    Strategic housing

    servicesLondon Borough of Barking and Dagenham

  • 7/30/2019 Strategic council housing plans in London boroughs

    2/43

    The Audit Commission is an independent watchdog,

    driv ing economy, efficiency and effectiveness in local

    publ ic services to deliver better outcomes for everyone.

    Our work across local government, health, housing,

    community safety and f ire and rescue services means

    that we have a unique perspective. We promote value for

    money for taxpayers, audit ing the 200 bill ion spent by

    11,000 local publ ic bodies.

    As a force for improvement, we work in partnership

    to assess local public services and make practical

    recommendations for promoting a better quality of life

    for local people.

  • 7/30/2019 Strategic council housing plans in London boroughs

    3/43

    Contents

    Local authority housing inspections ...............................................................2Summary.............................................................................................................3Scoring the service............................................................................................5Recommendations .............................................................................................8Report ...............................................................................................................12

    Context .......................................................................................................12Vision and strategic approach: how effectively do the Council and itspartners strategically plan work to balance the housing market anddevelop sustainable communities?.............................................................14Capacity to deliver: does the Council have the capacity to deliver itshousing vision effectively now and in the future? .......................................22Improving housing outcomes for the local community: is the strategicapproach to housing delivering better outcomes for the local community? 31

    Appendix 1 Performance indicators.............................................................. 39Appendix 2 Reali ty checks undertaken ........................................................40

    Audi t Commission Strategic housing services 1

  • 7/30/2019 Strategic council housing plans in London boroughs

    4/43

    Local authority housing inspections

    The Audit Commission is an independent body responsible for ensuring that

    public money is spent economically, efficiently and effectively and delivers

    high quality local services for the public.

    Within the Audit Commission, the Housing Inspectorate inspects and

    monitors the performance of a number of bodies and services. These

    include local authority housing departments, local authorities administering

    Supporting People programmes, arms length management organisations

    and housing associations. Our key lines of enquiry (KLOE) set out the main

    issues which we consider when forming our judgements on the quality of

    services. The KLOE can be found on the Audit Commissions website at

    www.audit-commission.gov.uk/housing.

    This inspection has been carried out by the Housing Inspectorate using

    powers under section 10 of the Local Government Act 1999 and is in line

    with the Audit Commissions strategic regulation principles. In broad terms,

    these principles look to minimise the burden of regulation while maximising

    its impact. To meet these principles this inspection:

    is proportionate to risk and the performance of the Council;

    judges the quality of the service for service users and the value for

    money of the service; promotes further improvements in the service; and

    has cost no more than is necessary to safeguard the public interest.

    Audi t Commission Strategic housing services 2

    http://www.audit-commission.gov.uk/housinghttp://www.audit-commission.gov.uk/housing
  • 7/30/2019 Strategic council housing plans in London boroughs

    5/43

    Summary

    1 We have assessed the London Borough of Barking and Dagenham's

    strategic housing service to be a fair, one-star service which has promising

    prospects for improvement.

    2 The Council's ambitions for housing are central to its wider vision for

    regeneration of the borough and this is reflected well across its strategies

    and plans. The Council has become only the fifth of 33 London authorities to

    adopt its core strategy for future development, the housing elements of

    which are informed by a sound understanding of the local housing market.

    There is a strong focus on quality and sustainability in new housing

    schemes and maximising the number of affordable homes built. i

    Improvements to existing council housing take account of both the internal

    and external environment in which residents live. To support housing's key

    role in improving the lives of local people, the Council has re-directed some

    resources for new and existing housing initiatives.

    3 However, the Council has not always consulted its partners and the

    community on all aspects of delivering its vision. There are some key gaps

    in its strategic policy framework and in how well it shares data and makes

    use of stock condition information on existing housing. Its approach to

    meeting the diverse needs of the community and ensuring value for moneyin the service is underdeveloped. The Council has made limited progress in

    enabling the number of new homes which are needed and in improving the

    condition of Council and private sector housing in the borough. It provides

    limited customer information on strategic housing services as a whole. The

    adaptations and disabled facilities grants' service lacks customer focus.

    4 A number of factors will support further improvement. Officers and

    members champion the role of housing effectively. The Council's ability to

    deliver its housing priorities has been enhanced by its housing plans which

    are clearly aligned to current and emerging regional policy frameworks,

    providing a strong framework for sustainable growth. Leadership of the

    service has improved significantly over the last two years, supporting a clear

    focus on ensuring the right capacity to deliver improvement. The Council is

    self-aware, strives to overcome potential barriers and is open to new ways

    of working to maintain the momentum for improvement. Over the next

    20 years, projections for new housing and the land available for

    development offer scope for the Council to significantly exceed its new build

    targets.

    i as a proportion of all new homes developed, on schemes where this is

    viable

    Audi t Commission Strategic housing services 3

  • 7/30/2019 Strategic council housing plans in London boroughs

    6/43

    5 However, there are some barriers to improvement. The views of the

    Council's partners are not always sought and understood and partnership

    outcomes are not maximised. There are internal and external perceptions of

    political resistance to considering some future options for improvement.

    There are still significant gaps in the Council's performance management

    framework and it has not yet finalised robust investment or riskmanagement plans. Some barriers to improvement are also outside the

    Council's control. In particular, current uncertainty over future funding and

    investment decisions mean it cannot be sure of the level of future resources

    to deliver its aims. The national economic conditions are also hampering its

    ability to attract development partners in an already challenging local

    housing market.

    Audi t Commission Strategic housing services 4

  • 7/30/2019 Strategic council housing plans in London boroughs

    7/43

    Scoring the service

    6 We have assessed the London Borough of Barking and Dagenham as

    providing a fair, one-star strategic housing service that has promising

    prospects for improvement. Our judgements are based on the evidence

    obtained during the inspection and are outlined below.

    Figure 1: Scoring chart i

    Prospects for improvement?

    Excellent

    Promising Uncertain

    Poor

    A good

    service?

    Poor Fair

    Good

    Excellent

    a fair service that has

    promising prospects

    for improvement

    Source: Audit Commission

    7 We found the service to be fair because it has a number of strengths,

    including:

    an ambitious vision for housing is at the forefront of regenerating the

    borough and promoting sustainability. This is reflected well across key

    strategies and plans;

    a sound core strategy, informed by a strong understanding of the local

    housing market, is informing the strategic approach;

    community and environmental sustainability of new development is

    supported by robust planning guidance and 'building for life'assessments;

    affordable housing is maximisedii with a focus on social rented housing

    for families, supporting a more effective balance in the housing market;

    in some key areas, such as new build space standards and council

    house improvements, the Council is focussing well on quality outcomes

    for customers;

    i the scoring chart displays performance in two dimensions. The horizontal

    axis shows how good the service or function is now, on a scale ranging

    from no stars for a service that is poor (at the left-hand end) to three stars

    for an excellent service (right-hand end). The vertical axis shows theimprovement prospects of the service, also on a four-point scale.

    ii as a proportion of the new housing developed on individual schemes,

    where this is viable

    Audi t Commission Strategic housing services 5

  • 7/30/2019 Strategic council housing plans in London boroughs

    8/43

    new housing is well designed and sustainable; and

    resources have been re-directed towards key housing priorities.

    8 However, there are also a number of areas which require improvement.

    These include:

    some weaknesses in how effectively partners and the community are

    consulted; gaps in the strategic policy framework and in the robustness and

    effective use of stock condition information to help target resources

    effectively;

    an inconsistent approach to sharing intelligence and data with others;

    limited clarity on how the needs of the borough's diverse community will

    be met and weak arrangements to measure progress;

    the Council's vision for private sector housing is not reflected in its

    sustainable communities strategy;

    limited progress in enabling the development of sufficient new homes to

    meet local needs and in improving the quality of existing private sectorand council homes;

    emerging progress in aspects of the private sector housing service are

    balanced against significant areas which still need improvement;

    a lack of customer focus, partnership working and effective

    management of the adaptations and disabled facilities' grants services;

    limited customer information on the services and assistance available;

    and

    an underdeveloped approach to value for money and maximising

    resources.

