STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report • Organisation and Management • Strategy and Planning • Review of experience • Status and Final Actions

Transcript of STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and...

Page 1: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 1

ST Division W2000 Migration status report

• Organisation and Management

• Strategy and Planning

• Review of experience

• Status and Final Actions

Page 2: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 2

Organisation and Management

• ST Migration Task Force group

Divisional SupportE. Sanchez-Corral, F. Skaar

Groups' linkmanDI K. Foraz

MAL. Hammoutti, F. Skaar, N. Dos Santos

CE K. Skelton, L. Jacob-RolsCV Y. BodyEL S. Oliger, G. BurdetHM J.P GranchelliTFM J. Garcin

Page 3: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 3

Organisation and Management (2)

• General Planning– Preparation

• Within the frame of the CERN W2000 migration project , define migration process, analysis and report ST specific needs

• January-May 2001

– Pilot Project in ST• June-July 2001

• No major problems found except “lack of sharing the Calendar with Outlook” -> not start yet Divisional migration

– Divisional Migration• October 2001- April 2002: using IT resources

• May-November 2002: using ST resources

Page 4: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 4

ST W2000 Migration preparation

• PC inventory analysis• ST minimum hardware configuration W2K compliant

– 300MHz (IT: 200MHz), 4G, 128 Mb (IT: 64Mb), PCI Ethernet card

• Done by every ST group desktop link man– Classify the PCs in W2K compliant, to upgrade (memory) and to replace.

– Take the appropriate actions to put PCs in conformity

• Results of the analysis (May 2001) : – Aprox. 130 obsolete, 100 to upgrade, 220 compliant

• IT/NICE provided (May 2001) information on “active” (logon to NICE servers) PCs

– Active W95/NT PCs = 402

• hardware information: memory, network card, disk, model

– Active W2000 PCs = 66

• Work is still required to process all the information and update accordingly the ST Inventory

Page 5: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 5

ST W2000 Migration preparation (2)

• Applications needs analysis: Applications required by ST not yet available in October 2001 when divisional Migration started:

– Outlook calendar sharing

• A workaround exist though it is mandatory to quit the calendar in order to allow access (R/W) to other granted users

• Under study by IT/NICE

– AutoCAD

• ~25 users. Deployment & training planned for mid-November 2001

– MP5

• ~150 users. Deployment planned for April 2002 (MP5 upgrade required first!)

• Alternative: deploy current MP5 granted Oracle Forms 4.5 is available on NICE2000 (but not certified by Oracle!) -> Support by IT required on W2000 MSI generation technology !

– CUBUS, OMNIS 7 and other specific applications (using Oracle, MS Access, Java)

• Only a few users, solution to be found, using if possible other compliant tool , otherwise upgrade licenses

Page 6: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 6

ST W2000 Migration Strategy

• Start ST divisional migration October 2001– Proposal agreed in the frame of ST W2000 migration task force

• Preliminary divisional migration plan defined (29/9/2001)– Feasible based on results ST Applications needs and PC inventory analysis

• Volume of work (+ co-ordination) should not be under estimated• Systematic but distributed on reasonable time (7-8 months)

– Profit IT/W2K Migration service resources available (October 2001- April 2002) • request service providing a Preliminary divisional migration plan

• ST management approval and support • “Migration process” launched weekly

– User (PC) follows Migration criteria – Minimum hardware configuration and required applications are available– Support personnel (IT, ST local desktop) available– Seminars and courses organised and user available to follow them

– User is available during migration (before, during, after)

Page 7: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 7

ST W2000 Migration Plan

• Migration phases defined based on Applications deployment planning and “migration criteria”

• Phase 1: migrate users of available applications (Basic, Advanced) -> COMPLETED !– 45% ST users= ~ 110 (~ 60 days: 0.5 days/user)– Planned : mid-October to January 2002

• Phase 2: migrate AutoCAD2002 users -> COMPLETED !– 5 % ST users= ~ 30 (~ 15 days)– Planned : November to January 2002 – Condition: co-ordinate with AutoCAD2002 training

• Phase 3: migrate MP5 users -> COMPLETED !– 50 % ST users= ~ 150 (~ 75 days)– Planned : April -June 2002

• if MP5 upgrade done at the same time as W2000 migration– Alternative planning done: February-April 2002

• Condition: If ORACLE Forms 4.5 available on W2000, then do first W2000 migration and only afterwards the MP5 upgrade.

