Stephen Natoli - Holding Redlich - Contract law - resolving the risk apportionment issue
-
Upload
informa-australia -
Category
Business
-
view
581 -
download
0
Transcript of Stephen Natoli - Holding Redlich - Contract law - resolving the risk apportionment issue
© Holding Redlich 2015
Risk Apportionment in Construction Contracts
Civil Contractors Federation National Conference
Stephen Natoli
16 October 2015
© Holding Redlich 2015 © Holding Redlich 2015
General overview
What is Risk Types of Risks
Basic Risk Analysis
Risk Allocation – theory vs practice
The Usual Suspects
Risk Mitigation Tools
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
What is risk?
Risk Effect of uncertainty on objectives Outcome must be uncertain
and relevant
Linked to strategy “Risk Appetite” – position on the
risk/return curve (depends on capacity) “Risk Tolerance” – acceptable exposure to a
particular risk (generally quantified)
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Types of Risk
Construction risk (e.g., technical, design, cost, schedule, quality etc.)
Sovereign risk (e.g., change of law) Performance risk Market risk (e.g., economic conditions) Financing risk Asset risk Contractual risk (e.g., warranties, indemnities,
force majeure etc.)
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Basic Risk Analysis
Risks identified
Risks quantified (likelihood x consequence)
Prioritised – e.g.‘Hot risks’ addressed
Ongoing monitoring
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Basic Risk Analysis
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Risk Allocation - in theory
Who is best placed to control/manage the risk? Who can transfer the risk (e.g., insurance,
specialist subcontractor) Who has the greatest economic incentive to
manage the risk? Who is the most efficient party top manage the
risk? Who bears the risk at first instance?
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Risk Allocation - in practice
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Function of the Contract
Risk Allocation Tool Should clearly state:
Rights
Responsibilities
Quality standards
Timing
Cost
Consequences if breached
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Risk management tools
Warranties Indemnities Insurance Limits on liability Project controls Sharing tools Priced Laid off
Risk management basics
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Workshop
What contractual risks typically get passed onto to you?
Can you successfully resist them?
If not, how do you manage the risk?
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Workshop
The usual suspects
Variations
Extensions of Time
Latent Conditions
Discrepancies
Defects
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Seeking relief
Claims mostly fought over time and scope issues (usually connected)
Consider:
Notification requirements
Time bars and waivers
Is there a back door to relief?
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects - variations
Contract price is normally fixed to scope of works Contractor may be directed to vary the works under contract
(WUC) by the Superintendent at any time before the date of practical completion by any one or more of the following: a) Increase, decrease or omit any part of the WUC
b) Change the character or quality of any part of the WUC
c) Change the levels, lines, positions or dimensions of any part of the WUC
d) Carry out additional work
e) Demolish or remove material or work no longer required by the Principal
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects - variations
Does the contract require a written direction to vary before work can be characterised as a variation?
If it is possibly contentious then what is the case for it being a variation?
What do I have to do and within what timeframe?
Have I documented cost adequately? Is there a time implication?
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects - variations
1 • Instructions received (if verbal go to 2 &3 but if written go to 4)
2 • Request a written variation direction (within 48 hours)
3 • Receive written direction
4 • Provide estimated price and projected impact on programme (within 5 days of receipt
of written direction to vary)
5 • Approval of price to be provided by Superintendent/ Principal within 48 hours
6 • Commence Work
7 • Value variation and submit as part of claim to payment
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects - Variations
Key considerations: Notice requirements (e.g., content and time
limits) Scope
Risk Mitigation considerations: Project controls measures Risk sharing tools (e.g., risk ceiling or floor) Scope (e.g., exclusions, qualifications etc.)
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects - Extensions of time
The basic obligation
the Contractor must ensure that WUC reaches practical completion by the date for practical completion
A failure to meet the obligation typically leads to liquidated damages
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects - Extension of time
Typical Requirements 1. Qualifying cause of delay 2. Notification within a certain time after delay
becomes evident 3. Activities on critical path must be delayed 4. Must prove that practical completion has been, or
will be delayed 5. Must submit claim within certain time after the
“delay occurs” or “delay ceases”
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects - Extension of time
Do I have a program in place that has enough detail in it to be able to credibly assess the impact of a delay event?
Have you experienced an event which is going to affect your ability to achieve PC on time – are activities on the critical path delayed?