    9 The service has promising prospects for improvement because

    strengths outweigh its weaknesses. These include:

    housing is a key strategic priority for the Council, which it champions in

    regional and sub-regional forums;

    strategic housing proposals are closely aligned with regional priorities,

    helping to maximise the potential for an increasing share of future

    regional capital resources;

    leadership of the service has improved significantly over the past two

    years;

    the Council has a strong focus on building the right capacity to deliverits housing priorities. Proposals for its future structure are seeking to

    maximise this;

    a pragmatic approach to developing new ways of working will help the

    Council maximise the potential for improvements to be achieved;

    momentum is maintained through an open approach to new ideas and

    initiatives and a focus on identifying solutions and overcoming barriers;

    self-awareness is strong. The Council clearly understands the

    challenges it faces in future and the key strengths and weaknesses of

    its current service;

    the Council's local development framework and core strategy provide arobust strategic framework for sustainable growth; and

    Audi t Commission Strategic housing services 6

  • 7/30/2019 Strategic council housing plans in London boroughs

    9/43

    projections for new housing over the next five years exceed target

    levels, with sufficient land identified to achieve the Council's targets over

    the next 20 years.i

    However, there are a number of barriers to improvement. These include:

    some weaknesses in ensuring the views of all local partners and the

    community are sought and understood and in maximising partnershipworking;

    internal and external perceptions of some political resistance to

    alternatives to Council led delivery of housing initiatives and housing

    stock management;

    significant gaps and weaknesses in the performance management

    framework;

    plans for improving the adaptations services which have not been

    subject to consultation or challenge and lack improved customer focus;

    future investment plans are not yet finalised and actions and alternative

    options to mitigate known risks are not well developed; inconsistent arrangements for learning to help improve the service; and

    uncertainty over investment decisions which are outside the Council's

    control. In particular, the future council housing funding framework and

    regional infrastructure funding which is critical for major regeneration

    schemes to proceed. National economic conditions have also

    exacerbated an already challenging local housing market.

    i subject to regional investment in the infrastructure required to enable key

    regeneration projects to proceed

    Audi t Commission Strategic housing services 7

  • 7/30/2019 Strategic council housing plans in London boroughs

    10/43

    Recommendations

    10 To rise to the challenge of continuous improvement, organisations need

    inspection reports that offer practical pointers for improvement. Our

    recommendations identify the expected benefits for both local people and

    the organisation. In addition, we identify the approximate costsi and indicate

    the priority we place on each recommendation and key dates for delivering

    these where they are considered appropriate. In this context, the inspection

    team recommends that the Council shares the findings of this report with

    residents and councillors; and takes action to address all weaknesses

    identified in the report. The inspection team makes the following

    recommendations.

    Recommendation

    R1 Strengthen the approach to developing and delivering the housing

    vision and strategic priorities, by:

    improving consultation to ensure the views of partners and the

    community more effectively inform future priorities and proposals;

    addressing weaknesses in sharing intelligence and data with

    partners;

    ensuring new and refreshed strategies and plans are more

    robust, for example, by integrating outcome milestones, diversity,

    value for money, risk and housing's contribution to quality of life

    measures more clearly;

    completing a comprehensive investment plan for the service,

    which includes risk modelling as part of strategic plans; and

    reviewing the sustainable communities' strategy to more clearly

    reflect all aspects of the vision for sustainable housing within the

    borough.

    The expected benefit of this recommendation is:

    a more robust strategic approach across the service which is fully

    informed by the views of the Council's partners and residents and more

    clearly demonstrates quality of life aspirations and outcomes for local

    people.

    The implementation of this recommendation will have high impact with low

    costs. It should be implemented by March 2011.

    i low cost is defined as less than 1 per cent of the annual service cost,

    medium cost is between 1 and 5 per cent and high cost is over

    5 per cent

    Audi t Commission Strategic housing services 8

  • 7/30/2019 Strategic council housing plans in London boroughs

    11/43

    Recommendation

    R2 Improve outcomes for local people, including the most vulnerable, by:

    improving the quality and accessibility of customer information to

    ensure it is widely available and effectively targeted;

    addressing the highlighted weaknesses in the private sectorhousing service to ensure a more proactive service is provided in

    line with best practice;

    revisiting the adaptations service review to ensure this addresses

    the needs of vulnerable service users, from enquiry through to

    completion of works, and reflects good practice within the housing

    and health sectors; and

    using service user feedback comprehensively, to inform

    improvements.

    The expected benefit of this recommendation is:

    easily accessible services which better support those most in need.

    The implementation of this recommendation will have high impact with low

    costs. This should be implemented by March 2011.

    Recommendation

    R3 Better ensure the service meets the diverse needs of the community

    by:

    increasing awareness of variations in the community profile indifferent parts of the service, such as in private sector rented

    housing;

    integrating better diversity information into strategies and plans to

    show current successes, what gaps exist and how these will be

    addressed to meet the varying needs of different community

    groups;

    addressing the gaps and weaknesses in equality impact

    assessments to maximise their potential for supporting and

    measuring improvements; and

    incorporating diversity indicators into the performance

    management framework.

    The expected benefit of this recommendation is:

    greater clarity in the strategic approach to meeting the needs of the

    community and better ability to measure and adapt services in response

    to outcomes.

    The implementation of this recommendation will have high impact with low

    to medium costs. This should be implemented by March 2011.

    Audi t Commission Strategic housing services 9

  • 7/30/2019 Strategic council housing plans in London boroughs

    12/43

    Recommendation

    R4 Improve the focus on value for money (VFM) within the service by:

    developing a VFM and procurement framework for the strategic

    housing service that supports, and is supported by, the corporate

    approach;

    prioritising a review of internal recharges to the service;

    including efficiency targets in the service's performance

    management framework;

    routinely measuring the VFM-related impact of services and

    initiatives;

    benchmarking cost, performance and quality indicators to identify

    areas for review and improvement; and

    identifying internal and external resource opportunities (financial

    and partners) within strategies and plans to ensure these are

    maximised.

    The expected benefit of this recommendation is:

    a more structured approach to improving value for money, with more

    potential for an increased level of efficiency savings to re-invest in

    service delivery.

    The implementation of this recommendation will have high impact with low

    costs. This should be implemented by March 2011.

    Recommendation

    R5 Strengthen management of performance by:

    developing a refreshed performance management framework for

    the service which addresses the weaknesses highlighted in this

    report;

    identifying key milestones, focusing on sustainability and quality

    of life outcomes for the community and incorporating these into

    the strategic planning framework;

    ensuring that robust risk management arrangements are part ofthe framework,

    developing a scrutiny programme to review key aspects of the

    service and challenge risk management within strategic plans;

    and

    implementing a more systematic approach to learning from

    service users and the service's own experience.

    The expected benefit of this recommendation is:

    a stronger performance management framework which helps maximise

    the scope for improvement.

    The implementation of this recommendation will have high impact with low

    costs. This should be implemented by March 2011.

    Audi t Commission Strategic housing services 10

  • 7/30/2019 Strategic council housing plans in London boroughs

    13/43

  • 7/30/2019 Strategic council housing plans in London boroughs

    14/43

    Report

    Context

    The locality i

    12 The London Borough of Barking and Dagenham is a small outer London

    borough situated in the east of London. It is one of the most industrial parts

    of the capital, being home to the large Ford Motors car plant in Dagenham

    for over 80 years. However, large scale heavy industry has declined in the

    area to be replaced by smaller service industries and manufacturing units.

    13 The borough has a population of around 166,900 people, which isgrowing at a rate that is one of the fastest in England. It has above average

    levels of both children and older people. At around 24.9 per cent, the

    borough has fewer people from minority ethnic backgrounds than the

    London averageii , although this is growing rapidly, as more people move

    into the borough. This remains a sensitive local issue, with some groups

    such as the British National Party, actively campaigning in the area.

