Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region Phase 1 Report Prepared by Jorge Centella Artola, Cuba Alexi Manuel Batista Ruiz, Dominican Republic William Alsina, Dominican Republic Riaaz Mohammed, Trinidad and Tobago César Turcios Valiente, COCESNA Eddian Méndez, ICAO August 2018

Transcript of Sub-Project to Develop and Implement a Performance-Based ...

Page 1: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based

Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report

Prepared by

Jorge Centella Artola, Cuba Alexi Manuel Batista Ruiz, Dominican Republic

William Alsina, Dominican Republic Riaaz Mohammed, Trinidad and Tobago

César Turcios Valiente, COCESNA Eddian Méndez, ICAO

August 2018

Page 2: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report

Contents

Contents 1. General ............................................................................................................................................. 1

2. Introduction ..................................................................................................................................... 2

3. Objectives ........................................................................................................................................ 2

4. Scope ................................................................................................................................................ 3

5. Methodology Employed by the Project Team ................................................................................. 4

6. Model Concept for PBN Harmonization within the CAR Region ..................................................... 7

7. CAR Region PBN Implementation Form ......................................................................................... 12

8. List of Common Challenges to PBN ................................................................................................ 12

9. Templates for RNAV 5 and SID & STAR Development ................................................................... 13

10. Reference Documents.................................................................................................................... 13

Page 3: Sub-Project to Develop and Implement a Performance-Based ...
Page 4: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report 1

1. General

Place of Initial Meeting: ICAO NACC Regional Office Mexico City, Mexico

Dates of Initial Meeting: 8 to 11 May 2018

Team Composition: Jorge Centella Artola, Cuba Alexi Manuel Batista Ruiz, Dominican Republic William Alsina, Dominican Republic Riaaz Mohammed, Trinidad and Tobago César Turcios Valiente, COCESNA

ICAO Representative: Eddian Méndez Regional Officer, Air Traffic Management and Search and Rescue

Objectives of the Mission: ● Develop a model structure for airspace and Terminal Areas (TMAs) that allows continuous flow in the upper and lower airspace of contiguous Flight Information Regions (FIRs) and TMAs, proposing a possible solution to the complex structure of the existing FIRs in the CAR Region.

Summary of Activities: ● Initial meeting with the Subject Matter Experts (SMEs) to discuss the sub-project mission objectives

● Assessment of information for regional PBN implementation, as appropriate

● Review information regarding FIR and TMA requirements for the CAR Region, and make an assessment of implementation in accordance with the NAM/CAR Regional Performance-Based Air Navigation Implementation Plan (RPBANIP) and Air Navigation Plan

● Draft a report summarizing the sub-project mission outcomes.

Page 5: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report

2 2. Introduction 2.1 PBN implementation is a living concept. Even though PBN regional implementation targets may or may not have been met, States and International Organizations need to work to comply with agreed objectives and continue improvement to allow an efficient flow of the increasing traffic. 2.2 The composition of the Caribbean (CAR) Region is very heterogeneous with different scenarios between adjacent States, with radar and non-radar environments, oceanic and continental airspaces, high density and moderate flows of traffic, different infrastructure and technologies amongst States, and other factors, reflected in this document, that create a challenge to harmonize the PBN implementation plans of the States and International Organizations within. 2.3 Despite the differences and challenges within the region, it is imperative to develop a harmonized approach to PBN implementation. This Sub-Project, led by the ICAO NACC Regional Office and consisting of Subject Matter Experts (SMEs) selected from among Project Member States, was formed with the objective to develop a model concept for airspace and Terminal Areas (TMAs) that allows continuous flow in the upper and lower airspace of contiguous Flight Information Regions (FIRs) and TMAs, proposing a possible solution to the complex structure of the existing FIRs in the CAR Region. 2.4 The model concept developed provides the minimum requirements that each State or International Organization should consider in developing its individual PBN implementation plan. It also provides an analysis of PBN implementation within the region; documents reported challenges and aims to provide recommendations to assist those States/International Organizations which are currently encountering difficulties in meeting PBN implementation objectives. 3. Objectives 3.1 The goal of ICAO is to ensure that no State is left behind. While it is understood that growth rates amongst individual States and International Organizations may differ based on various factors, it is important to ensure that there is a mechanism which allow all States and International Organizations to meet at least the minimum targets established for safety and efficiency within the region. 3.2 The main objective of this document is to ensure a balanced PBN implementation within the CAR Region which enhances the interoperability of air navigation services throughout the entire airspace. States with difficulty in the implementation can review the information in this document to determine what is required to develop an efficient and safe airspace structure and also what kind of assistance they need to acquire. 3.3 It is expected that with a harmonized approach to PBN implementation within the region, the following benefits will be derived:

Page 6: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report 3

• Assistance for States to comply with Aviation System Block Upgrade (ASBU)

Block Zero airspace optimization requirements • Assistance to meet and comply with Regional Performance Objectives (RPOs)

within the ICAO NACC Regional Performance Based Air Navigation Implementation Plan (RPBANIP)

• Achieve increased homogeneity in the airspace between adjacent States • Reduction of distance travelled from point to point for each aircraft operation • Improvement in aircraft fuel savings and reduction of CO2 emissions • Optimizations of continuous climb and descend profiles for aircraft • Reduction of the use of holding patterns • Greater access through mountainous areas • Reduction of noise in the vicinity of airports • Reduction of pilot and Air Traffic Controllers (ATCOs) workload • Reduction in occupancy of telecommunications frequencies • Reduction in the need to purchase and maintain ground based navigational aids • Less proximity alerts based on the terrain • Increased flexible use of airspace

4. Scope 4.1 In reviewing the Terms of Reference of the Sub-Project, the SMEs in collaboration with the ICAO NACC Regional Officer ATM/SAR, determined that based on the diversity of the individual CAR State’s/Organization’s airspace and also on the limited information available to the project team, it would be more productive to carry out the project on the following three phases:

1. Phase 1 – Concept Development In this phase the minimum requirements for upper and lower airspaces of the

CAR Region are defined. The model concept is presented as a report for the subproject.

