Study Team - Orica
Transcript of Study Team - Orica
Study Team
Study Team
URS Australia Pty Ltd EIS Study Team
Chris Jack Project Director
Neil Weston Project Manager
Judy Cao Associate Environmental Scientist
Andrew Dudgeon Environmental Engineer
Justin Bell Environmental Engineer
Neil Benning Principal Engineer – Floodplain Management
Andy Homewood Associate Landscape Architect
Chani Lokuge Associate Environmental Engineer
Joe Duran Principal Hydrogeologist
Carla Davies GIS and Drafting
Brook Hambly GIS and Drafting
Specialist Studies
Alternatives Assessment Gary Smith, Senior Project Manager
URS Corporation
Baton Rouge, Louisiana
Peter Dalglish, Principal Civil Engineer
URS Australia Pty Ltd
Statutory Planning Advice Michael England, National Practice Leader
HLA Envirosciences Pty Ltd
Geotechnical Investigations Grahame Wilson, Principal
Douglas Partners Pty Ltd
Groundwater Extraction Modelling Dr Noel Merrick
National Centre for Groundwater Management
accessUTS Pty Ltd
Groundwater Modelling Peer
Review
Alan D Lasse
A D Lasse Hydrologic Consulting
Grand Junction, Colorado
Noise Assessment Steven Cooper
The Acoustic Group Pty Ltd
Aquatic Ecology Dr. Peggy O’Donnell
The Ecology Lab Pty Ltd
AvifaunaAvifauna Research & Services
Botany Groundwater Cleanup Project – Environmental Impact Statement i
Phil Straw
Study Team
Air Quality Modelling Kirsten Lawrence
Pacific Air & Environment Pty Ltd
Preliminary Hazard Assessment
Dean Shewring
Pinnacle Risk Management Pty Ltd
Health Risk Assessment Jackie Wright, Principal Environmental Scientist
URS Australia Pty Ltd
Orica BGC Project EIS Team
Lucy Archer Environmental Consultant – KBR
Barbara Campany Communications Manager – Orica
Robert Castagnini Engineering Project Manager – Orica
Paul Cornford Process Technology Manager – Orica
Dr Brian Dale Risk Consultant Orica
Bob Duthie Project Manager – Orica
Dr Gillian Eckert Environmental Consultant – KBR
Robert Evans Site Environment Engineer Orica
Geoff Fairey Plant Engineer – Orica
James Fairweather Manager, Environmental Projects – Orica
Garry Gately Corporate Occupational Hygienist – Orica
Bruce Gotting Site Environment Manager Orica
Dr John Lear Project Technical Manager Orica
Kate O’Connell Communications Consultant Orica
Graeme Richardson General Manager, BGC Project Orica
Roy Rose General Manager, Technology & Environment – Orica
James Stening Senior Environment Engineer – Orica
Janice van Reyk General Counsel – Orica
Louise Walker Environment Writer – Orica
Isabel Workman Technical Editor – KBR
David O’Donnell, Rebecca Dixon
and Debra Townsend
Mallesons Stephen Jaques
ii Botany Groundwater Cleanup Project – Environmental Impact Statement
Abbreviations
A ABS Australian Bureau of Statistics AC asphaltic concrete ACARRE Australian Centre of Advanced Risk and Reliability Engineering Ltd ADI Acceptable Daily Intake AHC Australian Heritage Commission AHD Australian Height Datum ANSTO Australian Nuclear Science and Technology Organisation ANZECC Australian and New Zealand Environment and Conservation Council ARI Average Recurrence Interval AS Australian Standard ASS Acid Sulphate Soils B BAT Best Available Techniques BGC Project Botany Groundwater Cleanup Project BIP Botany Industrial Park BLEP Botany Local Environmental Plan 1995 BLEVE Boiling Liquid Expanding Vapour Explosion BOD Biochemical (Biological) Oxygen Demand BoM Bureau of Meteorology C CAMBA China–Australia Migratory Bird Agreement CAPER NSW Clean Air (Plant and Equipment) Regulation 1997 CBD Central Business District CCBB Council of the City of Botany Bay CEMP Construction Environmental Management Plan CHC Chlorinated Hydrocarbon CLC Community Liaison Committee Cl2 chlorine CO carbon monoxide CO2-e carbon dioxide-equivalent COD Chemical Oxygen Demand COPC Chemical (Contaminant) of Potential Concern CPT Cone Penetration Test CTC carbon tetrachloride D DA Development Application dB(A) decibels (A range) DEC Department of Environment and Conservation (incorporating National Parks
and Wildlife Service (NPWS), Environment Protection Authority (EPA), Royal Botanic Gardens and Resource NSW).
DEH Australian Government, Department of the Environment and Heritage DG Director-General (usually with reference to DIPNR) DG Act Dangerous Goods Act 1975 DGRs Director-General’s Requirements DIPNR Department of Infrastructure, Planning and Natural Resources DLWC Department of Land and Water Conservation (now DIPNR) DNAPL Dense Non-Aqueous Phase Liquid DUAP Department of Urban Affairs and Planning
Botany Groundwater Cleanup Project – Environmental Impact Statement i
Abbreviations
E EC Electrical Conductivity EDC ethylene dichloride (or 1,2-dichloroethane) EHC Act Environmentally Hazardous Chemicals Act 1985 EIS Environmental Impact Statement EMP Environmental Management Plan EMS Environmental Management System EP&A Act Environment Planning and Assessment Act 1979 (NSW) EPA Environment Protection Agency of NSW EPBC Act Environment Protection and Biodiversity Conservation Act 1999 (Cth) EPI Environmental Planning Instrument EPL Environment Protection Licence ERP Emergency Response Plan ESBS Eastern Suburbs Banksia Scrub ESD Ecologically Sustainable Development F FHA Final Hazard Analysis FM Act Fisheries Management Act 1994 (NSW) FRTR Federal Remediation Technologies Roundtable (US Govt) G GCP Groundwater Cleanup Plan GHG Greenhouse Gas GTP Groundwater Treatment Plant H ha hectare (1 ha = 10,000 square metres) HAZOP Hazard and Operability Studies HCB hexachlorobenzene HCE hexachloroethane HCBD hexachlorobutadiene HCl hydrogen chloride (forms hydrochloric acid on contact with water) HHRA Human Health Risk Assessment HIPAP 4 Hazardous Industry Planning Advisory Paper No. 4 HIPAP 6 Hazardous Industry Planning Advisory Paper No. 6 hr hour HRA Health Risk Assessment H2S hydrogen sulphide I IBC Intermediate Bulk Container ICI Imperial Chemicals Industry (ICI Australia is now Orica) IGAE Intergovernmental Agreement on the Environment J JAMBA Japan–Australia Migratory Bird Agreement K kg kilogram km kilometre kW kilowatt kWh kilowatt hour
II Botany Groundwater Cleanup Project – Environmental Impact Statement
Abbreviations
L LAT Lowest Astronomical Tide LEP Local Environmental Plan LGA Local Government Area M m metre m3 cubic metre
mg milligram µg microgram mm millimetres MW megawatt MWh megawatt-hour N Na sodium NaOH sodium hydroxide (caustic soda) ng/m3 nanogram per cubic metre NCUA Notice of Clean Up Action NHMRC National Health and Medical Research Council NOHSC National Occupational Health & Safety Commission NOx oxides of nitrogen NO2 nitrogen dioxide NO nitric oxide N2O nitrous oxide NPW Act National Parks and Wildlife Act 1974 NPWS National Parks and Wildlife Service of NSW NRTC National Road Transport Commission NSW New South Wales NSWASSMAC NSW Acid Sulfate Soils Management Advisory Committee NT National Trust O Orica Orica Australia Pty Ltd O2 oxygen O3 ozone OLM Ozone Limiting Method P PASS Potential Acid Sulphate Soils PCA Primary Containment Area PCE tetrachloroethene (commonly called perchloroethylene) PCDD polychlorinated dibenzodioxin (or dioxin) PCDF polychlorinated dibenzofuran (or furan) PFM Planning Focus Meeting PHA Preliminary Hazard Analysis PLC Programmable Logic Controller POEO Act Protection of the Environment Operations Act 1997 POEO Regs Protection of the Environment Operations Regulations 1998 POPs Persistent Organic Pollutants pphm parts per hundred million ppm parts per million PVC polyvinyl chloride Q QRA Quantitative Risk Assessment
Botany Groundwater Cleanup Project – Environmental Impact Statement iii
Abbreviations
R REF Review of Environmental Factors RF Act Rivers and Foreshores Act 1948 RO Reverse Osmosis RTA Roads and Traffic Authority S SCA Secondary Containment Area SEPP State Environmental Planning Policy SESPHU South East Sydney Public Health Unit SGS Societe Generale de Surveillance (independent lab) SIS Species Impact Statement SLOT Specified Level of Toxicity SOx oxides of sulphur SO2 sulphur dioxide SO3 sulphide SO4 sulphate SMS Stormwater Management Scheme SPC Sydney Ports Corporation SSU Steam Stripping Unit SWC Sydney Water Corporation SWMP Soil and Water Management Plan SWSOOS Southern and Western Suburbs Ocean Outfall Sewer (operated by Sydney
