studies have
shown that this ingress may be reduced by up to 80% (Toro, 2011).
At the Lake Maitland borefield, modelling of the drawdown was based upon expected water
demands without the use of barriers. The modelling demonstrated that large drawdowns are
confined to the immediate vicinity of the pumping areas (RPS Aquaterra, 2010a).
8.4 Tailings Deposition
At Millipede, mined pit voids would be back filled with mine overburden as well as used for storage
of tailings created during the processing of the ore. The tailings would be highly alkaline and, in
conjunction with worked mine overburden, would not be considered to provide suitable substrate
for stygofauna or troglofauna habitat.
Toro has undertaken modelling to investigate how uranium in the groundwaters would increase due
to seepage from the Tailings Storage Facility (TSF). The model found that, if unchecked, seepage
could increase groundwater uranium concentrations significantly. Interactions between the tailings
liquids and the clay barrier that would line the pits was input to the model, along with dilution and
Extension to the Wiluna Uranium Project
Public Environmental Review Page 19
reduction due to lake sediments (as demonstrated by Toro during recent drilling). With these inputs
it was found that seepage from the TSF would not lead to significant impacts to local groundwaters
(Prommer et al, 2015).
8.5 Groundwater Reinjection
The Project proposes to reinject mine pit water at the Lake Maitland deposit as a means of managing
potential excess water during operational periods or as a result of significant rainfall events. Water
from the Lake Maitland pit area would be generally hypersaline and not suitable for Project use.
Reinjection of this hypersaline water into the fresh water systems of the Barwidgee calcrete can
alter the salinity of the region and lead to widespread and potentially significant subterranean fauna
habitat loss in the Barwidgee calcrete system.
Toro has identified a preferred borefield to the south of the Lake Maitland deposit in a region where
the groundwater is saline (>14,000 mg/L salinity) (Pennington Scott, 2015). This region is separated
from the Barwidgee Calcrete by some 6km and groundwater flows within the nominal borefield
region flow away from the Barwidgee calcrete and back towards the lake (Pennington Scott, 2015).
For this reason, it is considered unlikely that the reinjection of groundwater will pose a long-term
threat to local subterranean fauna populations.
8.6 Spills and Localised Contamination
Spills or leaks from hydrocarbons or chemicals in the plant area, or from any vehicles or equipment
on the mine site may contaminate soil and groundwater affecting subterranean fauna communities.
On-site chemicals and hydrocarbons would be stored in bunded containers which would be stored in
areas away from drainage lines. Storage vessels and pipelines would be fitted with detection systems
to promptly inform Toro of any leaks. In order for a leak to significantly impact stygofauna species, it
would need to be a prolonged discharge or a catastrophic failure. Given the unlikelihood of such
events occurring due to engineered storage (e.g. double lined/bunded fuel cells) and standard
operating procedures, hydrocarbon and chemical spills would be identified and cleaned up and
remediated in a timely manner. It is considered that groundwater contamination in this area would
be a minor environmental impact.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 20
9 Environmental Objectives and Performance Indicators
The environmental objectives and performance indicators for management of impacts on
subterranean fauna are outlined in Table 2.
Table 2: Environmental Objectives and Performance Indicators
Environmental Objective Performance Indicator
Maintain the abundance and diversity of subterranean fauna species occurring within the Project area
Regular monitoring of subterranean fauna assemblages show that no long-term changes in species richness and assemblage composition is occurring
Avoid or minimise adverse impacts on subterranean fauna assemblages
Groundwater drawdown levels monitoring saturated extent of aquifer shows proposed modelled drawdown extents (vertical and lateral) are not exceeded
Groundwater quality parameters monitored and show that no change in groundwater chemistry due to abstraction or reinjection occurs
Groundwater SWL recovery occurs at or faster than modelled recovery
Subterranean fauna surveys show no decline in species richness and assemblage composition
Ensure no long-term or legacy impacts on subterranean fauna populations
Post-closure monitoring shows the leaching from tailings is not occurring
Contaminant transport monitoring is at or below modelled levels
Subterranean fauna surveys show no decline in species richness and assemblage composition
Extension to the Wiluna Uranium Project
Public Environmental Review Page 21
10 Environmental Aspects and Management Strategies
The environmental aspects and management strategies are presented in Table 3.