2. Phase 2 – Data collection and analysis The purpose of this phase is to collect evidence regarding the PBN

implementation status for each upper and lower airspace and the airspace optimization capabilities for each State and International Organization of the CAR Region.

3. Phase 3 – Assessment and development of individual plans After detailed information regarding the implementation and capacities of

States and International Organizations has been reviewed, an objective assessment of the situation is performed and individual plans to close the detected gaps are developed. Here will be also identified the assistance required and possible collaboration with other stakeholders.

Page 7: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report

4 4.2 The model concept is developed to ensure understanding amongst all States and International Organizations of the minimum requirements needed for an adequate and harmonized approach to PBN implementation within the CAR Region. This concept is intended to be applied in the airspaces of the CAR Region, detailed in Appendix A to this report. 4.3 Phases 2 and 3 should be carried out by the ICAO NACC Regional Office, supported by the ANI/WG PBN Task Force, following the guidelines provided by the Sub-Project. 4.4 While it is understood that United States is in the process of developing an airspace plan for the Miami Oceanic, Houston Oceanic and New York Oceanic FIRs, due to the high flow of traffic, and airspace complexity, a PBN point of contact from the FAA is required; For specific details regarding routes implementation, it is also recommended to identify points of contact for each of United States´ aforementioned FIRs, to coordinate with the adjacent CAR State/Organization representatives. 5. Methodology Employed by the Project Team 5.1 Phase 1 – Concept Development

The Project Team reviewed the PBN RPO stated within the RPBANIP and determined a list of minimum requirements for each airspace that each State/Organization should be engaged in to ensure an adequate level of airspace harmonization within the CAR Region. The team also reviewed previous reports provided by the ANI/WG PBN Task Force at past Working Group meetings and the airspace harmonization meetings and discussed common challenges faced by most of the States/International Organizations. As part of the process, the SMEs provided information relating to PBN implementation in their respective State/Organization, and discussed best practices employed in PBN implementation planning. The Team developed generic templates of work programmes for development of RNAV 5 routes and SIDs and STARs which are included within the document as Appendixes B and C. As part of the review, the Team recognized the fact the target dates specified in the RPBANIP had elapsed, and recommends that a review of target dates be considered during the ANI/WG/4 meeting.

5.2 Phase 2 – Data collection and analysis The Team created a form aimed at capturing information relating to the PBN implementation status of Individual States and Organizations within the CAR Region. A State letter will be sent by the ICAO NACC Regional Office, requesting that all

Page 8: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report 5

States/International Organizations complete the form and return it to the ICAO NACC Regional Office. Each State/International Organization will be required to designate a representative capable of coordinating with the ICAO NACC Regional Office and the Team. The information collected will be entered into a database within the ICAO NACC Regional Office and will be used by the Team to analyse the status of each State/Organization. Apart from creating an individual profile for each State/Organization, the Team will also update the list of common challenges and provide recommendations for their mitigation. During Phase 1 of this project, the Team collected and analysed data from the following States/Organization: • Cuba – upper/lower airspace • Dominican Republic - upper/lower airspace • Trinidad and Tobago - upper/lower airspace for TTPP. (Awaiting further

information from Eastern Caribbean States) • COCESNA – upper airspace (Some information provided for lower airspace.

Awaiting further information from Central American States)

5.3 Phase 3 – Assessment and development of individual plans On completion of Phase 2, the Team will provide specific recommendations to each State/Organization based on the profiles created. Additionally, the Team will identify both strengths and weaknesses of individual States/International Organizations and will provide recommendations to the ICAO NACC Regional Office regarding the best use of available resources within the region. The ICAO NACC Regional Office will seek the support of those States/International Organizations who are capable of providing assistance to any other State/Organization that may require it.

5.4 The table below shows the tasks and projected timelines for each phase.

Phase Task Responsible Start End Status

1 Review of PBN RPOs Project Team 8 May 2018

8 May 2018 Completed

Determine list of minimum requirements for all airspaces (upper/lower

Project Team 8 May, 2018

9 May 2018 Completed

Page 9: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report

6

Phase Task Responsible Start End Status

airspace) Review previous reports of ANI/WG PBN Task Force

Project Team 9 May 2018

9 May 2018 Completed

List common challenges faced by States/International Organizations in PBN Implementation

Project Team 9 May 2018

9 May, 2018 Completed

SMEs provide information on best practices within their States/International Organizations

Project Team 10 May 2018

10 May 2018 Completed

Develop form to collect data from States/Organization

Project Team 10 May 2018

10 May 2018 Completed

SMEs provide information on their respective States’/Organization’s PBN implementation status