Water Corporation) T TAPM The Air Pollution Model TCDD tetrachlorodibenzo-p-dioxin TCE trichloroethene (or trichloroethylene) TEQ Toxic Equivalency TPH Total Petroleum Hydrocarbons TMP Traffic Management Plan TOD Total Oxygen Demand TSC Act Threatened Species Conservation Act 1995 U UNEP United Nations Environment Programme URS URS Australia Pty Ltd US EPA United States Environmental Protection Agency UTS University of Technology, Sydney V VC vinyl chloride VCM vinyl chloride monomer VOC Volatile Organic Compound VRA Voluntary Investigation and Remediation Agreement W WARR Act NSW Waste Avoidance and Resource Recovery Act, 2001 WHO World Health Organisation WMP Waste Management Plan wt% percentage by weight X −
IV Botany Groundwater Cleanup Project – Environmental Impact Statement
Abbreviations
Y yr year Z − Greek Symbols µg microgram µS/cm microsiemens per centimetre (a measure of electrical conductivity, used to infer
salinity)
Botany Groundwater Cleanup Project – Environmental Impact Statement v
Glossary of Terms
Glossary of Terms
Activated Carbon A form of carbon with a fine porous structure, which makes it highly adsorbent and therefore effective in removing organic or inorganic compounds from water or gas.
Adsorption The attraction and adhesion of a layer of molecules from a liquid or gas to the solid surface with which it is in contact.
Air stripping Air is blown upwards through a falling column of contaminated water. The air ‘drives off’ the contaminants from the water, producing a dilute air stream containing organic vapours. This occurs in a structure called a stripping column.
Algae Simple organisms containing chlorophyll which live in aquatic habitats, or in locations with sufficient moisture on land.
Ambient Existing conditions to which people, plants and animals are exposed. Amphipod Small crustaceans, also known as freshwater shrimps, that feed by 'browsing'
i.e. moving over the surface of the sediment, consuming organic matter as they go.
Anticyclone Meteorological term, meaning winds spiralling out from a centre of high pressure.
Aquifer An underground geological formation that contains water and is capable of yielding water to a well or spring; a water bearing formation.
Artefact Man-made object. Arterial road Road which carries traffic from one region to another, forming principal avenues
of conveyance for metropolitan traffic movements. Atmospheric stability Refers to the atmosphere’s ability to mix and disperse a plume (or emission of
gas). Asphyxiant A gas or mixture which can displace the oxygen in an environment such that
respiration (breathing) cannot be supported. Basel Convention A convention at which Australia ratified an international treaty for the control of
trans-border movements of hazardous wastes and their disposal. Benthic Relating to the bottom of a water body such as a river, sea, lake or estuary. Bioaccumulation The build-up of a substance in the body of a living organism.
Biochemical Oxygen Demand (BOD)
A measurement of how much oxygen will be directly consumed by a particular sample of water through biological processes.
Biodiversity The variety of life forms, the different plants, animals and micro-organisms, the genes they contain and the ecosystems they form.
Bioregion A territory defined by a combination of biological, social and geographical criteria rather than by geopolitical considerations; generally, a system of related, interconnected ecosystems.
Bioremediation Removal of organic contamination by utilising naturally occurring or specifically engineered or introduced bacteria.
Biota Animal and plant life in a region. Biotic Involving biological activity. Botany Groundwater Cleanup Project
A group of activities, including the GTP, which Orica is undertaking to prevent contaminated groundwater flowing to Penhryn Estuary and Botany Bay, in order to meet the requirements of the NCUA.
Botany Industrial Park (BIP)
The BIP is occupied by various companies, including Orica, which have manufacturing facilities or operations there.
Bund A structure consisting of a base and walls designed to contain spillage/leakage from stored liquid materials, typically installed around storage
Botany Groundwater Cleanup Project – Environmental Impact Statement i
Glossary of Terms
tanks. Cadastral Showing property boundaries. Catchment The entire land area from which water (e.g. rainfall) drains to a specific
watercourse or waterbody. Central EDC Plume Composed of one plume (C1) which consists predominantly of EDC with
concentrations greater than 5,000 mg/L in the core of the plume, inferred to originate from the former EDC storage tanks on the BIP.
Chlorinated Hydrocarbon (CHC)
CHC is a generic term given to a range of chemical compounds, composed of chlorine, hydrogen and carbon. The groundwater below the BIP and nearby areas has been contaminated with CHCs. The main CHC contaminants in the groundwater are ethylene dichloride (EDC), carbon tetrachloride (CTC), tetrachloroethylene (PCE), trichloroethylene (TCE) and vinyl chloride (VC).
Commissioning The final stage of the construction phase, comprising a series of tests and adjustments to demonstrate the required performance of equipment prior to handover to the operator.
Cone Penetration Test (CPT)
Test involving a 35 mm diameter rod with a cone tip being pushed into the ground, and measuring the end bearing resistance on the cone and the friction resistance on a separate sleeve behind the cone. The measurements can be compared to empirical charts to derive an interpretation of the stratigraphic sequence (i.e. layers of different soil and rock types) through which the cone tip has penetrated.
Confined aquifer An aquifer whose upper and/or lower boundaries are confined by an impermeable geologic formation.
Decommissioning The final stage of a development, involving the ceasing of operations, and the dismantling, removal and disposal of its component parts.
Dense Non-Aqueous Phase Liquid (DNAPL)
DNAPLs are denser-than-water liquids, such as chlorinated hydrocarbon (CHCs), that may exist as interconnected droplets in the soil and/or groundwater. These substances are not very soluble in groundwater, so may exist for a long time slowly contaminating passing groundwater.
‘De novo’ synthesis Chemical reaction through which chemicals such as dioxins and furans can be formed by the recombination of destruction products following the destruction of chlorinated hydrocarbons in a thermal oxidiser.
Deposition The build-up, over time, of a material in the air as it settles out of the air (e.g. onto soil).
Drawdown A lowering of the water table of an unconfined aquifer or the potentiometric surface of a confined aquifer caused by pumping from wells.
Dioxins Dioxins and furans are halogenated aromatic hydrocarbons. There are 75 different dioxins, or polychlorinated dibenzodioxins (PCDDs), and 135 different furans, or polychlorinated dibenzofurans (PCDFs). Each different form is known as a ‘congener’. They are Persistent Organic Pollutants, which can bioaccumulate in the body, potentially leading to cancer.
Ecosystem An interdependent system of interacting plants, animals and other organisms together with the non-living (physical and chemical) components of their surroundings.
Ecologically Sustainable Development
Development that aims to meet the needs of the present community without compromising the ecological processes on which life depends for the benefit of future generations.
EDC Ethylene dichloride or 1,2-dichloroethane. The most common contaminant in the Botany groundwater. A manufactured chemical used commonly as a solvent and also used to make VC (vinyl chloride monomer) from which PVC (a common plastic) is manufactured.