    14 The borough is the 11th most deprived area in England and 6th most

    deprived of the 33 London boroughs. Of its 17 wards, 14 are among the

    poorest in the country. ii i Educational attainment of adults in the borough is

    comparatively low and though the level of test results and qualifications for

    children at school are better, they are not strong.iv Unemployment is higher

    than the London average, while average household incomes and wage

    levels are among the lowest in the capital.v Despite relatively low house

    prices and rentsvi , affordable housing is a key issue for many people

    locally.

    i data from 'Our Borough' and 'Key statistics' (January 2010) published bythe LBBD partnership, except where stated below

    ii outer London: 29.31 per cent and London (region): 35.69 per cent

    respectively. Figures relate to people classifying themselves as

    'non-white' (not White: British; White: Irish or White:Other). Office for

    national statistics, 2007-mid year estimates

    ii i five wards are in the 10 per cent most deprived in the country, the other

    nine in the 20 per cent most deprived.

    iv the level of adults with no qualifications is almost double the London

    average, while those with degree or equivalent qualifications are the

    lowest in London. School examination and test results are just under the

    national average.v c26,000 average income. Gross weekly wage of full time employees:

    498.50 compared to 580.80 for London

    vi typically around 25 per cent lower than London as a whole

    Audi t Commission Strategic housing services 12

  • 7/30/2019 Strategic council housing plans in London boroughs

    15/43

    15 A significant proportion of housing in the borough originates from

    council built housing estates, many of which were built in the 1920s.

    However, two-thirds of homes (68 per cent) are in the private sector, most of

    which are owner occupied (58 per cent). The remaining properties are

    mostly Council housing (28 per cent), with housing associations (RSLs)

    managing relatively little stock (4 per cent). Since 2001, the number ofCouncil homes has declined rapidly as a result of the right to buy, while

    private rented housing has almost doubled from 5.2 to 10 per cent of

    housing in the area. i

    The Council and the service

    16 Barking and Dagenham Council is one of 33 London authorities. It

    comprises 51 elected members, all Labour Councillors. The ruling party has

    had a majority in the borough since 1964, but the single party composition

    of councillors dates from the May 2010 local elections, when the Labour

    party gained the 19 seats previously held by other groups. These included

    12 seats previously held by the British National Party, which had until then

    been the official opposition on the Council.

    17 The London Borough of Barking and Dagenham is still a 'stock-holding'

    housing authority. This means it has responsibility for both the 'landlord

    service' to its 19,400 tenants and its statutory strategic housing role for the

    borough as a whole.

    18 The strategic housing service is part of the customer services

    directorate of the Council. It reports to the housing portfolio holder, who is a

    member of the cabinet, with a living and working board in place to provide

    scrutiny of policy and performance.

    19 Regeneration of large parts of the borough is planned or underway to

    promote healthy living and economic renewal. This includes the south of the

    borough, which is within the London Riverside area of the Thames Gateway

    Regeneration Programme, one of the major development sites in the

    capital. The Council's plans for regeneration include a considerable

    increase in new housing over the next 25 years, in areas such as Barking

    and Dagenham town centres and the Barking Riverside and Dagenham

    South areas. However, the medium to long term viability of many parts ofthese plans is heavily dependant on infrastructure investment by regional

    agencies, such as Transport for London, which is currently uncertain.

    20 Land values in the borough are relatively low, but the cost of developing

    new housing is similar to neighbouring boroughs. This makes it more

    difficult to attract developers and other partners, as the financial viability of

    development sites is often limited. This has become a more significant

    challenge in the current economic climate.

    i 2009 private sector stock condition report data compared to 2001 censusdata in the LBBD partnership key statistics. Most council house sales in

    this period were prior to 2008, as sale levels fell sharply thereafter, due to

    the recession

    Audi t Commission Strategic housing services 13

  • 7/30/2019 Strategic council housing plans in London boroughs

    16/43

    21 Between 2007 and 2010, the Council worked up plans for new housing

    supply and improvement delivery arrangements for the borough, after being

    selected by the government as one of only 14 authorities to pilot a 'local

    housing company' initiative. However, this project and other pilots nationally

    have not received the investment approval they need from the Homes and

    Communities Agency (HCA)i to make them viable. In 2008, the Council was

    also unsuccessful in bidding for additional resources through the private

    finance initiative (pfi) to support estate renewal of several blocks of council

    housing, where demolition and renewal is the most viable option.

    22 This inspection focuses on key aspects of the Council's strategic

    housing service: its roles in setting a strategic framework for housing in the

    borough; in enabling new housing provision; and in making the best use of

    existing private sector housing, including its approach to adaptations and

    disabled facilities grants. We also inspected its strategic approach to

    improving council owned homes. However, we did not look at its

    homelessness and housing advice services or the effectiveness of itssupported housing provision in the borough.

    Vision and strategic approach: how effectively do theCouncil and its partners strategically plan work tobalance the housing market and develop sustainablecommunities?

    Is there an overarching and shared vision for housing which supports

    wider ambitions for the community and is it championed effectively?

    23 This is an area where the Council is performing adequately. It has an

    ambitious vision for the regeneration of the borough, in which housing plays

    a defining role. Housing has a strong internal profile and it is championed

    well externally. Strategic plans are aligned to regional priorities,

    demonstrating how they contribute to key objectives for London as a whole.

    However, the Council is yet to ensure that its vision is shared by all key

    partners and that it is well translated into a clear strategic framework. Some

    key outcomes for local residents are not clearly articulated or integrated in

    strategies and monitoring frameworks.

    24 The Council's vision for housing shows clear ambition, with housing

    seen as central to the achievement of the borough's wider objectives.

    Housing and education form the two key components of the Council's

    ambitions to regenerate the borough and improve the life prospects of the

    community. They are cornerstones of the six prioritiesii within the borough

    sustainable community strategy (SCS) and council corporate plan. They are

    also well reflected in ambitious proposals to improve the health and wealth

    of residents, such as the Council's key long term regeneration project to

    i Homes and Communities Agency a national agency which provides

    government funding for affordable housingii local strategic priorities in the SCS and corporate plan are safe, clean,

    fair and respectful, prosperous and healthy and inspired and successful

    young people.

    Audi t Commission Strategic housing services 14

  • 7/30/2019 Strategic council housing plans in London boroughs

    17/43

    transform Barking Riversidei from a derelict industrial site to the largest

    housing development in the country. Housing is at the forefront of future

    objectives.

    25 The Council's focus on housing as a priority area is informed by a clear

    understanding of the challenges it faces in balancing the housing market

    and creating sustainable communities. This has led to a strong 'read across'between key strategies, policies and wider regeneration initiatives: all are

    inter-dependant and support the same high level objectives. There is also a

    strong recognition that the local context requires a sustained focus on

    providing the right housing mix to improve choices for low income

    households and support the borough's attraction to, and retention of, more

    affluent people. This understanding has ensured that the LDF ii and core

    strategy provide effective responses to these challenges, with plans for

    affordable and market housing integrated into wider regeneration and

    renewal ambitions.

    26 Political support for improving housing outcomes is strong. Councillors

    are considering a reduction in the number of strategic objectives, but

    improving the quality and supply of housing remains a clear priority. The

    housing portfolio holder and service steering groups ii i have maintained the

    services' high profile and actively informed cabinet discussions. As a result

    the cabinet has recently made some key decisions, including

    re-prioritising its capital programme to support a higher level of housing

    investment to pay for the redevelopment of large estates of council housing.

    27 The Council is proactively championing the borough's role in meeting

    regional housing needs. Its plans are aligned with current and future

    proposals for the region, including an increased focus on the delivery of

    socially rented, family sized homes. Key staff and members play an active

    role in liaising with a range of agencies in London, such as the GLA, LDA

    and LTGDCiv , and this has ensured support in developing its core strategy.