Table 3: Environmental Aspects and Management Strategies
Environmental Aspect Management Strategy
Pit excavation Pit outline identified early and surveyed for subterranean fauna
Ongoing periodic sampling of bores within the proposed mine footprint
Water barriers installed to prevent lateral flows of water and reduce the need for dewatering
Dewatering and Reinjection
Ongoing groundwater chemistry monitoring to ensure no changes to groundwater composition are occurring
Monitoring of drawdown rates to ensure that drawdown is occurring as modelled
Groundwater abstraction rates kept within approved Project limits
Sampling of established subterranean fauna bores to ensure assemblages are persisting
Regular monitoring of reinjection borefield for impacts such as mounding
Tailings Deposition Mine voids to be lined with compacted clay prior to tailings deposition
Water barriers installed during mining to prevent water ingress left in place, to prevent tailings egress
Downstream monitoring to commence after tailings cells are backfilled to identify any leakage of contaminants specifically uranium and other radionuclides
Spills and Contamination Spills to be cleaned up immediately
Storage of fuels and reagents to be in bunded areas to prevent contamination of the environment
Regular monitoring of local groundwaters for contaminants to identify whether fuels or reagents are making their way into the environment
Changes in Water Quality
Continued monitoring of local and regional bores to determine whether groundwater chemistry is being adversely impacted by mining activities
Monitoring to include radionuclide concentrations to ensure that they remain stable
Extension to the Wiluna Uranium Project
Public Environmental Review Page 22
10.1 Monitoring
Subterranean fauna monitoring is outlined in Table 4. The monitoring program would involve the
establishment of monitoring bores for each Project area designed to facilitate the survey of
stygofauna and troglofauna, as well as groundwater parameters from within impact areas and from
control bores outside of impact areas. Initially, it would be recommended that monitoring would
consist of four sample rounds per year (quarterly), with the seasonal timing of each sample round
kept consistent between each monitoring year. Complementing the sample rounds for
subterranean fauna would be the more frequent collection (monthly) of groundwater parameters
(e.g. SWL, salinity) undertaken by Toro onsite personnel that would be assessed to ensure
groundwater drawdowns and quality are not exceeding (or approaching exceedance) with modelled
parameters. If the first three to four years of quarterly monitoring indicate that subterranean fauna
assemblages are stable, and monitoring of groundwater levels and physicochemical parameters
continues monthly, then surveys may be reduced to biannually or annually, following consultation
with, and approval from DPAW.
Table 4: Subterranean Fauna Monitoring
Aspect Frequency
Subterranean Fauna Populations
Quarterly surveys of subterranean fauna
Surveys may become biannual if assemblages are shown to be stable
Pit Dewatering Volume Pumps to be fitted with meters to monitor volumes
Data to be collected monthly
Drawdown Level loggers will be placed into monitoring bores to continually monitor drawdown around mine pits (Lake Way, Millipede/Centipede, and the borefields
Pumps at the borefields to be fitted with meters and abstraction volumes are not to exceed section 5C limits
Data to be recovered monthly
Reinjection Volume Reinjection pumps to be fitted with meters to monitor volumes
Volumes to be collected monthly
Groundwater Quality Monthly analysis of basic water chemistry including EC, salinity, dissolved metals
Formulation of groundwater parameter trigger values for each Project area
Quarterly analysis of radionuclides
Annual analysis of organic compounds and potential contaminants
Tailings Storage Facility Integrity
Constant monitoring using real time data loggers that detect changes in EC, uranium concentration and other radionuclide concentrations.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 23
10.2 Trigger Levels
The following trigger levels would be established to inform Toro when contingency measures to
manage subterranean fauna are to be implemented (Table 5).
Table 5: Stygofauna Impacts Trigger Levels
Impact Trigger Level
Excess drawdown Level logger devices show that drawdown is occurring faster than modelled predictions
Monitoring bores SWL show that modelled lateral extent of groundwater 0.5 m bSWL drawdown is exceeded, or likely to be exceeded
Change in subterranean fauna community composition
The assessment of monitoring survey results find a significant reduction in the diversity of subterranean fauna assemblages compared to comparable seasonal baseline results
Changes in groundwater chemistry
Where groundwater monitoring finds that concentration of any analyte is more than two standard deviations from seasonally adjusted established trigger value means contingency action would be taken.