II Botany Groundwater Cleanup Project – Environmental Impact Statement
Glossary of Terms
Eight Part Test A test to analyse the significance of potential impacts of proposed developments on threatened species, populations and communities and/or their habitats as specified under Section 5A of the Environmental Planning and Assessment Act 1979.
Emergency Response Reaction by trained personnel and/or emergency services to an accident or emergency.
Endangered Species Those plants and animal species likely to become extinct unless action is taken to remove or control the factors that threaten their survival.
Endemic Species that naturally occurs in only one area or region. Environmental Impact Assessment
Formal and systematic evaluation of a proposal, to assess potential impacts on the environment and identify management measures to minimise such impacts
Environmental Management Plan
Control, training and management measures to be implemented in the construction and operation phases of a project in order to avoid, minimise or mitigate potential environmental impacts.
Ex situ External to the location. In the groundwater cleanup context, ex situ means cleanup of the water not in the ground.
Equipotential A line in a two dimensional groundwater flow field such that the total hydraulic heads (or pressures) are equal for all points along the line.
Fauna The entire animal life of a region. First-Flush The first runoff water after rain over a defined surface. Flora The entire plant life of a region. Foraging Searching for food. Fugitive Emissions Emissions released to the air other than those from stacks or vents. Geotechnical Relating to the form, arrangement and structure of the geology Greenhouse Challenge Launched in 1995. A joint voluntary initiative between the Federal Government
and industry to abate greenhouse gas emissions. Greenhouse Effect Predicted global climate change resulting from build-up of certain gases, such
as carbon dioxide, within the Earth’s atmosphere, trapping heat from the sun, increasing global temperatures
Greenhouse Gas A gas that increases the atmosphere’s ability to trap heat, rather than lose the heat to space.
Groundwater Groundwater is the general term for water in the ground. Underground water bodies are known as aquifers.
Groundwater Embargo Area
Previously known as Groundwater Protection Zone 2. The area has been declared by DIPNR as a combined buffer zone around the exclusion area and incorporates localities with known or suspected contamination from past industrial activity.
Groundwater Extraction Exclusion Area
An area around the known contamination plumes originating from the BIP (previously known as Groundwater Protection Zone 1). Within this area DIPNR has declared that no groundwater extraction should take place (unless with DIPNR’s permission) until further notice.
Heritage A term referring to Aboriginal and colonial archaeological sites and material remains.
Huntsman Corporation Australia Pty Ltd
Manufacturer of surfactants located on the BIP.
Hydrology The study of the behaviour of water in the atmosphere, on the surface of the earth and underground.
Hydrogeology Scientific considerations relating to geological formations, soil, surface water,
Botany Groundwater Cleanup Project – Environmental Impact Statement iii
Glossary of Terms
and especially groundwater. Hydraulic conductivity A coefficient of proportionality describing the rate at which water can move
through a permeable medium (e.g. an aquifer). Hydraulic containment Measures taken to lower the potentiometric surface and/or water table and
effect hydraulic capture of the contaminant plume. The use of a line of extraction wells pumping water out of the ground to form an effective barrier. This stops the groundwater moving past the barrier and contains the plumes.
Hydraulic gradient The change in total head in an aquifer, with the change in distance in a given direction. The steeper the ‘slope’ of the groundwater, the faster it should flow.
Infiltration The process of water entering the soil. Infrastructure Basic structure of fixed capital items to support the operation of a facility, e.g.
roads, drains, utilities (water, gas). In situ In the context of groundwater cleanup, this refers to performing the cleanup in
the ground. Inter-generational equity Principle whereby the present generation should ensure that the health,
diversity and productivity of the environment is maintained or enhanced for the benefit of future generations
Isotainer A bulk liquids tank container (typically 20 m3) designed to prevent spills or leaks during frequent transport movements through robust design. Designed to fit standard ISO (International Standards Organisation) sizes for transport containers.
Key Threatening Process
As defined under Section 220F of the Fisheries Management Act 1994 as a process that ‘adversely affects two or more threatened species, populations or ecological communities or causes the listing of a species, population or ecological community as threatened’.
Lamella filter A filter made up of a series of inclined plates designed to assist in the sedimentation (settling) of particles from solution.
LA90 Noise level exceeded for 90% of the 15 minute interval. Leq Equivalent continuous sound level in dB(A), i.e. the constant sound level that
has the same acoustic energy as the original fluctuating noise for the same period of time.
Lithology The geological (physical) character of a rock or soil. Maximum ground level (MGL) concentration
The maximum predicted concentration of a species, measured (or calculated) at ground level, at any position in the region of investigation.
Megawatt-hour A unit of energy equal to one million watts of power operating for one hour. Mollusc Invertebrae having a soft unsegmented body usually enclosed in a shell i.e.
oyster, mussel Northern Plume Comprises five separate plumes (N1, N2, N3, N4 & N5) consisting
predominantly of EDC with maximum concentrations between 100 mg/L and 200 mg/L originating from the northern end of the BIP.
Off-gas Gas containing VOCs generated by the air stripping process, and is treated in the thermal oxidiser.
Performance indicator A comparison of actual conditions with a specific set of reference conditions. They measure the 'distance(s)' between the current environmental situation and the desired situation (target): 'distance to target' assessment.
Persistent A chemical which doesn’t break down in the environment into safe chemicals. pH Measure of alkalinity or acidity of an aqueous solution. Paleochannel Ancient river or drainage feature which has been infilled by younger
sediments.
IV Botany Groundwater Cleanup Project – Environmental Impact Statement
Glossary of Terms
Phytoplankton Free-floating microscopic organisms suspended in the water column. They produce organic material by photosynthesis and are responsible for a large proportion of primary productivity in the ocean.
Piezometer A well with a short slotted screen for measuring a potentiometric surface or elevation of the water table. Also used for collecting groundwater samples at a discrete depth.
Plume (atmospheric) The trail leading from a source as it disperses through the atmosphere, like from a smoke stack.
Plume (groundwater) A mass of contaminated water extending outward from the source of the contamination, similar to smoke from a smoke stack.
PM10 PM10 refers to that fraction of total suspended particulates with an aerodynamic diameter smaller than 10 µm (10 microns, or one hundredth of a millimetre).
Potentiometric surface An imaginary surface representing the total head (or pressure) of groundwater and defined by the level to which water will rise in a well.
Primary Containment Area (PCA)
The Primary Containment Area is defined in the NCUA as Block 2 of Orica Southlands.
Project Area The land extending from the north of the BIP to Penrhyn Estuary and Foreshore Beach.
Qenos Pty Ltd Joint venture company formed by the merging of the polyethylene businesses of Exxon Mobil and Orica.
Quenching In the context of the thermal oxidiser, the rapid reduction in temperature by the addition of large quantities of liquid by spraying it into a hot gas. The cooling primarily occurs through the evaporation of the liquid.
Ramsar Australia is a contracting party to the Ramsar Convention on wetlands. This obliges us to designate and protect wetlands of international significance.
Reactive Iron Barrier In situ technology for the treatment of chlorinated solvents and other contaminants in groundwater via chemical reduction
Recharge The addition of water to an aquifer. Remnant vegetation A small fragmented portion of the former dominant vegetation which once
covered the area before being cleared for human land use. Reverse Osmosis A process for the removal of dissolved ions from water in which pressure is
used to force the water through a semi-permeable membrane which will transmit the water but filter out most other dissolved materials.
Riparian Riverine. Pertaining to a river bank. Scrubbers Equipment that washes a gas stream with liquid to effect the removal of a
substance from the gas. For the off-gas oxidiser, the gas from the thermal oxidiser (after hydrogen chloride removal in the acid absorbing column) is scrubbed with a caustic soda solution to remove residual hydrogen chloride and chlorine.
Secondary Containment Area (SCA)
The area defined in the NCUA as “the location where the EPA approved contaminant containment works upgradient of Botany Bay and Penrhyn Estuary, for the interception and containment of contaminant plumes that have migrated or may migrate beyond the primary containment area, are carried out”.
