Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope...
Transcript of Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope...
![Page 1: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/1.jpg)
Steering Committee Agenda 25-3-14
• Overall Program Status• High Level Program Schedule• Project scope by phases • Key milestones
– Phase 1 (P1)– Overall (P1 – P3)
• UK Channel launch sequence • Status By Track• “Go – live” recap• Value tracker• Next Steps• Appendix
– Financial summary– Contract status
![Page 2: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/2.jpg)
Overall Program Status
•Contracting: Completed 15 of 17 contracts/production licenses•Finance: On track and reconciled weekly•Beginning Madrid greenlight processProject Setup
•Initial Phase 1 “Go Live” on 4/14 with the channel migrations ending in August
•Revised schedule enables channel migration activities to be supported earlier in the process based on planned rollout of functionality
Schedule
•Original Scope OK•High level Madrid scope determinedScope
•Project financials are on track. Detailed reviews with individual project managers to update forecasts.
•Preliminary budget discussions have taken place regarding Madrid. Planned green light meeting in April/May
Project Budget
•Deployment risks mitigated based on new phased rollout•Resource availability through Q4•Vision 4.06 dependency
Issues & Risks
![Page 3: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/3.jpg)
High Level Program Schedule
Sept-July 2014 – Stage 1: Initial Build
Initial Build & Launch• Initial AWS Build with MAM & Initial screens
• MCS Tools• Initial Integrations including GPMS to UK Vision
• Network Project Complete• Local build complete• Aspera Project Complete• VOD workflows• First Channel live
April-August 2014 – Stage 2: Channel Rollout
Rollout Channels• Rollout channels on MediaCentre (All UK Channels live)
• Stabilize & Tune system• Additional Integration services live
• BCM Integration• Continued development and testing
July-Sept 2014 – Stage 3: Additional Automation
First Wave of Automations• New automated workflows• Additional screens and enhancements
• Additional integration services
• Cloud NLE prototype• Madrid Requirements
October 2014 – December Stage 4: BMS enhancements
Second Wave of Automation & BMS Enhancements• Additional workflow automation
• BMS enhancements• Additional Integration• Screen enhancements• Madrid Development
Dec - April 2015 – Stage 5: Madrid & Budapest Archive
Expand to Madrid & CE (Archive)• Launch Madrid Channels• Vision CE integrated• MediaCentre Services available
• CE Archive available
![Page 4: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/4.jpg)
P0 (App)
•Landing Page•Simple Login•Authentication
•User Management•Users/Roles•Sony IDM Integration
•Search (Vidispine)•Title/Alpha hierarchy traversal
•ODS Title/Alpha integration•ODS Metadata•Platform Ops Support
P1 (DAM/IMS)
•Profile Management:•Provider
•Monitoring Inbound (ingest):
•Provider Receiving•Proxy Generation•Aspera Integration
• Workflow Tasks:•Matching
•Workflow Management:•Ingest•Transcoding•Bulk Ingest•Migrations•Priority Ranking System•Rank by Admin Flag•Upload
•Inventory Detail
•MCS Tools Integration•Authentication•Ingest•Preview•Annotation
P2 (Delivery)
•Profile Management:•Channel & Recipient
•Monitoring Inbound (ingest):•Qcloud (monitoring UI)•Qcloud metadata & integration to Vidispine
•Workflow Tasks:•Ingest Order Management
•Manual QC
•Alpha Creation•Alpha creation via ODS service
P3 (Scheduling)
•Scheduling•ODS schedule integration (Vision)
•Monitoring Outbound:• Deliveries (Aspera Transfers)•Transcoding•Vidispine Jobs
•Dashboard:•Business Intelligence•Usage Activity•Logging•Alerts•Failures/Rejections•Reports
•Workflow Tasks:•Delivery Management•Compliance•Reports•Priority ranking•Rank by TX•File management rules
•Localization
•VOD/Catchup•Enhanced XML transform capability to support VOD catchup servicing•Additional VOD specific transcode profiles
01/22/2014 April 2014 (4/14) June 2014 (6/9) July 2014 (7/7)
“Go-Live” dates
ODIN
Local Build
Network
Aspera P1 Go-Live 4/14
![Page 5: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/5.jpg)
Key milestone dates (“Soft Go-Live” April 14th)
Feb March AprilProject threads
2/24 (Monday)
3/3(Monday)
3/10(Monday)
3/17(Monday)
3/24(Monday)
3/31(Monday
4/7 (NAB)(Monday)
4/14(Monday)
4/21(Monday)
MediaCentre
ODIN
Training
Onboarding
Change Mgmt.
