Study Items for the PMP EXAM

download Study Items for the PMP EXAM

of 66

Transcript of Study Items for the PMP EXAM

  • 8/8/2019 Study Items for the PMP EXAM

    1/66

    Study Items for the PMP EXAM

    This is a complete and very exhaustive list of major concepts, definitions and tems to remember when

    you will try to pass the PMP Exam. Despite it is in English it can be used by everybody just because all

    the items above you should have been seen during PM courses or training. You must:1. Read PMBOK once. Suggest reading 2 to 3 times.2. Memorized the mapping of project management processes to the project

    management process groups and the knowledge areas.

    3. Go through the terms mentioned in "Standards Glossary"

    4. Suggest reading books of Rita Mulcahy, Kim Helman, Harold Kerzner two to

    three times

    5. Flashcard from Rita Mulcahy, Clickme from Kim Heldman.

    6. Sample Q&A from Kerzner (several times), Kim & Rita. PMBOK Q&A Book

    supplied by PMI or whatever source for practice Q&A.

    7. Memorize the formulas for cost, time etc.

    8. Discipline yourself to a schedule and stick with it.

    9. Strong suggestion: take a course for preparing for the Exam.

    PMP websites:www.pmHub.net

    www.pmstudy.com

    www.readysetpass.com

    http://sydney.pmichapters-australia.org.au/

    Following PMP materials on the web also helped.

    1. free flashcard website for PMP with 1538 questions/flashcards.

    http://www.flashcardexchange.com/flashcards/view/287102 go to "Study".

    2. In addition there are lot of materials , questions in the other flashcards

    http://www.flashcardexchange.com/tag/pmp

    3. 75 free questions:

    http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm4.PMP Exam Tutorials, 200 questions:

    http://www.tutorialspoint.com/pmp-exams/pmp_mock_exams.htm

    5. Free 15 questions:

    http://www.testprepreview.com/modules/pmp.htm

    6. 20 practice questions:

    http://certification.about.com/od/projectmanagement/a/pmp_test_whiz.htm

    7. Free PMP Certification Practice Questions:

    http://www.certgear.com/products/preview/pmp_certification/index.html

    List of sites on web that provide some free PMP exam questions (as demos)

    Some of these sites point to other sites with free sample demos

    http://www.educationlist.in/pmp.html

    http://www.carlstumpf.com/PMP%20Study%20Group/pm%20study%20group%20i

    ndex.htm

    www.certgear.com/products/info/pmp.htm

    http://www.4pmti.com/

    http://www.pmpexamtips.com/pmp-exam.html

  • 8/8/2019 Study Items for the PMP EXAM

    2/66

    www.MeasureUp.com

    http://www.freedownloadscenter.com/Search/practice_exam_W1.html

    According to the Project Management Body of Knowledge (PMBOK), a project is a temporary endeavor

    undertaken to create a unique product or service.

    Triple constraint- project scope, time and cost

    Ap o rtf o lio is a collection of projects or programs and other work that are grouped together to facilitate

    effective management of that work to meet strategic business objectives. The projects or programs in the

    portfolio may not necessarily be interdependent or directly relatedProject Portfolio Management is a management process to select theprojects thatshould be invested in. Specifically, it is the selection processbased on the need,profitability, and affordability of the proposed projects.

    A project management office (PMO) is an organizational unit to centralize and coordinate the

    management of projects under its domain. A PMO can also be referred to as a "program management

    office," "project office," or "program office." A PMO oversees the management of projects, programs, or a

    combination of bothProject management is a set of tools and techniques that are used toorganize the work of the project to help bring about a successful project.The contract between the organization and the vendor super cedes all otherworkrelated documentsCustomers, internal or external, are the most importants take ho ld er s in aprojectScope verification must take place at the end of each phase

    Money already spent on a project is called sunk cost and should not be taken into consideration when

    determining if a project should continue. Instead, the cost of the work to complete is one of the elements

    that should be taken into consideration when considering to kill a projectPhase end reviews are also called phase exits, phase gates, or kill points.The project life cycle goes through a series of phases to create the productProject managersman ag e things, but l ead people. What's the difference?Management is the process of getting the results that are expected by

    project stakeholders.Lead ersh ip is the ability to motivate and inspireindividuals to work towards those expected results.Project

    Projects don't last forever. They are temporary and unique

    Projects pass through logical phases to reach their completion

    Purpose of Project is to attain its objective and then terminate

  • 8/8/2019 Study Items for the PMP EXAM

    3/66

    Operations

    Operations, however, do go on and on. They are ongoing andrepetitive

    Operations may be influenced, or even created, by the outcome of aproject

    Objective of an ongoing operation is to sustain businessOrganization Structure

    Functional

    Matrix

    Weak

    Balanced

    StrongProjectizedOrganization Structure And Project Characteristics

    oFunctional

    PM's Authority [Little or none]

    Resource Availability [Little or none]

    Who controls Project Budget [Functional Manager]

    PM's Role [Part - Time]

    PM Admin Staff [Part - Time]oWeak Matrix

    PM's Authority [Limited]

    Resource Availability [Limited]

    Who controls Project Budget [Functional Manager]

    PM's Role [Part - Time]

    PM Admin Staff [Part - Time]oBalanced Matrix

    PM's Authority [Low to moderate]

  • 8/8/2019 Study Items for the PMP EXAM

    4/66

    Resource Availability [Low to moderate]

    Who controls Project Budget [Mixed]

    PM's Role [Full - Time]

    PM Admin Staff [Part - Time]oStrong Matrix

    PM's Authority [Moderate to high]

    Resource Availability [Moderate to high]

    Who controls Project Budget [Project Manager]

    PM's Role [Full - Time]

    PM Admin Staff [Full - Time]o

    Projectized

    PM's Authority [High to almost total]

    Resource Availability [High to almost total]

    Who controls Project Budget [Project Manager]

    PM's Role [Full - Time]

    PM Admin Staff [Full - Time]TheW B S is a decomposition of all the deliverables the project will create

    Inspections may also be known as:

    a. Reviews

    b. Product reviews

    c. Audits

    d. Walk-throughsGraphical evaluation and review technique (GERT) models allow for loopsand conditional branchingCrashing adds more resources to activities to decrease their duration, whichtypically adds cost

    Project calendarThis calendar shows when work is allowed on the project.

    For example, a project may require the project team to work nights and weekends so as not to disturb the

    ongoing operations of the organization during working hours. In addition, the project calendar accounts for

    holidays, working hours, and work shifts that the project will coverResource calendarThe resource calendar controls when resources, such as

  • 8/8/2019 Study Items for the PMP EXAM

    5/66

    project team members, consultants, and SMEs are available to work on the project. It takes into account

    vacations, other commitments within the organization, or restrictions on contracted work, overtime issues,

    and so on

    Program Evaluation and Review Technique (PERT) uses a weighted average formula to predict the

    length of activities and the project. Specifically, PERT uses a 'pessimistic,' 'optimistic,' and 'most likely'estimate to predict when the project will be completedThe critical path is the longest path to completion in the network diagram.Activities on the critical pathha v e no float or slack.Free float is the amount of time an activity can be delayed without affectingthe next activity's scheduled start date.

    Total float is the amount of time an activity can be delayed without affectingthe project end date.

    Heuristic is simply a rule of thumbCrashing involves adding resources, which typically increases cost.Fast tracking adds risk as tasks are allowed to overlapEach resource in the project must be accounted for and assigned to a costcategory.Categories include the following:

    a. Labor costs

    b. Material costs

    c. Travel costs

    d. Suppliese. Hardware costs

    f. Software costs

    g. Special categories (inflation, cost reserve, and so on)

    There are three generally accepted categories ofestimating accuracy: a. Rough order of magnitude This

    estimate is rough and is used during the Initiating processes and in top-down estimates. The range of

    variance for theestimatecanbe

    25percentto+75

    percent. b.

    Budget estimate This estimate is also somewhat broad and is used early in the planning processes and

    also in top-down estimates. The range of variance for the estimate can be 10 percent to +25 percent. c.

    Definitive estimates This estimate type is one of the most accurate. It is used late in the planning

  • 8/8/2019 Study Items for the PMP EXAM

    6/66

    processes and is associated with bottom-up estimating. The range of variance for the estimate can be 5

    percent to +10 percent.The opportunity cost is the amount of the project that was not chosenQuality is the sum of the characteristics of a product that allow it to meet

    the demands or expectations of the projectGrade, according to the PMBOK, is a category or rank given to entities

    having the same functional use but different technical characteristics. For example, there are different

    grades of paint, different grades of metal, and even different grades of travel.