Reinjection is planned to occur inside the 14,000 mg/L salinity zone. If salinities in the zones that are less than 14,000 mg/L are found to increase by more than two standard deviations from seasonally adjusted averages, contingency actions would be taken.
10.3 Contingencies
If a significant change is recorded that can be attributed to the Project, the following would occur:
If there is a saline water/oil/chemical spill, operations in that area would cease until the spill was
halted and cleaned up (including removal of contaminated soil). Depending on the extent of
contamination a survey to ensure all contaminated material has been removed, may be
required.
In the event the subterranean fauna survey identifies a species that may be localised to the
Project area, further sampling outside the Project area may be undertaken to provide more
certainty about the range of the species. Conservation measures may be taken in consultation
with the Department of Environment Regulation and the WA Museum,
If groundwater drawdown is occurring at a faster rate than modelled, and /or extending laterally
or vertically in exceedance of modelled drawdown contours, then the mining method would be
examined to determine if smaller mining cells can be implemented to reduce drawdown.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 24
If seepage in the TSF is identified, work would commence immediately on repairing any breach
and further investigations will take place to find a permanent solution.
Where salinity in the fresh/brine water systems was found to be increasing, the borefield
configuration would be changed with those bores closest to the areas of salinity increase turned
off to give groundwater time to recover.
If there was a prolonged drought, then the rate of abstraction would be monitored to assess
rates of change and dewatering activities may be altered to minimise impacts on subterranean
fauna communities.
10.4 Interpretation and Reporting
Data would be analysed as it is gathered and aim to identify any trends and patterns including;
Any spills;
Any breaches of the TSF wall;
The overall groundwater chemistry, including establishment and modification of trigger values;
and
Groundwater abstraction rates.
All data would be included in Toro’s Annual Environment Report and made publicly available.
10.5 Review and Revision
A more comprehensive SFMP would be designed in consultation with DPAW for approval prior to
groundwater dewatering occurring at any of the proposed Project areas. The SFMP would be
actively managed with annual reviews occurring after the analysis of the monitoring data, and any
actions taken to modify the plan.
References
Environmental Protection Authority. (2007) Guidance for the assessment of environmental factors (in accordance with the Environmental Protection Act 1986). Sampling methods and considerations for subterranean fauna in Western Australia - No. 54a. Technical appendix to guidance statement 54. Environmental Protection Authority, Western Australia.
Environmental Protection Authority. (2013) Environmental Assessment Guideline (EAG) 12 for consideration of subterranean fauna in environmental impact assessment in Western Australia.
Environmental Protection Authority. (2014) Extension to the Wiluna Uranium Project (CMS 14025 Assessment No: 2002 Environmental Scoping Document September 2014.
Harvey, M. E., Rix, M. G., Volker, W. F., Hamilton, Z. R., Johnson, M. S., Teale, R. J., Humphreys, G. and Humphreys, W. F. (2011) Protecting the innocent: studying short-range endemic taxa enhances conservation outcomes. Invertebrate Systematics 25: 1-10.
Harvey, M. S. (2002) Short-range endemism among the Australian fauna: some examples from non-marine environments. Invertebrate Systematics 16: 555-570.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 25
MWH. (2015) Wiluna Uranium Project: Millipede Targeted Subterranean Fauna Assessment Report prepared for Toro Energy Ltd.
Outback Ecology. (2011) Wiluna Uranium Project Subterranean Fauna Assessment, March 2011. Prepared for Toro Energy Ltd, Perth, Western Australia.
Outback Ecology. (2012a) Lake Maitland Uranium Project Level 2 Stygofauna Assessment Prepared for Mega Lake Maitland Pty Ltd, Perth, Western Australia.
Outback Ecology. (2012b) Lake Maitland Uranium Project Level 2 Troglofauna Assessment Prepared for Mega Lake Maitland Pty Ltd, Perth, Western Australia.
