Strategic Slow Moving Spares Levels Optimisation€¦ · Gen. Gearbox Generator Fire/Gas Monitoring...
Transcript of Strategic Slow Moving Spares Levels Optimisation€¦ · Gen. Gearbox Generator Fire/Gas Monitoring...
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 1
Strategic Slow Moving Spares Levels Spares Levels
Optimisation Optimisation
By UMS Group Inc./ Asia Pacific
(Tony Saker, Principal)
Decision Support Tools Ltd&
The Woodhouse Partnership Ltd(Jack Huggett, Principal)
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 2
PRESENTATION OUTLINE
INTRODUCTION / OVERVIEW
TOOL DISCUSSION – DATA, INPUTS, COST/RISK CALCULATIONS, SENSITIVITIES
CASE STUDY
LIVE DEMONSTRATION
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 3
� An effective asset strategy must manage risk associated with the aging of the asset base and the overall growth in future asset demands
OVERVIEW
Mismanagement of the
Replacement
Wall Can Result In:
• Loss of asset performance
• Loss of market share
• Decreased asset value and function
• Loss of shareholder value
• Decline in business viability
Planning Horizon
Replacement Wall
Accumulated Asset Replacement Forecast
Potential Renewal
Liability at the end
of the planning
cycle
Accumulated Current Rate Of Renewal /
Spares Developments
Backlog
Accumulated Forecast
Replacement Cost
Ass
et R
epla
cem
ent C
ost
� The drive to asset life cycle optimality in cost, service, and risk performance is an ever increasing challenge to leading utilities worldwide. Effectively developing spares optimisation strategies and policies are key, supported by robust data systems, modelling and analysis techniques.
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 4
OPTIMUM = Minimum TOTAL cost/risk impact
Optimumis
2 spares
Number of spares held
Business Impact (A$000/year)
0
10
20
30
40
0 1 2 3 4
Money tied up
Storage & m'tce
Risk of write-off
Downtime risks
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 5
The European MACRO project
European EUREKA project EU1488
Main sponsors:
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 6
APT-Integrated Toolkit: 7 modules of structured
analysis & “what if?” techniques
APT-PROJECT Cost/Benefit/Risk Evaluation of Projects/Changes
APT-MAINTENANCE Optimisation of Planned Maintenance tasks
APT-INSPECTION Inspection, Condition Monitoring & Testing
APT-LIFESPAN Life Cycle Costs, Renewal & Upgrade Timing
APT-SCHEDULE Shutdown Strategy & Timing, Work Bundling
APT-SPARES Strategic/Slow-moving Spares Optimisation
APT-STOCK Purchasing & Inventory Optimisation
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 7
All decisions involve conflicting objectives
Ownership costs
• purchase costs
• money tied up
• storage costs
• in-storage
maintenance
• potential write-off
costs
Unavailability risks
• Production losses/delays
• Safety & environment
• Equipment damage
• Frustration and irritation
What spares should I hold?
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 8
APT-SPARES: Optimal stock holding of 50MVA transformers:
Optimal spares holding is 2:
If 1 spare is in stock:-
Consider purchasing 1
If 2 spares are in stock:-
Maintain stock level
If 3 spares are in stock:-
Do not restock if
1 spare is used
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 9
Step 1: Input Structured ‘best guesses’
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 10
Lack of accurate data?Lack of accurate data?
APT-SPARES
Range estimates of input factors
Max
Min
2
1
0
No. of spares
10
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 11
Step 2: Cost/risk calculations
Calculate
Risk if no spare is held
Residual risk if one spare
is heldCosts of
ownership for the spare
Total Business Impact is lowest if 1 spare is held
Conclusions & impact of change
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 12
Step 3: Data sensitivity analysis
But what if the data was
wrong?
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 13
Sensitivity to each input
Inputs ranked by the economic
effects of changing them by +/- 50%
Economic effect of reducingvalue by 50%
Economic effect of increasingvalue by 50%
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 14
What changes in assumptions are needed to change the result?
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 15
The ‘safety range’ for our decision
Our original ‘best guess’ assumptions (which implied that one spare is optimal)
The values that would be needed to justify holding a second spare
The values that would be needed
for the spare not to be justified
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 16
Using existing tacit knowledge - safely
• Forcing the right questions to be asked
• Range estimating – to the limits of credibility
• Tests for sensitivity, to find which assumptions really matter
• Rapid focus on the data that is (provably) worth collecting
• Clear audit trail for critical cost, risk and performance compromise decisions.
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 17
A further spare transformer would be worth holding from 2012-13 onwards (output from APT-SPARES)
Example of a Power transformer 50MVA class future spares requirements:
Spare 50MVA transformers:
0
1
2
3
4
2007
-820
08-9
2009
-10
2010
-11
2011
-12
2012
-13
2013
-14
2014
-15
2015
-16
2016
-17
2017
-18
2018
-19
Years:
Number of spares
no network support
Current policy
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 18
Power transformer 50MVA spares levels for various % of network support:
Spare 50MVA transformers:
0
1
2
3
4
2007
-820
08-9
2009
-10
2010
-11
2011
-12
2012
-13
2013
-14
2014
-15
2015
-16
2016
-17
2017
-18
2018
-19
Years:
Number of spares
no network support
30% network support
60% network support
90% network support
Current policy
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 19
APT-SPARES batch can handle large numbers of studies simultaneously:
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 20
APT-SPARES: optimal number of spares to hold now illustrated above:
www.decisionsupporttools.com/
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 21
APT Spares Optimisation Tool Description
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 22
Purchasing high cost spares might require investment funding:
APT-PROJECT – prioritises & evaluates investments such as purchase of high cost spares.