    The design of experiments (DOE) approach relies on statistical what-if scenarios to determine what

    variables within a project will result in the best outcome.Design of experiments is an analytical technique that identifies the elementsor variables that will have the greatest effect on overall project outcomes

    There are five types of powers the project manager yields: (R F C E R )a.Reward

    b.Formal

    c.Coercive (penalty)d.Experte.ReferentAmong the above powers Reward, Formal & Coercive (penalty) come withthe"P os it io n"Expert & Reward are considered the best types of powers and Coercive(penalty) is "Least" for obvious reasons

    Seven reasons for conflict, in order of most common to least common:

    a.Schedules

    b.Priorities

    c.Resources

    d.Technical beliefse.Administrative policies and procedures

    f.Costsg.PersonalitiesFive different approaches to conflict resolution

    a. Problem solving (win - win) [BEST]

    b. Forcing (win - lose)

    c. Compromising (lose - lose)

    d. Smoothing

    e. Withdrawal

    NOTE: Forcing (win - lose) and Problem Solving (win - win) are the ONLY

    two modes that result in a RESOLUTION to the conflict.

  • 8/8/2019 Study Items for the PMP EXAM

    7/66

    The halo effect is the promoting the person to manage projects since he/sheis good at a technologyConfronting (Problem Solving) is the best problem-solving technique since itmeets the problem directlyIn a Weak Matrix structure, functional management will have more authoritythan the project manager

    Withinc omm un ic ating there are five characteristics that affect the message:

    a. Paralingual: pitch, tone, and voice inflections

    b. Feedback: sender confirmation of the message by asking questions, for a

    response, or other confirmation signals

    c. Active listening: receiver confirms message receipt

    d. Effective listening: receiver offers confirmation of the message, such as

    nodding their head, asking questions, or other interactions.

    e. Nonverbal: facial expressions, hand gestures, and body language

    One of the first inputs to risk management is the project charterHistorical information is always an excellent source of information for riskidentificationBrainstorming is likely the most common approach to risk identificationForce majeure is a powerful and unexpected event, such as a hurricane orother disasterContracts are known by many names:

    a. Agreement

    b. Subcontract

    c. Purchase order

    d. Memorandum of understandingAll contracts in the United States are backed by the US court systems

    According to the Guide to the PMBOK, the project chartershould be published by a manager external to

    the project but with sufficient power and authority to carry it off.When a project is performed under contract, the contract can serve as theproject charterCost reimbursable contracts are used when the degree of uncertainty is high

    and when the project requires a large investment prior to completion of theproject

    The scope statement contains an exhaustive list of the project deliverables, their requirements, and

    measurable criteria used to determine project completionThe scope statement is an output to the Scope Definition process and isused to create the WBS

  • 8/8/2019 Study Items for the PMP EXAM

    8/66

    Cause-and-effect diagrams, also called Ishikawa or fishbone diagrams, showthe relationship between the effects of quality problems and their causesThe primary function of the Closing process is to formalize projectcompletion and disseminate this information to the project participants

    According to the Guide to the PMBOK, the project manageris identified and assigned as an output of the

    Initiation process. In practice, project managers are very often assigned at the beginning of this process.

    The work package level is the lowest level in the WBS. Time and cost estimation is easily determined at

    this level as are resource assignments. Quality control measurements can be determined at this level as

    well.The code of accounts is assigned to the elements in the WBSEach element in the WBS is assigned a unique identifier. These arecollectively known as the code of accounts

    The Responsibility Assignment Matrix (RAM) links project roles andresponsibilities with project activitiesTheW B S is the deliverables-oriented hierarchy of project work.

    The staffing management plan details how and when human resources will be added to and taken off the

    project. It is an output of Organizational PlanningAnalogous estimating is not a qualitatively based technique. It is a top-downestimating technique that considers previous similar activities whencalculating estimatesMandatory dependency, also known as hard logic. Mandatory dependenciesare inherent in the nature of the workDiscretionary dependencies, also called preferred logic, preferential logic,and soft logic, are defined by the project management team

    "Best Practice often refers to a specific sequence of work, described in terms of Soft Logic. Sometimes

    "Experience" is also attributes to Soft LogicFinish to start is the most commonly used logical relationship inP DMandmost project management software packages

    There are three major documents and each has a specific purpose:

    a. Project Charter. Formally authorizes the project.b. Project Scope Statement. States what work is to be accomplished and

    what

    deliverables need to be produced.

    c. Project Management Plan. States how the work will be performedPhilip Crosby devised the zero defects theory, meaning do it right the firsttime. Proper Quality Planning leads to less rework and higher productivity

  • 8/8/2019 Study Items for the PMP EXAM

    9/66

    According to Bruce Tuckmann, Forming, Storming, Norming and Performing are the stages of team developmentThe performing stage is similar to Maslows self-actualizationMyers Briggs theory states that Sensing and Intuition personality typesare related to Information preference in other words Hard Data verseswhat might beJuran = Fitness for use, conformance. Quality by design.Joseph M. Juran is noted for his fitness for use premise. Simply put, thismeans the stakeholders and customers expectations are met or exceeded.W. Edwards Deming suggested that as much as 85 percent of the cost ofquality is a management problemShewhart = Plan-Do-Check-Act cycle.

    TQM = Quality must be managed in and must be a continuous processSix Sigma = Six Sigma is a measurement-based strategy; no more than 3.4defects per million.Kaizen = Continuous improvement; improve quality of people first.Continuous improvement = Watch continuously for ways to improve quality.Statement of work (SOW) comprises ofoBusiness Needo

    Product Scope Description andoStrategic Plan

    Conflict should be addressed early and usually in private, using a direct,collaborative approachOrganization, Environmental & external assumptions should be addressed bythe Project CharterWBS Dictionary is a document which describes the details for each

    component in the WBS. It includes a breif description of the of the Scope or Statement of the work ,

    defined deliverables, a list of associated activities, and a list of milestonesProject Manager must consider cultural differences while deciding uponrecongnization and rewards during team development.Technical inability and poor risk management by the contractor is mostly thereason for the project not to meet the customer expectationsCritical Chain Project Management is typically the Management of Buffers

  • 8/8/2019 Study Items for the PMP EXAM

    10/66

    Critical Chain is another schedule network analysis technique that modifiesthe project schedule to account for limited resourcesThe Critical Chain method adds duration buffers that are non-work scheduleactivities to maintain focus on the planned activity durationsCost Of Quality (COQ) are the cost types in modern quality managementoPrevention Costs,oAppraisal costs &oFailure costs

    The key components of the communication modelinc lud e :

    a. Encode.

    b. Message.

    c. Medium.

    d. Noise.

    e. Decode.Common formats forperformance reportsinc lu d eoBar charts,oS curves,oHistograms, andoTables.Face-to-face meetings are the most effective means for communicatinga ndresolving issues with stakeholders.Order of Magnitude estimates are also knows as conceptual, ballpark orpreliminary estimatesTight Matrix is putting all project personnel together. Also referred ascollocatedStrategies for Negative Risks or threats (AvoidTransferMitigate)Strategies for Postive Risks or Opportunities (ShareExploitEnhance)

    Common Strategy for both threats and opportunities is AcceptanceThere are 3 stages ofreaction to stress(A la r m, Resistance & Exhaustion)Some of thet ra it s /q ua l it ies exhibited by effective leaders areoFlexibility,oAmbition,

  • 8/8/2019 Study Items for the PMP EXAM

    11/66

    oIntelligence,oDecisiveness,oCreativity,oPersistence andoEnergyDetailed Tasks are detailed in Project Schedule, which is part of ProjectPlan and note its NOT WBS. WBS is a deliverable oriented documentAn abnormal trend is formed when seven or more consecutive data pointsreflect a steadily increasing or decreasing pattern over timeScope Verification is concerned with the acceptance of deliverables

    Quality control is concerned with making sure the deliverables meet qualityrequirements. Quality Control is done first; both are Monitoring andControlling processes.Quality Assurance (Executing) is focused on process: process analysis,quality audits, etc.Quality Control (Monitoring and Controlling) is focused on sampling resultsto see if they meet quality standardsCode of Accounts identifies WBS items; Chart of Accounts monitors projectcosts by category

    In decision tree, a circle is a chanceIn Precedence Diagramming Method (PDM) or Activity on Node (AON)network diagrams, nodes are activities and arrows are dependenciesIn Arrow Diagramming Method (ADM) or Activity on Arrow (AOA) networkdiagrams, arrows are activities and nodes are dependenciesDummies are only used onAD MADM tasks can only have FS relationshipsPDM uses one time estimate to determine duration, while ADM can use morethan one time estimate.Scope Verification is done during Project monitoring and controlling BUTProduct verification is done during the Project Closing

    Audits:

    o Quality Audit in Perform QA,

    o Risk Audit in Risk Monitoring and Control,

  • 8/8/2019 Study Items for the PMP EXAM

    12/66

    o Inspections and Audits in Contract Administration,

    o Procurement Audits in Close Contracts

    The outputs of process groupsar e :

    o initiating: charter and preliminary scope statement;

    o planning: project management plan;o executing: work results;

    o monitoring: corrective actions;

    o closing: project product.

