Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in...
Transcript of Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in...
![Page 1: Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in the tank farm • Obtain renewed NPDES permit from EPA in 2011 . Title: BWTF Renovation](https://reader034.fdocuments.net/reader034/viewer/2022051919/600bd87bf91eb2214c7da125/html5/thumbnails/1.jpg)
1
January 2011 BWT Facility Renovation Status Page 1
Status Review of BWT Facility Renovation PWSRCAC Board of Directors Meeting
January 20, 2011
January 2011 BWT Facility Renovation Status Page 1
January 2011 BWT Facility Renovation Status Page 2
Introduction • Alyeska is in the process of completing a major renovation of
the Ballast Water Treatment (BWT) facility at the Valdez Marine Terminal
• The goals of this renovation were to: – Enhance safety – Reduce hazardous air pollutant (HAP) emissions – Comply with and renew the NPDES wastewater permit – Meet changing operating conditions – Maintain high reliability
• Renovation work is about one-year behind schedule due to the extensive amount of pilot testing which was required to ensure that appropriate technology is used
• The majority of goals have already been substantially met (e.g. air emissions greatly reduced and tank headspaces inert)
![Page 2: Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in the tank farm • Obtain renewed NPDES permit from EPA in 2011 . Title: BWTF Renovation](https://reader034.fdocuments.net/reader034/viewer/2022051919/600bd87bf91eb2214c7da125/html5/thumbnails/2.jpg)
2
January 2011 BWT Facility Renovation Status Page 3
Renovated BWT Facility Process • Facility treats water that may contain petroleum hydrocarbons • Influents are primarily non-segregated tanker ballast, storm
water runoff and industrial wastewater • Renovated plant configuration is a 4-step treatment process:
− Gravity separation in the 90s Tanks to remove readily separable oil and solids
− Dissolved Air Flotation (DAF) to provide removal of suspended and emulsified oil and solids
− Air Strippers to remove volatile hydrocarbons − Polishing Ponds to biodegrade trace amounts of residual pollutants
and enhance water clarity • Thermal Oxidizers / Incinerators are installed to control
hazardous air pollutant emissions • Plant includes facilities for recovering separable oil
(recovered crude system)
January 2011 BWT Facility Renovation Status Page 4
Key Issues Addressed • Safety:
– Headspace in fixed roof tanks were at times in the flammable range (This was per the original codes, but is no longer acceptable to APSC)
– Some areas of the plant required the periodic use of respirators or other measures to protect workers against hazardous air pollutant exposure
• Environmental: – Needed to renew and continually comply with the NPDES permit – Control of air emissions
• Process Changes: – BWT influent volumes have significantly decreased with marine fleet
conversion to segregated, double-hull tankers and reduced pipeline crude oil throughput (see following slide)
– Plant water temperature, contaminant loading and salinity reducing due to increased proportionality of storm water runoff to ballast water
• Lifecycle Upgrade: – Aging facility with older technology
![Page 3: Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in the tank farm • Obtain renewed NPDES permit from EPA in 2011 . Title: BWTF Renovation](https://reader034.fdocuments.net/reader034/viewer/2022051919/600bd87bf91eb2214c7da125/html5/thumbnails/3.jpg)
3
January 2011 BWT Facility Renovation Status Page 5
Ballast Water Flow Forecasts
(NOTE: Original plant design flow was 30,000,000 gal/day)
January 2011 BWT Facility Renovation Status Page 6
2007 BWT Facility Renovations • Tied BWT Tanks 93 & 94 to the VMT Vapor Control System • Installed upgraded (V5) oil skimmers in the BWT tanks • Performed pilot testing:
– Pilot four-cell Induced Gas Flotation (IGF) – Pilot walnut shell filters – Pilot 4 and 7 tray air strippers – Pilot photo-catalyst
![Page 4: Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in the tank farm • Obtain renewed NPDES permit from EPA in 2011 . Title: BWTF Renovation](https://reader034.fdocuments.net/reader034/viewer/2022051919/600bd87bf91eb2214c7da125/html5/thumbnails/4.jpg)
4
January 2011 BWT Facility Renovation Status Page 7
2008 BWT Facility Renovations • Cleaned Tank 92 and placed in standby • Performed detailed testing of secondary treatment equipment • Installed new Air Stripper System to remove volatile
hydrocarbons (BTEX): (Operational 2Q 2009) – New Power Distribution Center – Four Shallow Tray Air Strippers – Two Thermal Oxidizers – Three Propane Tanks
January 2011 BWT Facility Renovation Status Page 8
2009/2010 BWT Facility Renovations • Installed analyzers on Tanks 13 & 14 and West Metering to
limit and better control the BWT plant influent (Operational 1Q 2011) • Upgraded and completely renovated DAF Cells 5 & 6:
– Covered DAF 5 & 6 and tied to Thermal Oxidizers for vapor control – Replaced Pressure Retention Tanks and DAF Compressors – Performed major repairs to entire DAF system
![Page 5: Status Review of BWT Facility Renovation · 2011. 1. 20. · • BWT Tank 94 piping replacement in the tank farm • Obtain renewed NPDES permit from EPA in 2011 . Title: BWTF Renovation](https://reader034.fdocuments.net/reader034/viewer/2022051919/600bd87bf91eb2214c7da125/html5/thumbnails/5.jpg)
5
January 2011 BWT Facility Renovation Status Page 9
2010 BWT Facility Renovations • Completed construction of covered DAF renovations • Finalized pilot testing of Moving Bed Bio-film Reactor (MBBR),
Fixed Bed Bio-film Reactor (FBBR) and Multi-plate Bio-film Reactor (MPBR)
• Repaired and coated DAF Building structure • Replaced DAF inlet piping
January 2011 BWT Facility Renovation Status Page 10
Planned 2011/2012 BWT Renovations • Convert the existing Biological Treatment Tanks (BTTs) into
Polishing Ponds to biodegrade trace amounts of residual pollutants and enhance water clarity. Alternatively, a Moving Bed Bio-film Reactor may be installed in the DAF 1 - 3 area.
• Replace the DAF Building roofing • Replace DAF lighting with energy efficient induction lights • BWT Tank 94 piping replacement in the tank farm • Obtain renewed NPDES permit from EPA in 2011