Transcript of Storm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Cider Barrel Circle & Orr Drive
Storm Sewer Pipe Rehabilitation
Sully District
Project No. SD-000034
Cider Barrel Circle
Orr Drive
Project Details
Description:
The Maintenance and Stormwater Management Division completed a total of 48 linear feet of stormwater
conveyance system pipe replacement for these two projects. The reinforced concrete pipe segments
(RCP) were severely separated at the joints. To extend the service life and minimize further failures of
the storm pipes and nearby ground surfaces, the separated segments were excavated and replaced with
new reinforced concrete pipe segments.
Project Overview:
• Excavated and removed the separated 15” RCP.
• Installed new RCP and connected with existing storm sewer system.
• Backfilled and reestablished the disturbed areas, which included resurfacing the trail above the pipe
and seeding common areas.
DPWES Project Team:
• Project Manager: Matthew Adams
• Construction Manager: Qais Bashir
• Project Inspector: Thomas Cameron
Project Location
Cider Barrel Circle & Orr Drive - Tax Map No. 56-3-11-C
Cider Barrel Circle
Pipe Rehabilitation
Location
Orr Drive
Pipe Rehabilitation
Location
Pre-Construction Conditions
Large Separated Joint
Cider Barrel Circle
Large Separated Joint
Orr Drive
Construction: Work included excavating and
replacing the separated segments.
Separated
Joint
For additional Information, please call
Irene Haske, Public Information Officer
703-324-5821, TTY 711