Sub Station 220kv Status

21
As on 30.04.2011 Land Acqusition Civi works completed Structure, transformer, sub station eqpt.received Structure, sub station eqpt.erected Transf. erected& tested Original Target Date Actual/ Now Anticipated date 1 2 3 4 5 6 7 8 9 10 11 12 13 A 765/400kV Substations (a) Central Sector 1 Aug-08 a Gaya 765/400 3x1500 A 60% 60% 20% Yet to be started. Aug-12 Mar-12 Efforts being made to complete the sub station earlier. Threats from Maoist extremis is hampering progress b Sasaram 765/400 2x1500 U A * Aug-12 Aug-12 * To be accomodated in the existing HVDC station. Efforts being made to complete progressively from Dec'11 matching with associate line completion. c Fatehpur 765/400 2x1500 A 60% 60% 40% Yet to be started. Aug-12 Mar-12 Engg., civil works & erection under progress. d Lucknow 765/400 2x1500 A 70% 80% 50% Yet to be started. Aug-12 Mar-12 Engg., civil works & erection under progress. e Ranchi 765/400 2x1500 A 20% Aug-12 Aug-12 Engg. & supply under progress. Serious local problem being faced in land acquisation. Critical f 400 kV Balia Aug. to 765 kV 2x1500 A 70% 80% 50% Yet to be started. Aug-12 Mar-12 Engg., civil works & erection under progress. g 400 kV Agra Aug. to 765 kV 2x1500 A 40% 70% 30% Yet to be started. Aug-12 Aug-12 Engg., civil works & erection under progress. Completion affected due to delay in land acquisation. 2 Aug-08 a Fatehpur Extn. 765/400 2x315 A 70% 70% 40% Aug-12 Mar-12 Engg. ,civil works & erection in progress b Gaya Extn. 765/400 2x315 A 0% Aug-12 Mar-12 * Being constructed under DVC (main) project. Award placed in Aug'09. Date of Award Common Scheme for 765kV pooling Station and Network Associated with DVC & Maithon RB Project and import by NR & WR via ER STATUS OF CONSTRUCTION OF ONGOING SUB-STATIONS(220 KV and above) DURING 2011-12 Cummulative progress till date Commissioning Sl. No. Remarks Name of the Sub-Station Voltage ratio (kV/kV) Capacity MW/MVA Supplementary Transmission system Associated with DVC & Maithon Right Bank Project pspm(cea) Sub Stns 1 of 21

Transcript of Sub Station 220kv Status

Page 1: Sub Station 220kv Status

As on 30.04.2011

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

A 765/400kV Substations

(a) Central Sector

1 Aug-08

a Gaya 765/400 3x1500 A 60% 60% 20% Yet to be

started.

Aug-12 Mar-12 Efforts being made to complete the sub

station earlier. Threats from Maoist

extremis is hampering progress

b Sasaram 765/400 2x1500 U A * Aug-12 Aug-12 * To be accomodated in the existing

HVDC station. Efforts being made to

complete progressively from Dec'11

matching with associate line completion.

c Fatehpur 765/400 2x1500 A 60% 60% 40% Yet to be

started.

Aug-12 Mar-12 Engg., civil works & erection under

progress.

d Lucknow 765/400 2x1500 A 70% 80% 50% Yet to be

started.

Aug-12 Mar-12 Engg., civil works & erection under

progress.

e Ranchi 765/400 2x1500 A 20% Aug-12 Aug-12 Engg. & supply under progress.

Serious local problem being faced in

land acquisation. Critical

f 400 kV Balia Aug. to 765 kV 2x1500 A 70% 80% 50% Yet to be

started.

Aug-12 Mar-12 Engg., civil works & erection under

progress.

g 400 kV Agra Aug. to 765 kV 2x1500 A 40% 70% 30% Yet to be

started.

Aug-12 Aug-12 Engg., civil works & erection under

progress. Completion affected due to

delay in land acquisation.

2 Aug-08

a Fatehpur Extn. 765/400 2x315 A 70% 70% 40% Aug-12 Mar-12 Engg. ,civil works & erection in

progress

b Gaya Extn. 765/400 2x315 A 0% Aug-12 Mar-12 * Being constructed under DVC

(main) project. Award placed in

Aug'09.

Date of

Award

Common Scheme for 765kV pooling Station and

Network Associated with DVC & Maithon RB Project

and import by NR & WR via ER

STATUS OF CONSTRUCTION OF ONGOING SUB-STATIONS(220 KV and above) DURING 2011-12

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

Supplementary Transmission system Associated

with DVC & Maithon Right Bank Project

pspm(cea) Sub Stns 1 of 21

Page 2: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

3 Mar-10

a Vindhyachal Pooling station 765/400 2x1500 Nov-12 Award placed in Feb'11..

Completion affected due to land

acquisation.

4 Dec-10

a Jabalpur Pooling station 765/400 2x1500 Dec-13 Tendering under progress.

