Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in...

5
1 January 2011 BWT Facility Renovation Status Page 1 Status Review of BWT Facility Renovation PWSRCAC Board of Directors Meeting January 20, 2011 January 2011 BWT Facility Renovation Status Page 1 January 2011 BWT Facility Renovation Status Page 2 Introduction Alyeska is in the process of completing a major renovation of the Ballast Water Treatment (BWT) facility at the Valdez Marine Terminal The goals of this renovation were to: Enhance safety Reduce hazardous air pollutant (HAP) emissions Comply with and renew the NPDES wastewater permit Meet changing operating conditions Maintain high reliability Renovation work is about one-year behind schedule due to the extensive amount of pilot testing which was required to ensure that appropriate technology is used The majority of goals have already been substantially met (e.g. air emissions greatly reduced and tank headspaces inert)

Transcript of Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in...

Page 1: Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in the tank farm • Obtain renewed NPDES permit from EPA in 2011 . Title: BWTF Renovation

1

January 2011 BWT Facility Renovation Status Page 1

Status Review of BWT Facility Renovation PWSRCAC Board of Directors Meeting

January 20, 2011

January 2011 BWT Facility Renovation Status Page 1

January 2011 BWT Facility Renovation Status Page 2

Introduction •  Alyeska is in the process of completing a major renovation of

the Ballast Water Treatment (BWT) facility at the Valdez Marine Terminal

•  The goals of this renovation were to: –  Enhance safety –  Reduce hazardous air pollutant (HAP) emissions –  Comply with and renew the NPDES wastewater permit –  Meet changing operating conditions –  Maintain high reliability

•  Renovation work is about one-year behind schedule due to the extensive amount of pilot testing which was required to ensure that appropriate technology is used

•  The majority of goals have already been substantially met (e.g. air emissions greatly reduced and tank headspaces inert)

Page 2: Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in the tank farm • Obtain renewed NPDES permit from EPA in 2011 . Title: BWTF Renovation

2

January 2011 BWT Facility Renovation Status Page 3

Renovated BWT Facility Process •  Facility treats water that may contain petroleum hydrocarbons •  Influents are primarily non-segregated tanker ballast, storm

water runoff and industrial wastewater •  Renovated plant configuration is a 4-step treatment process:

−  Gravity separation in the 90s Tanks to remove readily separable oil and solids

−  Dissolved Air Flotation (DAF) to provide removal of suspended and emulsified oil and solids

−  Air Strippers to remove volatile hydrocarbons −  Polishing Ponds to biodegrade trace amounts of residual pollutants

and enhance water clarity •  Thermal Oxidizers / Incinerators are installed to control

hazardous air pollutant emissions •  Plant includes facilities for recovering separable oil

(recovered crude system)

January 2011 BWT Facility Renovation Status Page 4

Key Issues Addressed •  Safety:

–  Headspace in fixed roof tanks were at times in the flammable range (This was per the original codes, but is no longer acceptable to APSC)

–  Some areas of the plant required the periodic use of respirators or other measures to protect workers against hazardous air pollutant exposure

•  Environmental: –  Needed to renew and continually comply with the NPDES permit –  Control of air emissions

•  Process Changes: –  BWT influent volumes have significantly decreased with marine fleet

conversion to segregated, double-hull tankers and reduced pipeline crude oil throughput (see following slide)

–  Plant water temperature, contaminant loading and salinity reducing due to increased proportionality of storm water runoff to ballast water

•  Lifecycle Upgrade: –  Aging facility with older technology

Page 3: Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in the tank farm • Obtain renewed NPDES permit from EPA in 2011 . Title: BWTF Renovation

3

January 2011 BWT Facility Renovation Status Page 5

Ballast Water Flow Forecasts

(NOTE: Original plant design flow was 30,000,000 gal/day)

January 2011 BWT Facility Renovation Status Page 6

2007 BWT Facility Renovations •  Tied BWT Tanks 93 & 94 to the VMT Vapor Control System •  Installed upgraded (V5) oil skimmers in the BWT tanks •  Performed pilot testing:

–  Pilot four-cell Induced Gas Flotation (IGF) –  Pilot walnut shell filters –  Pilot 4 and 7 tray air strippers –  Pilot photo-catalyst

Page 4: Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in the tank farm • Obtain renewed NPDES permit from EPA in 2011 . Title: BWTF Renovation

4

January 2011 BWT Facility Renovation Status Page 7

2008 BWT Facility Renovations •  Cleaned Tank 92 and placed in standby •  Performed detailed testing of secondary treatment equipment •  Installed new Air Stripper System to remove volatile

hydrocarbons (BTEX): (Operational 2Q 2009) –  New Power Distribution Center –  Four Shallow Tray Air Strippers –  Two Thermal Oxidizers –  Three Propane Tanks

January 2011 BWT Facility Renovation Status Page 8

2009/2010 BWT Facility Renovations •  Installed analyzers on Tanks 13 & 14 and West Metering to

limit and better control the BWT plant influent (Operational 1Q 2011) •  Upgraded and completely renovated DAF Cells 5 & 6:

–  Covered DAF 5 & 6 and tied to Thermal Oxidizers for vapor control –  Replaced Pressure Retention Tanks and DAF Compressors –  Performed major repairs to entire DAF system

Page 5: Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in the tank farm • Obtain renewed NPDES permit from EPA in 2011 . Title: BWTF Renovation

5

January 2011 BWT Facility Renovation Status Page 9

2010 BWT Facility Renovations •  Completed construction of covered DAF renovations •  Finalized pilot testing of Moving Bed Bio-film Reactor (MBBR),

Fixed Bed Bio-film Reactor (FBBR) and Multi-plate Bio-film Reactor (MPBR)

•  Repaired and coated DAF Building structure •  Replaced DAF inlet piping

January 2011 BWT Facility Renovation Status Page 10

Planned 2011/2012 BWT Renovations •  Convert the existing Biological Treatment Tanks (BTTs) into

Polishing Ponds to biodegrade trace amounts of residual pollutants and enhance water clarity. Alternatively, a Moving Bed Bio-film Reactor may be installed in the DAF 1 - 3 area.

•  Replace the DAF Building roofing •  Replace DAF lighting with energy efficient induction lights •  BWT Tank 94 piping replacement in the tank farm •  Obtain renewed NPDES permit from EPA in 2011