    It is now developing a marketing strategy around this, to ensure a more

    systematic approach and maximise opportunities for promoting its role. This

    is crucial given increased regional competition for reducing resources.

    Potential government changes in the investment roles of the London

    Mayor's office could release extra resources but only where a borough's

    proposals are seen to best match regional priorities.

    i plans include the development of nearly 11,000 new homes combined

    with new education, community and transport infrastructure, linked to

    employment and environmental initiatives for Barking Riverside and

    adjacent existing housing.

    ii Local Development Framework: a collection of policies which outlines

    how development will be managed in an area and which must be subject

    to significant consultation by local people.

    ii i development and private sector steering groups, where key councilmembers and officers discuss key policy issues

    iv Greater London Authority, London Development Authority and London

    Thames Gateway Development Corporation

    Audi t Commission Strategic housing services 15

  • 7/30/2019 Strategic council housing plans in London boroughs

    18/43

    28 The Council has taken positive steps to support delivery of its vision.

    For example, it became one of 14 authorities in the country to be approved

    to pilot a local housing company initiative. More recently it re-prioritised its

    capital spending programme to provide resources to kick start estate

    renewal in key council housing estates. The housing team in the borough is

    relatively small so decisions like these require a significant commitment of

    staff and financial resources. With few objections to new development, the

    Council has not needed to make difficult decisions in light of local opposition

    to development plans. However, it is clearly prepared to make tough

    choices about resources to support housing as a priority.

    29 The Council has not yet achieved a consensus of understanding and a

    shared vision of how its housing aims can be delivered. The Council's key

    development and regeneration partners widely support its overall objectives,

    but they have not all been actively involved in shaping its related strategy

    and policies. This is partly because until recently the Council has been

    heavily focused on 'internal' proposals such as the local housing company(LHC) initiative. It has more to do to fully understand what current and

    potential partners want and need. This is particularly important because the

    borough will need to compete with neighbouring areas that may seem more

    attractive locations to some investors. Effective dialogue will be crucial to

    ensure long term buy in from partners and achieve better housing

    outcomes.

    30 Some key outcomes for local residents are not clearly articulated or

    integrated in strategies and monitoring frameworks. For example, diversity

    is recognised as important, but there is little clarity about what the range of

    diverse housing needs are, how these will be met or how progress will be

    measured. Additionally, the current SCS and local area agreement (LAA)

    targets are limitedi , so do not reflect the importance of private sector

    housing to both housing supply and quality outcomes, an issue now

    recognised by the Council. The contribution housing makes to community

    sustainability and to the quality of life of residents is also underdeveloped in

    strategic goals and monitoring frameworks. These gaps make it hard for the

    Council to be sure that housing outcomes are being maximised.

    How effectively is partnership work ing and community consultationshaping and supporting delivery of the strategic approach to housing?

    31 The Council is performing adequately in this area. It is working well with

    key strategic partners to align its plans with regional policy and has

    undertaken wide community consultation on its planning frameworks and

    major development schemes. However, its consultation arrangements, with

    both the community and other partners, are not consistently strong, leading

    to variations in outcomes.

    i focusing only on new housing (total and affordable) and decency levels in

    council homes

    Audi t Commission Strategic housing services 16

  • 7/30/2019 Strategic council housing plans in London boroughs

    19/43

    32 The Council is actively involved in a number of regional and

    sub-regional forums and partnerships to inform and lobby policy makers to

    support its strategic objectives. It works well alongside the key GLA 'family'

    of agencies. Liaison with the Mayor of London's office has resulted in a

    reduction in the borough's proposed London housing plan targets to a level

    the Council considers more realistic. Close working with the health servicehas enabled new health facilities to be recognised within the LDF and

    incorporated into plans for schemes such as Barking Riverside. The Council

    has also worked with Transport for London to ensure, where possible,

    critical infrastructure requirementsi are delivered. Joint working has also

    enabled it to access additional sub-regional resources, such as extra private

    sector grant fundingii , and to take the lead on new initiatives, such as the

    low carbon zone in Barking town centre. ii i This is helping to support the

    Council's housing objectives.

    33 Wide community consultation was undertaken in developing the corestrategy. Various written, verbal and electronic consultation methods have

    been used to seek community views and the Council has dedicated

    community communicators in place to help ensure the range of methods

    reflects the diverse community. This includes different ways to attract the

    views of minority groups and use of support agencies, faith groups and

    networks in the borough to help maximise the opportunities for people to get

    involved. The Council has faced little opposition to its proposals, with the

    borough becoming only the fifth of 33 authorities in London to have adopted

    its core strategy.

    34 Effective arrangements are also in place to plan consultation on major

    schemes. The Council invites members of the Council's residents' urban

    design forumiv to review and assess planning design in major schemes

    such as Barking Riverside, with feedback given to architects and planners.

    There is also a pre-application process for major schemes which allows land

    owners and their agents to informally discuss their proposals and plans with

    council officers before formal applications are made. These arrangements

    help support the planning process. There has so far been no major

    opposition to any submitted planning applications.

    35 Consultation on the strategic direction of some service areas isunderdeveloped. For example, the Council has only just re-started a private

    i a number of decisions on infrastructure investment, which hold the key to

    whether new housing can be delivered on the major schemes at Barking

    Riverside and Dagenham South from 2015 onwards, are currently on

    hold.

    ii 140,000 to help reduce the level of category 1 health and safety rating

    system hazards

    ii i an initiative to reduce carbon emissions by 20.12 per cent by 2020

    through support and assistance to residents, businesses, community

    groups and schools and for residents, to help reduce fuel poverty (thoughno targets for this are defined)

    iv six members of the Council's citizens panel, who have received training

    in design issues, who meet every two months

    Audi t Commission Strategic housing services 17

  • 7/30/2019 Strategic council housing plans in London boroughs

    20/43

    sector housing landlords (PSH) forum and little innovation has been used to

    consult partners, landlords or residents on its draft PSH strategy, with those

    landlords we contacted unaware of the process. No consultation has taken

    place about the adaptations service, either internallyi or with the home

    improvement agencyii (HIA) and residents. This is despite the Council now

    considering an options paper on future service delivery. In addition, while

    council tenants have significant influence on the details of individual scheme

    improvements where they live, they have so far had little involvement in the

    significant changes made to the strategic approach to asset management or

    development of the new draft strategy related to this. In some key areas,

    partners and residents have not had effective opportunity to influence the

    strategic direction and delivery of the service.

    36 The Council has not yet made the most of what RSL partners could

    offer. It has worked well with some individual RSLs on specific schemes, but

    only where these are on private land. Strategically it has lacked effective

    engagement to make sure it knows what these key partners want or needon a more collective basis. Input has been limited by the lack of effective

    housing partner forumsii i to influence housing matters. The Council is not

    ensuring it has a full range of views to inform its decisions and to make the

    most of resources which may be available.

    37 Inconsistent levels of partnership working have led to varying service

    outcomes. For example, the Council has worked very closely with its

    framework contractors to re-model improvement programmes in light of

    resources being less than anticipated. This has maintained relationships

    which could have become strained as the contractors' expected income wasreduced. However, the Council's adult and community services and housing

    sections have not worked well together on adaptation services and there

    has been no consultation with the HIA. This has resulted in a lack of shared

    responsibility at the Council and missed opportunities to maximise funding

    and improve the service for customers. The Council cannot demonstrate

    partnership arrangements are always maximised.

    Is there an up-to-date understanding of the housing market and

    housing conditions, socio-economic data and the broader policy

    context which informs the housing vision and strategic decisionmaking?