    Reporting formats:

    o Forecast Report (what is expected to happen on a project),

    o Progress Report (what happened since the last report),

    o Status Report (state of the project at the current time),

    o Earned Value Report (focuses on Earned Value Management),

    o Variance Report (what happened vs. what should have happened).

    Performance Reporting is a Controlling process. It creates PerformanceReports, which are comparisons of performance to the performancebaselines. These are typically done in tabular or graphical format.Information Distribution is an Executing process. It creates OrganizationalProcess Assets such as project presentations, stakeholder notifications andstatus reports.Develop Project Team is an Executing Process. It creates a TeamPerformance Assessment, and helps you determine what additional trainingwould be beneficial.Manage Project Team is a Controlling Process. It creates input toperformance appraisals as well as recommended changes, corrective actionsand preventative actions.Scope Baselinei nc l ud esoProject Scope Statement,oWBS, &oWBS DictionaryA large portion of the PMs time while the work is being done is spentmeasuring and implementing corrective actions

    Project Close Process includes creation of two procedureso Administrative closure procedure and

    o Contract closure procedure

    The difference between the two is focus, formality and frequency.

    Administrative closure focuses on closing the project or project phase

  • 8/8/2019 Study Items for the PMP EXAM

    13/66

    whereas Contract closure focuses on closing a contract that is part of the

    projectContingency Reserve (Known Unknowns) is for the risks remaining after the

    Risk Response Planning Management Reserve (Unknown Unknows is any extra amount reserved that

    cover unforeseen risks. Cost Baseline will include the Contingency Reserve. Cost Budget will include

    the Management ReserveQuality is defined as the degree to which the project fulfills requirementQuality MUST BE PLANNED IN AND NOT INSPECTED INThe Project Managerultimately has the responsibility for the Product of theProject andSenior Management is responsible for the Quality of entire OrganizationCost of Nonconformance is greater than the cost of conformance

    Most projects will fit one of the six needs and demands

    o Market demand

    o Business need

    o Customer request

    o Technological advance

    o Legal requirement

    o Social need

    The project charter (which is an output of the Develop the Project Charter process) is the written

    acknowledgment that the project exists. The project charter names the project manager and gives that

    person the authority to assign organizational resources to the projectNet present value (NPV) assumes reinvestment is made at the cost of capitalIRR assumes reinvestment at the IRR rate and is the discount rate whenNPV is equal to zeroPayback period does not consider the time value of money and is thereforethe least precise of all the cash flow analysis techniquesPreliminary project scope statement describes the objectives of the projectand the high level requirements needed to satisfy stakeholder expectationsTheP MI S in the Develop Project Management Plan process includes a

    subsystem called the configuration management systemChange control system, which is a subsystem of the configurationmanagement system

    Stakeholder analysis is a tool and technique of Scope Definition used to determine and document the

    needs, wants, and expectations of stakeholders and prioritize and quantify those needs into project

    requirements

  • 8/8/2019 Study Items for the PMP EXAM

    14/66

    The purpose of the project scope statement is to document the project objectives, deliverables, and

    requirements so that they can be used to direct the project teams work and as a basis for future project

    decisions

    The scope statement further elaborates the project objectives, deliverables, requirements, and

    constraints and assumptions defined in the preliminary scope statement. It serves as a basis for future

    project decisionsAlternatives identification is a tool and technique of the Scope Definitionprocess that includes brainstorming and lateral thinking techniquesPoor scope definition might lead to cost increases, rework, schedule delays,and poor morale

    According to the PMBOK Guide, functionality and specific conditions that must be met in order to satisfy

    the project, contract, standard, or specification describe the criteria for requirements, not objectives

    Product analysis (TT Scope Definition) includes techniques such as valueengineering, value analysis, systems analysis, systems engineering, productbreakdown, and functional analysis

    The product scope description can be used as an input to the Scope Definition process when the project

    charter and/or preliminary project scope statement are missingThe lowest level of any WBS is called the work package level

    For the exam, remember that the key to DOE is that it equips you with a statistical framework that allows

    you to change the variables that have the greatest effect on overall project outcomes at once instead of

    changing one variable at a time.Quality checklists are an output of the Quality Planning process, andchecklist analysis is a tool and technique of the Risk Identification processCost-benefit analysis considers trade-offs in the Quality Planning processBenchmarking compares previous similar activities to the current projectactivities to provide a standard to measure performance against.Failure costs; is also known as the cost of poor quality. Failure costs includeboth internal and external costs.

    Internal failure costs are costs associated with not meeting the customers expectations while you still hadcontrol over the product. This results in rework, scrapping, and downtime.

    The process improvement plan is a subsidiary plan of the project management plan and targets

    inefficiencies in a process or activity. The quality baseline is used to document the quality objectives of

    the project and is used as a basis for future Quality processes

  • 8/8/2019 Study Items for the PMP EXAM

    15/66

    The WBS dictionary should be documented with the code of account identifier, an SOW, the responsible

    organization, and a milestone schedule for the WBS componentsDesign of experiments is a tool and technique of the Quality Planningprocess that provides statistical analysis for changing key product or processelements all at once (not one at a time) to optimize the process

    According to the PMBOK Guide, the risk management plan should include

    the following elements:

    o Methodology

    o Roles and responsibilities

    o Budgeting

    o Timing

    o Risk categories

    o Definitions of risk probability and impact

    o Probability and impact matrix

    o Revised stakeholder tolerances

    o Reporting formats

    o Tracking

    The output of the Risk Identification process is the risk register. The risk

    register contains the following elements:

    o List of identified risks

    o List of potential responses

    o Root causes of risks

    o Updated risk categoriesRisk urgency assessment is a tool and technique of Qualitative Risk Analysis

    processQualitative Risk Analysis is a fast and easy method of determiningprobability and impactThe risk management plan details how risk management processes will beimplemented, monitored, and controlled throughout the life of the project.

    The risk management plan does not include responses to risks or triggers. Responses to risks are

    documented in the risk register as part of the Risk Response Planning process

    The information-gathering techniques in the Risk Identification process are

    o brainstorming,

    o the Delphi technique,

    o interviewing,

    o root cause identification, and

    o SWOT analysis.Quantitative Risk Analysis analyzes the probability of risks and theirconsequences using a numerical rating

  • 8/8/2019 Study Items for the PMP EXAM

    16/66

    Monte Carlo analysis is a simulation technique & not a Modeling technique

    When the question describes sensitivity analysis, which is a tool and technique of the Quantitative Risk

    Analysis process. Tornado diagrams are often used to display sensitivity analysis data

    The simplest form of Risk Analysis is Sensitivity Analysis

    Following options are diagramming techniques of the Risk Identification

    process

    o Ishikawa diagram

    o Process flowchart

    o Influence diagramPassive acceptance is when the team has decided to take no action andmake no plans for the risk. This is a strategy that can be used for eitherpositive or negative risks.

    The PMBOK Guide divides contracts into three categories:o Fixed price or lump sum (biggest risk is borne by the seller & good when

    original scope is well defined)

    o Cost reimbursable (biggest risk is borne by the buyer)

    o Time and materials (T&M)

    Understand the difference between bid and/or quotation and proposal for the exam. Bids or quotations

    are used when price is the only deciding factor among bidders. Proposals are used when there are

    considerations other than price

    A contract statement of work (SOW) contains the details of the procurement

    item in clear, concise terms. It includes the following elements:o The project objectives

    o A description of the work of the project and any post project operational

    support needed

    o Concise specifications of the product or services required

    o The project schedule, time period of services, and work location

    According to the PMBOK Guide, using templates and checklists is one way to ensure that you dont miss

    any key responsibilities when planning the project and will help reduce the amount of time spent on

    project planning

    According to the PMBOK Guide, theRAM (Responsibility Assignment Matrix) relates the OBS to the WBSto assure that every component of the work of the project is assigned to an individual.