Project Team 10 May 2018

11 May 2018 Completed

Develop Template for development of PBN SIDs and STARs as well as RNAV 5 routes

Project Team 11 May 2018

11 May 2015 Completed

Produce report on Phase 1 Project

Project Team 11 May 2018

30 June 2018 Completed

2 ICAO NACC Regional Office to promulgate State letter to each State/Organization

ICAO NACC Regional Office

28 August 2018

3 September 2018

Each State/Territory to complete and submit the form to the ICAO NACC Regional Office

States/Territories 3 September 2018

3 October, 2018

Create database of responses

ICAO NACC Regional Office

15 October 2018

30 November 2018

Analysis of State/Organization responses

Project Team 3 December 2018

7 December 2018

Create profile on each Project Team in 10 14 December

Page 10: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report 7

Phase Task Responsible Start End Status

State/Organization consultation with respective State/Organization

December 2018

2018

Update list of common PBN implementation challenges

Project Team 10 December 2018

14 December 2018

3 Provide each State/Organization with an assessment of their implementation, including recommendations

Project Team through the ICAO NACC Regional Office

14 January 2018

18 January 2018

Provide recommendations to the ICAO NACC Regional Office on best use of resources within the Region

Project Team 14 January 2018

18 January 2018

6. Model Concept for PBN Harmonization within the CAR Region 6.1 General 6.1.1 The model concept is based on the minimum requirements considered to accommodate all current and envisioned users of the airspace providing safety, capacity and efficiency of operations in a PBN environment. 6.1.2 The model concept is divided in requirements for upper and lower airspace, to facilitate States the verification of accomplishment for every airspace structure. 6.2. Minimum Requirements for the Upper Airspace 6.2.1 The minimum requirements for the upper airspace consider as listed in the following table:

Minimum Requirements

Upper Airspace

Implementation of RNAV 5 routes as agreed to in the Regional Air Navigation Plan

Removal of conventional routes made redundant by PBN route implementation

Implementation of RNAV 1/2 STAR/SIDs (CCOs and CDOs) to TMAs within the FIR

Page 11: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report

8

Minimum Requirements

Implementation of 20NM longitudinal separation at FIR boundaries (where applicable)

All routes and waypoints published by the States are correctly processed through the ICAO International Codes and Route Designators (ICARD) database

Oceanic airspace lateral separation (where applicable)

6.3 Description of the minimum requirements for the upper airspace 6.3.1 Implementation of RNAV 5 routes as agreed to in the Regional ANP 6.3.1.1 RNAV 5 operations are based on the use of RNAV equipment which automatically determines the aircraft position in the horizontal plane using input from one or a combination of the following types of position sensors, together with the means to establish and follow a desired path: a) VOR/DME; b) DME/DME; c) INS or IRS; and d) GNSS. 6.3.1.2 The air navigation service providers (ANSP) must assess the navaid infrastructure in order to ensure that it is sufficient for the proposed operations, including reversionary modes. It is acceptable for gaps in navaid coverage to be present; when this occurs, route spacing and obstacle clearance surfaces need to take account of the expected increase in lateral track-keeping errors during the “dead reckoning” phase of flight. 6.3.1.3 Regarding separation, in an ATC surveillance environment, the route spacing will depend on acceptable ATC workload and availability of controller tools, separation is considered as follows:

• 16.5 NM for same-direction traffic • 18 NM for opposite-direction traffic • As low as 10 NM where ATC intervention capability permits.

6.3.2 Removal of conventional routes made redundant by PBN route implementation. 6.3.2.1 RNAV/RNP routes are more efficient than conventional routes providing “gate to gate” operations and also do not rely on radio aids installed on ground, improving safety and accuracy. These are the main reasons why it is considered important to make redundant and replace conventional routes to RNAV/RNP routes.

Page 12: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report 9

6.3.3 Implementation of RNAV 1/2 STAR/SIDs (CCOs and CDOs) to TMAs within the FIR 6.3.3.1 The main objective is to improve safety, predictability of flights and airspace capacity while reducing noise, fuel consumption, CO2 emissions and pilot-controller communications at the same time. 6.3.3.2 Continuous Descent Operation (CDO) is an aircraft operating technique aided by appropriate airspace and procedure design and appropriate ATC clearances enabling the execution of a flight profile optimized to the operating capability of the aircraft, with low engine thrust settings and, where possible, a low drag configuration, thereby reducing fuel burn and emissions during descent. The optimum vertical profile takes the form of a continuously descending path, with a minimum of level flight segments only as needed to decelerate and configure the aircraft or to establish on a landing guidance system (e.g. ILS). 6.3.3.3 Continuous Climb Operation (CCO) is an aircraft operating technique enabled by airspace design, instrument procedure design and facilitation by ATC, allowing for the execution of a flight profile optimized to the performance of the aircraft. CCO enables the aircraft to attain initial cruise flight level at optimum airspeed and engine thrust settings set throughout the climb, thereby reducing total fuel burn and emissions. Ideally, the departure design is such that arriving traffic is also able to descend based on an optimum descent profile. Where the departure and arrival flows cannot be designed independently, there will need to be a compromise between the needs of the departure and arrival flow optimization; this compromise should be reached collaboratively. 6.3.3.4 An aircraft’s fuel efficiency in terms of fuel burned per kilometre flown in levelled flight increases with height. However, the fuel used in climbing to that altitude can be a significant part of the overall fuel used for the flight. Therefore, for any given route length, there is an optimum initial cruise flight level which will be dependent upon the aircraft type and mass, as well as on the meteorological conditions of the day. CCO is only one of the tools involved in a complete airspace design. Throughout the design process, CDO, CCO and other route modifications should all be considered. 6.3.4 Implementation of 20 NM longitudinal separation at FIR Boundaries (where applicable). 6.3.4.1 This requirement is based on the longitudinal separation minima based on distance using Distance Measuring Equipment (DME) and/or GNSS. 6.3.4.2 Separation shall be established by maintaining not less than specified distance(s) between aircraft positions as reported by reference to DME in conjunction with other appropriate navigation aids and/or GNSS. This type of separation shall be applied between two aircraft using DME, or two aircraft using GNSS, or one aircraft using DME and one aircraft using GNSS. Direct controller-pilot VHF voice communication shall be maintained while such separation is used. 6.3.5 All routes and waypoints published by the States in their AIP, are correctly processed through the ICAO International Codes and Route Designators (ICARD) database. 6.3.5.1 States/International Organizations are requested to submit and maintain up to date ICAO ICARD database with the new and previous routes and waypoints in order to eliminate codes