    38 The Council is performing below minimum requirements in this area. It

    works well in some ways with partners and stakeholders to share

    intelligence, but in other areas its approach is weak. Its understanding and

    i adaptations and disabled facilities grants are managed by the adult and

    community services section of the Council on behalf of the housing

    service

    ii a local agency which provides help and support to residents making

    applications for disabled facilities grantsii i for example, a previous RSL forum, which has not met for ten months

    was ineffective and the Council has instead relied on discussions with

    individual RSLs to communicate its plans

    Audi t Commission Strategic housing services 18

  • 7/30/2019 Strategic council housing plans in London boroughs

    21/43

    use of stock condition information is limited and information on the diverse

    needs of local people is not well identified within its strategic plans and

    targets. However, it does have a good understanding of the local housing

    market and has undertaken a robust assessment of future land availability.

    39 The effectiveness of the Council in sharing and challenging data is

    mixed. It has worked with local strategic partners to share their intelligencearound future infrastructure needs for its development proposals around

    education, health and transport, for example. However, data is not shared

    with members in a meaningful way and limited comparison and sub-regional

    data is shared with other Councils. The current status of the Council's

    strategies and the absence of effective partner forums for the service mean

    there is also little scope for wider data to be shared and its assumptions to

    be challenged. This means the Council is not maximising the level and

    robustness of the data available to enhance its strategic approach.

    40 The robustness and use of stock condition information is

    underdeveloped. Stock condition data for the Council's own stock is

    outdated and a new survey is now underway. A report last yeari identified

    problems with the reliability of the survey undertaken in 2005, concluding

    that it was impossible to accurately forecast investment requirements. The

    new survey could therefore make markedly different projections of the levels

    of current and future component failureii and investment required. In

    relation to the private sector stock, the Council's first stock condition survey

    was completed in September 2009. This has given the Council a good

    understanding of housing conditions in the sector and future needs for

    investment. It plans to integrate details from both surveys in the respectivestrategiesii i as these are finalised. However, it currently lacks any asset

    management tools to manipulate and model the findings, while data from

    other initiatives, such as energy efficiency schemes, is collected but not

    analysed on a strategic basis. So far the Council has not had up-to-date

    information or a sophisticated approach to identifying and targeting its

    resources.

    41 Socio-economic data is not effectively translated to inform the Council's

    strategic objectives. The Council has a good high level understanding of the

    demographic and economic make up of the community, but this has not led

    to targets or strategic milestones being put in place or measured.iv More

    specific data on the individual needs of different community groups and

    diversity strands are not well developed and little outcome information is

    captured to ensure progress can be measured and policies amended. The

    i stock condition data report (undated)

    ii initial soundings from surveys so far suggest current data is not

    extensively different from actual conditions, but changes in expected

    standards and renewal rather than repair will significantly increase

    required investment

    ii i asset management and private sector housing strategies, which arecurrently being developed

    iv the annual monitoring report includes some targets, but these are not

    routinely monitored or revisited through the year

    Audi t Commission Strategic housing services 19

  • 7/30/2019 Strategic council housing plans in London boroughs

    22/43

    Council is not robust in ensuring its policies and plans meet the needs of

    everyone in the community.

    42 The Council has a good understanding of the local housing market. In

    comparison with neighbouring boroughs, land costs are lower but

    development costs similar. This has been exacerbated by the national

    economic situation and often makes new housing difficult to justify infinancial terms. The Council commissioned a joint strategic housing market

    assessment with other east London authorities and received the draft report

    this summer. The reports findings build upon the outcomes from the

    Councils own 2005 housing needs study and have influenced its current

    thinking. A new housing needs survey is being undertaken this Autumn and

    the results will feed into a new Housing Strategy, planned for publication in

    early 2011. In the meantime the Council has a good awareness of changing

    prices and shifts in social housing demand. A good understanding of local

    housing market conditions is important in making sure strategies and plans

    address identified housing needs.

    43 The Council has a clear understanding of future land availability for new

    housing in the borough. A strategic assessment has been undertaken which

    identified sufficient land to provide the housing required under the London

    housing plan targets and its core strategy until 2023/24. This has enabled it

    to seek developer interest in sites such as Fresh Wharf, where planning

    permission has been granted, and Abbey Retail Park, where a planning

    application is anticipated. These sorts of sites will provide some of the more

    significant levels of developmenti in the borough until infrastructure funding

    gaps at larger regeneration schemes have been resolved.

    Are there robust housing and planning strategies and policies which

    support the delivery of housing priorities?

    44 This is an area where the Council's performance is adequate. Its overall

    housing plans and individual scheme proposals clearly identify how they

    meet both the borough's and wider regional aims. The core strategy is

    robust and community sustainability is supported by a range of planning

    advice, which also helps to balance the type of housing provided in new

    schemes against local needs. However, the strategic framework for

    delivering outcomes across the service is currently underdeveloped and the

    Council's approach to equality impact assessments is not yet robust.

    45 The Council's overall strategic approach to future development is

    effectively aligned with sub-regional and regional policy frameworks and

    opportunities. Its alignment with regional policy has been reflected in the

    core strategy and local development framework (LDF). At the same time,

    individual scheme plans systematically draw out common themes both in

    relation to housing and wider regeneration delivery. For example,

    regeneration plans for Dagenham South and Barking Riverside highlight the

    potential for providing large, sustainable, family housing along with neweducational and community facilities, while plans for Barking town centre

    i the planned number of homes at Fresh Wharf and Abbey Retail Park

    over the next five years, is 300 and 500 respectively

    Audi t Commission Strategic housing services 20

  • 7/30/2019 Strategic council housing plans in London boroughs

    23/43

    link housing development to the regeneration of the retail centre and

    associated infrastructure. This aims to maximise support for the borough's

    proposals and attract greater investment to support its plans.

    46 Development of new homes is supported by a robust core strategy

    which, after public examination, has now been adopted. The strategy

    received support from the key London agencies and was non-controversiallocally as plans mainly relate to development sites which are remote from

    existing housing, have been planned for many years and will enhance

    community and open space facilities. They include the provision of schools,

    health and other community facilities, while other LDF documents include

    the Councils policies on space standards, sustainable construction and

    design. All newly built homes have to meet lifetime homes and sustainability

    standards. Planning policies provide a strategy for sustainable growth,

    subject to the provision of the required social infrastructure.

    47 Sustainability of new housing developments is supported by a range of

    planning advice notes. Guidance is provided on sustainable construction,

    waste and recycling and crime prevention. The Council's detailed advice

    note on 'green roofs' won a commendation from the Royal Town Planning

    Institute and has led to this feature being incorporated into designs for a

    number of public buildings in the Barking Riverside scheme. The borough

    also has two qualified 'building for life' assessors who have undertaken

    assessments on all major schemes since 2008, linked to its commitment to

    ensuring better life opportunities through regeneration. The Council is

    incorporating environmental and community sustainability as a strong

    feature of scheme design through clear planning criteria.

    48 Planning guidance also supports the Council's priority to ensure the

    right balance between market and affordable housing. Its targets to

    maximise affordable housing provision and the split between housing for

    social rent and intermediate market sale are consistent with the London

    housing plan.i This, and design requirements, are clearly set out in a

    specific planning advice note. This highlights the Council's commitment to

    deliver the maximum amount of affordable, family sized housing in the

    borough, but also offers pragmatism and flexibility so that individual

    schemes can be assessed on their own merits.

    49 However, there are weaknesses in the current housing strategies and

    policies which provide the framework for strategic housing service delivery:

    renewal of the Council's now expired housing strategy has not yet

    started;

    the Council's first private sector housing strategy is only at first draft

    stage. Sub strategies and policies related to empty homes, affordable

    warmth and houses in multiple occupation are basic or still in draft form;

    and

    work has begun on addressing the lack of a robust asset management

    strategy in relation to the Council's own housing stock but is some wayfrom completion.

    i the council aims for 50 per cent of new housing to be affordable where

    this is financially viable, in a 70:30 rented:sale ratio

    Audi t Commission Strategic housing services 21

  • 7/30/2019 Strategic council housing plans in London boroughs

    24/43

    50 While the Council has plans to address these gaps, its timescales for

    doing so are very challenging because a number of factors need to come

    together to make this happen. These are both external such as the

    Government's review of the housing revenue account funding arrangements

    and further internal work, including the completion and analysis of the

    housing needs survey and stock condition data, plus consultation with

    stakeholders, which is only underway so far on the private sector housing

    strategy. In each of the current strategies the Council lacks clarity on how

    the plans contribute to its overall aims, clear milestones to support delivery

    and the outcomes expected in relation to diversity and value for money.