    The letters in the acronymRA CI (sample portion of a type of RAM) are the

    designations are

    o R = Responsible for performing the work

    o A = Accountable, the one who is responsible for producing the deliverable

    or work package and approves or signs off on the work

  • 8/8/2019 Study Items for the PMP EXAM

    17/66

    o C = Consult, someone who has input to the work or decisions

    o I = Inform, someone who must be informed of the decisions or resultsThe RAM and RACI charts are tools and techniques of Human ResourcePlanning process

    Standard forms are a tool and technique of the Plan Contracting process.Standard forms can be nondisclosure agreements, standardized contracts,and so on.Plan Purchases and Acquisitions can directly influence the project schedule,and the project schedule can directly influence this processResource availability is an output of the Acquire Project Team and SelectSeller processes

    For the exam, remember that resource availability isnt determined until the Executing stage and becomes

    an input to the Activity Resource Estimating process

    Remember that you cannot perform Schedule Development until you have completed all the following

    processes of project Planning: Scope Planning, Scope Definition, Create WBS, Risk Identification, Risk

    Response Planning, Plan Purchases and Acquisitions, Activity Resource Estimating, Activity Definition,

    Activity Sequencing, and Activity Duration EstimatingSchedule Development has 10 tools and techniques:

    o Schedule network analysis (produces the project schedule)

    o Critical path method ()

    o Schedule compression

    o What-if scenario analysis

    o Resource levelingo Critical chain method

    o Project management software

    o Applying calendars

    o Adjusting leads and lags

    o Schedule model

    The higher the standard deviation is for an activity, the higher the risk. Since standard deviation measures

    the difference between the pessimistic and the optimistic times, a greater spread between the two, which

    results in a higher number, indicates a greater risk. Conversely, a low standard deviation means less risk

    Monte Carlo is a simulation technique that shows the probability of all thepossible project completion datesMonte Carlo analysis can be used in the Schedule Development process todetermine multiple, probable project durationsResource leveling can cause the original critical path to change.CPM manages the total float of schedule networks paths, whereas criticalchain manages buffer activity durations and resources

  • 8/8/2019 Study Items for the PMP EXAM

    18/66

    Cost aggregation (TT of Cost Budgeting) is the process of tallying theschedule activity cost estimates at the work package level and then totalingthe work package levels to higher level WBS component levelsFunding limit reconciliation (TT of Cost Budgeting) involves reconciling theamount of funds spent with the amount of funds budgeted for the projectCost baselines are displayed as an S curve.The primary output of Cost Estimating is activity cost estimatesParametric estimating multiplies a known elementsuch as the quantity ofmaterials neededby the time it takes to install or complete one unit ofmaterials. The result is a total estimate for the activity

    The project schedule determines the start and ending dates of activities, determines float times, generally

    shows resource assignments, and details the activity sequences and durations.

    Motivation can be extrinsic or intrinsic.o Extrinsic motivators are material rewards and might include bonuses, the

    use of a company car, stock options, gift certificates, training opportunities,

    extra time off, and so on

    o Intrinsic motivators are specific to the individual. Some people are just

    naturally driven to achieveits part of their nature

    The introduction of a new team memberwill start the formation anddevelopment of the team all over again with the forming stageTeams in the norming stage of Develop Project Team exhibit affection andfamiliarity with one another and make joint decisionsRequest Seller Responses obtains bids and proposals from vendors.Select Sellers is the receipt of bids and proposals and the selection of avendor Independent estimates (TT of Select Sellers), also called should costestimates, are a way to check proposed pricingFait accompli is a tactic used during contract negotiations where one partyconvinces the other that the particular issue is no longer relevant or cannotbe changed

    The process analysis technique (TT of Perform Quality Assurance process) includes root cause analysis

    to analyze a problem and solution and to create preventive actions

    You are preparing project performance appraisals and have decided youd like each team member to get

    feedback regarding their performance from several sources, including peers, superiors, and subordinates.

    This is called 360-degree feedback and is part of the project performance appraisals tool and technique

    of the Manage Project Team process.

  • 8/8/2019 Study Items for the PMP EXAM

    19/66

    Understand for the exam that configuration managementinvo l ves

    o identifying the physical characteristics of the product, service, or result of

    the project (or its individual components); o controlling changes to those

    characteristics; and o Documenting changes to verify that requirements are

    met.

    o It also includes the change management system ando documents the process for requesting, tracking, and determining whether

    change requests should be approved or denied.

    Activities associated with configuration change management in the

    Integrated Change Control process

    o Configuration identification

    o Configuration status accounting and

    o Configuration verification and auditingIntegrated Change Control, Schedule Control, and Cost Control are all

    concerned with three issues:o influencing the things that cause change,

    o determining that change is needed or has happened,

    o and managing the changeChange control systems are documented procedures that describe

    o How to submit change requests.

    o They track the status of the change requests,

    o document the management impacts of change,

    o track the change approval status, and

    o define the level of authority needed to approve changes.

    Change control systems do not approve or deny the changesthats theresponsibility of the configuration control board (CCB)The configuration control board (CCB) has the authority to approve or denychange requests. Their authority is defined and outlined by the organization

    Recommended corrective action is an output of several of the change control processes, including

    Scope Change Control, Schedule Control, Cost Control, Risk Monitoring and Control, and Perform Quality

    Control.Approved corrective action is an output of the Integrated Change Controlprocess. Remember that Integrated Change Control is where all change

    requests are processed and either approved or denied.Also note that corrective action is an output of the Monitoring andControlling processes and an input to the Executing processes

    Cost variances (both positive and negative) are calculated using aperformance measurement analysis tool (specifically earned valuetechniques)

  • 8/8/2019 Study Items for the PMP EXAM

    20/66

    EVT (earned value techniques) compares what youve received or producedto what youve spent.Workarounds are unplanned responses. Workarounds deal with negative riskevents as they occur.

    Schedule variances will sometimesbut not alwaysimpact the schedule. Changes to noncritical pathtasks will not likely impact the schedule, but changes to critical path tasks will always impact the scheduleBudget updates might require cost rebaselining

    You can remember the difference between Scope Verification and Perform

    Quality Control this way:

    o Scope Verification = accepting work results

    o Perform Quality Control = checking for correct work results (assuring that

    the quality requirements are met)

    Projects come to an end for several reasons:

    o Theyre completed successfully.

    o Theyre canceled or killed prior to completion.

    o They evolve into ongoing operations and no longer exist as projects.

    Four formal types of project endings exist that you might need to know for

    the exam:

    o Addition

    o Starvation

    o Integration

    o Extinction

    For the exam, remember that product verification performed during the Closing processes determines

    whether all of the work of the project was completed correctly according to the contract terms and

    satisfactorily according to stakeholder expectations, whereas product documentation is verified and

    accepted during the Scope Verification process. One more note: when projects end prematurely, the

    Scope Verification process is where the level of detail concerning the amount of work completed gets

    documented.Contract documentation is an input to both the Close Project and ContractClosure processes

    Note PMI defines Scope Statement as the basis for making future project decisions and for confirming

    or developing common understanding of project scope among project stakeholders.Scope Verificationo Verified work resultsPerform Quality Controlo Assured quality requirements were metClose Project

  • 8/8/2019 Study Items for the PMP EXAM

    21/66

    o Product verification (work was correct and satisfactory)

    o Collecting project documents

    o Disseminating final acceptance notice

    o Documenting lessons learned

    o Archiving project records

    Contract Closureo Product verification (work was correct and satisfactory)o Formal acceptance and closureWBS element changes are scope changes. Schedule revisions are oftenrequired as a result of scope changes.Close Project and Contract Closure are the processes in the Closing processgroup and are performed in that order

    The work performance information is reviewed to determine the status of project activities and make

    certain the project goals and objectives are met. This is an input to the Close Project process

    According to the PMBOK Guide, the procurement audit examines the procurement process from

    Procurement Planning through Contract AdministrationIntegrity means adhering to an ethical standardHammocks are summary-level activities or aggregate activities shown as asummary activity on a project schedule network diagram.Contract Negotiation has 5 Sequential steps (Note Agreement is AFTER

    Closure)

    o Protocol

    o Probing

    o Scratch Bargaining

    o Closure and

    o AgreementThe Primary Objective of establishing a Quality Assurance Process is ForQuality Improvement

    Quality Function Deployment Process identifies what the customers needs are (Spoken/unspoken

    words) and translates those needs into technical requirements. Appropriate for each stage of the product

    development life cycle

    Decision Tree is a diagram that describes a decision under consideration andthe implications of choosing one of the alternatives

    The Project Charterprovides the

    o high level requirements,

    o constraints,

    o assumptions,

  • 8/8/2019 Study Items for the PMP EXAM

    22/66

    o stakeholders and

    o the measures of success.Based on this information, or the lack of it, the Charter is an excellentsource to start to identify the Project Risks

    9 bilitiesMaintainability: The ability of a unit to be restored within a specified time to

    its performance capability under the environmental operating conditions

    within a specified, average period of time

    Usability: is the ability of a product to perform its intended function for the

    specified user under the prescribed conditions

    Reliability: is the degree to which a unit of equipment performs its intended

    function under specific conditions for specified period of time

    Availability: is the probability of the product being capable of performing a

    required function when called upon

    Activity Resource Estimating involves determining what physical resources(People, Equipment, etc) and what quantities should be used and when theywould be needed to perform project activitiesPhysical limitations are an attribute of Mandatory DependenciesA Project Phase is Marked by the completion of one or more deliverablesA Product Description should define the relationship between the productthat is being created and the business needContingency Plans can be best described as Planned responses to RiskEvents

    Staff assignments and resource availability are the outputs of Acquire theProject Team ProcessComplex and large projects would be more effectively managed in Strongand Projectized StructureIf Changes are well defined, its Fixed Price Contract but if they are not thenits T & M

    Contract Management Plan is an OUTPUT to Select Seller ProcessPunitive Damages are the damages intended to punish the wrong doerUtility Theory considers the pains or tolerance level a stakeholder has torisk

    There are three key components to a Risk

    o Risk Event (The Event)

    o Probability of the Event

    o Impact or Effects of the Event (Amount at Stake)