Section 90 Permit Approval under the National Parks and Wildlife Act, regarding consent to knowingly destroy, deface or damage, or knowingly cause or permit such damage to an Aboriginal artefact or place.
Steam stripping Steam is injected through the groundwater and used to ‘drive off’ the contaminants from the groundwater, and then condensed into a liquid for
Botany Groundwater Cleanup Project – Environmental Impact Statement v
Glossary of Terms
subsequent disposal/destruction. Sound Power Level Logarithmic measure of the sound power in comparison to the reference level
0 dB. Southern Plumes Comprised of three separate plumes (S1, S2 & S3) inferred to be derived from
the former Solvents Plant and the former TCE Plant. Spoil Soil available for use in earthworks. Spot height The elevation (in m AHD) of a point on a map. Stockholm Convention An international treaty to which all signatory parties would phase out the use
and manufacture of persistent organic pollutants including dioxins and furans. Stratigraphy The distribution, deposition and age of rock and soil strata. Sub-arterial road Road which connects arterial roads to areas of development or carry traffic
directly from one part of a region to another. Subsidence Movement of a structure due to change in the structural properties of the
underlying material. The change in groundwater level could lead to movement (collapse) of the soil.
Substation A premises where high-voltage supply is converted, controlled or transformed Sustainable Use The use of an organism, ecosystem or renewable resource at a rate within its
capacity for renewal Temperature inversion A temperature inversion is a meteorological phenomenon where warm air gets
trapped beneath cold air, preventing circulation within the atmosphere. Terrestrial Of, or pertaining to the land Thermal oxidation Process of oxidising materials by raising the temperature of the material in the
presence of oxygen, and maintaining it at a high temperature for sufficient time to complete a reaction to carbon dioxide and water (and HCl where chlorinated hydrocarbons are present in the gas stream).
Threatened species A generic term for a plant or animal generally considered as vulnerable or endangered under various threatened species conservation laws. It is used to indicate that there is some level of threat as to the species viability in the wild.
Topographic Generally refers to a map showing lines of equal height (contours). Toxicity The degree to which a substance is harmful to human health. Volatile Organic Compound (VOC)
Organic chemical with sufficiently low vapour pressure to become a gas at room temperature.
Water balance A method of reconciling all volumes entering or leaving a region, the root zone, or the groundwater system.
Water column A hypothetical cylinder of water from the surface of a water body to the bottom and within which physical and chemical properties can be measured.
Water table The top of the saturated zone where unconfined groundwater is under atmospheric pressure.
Weed Naturalised non-indigenous plant species that is undesirable in a specific location.
VI Botany Groundwater Cleanup Project – Environmental Impact Statement
Executive Summary
ES Executive Summary
ES.1 Background to Botany Groundwater Cleanup (BGC) Project
From 1942 until 1998, ICI Australia Limited then a subsidiary of ICI plc of the UK manufactured a wide
range of chemicals on the Botany site now known as Botany Industrial Park (BIP). As a result of historical
manufacturing activities at that site, there is a legacy of groundwater contamination within the Botany
Sands Aquifer. This contamination occurred during a time when environmental consciousness, and
scientific knowledge about the potential impacts on the environment and standards, were less than they
are today. The operations that caused the contamination have long since been discontinued on the BIP.
In 1997 ICI plc sold its holding in ICI Australia, which was renamed Orica. In 1998 the BIP was subdivided
and is now occupied by various companies with manufacturing plants, including Orica. Orica retained
responsibility for environmental legacies at the site.
Orica has stated that it regrets the groundwater contamination caused in the past and that it is committed
to cleaning it up to prevent long-term environmental damage. Orica realises that many people are
concerned, and it is doing everything possible to address the groundwater contamination with the best
available technology.
Today, the groundwater contamination is present in several underground plumes, which have been
identified and are moving with the groundwater in a southwesterly direction toward Botany Bay. The most
concentrated of the plumes is centred beneath the Orica property known as Southlands, located on
McPherson Street, Banksmeadow.
If no action is taken to contain, recover and treat the contaminants in the groundwater, they will
increasingly pollute Penrhyn Estuary and possibly Botany Bay. Based on most recent monitoring, it is
estimated that high concentrations of contaminants could reach the upper extent of Penrhyn Estuary in
the first half of 2006. This would present potential risks to the recreational users in that area, the marine
environment and protected migratory shorebirds in Penrhyn Estuary.
The Botany Groundwater Cleanup Project (BGC Project) is urgently needed to prevent this from
happening. A key part of this project is the construction and operation of the Groundwater Treatment
Plant (GTP). The GTP requires approvals from relevant government authorities before construction and
operation can begin. These authorities will assess the proposal based on its merits and after considering
the responses received from the community.
The current project follows some 15 years of investigation, research and passive remediation. ICI
Australia, and later Orica, began investigating the contamination problem in 1989. Since that time, Orica
has been investigating and trialing a number of different remediation strategies under a Voluntary
Remediation Agreement (VRA) with the NSW Environment Protection Authority (EPA). These strategies
have included bioremediation and reactive iron barriers.
In September 2003 the EPA issued Orica with a Notice of Clean Up Action (NCUA), which was amended
and consolidated in February 2004. The NCUA sets a framework and timeframe for Orica to contain the
contaminant plumes. Orica’s Groundwater Cleanup Plan (GCP), prepared in response to the NCUA,
resulted in the fast-tracking of a number of projects that focused on hydraulic containment. These include
interim containment and treatment, which is currently in operation.
Botany Groundwater Cleanup Project – Environmental Impact Statement ES-1
Executive Summary
ES.2 Outline of the BGC Project
The broad objective of the BGC Project is to achieve hydraulic containment and reduction of the
contaminants in the groundwater in and around the BIP, to meet the requirements of the NCUA and stop
the plumes moving towards Penrhyn Estuary and Botany Bay. The Project Area is shown in Figure ES.1.
The key elements of the BGC Project are shown schematically in Figure ES.2, and involve:
the extraction of groundwater from the wells installed in the three containment lines (primary,
secondary and DNAPL);
transfer of groundwater via pipelines to the Groundwater Treatment Plant (GTP);
construction and operation of the GTP;
transfer of treated water via pipelines for reuse by process plants in the BIP or discharge to
Bunnerong Canal; and
installation of a discharge point into Bunnerong Canal.
The construction and operation of the GTP is a key part of the BGC Project.
Some of the infrastructure for the BGC Project has already been constructed, under approvals granted
earlier in 2004 by various government authorities as part of the interim containment works required to
enable Orica to meet its obligations under the NCUA. Other infrastructure will be constructed under
separate approvals.
ES.3 The Proponent
The proponent of the BGC Project is Orica Australia Pty Ltd (Orica). Orica is a major manufacturer of
industrial specialty chemicals, fertilisers, explosives and mining chemicals, and paints and consumer
products. Orica operates at several sites, including Botany, and employs some 1500 people in NSW.
ES.4 Planning Approvals Process
Under State Environmental Planning Policy No. 55 – Remediation of Land (SEPP 55), the BGC Project
does not require development consent, because it is being undertaken to comply with the NCUA issued
by EPA. Instead, various elements of the BGC Project must be assessed under Part 5 of the Environment
Planning & Assessment Act (EP&A Act).
Activities assessed under Part 5 that are likely to significantly affect the environment are required to be
assessed in an environmental impact statement (EIS). Although only certain elements of the BGC Project
comprise an ‘Activity’ for the purposes of Part 5, the environmental impact of the overall BGC project is
assessed in this EIS. There are a number of determining authorities responsible for approving various
aspects of the BGC Project, as discussed in Chapter 6.
ES-2 Botany Groundwater Cleanup Project – Environmental Impact Statement
Executive Summary
In accordance with clause 73 of the Environment Planning & Assessment Regulation 2000 (EP&A
Regulation), the requirements for this EIS were sought from relevant government agencies. These
requirements, known as the Director-General’s Requirements (DGRs), have been addressed in this EIS.
