Substation/Enclosed Switchgear/PCC Fundamentals Niel Miele, PE, LEED AP PACS Industries

Transcript of Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI...

Page 1: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Substation/Enclosed Switchgear/PCC Fundamentals

Niel Miele, PE, LEED AP PACS Industries

Page 2: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Let’s go Golfing

Page 3: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Swing = Energy

Page 4: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

The Water Tank

Page 5: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Voltage

Page 6: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Impulse

Page 7: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Voltage

Page 8: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Nominal Current

Page 9: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Short Circuit Current

Page 10: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Electrical System

• Voltage – Steady State – Basic Impulse Level (BIL)

• Current – Nominal – Short Circuit

Page 11: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Dangerous Territory

Page 12: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Electrical Danger

• Electrical Current is Very Powerful • Any Path to Ground Results in Electrical

Current • Less Than 100mA Can Kill • Electrical Current Can Jump Between

Conductors • Arc Fault

Page 13: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Arc Flash

Page 14: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Arc Flash

Page 15: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Arc Flash

• Plasma Arc Can be Greater than 35,000 Degrees

• Copper Expands and Vaporizes by a Factor of 67,000

• Arc Blast at 160dB • Flame, Metal, Smoke and Debris Expel at

600MPH

Page 16: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Arc Flash Boundaries

Page 17: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Arc Flash Boundaries @ 13.8kV

26 INCHES

7 INCHES

60 INCHES

15 FEET

Page 18: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

System Model

Page 19: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

System Model

Utility

Substation

Consumer

Page 20: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Power Grid

Page 21: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Electrical Substation

• Hub on the Power Grid • Voltage Converter • Distribution Point • Link

Page 22: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Substation Components

• Transformer • Circuit Switches/Breakers • Command and Control System • Communication Network

Page 23: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Circuit Breaker

Page 24: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Circuit Breaker

Page 25: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Circuit Breaker-Low Voltage

Page 26: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Circuit Breaker-Low Voltage

Page 27: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Circuit Breaker-Medium Voltage

Page 28: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Circuit Breaker-High Voltage

Page 29: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Circuit Breaker-Extra High Voltage

Page 30: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Command/Control Systems

• Breaker Control • System Monitoring • Circuit Protection/Logic • Feedback • Metering

Page 31: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Breaker Control

Page 32: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Control Switches

Page 33: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Current Monitoring

Page 34: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Current Transformer

Page 35: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Overcurrent Trip

Page 36: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Voltage Monitoring

Page 37: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Potential Transformer

Page 38: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Undervoltage Trip

Page 39: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Electromechanical Relays

Page 40: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Multi-Function Relay

Page 41: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Multi-Function Relay

Page 42: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Communication

Page 43: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Communication Network

• Multiple Communication Loops • Internal/External

– Status – Health – Data Collection

• Copper and Fiber Optic Connection

Page 44: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Communication Network

Page 45: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

SCADA

• Supervisory Control And Data Acquisition • Series of Inputs and Outputs • Digital • Analog • Master CPU or PLC • Communicates To/From Master Processor

Page 46: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

SCADA

Page 47: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Substation Design Criteria

• IEEE/ANSI Standards/Guidelines – Equipment and Conductor Clearances

• Transmission 69kV – 765kV • Distribution 5kV – 35kV • Overhead Bus and Lines • Large Sites with Civil Issues

– Drainage – Grounding – Steel Foundations

Page 48: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Transmission Substation

Page 49: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Distribution Substation

Page 50: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear Design Criteria

• IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance

• Medium Voltage 5kV – 38kV • High Current 1000A – 5000A • Self Contained in One or More Lines of Cubicles • Indoor or Outdoor • Confined Space for Operation • Metalclad • Arc Resistant

Page 51: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear

Page 52: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear

Page 53: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear

Page 54: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear

Page 55: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear

Page 56: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear

Page 57: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Design Considerations

• Space Allocation – Sufficient Arc Flash Boundary – Work Clearance per NEC

• Controllability • Accessibility • Maintainability • Personnel/Arc Flash Protection

Page 58: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Warning Signs

Page 59: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Personnel Protective Equipment (PPE)

Page 60: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Special Tools

Page 61: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Special Tools

Page 62: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Arc Resistant Switchgear

Page 63: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Power Control Centers

Page 64: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Power Control Centers

Page 65: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Power Control Centers

Page 66: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear Construction

Page 67: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear Construction

Page 68: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear Construction

Page 69: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear Construction

Page 70: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear Construction

Page 71: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear Construction

Page 72: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear Construction

Page 73: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear Construction

Page 74: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear Construction

Page 75: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Manufacturing

Page 76: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Manufacturing

Page 77: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Special Tools

Page 78: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

PPE

Page 79: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Switchgear

Page 80: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Substations

Page 81: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Protection/Controls

Page 82: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Components

Page 83: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Arc Flash

Page 84: Substation/Enclosed Switchgear/PCC Fundamentals · Switchgear Design Criteria • IEEE/ANSI Standards/Guidelines – Internal Bus Needs Phase to Phase/Ground Clearance • Medium

Voltage/Current

• System Voltage • BIL • Nominal Current • Short Circuit Current