  • 8/8/2019 Study Items for the PMP EXAM

    23/66

    Delhi technique is a Consensus TechniqueResidual Risk are those that Remain after Risk Responses have been taken

    Inputs to Performance Reportinga r e

    o Work Performance Informationo Performance Measurements

    o Forecasted Completion

    o QC Measurement

    o Project Plan

    o Approved Change Requests and

    o DeliverablesInterpersonal communication takes three forms

    o Verbal

    o Non-verbal and

    o WrittenWhen distributing information, the total message impact from the sender iso7% words ,o38% vocal tones ando55% body language

    A Planning Package is a WBS component below the control account but above the work package. It is

    used for planning unknown work content that does not have detailed schedule activities

    There are two types ofDecision Models that can be used for Project

    Selection during the initiation Process

    o Comparative (Benefit measurement Rating) Models

    o Constrained (Mathematical Decision Models)

    Comparative (Benefit measurement Rating) Models

    o Decision Tree

    o Criteria Profiling

    o Weighted Factor

    o Q-Sorting

    o Delphi Technique

    Constrained (Mathematical Decision Models)

    o Logical Framework Analysis

    o Linear Program ProgrammingThe Control Points in the WBS used for isolated assignment to workcenters are referred to as the Control Account PlanControl account Plan (CAP) is a management control point where the

  • 8/8/2019 Study Items for the PMP EXAM

    24/66

    integration of scope, budget and schedule take place and where the measurement of performance takes

    place. These CAPS are placed at the selected management points in the WBS.Cost Estimates include All Resources to be charged to the ProjectA Control Account is a management control point that can be placed at

    selected management points of the WBS above the Work Package Level

    To convey information between two or more parties, the communication

    process must have a medium. The three most common mediaa re

    o Visual

    o Auditory and

    o Tactile

    Four steps of performing RCA (Root Cause Analysis) are

    o Data Collection

    o Casual Factor Charting

    o Root Cause Identification

    o Recommendation Generating and ImplementationScatter Diagrams are used to investigate the possible relationship betweentwo variables that both relate to the same EVENTBCR (Benefit Cost Ratio) compares the benefits to the costs of the projectwhere the Benefits are the same as Revenues or often referred to as thePayback period

    Project performance is impacted by Four Basic Cultures

    o World

    o National

    o Business and

    o LeadershipWhen one considers their Culture to be superior, they are calledEthnocentricUse of personal space during social interaction is known asProx em ic s Riskisthe

    notionofdealingwithUncertaintyo Knows at the extreme end of the Uncertainty Spectrum will definitelyaffectyou,althoughyou

  • 8/8/2019 Study Items for the PMP EXAM

    25/66

    havenocontrolover

    them o

    Knows-Unknowns are items that will affect you although you are not able to

    predicthoworhowmuchtheywilleffect

    you o

    Unknown Unknowns are items or situations whose existence we cannot imagine

    A Records Management Systems is a specific set of processes, related control functions and automation

    tools used by the PM to manage contract documentation and records. Its the TT of ContractAdministration ProcessParametric (Top Down) uses historical data and statistical relationships todetermine costsConstructive team roles include Initiators, Information seekers, Informationgivers, Encouragers, Clarifiers, Harmonizers, Summarizers and Gate KeepersDestructive team roles include Aggressor, Withdrawer, Blocker, Devilsadvocate, Recognizer, Topic Jumper and Dominator

    To Complete Performance Indicator (TCPI) determines the cost performance efficiency required to

    complete the project within the original budget (BAC) or revised budget (EAC);TCPI > 1 is NOT good; To calculate TCPI, take the value of the workremaining over the value of funds remainingEustress is a stress that will motivate and contribute to an increase inperformance

    Quantitative based durations (Parametric technique) multiply a known element, like lines of code required

    by the time it takes to develop one line of code. The result is the total estimate for the activityQuality Metrics are the Outputs of Quality Planning. It is an operationdefinition that describes what something is and how it will be measured

    in very specific termsStraight-line depreciation is the simplest method of depreciating an asset

    and is frequently utilized on a project to determine its economic feasibility. Straight-line depreciation is a

    method that divides an assets cost and its expected salvage value by its expected utilization periodPerformance Reporting is an INPUT to all Control Process (Except QualityControl)

  • 8/8/2019 Study Items for the PMP EXAM

    26/66

    Decision Trees are considered Quantitative while Influence diagramareconsidered Qualitative.

    Influence diagram shows the dependencies among the variables moreclearly than the decision treeA Bill of Material (BOM) describes the product in terms of its assemblies,sub-assemblies and basic partsAllowing Automatic Approval of changes is a function of the ChangeControl System and NOT Configuration ManagementContingency Plan document outlines the actions to be taken if an identifiedrisk event should occurVariable and attribute sampling are forms of acceptance sampling.Variable sampling evaluates a characteristic measured on a numerical scaleAttribute sampling tests for defective or non defective

    Parametric Modeling applies to only Project with Similar characteristics

    The point of total assumption (PTA) is a price determined by a fixed price plus incentive fee contract

    (FPIF) above which the seller bears all the loss of a cost overrun. It is also known as the "most

    pessimistic costVariance analysis involves comparing actual project results to planned orexpected resultsTrend analysis involves examining project results over time to determine ifperformance is improvingHistorical Records need to collect and use for planning, estimating and riskKickoff meetings are importantDo not introduce benefits that are not stated in requirementsNeeds of all stakeholders should be taken into account during all projectsTeam Members must be involved in project planningProject Mangers must be pro-activeProject Phases are marked by the completion of a deliverableo

    Tangible, verifiable work productoReview of deliverables and approval/denial are phase exits, stagegates, or kill pointsPhases are collected into the Project Life CycleSet of defined work procedures to establish management control

  • 8/8/2019 Study Items for the PMP EXAM

    27/66

    Project Management SkillsoGeneral Business Management (consistently producing resultsexpected by stakeholders)oLeading (establishing direction, aligning resources, motivating)oCommunicating (clear, unambiguous, and complete)oNegotiating (conferring with others to reach an agreement)oProblem Solving (definition and decision making)oDistinguish causes and symptomsoIdentify viable solutionsoInfluencing Organization (understanding power and politics)Socioeconomic Influences

    oStandards document approved that provides common, repeateduse, rules and guidelinesoCompliance is not mandatoryoRegulations document that identifies products, services orcharacteristicsoCompliance is mandatoryoStandards often become de facto regulationso

    InternationalizationoCultural InfluencesInitiating and Planning ProcessesCommitting the organization to beginInitiation, High-level planning, CharterAmount of planning proportional to the scope of the project Core PlanningoScope Planning written statement

    oScope Definition subdividing major deliverables into moremanageable unitsoActivity Definition determine specific tasks needed to produceproject deliverablesoActivity Sequencing plotting dependencieso

  • 8/8/2019 Study Items for the PMP EXAM

    28/66

    Activity Duration Estimating determine amount of work neededto complete the activitiesoSchedule Development analyze activity sequences, duration, andresource requirementsoResource Planning identify what and how many resources areneeded to perform the activitiesoCost Estimating develop resource and total project costsoCost Budgeting allocating project estimates to individual workitemsoProject Plan Development taking results from other planningprocesses into a collective documentPlanning/Facilitating Processes manage the interaction among theplanning processeso

    Quality Planning standards that are relevant to the project anddetermining how to meet standardsoOrganizational Planning identify, document, and assigningproject roles and responsibilitiesoStaff Acquisition obtaining the human resourcesoCommunications Planning determining rules and reportingmethods to stakeholdersoRisk Identification determining what is likely to affect the projectand documenting these risks

    oRisk Quantification evaluating risks and interactions to accessthe possible project outcomesoRisk Response Development defining enhancement steps andchange control measuresoProcurement Planning determining what to buy and whenoSolicitation Planning documenting product requirements andidentifying possible sourcesExecuting Processes

    oProject Plan Execution performing the activitiesoComplete Tasks/Work PackagesoInformation DistributionoScope Verification acceptance of project scopeoQuality Assurance evaluating overall project performance on a

  • 8/8/2019 Study Items for the PMP EXAM

    29/66

    regular basis; meeting standardsoTeam Development developing team and individual skill sets toenhance the projectoProgress MeetingsoInformation Distribution making project information available ina timely manneroSolicitation obtaining quotes, bids, proposals as appropriateoSource Selection deciding on appropriate suppliersoContract Administration managing vendor relationshipsControlling Processes needed to regularly measure project performanceand to adjust project planTake preventive actions in anticipation of possible problems

    oChange Control coordinating changes across the entire projectplanoScope Change Control controlling scope creepoSchedule Control adjusting time and project schedule of activitiesoCost Control managing project budget

    oQuality Control monitoring standards and specific project results;eliminating causes of unsatisfactory performance

    oPerformance Reporting status, forecasting, and progressreporting scheduleoRisk Response Control responding to changes in risk during theduration of the projectClosing ProcessesoAdministrative Closure generating necessary information toformally recognize phase or project completionoContract Close-out completion and delivery of projectdeliverables and resolving open issuesoProcurement AuditsoProduct VerificationoFormal AcceptanceoLessons Learnedo