Northern Region

5 Jul-09

a Jhatikara 765/400 4x1500 A 40% 60% 10% Jan-12 Award placed in Sep'09. Engg. civil

works & erection in progress.

b Meerut (Aug.) 765/400 2x1500 A 30% 40% Jan-12 Engg. & civil works under progress.

c Moga (Aug.) 765/400 2x1500 A 40% 20% Jan-12 Award placed in Nov'09. Engg. & civil

works under progress.

6

a Bhiwani 765/400 2x1500 Part land

acquired

May-12 Award placed in Dec'09. Engg. in

progress. Delay in commencement of

works due to now availability of S/S

land. Now part land handed over &

work being started. Completion

expected by Mar'13.

7 Aug-10

a Bareilly (with 125 MVAR

Reactor)

765/400 2x1500 U A Apr-13 Award under progress.

Western Region

8 Jul-09

a Wardha 765/400 3x1500 A 88% 30% 15% Oct-12 Oct-12 Engg., supply & civil works under

progress.

765KV System for Central Part of Northern Grid -

PART-III

765KV System for Central Part of Northern Grid -

PART-II

Trans. System associated with Mundra Ultra Mega

Power Project

Transmission System for Phase-I

Generation Projects in ORISSA - Part - B.

Transmission System of Vindhyachal-IV and Rihand -

III (1000MW each) Gen. Proj.

Northern Regional System Strengthening

Scheme - XXI

pspm(cea) Sub Stns 2 of 21

Page 3: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

9 Oct-08

a Satna 765/400 2x1000 A 90% 81% 4% Dec-12 Jun-13 Engg., supply & civil works under

progress.

a Indore 765/400 2x1500 A Dec-12 Dec-12 Award placed in Aug'10.

b Bina 765/400 2x1000 A 40% 80% 28% Dec-12 Dec-12 Engg., supply & civil works under

progress.

c Gwalior 765/400 2x1500 A Dec-12 Dec-12 Award placed in Aug'10.

10 Feb-09

a WR Pooling Station near Sipat 765/400 2x1500 A 72% 28% 13% Feb-12 Feb-12 Engg., civil works & erection in

progress.

11 Feb-09

a WR Pooling Station near Sipat

(3rd ICT)

765/400 1x1500 A 10% Feb-12 Feb-12 Engg. & supply under progress.

12

a Raigarh Pooling Station 765/400 4x1500 Aug-13

b Raipur Pooling Station 765/400 1x1500 Aug-13

Eastern Region

13 Sep-10

a Jharsuguda Pooling Station 765/400 2x1500 U A Mar-13 Award placed in Mar'11.

* Land acquisation critical.

b Angul Pooling Station 765/400 4x1500 U A Mar-13 Award placed in Mar'11.

* Land acquisation critical.

(b) State Sector

UTTAR PRADESH (UPPCL) :

Trans. System associated with Sasan Ultra Mega

Power Project

Establishment of Pooling Station at

Raigarh (Korba) and Raipur for IPP Gen.

Proj. in Chhatisgsrh

Part-B- Regional System Strengthening in WR for

Sasan

Western Region System Strengthening-XI

Part-A- Tr. System of Sasan(4000) UMPP

Transmission System for Phase-I

Generation Projects in ORISSA - Part - A.

Western Region System Strengthening-X

pspm(cea) Sub Stns 3 of 21

Page 4: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

1 Unnao 765/400 2x1000 Mar-11 May-11 LOI issued on 23.01.2010.Work

awarded to M/s Crompton Greaves.

Soil testing completed.Foundation

work of Towers in Progress.

2 Anpara C 765/400 2x600 +

1000

Mar-11 May-11 Work awarded to Ms Areva. Soil

testing completed .Pile testing for soil

stablisation in ash dump yard area is

in progress.

3 Mainpuri 765/400 2x1000 May-12 May-12 Proposed under PPP mode

B 400/220kV Substations

(a) Central Sector

1

a Misa (2nd ICT) 400/220 315 A Feb-13 Feb-13 Awarded. Engg. in progres.

2 Feb-09

a Biswanath Chariyali Pooling

Station

400/132 2x200 U A Aug-13 Aug-13 Packages under tendering.

Completion affected due to delayed in

award (ant. in Mar'14)

b Aug. of 400KV Agra S/Stn. 400/220 4x105 A Aug-13 Aug-13 Completion matching with Gen.

NORTHERN REGION

3 Sep-07

a Part-I, GIS Pooling Station near

Chamera-II HEP

400/220 630 ACompleted Completed 95%

Yet to be

received

Mar-10 Aug-11 Testing & commissioning under

progress.