Outback Ecology. (2012c) Wiluna Uranium Project Stygofauna Assessment Prepared for Toro Energy Ltd, Perth, Western Australia.
Extension to the Wiluna Uranium Project
Public Environmental Review Page 26
Appendix A: Ministerial Conditions 7 and 11 (Ministerial Statement 913)
7 Groundwater Drawdown
Management of Groundwater Drawdown Impacts on stygofauna, Tecticornia and inferred groundwater dependent vegetation located within the groundwater drawdown (0.5 mRL) area.
7-1 Prior to groundwater abstraction for dewatering, unless otherwise approved by the CEO, the proponent shall prepare a Groundwater Drawdown Monitoring and Management Plan for approval by the CEO to limit potential impacts on stygofauna, Tecticornia dominated vegetation and inferred groundwater dependent vegetation through the design and implementation of a suitable groundwater barrier system around the Project mining areas. The Groundwater Drawdown Monitoring and Management Plan shall include:
1. development of trigger levels for groundwater drawdown levels;
2. design and implementation details of a barrier system to control groundwater drawdown so that the trigger levels are not exceeded; and
3. implementation of the outcomes of the Groundwater Dependent Vegetation Research Plan required by Condition 6-6.
7-2 Prior to groundwater abstraction for dewatering, the proponent shall implement the approved Groundwater Drawdown Monitoring and Management Plan required by condition 7-1 and any subsequent approved revisions, until advised by the CEO that implementation of the Groundwater Drawdown Monitoring and Management Plan can cease.
7-3 Should the results of monitoring from the implementation of the Groundwater Drawdown Monitoring and Management Plan required by condition 7-1 show that trigger levels identified in condition 7-1(1) have been reached or exceeded, the proponent shall take immediate corrective actions to protect Tecticornia dominated vegetation and inferred groundwater dependent vegetation in
Extension to the Wiluna Uranium Project
Public Environmental Review Page 27
response to monitoring results, and shall provide a report to the CEO within 21 days of the trigger levels being reached or exceeded which:
1. describes the event resulting in a trigger level being reached or exceeded;
2. provides information which allows determination of the likely root cause of the trigger levels being reached or exceeded; and
3. proposes actions and associated timelines to remediate the cause of the trigger values becoming reached or exceeded.
7-4 Should the trigger levels being reached or exceeded identified in condition 7-2 be determined by the CEO to be caused by activities undertaken in implementing the proposal, the proponent shall, on approval by the CEO, implement the actions identified in condition 7-3(3) until the CEO determines that the remedial actions can cease.
11 Fauna - Stygofauna
The assessment and management of potential impacts to stygofauna.
11-1 Prior to groundwater abstraction for dewatering, unless otherwise approved by the CEO, the proponent shall prepare a Stygofauna Monitoring Plan for approval by the CEO on advice of the DEC. The Stygofauna Monitoring Plan shall include:
1. a survey regime for stygofauna in the Hinkler Well, Uramurdah and Lake Violet calcretes both within and outside the area of impact of the proposal; and
2. a monitoring regime for water quality and quantity in the Hinkler Well, Uramurdah and Lake Violet calcretes both within and outside the area of impact of the proposal.
11-2 Prior to groundwater abstraction for dewatering, unless otherwise approved by the CEO, the proponent shall implement the approved Stygofauna Monitoring Plan required by condition 11-1 and any subsequent approved revisions until advised by the CEO that implementation of the Stygofauna Monitoring Plan can cease.
11-3 Should results of monitoring from the implementation of the Stygofauna Monitoring Plan required by condition 11-1 show a significant change in groundwater quality and quantity not identified through the implementation of condition 7-1, the proponent shall provide a report to the CEO within 21 days which:
1. describes the event resulting in a significant change; and
2. provides information which allows determination of the likely cause of the significant change;
3. proposes actions and associated timelines to remediate the significant change.
11-4 Should the significant change in groundwater quality and quantity be determined by the CEO to be caused by activities undertaken in implementing the proposal, the proponent shall, on approval by the CEO, implement the actions identified in condition 11-3(3)
Extension to the Wiluna Uranium Project
Public Environmental Review Page 28
until the CEO determines that the remedial actions can cease.