Page 13: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report

10 duplication and differences between the geographical coordinates of waypoints published in the AIP and those feed it in the ICARD. 6.3.5.2 States/International Organizations are also requested to make coordination with neighbouring FIRs to publish in the respective AIP the same coordinates for the Transfer of Control Points (TCP). 6.3.6 For oceanic airspace, use of 50 NM lateral separation. 6.3.6.1 RNAV 10 (designated and authorized as RNP 10) supports 50 NM lateral and 50 NM longitudinal distance based separation minima in oceanic or remote area airspace. 6.3.6.2 States/International Organizations shall comply with this separation in order to maintain a safety flow of traffic and a separation harmonization with all FIRs of the CAR Region. 6.3.7 For oceanic airspace, use of 30 NM longitudinal and lateral separation. 6.3.7.1 RNP 4 supports 30 NM lateral and the 30 NM longitudinal distance based separation minima in oceanic or remote area airspace. 6.3.7.2 States/International Organizations shall comply with this separation in order to maintain a safety flow of traffic and a separation harmonization with all FIR of the CAR Region. 6.4. Minimum Requirements for the Lower Airspace 6.4.1 The minimum requirements for the lower airspace considered are listed in the following table:

Minimum Requirements

Lower Airspace

Implementation of RNAV 1/2 STAR/SIDs(CCOs and CDOs) to TMAs within the FIR

Implementation of at least LNAV approaches for International Airports

LNAV/VNAV (BARO VNAV) Approaches if analysis determines a benefit

Implementation of RNP AR Approaches if analysis determines a benefit

Implementation of APV (GBAS) Approaches if analysis determines a benefit

6.5 Description of the requirements for the lower airspace 6.5.1 Implementation of RNAV 1/2 STAR/SIDs (CCOs and CDOs) to TMAs within the FIR 6.5.1.1 See paragraph 6.3.3.

Page 14: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report 11

6.5.2 Implementation of at least LNAV approaches for international airports 6.5.2.1 RNP APCH LNAV procedures provides lateral guidance and can be defined with fly-by and fly-over waypoints as "T" or "Y" type approach. 6.5.2.2 RNP APCH is defined as an RNP approach procedure that requires a lateral Total System Error (TSE) of +/-1 NM in the initial, intermediate and Missed Approach Segments (MAS) and a lateral TSE of ±0.3 NM in the Final Approach Segment (FAS). 6.5.2.3 RNP APCH LNAV procedure does not rely on ground radio aids and are more accuracy than conventional VOR/DME procedures. Also improve access being aligned in most cases with the runway centre line. 6.5.3 LNAV/VNAV (BARO VNAV) Approaches if analysis determines a benefit 6.5.3.1 Baro-VNAV approach procedures are classified as APV procedures in support of Type A 3D approach operations. They utilize a DA/H and not an MDA/H, and neither a FAF nor a Missed Approach Point (MAPt) is identified. They use obstacle assessment surfaces similar to those for ILS, but based on the specific lateral guidance system. 6.5.3.2 Baro-VNAV procedures are used in association with LNAV-only procedures. The LNAV-only FAF and MAPt are needed to define the lateral areas and to support the lateral guidance but they are not used for the vertical navigation function. 6.5.3.3 Baro-VNAV procedures shall not be authorized with a remote altimeter setting. 6.5.3.3 Providing lateral and vertical guidance, BARO-VNAV approaches increase safety, access and accuracy compared with an RNP APCH LNAV procedure. 6.5.4 Implementation of RNP AR Approaches if analysis determines a benefit 6.5.4.1 Implementation of RNP AR procedures extends beyond procedure design in that an authorization process for aircraft operators is necessary to ensure that other critical dependencies and associated airworthiness and operational procedure approvals are complete prior to implementation. Guidance on implementation and operational approval is provided in the PBN Manual. 6.5.4.2 RNP AR APCH is defined as an RNP approach procedure that requires a lateral Total System Error (TSE) as low as ±0.1 NM on any segment of the approach procedure. RNP AR APCH procedures are only published where significant operational advantages can be achieved while preserving or improving safety of operation. 6.5.4.3 RNP AR APCH are very useful in mountainous and noise sensitive areas to improve access to the airport through radius to fix RF turns. 6.5.5 Implementation of APV (GBAS) Approaches if analysis determines a benefit