P1 Dev
P1 QA P1 UAT
MC P1 practical
P1 UAT (Users)
P1 Go-Live 4/14
On-board Russia & Africa
Title (AMMO)
Dev
Technical Aspera set-up
Title process Go live 4/14
Outreach to providers
QA Mirror/UAT (Titles)
Title (ODIN, Vision)
Title training dev.
High level communications
Logistics
Weekly UpdatesProcess changes (document,
approvals, communicate)
Code freeze 2/26Fixes 2/27 & 2/28
Data Migratio
n Train the
trainer
User Forums
MC P1Dev complete
Title trainingready
Title Training
MCMTraining
MC Go-Live
![Page 6: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/6.jpg)
Key milestone dates (P1- P3 “Go - Live”)
Feb March April May June2/24 2/28
3/33/7
3/103/14
3/173/21
3/243/28
3/314/4
4/74/11
4/144/18
4/214/25
4/285/2
5/55/9
5/125/16
5/195/23
5/265/30
6/26/6
6/96/13
6/166/20
6/236/27
6/307/4
MediaCentre
Training
P1 Dev
P1 QA P1 UAT UAT
P1 Go-Live 4/14
P2 Dev
P2 QA P2 UAT
MC P2
P2 Go-Live 6/9
P3 Dev
P3 QA P3 UAT
MC P3
P3 Go-Live 7/7
MC P1
P2 UAT
P3 UAT
![Page 7: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/7.jpg)
UK Channel Launch Schedule Update
Ongoing parallel work for migration:• Distributor on-boarding
migration and standard operating procedure defined
• Aspera in place• Schedule has been validated in
meetings with core teams• Schedule is built with UAT &
Training considerations.
Region Provider
Onboarding Start Go Live ReviewAfrica Sony Max Africa 17/03/2014 14/04/2014 13/05/2014SET Africa 17/03/2014 14/04/2014 13/05/2014
Russia SET Russia 17/03/2014 14/04/2014 13/05/2014SET Baltics 17/03/2014 14/04/2014 13/05/2014Sony Turbo Russia 17/03/2014 14/04/2014 13/05/2014Sony Turbo Baltics 17/03/2014 14/04/2014 13/05/2014AXN Sci-Fi Russia 17/03/2014 14/04/2014 13/05/2014
UK Movies4Men 28/04/2014 07/07/2014 21/07/2014More Than Movies 28/04/2014 07/07/2014 21/07/2014SET UK 28/04/2014 07/07/2014 21/07/2014SMC UK 28/04/2014 07/07/2014 21/07/2014
Italy AXN Sci-Fi Italy 26/05/2014 21/07/2014 04/08/2014AXN Italy 26/05/2014 21/07/2014 04/08/2014
Germany AXN Germany 23/06/2014 04/08/2014 18/08/2014Animax Germany 23/06/2014 04/08/2014 18/08/2014SET Germany 23/06/2014 04/08/2014 18/08/2014
P1 Soft Go Live – 14/04
P3 Go Live – 07/07
![Page 8: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/8.jpg)
The MediaCentre’s Projects
Asp
era
Asp
era
JBOSS ESB & Rules120 ESB
MAM
Metadata
Update
GPMS
Vision
BCM
ODS
2
1
INTEGRATION BMS Systems
3
MAM in Cloud
4
Network
ESB
Local56 MASTER7
MCS ???UI Screens
• On track • Vision upgrade
complete• Provys migration
(March – May)• Performance issue
patch implemented• Meetings with users
regarding title metadata management
• On track• ODIN in production
3/14• ODIN training this
week• ODIN migration
scripts and validation
• Development behind initial plan schedule by 6 weeks for P1, assessing overall impact on P2-3
• Project Structure changed to address schedule
• All screens to support P0 – P3 functionality have been completed and approved
• P1 UAT in progress• Vidispine configured, deployed and
demonstrated in HA configuration• MCS’s integration activities are complete
• Project Completed• Solution integrated
into current workflows
• On track• Training complete• London and
Budapest using Aspera
• On track• 15 of 17 contracts
approved• Financials on track• MediaCentre training
scheduled for beginning of April
• Project Completed
• Both primary/back-up 10G connections are up and running