• MP5 MSI package (including Oracle Forms 4.5) available since end January 2002. Some settings & installation actions required if also Oracle 2000 is needed (not compatible with MP5 Oracle).

• Phase 4: Completion: migrate not yet migrated users (PC not compliant, application)– Planned : April-June 2002 -> July-October 2002 !

Page 8: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 8

Review of Experience• No major problems encountered

– Migration procedure well defined and documented by IT division– Migration service offered by IT to Divisions– Training and support provided by IT to both administrators and users– Deployment of applications on W2000 went (goes!) smoothly

• IT: http://w2kmtf.web.cern.ch/w2kmtf/Applications.htm– Basic Applications (MS office, IE, Outlook), Labview, Oracle, Java available and

supported since June 2001.– Engineering applications (AutoCAD 2002) available since December 2001. Training

also provided.– Siemens S5, S7 available by end 2001.– Calendar sharing: extension to Exchange of mail servers required. Pilot project launched

in May 2002.

• ST– Specific tools: licenses upgraded. – Porting of Oracle (Forms) and Java applications done .– MP5 available since February 2002.– Being done the “porting” to MP5 of other specific applications : OMNIS- Car Pool,

TFM- Cleaning and Space management .– Exchange-Calendar. Testing: positive results, some migrations done. Plan the others.

Page 9: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 9

Review of Experience (2)

• Requirements – Migration required

– advance planning in the division: PC inventory and applications needs

– PC upgrades (memory, disks), replacement

– divisional co-ordination

– availability of users during the upgrade (at least at the beginning and end)

• Workload – Approx. 200 PCs were migrated

– Total migration process: 1/2 day / PC (user)

• Preparation: varied a lot from 1h to several hours (local data, applications and user settings)

• “Installation”: estimate duration: 90 min (CD-ROM) - 2.30h (diskette)

• Post-installation: varied a lot from 1/2h to a few hours

Page 10: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 10

Review of Experience (3)

• Resources– Divisional co-ordination

• Define planning and prepare & follow-up migration of 8-16 users (1-2 fixed days) per week since October 2001 till April 2002

• Quite a lot of effort required (1 person)– Sometimes user was not available as planned– Long process on not powerful PCs, or heavy user profiles – Lack of feedback (IT survey questionnaire rarely filled in)

– Migration Process• Preparation and Post-installation: support provided by ST Local Desktop

Support (1 person) and Migration groups linkmen• Installation done using IT resources: two to four persons from October 2001 till

April 2002

– PC upgrades and replacements• 2001-2002:

– Upgrade memory for approx. 80 PCs– approx. 140 PCs have been bought (Vobis PIII 800/850)

Page 11: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 11

Status

PCs in ST Division: 381 (June 2002)

280

101

WIN2000

Not migrated toWIN2000

Page 12: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 12

Status (2)

61

32

8HW not

compatibleNT4, Omnis, Calendar,

development etcTo be checked

ST PCs not migrated to W2000: 101

(June 2002)

Page 13: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 13

Final Actions

• Migration Process– Phase 4: Completion: review not yet migrated PCs (PC not compliant, application

not available) and migrate if possible• Period : July- October 2002

• ST PC Inventory update – Send to recuperation obsolete PCs

• Period : September- December 2002– Upgrade (memory) PCs

• Applications deployment– Provide support to applications migration/deployment (Exchange Calendar,

candidates of using MP5)• Period : September- November 2002

• ST users survey• Provide and promote training

– Seminars on general use of W2000 or specific tools

Page 14: STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.

STTC 20/08/2002 Eva Sánchez-Corral 14

News on NICE2000

• Future of NICE95/NT (Announced in Desktop Forum June 2002)

• Frozen from end of 2002

• Central support stopped by mid-2003

• IT PC Shop: CERN supported PCs • portables delivered only with W2000 since June 2001

• desktops delivered only with W2000 since January 2002