Page 15: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report

12 6.5.5.1 Ground-Based Augmentation System (GBAS) is also referred as LAAS (Local Area Augmentation System), it can be used to achieve accuracy required to CAT I-III and is done by locating 4 receivers on the ground at a precisely -surveyed (centimetre accuracy) positions. 6.5.5.2 The cost of one GBAS ground station is less that the cost of multiple ILSs for an airport. Another advantage of GBAS is that the accuracy enhancement is provided for the whole airport. 7. CAR Region PBN Implementation Form 7.1 The CAR Region PBN Implementation Form is included in the Appendix D to this Report. 7.2 General 7.2.1 An implementation form has been created in order to help States/International Organizations to determine the level of accomplishment of the airspace model structure. 7.2.2 It is mandatory to indicate an AIP reference as evidence to ICAO NACC Regional Office on each item of the form you agree. 7.2.3 For all longitudinal separation items filled in the form, an existing letter of agreement (LOA) shall be attached. 7.2.4 Information provided by States/International Organizations shall remain confidential in ICAO NACC Regional Office. 7.3 Description of theCAR Region PBN Implementation Form 7.3.1 The CAR Region PBN Implementation Status Form is intended to help States and International Organizations in the assessment of their implementation progress in accordance with the PBN airspace concept. The form has specific initiates for both upper and lower airspace. States/International Organizations shall list all the initiatives they have accomplished or that are in progress to implement and also provide an AIP reference as evidence to ICAO NACC Regional Office on each item of the form agreed. The form has a remark section where States/International Organizations can describe with more detail the status and difficulties they have face or are facing to achieve any of the initiatives listed on the form. At the end of the form a Comments section regarding PBN Implementation roadblocks has been created to provide space to communicate any issue or concern they might have in terms of the Implementation progress. 8. List of Common Challenges to PBN

• Lack of transparency with regards to internal issues preventing PBN implementation.

• Limited Collaborative Decision Making and Communication Channels between States/International Organizations/ANSPs regarding regional PBN implementation.

Page 16: Sub-Project to Develop and Implement a Performance-Based ...

Sub-Project to Develop and Implement a Performance-Based Navigation (PBN) Airspace Concept Document for the CAR Region

Phase 1 Report 13

• Lack of consultation process with stakeholders to obtain feedback about PBN

implementation initiatives. • Lack of trained personnel in terms of PBN concept development and

implementation. • Poor data collection and database management regarding obstacles and

aeronautical information. • Difficulties to obtain proper design tools to develop Terminal and En-route

procedures under PBN concept.

9. Templates for RNAV 5 and SID & STAR Development 9.1 Templates for RNAV 5 and SID/STAR help States/International Organizations and ANSPs to design routes and procedures according to a proposed work breakdown with organized tasks, time frames and parties involved. The templates aim to describe and consolidate the procedures/route initiation, data collection and validation, conceptual design, stakeholders, CDM, evaluation, simulation, draft design, safety assessment and others steps that are mandatory in a PBN concept design in accordance with ICAO standards. Both templates are presented in the Appendixes B and C. 10. Reference Documents 10.1 ICAO Reference Documents

a) Performance Based Navigation (PBN) Manual (Doc 9613)

b) Continuous Climb Operations (CCO) Manual (Doc 9993)

c) Continuous Descent Operations (CDO) Manual (Doc 9931)

d) Required navigation Performance Authorization Required (RNP AR) Manual (Doc 9905)

e) Aircraft Operations volume 2- Construction of Visual and Instrument Flight Procedure (Doc 8168)

f) Procedures for Air Navigation Service-Air Traffic Management (Doc 4444)

g) Regional Performance-based Air Navigation Implementation Plan (RPBANIP) for NAM/CAR Regions.

Page 17: Sub-Project to Develop and Implement a Performance-Based ...

PBN Airspace Concept for the CAR Region Appendix A to the Report

A-1

APPENDIX A Airspaces of the CAR Region

Upper Airspace Lower Airspace

COCESNA (Central America)

Belize (Belize TMA)

Guatemala (La Aurora TMA)

Honduras (La Mesa TMA; Toncontín TMA; Roatán ATZ; La Ceiba CTR)

El Salvador (El Salvador TMA)

Nicaragua (Managua TMA)

Costa Rica (El Coco TMA; Liberia TMA)

Mexico (Mexico & Mazatlán Oceanic)

Acapulco; Cancún-Cozumel; Ciudad Del Carmen; Ciudad Juárez; Ciudad Obregón; Ciudad Victoria; Culiacán; Chihuahua; Durango; Guadalajara; Hermosillo; Ixtapa-Zihuatanejo; La Paz; Los Mochis; León - Aguascalientes; Manzanillo; Matamoros; Mazatlán; Mérida; Mexico; Monterrey; Morelia; Nuevo Laredo; Oaxaca; Puebla; Puerto Vallarta; Querétaro; Reynosa; Saltillo; San Jose Del Cabo; San Luis Potosí; Tampico; Tijuana; Torreón; Tuxtla Gutiérrez; Veracruz; Villahermosa;