4 Feb-09

a Extn. Patiala (1x500) 400/220 500 A40% 80% 30%

Aug-11 Aug-11 Award placed in July'09. Engg. & civil

works under progress.

b Extn. Malerkotla (1x500) 400/220 500 Commissioned 3/11

5 Dec-09Northern Region System Strengthening-XXIII

Eastablishment of 400/220 kV GIS Pooling Station

near Chamera-II HEP

Part-A : North East - Northern/ Western

Interconnector -I

Northern Region System Strengthening-XIV

North East - NR/WR Inter - connector (Subansiri &

Kameng)

pspm(cea) Sub Stns 4 of 21

Page 5: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

a Extn. Bahadurgarh 400/220 1x500 A 30% 30% Dec-11 Award placed in Mar'10.Engg. & civil

works under progress.

b Extn. Lucknow 400/220 1x500 A 40% 60% 20% Dec-11 Award placed in Mar'10. Engg. & civil

works under progress.

6 Feb-09

a Neemrana 400/220 2x315 A 10% 40% Nov-11 Feb-12 Engg. & civil works under progress.

Completion affectted due to delay in

land acquisation.

b Kotputli 400/220 2x315 U A Nov-11 Feb-12 Engg. in progress. Completion

delayed due to land acquisation (ant.

in Dec'12).

7 Feb-09

a Dehradun 400/220 2x315 U A Nov-11 Feb-13 Engg. in progress. Completion

delayed due to land acquisation (ant.

in Mar'13).

8 Feb-09

a Bagpat (GIS) 400/220 2x500 Feb-12 Mar-13 Engg. in progress. Completion

delayed due to land acquisation (ant.

in Mar'13).

9 Feb-09

a Manesar (GIS) 400/220 2x500 A 2% 10% Nov-11 Mar-12 Engg. & civil works under progress.

Completion matching with line.

10 Dec-09

a Sikar 400/220 2x315 A 40% 40% 10% Aug-12 Award placed in Mar'10. Civil works

under progress.

b Panchkula 400/220 2x315 30% 30% Aug-12 Award placed in Mar'10. Engg. in

progress. Civil works under progress.

11 Mar-10

a Sohawal 400/220 2x315 A 20% Nov-12 Award placed in Aug'10

Northern Region System Strengthening Scheme -

XV

Northern Region System Strengthening

Scheme - XVIII

System Strengthening in Northern Region

for SASAN & MUNDRA (UMPP)

Northern Region System Strengthening

Scheme - XIX

Northern Region Transmission

Strengthening Scheme

Northern Region System Strengthening Scheme -

XIII

pspm(cea) Sub Stns 5 of 21

Page 6: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

b Shahajanpur 400/220 2x315 A 20% Nov-12 Award placed in Aug'10

c Saharanpur 400/220 2x315 U A Nov-12 Award placed in Nov'10

d Jind 400/220 2x315 U A Mar-13 Tendering under progress.

Land acquiation delayed . Section -6

awaited. State Govt. asking for

repeating Section-4 as one year

lapsed after Sec-4.

e Jaipur (South) 400/220 2x500 A 5% 20% Nov-12 Engg. & civil works under progress.

f Bhiwadi Extn. 400/220 1x315 A 10% Mar-13 Award placed in Nov'10

12 Jul-10

a Wanpoh 400/220 2x315 A Jul-13 Award placed in July'10. Engg. in

progress. Land hand-over in Dec'10.

13 Aug-10

a Hamirpur GIS (with 80 MVAR B.

Reactor)

400/220 2x315 U A Mar-13 Award placed in Nov'10. Engg. in

progress. Land acqusition to be

expedited.

14 Dec-10

a Samba (with 80 MVAR B.

Reactor)

400/220 2x315 U A Aug-13 Award under progress.

15 Nov-09

a Bhiwani 765/400 2x315 Part land

acquired

May-12 Award placed in Dec'09. Engg. in

progress. Delay in commencement of

works due to now availability of S/S

land. Now part land handed over &

work being started. Completion

expected by Mar'13.

WESTERN REGION

Northern Regional System Strengthening

Scheme - XXII

765KV System for Central Part of Northern Grid -

PART-III

Northern Regional System Strengthening

Scheme - XVI

Northern Regional System Strengthening

Scheme - XX

pspm(cea) Sub Stns 6 of 21

Page 7: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

16 Dec-07

a Navi Mumbai (GIS) 400/220 630 A 95% 95% 50% Sep-10 Mar-13 Engg., supply, civil works & erection

under progress. Sub station to be

completed matching with commissioning

associated line.

17 Feb-08

a Wardha Extn. 400/220 315 A A A 85% Nov-10 Dec-11 Supply & erection under progress.

b Pune Extn. 400/220 315 A A A 98% Nov-10 Dec-11 Supply & erection under progress.

c Raipur Extn. 400/220 315 A Complected Complected 90% 80% Nov-10 Jun-11 Erection under progress.

