STH 145 Roundabout Presentation Bloom Companies, LLC July 3, 2012.
-
Upload
jayson-miller -
Category
Documents
-
view
218 -
download
2
Transcript of STH 145 Roundabout Presentation Bloom Companies, LLC July 3, 2012.
Bloom Companies, LLCBloom is a multi-disciplinary architecture/engineering/construction firm specializing in providing innovative and sustainable solutions for the built environment. Our engineering services include: Structural Engineering, Geotechnical Engineering, Environmental Engineering, Land Surveying Services, Site/Civil Engineering, Bridge Engineering, Transportation Engineering, Traffic Engineering, Water Resources Engineering, Value Engineering, Construction Engineering and Architecture. Our Construction services encompass: Buildings, Bridges, Infrastructure, Pile Foundations, Sheet Piling, Concrete, Carpentry, Site Work and Construction Management.
•Project History▫TIA in Aug. 2009
intersection needs improvements▫March 31, 2011 – Selected for Master
Contract project▫Mid June 2011 work order is approved▫Late June 2011 survey completed▫OPM held Sept. 27, 2011▫30% plans completed Dec. 12, 2011
1 Signalized design 1 Roundabout design
▫PIM No. 1 on Feb. 8, 2012▫ICE approval on June 6, 2012
Roundabout recommended
•Design process▫Original thought presented at OPM:
▫Center the Roundabout, show historic school house impact (basis for design)
▫Was told any design involving historic properties must be feasible and leave historic property intact.
▫Slide center of intersection NE within both options
▫Multiple iterations and discussions with Ourston on Roundabout design
▫October thru early December 2011▫1 Signalized design and 1 Roundabout design
submitted to Department and Village for comments (seen in agenda package)
PIM No. 1 comments / themes4
12 comment forms turned in; comments include:
1) Concern for speed on 145, mentioned roundabout could help this2) One misunderstood roundabout to be 2 lane with need to switch lanes3) 3 liked the roundabout idea, 1 liked safety of Roundabout4) 7 said no roundabout, multiple mentioning lower cost of signal option
(incorrect assumption) Signal = $1.9 million Roundabout = $1.4 million
5) Concerns about utility lines, trees and ability to make left out of driveway6) Waste Mgmt – desires signal or 50% larger Roundabout7) 1 thought – signal easier on semi’s and garbage trucks8) 2 concerned about space required for roundabout9) 1 said go with signal due to cost (see above #’s)
Shared with stakeholders on Feb. 9, 2012 via synopsis / overview doc.
ICE Review, continued
4
Signal LOS = C Roundabout LOS = BSignal Delay = 34 seconds Roundabout Delay = 14 seconds