Jamaica (Kingston) Jamaica TMA; Haiti (Port Au Prince) Port Au Prince TMA Cuba (Havana) Havana TMA; Santa Clara TMA; Santiago TMA Curacao (Curacao) Curacao TMA; Juliana TMA; Beatrix CTR; Flamengo CTR; Dominican Republic (Santo Domingo) Punta Cana TMA; Las Americas TMA; Cibao TMA United States (San Juan) San Juan

Trinidad And Tobago (Piarco)

Trinidad And Tobago (Piarco Ctr)

Antigua And Barbuda (Vc Bird TMA)

Barbados (Adams TMA)

Martinique (Martinique TMA)

St Lucia (St Lucia CTR)

St Vincent And The Grenadines (Argyle TMA)

Grenada (Maurice Bishop TMA)

Guadeloupe (Pointe-A-Pitre-TMA)

Page 18: Sub-Project to Develop and Implement a Performance-Based ...

PBN Airspace Concept for the CAR Region Appendix B to the Report

B-1

APPENDIX B ANSP– PBN Route Design Work Flow

Proposed work breakdown plan for development SIDs and STARs for CAR Region in accordance with the CAR PBN Harmonization Sub-Project

TASK

# DESCRIPTION INVOLVED PARTIES TIME

(APPROX.) REMARKS

1 Initiation Stakeholders -Procedure Designers -ASM -ATM - ATS and ANS Safety - Airlines. - Safety Regulations - Any other stakeholder

Variable Start date based on agreement by ASM and ATM managers & ANS Safety and approval. During this meeting, KEY stakeholders and responsibilities will be identified and a more detailed project plan will be created. Actual time for this phase is dependent on the CDM process and the time it takes for each stakeholder to respond. Based on CDM, a determination will be made on the current number of SIDs and STARs to be designed. This decision does not preclude future requests from any stakeholder.

2 Collection and validation of all data

Procedure designers. ASM, ATS, AIM. CNS Stakeholders. Data sources.

TBD Start date – Based on agreement by ANS Management. It is NOT totally dependent on responses from all stakeholders in task 1.

o PBN Equipage data collection ▪ RNAV 1/2 (SIDs and STARs) ▪ RNAV 5 (PBN Feeder routes ▪ RNP APCH (IAPs)

o Operational Flight data

▪ Trajectory ▪ Climb and Descent Profiles ▪ ATC considerations ▪ Radar data

i. Playback ii. Voice

iii. Recording

o Terrain and Obstacle o Helicopter Operations

3 Create conceptual

design ASM Procedure designers

TBD Time is dependent on 1 & 2 being completed.

4 Review by stakeholders

Involved Stakeholders. ASM

Variable This is dependent on 3 being completed. Time may vary based on responses from stakeholders.

5 Re-design and further CDM if necessary

ASM and required Stakeholders

TBD To address any critical issues with the initial conceptual design

6 Formal IFP Design and Evaluations

ASM Procedure designers

TBD Time may be greater depending on design complexities.

Page 19: Sub-Project to Develop and Implement a Performance-Based ...

PBN Airspace Concept for the CAR Region Appendix B to the Report

B-2 TASK

# DESCRIPTION INVOLVED PARTIES TIME

(APPROX.) REMARKS

7 Simulation Exercises ASM Procedure designers ATS & ANS Safety

TBD Requires simulator exercises to be built. This is for initial validation of the design and is not to be confused with ATCO training. This may require incorporation of ALL designs in order to determine how each procedure affects another. They will provide insight into any possible ATS operational concerns.

8 Create draft IFP chart ASM Procedure designers

TBD Dependent on 7 being completed. Time is dependent on design complexities.

9 Document and Store ASM Procedure designers

TBD Completion of Procedure and ARINC 424 Coding reports.

10 Conduct safety activities

ASM Procedure designers ATS and ANS Safety

TBD Recommended to start simultaneously with 7 but also requires 9 to be completed in order for full safety assessment to be conducted.

11 Conduct IFP design verification

ASM Procedure designers

TBD 2 days for first review. 1 day for any corrective actions to be addressed by designer. 1 day for second review. Time may be greater depending on design complexities.

12 Conduct Ground validation

Qualified IFP Validator.

TBD Time can vary based on availability of resources.

13 Present final design to stakeholders and agreement on effective date

Relevant Stakeholders. ASM Procedure designers ATS & ANS Safety

Variable Stakeholders’ endorsement. Timeline depends on stakeholders’ response time.

14 Flight Validation (if required)

Flight Validation service provider. CNS ASM Safety Regulations

TBD Coordination with CNS regarding the Flight scheduling.

15 ICAO Approval

ASM

TBD Waypoint 5LNC approvals. ICARD Database update. Time is dependent on ICAO response.

16 IFP Approval Safety Regulations ASM

TBD Time dependent on Safety Regulations

17 ATM system update to reflect map/route changes on GRP

ASM Procedure designers CNS ATS & ANS Safety

TBD Coordination with ATM System provider.

Page 20: Sub-Project to Develop and Implement a Performance-Based ...