    They also do not adequately address how future funding risksi will be

    managed. Current strategic documents do not therefore provide a robust

    framework to demonstrate what needs to change, how this will happen or

    how the Council will measure its success towards its stated aims.

    51 Limited outcomes have been achieved through the Council's approach

    to equality impact assessments (EIAs). They have been undertaken onsome key strategies and are self-critical, which has led to some

    improvements, such as better translation arrangements for key documents.

    However little has been measured in part because of a lack of baseline

    data. Consultation to assess the impact of service delivery or whether new

    or improved homes address the range of diverse needs in the community

    has been limited. No EIAs have been undertaken in relation to council

    house improvements or the adaptations service. At present EIAs do not

    provide a robust assessment of the service's contribution to improving

    equality and community cohesion in the borough.

    Capacity to deliver: does the Council have the capacityto deliver its housing vision effectively now and in thefuture?

    Are the right ski lls and tools in place to ensure effective delivery of

    housing priorities?

    52 This is an area where the Council is performing adequately. The

    Council is focussing well on ensuring it has the right skills in place, both for

    now and in a more challenging financial climate. This is supported by astrong approach to maximising the talent of the Council's workforce. It has

    sufficient land to deliver its new housing targets. However, existing staff

    skills to deliver improvement are not consistently strong. Some council

    member development is also needed and the reasons for negative external

    perceptions of political support for some housing options need to be

    explored. Gaps in information technology are being addressed but are

    currently weakening service delivery.

    i key schemes depend on funding provided by other agencies. The

    borough's investment plan is also still in draft

    Audi t Commission Strategic housing services 22

  • 7/30/2019 Strategic council housing plans in London boroughs

    25/43

    53 The Council has a strong focus on ensuring it has the right people to

    deliver its housing priorities. It is currently reviewing its entire structure a

    process which has been brought into sharper focus by the government's

    announcements of reduced revenue funding. Final proposals have not yet

    been agreed, but the Council is seeking to streamline its management

    arrangements and focus on skillset matching to ensure the new structure iswell placed to deliver its strategic objectives. It is focussing on how its

    capacity to deliver its housing plans can be enhanced, to take advantage of

    new ways of working and to better exploit commissioning opportunities.

    54 A positive strategic approach to building and retaining skills is helping to

    boost capacity. The Council has a proactive approach to support staff, with

    comprehensive training and development arrangements aligned to personal

    and organisational development. Support and communication arrangements

    have recently been enhanced in recognition of the impact of the current

    economic climate and the challenging decisions that need to be made

    around future staffing levels. The HR strategy is being renewed next year,

    recognising that new ways of working need to continue to be supported

    through effective people management. Currently soundings are being taken

    with elected staff representatives, ahead of a planned staff survey which will

    inform the strategy focus. This approach helps to maximise people's talents

    and abilities.

    55 The Council has sufficient land available to achieve its short and

    medium term housing development targets. Its strategic land assessment

    shows it has adequate land to provide the housing required under the

    London housing plan targets and its core strategy until 2023/24. Although inthe medium to long term actual housing delivery is reliant on infrastructure

    funding, this reduces the risk that development of new housing will stop

    because suitable sites cannot be found.

    56 Existing capacity to deliver the Council's plans is mixed. The right

    capacity and extensive knowledge, skills and experience exist in some

    areas of the service, such as planning and regeneration, capital programme

    delivery and procurement. Sickness levels are also relatively low. However,

    in some areas such as in housing strategy and private sector housing, staff

    need development to promote greater capacity to improve. Internal jointworking also needs improvement in some areas, though not always for the

    same reason. For example, the relationship between housing and adult and

    community services is poor and so ineffective. In contrast, planning and

    housing strategy staff work well together, but the teams are not co-located

    and a lot of time is spent communicating and checking information between

    the two functions. This increases inefficiency and opportunity costs. The

    Council recognises this and plans to help address these issues through its

    structural proposals. However, current capacity is only optimal in some

    areas of the service.

    Audi t Commission Strategic housing services 23

  • 7/30/2019 Strategic council housing plans in London boroughs

    26/43

    57 Some development of Council member capacity is needed. The large

    turnover of councillors in May 2010 means that there is need to ensure a

    stronger awareness of future policy direction. Although there is some

    understanding of this, there are internal and external perceptions that some

    Councillors remain resistant to alternatives to Council-led delivery of

    housing initiatives and future management of stock. Currently no Councillorsare members of the boards of any RSLs operating in the borough. The

    authority needs to be sure all its Councillors have a realistic understanding

    of how its proposals fit within the emerging policy environment, the range of

    options available and the potentially challenging decisions that might need

    to be made.

    58 The Council is investing in new information technology to address

    significant gaps in current systems. In particular, it is currently working to

    implement new asset management databases for both council and private

    sector housing data, including software to model investment decisions, to

    record action taken and to enable better outcome reporting. These are not

    in place currently, restricting the Council's ability to understand the potential

    and actual impact of its decisions and make more effective use of its

    resources.

    Are effect ive arrangements in place to keep the delivery of housing

    priorities on track and promote a culture of cont inuous improvement?

    59 In this area the Council is performing adequately. Leadership of the

    service is now strong. Senior officers and key elected members have a

    strong awareness of what needs to be achieved and are focussed on findingsolutions and implementing new ways of working to drive forward

    improvements. In some key areas a focus on service quality is delivering

    positive outcomes for customers. However, there are significant

    weaknesses in the performance management of the service overall and in

    the adaptations service for vulnerable people, in particular. Risk

    management and learning are also inconsistent, hindering the Council's

    ability to maximise the improvements it can deliver.

    60 Leadership of the service is now strong. It has improved significantly

    over the past two years, with senior officers and key council members nowhaving a strong awareness of what the service does well and the key areas

    for improvement. At corporate level there is also better understanding of

    how the Council's revised structure and its commissioning ability will support

    the service going forward. Managers are clear about priorities and are

    implementing a systematic approach to improvement as part of current and

    planned activities. This has, for example, already resulted in increased

    private sector housing capacity and plans for better performance

    management. Although current strategies and plans do not fully reflect this,

    the service is led by officers who are proactively responding the challenges

    the service faces.

    Audi t Commission Strategic housing services 24

  • 7/30/2019 Strategic council housing plans in London boroughs

    27/43

    61 Changes in the political make up of the Council have given a fresh

    impetus to leadership, transparency and challenge to policy decisions. The

    change to an unopposed ruling party could have created a vacuum in these

    areas. However, new councillors have constructively challenged policy and

    direction, leading to renewed debate around future housing proposals. This

    has increased capacity for new thinking. The housing portfolio holder alsoshows a strong understanding and commitment to improving the quality and

    supply of housing and achieving greater value for money. The Council's

    commitment to housing has been retained while capacity for exploring better

    ways to achieve its objectives has been increased.

    62 In limited areas performance arrangements are effective. The Council

    closely monitors the forward supply of housing sites, with its annual

    monitoring report highlighted as best practice by the former Government

    Office for London. Close monitoring is also in place for the Council housing

    improvement programme, using a range of financial, quantitative and quality

    indicators to track progress against programme targets. This provides key

    monitoring information for the Council in these areas.

    63 The Council's approach has also ensured customer focussed outcomes

    in some key areas. For example, new council housing is designed to meet

    space standards which significantly exceed minimum requirements and

    more closely reflect emerging thinking by the Mayor's office on providing

    greater living space for families. This is in preference to additional 'units'

    being provided. Similarly, council house improvement schemes have been

    designed with residents and incorporate wider security and environmental

    improvements, for example, ahead of maximising the total number ofimprovements. Though this focus on quality is not applied universally, it

    provides the community with some assurance that the Council is seeking to

    achieve qualitative as well as quantitative outcomes.