  • 8/8/2019 Study Items for the PMP EXAM

    30/66

    Update RecordsoArchive RecordsoRelease TeamProject Integration ManagementoEnsures that the project processes are properly coordinatedoTradeoffs between competing objectives and alternatives in order tomeet stakeholder approvaloProject Plan DevelopmentoProject Plan ExecutionoOverall Change ControloThese processes may occur repeatedly over the project duration

    oHistorical Records are needed to perform project management well,they are inputs to continuous improvementoFilesoLessons LearnedoActual CostsoTime EstimatesoWBS

    oBenchmarksoRisksProject Plan DevelopmentoUses outputs from other planning processes to create consistentdocument to guide project execution and controloIterated several timesoDocuments planning assumptions

    oDocuments planning decisions that are chosenoFacilitates communicationoDefines key management reviewsoProvides a baseline to track progress measurement and projectcontrol

  • 8/8/2019 Study Items for the PMP EXAM

    31/66

    Project Plan Development InputsoOther planning outputs: primarily the planning process outputs(WBS, base documents, application area inputs)oHistorical information verify assumptions, records of past projectperformanceoOrganizationalpolicies

    qualitymanagement,personneladministration, Financial controlsoConstraints factors that limit performance, contractual provisions,budgetoAssumptions risk factors

    Tools & Techniques for Plan Development

    oProject Planning Methodology any structured approach (software,templates, forms, start-up meetingsoStakeholder Skills & Knowledge tap into plan development; useexpertise for reasonablenessoPMIS Out of the box approach to support all project aspectsthrough closure

    Project Plan Development OutputsoProject Plan is a collection that changes over time as moreinformation about the project becomes availableoBaseline will change only in response to approved scope changeoProject Plan includes some or all of the following:oProject CharteroProject Management approach or strategyoScope statementoWork Breakdown Structure (WBS)oBudget, schedule, risksoKey Staff, Major MilestonesoChange Control Plan, Management and Communications Plan

  • 8/8/2019 Study Items for the PMP EXAM

    32/66

    Project Plan ExecutionoPrimary process for carrying out the project planoMost costly aspect of project managementoDirection of organizational resources and interfacesProject Plan Execution Inputs:oProject PlanoSupporting DetailoOrganizational PoliciesoCorrective Action anything to bring expected performance in linewith the project planTools & Techniques for Plan Execution

    oGeneral Management SkillsoProduct Skills and Knowledge defined as part of planning, providedby staffingoWork Authorization System formal procedure for sanctioning workto ensure completion written or verbal authorizationoStatus review meetings regular exchanges of informationoProject Management Information Systemo

    Organizational ProceduresProject Plan Execution OutputsoWork results the outcome of activities performed is fed into theperformance reporting processoChange Requests expand/shrink project scope, modify costs andschedule estimatesOverall Change ControloInfluencing factors that create change to ensure beneficial results;

    ensure that change is beneficialoDetermining that change has occurredoManaging actual changes as they occur

    Evaluate impact of change

    Meet with team to discuss alternatives

  • 8/8/2019 Study Items for the PMP EXAM

    33/66

    Meet with management to present decisionChange control requiresoMaintaining integrity of performance measurement baselines (projectplan)oEnsuring changes to scope are accurately recordedoCoordinating changes across knowledge areas (scheduling, risk, cost,quality, etc.)

    oDetermine all factors that control change and pro-actively preventingthe occurrence; evaluate the impact of changeInputs to Change ControloProject Plan baseline performanceo

    Performance Reports issue tracking, risk managementoChange Requests orally or written, externally or internallyinitiates, legally mandated or optionalChange Control Tools & TechniquesoAll Changes must be evaluated before a decision can be reachedoChange Control System collection of formal procedures,paperwork, tracking systems, approval levelsoChange Control Board decision making authority

    oConfiguration Management documented procedure to applytechnical and administrative direction

    ID and document functional and physical characteristics

    Control changes to these characteristics

    Record and report change and implementation status

    Audit items and system to verify requirementsoPerformance Measurement earned value, plan variance analysisoAdditional Planning revised cost estimates, modify activitysequences, plan adjustmentsoProject Management Information SystemoChange Control System may have

    Change Control Plan

  • 8/8/2019 Study Items for the PMP EXAM

    34/66

    Change Control Board

    Change Control Procedures, Corrective Action plans

    Performance Statistics, Reports, Change forms

    Specification reviews, Demonstrations, Testing, MeetingsoConfiguration ManagementChange Control OutputsoProject Plan UpdatesoCorrective ActionsoLessons Learned variance causes and reasoning documented forhistorical purposesConfiguration Management

    oRigorous Change Management as it relates to scope

    Subset of the change control systemWork Authorization SystemoControls gold plating; defines what task is/is notMeetingsoMost are inefficient; keep minuteso

    Status can be determined without meetingLessons LearnedoProject is not complete until a Lessons Learned is completedoWhat have we done, how can we do it better

    Technical Aspects of the project

    Project Management (WBS, plans, etc.)

    Overall Management (communications, leadership)

    Best to have whole team complete and made available

    Also called Post MortemProject Scope ManagementoProcesses required to ensure that the project includes all, and only,work requiredo

  • 8/8/2019 Study Items for the PMP EXAM

    35/66

    Defining what is/is not included in the projectoProject scope work that must be done measured against projectplan

    oProduct scope features and functions included in the product orservice measured against requirementsInitiation process of formally recognizing that a new project exists, or anexisting project continue to next phaseInvolves feasibility study, preliminary plan, or equivalent analysisAuthorized as a result of:oMarket DemandoBusiness Needo

    Customer RequestoTechnological AdvanceoLegal RequirementInitiation Inputs:

    Product Description characteristics of the product/service thatthe project was to createLess detail in early phases, more comprehensive in latter

    Relationship between product/service and business needShould support later project planningInitial product description is usually provided by the buyer

    Strategic Plan supportive of the organization's goals

    Project Selection Criteria defined in terms of the product andcovers range of management concerns (finance, market)

    Historical Information results of previous project decisionsand performance should be consideredSigned contractProject Manager Identification & Authority levelSenior Management approvalProjects Goals and Objectives -Constraints factors that limit project management teams

  • 8/8/2019 Study Items for the PMP EXAM

    36/66

    optionsAssumptions factors that are considered true for planningpurposes. Involve a degree of riskScope Planning process of developing a written statement as basis forfuture decisionsScope Definition subdividing major deliverables into smaller,manageable components

    Improve accuracy of cost, time, and resource estimates

    Define a baseline for performance measurement

    Clear responsibility assignments

    Critical to project success reduces risk of higher cost, redundancy,time delays, and poor productivity

    Defines what you are doing; WBS is the toolScope Change Control:

    Influencing factors to ensure that changes are beneficial

    Determining scope change has occurred

    Managing changes when they occur

    Thoroughly integrated with other control processesProject Time Management

    Processes required to ensure timely completion of the project

    No consensus concerning differences between activities and tasks

    Activities seen as composed of tasks most common usage

    Other disciplines have tasks composed of activitiesActivity Definition: identifying and documenting specific activities toproduce project deliverables identified in the WBS

    Must be defined to meet the project objectives

    Activity Sequencing identifying and documenting interactivedependencies among activities. Support later development of a realisticschedule

    Project Management software often usedNetwork Diagrams

  • 8/8/2019 Study Items for the PMP EXAM

    37/66

    Shows how the project tasks will flow from beginning to endProves how long the project will take to complete

    Takes project tasks from low levels of WBS and placing them intotheir order of completion (beginning to end)Activity Duration Estimating

    Involves assessing number of work periods needed to completeidentified activities

    Requires consideration of elapsed time, calendars, weekends, andday of week work startsSchedule Development

    Determining start and finish dates for project activities

    Without realistic dates, project unlikely to be finished as scheduled

    Schedule development process often iterates as more informationbecomes available (process inputs)Key Definitions:

    Slack (Float): the amount of time a task can be delayed withoutdelaying the entire project. Tasks on critical path have no slack.Slack is calculated by the difference between Early Start andLate Start of a task

    Free Slack (Float): the amount of time a task can be

    delayed without delaying the early start date of its

    successorTotal Slack (Float): the amount of time a task can bedelayed without delaying the project completion date

    Lag: inserted waiting time between tasksGeneral Comments:

    Projects can have more than 1 critical path (increases risk) and caninvolve dummy tasks

    Negative float indicates that you are behind

    Resource Leveling involves possibly letting schedule and cost slip

    Heuristics just means rule of thumb e.g. 80/20 rule

    Schedules are calendar based makes this different than a timeestimate

  • 8/8/2019 Study Items for the PMP EXAM

    38/66

    Bar Chart a.k.a. Gantt chart (track progress, report to entireteam including stakeholders, control tool)Network Diagram (to show task inter-dependencies, showproject organization, basis for project control)Milestone chart (report to Senior management, shows majorevents)