The EIS will be publicly exhibited for a minimum of 30 days. The public exhibition period allows
stakeholders and the community to convey their views on the project to the determining authorities.
ES.5 Overview of the Project
The following is a high level overview of the key aspects of the BGC Project.
The project will use the proven technique of hydraulic containment to prevent the plumes moving
towards Penrhyn Estuary and Botany Bay.
The selected treatment technologies will achieve the critical timeline in the NCUA required to stop the
plumes.
Selected treatment technologies to be used in the GTP are based on the use of best practice and
proven equipment, to achieve safe and effective destruction of the contaminants, and to control and
minimise emissions to air, including dioxins and furans.
The technology conforms to the principles of inherent safety, by minimising the inventory of
hazardous materials, and by operating at low pressures and low concentrations.
A systematic human health risk assessment undertaken in consultation with NSW Health as part of
the EIS indicates that the incremental risk from the operation of the GTP to the health of residents,
recreational users of areas surrounding the BIP, and BIP workers is negligible, even under worst case
scenarios. The analysis included an assessment of the potential impacts of long-term exposure to
trace levels of chemicals, such as dioxins, and found the human health impact to be negligible.
Groundwater will be treated to achieve a water quality suitable for reuse as process water for the BIP
and nearby users, thereby reducing the demand on Sydney’s townswater supply.
Emissions to atmosphere from the GTP will meet best practice, stringent air quality emission
guidelines.
The preliminary hazard analysis undertaken as part of this EIS concluded that the potential project
risks comply with the relevant DIPNR risk guidelines.
Preventing contaminants moving towards Penrhyn Estuary and Botany Bay will lead to an
improvement in the commercial, recreational and ecological activities in the foreshore area. Flora and
fauna are unlikely to be significantly affected.
The project incorporates an extensive monitoring program to assess the effectiveness of the hydraulic
containment throughout the project lifetime.
There is negligible land subsidence risk to residential or commercial structures as a result of the
contaminated groundwater extraction.
Energy efficiency measures have been taken into account to minimise greenhouse gas emissions.
Botany Groundwater Cleanup Project – Environmental Impact Statement ES-5
Executive Summary
Even considering existing and proposed industrial and other developments in the area, no significant
cumulative impacts from the project were identified.
The project is consistent with the principles of Environmentally Sustainable Development (ESD),
because it is designed to clean up past contamination legacies for the benefit of current and future
generations in the local communities.
The project will involve the implementation of a range of environmental management measures to
monitor and minimise the impact on the environment throughout the life of the project.
Measures will be put in place to minimise waste generation, and waste will be controlled via a
comprehensive waste management program.
The project will not generate unacceptable levels of noise or cause traffic congestion on local or
arterial roads. Visual impact will be low.
ES.6 Need for the BGC Project
The BGC Project is necessary to address the potential impacts of groundwater contamination on the
environment of Botany Bay and Penrhyn Estuary. Without the proposed containment and treatment, high
levels of the contaminants are likely to eventually discharge into Botany Bay.
Using best practice techniques and processes, the BGC Project seeks to:
achieve the required level of groundwater containment;
achieve the required reduction of the concentration of contaminants in the groundwater;
clean up the contaminant plumes;
minimise air emissions and generation of waste, according to ‘best practice’ design standards; and
undertake sufficient monitoring to identify changes in contaminant concentrations and spatial
distribution of the contaminants and groundwater levels, to optimise the effectiveness of the hydraulic
containment.
ES.7 Alternatives
In order to identify the best technical solution for handling the extracted groundwater, an extensive review
of the locations, treatment techniques and performance requirements was carried out. The following key
objectives were considered mandatory in assessing alternative technologies for treatment:
The technology must be proven and safe.
The technology must be able to handle a large volume of groundwater (up to 15 ML/day) with low
concentrations of contaminants (0.02% w/w).
The technology must be able to meet the air and water emission specifications.
ES-6 Botany Groundwater Cleanup Project – Environmental Impact Statement
Executive Summary
The technology must achieve a critical start-up timeline that stops the plumes in time.
For the BGC Project, best practice is required, particularly in relation to meeting strict air and marine
discharge standards and a high destruction efficiency of contaminants.
Orica reviewed available technologies and identified air stripping with thermal oxidation or steam stripping
as candidate technologies. These options were analysed by the international engineering consultants
Aker Kvaerner, and were found to be technically feasible. Orica further refined these reviews and
selected air stripping with thermal oxidation as its preferred option. The key reasons for this selection
were:
its proven performance in groundwater treatment;
there is no intermediate storage of a hazardous, flammable liquid; and
the thermal oxidiser represents ‘Best Available Technology' as defined by the European Commission
and the United Nations Environment Program for the destruction of CHCs in this type of application.
An independent review by an international remediation expert from URS, carried out as part of the EIS,
identified three alternatives of equal ranking:
air stripping with thermal oxidation;
steam stripping with thermal oxidation; and
steam stripping with thermal pyrolysis (e.g. plasma arc)
This validated Orica’s choice of preferred technology.
The thermal oxidiser proposed will be designed to achieve greater than 99.99% contaminant destruction
efficiency and to satisfy the best practice air emission standards. The selected technology will meet
Australia’s obligations for the minimisation of dioxin and furan emissions under the Stockholm
Convention.
The most suitable site for establishing the GTP was found to be the former Silicates Plant site within the
BIP. The logistics of transporting the huge quantities of groundwater (equivalent to 15 Olympic pools per
day) precluded off-site treatment options for the GTP. In addition, off-site treatment was not feasible
because there is no suitable existing plant that can treat the volume of groundwater required, and Orica
considered that it was not feasible to identify an off-site location for a new plant, and gain the relevant
approvals, in the required timeframe.
Similarly, it was not considered possible to send the extracted contaminants to an off-site facility, because
there is inadequate capacity available. The Basel Convention precludes sending the contaminants for
treatment and disposal overseas. Extended storage of the extracted contaminants would require
significant storage with associated increased risk. The Basel Convention requires destruction at the place
of generation where practical.
A number of options were considered for the management and disposal of the 15 ML/day of treated
groundwater. Reinjection into the aquifer is not preferred, as there are significant challenges in performing
this reliably without disturbing the aquifer and causing flooding. Discharge into the sewer system is not
feasible, because the sewer does not have adequate spare capacity. Reuse of the treated water by users
Botany Groundwater Cleanup Project – Environmental Impact Statement ES-7
Executive Summary
on the BIP was identified as the preferred option, as it provides a sustainable outcome by reducing the
demand from Sydney Water supply. The excess volume that cannot be taken up for reuse would be
safely discharged to Botany Bay.
ES.7.1 ‘Do Nothing’ Option
The ‘do nothing’ option would mean that groundwater could not be extracted at the rates required (some
15 ML/day) to contain the plumes and to provide treatment of this volume of groundwater. It may be
possible to continue with the interim measure already in place, but this would be limited to 2 ML/day and
would not provide adequate long-term protection.
The ‘do nothing’ option would result in high levels of contaminants reaching Penrhyn Estuary and Botany
Bay, leading to:
a potential increase in the impact on the terrestrial and marine flora and fauna in the Foreshore
Beach and Penrhyn Estuary ecosystems, which could affect the migratory shorebirds;
a potential increase in the risks to human health for recreational users on the foreshore and within
Botany Bay, and potential diminished quality of life for residents and workers in the area; and
failure to achieve the aims of the NCUA.
The ‘do nothing’ option would be socially, environmentally and legally unacceptable.
ES.8 Project Description
ES.8.1 Extraction Wells and Pipelines
Groundwater will be extracted by a submersible pump suspended inside each well, discharging into the
transfer pipeline leading to the GTP. Extraction rates are designed to be adjustable, and responsive to
changes in groundwater flow patterns and reducing contamination levels over time.
Monitoring wells will be installed along the containment lines for sampling and measurement, to assess
and optimise the effectiveness of the hydraulic containment and extraction of the contaminant plumes.
The transfer pipelines are 150 mm in diameter and are designed to minimise potential points of leakage.