How long after the delay event must I notify? What can I do to mitigate any delay?
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects - Extensions of Time
Key considerations: Qualifying cause of delay Notice requirements (eg content and time limits)
Risk Mitigation considerations:
Project controls measures Indemnities Risk sharing tools (eg risk ceiling or floor) Caps on liability (eg LD cap)
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects – Latent Conditions
What are they?
Standard clause from AS4300-1995:
Latent Conditions are:
a) physical conditions on the Site or its surroundings, including artificial things but excluding weather conditions, which differ materially from the physical conditions which should reasonably have been anticipated by the Contractor at the time of the Contractor’s tender if the Contractor had:
i) examined all information made available in writing by the Principal to the Contractor for the purpose of tendering;
ii) examined all information relevant to the risks, contingencies and other circumstances having an effect on the tender and obtainable by the making of reasonable enquiries; and
iii) inspected the Site and its surroundings; and
b) any other conditions which the Contract specifies to be Latent Conditions.
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects – Latent Conditions
Notification
If during the execution of the work under the Contract, the Contractor becomes aware of a Latent Condition, the Contractor shall forthwith and where possible before the Latent Condition is disturbed, give written notice thereof to the Superintendent.
If required by the Superintendent, the Contractor shall provide to the Superintendent a statement in writing specifying:
a) the Latent Condition encountered and in what respects it differs materially;
b) the additional work and additional resources which the Contractor estimates to be necessary to deal with the Latent Condition;
c) the time the Contractor anticipates will be required to deal with the Latent Condition and the expected delay in achieving Practical Completion;
d) the Contractor’s estimate of the cost of the measures necessary to deal with the Latent Condition; and
e) other details reasonably required by the Superintendent.
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects – Latent Conditions
Time and cost relief
Delay caused by a Latent Condition may justify an extension of time under Clause 35.5. If a Latent Condition causes the Contractor to: a) carry out more work; b) use more Constructional Plant; or c) incur more cost (including but not limited to extra costs for delay or
disruption),
than the Contractor could reasonably have anticipated at the time of tendering, a valuation shall be made under Clause 40.5.
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects – Latent Conditions
What are they? Amended clause – additional requirements Latent conditions are physical conditions on the site and its near surrounds, including artificial things but excluding weather conditions, which differ materially from the physical conditions which should reasonably have been anticipated by a prudent, experienced and competent contractor at the date of Contract if such contractor had: a) inspected all written information made available by the Purchaser to the
Contractor for the purpose of tendering; b) inspected all information influencing the risk allocation in the Contractor's
tender and reasonably obtainable by the making of reasonable enquiries; c) inspected the site and its near surrounds; and d) done those things referred to in the subclause on the next slide.
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects – Latent Conditions
Additional requirements The Contractor warrants that it did (and it is deemed to have done) each of the following things before the date of Contract:
a) examined and carefully checked and acquired actual knowledge of the contents of the documents which constitute the Contract;
b) Informed itself completely as to:
i) site conditions;
ii) the risks, contingencies and other circumstances which might have an effect on the execution of WUC or the cost of executing WUC;
iii) the nature of the work and of the plant, equipment, materials and other items necessary for the execution of WUC and the means of access to and facilities and services at the site and the means of transport, transport routes and facilities for deliveries to and from the site;
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects – Latent Conditions
iv) all measures necessary to protect the environment from any adverse effect or damage arising from the execution of WUC or the operation of the Works;
c) satisfied itself as to the correctness and sufficiency of its price for WUC and that the contract sum covers the cost of complying with all of its obligations under the Contract and of all matters and things necessary for the due and proper performance and completion of its obligations under the Contract; and
d) obtained all appropriate professional and technical advice with respect to the matters referred to in this subclause, and any failure by the Contractor to have done any of those things will not relieve the Contractor of its obligation to perform and complete WUC in accordance with the Contract.
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects – Latent Conditions
Alternatively providing no cost or time relief
The Contractor: a) is responsible for, and assumes the risk of, all increased costs and
any losses and expenses in respect of the physical conditions and characteristics of the site and its surroundings encountered during the WUC; and
b) acknowledges and agrees that it will not be entitled, in any circumstances, to any additional payment for, or EOT in relation to, any such physical conditions and characteristics.
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects – Latent Conditions
Key considerations Relief event?