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 23
APT-PROJECT output page:
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 24
Optimal Timing - Restricted investment in the future?: Purchase of a 50MVA transformer could be delayed making it more cost effective with time:
As the risk of failure increases with network
expansion, payback of the spare transformer
improves from 2012-13:
0
20
40
60
80
100
120
140
160
2007
-8
2008
-920
09-1
020
10-1
120
11-1
220
12-1
320
13-1
420
14-1
520
15-1
620
16-1
720
17-1
820
18-1
9
Year:
Payback in y
ears
If from 2013 spare transformers need to have a minimum payback of 10 years (for
example), purchase of the spare would be delayed to
2014-15
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 25
Summary - for a future scenario of restricted investment funding…
• Spare transformers cost c.AUD $ 1,000,000 (for the illustration that follows)
• The investment in a spare is likely to be compared to other investments in a process of annual investment rationing
• The previous slides illustrates how one can carry out such a process:
• As the number of installed transformers increases and the risk of transformer failure increases too, the payback on the investment will improve until it is approved in a current annual investment budget.
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 26
An example of a model for project priority ranking & investment rationing:
Payback ranking @ 7% DR & investment rationing:
0500000
10000001500000200000025000003000000
1. Protecti
ve devic
e r...
2. Ove
rhead line in
sulat..
3. Increase
earth w
ire...
4. Spare 50MVA tra
ns...
5. T/fo
rmer fi
re & bund...
Investments
Cumulative $
invested
050100
150200250
Discounted
payback
(months)
Cumulative $ Payback months
24 month (2 year) payback
$2,750,000 cumulative investment
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 27
TAKING AN EVEN MORE WHOLISTIC VIEW IN priority ranking & investment rationing and part of an Asset and Spend Optimisation process: The UMS Group Spend Optimization Suite is designed to support the decision process; identifying and prioritizing the risks, analyzing investments and optimizing the portfolio of spend
SA IOIDSRIO
SO1
SO2
SO3
SO4
SO5
SO6
2.1 Inventory
and analysis of
risks
2.1 Inventory
and analysis of
risks
2.2Prioritizing
Risks
2.2Prioritizing
Risks
Risk Management Investment Planning Investment Strategy
3.4 Validate
Investment Plan
3.4 Validate
Investment Plan
4.1 Analyze
Investment Scenarios
4.1 Analyze
Investment Scenarios
4.2 Optimize
Investment Portfolio
4.2 Optimize
Investment Portfolio
4.3 Monitor/
Adjust Portfolio
4.3 Monitor/
Adjust Portfolio
3.1Generating Mitigation Solutions
3.1Generating Mitigation Solutions
3.2Analyzing Solutions
3.2Analyzing Solutions
3.3Develop
Investment Plan
3.3Develop
Investment Plan
R1
R2
R3
R4
R5
R6
.
R20
R21
R22
R23
R24
R25
.
R105
R106
R107
.
.
Rn
R1
R2
R3
R4
R5
R6
.
R20
R21
R22
R23
R24
R25
.
R105
R106
R107
.
.
Rn
S1
S2
.
S4
S5
S6
S7
S8
S9
.
.
S10
S11
.
.
S12
S13
S14
S15
.
S16
P1
P2
.
.
P5
P6
.
.
P9
.
.
P10
P11
.
.
P12
P13
.
P15
.
P16
P1
P2
.
.
P5
P6
.
.
P9
.
.
P10
P11
.
.
P12
P13
.
P15
.
P16
P1
P2
.
.
P5
P6
.
.
P9
.
.
P10
P11
.
.
P12
P13
.
P15
.
P16
P1
P2
.
.
P5
P6
.
.
P9
.
.
P10
P11
.
.
P12
P13
.
P15
.
P16
Optimized
Deferred
.
.
Optimized
Optimized
.
.
Optimized
.
.
Deferred
Optimized
.
.
Deferred
Deferred
.
Optimized
.
Optimized
1.1 Identify Business Strategy
1.1 Identify Business Strategy
Strategic Planning
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 28
Case study:
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 29
Spares for an Atlantic gas platform:
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 30
Cost effectiveness of proposed spares purchases:
0
10
20
30
40
50
60
70
80
90
100
< 2 years 2 to <5 yrs 5 to <10 yrs >10 yrs Not Cost
Effective
Overstocked
Payback in years:
Number of spares:
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 31
0 200000 400000 600000 800000 1000000 1200000 1400000 1600000
HP N2 Compressor
Sewage System
Production SIS
Allied Crane
Gen. Gearbox
Generator
Fire/Gas Monitoring
Auxilliary SIS
Fire H2O Pump Engine
Sump System
Gas Turbine (Gen)
MCC & Control Room HVAC
Pump Gearbox
Air Comp / LP N2
Gas Turbine (Comp)
Gas Compressor
Fire H2O Pump
Increased Spares Cost ($) Risk Reduction ($/yr)
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 32
Example of a compressor shaft:
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 33
Breakpoint analysis:
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 34
Sensitivity testing:
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 35
APT-SPARESlive demonstration
now follows:
© The Woodhouse Partnership Ltd 2010 © UMS Group Inc 2010 36
Tony SakerPrincipal & General Manager
UMS Group Asia Pacific
Suite 2b12-14 Falcon StreetCrows Nest NSW 2065
AustraliaOffice: +61 2 8413 0007
Fax, +61 2 8413 0010Mobile: +61 (0) 439 88 55 39
Contact Information