    64 Strong leadership has resulted in a focus on finding solutions and

    overcoming barriers. The Council is not put off by significant challenges,

    such as the deferred infrastructure decisions. Instead, planners and

    regeneration officers continue to work closely with developers to achieve

    better outcomes over the long term and to seek alternative options. For

    example, the Council has now developed a new proposal for estate renewalafter failure of its PFI i funding bid. It responded to the failure of the LHC by

    working closely with developers and the HCAii to get funding switched to its

    council house building programme. This will provide the first new council

    housing in the borough for over 20 years, with the first properties, at William

    Street Quarter in Barking, due for completion towards the end of this

    calendar year. This ensures momentum for improvement is not lost when

    things do not go to plan.

    i public finance initiative a former government model for private sectorinvestment in public sector led initiatives

    ii Homes and Communities Agency a national agency which provides

    government funding for affordable housing

    Audi t Commission Strategic housing services 25

  • 7/30/2019 Strategic council housing plans in London boroughs

    28/43

    65 The Council also takes opportunities to lead initiatives in the region. For

    example, it was one of 14 authorities which volunteered for the local

    housing company initiative nationally and has taken a lead on implementing

    a community low carbon zone, with its initiative in Barking Town Centre

    aiming to reduce carbon emissions by 20 per cent and support people in

    fuel poverty. This approach means it is open to new ideas and initiatives to

    help support its objectives.

    66 Going forward, the Council has an emerging pragmatic approach to

    delivering its housing ambitions. It recognises that it will need to consider

    new ways of working, such as joint ventures, and to improve working

    relationships with RSLs to make best use of their skills and experience and

    access potential funding streams. It is also aware that different management

    arrangements for its own stock i may be needed. There are some

    perceptions that there is yet to be full political support for having all options

    'on the table'. While this needs to be addressed, the Council has already

    made some important decisions, such as the 7 million capital fundingcommitted to kickstart its estate renewal programme. There is a clear drive

    towards exploring a wider range of options to achieve necessary

    improvements.

    67 But performance management arrangements are poor overall. The

    Council is in the process of reviewing and improving its performance

    arrangements for the service, but there are currently significant gaps in the

    scope of reported information at both operational and strategic level. Few

    strategic housing indicators are reported as part of current housing

    performance reports, above team level. Additionally, while action plans aremonitored, the Council does not effectively assess whether this has led to

    quality of life improvements or contributed to its wider objectivesii , as

    strategies rarely feature clear success measures to assess this. Delivery

    against existing housing strategy priorities have also not been publicly

    reported and there is no scrutiny or external challenge of performance. The

    Council's current performance management arrangements are not effective

    in underpinning its progress towards key priorities.

    68 Poor management of the DFG and adaptations service has resulted in

    poor customer and value for money outcomes. Ineffective control has

    resulted in lost funding, poor service delivery and a lack of integration

    across service areas. The Council is now reviewing this service and has

    completed an options paper on its future. However, the robustness of this is

    undermined by a lack of challenge. For example, there is still limited

    communication between the adult and community services team ii i and

    housing services about the arrangements and no consultation with service

    users, community groups or the current HIA service provider has yet taken

    i subject to stock options appraisal and consultation with residents

    ii there is some reference in the annual monitoring report, but this is onlymonitored annually, 12 months after year end.

    ii i which administers major adaptation grant funding and adaptations to

    council homes on behalf of the housing service

    Audi t Commission Strategic housing services 26

  • 7/30/2019 Strategic council housing plans in London boroughs

    29/43

    place. It is not possible to determine how well the Council will achieve

    improvements that customers will recognise in this area.

    69 Risk management arrangements are mixed. The Council has a strong

    corporate approach to risk and this is translated into divisional and service

    based risk plans. Senior managers are well aware of the risks for the

    housing service going forward and have put into place some effectiveactions to mitigate them. However, some of the significant risks to the

    service are not well documented in current strategies and plans and there

    has also been little scrutiny of these or the strategic housing service as a

    whole through the Council's scrutiny board.i The Council is not ensuring an

    agreed approach to mitigating risks and alternative solutions is in place.

    70 Arrangements for learning are also mixed. The Council can

    demonstrate some learning from other organisations, which has led to a

    clear awareness of what excellence should look like in some areas of the

    service. However, it has weak arrangements for learning from its own

    experience. Its approach to seeking customer feedback is limited and it

    does not have systematic processes for measuring 'quality of life' impacts

    from projects and initiatives it is involved in or funding. The Council is

    missing opportunities to identify good practice and areas for improvement to

    feed into future initiatives and proposals.

    Does the Counci l plan its finances and other resources robust ly, to

    support the effective delivery of its strategic housing priorities and

    achieve value for money?

    71 The Council is performing below minimum requirements in this area. Itis not ensuring value for money (VFM) within the service, as it lacks a

    strategic framework, targets and comparative data and is poor at analysing

    the VFM of initiatives it has invested in. Although improving, it has not

    ensured it maximises external resources and its spending decisions are not

    informed by robust investment plans. It has however sought to positively

    influence future government decisions on council housing revenue funding

    and has successfully attracted some resources from national and

    sub-regional housing funding schemes. It has also re-directed some

    resources to support housing outcomes. Planning processes help deliver

    better outcomes from local developments.

    72 The Council is not ensuring value for money in its strategic housing

    services. It was assessed as having an 'adequate' approach in its corporate

    use of resources in 2009 ii , but this is not translated into a clear approach at

    service level. The service does not have a clear strategic approach to

    promote value for money and lacks any benchmarking data to show

    comparative quality, performance or cost, except in the planning service. It

    i membership of the 'living and working board' has changed significantly

    as a result of the May 2010 elections. It is now developing its knowledge

    and understanding to help it provide a more effective challenge goingforward

    ii December 2009 Annual Audit Letter to the Council (from the Audit

    Commission) based on 2008/09 annual audit

    Audi t Commission Strategic housing services 27

  • 7/30/2019 Strategic council housing plans in London boroughs

    30/43

    has no efficiency targets at service level to support wider corporate aims.

    While some tentative steps are being taken to improve its approach, there is

    no service framework in place to guide this. The Council cannot

    demonstrate a structured assessment of whether services provide value for

    money or how they will improve.

    73 Funding streams have not always been maximised to increaseresources. For example, the Council has missed opportunities to claim

    around 1.5 million of additional external disabled facilities grant funding

    over the past three years, while it also underspent private sector grant

    funding until last year. Few loans are provided in place of improvement

    grants to recycle funding, nor does it charge any fees for its private sector

    work. Internal recharges for services provided by other departments have

    not been reviewed systematically, with some estimates that this could save

    at least 4 million each year. Some steps are being taken to improve this,

    but as current strategies and action plans lack clarity about the level of

    resources required, it is not clear how effectively this will change in future.

    74 Partnerships have not been evaluated in relation to value for money.

    The Council has not undertaken a review of internal and external

    partnerships to assess how effectively they are helping to deliver shared

    priorities for housing. It has not used existing strategies and targets to

    formally sign up internal or external partners, such as PCTsi , the HIA and

    RSLs, to delivery, sharing responsibilities for targets or identifying

    opportunities to share resources. As a result it is missing opportunities to

    maximise the contribution of partners in delivering the vision for the area.