PBN Airspace Concept for the CAR Region Appendix B to the Report

B-3 TASK

# DESCRIPTION INVOLVED PARTIES TIME

(APPROX.) REMARKS

18 Develop Training Plan and Training Delivery to Operational ATS Staff

ASM Procedure designers ATM ATS & ANS Safety Safety Regulations

TBD Requires coordination with ATM regarding the development of a training plan and provision of instructors. ATS & ANS Safety to advise of training schedule

19 Submit IFP package to AIM for publication

AIM TBD IFP Data to be submitted 1 month before proposed promulgation date for AIM processing.

AIRAC supplement to be promulgated 1 or 2 months prior to effective date.

20 Verify Draft Publication

ASM AIM.

TBD This will occur simultaneously with 19 and must be completed prior to promulgation of the AIRAC supplement.

21 Implementation ATS & ANS Safety ASM Procedure designers

TBD Requires completion of all above tasks

22 Obtain and analyse feedback from stakeholders

ASM

Variable Post implementation

23 Conduct continuous maintenance

ASM AIM ATS & ANS Safety Airline Operators

Variable Post implementation

24 Conduct periodic review

Designer. AIM. Safety Regulations

TBD Post implementation. ICAO requires periodic review to ensure that IFPs continue to comply with changing criteria and meet user requirements, and to ensure that significant changes to the obstacles, aerodrome, aeronautical and navaid data are assessed for their impact on the IFPs. ICAO stipulates review period must not exceed 5 years.

Page 21: Sub-Project to Develop and Implement a Performance-Based ...

PBN Airspace Concept for the CAR Region Appendix C to the Report

C-1

APPENDIX C ANSP– PBN Route Design Work Flow

Proposed work breakdown plan for continued development of RNAV 5 routes within the CAR Region in accordance with the CAR PBN Harmonization Sub-Project

Task # Descriptions Parties Involved Time

(Approx.)

Remarks

1 Initiation Stakeholders -Procedure Designers -ASM - ATS & ANS Safety - Airline operating agencies - ICAO NACC Offices - IATA - CANSO - Safety Regulations -Adjacent ANSPs - Any other stakeholder

TBD Start date based on agreement by ASM and ATM managers & ANS Safety and approval. During this meeting, KEY stakeholders and responsibilities will be identified and a more detailed project plan will be created. Actual time for this phase is dependent on the CDM process and the time it takes for each stakeholder to respond. The East/West and North/South traffic flow will be addressed in this project.

2 Collection and validation of all data

ASM, ATS and ANS Safety, AIM, CNS IATA Aircraft Operators Additional Stakeholders.

TBD Start date – Based on agreement by ANS Management. It is NOT totally dependent on responses from all stakeholders in task 1.

o PBN Equipage data collect

▪ RNAV 5

o Operational Flight data ▪ ATC considerations ▪ Operator preferred flight routes

3 Create conceptual

design ASM Procedure designers

TBD Time is dependent on 1 & 2 being completed

4 Review by stakeholders

ASM Procedure designers ATS & ANS Safety Involved Stakeholders.

Variable This is dependent on 3 being completed. Time period may be varied based on responses from stakeholders.

5 Re-design and further CDM if necessary

ASM Procedure designers Required Stakeholders

TBD To address any critical issues with the initial conceptual design

6 Formal Route Design and Evaluations

ASM Procedure designers

TBD Time will depend on design complexities.

7 Simulation Exercises (if required)

ASM Procedure designers ATS & ANS Safety

TBD This requires simulator exercises to be built. This is for initial validation of the design and is not to be confused with ATCO training. Will provide insight into any possible design flaws.

Page 22: Sub-Project to Develop and Implement a Performance-Based ...

PBN Airspace Concept for the CAR Region Appendix C to the Report

C-2

Task # Descriptions Parties Involved Time

(Approx.)

Remarks

8 Create draft aeronautical chart

Procedure designers TBD Dependent on 7 being completed. Time will depend on design complexities.

9 Document and Store

ASM Procedure designers

TBD Process and assimilate all aeronautical data required for safety assessment and publication.

10 Conduct Safety Assessment

ASM Procedure designers ATS & ANS Safety

TBD Recommended to start simultaneously with 7 but also requires 9 to be completed in order for full Safety assessment to be conducted.

11 Present final design to stakeholders and agreement on effective date

Relevant Stakeholders. ASM Procedure designers ATS & ANS Safety

Variable Stakeholders’ endorsement. Timeline depends on Stakeholders’ response time. It should be noted that this process MAY be lengthy as it involves coordination with adjacent ANSPs.

12 ICAO Approval

ASM

TBD Routes and Waypoint 5LNC approvals. ICARD database updates. Time is dependent on ICAO response.

13 ATM system update to reflect map/route changes on GRP

ASM Procedure designers CNS ATS & ANS Safety

TBD Coordination with ATM System provider.

14 Develop Training Plan and Training Delivery to Operational ATS Staff

ASM Procedure designers ATM ATS & ANS Safety Safety Regulations

TBD Requires coordination with ATM regarding the development of a training plan and provision of instructors. ATS & ANS Safety to advise of training schedule

15 Notification to Safety Regulations

State Licensing. ASM

TBD

16 Submit aeronautical information package to AIM for publication* (*Logistics for responsibilities still to be finalized)

ASM AIM

TBD Data to be submitted 1 month before proposed promulgation date.

AIRAC supplement to be promulgated 1 or 2 months prior to effective date.

17 Verify Draft Publication

ASM Procedure designers AIM.

TBD This will occur simultaneously with 16 and must be completed prior to promulgation of the AIRAC supplement.