18 Apr-08

a Shujalpur 400/220 630 A 95% 95% 78% Jan-11 Oct-11 Engg.,Supply ,civil works & erection in

progress

19 Oct-08

a Bachchau 400/220 630 A Complected Complected 75% 50% Oct-12 May-11 Efforts being made to prepone the

S/Stn. matching with Gen. proj.

b Navsari GIS 400/220 630 A 15% 80% 10% 80% Oct-12 Mar-12 Award placed in July'09. Engg. & civil

works under progress.

c Aurangabad 400/220 630 U A Oct-12 Oct-12 Tendering under progress.

SOUTHERN REGION

20 Kaiga 3 & 4 Trans. System Mar-05

a Kozhikode S/Stn. (2x315) 400/220 630 A Completed Completed Completed 95% Dec-07 Mar-13 Civil work & erection under progress.

Completion matching with line.

21 Kundankulam - APP

Transmission System (Balance

portion)

Mar-05

a Muvattapuzha ( 2nd Trf.) 400/220 315 A Completed Completed Completed 80% Nov-08 Mar-12 * Completion matching with line.

22 Mar-09

a Chulliar (Palakkad) 400/220 2x315 A 30% 70% 10% Jul-11 Feb-12 civil works under progress.

Transmission System Associated with Mundra Ultra

Mega Power Project

System Strenghthening -XI of SR

WESTERN REGION Strengthening Scheme-VI

WESTERN REGION Strengthening Scheme-IX

Western Region System Strengthening-V

pspm(cea) Sub Stns 7 of 21

Page 8: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

23 Dec-09

a Bidadi (GIS) 400/220 2x500 A 70% 80% 10% Mar-12 Award placed in Dec'09.

Engg.,supply, civil works & erection

under progress.

24 Feb-10

a Yelahanka (GIS) 400/220 2x500 A 40% 20% Jun-12 Supply & Civil works under progress.

EASTERN REGION

25 May-10

a Kishanganj 400/220 2x315 U A Jan-13 Award placed in Jun'10. Engg. in

progress.* Land acquisation critical.

26 Jul-10

a Daltonganj 400/220 2x315 U A Nov-12 Tendering under progress.

Completion likely to be delayed (ant.

in Mar13). Land yet to be acquired.

b Bolangir 400/220 2x315 A Nov-12 Award placed in July'10.

c Kenonjhar 400/220 2x315 A Nov-12 Award placed in July'10.

d Chaibasa 400/220 2x315 U A Nov-12 Tendering under progress.

Completion likely to be delayed (ant.

in Mar13). Land yet to be acquired.

e Uttara 400/220 2x315 U A Nov-12 Tendering under progress.

Completion likely to be delayed (ant.

in Mar13). Land yet to be acquired.

f Lakhisarai 400/132 2x200 U A Nov-12 Award placed in Feb'11.Engg. In

progress.

g Banka 400/132 2x200 A Nov-12 Award placed in Feb'11.Engg. In

progress.

System Strengthening - XII of SR

Transmission System for Transfer of

Power from Generation Project in SIKKIM

to NR/WR Part - A.

System Strengthening - X of SR GRID

Eastern Region Strengthening Scheme -

III

pspm(cea) Sub Stns 8 of 21

Page 9: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

27 Mar-11

a Rangpo (GIS) 400/220/

132KV

16x105

3x100

U A Nov-13 Tendering under progress.

28 Feb-10

a Silchar (New) 400/220 2x200 A 40% Mar-12 Work under progress.

(b) STATE SECTOR (SS)

NORTHERN REGION (NR) :

1 Harsh Vihar GIS 400/220 Dec-11

2 Loni S/S (2x315) 400/220 630 Dec-10 Sep-11 (i) Contract awarded on 31.3.2010 with

18 months completion period .Soil testing

done. (ii) Out of 80 hec.,60

hec.land has been accquired.

(iii) Boundary wall construction obstructed

by villagers

System Strengthening

1 Nawada 400/220 2x315 Mar-11 Jun-11

2 Nuhiawali 400/220 3x315 Jun-11 Aug-11 Purchase order placed to M/s GET

Power private Ltd Chennai.

3 Dhanoda(Mohindergarh) 400/220 2x315 Mar-11 Dec-11

UTTAR PRADESH (UPPCL) :

Parichha TPS (2x250MW)

1 Orai S/S 400/220 2x315 Apr-11 May-12 Land available.

2 Paricha Ext. 400/220 2x315 Dec-10 Jun-12

WESTERN REGION (WR) :

DELHI (DTL)

Transmission System associated with

Pallatana gas Based Power Project and

Bongaigaon Thermal Power Station

(BTPS)

HARYANA (HVPNL)

Transmission System for Transfer of

Power from Generation Project in SIKKIM

to NR/WR Part - B.

pspm(cea) Sub Stns 9 of 21

Page 10: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

Bhilai TPP (P) (JV- NSPCL)

1 NSPCL (2x315 MVA) ICT - II 400/220 630 Oct.07 Jun-11 Failed during S C test. Under repair

Korba (W)

1 Raipur (2x315 MVA) 400/220 630 Oct.07 Mar-12 Order placed 7/09,WIP.

GUJARAT (GETCO) :