All aboveground pipelines are within Orica owned land. Underground pipes (used when crossing non-
Orica land) use dual-contained pipes for additional integrity and leak protection.
ES.8.2 Groundwater Treatment Process
A 3D visual simulation of the GTP is shown in Figure ES.3. The proposed process to treat the extracted
groundwater is shown in Figure ES.4. The GTP has been designed for continuous operation to treat up
to 15 ML/day for about 30 years. The process consists of four key stages.
ES-8 Botany Groundwater Cleanup Project – Environmental Impact Statement
Executive Summary
Feed Pre-Treatment
The extracted groundwater will be dosed with hydrochloric acid to minimise the potential for fouling in the
air strippers. The hydrochloric acid will be generated in the GTP off-gas treatment unit.
Air Stripping
The volatile contaminants will be removed from the groundwater by air stripping, where air is blown
upwards through a falling column of groundwater in an enclosure. This produces an off-gas stream
containing the volatiles from the groundwater.
Off-Gas Treatment
The contaminants in the off-gas will be destroyed using thermal oxidation, where they react with oxygen
at high temperature to produce carbon dioxide, water and hydrogen chloride. The operating temperature
will be 1000°C, with a residence time of two seconds to achieve greater than 99.99% contaminant
destruction and to match world’s best practice for dioxin control. Natural gas will be used in the oxidiser to
maintain the required operating temperature.
The hot gases coming out of the thermal oxidiser will be cooled by generating steam in a waste heat
boiler and pre-heating the off-gas from the air stripping units (achieving some energy recovery), followed
by a rapid quench with weak acid to quickly reduce the temperature through the ‘de novo’ zone to
minimise the chance of dioxin formation.
The cooled gas will then pass through an acid absorbing column to produce weak hydrochloric acid (for
use in feed pre-treatment), then through a caustic scrubbing unit to remove any trace hydrogen chloride
or chlorine, before discharge through a stack about 20 m tall.
Stripped Water Treatment
Stripped water from the air stripping process will undergo iron removal (by the addition of caustic soda
and filtration) followed by removal of trace organic compounds (e.g. phenols) using activated carbon.
About 10 ML/day of this water will undergo further treatment using reverse osmosis (RO) to remove salt,
so that the water can be reused on the BIP and elsewhere. This will produce a salty wastewater stream of
about 2.5 ML/day.
The 5 ML/day of excess treated water that does not pass through the RO unit will be combined with the
2.5 L/day of salty wastewater. This combined stream will undergo further treatment to remove organic
acids (e.g. acetic acid) and ammonia. This water will then meet the ANZECC Marines Guidelines to allow
discharge into Botany Bay, via Bunnerong Canal and Brotherson Dock using a refurbished underground
pipeline and a newly constructed outlet.
In the event that the demand on the BIP is lower than predicted (e.g. during maintenance periods) the
unused water would also be diverted to Brotherson Dock via the discharge pipeline.
Orica will continue to seek additional users of the treated water and will expand the RO treatment
capacity as required.
Botany Groundwater Cleanup Project – Environmental Impact Statement ES-11
Executive Summary
ES.8.3 Process Control
Groundwater extraction, transfer, treatment in the GTP and discharge will be operated as an integrated
process, with an automatic computer control system installed to ensure operation within design
parameters. The control system will be located within a dedicated Control Room, with operators based
permanently at the GTP to carry out regular inspections, and to respond to plant upsets.
A separate, high integrity safety shutdown system will be installed, so that in the event of an abnormal
condition being detected, the GTP would be shut down, isolating all feeds and stopping all discharges.
ES.8.4 Construction
GTP
The target construction completion date for the GTP is August 2005. The key milestones required to meet
this target, subject to approvals being obtained, are shown in Table ES.1.
Table ES.1 Construction timing
Timing Activity
February– April 2005 Civil foundations and structural steel works
May August 2005 Equipment, piping, instrumentation and electrical works
August October 2005 Plant commissioning and operation
Before starting construction of the GTP, minor demolition to clear and level the GTP site will occur.
The estimated construction workforce for the GTP is likely to range from about 28 at the start of
construction to a peak of around 115 over the nine month construction period.
ES.8.5 Decommissioning
Whilst the treatment of contaminated groundwater is expected to cease after approximately 30 years,
Orica may continue to treat groundwater from other sources, if available, to provide clean water to
industrial users. In the event that this activity is not pursued, the BGC Project and the GTP would be
decommissioned in consultation with the EPA.
ES-12 Botany Groundwater Cleanup Project – Environmental Impact Statement
Executive Summary
ES.9 Consultation
ES.9.1 Government Consultation
There has been extensive consultation with relevant authorities and agencies throughout the investigation
and assessment of the groundwater contamination issue since the early 1990s.
Consultation during the environmental impact assessment process included a planning focus meeting
with government agencies, and discussions with the following authorities:
Department of Infrastructure, Planning and Natural Resources (DIPNR);
Environment Protection Authority (EPA), part of Department of Environment and Conservation (DEC);
NSW Health;
South East Sydney Public Health Unit (SESPHU);
Council of the City of Botany Bay (CCBB);
Sydney Ports Corporation (SPC);
NSW Waterways Authority (now NSW Maritime Authority);
NSW Fisheries;
NSW Roads and Traffic Authority;
NSW Rail Corp; and
Sydney Water Corporation (SWC).
ES.9.2 Community Consultation
Orica has been engaged in community consultation regarding the groundwater contamination since it was
discovered, through an extensive program designed to inform all stakeholders of actions and activities
being undertaken and to provide the opportunity for effective comment and participation throughout the
process. The process utilises various communications channels including:
the Community Liaison Committee (CLC);
the Orica Botany Groundwater website, at http://www.oricabotanygroundwater.com;
quarterly newsletters distributed throughout the suburbs neighbouring the Orica site;
a regular Orica column in the Southern Courier newspaper presenting information on progress with
the project; and
Botany Groundwater Cleanup Project – Environmental Impact Statement ES-13
Executive Summary
an on-site communications team contactable by telephone or email (with details regularly
advertised).
Four EIS workshops were organised during the preparation of the EIS. Invitations to the workshops were
extended to all interested stakeholders, including members of the CLC, members of the local
communities, representatives of community groups, local industries and non-governmental organisations.
Aside from the EIS workshops, a number of meetings and teleconferences were conducted with specific
organisations (National Toxics Network, Greenpeace and the Council of the City of Botany Bay) to
understand the particular issues and concerns that they and their associated members may have about
the BGC Project, and to ensure that these issues were addressed in the EIS.
Under the Community Relations Plan developed for the BGC Project, consultation and communication
with the local communities will be maintained throughout the life of the project.
ES.10 Environmental Impact Assessment
Detailed scientific and environmental studies were undertaken by technical experts as part of this EIS to
enable the potential impacts of the BGC Project to be understood and assessed These studies are
included in the EIS as appendices. The findings of studies, assessment of impacts and the identification
of safeguards are presented in this EIS and are summarised below.
ES.10.1 Land Use
The BGC Project will be compatible with industrial development already existing in the Banksmeadow
industrial area and will not affect existing land uses within the Project Area. In addition, the successful
completion of the project could eventually lead to lifting of DIPNR’s current restrictions on use of the
groundwater in the area, and to an alleviation of concerns relating to recreational activities in and around
Foreshore Beach, which would have a positive impact on surrounding land uses and improved amenity.
ES.10.2 Geology, Soils and Geotechnical
Geotechnical studies indicate that the GTP site would provide suitable support for shallow foundations
and pavements. Assessment of soil at the GTP site found that concentrations of metals, hydrocarbons
and chlorinated hydrocarbons (CHCs) are very low and that potential risks to human health and the
environment during or after construction are therefore considered to be negligible.
The potential for erosion and sedimentation during construction of the GTP and off-site infrastructure
would be minimised by employing a Soil & Water Management Plan before and during construction. Due
to the potential for acid sulphate soils (ASS) to be present within the BGC Project area, an ASS
Management Plan will be developed for implementation, should ASS be encountered during construction.