• Encompass Upgrades completed
MADRID…8
• Plan developed• Investigating
Broadcast Master
![Page 9: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/9.jpg)
“Go-Live” RecapJanuary• 10G connectivity to AWS (primary and backup)• Aspera software installed • Encompass Aspera complete• Tape ingest and Aspera training complete• Upgraded workstations connected to the SAN storage, Adobe Premier
rolled out February • Vision upgraded to 4.06• Arqiva and Encompass upgradesMarch• ODIN live 3/14 (autopublish in April)• Title metadata management (ODIN/Vision) meetings week of 3/24• MediaCentre training beginning in April
![Page 10: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/10.jpg)
Value Tracker
Benefit Jan Feb Mar Apr May Jun Jul AugCost Reduction/Avoidance Reduce Third party Content Prep and Encompass services Simpler Content Prep for future Channels
Retire Bespoke solution, Avoid future Infrastructure build-out in Golden Square
Lower Cost for new channels, including lower HD Acquisition cost Single File Ingest Point for SPTN, leveragable across territories
Reduce Local Technology spend and expensive third party media management spend
German VOD catch-up service Operational Efficiency Improvement Avoid email and .XLS for workflow and communication Better exploitation of assets across territories / brands
Shared inventory visibility in other regions and worfklow flexibility best practices
More efficient compliance editing on shared content Risk Mitigation Reduced risk of future OFCOM violations through system controls
Today
Align current costs and scheduleMedianMoterGovernance
![Page 11: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/11.jpg)
Next Steps
• Upcoming Focus– MAM Buildout for P1– Madrid Greenlight meeting– MediaCentre training (contextual, hands on)– ODIN autopublish to Vision – Change management– Channel onboarding– Continue Vision upgrade & Provys migrations
work
![Page 12: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/12.jpg)
Appendix
• Media Centre Project Financials• Contract Summary Status
![Page 13: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/13.jpg)
Media Centre Project Financials
Summary includes actual activity through February 2013 and estimates to complete the project
CPR VARIANCE
Project Project #Prior FY Actuals
YTD Actuals
FY14 Remaining Forecast
FY15 Forecast
Current Forecast CPR Total Variance
Master I01803 70,800 402,434 178,024 519,276 $1,170,534 $1,116,140 ($54,394)
ASPERA I02005 0 282,917 9,120 0 $292,037 $300,000 $7,963
BMS I02006 0 0 0 325,000 $325,000 $325,000 $0
Integration I02007 0 608,843 97,141 570,560 $1,276,544 $1,392,205 $115,661
Local I02008 0 299,762 4,538 0 $304,300 $502,444 $198,144
MAM-AWS I02009 0 692,669 530,000 646,500 $1,869,169 $1,929,700 $60,531
Network I02010 0 514,400 17,228 0 $531,628 $550,000 $18,372
Total
70,800 2,801,024 836,051
2,061,337 $5,769,212 $6,115,489 $346,277
![Page 14: Steering Committee Agenda 25-3-14 Overall Program Status High Level Program Schedule Project scope by phases Key milestones – Phase 1 (P1) – Overall (P1.](https://reader035.fdocuments.net/reader035/viewer/2022062516/56649d985503460f94a829d4/html5/thumbnails/14.jpg)
Contract Summary Status (15 of 17 complete)• DSB AWS reseller agreement: initial
draft completed and submitted for review by team
• MCS Production License: pricing agreed upon, working on finalizing SPE wide SLAs