Status of the ASDEX Upgrade Tokamak Programme Hartmut Zohm MPI für Plasmaphysik, EURATOM...
-
Upload
beverly-doyle -
Category
Documents
-
view
222 -
download
0
Transcript of Status of the ASDEX Upgrade Tokamak Programme Hartmut Zohm MPI für Plasmaphysik, EURATOM...
Status of the ASDEX UpgradeTokamak Programme
Hartmut ZohmMPI für Plasmaphysik, EURATOM Association
Joint Executive Committee session of IEA-IAs on Pol. Div Tokamaks and Large Tokamaks, Naka, Japan, May 21, 2007
• Status of flywheel generator(s)
• Midterm hardware extensions
• planning for 2007/2008 campaign(s)
• Status of ITPA joint experiments
Status of Generator EZ4
ASDEX Upgrade powered by 3 flywheel generators:
• EZ2 (1450 MJ / 167 MVA) for toroidal field coils
• EZ3 ( 500 MJ / 144 MVA) + EZ4 (650 MJ / 220 MVA) for poloidal
field coils and auxiliary heating Accident in April 2006 led to severe damage on EZ4
• failure of control system – generator continued to run until out of oil
• rotor touched stator – damage to stator windings, rotor shaft
rotor - can be repaired stator - must be rebuilt
Repair is possible at Siemens Dynamowerk Berlin
• expensive and time consuming, projected delivery ~mid 2008
Midterm Hardware Extensions
Midterm Hardware Extensions
Will open unique possibilities for the EU Accompanying Programme
Status of Tungsten Wall Project
April 2007
W-coated divertor tile with solid W Langmuir heads
Status of Tungsten Wall Project
Full W-coverage in 2007:
• all PFCs now W-coated
Future AUG wall could be W or C:
• depends on possible performance limitations
• need qualified answer for ITER first
• JET ‘ITER-like wall project’ may need direct experimental support)
Extension of ASDEX Upgrade ECRH system
2-frequency gyrotron (GYCOM, Russia) 105/140 GHz, 1 MW, 10 s(first of its kind – next will be 4-frequency)
2-frequency gyrotron (GYCOM, Russia) 105/140 GHz, 1 MW, 10 s(first of its kind – next will be 4-frequency)
Fast (50 ms)steerable launcher forreal-time deposition control
Fast (50 ms)steerable launcher forreal-time deposition control
Internal Coils and Conducting Shell
Proposal is staged to allow several physics applications
• 24 coils to generate up to n=4 error fields with different poloidal strucuture
• with 1 power supply, n=1,2 and 4 is possible (fast track to ELM suppression)
• with 12 power supplies, n=3 and rotating helical field studies can be done
• together with conducting shell, n=1 RWM stabilisation experiments possible
• further upgrade to 24 power supplies would enable multi-mode control
3 poloidal sets (midplane outside)4 toroidal sets
Planning for 2007/2008 campaigns
Programme Planning for 2007
Operation of ASDEX Upgrade without EZ4 possible at reduced parameters
• limit to current/shaping capability, pulse length and heating power
The tungsten wall programme in 2007 can be conducted
• will require careful approach (power, pulse length) anyway
ITER relevant plasma physics experiments will need EZ4 back in 2008
• need to go to small * at low collisionality
• demonstration of sophisticated feedback control needs longs pulses
Programme Planning for 2007
A stepwise approach for the tungsten programme was agreed:
1.) study of compatibility of W-wall with ITER scenarii
2.) extension of parameter space to higher power/lower density
3.) ITER physics studies where emphasis is not on W (e.g. Improved H-mode)
significant limitation to general ITER physics studies in 2007 (also impacting possibilities for ITPA joint experiments)
• Operation/investigation of W machine without (any) intrinsic low-Z
radiator• Comparison of boronised / un-boronised machine:
maybe able to proof of hypothesis on B influence• D retention ‚without‘ low-Z (C,B) contamination• Comparison of D pumping W wall / boronised W wall
and H-D transition
However, at the cost of higher (initial) O-concentration
Together with reduced generator power, restart was somewhat slower
Startup without boronisation…
…successfully accomplished this month!
…successfully accomplished this month!
…successfully accomplished this month!
Low loop voltage startupSaves generator power
Low loop voltage startupSaves generator power
…successfully accomplished this month!
Radiated power is low(Prad/Ptot = 1/3) and stable
Radiated power is low(Prad/Ptot = 1/3) and stable
…successfully accomplished this month!
Managed to inject 3 MW(2.5 absorbed) of ECRHfrom 5 gyrotrons!
Managed to inject 3 MW(2.5 absorbed) of ECRHfrom 5 gyrotrons!
Status of ITPA joint experiments
Status of ITPA joint experiments
No experiments since April 2006, but AUG staff participating in otherjoint experiments:
• role of pedestal in improved H-mode (C. Maggi at DIII-D)
• investigation of b-scaling of transport (L. Vermare at DIII-D)
• size scaling of NTM stabilisation by ECCD (L. Urso at JT-60U)
Highest priority in 2007 is on tungsten wall programme
• ITPA experiments only within present boundary conditions
In mid 2008, full performance experiments should be possible again
• damaged generator should be back in operation
• full W-wall is still a boundary condition that has to be observed