ES-14 Botany Groundwater Cleanup Project – Environmental Impact Statement
Executive Summary
ES.10.3 Hydrogeology
The operation of the BGC Project is designed to alter the existing groundwater flow regime so that
contaminated groundwater is contained before it enters Penrhyn Estuary and Botany Bay.
Computer modelling has been used to determine the optimal layout and operation of groundwater
extraction wells for the cleanup of the groundwater. The results of the modelling have illustrated that the
proposed groundwater extraction well network would be successful in satisfying the requirements for
hydraulic containment of the plumes as described in the NCUA.
One consequence of the groundwater extraction will be a 15% reduction of the total groundwater
discharge into Botany Bay. The rate of groundwater discharge to Penrhyn Estuary will reduce, and the
contaminant levels in that discharge will eventually decline. It is likely that there will be no dry weather
flow in Springvale and Floodvale Drains.
Groundwater extraction and transfer via pipelines to the GTP will be managed and optimised through a
monitoring regime to minimise any potential impacts and to maintain the effectiveness of the hydraulic
containment and groundwater treatment.
Potential subsidence impacts have been assessed and are concluded to be negligible. Orica proposes to
monitor subsidence at relevant locations.
ES.10.4 Water Quality and Wastewater
Construction works will generate small quantities of wastewater from the commissioning of wells. This
contaminated groundwater will be collected by a licensed waste contractor and transferred to existing
bunded tanks prior to treatment at the BIP.
The GTP has been designed to achieve the water quality standards to enable reuse of the treated water
on both the BIP and by other users, and to ensure that there is no negative impact from the discharges of
excess water to Brotherson Dock.
Orica has identified demand for about two-thirds of the available treated water. Treatment capacity will be
installed to meet current reuse demand, with room for expansion to meet future requirements. Orica has
in-principle approval from the NSW Government to recycle and make the treated water available for sale
to other industrial users. Orica will continue to work with relevant authorities and other potential users of
the treated groundwater to maximise the level of reuse, thus reducing the demand on Sydney’s water
supply.
ES.10.5 Hydrology
Assessment of potential surface hydrology impacts determined that the GTP would have negligible effect
on current flood levels along Springvale Drain, both upstream and downstream of the site, up to the 1 in
100 year Average Return Interval (flood) event.
The treated water discharges to Bunnerong Canal will not result in any significant effects on flood levels.
There will be no detrimental effects on sediment transport and erosion in the canal.
Botany Groundwater Cleanup Project – Environmental Impact Statement ES-15
Executive Summary
A Soil and Water Management Plan (SWMP) will be developed for the construction and operational
phases to minimise contaminated runoff from the site.
Potentially contaminated stormwater from the GTP site will be retained within either containment bunds or
the first-flush pit system, to prevent discharge during stormwater events. The retained stormwater (equal
to the volume from the first 15 mm of rain) will be analysed and treated before discharge into either the
GTP feed or the sewer.
All underground sections of the groundwater collection pipes have dual-containment and leak detection.
Regular inspection of the aboveground sections of the transfer pipes will ensure no uncontrolled
discharge of contaminated groundwater to the environment.
ES.10.6 Waste
A Waste Management Plan (WMP) will be developed prior to the construction and operation of the GTP
to optimise the reduction, recycling and reuse of waste materials during the project. The amount of waste
generated during the construction of the GTP will be small. Soil generated during construction of wells will
be collected, dewatered and analysed before disposal.
The principal solid wastes generated by operation of the GTP comprise the spent activated carbon (if it
cannot be regenerated) and dewatered solid waste (from the iron removal and organic acid and ammonia
removal units). Analyses will be undertaken to confirm whether these wastes are suitable for safe
disposal to landfill. Ongoing monitoring of the waste streams will be undertaken according to a program
developed in the WMP to ensure ongoing suitability for landfill disposal.
ES.10.7 Traffic and Transportation
The traffic associated with the construction and operation of the BGC Project will lead to very minor
increases on arterial and sub-arterial road traffic volumes, which are not considered significant. Local
roads will not be used. Therefore, any increases in traffic as a result of the project will not affect local
traffic or the availability of parking on local streets. Transport of the recovered waste EDC liquid,
temporarily stored at Terminals Pty Ltd’s facility at Port Botany, to the BIP will be undertaken using
designated access routes, in accordance with the Botany Local Environment Plan 1995.
ES.10.8 Energy and Greenhouse Gases
The overall design of the BGC Project incorporates energy efficiency design criteria while still achieving
best practice destruction efficiencies of the extracted contaminants. Energy use during the construction
phase, mainly of fuel, is not expected to be significant. The electrical energy use has been estimated to
be equivalent to about 22,500 tonnes of carbon dioxide (CO2) a year. The operation of the thermal
oxidiser is estimated to be equivalent to about 33,000 tonnes of CO2 annually.
ES-16 Botany Groundwater Cleanup Project – Environmental Impact Statement
Executive Summary
ES.10.9 Visual Impact Assessment
The BGC Project is located within an existing industrial development with large manufacturing plants that
include highly visible industrial features such as storage tanks, cooling towers, boiler stacks and
distillation columns.
Within this context, the GTP and associated off-site infrastructure will have a low level of visibility across
all elements of the BGC Project, during both construction and operation.
ES.10.10 Flora and Fauna
The project infrastructure is on developed areas with little native vegetation. Only the heavily disturbed
and contaminated Southlands site contains potential fauna habitats. Wells and an aboveground pipeline
will be located on Southlands. The site may become less boggy due to groundwater interception. The
threatened green and golden bell frog has been recorded on this site in the past, but no permanent
population is present.
Hydraulic containment will reduce groundwater entering Penrhyn Estuary and the eastern end of
Foreshore Beach. In addition, the existing dry weather flows in Floodvale and Springvale Drains, which
discharge into Penrhyn Estuary, are likely to stop. Little is known of the effects of interception of
groundwater on marine communities; however, it is predicted to lead to changes in the species of benthic
invertebrates that occur in the intertidal and subtidal areas close to shore. The single, sparse intertidal
seagrass bed may be at risk due to drying at low tide.
Penrhyn Estuary is the only feeding and roosting area for threatened and migratory shorebirds remaining
in northern Botany Bay. While the species of invertebrate prey are expected to change, the overall
abundance of invertebrates, and therefore potential food, is expected to be maintained. Shorebirds are
expected to adapt to the change in invertebrate prey species, as they are known to readily switch prey
due to their migratory habit.
Removal of groundwater may create conditions more favourable to saltmarsh than mangrove habitat.
Species composition of the existing saltmarsh is predicted to shift towards the more salt-tolerant species
such as Sarcornia, which provides a preferred roosting habitat for shorebirds. Monitoring will be
undertaken to assess impacts and the need for management.
ES.10.11 Heritage
The Project Area has been significantly previously disturbed, with no current or past evidence of any
Aboriginal relics or Aboriginal places. No known non-Indigenous heritage items will be affected.
ES.10.12 Air Quality
There is a significant buffer distance between the GTP site and nearby residential areas. This factor,
combined with dust control by limited water spraying during construction, will mean that dust emissions
from construction will not be expected to result in off-site nuisance impacts.
Botany Groundwater Cleanup Project – Environmental Impact Statement ES-17
Executive Summary
The GTP will be designed to meet strict air quality emission limits matching the best performance from
around the world. In particular, the dioxin emission limits will equal the world’s strictest values.
To assess the impact of the GTP operation on ambient air quality, a detailed atmospheric dispersion
modelling study was undertaken. This indicated that, even if the GTP was operating at the maximum
allowable emission limits (worst case), the GTP would not be expected to have a significant impact on air
quality in the surrounding area. The maximum ground level concentration of oxides of nitrogen (NOx),
sulphur dioxide (SO2), carbon monoxide (CO), particulates, chlorine (Cl2), hydrogen chloride (HCl) and
organics (including ethylene dichloride (EDC), vinyl chloride (VC) and benzene) are below the accepted
level for no impact.