    To shorten project schedule examine the critical pathCrashing add more resources to the critical path tasks

    Usually results in increased costFast Tracking performing tasks in parallel

    Can result in re-work and increased risk

    Best to select method that has least impact on the project

    Bar (Gantt) ChartsWeak Planning Tool, effective progress and reporting toolDoes not show interdependencies of tasksDoes not help organize the project more effectively

    Network Diagrams (PERT, CPM, PDM)Shows task interdependencies

    Aids in effectively planning and organizing work

    Provides a basis for project control

    Milestone ChartsOnly shows major eventsGood for reporting to management and customer

    Flow ChartsDepicts workflow and not commonly used for projectmanagement

    Free Slack (Float) amount of time a task can be delayed withoutdelaying the early start date of its successor

    Total Slack (Float) amount of time a task can be delayed withoutdelaying the project completion dateLag inserted waiting time between tasks

  • 8/8/2019 Study Items for the PMP EXAM

    39/66

    Resource Leveling level peaks of resource usage; stable numberof resources allows schedule and cost slip in favor of levelingresourcesHeuristic rule of thumb (80/20 rule)Project Cost Management

    Ensure that the project is completed within budget

    Concerned with cost of resources needed to complete activities;

    consider effect of project decisions on cost of using product life-cycle

    costingMost prospective financial impact of using the product is outside theproject scope

    Consider information needs of stakeholders, controllable and

    uncontrollable costs (budget separately for reward and recognition

    systems)Estimating should be based on WBS to improve accuracy

    Estimating should be done by the person performing the work

    Having historical records is key to improving estimates

    Costs (schedule, scope, resources) should be managed to estimates

    A cost (schedule, scope, baseline) should be kept and not changed

    Plans should be revised as necessary during completion of work

    Corrective action should be taken when cost problems (schedule,scope and resources) occur.Resource Planning:

    Determining what physical resources and quantities are needed toperform workCost Estimating:

    Develop approximate costs of resources

    Distinguish estimating from pricingEstimating likely amountPricing business decision

    Identify alternatives and consider realigning costs in phases to theirexpected savings

  • 8/8/2019 Study Items for the PMP EXAM

    40/66

    Cost Budgeting

    Involves allocation of total estimate to individual work to establish acost baseline to measure performanceCost Control

    Concerned with influencing factors that create changes to the costbaseline that are beneficial

    Determining that the cost baseline has changed

    Managing actual changes as they occurMonitor cost performance to detect variancesRecord all appropriate changes accurately in the cost baselinePreventing incorrect, unauthorized changes being included in

    the cost baseline

    Informing stakeholders of authorized changesDetermine the whys of positive and negativevariancesIntegrated will all other control processes (scope,change, schedule, quality)Earned Value Analysis

    Terms:BAC Budget at Completion (how much did you budget forthe total job)EAC Estimate at Completion (what do we expect the totalproject to cost)ETC Estimate to Completion (how much more do we expectto spend to finish the job)VAC Variance at Completion (how much over/under budgetdo we expect to be)

    FormulasVariance (Plan Actual)Cost Variance (CV): BCWP ACWP; negative is over budgetSchedule Variance (SV): BCWP BCWS; negative is behindschedule

  • 8/8/2019 Study Items for the PMP EXAM

    41/66

    Cost Performance Index (CPI):B CWPACWPSchedule Performance Index (SPI):B CWPBCWS

    I am only progressing x % of the planned rateEstimate at Completion (EAC):BA CCPI

    As of now we expect the total project to cost x$Estimate to Complete (ETC): EAC ACWP; how much will itcost from now to completionVariance at Completion: BAC EAC; when the project isover how much more or less did we spend (most common wayof calculating EVA

    Accuracy of Estimates

    Order of Magnitude Estimate: -25% - 75%; usually made duringInitiation Phase

    Budget Estimate: -10% - 25%; usually made during the Planningphase

    Definitive Estimate: -5% - 10%; usually made during the Planningphase

    Accounting Standards

    Sunk Costs: expended costs. Sunk costs should not be considered

    when determining to continue with a troubled projectLaw of Diminishing Returns: the more that is put in the less of anoutcome is received

    Working Capital: current assets current liabilities

    Variable Cost: costs that change with the amount of production orthe amount of work (materials, wages)

    Fixed Cost: non-recurring costs that do not change

    Direct Cost: directly attributable to project work (travel, wages,

    materials)Indirect Cost: overhead items or costs for the benefit of more thanone project (taxes, fringe benefits)

    Depreciation: assets lose value over timeStraight Line depreciation: same amount is taken each year

  • 8/8/2019 Study Items for the PMP EXAM

    42/66

    Accelerated Depreciation: 2 formsDouble Declining Balance

    Sum of the Years Digits

    Life Cycle Costing: includes operations and maintenance phases

    Value Analysis: find a less costly way to do same work

    Make or Buy decisions at Development (Planning) phase, notconceptual phase

    Definitive Estimate most precise/accurate estimate fordetermining project costs

    Management Reserve over time PM wants no change to reserve;customers wants $ back

    Cost and Schedule Data predicts future performance

    ROI, Nest Present Value and Discounted Cash Flow all can beused to measure total income vs. total $ expended

    Undistributed budget budget that contains approved scopechanges but are not planned yet

    Depreciation is not a measurement of profitability

    Pay Back Period - # of periods required to recover the initialinvestment

    Project Quality Management

    Processes required to ensure that the project will satisfy the needsfor which it was designed

    Includes all activities of the overall management function that

    determine the quality policy, objectives, and responsibilities. These

    are implemented by quality planning, quality control, quality

    assurance, and quality improvement.3 major processes:

    Quality Planning identifying quality standards that are relevant to

    the project (Plan); Project Manager, Project OwnerQuality Assurance evaluating overall project performance toprovide confidence that project will satisfy relevant quality standards(Implement or Execution); Project Team

    Quality Control monitoring specific results to comply with qualitystandards and eliminating unsatisfactory performance causes (Checkor Control); Project Manager, Project Team

  • 8/8/2019 Study Items for the PMP EXAM

    43/66

    Compatible with ISO 9000 and 10000 seriesProprietary and non-proprietary approaches (total qualitymanagementMust address the management of the project and the productof the project

    Quality the totality of characteristics of an entity that bear on its ability tosatisfy stated or implied needs

    Critical aspect is to turn implied needs into stated needs throughproject scope management

    Do not confuse with grade category or rank given to entitieshaving the same functional use but different requirements for quality

    Customer satisfaction conformance to specifications (mustproduce what is stated) and fitness for use (must satisfy real needs)

    Prevention avoid mistakes vs. cost of correctionManagement responsibility requires participation of team;responsibility of management to provide resources

    Processes within phases plan-do-check-act cycle

    Recognize that the investment in product quality

    improvements may be borne by the performing organization

    since the project may not last long enough to reap rewardQuality Planning

    Identify quality standards are relevant and how to satisfy

    Quality Assurance

    All planned and systematic activities implemented within the quality

    system to provide confidence that the project will satisfy quality

    standardsQuality Control monitoring specific results to determine if they complywith quality standards and identifying ways to eliminate causes ofunsatisfactory results

    Includes project (deliverables) and management (cost and scheduleperformance) results

    Awareness of statistical quality controlPrevention (keep errors out of process) and inspection (keeperrors from customers)Attribute sampling (result conforms) and variable sampling

  • 8/8/2019 Study Items for the PMP EXAM

    44/66

    Special Causes (unusual events) and random causesTolerances (acceptable range) and control limits (result fallswithin range)

    Tips from the Review Guide

    Philosophy: definition of quality, avoidance of gold plating givingcustomer extras, prevention over inspection

    Conformance to requirements, specifications and fitness of use

    Quality Management processes required to ensure that theproject will satisfy the needs for which it was undertaken

    Continuous Improvement- small improvements to reduce costsand ensure consistency

    Marginal Analysis optimal quality is reached at the point when

    revenue from improvement equals the costs to secure itJust in Time- decrease amount of inventory/decrease investment

    ISO 9000 or 10000 standards to ensure that corporations followtheir own quality procedures

    Total Quality Management continuous improvement in businesspractices

    Normal Distribution most common probability used to measurevariations

    Standard deviation (sigma) measure how far away from themean (dotted vertical line)

    3 or 6 sigma represents level of quality+/- 1 sigma equal to 68.26%+/- 2 sigma equal to 95.46%+/- 3 sigma equal to 99.73%+/- 6 sigma equal to 99.99%

    Responsibility to quality entire organizationUltimate employeeOverall or Primary Project ManagerDesign and Test Specifications engineer