1 Rajkot(Hadala) ICT-II 400/220 1x315 Mar-08 Jun-11

system strengthening

1 Halvad 400/220

Khaperkheda TPS

1 Khaperkheda S/S (2x500) 400/220 1000 Oct-10 May-11

System Strengthening

1 Bhusaval (2x500) 400/220 1000 Mar-11 May-11 Test charged

2 Koradi -II 400/220 500 Sep-11 Dec-11

3 Warora 400/220 500 Sep-11

4 Lonikhand 400/220 500 Sep-11

5 Chandrapur-II 400/220 500 Sep-11

SOUTHERN REGION (SR) :

KARNATKA (KPTCL):

1 Nelamangala (Addl. 3rd Trf.) 400/220 500 Existing Dec-11 LOA issued on 04.02.11 . Work to be

commenced.

1 S V Chatram 400/230 2x315 A 100% 100% 80% 80% Jul-10 Jun-11

EASTERN REGION (ER) :

System Strengthening

MAHARASHTRA(MSETCL)

ORISSA (OPTCL)

Chhattisgarh (CSPTCL)

TAMILNADU (Tantransco) :

Adani Power Limited (State) 1000 MW (Bid-1)

pspm(cea) Sub Stns 10 of 21

Page 11: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

1 Dubri 400/220 (2x315) 400/220 630 May-08 Jun-11 220 kV portion charged.Pre

commissioning test of 2 nos. ICT &400

kV Bay to be taken up after completion of

Meramundali-Duburi line by PGCIL.Oil

filtration work is in progress.

System Strengthening

1 Kharagpur 400/220 2x315 Apr-09 A Partially

completed.

Partially

received.

Yet to be

started

Mar-10 Mar-12 Equipment supply work in progress.

2 Arambag (Aug.) 400/220 315 Mar-12

3 Jeerat (Aug.) 400/220 315 Mar-12

EASTERN REGION (ER) :

1 Palatana Gas Power Project ,

(2x363.3MW)

a Surajmaninagar S/S 400/132 2x200 Dec-11

1 Palatana Gas Power Project ,

(2x363.3MW)

a Kukurmara S/S (2x315) 400/220 630 Dec-11

1 Palatana Gas Power Project ,

(2x363.3MW)

a Killing (Byrnihat) S/S 400/220 630 Dec-11

C 220 KV Substations

(a) CENTRAL SECTOR (CS)

POWERGRID (PGCIL) :

1

WEST BENGAL (WBSTCL) :

Augmentation of 220/132KV Transformation

Capacity at Raebareli (PG) by 1x100 MVA

Transformer

TRIPURA (TSECL)

ASSAM (AEGCL)

MEGHALAYA (MePTCL)

pspm(cea) Sub Stns 11 of 21

Page 12: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

a Raebareli (POWERGRID) 220/132 100 Aug-10 A Mar-12 Mar-12

2 Feb-10

a Mokokchung (New) 220/132 2x50 A Dec-12 Engg. in progress.

DAMODER VALLEY CORPORATION (DVC) :

Mejia TPS Unit-6 (1x250MW)

1 Gola (2x50 MVA) 220/33 2x80 Jun-11 Jun-12 Order placed in Nov.2009 with

completion time of 12 months. Work

could not be started due to ROW

problem on the substation land

acquisition.Matter has been taken up

with district adminstration .supply &

erection awarded.

Chandrapura TPS Extn.(2x250)

1 Giridih (2x150+2x80) 220/132 460 A Partially

received

Partially

erected

Oct-10 Mar-12 Order placed on 27-08-09 and WIP.

2 Dhanbad (1x80) MVA 220/33 80 Mar-09 May-11 Work in progress, Order placed in

July 08 and erection of equipment

almost completed.

3 Dhanbad (2x150) MVA 220/132 300 Jul-10 Jun-11 WIP

4 Koderma (2x80) MVA 220/33 160 A 98% 95% 95% Jul-10 Jun-11 WIP

5 Koderma (2x150 ) MVA 220/132 300 A 98% 95% 95% Jul-10 Jun-11 WIP

(b) STATE SECTOR (SS) :

NORTHERN REGION (NR) :

DELHI (DTL) :

Commonwealth Games

1 Electric Lane (GIS) 220/33 2x100 Mar-08 May-11 Delay due to tree cutting permission

from forest department.

2 Trauma Centre/AIIMS (GIS) 220/33 2x100 Mar-08 May-11 S/Stn is ready. Electircal Inspector

clearance awaited.

Transmission System associated with Pallatana gas

Based Power Project and Bongaigaon Thermal

Power Station (BTPS)

pspm(cea) Sub Stns 12 of 21

Page 13: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

System Strengthening

1 Wazirpur 220/33 100 Sep-11

2 Rohini 220/66 160 Sep-11

3 Harsh Vihar GIS 220/66 160 Dec-11

System Strengthening

1 Masudpur 220/132 100 Sep-11

2 A-5 Faridabad 220/66 100 Sep-11

3 Dhanonda 220/132 100 Sep-11

4 Lula Ahir 220/66 100 Sep-11

5 Sampla 220/132 100 Commissioned 3/11

6 Mohana 220/132 100 Dec-11

7 IMT Manesar (2nd) 220/66 1x100 Mar-06 May-11 Trf. Received at site erection by

HSIDC.