    75 The Council cannot be certain it has the financial resources to deliver itshousing plans. A number of key proposals ii rely almost entirely on funding

    and investment decisions from other agencies. The Council needs a

    favourable outcome from the government's review of housing revenue

    account fundingii i to ensure the financial viability of its stock and housing

    management service and to lever in other funding. It needs, for example,

    38 million to bridge the funding gap for its estate renewal programme,

    between the 7 million it has committed and the total cost. It anticipates the

    review outcome will help, but the level of headroom it will generate is

    expected to be limited. Its major regeneration schemes are also constrained

    by a lack of approved funding for major infrastructure. Some investment

    decisions have been deferred and other funding cannot be guaranteed. iv

    This could result in the Council being unable to achieve the desired

    improvements at its major regeneration sites and only a small percentage of

    the homes it has planned.

    i Primary Care Trusts (within the NHS

    ii including new housing delivery, estate renewal and investment in

    maintenance of council housing.

    ii i a national review of how council house management and maintenance isfunded.

    iv such as the Docklands Light Railway extension and later phases of the

    proposed bus service

    Audi t Commission Strategic housing services 28

  • 7/30/2019 Strategic council housing plans in London boroughs

    31/43

    76 Spending decisions are not yet informed by robust proposals for

    housing investment. The Council has drafted a borough investment plan,

    but this is not yet complete and it lacks clarity on investment in housing

    services other than major projects. Budgets for key services, such as private

    sector housing and disabled facilities grants, have not been assessed either

    in terms of what they have delivered to date or against actual and potentialdemand, despite significant previous under and over spends respectively.

    Resources are not clearly identified against any strategic proposals and

    strategies do not target resources to particular areas or groups. The Council

    cannot be certain if its resources match its priorities.

    77 The impact of initiatives and funding decisions is not routinely captured.

    Individual teams often monitor the number of outputs, such as private sector

    interventions or new homes built, but the Council rarely captures the actual

    impact of delivery on local people. For example, it has improved housing in

    unpopular areas where turnover has been high due to significant actual or

    perceived levels of anti-social behaviour (ASB) and crime. However, it does

    not know whether the new or improved housing has led to more sustainable

    communities or reduced ASB, crime levels or perceptions of crime. Similarly

    it has little information on changes made at a local level, such as private

    sector housing improvements. Little strategic housing service data is

    captured in corporate performance reports. This limits its ability to

    understand the contribution to the Council's overall objectives or to evaluate

    whether resource levels are appropriate.

    78 The Council has sought to maximise outcomes from the government's

    review of housing revenue funding. It has played a positive role indiscussions with government officials, submitting proposals which offer

    realistic options for the Treasury to consider. While the actual outcome of

    the review is out of the Council's hands, it has played a constructive role in

    seeking to secure the best outcomes the borough can achieve.

    79 The Council has successfully secured some external funding for new

    housing. It was successful in seeking approval from the HCA to switch

    NAHPi funding from the LHC to its own house building programme.

    Together with funding for RSL schemes, this is expected to total around

    18.5 million between 2009/10 and 2010/11. Uncertainty about theoutcomes of the government's forthcoming spending review makes it

    difficult to predict how much of future planned NAHP fundsii will be made

    available. However, the Council hopes that proposed changes in the

    planning, funding and delivery of new homes in London will improve its

    funding prospects, particularly as it has closely aligned its plans with the

    region's identified priorities.

    i national affordable housing programme

    ii of between 105.5 million and 165.8 million, over the next four years

    Audi t Commission Strategic housing services 29

  • 7/30/2019 Strategic council housing plans in London boroughs

    32/43

    80 Some sub-regional funding has been attracted for private sector

    housing work. For example, 1.6 million has been secured to support

    bringing empty homes back into use, along with 140,000 to address high

    risk safety hazards in housing occupied by vulnerable people. The Council

    is also bidding for 're-new' energy efficiency funding to improve the thermal

    efficiency of dwellings. This supplements the Council's own resources toimprove outcomes.

    81 Some resources have been re-directed to service priorities and are

    planned to do so in future. For example, the Council created additional

    posts for the private sector housing team in recognition of its higher profile

    and it has also committed 7 million to kickstart estate renewal. It provided

    funds for a new primary school as part of the Barking Riverside

    development, in light of cancelled BSF funding.i It has also withdrawn some

    land disposal plans so that the necessary infrastructure can be provided

    which support its housing plans or used other sites for housing development

    directly.ii Its draft investment plans mean housing will be second only to

    education in capital funding allocations, with 76.6 million earmarked for

    housing over the next four years. The Council is targeting resources to

    support improvements in the housing service.

    82 Planning processes support value for money in the delivery of strategic

    housing objectives. Clear guidance is provided which sets out expectations

    and these help ensure that suitable infrastructure and community facilities

    are provided, promotes the right quality standards and helps maximise the

    level of affordable housing achieved. This helps deliver better outcomes

    from developments in the borough.

    Do the Council's commissioning and procurement arrangements for

    strategic housing delivery help to maximise value for money and

    sustainability?

    83 The Council's performance in this area is below minimum requirements.

    Despite some procurement activity which may have improved VFM, the

    Council is not analysing outcomes to ensure this is the case. In can

    however demonstrate reduced commissioning fees for some work. It is

    supporting greater sustainability through existing and planned procurementactivity.

    i Building schools for the future' funding was cancelled following the

    government's review of the BSF programme

    ii for example, the St George's Centre and Canington Road sites are nowearmarked for new primary schools and unviable council garage sites

    have been used for the provision of new three and four bedroom social

    rented homes

    Audi t Commission Strategic housing services 30

  • 7/30/2019 Strategic council housing plans in London boroughs

    33/43

    84 The Council cannot demonstrate value for money improvements as a

    result of its procurement arrangements. Despite procurement and supply

    chain management activity related to the council home improvement

    programme and joint procurement of the SHMA, the Council lacks any data

    to quantify the related savings or added value offered. Benchmarking of

    costs and service outcomes is extremely limited. A new procurementexercise is planned for 2011 when the existing council home improvement

    contracts end. Work is now taking place to check what new opportunities

    might exist, such as collaborative procurement with neighbouring authorities

    or more emphasis on sustainability and local employment. However, the

    Council cannot currently demonstrate positive outcomes from its

    procurement choices.

    85 Preliminary costs and fees for commissioning capital housing projects

    have reduced significantly. In 2007/08 they totalled 2.6 million, but reduced

    to 0.95 million, (a fall of 63 per cent) by this year, taking account of

    changes in the size of programmes in place. The Council lacks a breakdown

    of the different savings for different projects, but this has resulted in extra

    resources to invest in service delivery.

    86 Sustainability is reflected in some commissioning and procurement

    activity. In particular, the Council's improvement programme is now based

    on schemes which consider the safety and security of residents and

    environmental wellbeing. Specifications have been changed and the life

    cycle of materials is taken into account in material choices. This helps to

    promote greater value for money through more sustainable communities

    and reduced renewal and repair costs over the long term.

    87 The Council is considering providing minor adaptation equipment at

    accredited retail outlets. It is expanding the current provision of mobility aids

    at local specialist outlets to provide people with quick and easy local access

    to adaptations on a 'prescription' basis. This can help to increase access

    and reduce waiting times for adaptations, helping to maintain independence

    in people's own homes.

    Improving housing outcomes for the local community:

    is the strategic approach to housing delivering betteroutcomes for the local community?

    Is new market and affordable housing offering greater choice for new

    and existing households and promoting sustainable communities?

    88 This is an area where the Council is performing adequately. In future

    years the Council's plans for new housing development provide scope for it

    to significantly exceed the targets set out in the draft London Plan. It

    continues to push for the maximum level of affordable housing that is viable

    on new schemes and has a strong focus on quality and sustainability within

    new housing developments. However, its recent track record in delivering

    new homes and affordable properties is not strong and it lacks clarity on

    Audi t Commission Strategic housing services 31

  • 7/30/2019 Strategic council housing plans in London boroughs

    34/43

    how it is meeting or planning to meet the housing needs of everyone in the

    community.

    89 Going forward, the Council predicts significant improvement in the level

    of new homes it enables. Between 2011/12 and 2014/15, it expects new

    housing supply to average between 1,242 and 1,479 properties i annually,

    significantly exceeding the new proposed annual target of 1,065 properties.It also has the land available to deliver a similar level of homes for the

    following 15 years, although much of the ongoing development is subject to

    infrastructure in