    Prevention over inspection quality must be planned in notinspected in

  • 8/8/2019 Study Items for the PMP EXAM

    45/66

    Cost of conformance vs. non-conformanceQuality Training vs. reworkStudies vs. ScrapSurveys vs. Inventory Costs and warranty costs

    Quality Planning (Plan) determine what will be quality onproject and how quality will be measured done during PlanningPhasesIdentifying which standards are relevant to project how tosatisfy them

    Benchmarking look at past projects to determine ideas forimprovement

    Cost Benefit AnalysisFlowcharts (fishbone)Design of Experiments

    Quality Assurance (Implement) determine if your measurementof quality is appropriate done during Execution phasesProcess of evaluating overall performance on a regular basisQuality Audits structured review of quality activities thatidentify lessons learned

    Quality Control (Check) perform the measurement and compareto the quality plan done during Control phases

    Process of monitoring specific project results to determine if

    they comply with relevant quality standards and identify ways

    of eliminating unsatisfactory performancePerformance of the measurement or process, using qualitycontrol tools checking workQuality Control Tools

    Pareto Diagrams 80/20 rule the chart presentsthe information being examined in its order of priorityand helps focus attention on the most critical issues

    Fishbone diagram (Cause and Effect)

    A creative way to look at the causes or potentialcauses of a problem

  • 8/8/2019 Study Items for the PMP EXAM

    46/66

    Helps stimulate thinking, organizes thoughtsand generates discussion

    Can be used to explore a desired futureoutcome and the factors to which it relates

    Checklists list of items to inspect

    Control Charts graphic displays of the results overtime used to determine if a process is in control

    Upper and Lower Control Limits two

    dashed lines show the acceptable range of a

    variation range determined by companys

    quality standard (sigma)Mean line in the middle shows middle ofthe range of acceptable results

    Specification Limits 2 solid lines outside theupper and lower control limits represent thecustomer's expectations/requirements of qualityQuality Control Tools

    Out of Control process is out of controlwhen:

    A data point falls outside of the upper or lowercontrol limit

    Non-random data points are within the upper

    control and lower control limitsRule of 7 non-random points outside themean - process should be investigated

    Assignable Cause data point the requiresinvestigation to determine the cause of thevariationPMI and Deming

    Cost of conformance 85% of costs of quality areresponsibility of Management

    Quality Training Rework

    Studies Scrap

    Surveys Inventory and Warranty costsCrosby absolutes of quality

  • 8/8/2019 Study Items for the PMP EXAM

    47/66

    Performance standard is zero defects; measurementsystem is cost of non-conformanceContinuous Improvement

    Japanese (Kaizen)Marginal Analysis optimal quality is reached whenincremental revenue from improvement equals incrementalcost to secureVariable characteristic to be measuredAttribute measurement (objective or subjective)Increase quality = increased productivity, increased costeffectiveness, decreased cost risk

    Project Human Resource Management

    Processes required to make the most efficient use of people3 major processes:Organizational PlanningStaff AcquisitionsTeam Development

    Keep in mind of transient nature of projects

    Apply techniques that apply to current project needs

    Ensure HR compliance with project management activities

    Project OrganizationConflict between PM and Functional ManagersDual allegiance of team membersComplex prioritization of resourcesLoss of developed procedures on project dissolution

    Compromise = both sides will loseDelegationDefer the decisionInterpreted as passiveEmphasize task vs. personnel

  • 8/8/2019 Study Items for the PMP EXAM

    48/66

    Can be frequently usedIf there is a team of experts, PM decisions will promote highsatisfaction

    Functional/Project Managers likely to exercise:PowerAuthorityInfluence

    Traditional organization forms have no single point of contact forclient/sponsor

    Organizational Planning

    Identifying, documenting and assigning project roles, responsibilities,and reporting relationships

    Individual and group assignmentsInternal and external employeesLinked with communication planning

    Staff Acquisition

    Ensure resources are available for project work

    Team Development enhancing stakeholders to contribute along withmaintaining the project teams functionality

    Personal development is the foundation

    Team members often balance responsibilities to a functional managerand project managerCritical to success of project

    Review Guide Tips

    Roles and responsibilitiesProject Manger plan, estimate and schedule of projectTeam help prepare the WBS, Network Diagrams, andestimate time for tasks, complete tasksSenior Management approve Overall project plan, budgetand schedule and to approve any changes that are made tothose figuresThe person experiencing the problem must try to solve it

  • 8/8/2019 Study Items for the PMP EXAM

    49/66

    themselves as long as means are in their controlPowers:Formal (legitimate)RewardPenalty (coercive)Expert (earned)Referent authority of a higher position

    Best are Expert and Reward; Penalty is the worstFormal, Reward and Penalty derived from PMs position withinthe company

    Conflict

    Inevitable consequence of organizational interactionsCan be beneficialResolved by identifying the causes and problem solving bypeople that are involved & their immediate managerNature of projectLimited power of the project managerNecessity for obtaining resources from functional managers

    Conflict Sources (in order of frequency)SchedulesProject PrioritiesResourcesTechnical opinionsAdministrative Procedures

    CostPersonality

    Motivational TheoriesMaslows Hierarchy of Needs people work to get achance to contribute and use their skills

    self-actualization

  • 8/8/2019 Study Items for the PMP EXAM

    50/66

    McGregors Theory of X and Y

    X people need to be watched every minute

    Y people willing to work without supervisionHerzbergs Theory poor hygiene factors destroymotivation but improving them will not improve motivation

    Motivating Agents

    Responsibility

    Self-actualization

    Professional growth

    Recognition

    Responsibility ChartsMatrix cross references team members with tasks (does notshow time when job is done)Histogram months vs. number of resourcesGantt Chart shows when staff allocated to tasks

    Leadership SkillsDirective

    FacilitatingCoaching

    Supportive

    Team Building Skills

    Projectized OrganizationConflict between PM and Functional ManagersDual Allegiance of team membersComplex prioritization of resourcesLoss of developed procedures on project dissolution

    Compromise both sides will lose

    Delegation

  • 8/8/2019 Study Items for the PMP EXAM

    51/66

    Defer the decisionInterpreted as passiveEmphasize task vs. personnelCan be frequently utilized

    Project Communications Management

    Processes to ensure timely and proper generation, collection,dissemination and disposition of project information

    General communications managementCommunications Planning determining informationalneeds, who needs what and when; 90% of PMs time is spentcommunicatingInformation Distribution making information available

    Performance Reporting collecting and disseminating projectinformationAdministrative Closure formalize project/phasecompletion

    Communications Planning

    Determining information requirements of stakeholders

    Tightly linked with organizational planning

    Information Distribution making information available in a timelymanner by implementing the communications plan; responding to requestsfor information

    Performance Reporting

    Collecting and disseminating performance indicators to provide

    stakeholders information how resources are achieving project

    objectivesStatus reportingProgress reportingForecastingProject scope, schedule, cost and quality, risk andprocurement

    Administrative Closure

    Projects/phases after achieving results or terminated require closure

  • 8/8/2019 Study Items for the PMP EXAM

    52/66

    Verifying and documenting project results to formalize acceptance

    Collection of project records, analysis of effectiveness, reflect finalspecifications and archiving of material

    Tips from Review Guide

    Understand all concepts and major points

    Memorize the communications model

    Understand the inputs/outputs of Administrative Closure

    Understand how administrative closure differs from contract closeout

    Contract closeout has product verification and administrative

    closeout but the contract terms may have special

    provisions/procedures for closeout

    Communication Model

    Messages are encoded by sender and decoded by receiver based onreceivers education, experience, language and culture

    Sender should encode message carefully

    Nonverbal

    Paralingual (pitch and tone)

    Active Listening receiver confirms they are listening,confirms agreement and ask for clarification

    Effective Listening watching speaker, think before

    speaking, ask questions, repeating and providing

    feedbackCommunication Methods

    Pick the form of communication that is best for the situationFormal Written complex problems, All Plans,communicating over long distances

    Formal Verbal Presentations, speechesInformal Written memos, e-mail, notesInformal Verbal Meetings, conversations

    Communication Blockers

    Noise, Distance, Improper en-coding, bad idea, Hostility, Language,

  • 8/8/2019 Study Items for the PMP EXAM

    53/66

    CulturePerformance Reporting

    Status Reports (where project stands)

    Progress Reports (what has been accomplished)

    Trend Report (project results over time)

    Forecasting Report (projecting future status)

    Variance Report (actual results vs. planned)

    Earned Value

    Communication Channels communications grow at a linear rate

    N (N-1)/2 where N = the number of people

    Example 4 people equals 6 communication channelsTo determine if someone understands message feedback must be obtained

    Unanimous Agreement

    All members committed

    Decisions reached slowly

    Integrity is developed

    Future decision making is enhanced

    Clearly defined group goals

    Motivate team behavior

    Cause tension until completed

    Encourage member identification

    Complex messages need oral, written and non verbal methods

    There are 5 directions of communication

    Faade when an individual processed needed information but withholdsthe informationLeast effective for