8 Tepla Aug 220/132 2x100 Jun-09 May-11

9 Nuhiawali 220/132 2x100 Mar-11 Jun-11

1 Baddi (Addl.) 1x100 MVA 220/66 1x100 Mar-08 Mar-12 Delay due to forest case in HC

JAMMU & KASHMIR (J&K):

1 Alusteng 220/132 320 A 30% 10% 10% Trf.

Received

Sep-09 Dec-11 Levelling&construction walls/ control

room building under progress.

2 Mirbazar 220/132 320 A 70% 65% 65% Trf.

Received

Mar-09 Jun-11 transformers received

3 Budgam 220/132 320 A 70% 60% 60% Trf.

Received

Mar-09 Jun-11 transformers received

4 Amargarh 220/132 160 A 80% 60% 60% Trf.

Received

Sep-09 Jul-11 WIP

5 Bishnah 220/132 2x160 Mar-09 Dec-11 Laying of earth mat in progress,

equipment foundations completed,

control room in progress.

6 Ramban (3x40) 220/132 1x120 Jun-09 Mar-12 WIP

7 Ziankote 220/132 3x150 Jun-09 Mar-12

HARYANA (HVPNL) :

HIMACHAL PRADESH (HPSEB Ltd.) :

pspm(cea) Sub Stns 13 of 21

Page 14: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

System Strengthening

1 Mastewala 220/66 100 May-11

2 Jhunir 220/66 100 Commissioned 3/11

3 Mandi Govindgarh 220/66 100 May-11

4 Mehal Kalan 220/66 100 Dec-11

5 Rehana Jattan 220/66 100 Dec-11

6 Ghobaya 220/66 100 Commissioned 3/11

7 Patran 220/66 100 Dec-11

8 Lalru 220/66 100 Sep-11

9 Ferozepur Road Ludhiana

(1x100 MVA)

220/66 100 Mar-07 Feb-12 Civil/Erection work in progress

10 Doraha (U/G) (1x100 MVA) 220/66 100 Jun-10 May-11 Civil work in progress

System Strengthening

1 Madri (Udaipur) 220/132 100 Jul-11

2 Kishangarh 220/132 100 Commissioned 3/11

3 Dechu 220/132 100 Dec-11

4 Gajner 220/132 100 Dec-11

5 Gangapurcity 220/132 100 Dec-11

6 Barli 220/132 100 Dec-11

7 Manoharpur 220/132 100 Dec-11

8 Padampur 220/132 100 Mar-12

9 Aspur 220/132 100 Mar-12

10 Jhalmand 220/132 100 Mar-12

11 Sawa 220/132 100 Commissioned 3/11

PUNJAB (PSTCL) :

RAJASTHAN (RRVPNL) :

pspm(cea) Sub Stns 14 of 21

Page 15: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

12 Sanchore(1x100) 220/132 100 Jun-09 May-11 Test charged

UTTAR PRADESH (UPPCL) :

System Strengthening

1 Bhelupur 220/33 120 Dec-11

2 Gajokhar 220/132 100 Dec-11

3 Jhansi 220/132 100 Dec-07 Dec-11 Earthmat laying 85% completed.

Transf.plingth 75% completed.

4 Bithoor 220/132 160 Sep-11

5 Kanpur South 220/132 160 Sep-11

6 Partapgarh 220/132 100 Mar-12

7 Jhusi 220/132 160 Mar-12

UTTARAKHAND (PTCUL) :

1 Dehradun 220/132 1x160 Jun-06 Dec-11 Land acquisition under progress.

2 Ghansali 220/132 2x50 Dec-10 Jun-11 Bid evaluation completed.WIP.

3 Mahnabheraganj 220/132 2x100 Dec-10 Jun-11 Work in progress.Equipment supply

completed.WESTERN REGION (WR) :

System Strengthening

1 Mungeli 220/132 160 Mar-12

2 Saraipally 220/132 160 Mar-12

3 Vishrampur 220/132 1x160 Apr-07 Dec-11 Order placed in Aug.2009.Site handed

over.