18 Implementation ATS & ANS Safety ASM Procedure designers

TBD Requires completion of all above tasks

19 Obtain and analyse feedback from stakeholders

ASM

Variable Post implementation

Page 23: Sub-Project to Develop and Implement a Performance-Based ...

PBN Airspace Concept for the CAR Region Appendix C to the Report

C-3

Task # Descriptions Parties Involved Time

(Approx.)

Remarks

20 Conduct continuous maintenance

Procedure designers State Safety Regulations ATS and ANS Safety AIM

Variable Post implementation

21 Conduct periodic review

ASM Procedure designers AIM State Safety Regulations

TBD Post implementation ICAO requires periodic review to ensure that Airspace Organization and Management continue to comply with changing criteria and meets user requirements.

Page 24: Sub-Project to Develop and Implement a Performance-Based ...

APPENDIX D

PBN IMPLEMENTATION STATUS FORM

Table 1 – STATE/ORGANIZATION INFORMATION STATE: Name of State. If not applicable use N/A.

ORGANIZATION: Name of the Organization.

FIR: Name of FIR. If not applicable use N/A.

TMA(s): List the Terminal Area(s) (TMAs) for which the STATE/ORGANIZATION has responsibility.

AERODROMES: List the Aerodromes for which the STATE/ORGANIZATION has responsibility.

Table 2 – GENERAL PBN QUESTIONS QUESTION ANSWER REMARKS

Has a PBN Airspace Concept Document been approved by your organization? Y N

Has the PBN Airspace Concept Document been submitted to the ICAO NACC Office?

Y

N

Is your Aeronautical information Publication (AIP) published online? Y N

Page 25: Sub-Project to Develop and Implement a Performance-Based ...

D-2

Table 3 – UPPER AIRSPACE INFORMATION UPPER

AIRSPACE INITIATIVE STATUS

Statement as to whether task has been achieved.

Provide evidence in the form of reference to AIP and Scanned page(s)

If not applicable (for States/Organization who may

not have an UPPER Airspace) use N/A

REMARKS Comments from State/Organization regarding why the task has

not been achieved. Projected timeline for completion (if available).

FIR NAME CONTINENTAL AIRSPACE

If not applicable use N/A

Implementation of RNAV 5 routes as agreed to in the Regional ANP

Removal of conventional routes made redundant by PBN route implementation

Page 26: Sub-Project to Develop and Implement a Performance-Based ...

D-3

UPPER

AIRSPACE INITIATIVE STATUS

Statement as to whether task has been achieved.

Provide evidence in the form of reference to AIP and Scanned page(s)

If not applicable (for States/Organization who may

not have an UPPER Airspace) use N/A

REMARKS Comments from State/Organization regarding why the task has

not been achieved. Projected timeline for completion (if available).

FIR NAME CONTINENTAL AIRSPACE

If not applicable use N/A

Implementation of RNAV 1/2 SIDs/STARs (CCOs and CDOs) to TMAs within the FIR

Implementation of 20NM longitudinal separation at FIR Boundaries (WHERE APPLICABLE)

All points corresponding to routes from the regional air navigation plan, published by the State in their AIP, are identical to the coordinates stored in the ICARD database.

Page 27: Sub-Project to Develop and Implement a Performance-Based ...

D-4

UPPER

AIRSPACE INITIATIVE STATUS

Statement as to whether task has been achieved.

Provide evidence in the form of reference to AIP and Scanned page(s)

If not applicable (for States/Organization who may

not have an UPPER Oceanic Airspace) use N/A

REMARKS Comments from State/Organization regarding why the task has

not been achieved. Projected timeline for completion (if available).

FIR NAME OCEANIC AIRSPACE

If not applicable use N/A

Use of 50 NM Lateral Separation

Use of 30NM Longitudinal and Lateral Separation

Page 28: Sub-Project to Develop and Implement a Performance-Based ...

D-5

Table 4 LOWER AIRSPACE INITIATIVE STATUS

For each Aerodrome and RWY Statement as to whether task has been achieved.

Provide evidence in the form of reference to AIP and

Scanned page(s)

If not applicable (for States/Organization who may not have Lower Airspace) use N/A

REMARKS Comments from State/Organization regarding why task has not been achieved. Projected timeline for completion (If available).

If not applicable use N/A

Name of TMA If not applicable use N/A

List Aerodromes for which the STATE/ORGANIZATION has responsibility

Implementation of LNAV approaches for International Airports

Implementation of APV BARO VNAV approaches for International Airports if analysis determines a benefit

Implementation of RNP AR Approaches if analysis determines a benefit

Page 29: Sub-Project to Develop and Implement a Performance-Based ...

D-6

LOWER AIRSPACE INITIATIVE STATUS

For each Aerodrome and RWY Statement as to whether task has been achieved.

Provide evidence in the form of reference to AIP and

Scanned page(s)

If not applicable (for States/Organization who may not have Lower Airspace) use N/A

REMARKS Comments from State/Organization regarding why task has not been achieved. Projected timeline for completion (If available).

If not applicable use N/A

Implementation of APV (GBAS) Approaches if analysis determines a benefit

Implementation of RNAV 1/2 SIDs and STARs

Table 5 ‐ Comments COMMENTS FROM STATE/ORGANIZATION REGARDING PBN IMPLEMENTATION ROADBLOCKS

— END —