STH 145 Roundabout Presentation Bloom Companies, LLC July 3, 2012.

22
STH 145 Roundabout Presentation Bloom Companies, LLC July 3, 2012

Transcript of STH 145 Roundabout Presentation Bloom Companies, LLC July 3, 2012.

STH 145 Roundabout Presentation

Bloom Companies, LLCJuly 3, 2012

Our Team

Bloom Companies, LLCBloom is a multi-disciplinary architecture/engineering/construction firm specializing in providing innovative and sustainable solutions for the built environment.  Our engineering services include:  Structural Engineering, Geotechnical Engineering, Environmental Engineering, Land Surveying Services, Site/Civil Engineering, Bridge Engineering, Transportation Engineering, Traffic Engineering, Water Resources Engineering, Value Engineering, Construction Engineering and Architecture. Our Construction services encompass:  Buildings, Bridges, Infrastructure, Pile Foundations, Sheet Piling, Concrete, Carpentry, Site Work and Construction Management.

•Project History▫TIA in Aug. 2009

intersection needs improvements▫March 31, 2011 – Selected for Master

Contract project▫Mid June 2011 work order is approved▫Late June 2011 survey completed▫OPM held Sept. 27, 2011▫30% plans completed Dec. 12, 2011

1 Signalized design 1 Roundabout design

▫PIM No. 1 on Feb. 8, 2012▫ICE approval on June 6, 2012

Roundabout recommended

•Design process▫Original thought presented at OPM:

▫Center the Roundabout, show historic school house impact (basis for design)

▫Was told any design involving historic properties must be feasible and leave historic property intact.

▫Slide center of intersection NE within both options

▫Multiple iterations and discussions with Ourston on Roundabout design

▫October thru early December 2011▫1 Signalized design and 1 Roundabout design

submitted to Department and Village for comments (seen in agenda package)

Signalized Intersection1

Roundabout Intersection2

PIM No. 1, Feb. 8, 20123

42 attendees signed in

PIM No. 1 comments / themes4

12 comment forms turned in; comments include:

1) Concern for speed on 145, mentioned roundabout could help this2) One misunderstood roundabout to be 2 lane with need to switch lanes3) 3 liked the roundabout idea, 1 liked safety of Roundabout4) 7 said no roundabout, multiple mentioning lower cost of signal option

(incorrect assumption) Signal = $1.9 million Roundabout = $1.4 million

5) Concerns about utility lines, trees and ability to make left out of driveway6) Waste Mgmt – desires signal or 50% larger Roundabout7) 1 thought – signal easier on semi’s and garbage trucks8) 2 concerned about space required for roundabout9) 1 said go with signal due to cost (see above #’s)

Shared with stakeholders on Feb. 9, 2012 via synopsis / overview doc.

ICE Review4

9 different areas within chart, operational analysis shown below.

ICE Review, continued

4

Signal LOS = C Roundabout LOS = BSignal Delay = 34 seconds Roundabout Delay = 14 seconds

5

Project initiation6

Some items initiating project

7

TIA recommendations8

Roundabouts VS Signals9

Present design (Roundabout)

•Safety▫Speed reduction through use of Chicane

1

Present design (Roundabout) •Right-of-way impacts

▫Similar for both options

1

Present design (Roundabout) •Access – lost with signal but not with Rdbt.

1

Village comments desired • Can help better design• Now or later, form provided

1

Thank You!!

Any Questions?Emmanuel Yartey, PEWisDOT Project Manager262-548-6429

Jeremy Hinds, PEBloom Project Manager414-292-4552