System Strengthening

1 Shapur 220/132 315 Mar-12

2 Vadala 220/66 100 Mar-12

3 Popda 220/66 100 Mar-12

4 Suva 220/66 100 Mar-12

5 Bhatiya 220/132 100 Mar-12

GUJARAT(GETCO) :

CHHATTISGARH (CSPTCL) :

pspm(cea) Sub Stns 15 of 21

Page 16: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

6 Lunawada 220/66 100 Mar-12

7 Jasdan 220/132 100 Mar-12

8 Tankara 220/66 100 Mar-12

9 Saria 220/132 100 Mar-12

10 Vyankatpura 220/66 100 Mar-12

11 Kalawad 220/66 100 Mar-12

12 Kosamba 220/66 1x100 Mar-08 Jun-11

GOA :

1 Cuncolim 220/33 3x50 Dec-10 Jun-11 Work order with IRCON.

MADHYA PRADESH (MPPTCL) :

System Strengthening

1 Daloda 220/132 160 Mar-12

2 Chichali 220/132 160 Mar-12

3 Astha 220/132 160 Dec-11

4 Seoni 220/132 160 Mar-12

MAHARASHTRA (MSETCL) :

System Strengthening

1 Paranda 220/132 200 Jun-11

2 Patoda 220/33 50 Dec-11

3 Bhokardhan 220/132 100 Dec-11

4 Jath 220/132 100 Sep-11

5 Bhambori (Jalgaon) 220/132 100 Sep-11

6 Vasai 220/100 200 Sep-11

7 Bapgaon 220/132

220/33

2x200

2x50

Mar-08 Jun-11 WIP

8 Shendra 220/132 2x100 Mar-08 Jun-11 WIP

SOUTHERN REGION (SR) :

ANDHRA PRADESH (APTRANSCO) :

System Strengthening

pspm(cea) Sub Stns 16 of 21

Page 17: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

1 Rachagunneri 220/132 2x100 Partially

received.

Partially

erected.

Dec-11 Foundation works and structure

erection works under progress.

2 Osmania University 220/132 2x160 Partially

completed.

Dec-11

3 Erragadda 220/132 3x160 Partially

completed.

Dec-11 Work commenced and are in

progress.

4 lmliban (GIS) 220/132 2x160 Partially

completed.

Sep-11

5 Gunrock 220/132 2x160 Partially

completed.

Dec-11 Site levelling is under progress.

6 Nagari 220/132 2x100

+2x50

Partially

received.

Partially

erected.

Dec-11 Foundation works, Structure erection

and euipment erection works under

progress.

7 Palamaneru 220/132 2x100 Dec-09 Jun-11 All works completed . Connected line

works are under progress.

8 Bellampally (Mandamarri) 220/132 2x100 Oct-08 May-11 All works completed. Connected line

work in progress.

9 Sadasivpet 220/132 2x100 Partially

received.

Partially

erected.

May-11 Substation is charged from 132 kV

side. Change of scope of line works

due to 400 kV Yeddumailaram

evacuation lines. LOI issued for

revised 220 kV line.

10 Jurala 220/132 2x100 Erection

completed.

Yet to be

erected.May-11 Substations work complected.

11 Settipally 220/11 3x25 99% May-11

12 Yellanur 220/11 2x25 70% May-11

13 Gaddamvaripalli 220/11 2x25 75% May-11

14 Goddumarri 220/11 2x50 50% Jul-11

15 Kambalapadu 220/11 3x25 100% May-11

16 Thimmapuram 220/11 2x25 95% May-11

17 Kondapuram 220/132 2x100 100% May-11

18 Nansuralla 220/11 3x25 100% May-11

19 Vemnur 220/11 2x50 70% Jun-11

20 Medaram 220/11 2x50 15% Aug-11

pspm(cea) Sub Stns 17 of 21

Page 18: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

21 Krishnagiri 220/11 3x25 22% Aug-11

22 Lakkasagaram 220/11 3x25 100% May-11

23* Brahmanakotkur 220/11 3x25 Apr-11 25 MVA Trf. Commissioned 4/11.

24* Malyala 220/11 126 Apr-11 95 MVA Trf. Commissioned 4/11.

KARNATAKA (KPTCL) :

1 Jigani (2x150) MVA 220/66 300 A Near

completion.

Received Partially

erected

Erected Sep-11

2 Vikas Tech Park (2x150) MVA 220/66 300 A Partially

complection.

Partially

received

Partially

erected

Partially

erectedDec-11

3 Halbarga (2x100) MVA 220/110 200 A Partially

complected

Partially

received

Partially

erectedDec-11

4 Ramanagar(Kothipura) 220/66 100 A Completed Received Erected Erected Jun-11

5 Chikkmagalur (2nd Trf.) 220/66 100 A complected Received Erected Erected Jun-11 All equipments erected. Road

formation and PC test under progress.

6 Kushalanagara (2nd Trf.) 220/66 100 A complected Received Erected Erected Jun-11 All work complected.

7 Somanahalli (Addl.) 220/66 100 A CR existing. Existimg. Erected Erected Jun-11 Oil to be filtered. Work stopped by the

firm.KERALA (KSEB) :

1 Punnapra 220/110 2x100 Jun-07 Dec-11 Erectionof yard structure,cable

trench,Equipment foundation completed.

Overall 92% completed.

