Station and footbridge closure - Queensland Rail viewShorncliffe station precinct heritage...

Station and footbridge closure - Queensland Rail viewShorncliffe station precinct heritage restoration Queensland Rail is undertaking a restoration of the historic Shorncliffe station,
Station and footbridge closure - Queensland Rail viewShorncliffe station precinct heritage restoration Queensland Rail is undertaking a restoration of the historic Shorncliffe station,
Station and footbridge closure - Queensland Rail viewShorncliffe station precinct heritage restoration Queensland Rail is undertaking a restoration of the historic Shorncliffe station,
download Station and footbridge closure - Queensland Rail viewShorncliffe station precinct heritage restoration Queensland Rail is undertaking a restoration of the historic Shorncliffe station,

of 3

  • date post

    23-Apr-2018
  • Category

    Documents

  • view

    216
  • download

    1

Embed Size (px)

Transcript of Station and footbridge closure - Queensland Rail viewShorncliffe station precinct heritage...

Station and footbridge closure

Shorncliffe station precinct heritage restoration

Queensland Rail is undertaking a restoration of the historic Shorncliffe station, located on Railway Parade.

Completed in 1897 and then called Sandgate station, the station building has been added to over its long life and was renamed Shorncliffe station in 1938. Currently listed on Queensland Rails heritage register, these restoration works will return the main station building closer to its original 1897 appearance.

A12 class steam locomotive standing at the Sandgate (later Shorncliffe) station

ca. 1905 QR historical collection

What is involved?

The current condition of the station building means that it is deteriorating faster than maintenance can prevent. Extensive works are required to preserve this historic Queensland icon, requiring temporary station facilities to be established.

The restoration works will involve, among other activities:

Moving the main station building from its current site to facilitate foundation repairs

Removal of all asbestos materials and repair of extensive water and termite damage

Replacing the existing roofing

Renewing the interior fit out of the building

Building a new separate staff operations facility

Restoration of the air raid shelter

These works will enhance the historic character of the station and are designed to preserve the station and its place in the local history of Shorncliffe for future generations.

Additionally, in line with modern day safety and security requirements, further works undertaken at the station will include the replacement of lighting and security cameras and the installation of new fencing.

Help us celebrate the Shorncliffe station precinct heritage restoration

Sunday 20 March 2016

1:00pm 3:00pm

Shorncliffe station, Railway Parade, Shorncliffe

Meet the Queensland Rail project team

Have a look at the proposed plans for the new station building

Discuss potential tree removal

Understand construction timeframes

Provide feedback on the historic legacy to remain at the station

Enjoy a sausage sizzle while you learn about this essential project.

The project team will also be available at Shorncliffe station on Monday 21 March between 7:00am to 9:00am and 4:00pm to 6:00pm to answer any questions and take feedback.

Projected timeline

The Shorncliffe station restoration will take around 12 months to complete, weather and construction conditions permitting. Early works associated with the restoration are scheduled to commence in April 2016. The following key milestones provide a rough guide for project timings:

April-May 2016: Site preparation including construction of temporary access and amenities and start the restoration of the lamp room and air raid shelter

June-July 2016: Construction of new permanent staff facility

August 2016: Relocation of station staff and ticket office, close station building and start investigations

September 2016 mid 2017: Demolition works including removal of asbestos station roof and then moving into renovation works for the station building

Mid 2017: Open new station building to the public.

Keeping you informed

Queensland Rail is committed to keeping stakeholders and the community informed about this project. For more information, please call 13 16 17 between 8:00am and 5:00pm Monday to Friday or email communityengagement@qr.com.au.