Two abnormal (worst case) operating scenarios were considered, which involve the simultaneous failure
of numerous measurements, controls and trips This is estimated to occur once in 50,000 years. For both
these scenarios, there are no exceedances leading to health concerns.
The GTP will be continuously monitored for a range of process parameters to ensure optimum
performance, including air stripper flows and temperatures and thermal oxidiser temperature, quench and
scrubbing performance. Air emissions will be continuously monitored for key measurements including HCl
and EDC. Periodic laboratory analysis will validate the performance. The human health impacts of air
emissions from the GTP are assessed in the human health risk assessment chapter (Chapter 24).
ES.10.13 Preliminary Hazard Analysis
The risk associated with the GTP has been assessed and compared against the DIPNR risk criteria
through the process of a Preliminary Hazard Analysis (PHA). This analysis shows that the risk complies
with DIPNR guidelines for tolerable fatality, injury, irritation and societal risk. The impact on the
cumulative risk in the Botany/Randwick Industrial Area from releases is also acceptable. These
conclusions apply to risks both on-site (neighbouring industrial facilities) and off-site (residential areas
and other sensitive receivers).
The primary reasons for the low risk levels are the low inventory of hazardous material, low pressures
and concentrations, and the distance to nearby facilities and residences.
The risk associated with the wells and pipelines is negligible because the materials are non-hazardous.
The system is designed to minimise the chance of leaks.
The PHA will be reviewed throughout the project design stage via the HAZOP methodology and updated
in the Final Hazard Analysis.
ES.10.14 Human Health Risk Assessment
Risks to human health associated with the construction and operation of the GTP have been evaluated
using a systematic, standardised approach as outlined in guidance provided by enHealth (2002). This
includes the identification of key issues, evaluation and quantification of exposure, evaluation and
quantification of hazards or chemical toxicity, and the characterisation of risk.
The calculation of risks was based on highly conservative assumptions developed in consultation with
DEC and NSW Health.
ES-18 Botany Groundwater Cleanup Project – Environmental Impact Statement
Executive Summary
The prescribed human health risk assessment is very detailed, providing a systematic review of many
aspects of the BGC Project, the surrounding areas and key aspects associated with chemicals that
require evaluation. The health risk assessment provided an evaluation of incremental risk to human
health associated with the BGC Project, including the long-term impact of trace levels of dioxins emitted
from the GTP. While the study shows the impact of this project on community health, it cannot effectively
review the wider community health status, since this is dependent on many individual factors, including
age, family history (genetic make-up) and lifestyle choices such as sports, diet and consumption of drugs
(particularly tobacco and alcohol).
The exposure routes considered a range of scenarios, such as residents living near the BIP, school
children, workers on- and off-site, and users of the nearby athletics field. Emissions from the BGP Project
were conservatively evaluated under worst case (abnormal) operating conditions.
The assessment indicates that incremental risk to the health of residents, recreational users of areas
surrounding the BIP, and workers from the operation of the GTP is negligible for both short- and long-
term exposure to all emissions.
Operational conditions (assessed for normal and worst case scenario releases) have been based on
estimated emissions from the GTP. These emissions are expected to be conservative, and once the GTP
is operational, should be monitored and re-evaluated against the assumptions used in the health risk
assessment.
ES.10.15 Socio-Economics
The construction phase of the BGC Project is expected to have short-term direct positive impacts on the
local economy, through the injection of capital investment of $86 million and the creation of 53 full-time
equivalent jobs (with a peak of 115 jobs for two months) over the construction period. A team of 10 skilled
process operators will be employed on the GTP. There is also an associated increase in potential
household spending and demand for goods and services in the local area. Construction activities will also
generate indirect jobs, which in turn have induced effects that will filter through the economy.
The BGC Project will have the significant positive benefit of avoiding the discharge of the contaminant
plumes into Penrhyn Estuary, in turn avoiding the significant potential impacts on the commercial,
recreational and ecological activities within the area. As an additional benefit, the quality of the treated
groundwater will be such that it can be reused by BIP and nearby users, thereby reducing the demand on
the Sydney’s water supply, a particular benefit in the current drought conditions.
ES.10.16 Noise
A noise study has been carried out by an independent acoustic noise consultant to ensure that the BGC
Project will comply with statutory and BIP noise requirements. The GTP will be located within the BIP and
will comply with the stringent noise emission criteria set down in the Environmental Protection Licence
issued by the EPA to Orica. The GTP will be subject to further noise evaluation during the detailed design
stages, and noise testing will be undertaken during commissioning to verify that all noise criteria are met.
The statutory requirements for occupational noise exposure level will also be complied with. The GTP will
be designed in accordance with BIP engineering requirements for cumulative effects of additional plant on
Botany Groundwater Cleanup Project – Environmental Impact Statement ES-19
Executive Summary
the BIP. While no specific operational noise criteria apply to the associated off-site infrastructure, such as
extraction wells and pipelines, these will also to be covered by the GTP noise design goals.
Construction activities for the BGC Project are not anticipated to result in any significant noise impact at
sensitive receptors. Similarly, noise impacts are not anticipated as a result of traffic arising from either the
construction or the operation of the BGC Project, given the relatively small amount of additional traffic that
will be generated when compared with the existing traffic levels on Denison Street and the surrounding
road network.
ES.10.17 Cumulative Impacts
The potential cumulative impacts of the BGC Project with existing and proposed major developments in
the Botany area have been considered. No significant cumulative impacts have been identified.
Therefore, the potential cumulative effect of the BGC Project with other existing or proposed
developments in the area is considered to be low.
ES.11 Environmental Management
An Environmental Management Plan (EMP) will be developed and implemented for the BGC Project, in
accordance with the management and monitoring measures set out in this EIS, statutory requirements
and the conditions of approval for the BGC Project. The EMP will incorporate the mitigation measures
discussed in the EIS.
Environmental monitoring will be a fundamental component of both the construction and operation EMPs
for the BGC Project. Orica has committed to undertake regular environmental performance reporting, and
will investigate the establishment of an independent monitoring process with community representation to
provide stakeholders with assurance of the performance of the project.
Implementation of the environmental management and monitoring requirements identified in the EIS will
ensure that the impact on the physical, social and economic environments of the BGC Project will be
acceptable.
ES.12 Ecologically Sustainable Development
The BGC Project is focused on the principles of ESD, because it is designed to clean up the legacy
groundwater contamination for the benefit of current and future generations in the local communities.
ES.13 Project Justification
The BGC Project is designed to meet the requirements of the NCUA, by achieving hydraulic containment
of the plumes to prevent discharge from the groundwater into Penrhyn Estuary and Botany Bay, and to
remove and destroy the contaminants safely and effectively.
Hydraulic containment is a proven technique for groundwater cleanup. The selected treatment
technologies to be used in the GTP are based on best practice and proven equipment to achieve effective
ES-20 Botany Groundwater Cleanup Project – Environmental Impact Statement
Executive Summary
destruction of the contaminants, and to control and minimise emissions to air, including dioxins and
furans.
The treatment technologies have also been selected to ensure that the groundwater treatment achieves a
water quality that meets a combination of relevant standards for reuse as process water, thereby reducing
demand on Sydney’s townswater supply.
The BGC Project also incorporates an extensive monitoring program, to continually assess the
effectiveness of the containment and treatment throughout the project lifetime.
While the BGC Project will have significant environmental benefits, it is recognised that it will also have
some unavoidable environmental impacts. These are relatively minor, and have to be balanced against
the impacts that would occur if the containment and treatment were not implemented and uncontrolled
groundwater contaminant discharge occurred. A range of mitigation measures has been identified to
minimise the impact on the environment. The environmental performance of the BGC Project will be
monitored to ensure that the adopted environmental standards are met and maintained.
Based on the assessment in this EIS, undertaking the BGC Project in the manner proposed is justifiable,
taking into consideration potential environmental, health, economic and social impacts and the principles
of ESD.
Botany Groundwater Cleanup Project – Environmental Impact Statement ES-21