2 Kanjikkod(Add.Tr.) (2x25) 220/110 50 Mar-12

3 Pothencode(3rd

Trf.) 220/110 200 Commissioned 3/11

4 Kattakkada(New) 220/110 200 Mar-12

1 Karambayam 230/110 2x100 A 100% Partially

Received

50% Dec-10 Jun-11

2 Karamdai (2x100) 230/110 100 A 20% Mar-12

3 Aliyar (2x100) 230/110 100 A 100% Partially

Received

80% Dec-11

4 Nallamanaickenpaty (2x100) 230/110 100 A 50% Partially

Received

10% Sep-11

5 Vyasarpadi 230/110 100 A 20% Mar-12

TAMILNADU (Tantransco) :

pspm(cea) Sub Stns 18 of 21

Page 19: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

6 Athipet 230/110 100 A 100% Received 90% 5% Jun-12

7* Sadayapalayam 230/33 100 Apr-11 Commissioned 4/11.

8* Oragadom 230/110 100 Apr-11 Commissioned 4/11.

9* Alundur (Aug.) (100-50) 230/110 50 Apr-11 50 MVATrf. Commissioned 4/11.

1 Thondamanatham 230/110 2x100 Jun-10 May-11 Both transformers placed on plinth

EASTERN REGION (ER) :

BIHAR (BSEB) :

System Strengthening

1 Hazipur (2x100) 220/132 2x100 May-08 Dec-11 Order placed and work has been

stated.

2 Sipara (Patna) (2x150) 220/132 2x150 May-08 Sep-11 Works are being executed by PGCIL.

3 Madhepura (2x100) 220/132 2x100 Jun-11 Work in progress

4 Dehri (Aug.) 220/132 1x100 May-11

5 Muzaffarpur TPS (kanti) (Aug.) 220/132 1x100 Dec-08 May-11 Work in progress

1 Chaibasa 220/132 2x150 Jun-10 Jun-11 Land under development.

ORISSA (OPTCL ) :

System Strengthening

1 Bolangir 220/132 100 Commissioned 3/11

2 Mendhasal 220/33 20 Mar-12

3 Bonai 220/33 80 Dec-11 Substations boundary wall in

progress. Contour survey of the S/S

site complected.

System Strengthening

1 Kharagpur 220/132 320 Apr-09 A Partially

received.

yet to be

started.

Mar-12 Mar-12 Equipment supply work in progress.

WEST BENGAL (WBSETCL) :

PUDUCHERRY

JHARKHAND (JSEB) :

pspm(cea) Sub Stns 19 of 21

Page 20: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

2 Dalkhola 220/132 320 Jun-09 Partially

completed.

Partially

received.

Partially

complted.

Jun-11 Sep-11 Control room building is completed.

Equipment erection work in progress.

3 Kasba (Aug) 220/132 160 Mar-12

4 Laxmikantapur (Aug) 220/132 160 Mar-12

5 Howrah (Aug) 220/132 160 Mar-12

6 Rishra(aug.) 220/132 100 Jul-09 90% 100% Partially

completed.

Yet to be

started.

May-11 Equipment erection work in progress.

NORTH-EASTERN REGION (NER) :

1 ATS of Palatana Gas Power

Project , (2x363.3MW)

a Kukurmara S/S (2x50) 220/132 100 Dec-11

2 ATS of BongaigaonTPS

(Salakati)

a Rangia S/S (2x100) 220/132 200 Dec-11

1 Nangalbibra 220/132 100 Dec-11

LEGEND: * Outside programme

S/C Single circuit MVA Mega Volt Ampere

D/C Double circuit MW Mega watt

M/C Multi circuit ckt Circuit

S/C on

D/C

Single circuit on Double circuit S/S Sub-station

kV Kilo- volt PGCIL Powergrid corporation of India limited

CKm Circuit kilometer UPPCL Uttar Pradesh Power corporation Limited

LILO Loop in Loop out PFC Power Finance Corporation

TPS Thermal Power station C.R. Control Room

CR Panel Control and Relay panel Struct. Structure

NHPC National Hydro Power Corporation Transf. TransformerNR Northern Region

AEGCL

MEGHALAYA(MeSEB)

pspm(cea) Sub Stns 20 of 21

Page 21: Sub Station 220kv Status

Land

Acqusition

Civi works

completed

Structure,

transformer,

sub station

eqpt.received

Structure,

sub station

eqpt.erected

Transf.

erected&

tested

Original

Target

Date

Actual/ Now

Anticipated

date

1 2 3 4 5 6 7 8 9 10 11 12 13

Date of

Award

Cummulative progress till date CommissioningSl.

No.

RemarksName of the Sub-Station Voltage

ratio

(kV/kV)

Capacity

MW/MVA

Aug Augmentation SG Switch gearWR Western Region

CS Central Sector NR Northern Region SR Southern Region

SS State Sector SR Southern Region ER Eastern Region

NER North-East Region A Available/Acquired

U A Under Acquisition

pspm(cea) Sub Stns 21 of 21