Notification requirements (e.g., timing and content)
Risk mitigation strategies Project control measures
Warranties/indemnities
Scope
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects – Discrepancies in Documents
Who bears risk for discrepancies/errors in contractual documents
Standard clause from AS4300:
The several documents forming the Contract are to be taken as mutually explanatory of one another. If either party discovers any ambiguity or discrepancy in any document prepared for the purpose of executing the work under the Contract, that party shall notify the Superintendent in writing of the ambiguity or discrepancy. In the event of an ambiguity or discrepancy being discovered and brought to the attention of the Superintendent, or discovered by the Superintendent, the Superintendent shall direct the Contractor as to the interpretation to be followed by the Contractor in carrying out the work.
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects – Discrepancies in Documents
If the direction causes the Contractor to incur more or less cost than the Contractor, having complied with Clause 4.1(c), could reasonably have anticipated at the time of tendering, then to the extent that such ambiguity or discrepancy is: a) in the Principal’s Project Requirements, the difference shall be
valued under Clause 40.5; and
b) in the Design Documents or between the Design Documents and the Principal’s Project Requirements, such ambiguity or discrepancy shall be at the Contractor’s risk and the direction shall not entitle the Contractor to any extra payment or an extension of time.
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects – Discrepancies in Documents
Who bears risk for discrepancies/errors in contractual documents
Amended Clause The Contractor warrants that it has thoroughly examined and reviewed all plans, drawings and specifications, Principal's Project Requirements and other documents relating to the WUC, the Works and that those plans, drawings and specifications and Principal's Project Requirements are: a) suitable, appropriate, complete and adequate for the purposes
of constructing the Works and carrying out the WUC; and b) consistent with and conform with, all legislative requirements
and all requirements of the Building Code of Australia; and
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects – Discrepancies in Documents
c) it has not identified, except as previously notified to the Principal or the Superintendent in writing, any inconsistency, ambiguity, omission or discrepancy.
The Contractor is not entitled to claim any adjustment to the contract sum or make any claim for an EOT arising out of or in connection with any inconsistencies, ambiguities or discrepancies in any document forming this Contract.
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects – Discrepancies in Documents
Key considerations
Standard of care (eg. full risk vs competent contractor vs no risk)
Notification requirements (eg. timing and content)
Risk mitigation strategies
Project control measures
Warranties/indemnities
Scope
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects - Defects
When are you responsible for rectifying defects and what is the consequence of failing to meet these obligations?
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
The usual suspects - Defects
Key considerations: Scope of defect rectification obligations
Risk Mitigation considerations: Caps on liability
Project controls measures
Indemnities
Risk sharing tools (e.g., risk ceiling or floor)
Laid off risk
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Risk mitigation tools - Warranties
Contractual statement of fact Aims to put claimant in position it would have
been in if warranty was true Breach of contract with damages a remedy
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Risk mitigation tools - Indemnities
Contractual promise to hold a specific person harmless against specified losses or the occurrence of a particular event
Consider Scope (e.g., loss covered)
Trigger event
No issue of remoteness of damage or obligation to mitigate
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Risk mitigation tools - Insurance
Policy risk (e.g., limits of policy)
Procedural risk (e.g., compliance)
Quantum risk (e.g., excess)
Indemnity vs insurance (e.g., contractual terms vs policy terms)
Role of caps on liability
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Risk mitigation tools – Caps on liability
Types of caps (e.g., financial caps, consequential loss exclusion, LD cap, sunset liability)
Exclusions
Role of insurance
Risk Apportionment in Construction Contracts
© Holding Redlich 2015 © Holding Redlich 2015
Risk mitigation tools – Control Procedures
Types (e.g., project management plans, risk registers, issue registers)
Regular, documented meetings to consider key risks
Project meetings – use the minutes to your advantage
Risk Apportionment in Construction Contracts
© Holding Redlich 2015
Key Contacts
© Holding Redlich 2015
Disclaimer The information in this publication is of a general nature and is not intended to address the circumstances of any particular individual or entity. Although we endeavour to provide accurate and timely information, we do not guarantee that the information in this publication is accurate at the date it is received or that it will continue to be accurate in the future. We are not responsible for the information of any source to which a link is provided or reference is made and exclude all liability in connection with use of these sources.
Stephen Natoli
Partner
T +61 3 9321 9796
Risk Apportionment in Construction Contracts