Status of Glasgow module production
Richard Bates
The University of Glasgow
K.Smith, R. Bates, A. Cheplakov, V. O’Shea
W. Bell, J. Melone, F. Doherty, M. Horn
SCT Meeting –22nd September 2003
![Page 2: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/2.jpg)
22nd Sept. 2003 Richard Bates 2
Overview
Pre-qualification 5 qualification modules S-curves Wirebonding Multi-module testing Conclusions
![Page 3: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/3.jpg)
22nd Sept. 2003 Richard Bates 3
Glasgow pre-qualified start of July 2 Modules:
M-O-040_20220240100028 – 3 un-bonded channelsM-O-044_20220240100032
Problems with fan-in Glue on fan-in during construction Three groups of un-bondable channels ( => 191 defects!) Remove these => 19 defects, 5 un-bonded (12 bad to start with)
Pre-qualification
![Page 4: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/4.jpg)
22nd Sept. 2003 Richard Bates 4
5 qualification modules
4 Finished all Glasgow steps and in spec! One requires rework of VDC chip wire bond
Output of VDC bond wire touching VDC chip Then final electrical tests to be performed
Glasgow steps Wirebonding Thermal cycling Long term test Electrical Characterisation
![Page 5: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/5.jpg)
22nd Sept. 2003 Richard Bates 5
Modules
20220240100035 20220240100038 20220240100041 20220240100043 20220240100044
All in spec bar high noise on #44 100 extra electrons Work in progress on VDC bonding
S-curve problems has delayed qualification request!
![Page 6: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/6.jpg)
22nd Sept. 2003 Richard Bates 6
Summary of 20220240100035
IV – good – see plot 13 bad channels (started with 10 defects) 0 un-bonded T=9oC Gain = 55.4 Noise: link0=1432ele, link1=1428ele No: module = 7.53x10-6, link0=6.97x10-6,
link1=6.81x10-6
TW: link0 = 10.3ns, link1 =10.2ns
![Page 7: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/7.jpg)
22nd Sept. 2003 Richard Bates 7
Summary of 20220240100035
T=20oC RH<10% I@150V
502nA
I@350V 656nA
![Page 8: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/8.jpg)
22nd Sept. 2003 Richard Bates 8
TW of 20220240100035
TW: link0 = 10.3ns link1 =10.2ns
![Page 9: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/9.jpg)
22nd Sept. 2003 Richard Bates 9
Summary of 20220240100038
IV – good – see plot 8 bad channels (started with 0 defects) 7 un-bonded T=11oC Gain = 56.0 Noise: link0=1408ele, link1=1421ele No: module = 5.4x10-5, link0=5.6x10-5, link1=5.5x10-
5
TW: link0 = 10.1ns, link1 =10.4ns
![Page 10: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/10.jpg)
22nd Sept. 2003 Richard Bates 10
Summary of 20220240100038
T=20oC RH<10% I@150V
266nA
I@350V 420nA
![Page 11: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/11.jpg)
22nd Sept. 2003 Richard Bates 11
TW of 20220240100038
TW: link0 = 10.1ns link1 =10.4ns
![Page 12: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/12.jpg)
22nd Sept. 2003 Richard Bates 12
Summary of 20220240100041
IV – good – see plot 18 bad channels (started with 12 defects) 6 un-bonded T=10oC Gain = 54.7 Noise: link0=1478ele, link1=1499ele No: module = 1.3910-5, link0=8.46x10-6,
link1=1.12x10-5
TW: link0 = 10.4ns, link1 =10.9ns
![Page 13: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/13.jpg)
22nd Sept. 2003 Richard Bates 13
Summary of 20220240100041
T=20oC RH<10% I@150V
430nA
I@350V 594nA
![Page 14: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/14.jpg)
22nd Sept. 2003 Richard Bates 14
NO of 20220240100041
![Page 15: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/15.jpg)
22nd Sept. 2003 Richard Bates 15
TW of 20220240100041
TW: link0 = 10.4ns link1 =10.9ns
![Page 16: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/16.jpg)
22nd Sept. 2003 Richard Bates 16
LongTerm test of 20220240100041
![Page 17: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/17.jpg)
22nd Sept. 2003 Richard Bates 17
Summary of 20220240100043
IV – good – see plot 25 bad channels (started with 10 defects) (just in spec!)
11 un-bonded, 1 part-bonded T=11oC Gain = 54.4 Noise: link0=1503ele, link1=1506ele No: module = 2.90x10-5, link0=3.35x10-5,
link1=3.13x10-5
TW: link0 = 10.8ns, link1 =11.6ns
![Page 18: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/18.jpg)
22nd Sept. 2003 Richard Bates 18
Summary of 20220240100043
T=20oC RH<10% I@150V
318nA
I@350V 523nA
![Page 19: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/19.jpg)
22nd Sept. 2003 Richard Bates 19
TW of 20220240100043
TW: link0 = 10.8ns link1 =11.6ns
![Page 20: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/20.jpg)
22nd Sept. 2003 Richard Bates 20
LongTerm Test of 20220240100043
![Page 21: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/21.jpg)
22nd Sept. 2003 Richard Bates 21
Summary of 20220240100044
IV – good – see plot 1 bad channels (started with 1 defect) 0 un-bonded T=8oC Gain = 51.2 Noise: link0=1640ele, link1=1655ele No: module = 7.53x10-6, link0=6.97x10-6,
link1=6.81x10-6
TW: link0 = 10.0ns, link1 =10.3ns
![Page 22: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/22.jpg)
22nd Sept. 2003 Richard Bates 22
Summary of 20220240100044
T=20oC RH<10% I@150V
215nA
I@350V 338nA
![Page 23: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/23.jpg)
22nd Sept. 2003 Richard Bates 23
TW of 20220240100044
TW: link0 = 10.0ns link1 =10.3ns
![Page 24: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/24.jpg)
22nd Sept. 2003 Richard Bates 24
S-curves
Measurements made In Valencia test box Inside metal enclosure AERO r/o Shielded twisted pair power cables with KEK style chokes Shielded TP signal cables + ferrite chokes near patch card
Tried many grounding schemes Unable to remove discontinuity
Problem due to degradation of electrical contact between module and cooling block during cooling? To try spring washer
![Page 25: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/25.jpg)
22nd Sept. 2003 Richard Bates 25
Example of S-curves
Discontinuity at 50mV and ~60mV
Not effected by Vled value
![Page 26: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/26.jpg)
22nd Sept. 2003 Richard Bates 26
Wirebonding Summary
Some lost bonds : average = 4.8 + 1 part-bonded All chip to fan-in bonds Lost bonds due to jig
Only holds hybrid on edges – slight bounce Improved jig by holding module at mounting point No support on fan-in as this is of unknown height
Used for #44 0 un-bonded
![Page 27: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/27.jpg)
22nd Sept. 2003 Richard Bates 27
Multi-module testing
All measurements to date done in single enclosure with capability for two modules
Second DAQ for multi-module testing present
All hardware present – waiting for final grounding scheme
![Page 28: Status of Glasgow module production Richard Bates The University of Glasgow K.Smith, R. Bates, A. Cheplakov, V. O’Shea W. Bell, J. Melone, F. Doherty,](https://reader030.fdocuments.net/reader030/viewer/2022032722/56649f505503460f94c72391/html5/thumbnails/28.jpg)
22nd Sept. 2003 Richard Bates 28
Conclusions
Not quite there yet! Need to understand s-curve problem Transfer grounding to multi-module set-up Hope to make progress during this week on
s-curves